Dinneen v Clayton t/a AT Fencing [2010] QCAT 245
CITATION: Dinneen v Clayton t/a AT Fencing [2010]
QCAT 245
PARTIES: Jacqueline Mary DINNEEN
v
Allan CLAYTON trading as A.T. FENCING
APPLICATION NUMBER: BD384-09
MATTER TYPE: Building Matters
HEARING DATE: 7 June 2010
HEARD AT: Brisbane
DECISION OF: C Endicott, Senior Member
DELIVERED ON: 7 June 2010
DELIVERED AT: Brisbane
ORDERS MADE: Allan Clayton is to pay $11,576.45 to
Jacqueline Dinneen by 5 July 2010.
CATCHWORDS : Domestic building work – defective work –
breach of statutory warranty - damages for
cost of repair
APPEARANCES and REPRESENTATION (if any):
The hearing took place on the papers in the absence of the parties.
-- 1 of 4 --
`
2
REASONS FOR DECISION
1. On 13 August 2009 Jacqueline Dinneen commenced a proceeding in the
Commercial and Consumer Tribunal claiming payment from Allan
Clayton (trading as AT Fencing) for costs she had incurred and would
further incur in rectifying work carried out under a contract for the
removal and replacement of a wooden post and sleeper retaining wall at
her residence.
2. On 28 August 2009 Mr Clayton filed a defence to Ms Dinneen’s claim in
which he contended that any defects in the retaining wall he had erected
were caused by Ms Dinneen’s neighbour placing soil on top of the
retaining wall and the effect of heavy rain.
3. The parties were directed to file their statements of evidence and
documents and Ms Dinneen complied with the directions but Mr Clayton
did not comply.
4. From 1 December 2009 the Queensland Civil and Administrative
Tribunal (the Tribunal) has replaced the Commercial and Consumer
Tribunal as a result of the Commercial and Consumer Tribunal being
abolished by the Queensland Civil and Administrative Tribunal Act 2009
(the Act).
5. Under section 256 of the Act, a pending proceeding (being a proceeding
commenced in one of the Tribunals abolished by the 2009 Act but not
heard by the abolished Tribunal prior to 1 December 2009) is taken to be
a proceeding before the Queensland Civil and Administrative Tribunal.
6. On 25 March 2010 the Tribunal directed Mr Clayton to file and serve his
statements of evidence by 31 March 2010. The Tribunal made a further
direction that the proceeding would be determined by a member on the
papers not before 31 March 2010.
7. According to evidence on the Tribunal file, Mr Clayton had been
provided with a copy of the documents supporting Ms Dinneen’s claim
on 19 February 2010. Mr Clayton has not filed any statements of
evidence nor provided any documents in support of the defence of this
claim.
Evidence supplied by Ms Dinneen
8. The Tribunal was provided with a copy of the quotation given by Mr
Clayton under his trading name of A.T. Fencing on 23 December 2005 to
remove an existing retaining wall at Ms Dinneen’s residence and to
supply and install a retaining wall comprising of 22 posts and 110
sleepers. The total quoted cost of contract was $8,192.
9. The quotation was accepted by Ms Dinneen and the work was
commenced on 6 March 2006.
10. In about January 2008 the retaining wall had cantilevered forward. A
report from NJA Consulting Engineers dated 21 February 2008 stated
that the retaining wall was comprised of posts at a spacing of 2.4 metres
-- 2 of 4 --
`
3
and sleepers. The retained height was estimated at 970 mm. The
consulting engineers concluded that the failure of the retaining wall was
most likely caused by a combination of three factors - inadequate post
footing being less than the 1.2 metres in depth specified by Tradac
Technical Data Sheet for Timber Retaining Walls, disturbance of the
ground surface near the retaining wall and associated poor drainage in
front of the retaining wall, and poor drainage behind the retaining wall.
11. Rainfall records for the area disclosed that there had been little rainfall
between March 2006 and November 2007 but there had been heavier
falls in December 2007 and January 2008. The rainfall records also
disclosed that there had been periods of relatively heavy rainfall between
1989 and 2004 in the same area.
12. Ms Dinneen was unsuccessful in having Mr Clayton agree to repair the
retaining wall and in January 2009 Ms Dinneen contracted with DWR
Fencing to repair 6.7 metres of the retaining wall. In the course of
carrying out that work, DWR Fencing ascertained that the posts had
been installed to a depth of 500mm. Some of the posts were able to be
removed by hand. The cost of repair of 6.7 metres of retaining wall was
$3,759.20.
13. An inspection was carried out at the residence of Ms Dinneen in March
2009 by an inspector from the Building Services Authority. A report
subsequently prepared by the inspector disclosed that a number of the
retaining wall posts had rotated forward by approximately 130 to 150
mm.
14. The report disclosed that a segment of the retaining wall had been
recently replaced and an inspection of the posts which had been
removed from the repaired section showed that the footing depth had
been 500 mm when the specified footing depth was 1.2 metres. The
inspector concluded that a significant contributing cause to the failure of
the retaining wall was an inadequate post footing size.
15. On 26 May 2009 the Building Services Authority issued a direction to Mr
Clayton to rectify the defective work on the basis that the installation of
the timber retaining wall was not in accordance with Timber Queensland
data sheet “Timber Retaining Walls for Residential Applications”
resulting in excessive movement of the retaining wall.
16. In May 2009 Ms Dinneen contracted with DWR Fencing to repair a
further 7.2 metres of the retaining wall at a cost of $1,550.
17. Ms Dinneen obtained a quotation from DWR Fencing for the repair of a
further 26.5 metres of the retaining wall in April 2009 for $4,919. Those
repairs have not been undertaken.
Findings and conclusion
18. Mr Clayton agreed to perform for Ms Dinneen domestic building work as
defined by section 8(3) and (4) of the Domestic Building Contracts Act
2000 in March 2006. The work was to remove an existing retaining wall
at Ms Dinneen’s residence and to supply and install a retaining wall
-- 3 of 4 --
`
4
comprising of 22 posts and 110 sleepers. The total cost of contract was
$8,192.
19. Mr Clayton removed the existing retaining wall and constructed a
retaining wall comprising of posts at a spacing of 2.4metres and
sleepers. The retained height was 970 mm. The posts were installed to
a depth of 500 mm.
20. By January 2008 the retaining wall had failed and had cantilevered
forward. A significant contributing cause to the failure of the retaining
wall was an inadequate post footing size of 500mm when the specified
footing depth for a timber retaining wall of this type was 1.2 metres.
21. Rainfall in the area in December 2007 and January 2008 also was a
contributing factor in conjunction with inadequate drainage behind and
adjacent to the retaining wall. As the former timber retaining wall had
not failed in a similar fashion despite heavier periods of rainfall prior to its
replacement in March 2006, the Tribunal is satisfied that the contribution
made by rainfall to the failure of the retaining wall was relatively minor
and that the most significant contributing factor was the inadequate
depth at which the post footings were installed by Mr Clayton.
22. Ms Dinneen has incurred repair costs as follows:
• Repair of 13.9 metres of retaining wall $5,309.20
• Engineers report and soil test $1,108.25
22. The estimated cost to repair the bAllance of the retaining wall is $4,919.
23. These repair costs totalling $11,336.45 are the result of the work
performed by Mr Clayton who installed posts at 500mm footing depth in
the retaining wall. The Tribunal accepts the unchallenged evidence of
the inspector from the Building Services Authority that the work was
defective and finds that the work was not in accordance with Timber
Queensland data sheet “Timber Retaining Walls for Residential
Applications” resulting in excessive movement of the retaining wall.
24. The Tribunal concludes that Mr Clayton had failed to perform the work in
an appropriate and skilful way and that he had not performed the work
with reasonable care and skill in beach of the statutory warranty imposed
by section 44 of the Domestic Building Contracts Act 2000.
25. As a result of the breach of the statutory warranty, Mr Clayton is in
breach of the contract he entered into with Ms Dinneen and she is
entitled to recover damages for that breach. The Tribunal is satisfied
that the damages for breach should quantified by the repair and
associated costs already incurred by Ms Dinneen together with the
further costs estimated to repair the remaining parts of the retaining wall.
26. The Tribunal orders Allan Clayton to pay to Ms Dinneen $11,576.45
being the costs of repair and $240 for reimbursement of her filing fee.
Ms Dinneen has not sought payment of interest. Payment of $11,576.45
is to be made by 5 July 2010.
-- 4 of 4 --