Clarke v Cascade Pools (Qld) Pty Ltd [2010] QCAT 323
CITATION:
PARTIES:
Clarke v Cascade Pools (Qld) Pty Ltd [2010]
QCAT 323
Ms Katherine Clarke aka Marianne Morel
v
Cascade Pools (Qld) Pty Ltd
APPLICATION NUMBER: BD382-09
MATTER TYPE: Building matters
HEARING DATE: Decision on the papers
HEARD AT: Brisbane
DECISION OF: Peta Stilgoe
DELIVERED ON: 6 July 2010
DELIVERED AT: Brisbane
ORDERS MADE: 1. The proceeding records the applicant as
both Katherine Clarke and Marianne
Morel.
2. Applicant’s claim is dismissed.
3. The applicant pays the respondent
$3,081.57 within 60 days of order.
CATCHWORDS : Swimming pool contract – exercise of discretion
to consider late submissions where guillotine
order – where decision on the papers because
applicant unable to attend hearing – where no
evidence of quantum – s61 QCAT Act
APPEARANCES and REPRESENTATION (if any):
This matter was heard on the papers in accordance with section 32 of the
Queensland Civil and Administrative Tribunal Act 2009
-- 1 of 18 --
REASONS FOR DECISION
1. By contract dated 15 August 2007, Ms Clarke engaged Cascade Pools
(Qld) Pty Ltd (“Cascade”) to construct a pool. On either party’s account, it
was not a happy experience. Ms Clarke claims payment of money owing,
relief from payment and damages for breach of contract. Cascade claims
money due and owing pursuant to the contract.
Preliminary comments
2. This proceeding was brought in the name of Katherine Clarke. Cascade
makes the point that much of the correspondence from the applicant is in
the name of Marianne Morel. As Ms Clarke has pointed out, she is entitled
to call herself whatever name suits her. The proviso is, however, that no
person can adopt another name for a dishonest purpose. To avoid doubt, I
find that Katherine Clarke is the same person as Marianne Morel, and that
correspondence to Cascade from Marianne Morel is, in fact,
correspondence from Ms Clarke. I also order, therefore, that this
proceeding record both names.
3. The Queensland Civil and Administrative Tribunal Act (“QCAT Act”)
intends that parties conduct their own proceedings in this tribunal. The Act
also intends that proceedings in this tribunal are to be informal and that the
tribunal is not bound by the rules of evidence. Further, the QCAT Act
makes it clear that the tribunal has an inquisitorial function. For these
reasons, no member expects a self-represented party to present a case in
the same way as would be expected from a member of the legal
profession. There are, however, limits. In the face of poorly prepared
material, the tribunal cannot make assumptions or guess at facts and
events or the meaning or importance of material. The tribunal cannot
make findings of fact where there is no evidence. It cannot award
damages if there is no material that points to the quantum of the damage
suffered. Parties must take responsibility for the preparation of their own
case.
4. In the many documents filed in this proceeding, neither party has provided
the tribunal with a narrative of what actually occurred. Ms Clarke’s
application filed 11 August 2009 is a series of dislocated and unreferenced
dot points. It has been difficult to discern the true nature of the submission.
In the absence of a language disability, and given the parties’ apparent
facility in correspondence, the tribunal is entitled to expect submissions in
complete sentences.
5. Both parties referred to documents that are not attached to statements,
included documents without explanation and referred to observations,
actions or comments by third parties without providing statements from
those parties. Both parties have failed to include relevant documents in
their material. Neither party to this dispute provided the tribunal will a full
and complete copy of the contract, which is surprising, given that its terms
are central to the dispute.
6. There are a number of iterations of Ms Clarke’s claim and they are difficult
to reconcile. This decision is based upon the list of orders ought in Ms
Clarke’s submissions filed on 3 June 2010.
-- 2 of 18 --
Ms Clarke’s late submissions
7. The first thing I have to decide is whether to allow the further submissions
filed by Ms Clarke on 23 June 2010. On 21 May 2010, a Senior Member of
this tribunal ordered Ms Clarke to file and serve any further material
evidence and submissions by 3 June 2010. The Senior Member further
ordered that, if Ms Clarke’s submissions were not filed by 3 June 2010, her
application would be dismissed without further notice. Ms Clarke did file
submissions within time but, as I have noted, also filed further submissions
in reply to Cascade’s submissions.
8. Cascade submits that these additional submissions should not be
accepted by the tribunal as submissions in reply were not part of the order
of 21 May, and they have been filed out of time.
9. Section 61 of the Queensland Civil and Administrative Tribunal Act
(“QCAT Act”) allows the tribunal to extend times and waive compliance
with procedural requirements unless doing so would cause prejudice or
detriment that cannot be remedied by an order for costs or damages.
Cascade has not claimed that it has suffered any prejudice because of the
further submissions. It has not commented on new material filed. I
consider that Cascade may suffer prejudice if the tribunal considers new
factual material from Ms Clarke without Cascade having the opportunity to
comment upon it.
10. One of the options open to me is to adjourn the decision to enable
Cascade to reply to the material. However, I am mindful that this dispute
has been on foot for some time, Guillotine orders – those orders where a
party’s claim is dismissed through failure to comply with a step without
further reference to the tribunal – are not lightly made. Clearly the Senior
Member was concerned that Ms Clarke prosecute her claim with some
diligence. The history of file is as follows:
a) On 7 October 2009, the Commercial and Consumer Tribunal ordered
that Ms Clarke file and serve her material by 23 November 2009. She
complied with that order.
b) At a callover on 17 February 2010, this proceeding was set down for a
compulsory conference on 4 May 2010. Both parties applied to re-
schedule the conference due to ill-health.
c) On 30 April 2010, the order for a compulsory conference was vacated.
Apparently, Ms Clarke was unable to attend a conference even though
it was scheduled to occur at her home. This tribunal ordered Ms Clarke
to file and serve any further material by 14 May 2010.
d) On 13 May 2010, Ms Clarke asked for an extension until 21 May 2010.
On 20 May 2010, she asked for an extension to 4 June 2010. In
support of the second application, Ms Clarke submitted a medical
certificate stating she would be unfit for work for a period of 10 weeks.
That certificate does not sit well with a request for an extension of only
two weeks.
11. Ms Clarke has advanced no reason why the factual material contained in
her most recent submissions could not have been obtained at an earlier
date. Therefore, I do not think she should be granted a further indulgence
-- 3 of 18 --
in relation to the presentation of additional material. I will not allow, nor
have regard to, the additional material filed by Ms Clarke.
Claim for refund of $3371.74 overcharged
12. On 26 November 2007, Cascade issued a variation for $3,650.00. The
variation related to “extra reinforcing/extra width coping of pool.” The
parties agree that the variation was negotiated down to $3371.74 and
paid.
13. Ms Clarke says that she paid the variation under duress because, unless
she paid it, Cascade would not complete the construction of the pool.
Clarke points to a series of emails between the parties in support of her
claim. In its letter of 3 December 2007, Cascade says, in the final
paragraph, “If this variation is not signed and money paid, I will not
proceed with the construction of the pool.”
14. As the Court of Appeal pointed out in Mitchell –v- Pacific Dawn Pty Ltd1,
“in several cases the threat to break an existing contract between the
parties has been held to be unlawful and such as to amount to economic
duress”. That does not mean that it will be so in every case. Courts tend to
look at the nature of the pressure and the nature of the demand.
15. Clause 16.1(b) of the contract provides that a builder may suspend works
if the owner fails to pay progress payments. Clause 16.1(d) of the contract
provides that a builder may suspend performance of the work if the owner
unreasonably fails to consent to any variation or fails to sign a variation
document provided. I interpret Cascade’s letter of 3 December as an
imperfect, but effective, notice under the contract that it would suspend
works if the variation was not paid. In those circumstances, Ms Clarke’s
action in signing and paying the variation cannot amount to duress. The
real question is whether Cascade was entitled to charge the variation.
16. There are two parts to this variation. One element in the variation is the
extension of the coping on one side of the pool. Ms Clarke says:
a) She always intended for the pool to “be 300mm on the left side and
1200 mm on the right side” and the sales person drew it up incorrectly.
b) The salesperson’s mistake was noticed when variation 1 was signed
and corrected by that variation, making the pool smaller so there was
room on the right hand side to put furniture.
c) The excavation was dug with reference to the salesperson’s incorrect
plans, not the updated variation. Variation 1, which deals with the
reduction in pool size, is silent in relation to the coping.
17. There is a hand drawn plan attached to the contract which does tend to
show the pool offset to the left with a wider coping on the right had side.
This plan has a number of changes marked and it is difficult to discern
what final layout was intended. In her statement of 20 November 2009, Ms
Clarke attaches a copy of the approved plans as evidence of what the true
position should have been.
18. The approved plans show a constant size coping around the entire
perimeter, with the pool slightly offset to the left. They are quite different
1 [2006] QSC 198 at paragraph [25]
-- 4 of 18 --
from the plans accompanying the contract. The approved plans, in fact,
support Cascade’s contention that a variation was required. I accept that
submission.
19. The other aspect of the variation was to rectify a cave in of the pool wall
caused by heavy rain after excavation and before concreting.
20. Ms Clarke says that the delay between digging, forming and concreting the
pool was Cascade’s fault because it was too busy at the time. Cascade
says the delay was Ms Clarke’s fault because she could not decide what
coping tiles she wanted.
21. Cascade says that:
a) It excavated the pool site on 26 October 2007 but the pool could not be
formed until Ms Clarke advised what size coping she wanted.
b) The pool was re-excavated on 1 November as it had collapsed due to
heavy rain.
c) On 2 November 2007, Ms Clarke advised that she wanted 450 mm
coping. Cascade installed formwork and reinforcing accordingly.
d) On 5 November 2007, the steel worker was asked to stop work
because the siting of the pool was wrong.
e) On 6 November 2007 the steel work was completed.
f) On 7 November 2007, the steel work was inspected and passed.
g) On 8 November 2007, the pool caved in because of heavy rain
overnight.
22. Ms Clarke says that:
a) The failure to form up the pool was because of Cascade’s delay and
that Cascade had admitted to Ms Clarke’s builder that it had too much
work.
b) The concrete should have been poured on 3 November 2007, that the
pour was booked for this date and that all issues about the pool had
been resolved that morning.
23. It is difficult to determine whose version of events is to be preferred as
both sides’ stories have internal inconsistencies. Neither party has
produced any independent evidence. The steel worker has not provided a
statement, nor has the builder to whom Ms Clarke refers. It’s probable that
both parties were the cause of some of the delay.
24. Ms Clarke does not dispute Cascade’s assertion that the steel worker was
stopped from completing his work on 2 November 2007. She says that the
dispute was resolved by 3 November 2007 and that the pour could have
taken place that afternoon. Critically, however, she does not dispute
Cascade’s assertion that the steel work was not inspected and passed
until 7 November 2007. If I accept that assertion, the earliest the concrete
could have been poured was 7 November 2007. I do not accept that the
delays between agreement being reached on 2 November 2007 and
inspection of the finished steel work on 7 November 2002, or between that
approval and planned concreting the next day to be unreasonable. Once I
make that finding, any delay up to that point is irrelevant.
-- 5 of 18 --
25. I find that the additional work occasioned by the collapse of the wall was
necessary because of the intervening rain and could not have reasonably
been avoided.
26. I note Mr Diggles’ statement that he did not think any extra reinforcing was
delivered to the block or that extra concrete was required. The details of
the variation are contained in Cascade’s invoice of 3 December 2007. It
notes that Ms Clarke was charged for only 3 metres of additional concrete;
the balance related to plant hire and labour. In a letter of the same date,
Cascade says that it was entitled to charge an additional 13 metres of
concrete but chose not to do so. I accept that Mr Diggles honestly holds
his belief but there is agreement that extra concrete was involved (in
concreting up to the fence) and any additional reinforcing may not have
been visible to the casual observer.
27. Cascade is entitled to payment of the variation. There is no reason to set it
aside.
Claim for liquidated damages for delay
28. The contract provided for a construction period of 61 days. Ms Clarke has
calculated that the work should have been completed on 13 December
2007. She says that, because there has been no final handover, the work
is still not complete.
29. Cascade says that part of the delay was due to inclement weather.
Inclement weather is a legitimate reason for extensions of time and both
parties agree there was some rain during the period of the works.
30. Cascade points to other delays out of its control, one of which is that tiles
were not available. Ms Clarke concedes that the tiles were not ordered
until just before Christmas. She says that the delay was a result of the
dispute about the size of the coping tile, with Mr Dufty of Cascade trying to
persuade Ms Clarke to change the coping tile. As I have mentioned before,
the evidence about this period is confusing and no clear picture emerges.
Ms Clarke does not dispute Cascade’s assertion that the tiles were not
available for collection until early February 2008. Therefore, the time for
completion must be extended to some reasonable time after February
2008.
31. Cascade also points to the failure to install boundary and pool fencing.
Cascade says:
a) It is prohibited from finishing and filling a pool until the pool fencing has
been installed and passed.
b) Under the contract, the pool fencing is the responsibility of the owner.
c) The boundary fence was installed on 3 April 2008 but the pool fencing
was not installed because additional tiling, to be carried out by Ms
Clarke’s house builder, had not been completed.
d) The pool fence was inspected on 1 October 2008 but it failed the
inspection.
32. Ms Clarke says:
-- 6 of 18 --
a) The permanent pool fencing was booked for installation a number of
times in January and February 2008 but cancelled because the pool
was not finished.
b) Installing the pool fencing was not contingent upon completion of the
house.
c) The permanent fencing could not be installed until the tile band was
completed. This was a problem caused by Cascade’s decision to raise
the height of the pool by 100 mm. Ms Clarke says that this meant the
tiling had to be redone as she was not able to line up the patio tiling.
d) Eventually, she decided to call for the permanent fencing when the pool
was finished but, as at November 2008, the pool didn’t even have
water in it.
33. In her submissions, Ms Clarke concedes that the installation of permanent
fencing is her obligation, could not occur until the patio tiling was complete
and that the pool would not be filled until the fencing was in place.
34. Even if I accept that Cascade’s tiling was faulty, and this prevented
completion of the tiling and, therefore, the installation of the fencing, the
delay is not all the fault of Cascade. Ms Clarke has submitted a quote for
re-tiling dated 21 April 2008. The work was completed in July, as is clear
from an invoice dated 1 August 2008. A delay of four months between
quote and execution of the work cannot be attributed to Cascade. Any
delay between completion of the work in July and the inspection in October
is, likewise, delay not attributable to Cascade.
35. I reject any claim for damages for delay.
36. The copy of the contract on the tribunal’s file has the liquidated damages
section of the schedule obscured. I surmise from Ms Clarke’s submission
that the amount inserted in that section was $1 per day. She claims that
amount is not a proper reflection of the loss occasioned by delay but does
not provide any alternative means by which that loss can be calculated.
For example, it would have assisted the tribunal if Ms Clarke had provided
copies of receipts for membership to a swimming club of other water-
based health facility. In the absence of such assistance, if I had been
minded to award damages for delay, they would have been fixed at $1 per
day.
Claim for payment for final inspection and certification
37. It is common ground that the pool did not pass its first inspection. Cascade
says the contract provides that it will pay for one inspection. Clause 17.12
of the contract provides that final approval by the local authority is the
responsibility of the owner (Ms Clarke).
38. In a letter of 11 April 2009, Ms Clarke complains that Cascade booked the
appointment for the final inspection and should not have done so unless it
was confident that the pool fence would pass. The pool fencing was not
supplied or installed by Cascade. It is difficult to see how it could be
responsible for the failure of the fence on inspection.
39. The re-inspection fee is quoted as $110. There is no evidence that this
amount has been paid. Ms Clarke has not, for example, produced a
receipt.
-- 7 of 18 --
40. There is some suggestion in Ms Clarke’s material that she is also claiming
damages for the failure to provide a proper handover.
41. Cascade says it provided a handover to Ms Clarke’s son on 7 October
2008. It has provided a statement to that effect from Mr Barry. Ms Clarke
says that :
a) Her son was not present for a handover. Mr Barry arrived as her son
was leaving.
b) There could not have been a handover because when she came home,
there were pieces of pool equipment scattered around he pool.
c) Her son had no authority to accept a handover on her behalf.
d) No one made an appointment with her to conduct the handover.
e) She has not received any warranties or final certificates.
f) She has not been shown how to operate the pool properly.
42. Unhelpfully, there is no statement from Ms Clarke’s son as to what
occurred.
43. Even if I found in Ms Clarke’s favour, I have nothing to guide me as to
what might be fair compensation for the failure to provide a handover. She
has not asked for the handover to be conducted now – almost two years
after the purported handover. Ms Clarke complains about a missing steel
brush that she had to replace but she does not provide a copy of a receipt
for that item. I am unable to make any order for compensation.
Claim for replacement of remote control system
44. There is no dispute that a remote controller was provided to Ms Clarke.
Ms Clarke says, and Cascade does not dispute, that the remote controller
is not big enough to handle all the applications. Cascade says it was
provided as a gift, as neither the quote nor the contract refers to the
provision of a remote control.
45. Ms Clarke asserts that the provision of a remote control was detailed in the
specifications. In the statement filed 20 November 2009, Ms Clarke says
that she provided a copy of her requirements to Cascade’s salesman at
the time. A copy of the specifications is Exhibit KCC2. That document
states “Remote control for spa, swimjets and lights – large not small”. The
document is not signed by either party.
46. The tribunal has a copy of Cascade’s quotation of 21 November 2006. “4
stage remote + 250” is written into that quote in a different hand. Those
words do not appear in the copy of the quote included with Ms Clarke’s
original application. The quote was for $32,800. The eventual contract
price was $31,860. I can only conclude that the additional words were
added after the contract was entered into.
47. There are two sections of the contract where you might expect to find
reference to a remote controller. Item 23 “Other Equipment or
Accessories” is blank. Item 28 – “Other Items” refers to two months’ safety
fence. It does not refer to a remote controller although many other items in
Ms Clarke’s specifications are specifically referred to in the contract. That
the remote controller is not referred to leads me to the conclusion that its
-- 8 of 18 --
provision was not included in the contract price, particularly as the agreed
price was less than the quoted price, excluding the remote.
48. Ms Clarke states that, in previous pool contracts, a remote control was a
standard requirement. She exhibits a copy of a previous contract. The
provision of a remote control is clearly stated in that contract. In view of the
terms of the actual contract which is in dispute, this evidence is of no
assistance.
49. Ms Clarke also refers to KCC3. That is a contract information statement.
Ms Clarke’s material includes note: “I refer to many other items in this
Contract booklet which sets out the contract rules that have not been
adhered to. These are marked within the booklet itself.” When the tribunal
looks at the booklet, the only assistance given is that certain items are
underlined and marked with an asterisk. There are two problems with this
approach. Firstly, the “booklet” is a commentary, not the contract.
Secondly, simply pointing out the issues that may be relevant, without
applying them to the facts and showing the tribunal how they apply, is of
no assistance.
50. I find that Cascade was under no obligation to provide a remote controller.
Therefore, it is under no obligation to replace it. I disallow this claim.
Compensation for pool not being operational due to rain “flowing dirt
into the pool”
51. Ms Clarke has provided a number of photos that show the pool water
discoloured and dirty. It is accepted that the cause of the discolouration is
suspended solids in rainwater overflow draining into the pool.
52. Cascade says that:
a) The pool is approximately 600 mm below the ground level of the
surrounding properties. Ms Clarke’s photos show that the pool is
surrounded on three sides by sleeper walls of about that height.
b) When there is heavy rain, water and mud run through the retaining
walls and pollute the pool.
c) The problem could be fixed by replacing the sleeper walls with
waterproof masonry walls. This solution was suggested to, and rejected
by, Ms Clarke at the time of construction.
d) The pool was raised 100 mm at Cascade’s suggestion. If it had been
constructed at the original level, the problem would have been even
worse.
53. Ms Clarke agrees that the wash comes from the higher ground of
surrounding properties. She says that:
a) The pool was built 100 mm too high; this caused “aggravation with the
house builder which escalated this whole case to where it presently
sits…”
b) The yard was excavated by the builder (It is not clear whether she is
referring to the pool builder or the house builder), that excavation was
not her decision and it “was clearly on the plans and set by the
Engineer/Certifier.”
-- 9 of 18 --
54. The approved plans show the pool sitting on top of a 500 mm high existing
retaining wall. That retaining wall is not referred to in any of the evidence
and I cannot see it in any of the pictures. It is counterintuitive to build a
pool fence 100 mm too high, on top of an existing retaining wall and still
have a retaining wall above the surface of the pool. Whether or not the
pool was built at the correct level, given the levels of the surrounding
properties and the finished level of the pool seepage from higher
surrounding properties was always going to be a problem.
55. Ms Clarke did not file any material in time that satisfactorily addressed
these difficulties and Cascade’s assertion that it could have been avoided.
I therefore accept that Cascade recommended a masonry wall and that Ms
Clarke rejected this suggestion. Any loss or damage occasioned by
seepage is, therefore, to Ms Clarke’s account.
56. If I was minded to award damages, the quantum would be problematic. Ms
Clarke has provide dates on which the pool was unusable and some
information about the cost of chemicals but there are no receipts, not all
chemicals used are costed nor is the tribunal given details of the amount of
additional chemicals used. Ms Clarke has provided water and sewerage
accounts but, again, Ms Clarke does not provide details of how the claim
for excess water should be calculated. It is not the job of the tribunal to
guess.
Spa jets not working
57. Ms Clarke says that the back jets in the spa have never worked. She
wants them fixed and compensation for the fact that they have never
worked.
58. Cascade says that it has never been asked to fix these jets and that they
were operating correctly on handover. Cascade points out that it was
asked to attend site on numerous occasions to fix other problems but that
the issue of the jets was never raised.
59. I have considered Ms Clarke’s material in detail. She has provided many
copies of emails between the parties. The first reference to inoperative jets
was in her submission filed 3 June 2010. Neither in that document, nor
her statement filed 20 November 2009 does she ever assert that she told
Cascade there was a problem with the jets. I do not accept this claim.
Heating unit not working
60. Ms Clarke says that the heating unit worked for six weeks then failed. She
says it was not working throughout winter 2009.
61. There is a lot of correspondence between the parties about this issue. Ms
Clarke has also included copies of her emails to Hurlcon, the manufacturer
of the heating equipment. Unfortunately, she has not provided a copy of
any response from that company. The only way the tribunal can discern
Hurlcon’s view of the problem is by reading Ms Clarke’s responses. This is
not ideal.
62. Cascade says:
a) On the numerous occasions it returned to look at the heating, the
controller had been tampered with.
-- 10 of 18 --
b) When Hurlcon attended (at Ms Clarke’s request) the heating was
operating normally.
c) The Electrical Safety Board established that the heater sometimes
failed due to earth leakage because the heater had been wired
incorrectly through the safety switch. Hurlcon then re-wired the heater
correctly.
63. Item 22 of the contract provides that connections for electrical equipment
are to be arranged by the owner. That Ms Clarke accepts this obligation is
implicit in her letter to Hurlcon of 29 June 2009 in which she says “I have
had an electrician check out the power side of things at the box and he
tells me…All the required power requirements discussed before installation
has been supplied”.
64. There is a handwritten note in the material that “John” from Poolwerx
turned up and fixed the pool heater by removing the safety switch. The
handwritten note goes further and refers to a comment by John that the
Hurlcon installation manual is wrong and needs to be updated to remove
the requirement that the heater be routed through the safety switch.
Unfortunately, Ms Clarke has not submitted a copy of the Hurlcon manual,
nor has she submitted a statement from “John”. There is no suggestion
from Ms Clarke that Cascade knew the Hurlcon manual was wrong or that
it relied upon it to advise Ms Clarke of the electrical connection
requirements. In the absence of these vital elements, I am unable to find in
Ms Clarke’s favour.
65. The heater has been fixed. I was given no guidance as to how Ms Clarke
quantified her claim for damages. I disallow the claim.
66. Ms Clarke has been charged a $158.40 callout fee. By invoice dated 13
March 2009, Cascade passed on an invoice from Specialised
Refrigeration. There is no direct explanation from Cascade as to why this
invoice has been on-charged, although I note it asserts that Ms Clarke was
calling in a technician without reference to either Cascade or Hurlcon.
Conversely, in her letter of 11 April 2009, Ms Clarke tells Cascade that the
first thing she knew about a refrigeration company being involved was
when the technician arrived. I accept this evidence and allow this part of
Ms Clarke’s claim.
Pool pebbles are the wrong colour
67. Ms Clarke says that the mix was supposed to be 80/20 black and white but
Cascade pebbled the other way around. Cascade says it pebbled the pool
in accordance with the contract. The contract provides for “salt and pepper
with extra black”.
68. The specifications nominate a pebble colour of “salt and pepper with extra
black 80/20mix approx”. If the specifications formed part of the contract,
and I have found that they do not, then a reasonable interpretation of the
requirement is 80 percent white and 20 percent black, given the
juxtaposition of “salt” (white) and “pepper” (black). That understanding is
echoed in the way the contract is written.
69. I am satisfied that Cascade has installed the pebble coating in accordance
with the contract.
-- 11 of 18 --
70. Ms Clarke raised this issue for the first time in her material filed 20
November 2009. She did not raise this issue in any of the extensive
correspondence between the parties, nor is it referred to in her initial claim.
71. There is a note in her submission filed 3 June 2010 that, on 3 October
2008, Ms Clarke told the pool pebblers that it was the wrong colour but she
has not provided a statement to that effect, either in her own statement or
one from the pebble installer. Given her comprehensive complaints about
other matters, I do not accept that she complained to the installers but not
Cascade. I do not accept the assertion.
72. Ms Clarke has not provided the tribunal with any guidance as to what
would be required to correct this problem or the cost of that step. Again,
even if I was inclined to find in Ms Clarke’s favour, there is no material that
would enable a tribunal to form a view as to the appropriate amount of
compensation.
Credit for pool tiles supplied
73. Ms Clarke’s submission is in the following terms “coping $13 per sq m
allowed $1117.50 why? 450 mm tiles advised this size right from the
beginning as had these tiles chosen and ordered early on – Allowance was
$1250 + $310. – seeking back + 15% margin on tiles which he didn’t
supply – didn’t give this back.”
74. In her application, Ms Clarke refers to a credit on 13 February 2008 for
$1117.50. She does not provide a copy of that document but says “didn’t
give back 15% margin charged – charged me for more concrete – his
blunder in not concreting within a short time frame after forming”.
75. Cascade agrees that it gave Ms Clarke a credit of $1117.50
76. I take Ms Clarke’s submissions to mean that Cascade gave Ms Clarke a
credit of $1117.50 but she wants a credit of a further 15%.
77. If the claim is for a refund of the builder’s margin, then there is no basis for
the claim. The rates are set out in the contract - item 7 of the contract
provides an allowance for pool coping at $13/metre and tiles at
$40/metre 2 . Cascade is entitled to charge for the laying of those tiles and a
reasonable profit. The builder’s margin is normally an agreed rate for profit.
There is no justification for Ms Clarke receiving a credit for the builder’s
margin.
78. If the claim is for something else then I have no way of ascertaining what
the claim is or the basis for the calculation. The onus to prove an
entitlement for an additional credit lies with Ms Clarke. She has not
discharged that onus. I do not allow this claim.
Cascade claimed monies ahead of being due
79. Ms Clarke’s submissions state “claimed monies ahead of being due
23.1.08, 25.2.08, 12.6.08 – (filtration equipment delivered after being
requested no to until side fences of property up, then charged $4779.00
although by then picked these up again and not on property”
80. The only evidence from Ms Clarke that even remotely relates to this claim
is an invoice for temporary fencing dated 23 January 2008, being one of
the date referred to by Ms Clarke.
-- 12 of 18 --
81. Cascade says that the payments were not claimed ahead of time. Once
again, the onus lies with Ms Clarke. She has not articulated the claim in
any logical way and not discharged the onus. I do not allow the claim.
Datum point for the pool was wrong
82. Item 2 of the contract provides that the datum point is “same as patio
concrete”. To the extent that they are relevant, the specifications provide
for “pool to flow directly to house – all one level to patio tiles”.
83. The parties agree that the house builder gave Cascade an RL point from
which to work. Cascade says that it was concerned about this level; it was
very low and the pool would have been a sump for the yard. It says that,
after discussion with Ms Clarke, the datum point was raised 100 mm.
84. In her letter to Cascade of 4 December 2007, Ms Clarke:
a) Agrees that there was a discussion about raising the pool but she says
the discussion was necessary because Cascade dug the pool at the
wrong height.
b) Concedes that she agreed to the change in the datum point but says
that this change has cost her more in the house building work. She
says that:
i) The change in the datum point meant that the house builder would
impose a variation.
ii) The house builder would have to do the tiling, not her own, cheaper,
tiler.
iii) There is a slope in the ground that she was not happy about.
iv) (the area?) needs a spoon drain right across it.
85. As to the additional costs, Ms Clarke has provided the following:
a) A quotation from N Kennedy dated 21 April 2008 for $2,612.50 for re-
tiling the pool area, repairing concrete, rendering concrete and
removing tiles.
b) An invoice dated 30 July 2008 for $611.16 for “further tiles needed
when existing tiles had to be ripped up.”
c) An invoice from BK & GD Leech dated 1 August 2008 for $4,139.00.
That invoice refers to removing tiles from the edge of the pool,
rendering the pool area and re-tiling the pool area.
d) An invoice from N Kennedy dated 1 August 2008 for $4,139.00. That
invoice details the same work as the invoice from Leech.
e) A variation from Paul Straka Pty Ltd dated 10 July 2008 that shows a
variation “slab heights - lower living area now to be 200 mm above
garage floor height”.
f) An invoice from Andersons dated 1 August 2008 for $185.90.
86. The invoices from Leech and Kennedy have a hand written notation that
they have been paid – on different dates.
87. I note that clause 10(b) (iv) of the contract allows a variation in the datum
point of up to 70mm above the agreed height. In fact, without the agreed
-- 13 of 18 --
variation to the height, the actual height is “unacceptable” only to the
extent of 30 mm.
88. I have already commented that the evidence in relation to the finished level
of the pool is somewhat confusing but the photos do show a shallow step
between the pool and the patio at the location of the pool fence.
89. I accept that the change in the datum point may have caused Ms Clarke
some additional costs in her house project. There is no evidence that the
house builder imposed a variation to Ms Clarke’s detriment. There is no
evidence that the house builder completed the tiling rather than Ms
Clarke’s own, cheaper, tiler.
90. There is evidence that the tiler had to accommodate different levels
between the patio and the pool. It seems that this problem was addressed
by rendering the patio. Nobody has explained why the pool tiling needed to
be redone and nobody has dissected the various invoices to assign a
value to only that work that was required by the change in the datum point.
It is something less that $2,612.50 but I have no information as to the
precise sum. The fact that there are two identical invoices from two
different tilers only serves to complicate matters.
91. Once again, the onus lies with Ms Clarke and she has failed to discharge
it. I do not allow the claim.
92. Ms Clarke claims that she cannot fit a table where “it was allowed to go
(and it will not go anywhere else).” She also says that the table is warped
and ruined. I have no information about he cost of the table. I do not allow
the claim.
93. Ms Clarke also says she has a 50 mm step that was unplanned and
unwanted. She says that it changes the whole perspective and makes it
difficult to move sunloungers and other furniture around. Once again, Ms
Clarke has not provided any assistance as to how the tribunal might
compensate her for this.
Kreepy Krauly keeps stopping
94. Ms Clarke says that the Kreepy Krauly catches on the rough edges of the
pool returns and a broken cover which keeps coming off. She claims $300
for three worn pads at $100 each and “another part” at $30.00.
95. Cascade says that Ms Clarke should direct any problems to the supplier
and that wearing components are consumables.
96. If the Kreepy Krauly is catching on a rough surface, a referral to the
supplier will not assist. That is a problem for Cascade. I am also not
convinced that three worn pads in two years is reasonable wear and tear.
However, once again, Ms Clarke has not assisted her claim by providing
copies of invoices. Certainly, the tribunal cannot allow a claim for “a part”. I
do not allow the claim.
Pool not the right depth
97. Ms Clarke says that the pool is “not right”, that it was supposed to be 1.3 x
2 metres deep and it’s “NOT”. Ms Clarke does not articulate why the depth
is not right but I suspect that she thinks it is too deep from these
comments: “Bench is not right depth from surface of water, so can’t sit on it
– steps are too deep between steps”.
-- 14 of 18 --
98. Cascade says that the water depth is measured from the water line at the
middle of the mouth of the skimmer box, not the top of the coping.
99. Item 1 of the contract provides that the pool will be 2 metres at its deepest
point and 1.3 metres at the shallowest point. Clause 10.2(b)(i) of the
contract provides that an acceptable pool depth can be +10% or -5% of
the agreed water depth. The approved plans show three points at which
the depth is nominated. Ms Clarke has not provided any detail of the actual
depth at these points.
100. The depth adjacent to the steps is shown on the plan at 1.1 metres.
The plan shows three steps. Presumably, the height of the steps was
determined by the depth of the pool at this point plus the distance to the
top of the coping. There are no details, either on the specifications,
approved plans or the hand drawn plans that accompany the contract, as
to the depth of the bench.
101. Once again, Ms Clarke has not provided sufficient information to prove
her claim or to quantify any loss that she has suffered. I do not allow the
claim.
Dirt from excavation of site not removed from the block
102. Ms Clarke has provided a copy of an invoice in the sum of $1,177.00
for the removal of soil left on the adjacent block. Cascade says:
a) It did place soil on the adjacent block at the request of the house
builder, Mr Conti. That soil was levelled and compacted.
b) The soil Ms Clarke now complains about was deposited as a result of a
separate contract to install a water tank on that block.
103. In her statement filed 20 November 2009, Ms Clarke says that the soil
was never levelled by Cascade but only recently levelled by the owner,
who had threatened to sue for illegal dumping. There is no statement from
the owner of the land to support this assertion.
104. In a letter dated 17 April 2009, Ms Clarke says this:
a) “I will also be lodging another claim …in your leaving dirt on site when
excavating for the tank which I then had to pay YET ANOTHER
variation payment with the house builder to remove same…”
b) “The fact that you also had the cheek to write a clause in the contract
for the tank very connivingly for the dirt to be left on site….This result
was a Variation from the builder of $1177.00 and I will now be claiming
this amount back from you for its removal.”
105. The letter of 17 April 2009 refers to a letter from Paul Straka
complaining about the situation but that letter is not before the tribunal.
106. Ms Clarke’s contemporaneous evidence confirms Cascade’s version of
events.
107. This claim does not relate to this contract and the terms of the “tank”
contract are not in evidence. Ms Clarke has not proved her claim. I do not
allow it.
Removal of pool tiles
-- 15 of 18 --
108. Ms Clarke says that the pool tiles needed to be removed and tiled
properly as “all wrong”. She refers to the invoices for tiling as support for
her claim.
109. I have already commented that Ms Clarke has not provided details of
the way in which the tiling was “all wrong”. Cascade says that the change
in tiles was as a result of Ms Clarke’s desire to use different tiles. At least
that explanation makes sense.
110. Ms Clarke has not provided any evidence of the need to replace the
tiles and, as I have already commented, the documents relating to the
quantum of the claim do not allow the tribunal to form a view as to what is
appropriate.
Relief from charges for temporary fencing
111. Item 28 of the contract states “2 months safety fencing inc”. According
to Ms Clarke’s material, Cascade rendered eight invoices totalling
$1,875.00 for additional fencing hire from 11 January 2008 to 25 August
2008.
112. Temporary fencing was required until the permanent fencing was
installed. I have already determined that the need temporary fencing was
within Ms Clarke’s control.
113. Ms Clarke also alleges, without foundation, that most pool builders own
their own temporary fencing so why should she be required to pay for it.
There are two answers to this suggestion. Firstly, Cascade says that it
does not own the temporary fencing and that it hired it from Temporary
Fence Hire Pty Ltd. I note that there are no supporting documents but the
onus is on Ms Clarke. Secondly, even if Cascade owned the temporary
fencing, it was entitled to charge for the extra time that it remained on site.
Invoices wrongly costed to the job
114. SC Concrete Specialists $2,398.00:
a) Ms Clarke says the address on the invoice is Wright St so it cannot
refer to her job. She also says that the handwriting on the invoice is Mr
Dufty’s. Mr Dufty denies that it is his handwriting. It is true that the
invoice refers to Wright St but this is an understandable mistake.
b) Corey Mosley’s invoice does not include GST. Cascade says that Mr
Mosley is not registered for GST. That is a reasonable explanation. I
am not sure what point Ms Clarke is making in any event. If GST was
added, that would increase the amount of the invoice.
c) Ms Clarke says that the concrete account from “Eagners” has an
amount of $805.00 and $4,781.70. Cascade points out that the first
page is a sub-total and the second page is the final figure. “Subtotal” is
legible at the bottom of the first page. There is nothing in Ms Clarke’s
submission.
d) The invoice from Carey’s Plant Hire is dated 11.1.2007 so cannot refer
to her job. Cascade points out that only $240.00 was on-charged to Ms
Clarke as a variation. An examination of the whole invoice shows that
Carey’s Plant Hire adopts the American style of date - mm/dd/yyyy - as
there cannot otherwise be a date of 10/22/2007. There is nothing in Ms
Clarke’s submission.
-- 16 of 18 --
e) As to Mick’s Backhire, Ms Clarke says the reference is to 121 White St
and the amount is unreadable so it cannot refer to her job. Cascade
explains the invoice as being part of the work required to address the
cave in. The variation was presented to Ms Clarke in November 2007.
Ms Clarke has had ample opportunity to obtain a legible copy of the
invoice or to query its relevance. She wrote a number of letters to
Cascade about the variation but did not question the invoice. Mr
Diggles provided a statement in which he questions the amount of
reinforcement and concrete, and the liability for the cost of the works,
but not the need for excavation. There is nothing in Ms Clarke’s
submission.
Insufficient reduction in price for variation in pool length
115. Variation 1 dated 3 September 2007 records a reduction in the pool
from 8.5 metres to 8 metres and gives a credit of $880. Ms Clarke says
this is not enough. She does not assist the tribunal by saying why it is not
enough or what other figure may be appropriate.
116. Item 9 of the contract provides that extra pool walls will be charged at
$100 per linear metre and additional pool flooring at $60 per square metre.
If I apply those rates to the reduced size, the credit should be:
Original size 8.5 x 5 Agreed variation 8 x 5 Variation
42.5 square metres 40 square metres $150 (2.5m x $60)
27 linear metres 26 linear metres $100 (1m x $100)
$250.00
117. Cascade says that it actually applied a rate of $880 per linear metre, to
the benefit of Ms Clarke.
118. The variation is reasonable and Ms Clarke has given me no reason to
amend it or apply a further credit in her favour.
Variation 1 charged ahead of time
119. Variation 1 related to the reduction in the size of the pool and a change
from solar heating to a heat pump. Ms Clarke says that the charge was
ahead of time because the pump was not delivered until April 2008.
120. The variation, on its face, is not payable until the completion of Stage 3.
Stage 3 is described in Items 10 of the contract as “delivery of filtration
and/or equipment”. Although it was calculated in the early stages of the
contract, the variation was not charged ahead of time. Cascade notes that
it did not receive payment for the variation until 19 August 2008
Conclusion
121. Ms Clarke has claimed damages from Cascade and relief from
payment of $2,468.00 owing under the contract. On the whole, Ms Clarke
has not proved her claim. In those instances where she has been able to
demonstrate that Cascade breached its obligations towards her, she has
not been able to provide any evidence of the quantum of the loss.
122. On the other hand, Ms Clarke’s evidence has demonstrated, and she
does not deny, that there is an amount outstanding under the contract. I do
find that $158.40 – the callout fee for the refrigeration technician - has
been wrongly charged to Ms Clarke. The amount payable under the
contract, therefore, is $2,309.60
-- 17 of 18 --
123. Item 20 of the contract provides that interest is payable on overdue
amounts at 20% per annum. I find that Ms Clarke should have paid the
amount due on or about 3 November 2008 (7 days from the statement
dated 27 October 2008). Interest to today’s date is 610/365 x $2,309.60 x
20% = $771.97. I order Ms Clarke pay $3,081.57 to Cascade within 60
days of order.
-- 18 of 18 --