Adam's Earthworks Pty Ltd v Empire Constructions Pty Ltd [2010] QCAT 228
CITATION: Adam’s Earthworks Pty Ltd v Empire
Constructions Pty Ltd [2010] QCAT 228
PARTIES: Adam’s Earthworks Pty Ltd
v
Empire Constructions Pty Ltd
APPLICATION NUMBER: BN070-09
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Fitzpatrick
DELIVERED ON: 2 June 2010
DELIVERED AT: Brisbane
ORDERS MADE: (1) That the Queensland Civil and
Administrative Tribunal has jurisdiction to
deal with Application BN070-09; and
(2) The Applicant’s application for an order for
costs and interest be dismissed.
CATCHWORDS : Jurisdiction of the Commercial and Consumer
Tribunal and the Queensland Civil and
Administrative Tribunal, meaning of “building
contractor”; costs order and interest.
APPEARANCES and REPRESENTATION (if any):
APPLICANT : Adam’s Earthworks Pty Ltd ABN 49 089 096 837
RESPONDENT: Empire Constructions Pty Ltd ABN 78 126 517
682
-- 1 of 5 --
REASONS FOR DECISION
1. This decision relates to:
(a) A request by the Commercial and Consumer Tribunal for submissions
by the parties on the question of the Tribunal’s jurisdiction with
particular reference to how the work performed by the Applicant, the
subject of its claim, can be defined as “building work”; and
(b) The Applicant’s claim for costs and interest arising out of its original
claim against the Respondent for moneys owing. The Applicant’s
original claim is set out in an Application – Commercial Building
Dispute (BN 070-09), filed in the Commercial and Consumer Tribunal
on 14 August, 2009.
Background
2. By Application BN070-09 the Applicant sought an order for payment of
the sum of $33,426.61 from the Respondent, being “for machinery hire
for the purposes of its commercial building project “.
3. It is not evident from the face of Application BN070-09 if the Applicants
claim related solely to equipment hire or related to equipment hire and
labour.
4. The Commercial and Consumer Tribunal sought submissions from the
parties as to its jurisdiction, in particular how the work performed by the
Applicant can be defined as “building work”.
5. The Applicant filed submissions on 7 October, 2009. The Respondent
did not file submissions.
6. On 1 December, the Queensland Civil and Administrative Tribunal
(QCAT) commenced. It assumed responsibility for matters formerly
subject to the jurisdiction of the Commercial and Consumer Tribunal.
The question of jurisdiction had not been determined at the date of
commencement of the QCAT and has remained undetermined until this
Decision.
7. In the meantime, the Respondent paid to the Applicant most of the
moneys claimed by it.
8. At a Directions Hearing held on 17 February, 2010, His Honour Justice
Wilson ordered the Respondent to pay the sum of $544.50 to the
Applicant. That sum was paid on 19 February, 2010. At that Directions
Hearing the Applicant sought payment of its legal costs and interest on
the moneys the subject of the claim.
9. His Honour Justice Wilson ordered that the parties file submissions in
relation to the Applicant’s claim for costs and interest.
Jurisdiction
10. Pursuant to Directions of this Tribunal the Applicant has provided
copies of the invoices referred to in the Application. Those invoices
give a description of the work performed by the Applicant which
includes various equipment hire together with various items of work
such as “fall trees for house pad”, “load truck”, “cut house pad”, “cart
fill”, “ripping and loading trucks” and “level house pad and tidy up”.
-- 2 of 5 --
11. The Respondent has not taken issue with the fact that labour was
performed by the Applicant as described in the invoices.
12. The lawyers for the Applicant advised the Tribunal by letter dated 26
May, 2010 that the services provided were “Machinery with operators
to establish building pad, foundations and trench works”. It was said the
nature of the building work on site was one detached single residential
dwelling.
13. Section 77 of the Queensland Building Services Authority Act 1991
empowers the QCAT and previously empowered the former
Commercial and Consumer Tribunal to decide a “building dispute”; to
order payment of an amount found to be owing by 1 party to another; to
award damages and interest on the damages at the rate and calculated
in the way, prescribed under a regulation and award costs.
14. “Building dispute” is defined in Schedule 2 of the Queensland Building
Services Authority Act 1991 as including a “domestic building dispute”.
15. “Domestic building dispute” is defined to mean, inter alia -
“(b) a claim or dispute arising between 2 or more building
contractors relating to the performance of reviewable domestic
work or a contract for the performance of reviewable domestic
work…”
16. “Reviewable domestic work” is defined to mean ”domestic building
work under the Domestic Building Contracts Act 2000…”
17. “Domestic building work” is defined in section 8(1) of the Domestic
Building Contracts Act 2000 to include:
“(a) the erection or construction of a detached dwelling”
18. Section 8(7) of the Domestic Building Contracts Act 2000 provides that
domestic building work also includes site work relating to work
mentioned in subsection (1).
19. In determining this Tribunal’s jurisdiction in this matter it is necessary
for the definition of “domestic building dispute” to be met. In particular,
the Applicant and the Respondent must be “building contractors” and
the dispute must arise out of a contract for the performance of
“reviewable domestic work”.
20. As the Applicant at the time of the Claim was carrying out domestic
building work in respect of the erection of a single detached dwelling at
131 Kookaburra Drive, Cannon Valley I find that the Applicant was a
building contractor within the meaning of the Domestic Building
Contracts Act 2000. I draw from the Respondent’s description in its
Defence, of the process of developing the site at Lot 22 Kookaburra
Drive, Cannon Valley, that it is a building contractor.
21. The work in question was site works connected with a detached single
dwelling at Lot 22 Kookaburra Drive, Cannon Valley. Accordingly, I find
that the work performed was reviewable domestic work.
-- 3 of 5 --
22. Given the Respondent’s admission in its Defence that it owed money
claimed by the Applicant for the work, I find that the dispute has arisen
out of a contract for the performance of site work related to the
construction of a single detached dwelling. The Respondent’s most
recent submissions suggest that the contract in question may have
been entered into with the Applicant by the Respondent’s agent. That
fact does not alter the finding I made.
23. On these grounds, I find that the QCAT has jurisdiction to hear this
matter, as did the former Commercial and Consumer Tribunal.
Costs and Interest
24. The Applicant filed a submission claiming costs and interest from the
Respondent, on 1 March, 2010 and 6 May, 2010. The Respondent filed
a submission in response on 29 March, 2010 and 12 May, 2010.
25. In relation to a pending proceeding such as this, as a result of section
271 of the Queensland Civil and Administrative Act 2009, the QCAT
has and only has the functions that the former Commercial and
Consumer Tribunal had and can and can only make a decision the
former Tribunal could have made in relation to the matter under the
Commercial and Consumer Tribunal Act 2003.
26. Section 70 of the Commercial and Consumer Tribunal Act 2003
provides that the main purpose of the Costs Division of the Act is to
have parties pay their own costs unless the interests of justice require
otherwise.
27. The Applicant has not made any submission as to why the interests of
justice demand that the usual rule be departed from. In particular it has
not addressed the matters set out in section 71 of the Commercial and
Consumer Tribunal Act 2003, being the matters the Tribunal may have
regard to in deciding whether to award costs, and the amount of the
costs. The Applicant has asserted that it engaged a solicitor to pursue
payment through letters, emails and lodgement of tribunal paperwork.
28. Mere legal representation is not sufficient in my view, to entitle a party
to an order for costs. I decline to order costs in favour of the Applicant.
29. In this regard I am also persuaded by the fact that the Respondent
made early admissions of fact which limited the dispute in the matter
and that all moneys claimed have been paid.
30. In relation to the claim for interest, it is not asserted that there was any
contractual agreement between the parties to pay a certain rate of
interest on unpaid moneys. Section 77 of the Queensland Building
Services Authority Act 1991 empowered the Commercial and
Consumer Tribunal to order the payment of interest on awards of
damages. There has been no award of damages in this matter, other
than the order made by Justice Wilson on 17 February, 2010 that the
Respondent pay to the Applicant the sum of $544.00.
-- 4 of 5 --
31. I decline to order the payment of interest on that sum. It is noted that
the Respondent seeks in his submissions filed on 25 March, 2010 to
reopen the question of its obligation to pay the Applicant the sum of
$544.50. I have no statutory power to reconsider that issue. The
remedy available to the Respondent is to appeal the order of Justice
Wilson.
Orders
32. For the reasons set out in this decision I find that the Commercial and
Consumer Tribunal and the QCAT have jurisdiction to deal with the
Application.
33. I dismiss the Applicant’s application for an order for costs and interest.
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2010/228