Al-Hakim v Goolburri Regional Housing Company Ltd [2010] QCAT 127
Al-Hakim v Goolburri Regional Housing
Company Ltd [2010] QCAT 127
PARTIES: Mr Latif Al-Hakim
v
Goolburri Regional Housing Company Limited
APPLICATION NUMBER: BD037-09
MATTER TYPE: Building matters
HEARING DATE: 22 April 2009
HEARD AT: BRISBANE
DECISION OF: Mr Richard Oliver
DELIVERED ON: 22 April 2010
DELIVERED AT: BRISBANE
ORDERS MADE: The hearing of this application shall be limited to
paragraphs 1 -2, 13 – 21 and paragraphs 26 -27
inclusive of the Statement of Claim filed in the
Tribunal on 19 October 2010.
The balance of the Statement of Claim filed on
19 October 2010 is struck out
CATCHWORDS : Application to strike out pleadings; pleadings
based on a compromise agreement; whether the
Tribunal has jurisdiction to consider settlement;
claim for defective building work subsequent to
the compromise agreement permitted.
APPEARANCES and REPRESENTATION (if any):
APPLICANT : Mr Latif Al-Hakim self represented
RESPONDENT: MR Griffin QC of Counsel instructed by Hartley-
Holl Solicitor
-- 1 of 6 --
«CaseCode» / Page 2 of 6
REASONS FOR DECISION
1. On 29 January 2009 the applicant commenced a proceeding in the former
Commercial and Consumer Tribunal making a claim against the respondent
for, inter alia, damages for breach of contract in the sum of $190,200.00 or
alternatively $179,950.00 together with liquidated damages continuing at a rate
of $25 per day.
2. The particulars filed in support of the application relate to what has been
described as a “variation agreement” entered into between the parties on 29
November 2005. The variation agreement encompasses the terms of
settlement in respect of a contractual dispute between the parties. The dispute
arose out of a building contract entered into between the parties on 1 July 2004
in respect of the construction a house for the applicant at 18 Samuil Court in
Toowoomba.
3. The respondent terminated the variation agreement because the applicant
failed to comply with clause 2 of the agreement which provided that:
“It is a condition of this agreement that within 14 days from the date hereof
the owner will obtain from his bank namely Westpac Banking Corporation
a letter confirming that the owner has sufficient funds to pay for the
balance of the monies owing under the said contract and agreeing to
secure the same and pay each instalment without any deduction upon the
completion of the various stages set out in Appendix Method B of the said
contract as herein after varied.”
4. The initial proceeding in the former Tribunal, BD249.05 dismissed Mr Al-
Hakim’s application as the Tribunal held it did not have jurisdiction because the
relief sought was based on a compromise agreement which of course
encompassed in the variation agreement.
5. After the initial application was dismissed the applicant then commenced a
second proceeding in BD120-08, again before the former Tribunal. An
application was made in the proceeding to strike out the claim and the Tribunal
ordered on 7 October 2008 that the application be struck out, but the applicant
was given leave to re-plead and reapply. It is not for this Tribunal on this
application to reconsider or question the orders made in both BD120-08 and
BD249-05.
6. As a consequence of the order in BD120-08 the applicant commenced a third
proceeding in BD037-09. It is useful to recite the facts relied on in that
application to get a better understanding of the basis for this application to
dismiss, they are:
(a) On 29 November 2005, the parties signed a variation agreement purported
to solve dispute between them and vary certain items of the original contract
signed on 1 July 2004.
-- 2 of 6 --
«CaseCode» / Page 3 of 6
(b) The agreement is conditional and deals with issues of costs and remaining
stages of the building. It contains no statement related to the existing
foundation work performed by the Respondent.
(c) By the Tribunal Orders on 1 December 2005, the Respondent obliged to
ask the Tribunal for further directions before conducting any action that affect
the existing proceedings before the Tribunal.
(4) On 15 December 2005, the Respondent terminated the variation agreement
and the original contract. The Respondent asserted that the variation
agreement “now has no effect whatsoever” and gave notice in terms of Clause
22.2 that the Respondent “hereby terminates the contract”.
(5) The applicant asserts that the termination of the Contract (variation
agreement and the original contract; the varied contract) by the Respondents
wrongful.
(6) The Respondent did not ask the Tribunal for further directions and had not
given a notice to remedy breach pursuant to Clause 22.1 so the right to
terminate pursuant to Clause 22.2 did not arise. Further, as at the date of
alleged termination the Respondent was already in substantial breach by its
failure to comply with the warranty contained in Clause 10 of the General
Conditions in that the existing work (footings/foundations) had not been
constructed in accordance with the foundation design specifications.
(7) On 15 January 2007, the Applicant served the Respondent with notice
under Clause 22.2 of the Contract General condition. The Respondent did not
deny unsuitability of the foundation but asserted that this matter was dealt with
in the Tribunal proceedings.”
7. The respondent then filed an application in a proceeding to strike out that
application/statement of claim, which application was heard by the Tribunal on
22 April 2009. On 10 June 2009 the Tribunal made the following order:
1. “The application to strike out the application is allowed in part.
2. The applicant can amend the application so as to only claim in respect
to any breach of the variation agreement on or before 4pm on 3 July
2009.
3. Costs reserved”
10. This order does not sit comfortably with the dismissal of the application in
BD249-05 because that dismissal was based on a lack of jurisdiction to make
any determination about the variation agreement. In any event, a further order
was made by the Tribunal on 9 July 2009 as follows:
“The applicant can amend the application so as to only claim in respect of any
breach of the variation agreement on or before 4pm on 17 July 2009.
11. As a consequence of those orders, the applicant then filed an application on 10
July 2009 which had attached to it, “the nature of the orders sought” and “the
basis of this application”. These two documents are described as attachment
A and attachment B. Essentially, the relief sought is that the variation
agreement entered into between the parties is invalid. Secondly, the
respondent, it is alleged, had no right to terminate the contract, as it admittedly
-- 3 of 6 --
«CaseCode» / Page 4 of 6
did, for the failure of the applicant to comply with clause 2 of the variation
agreement.
12. Attachment B sets out why it is asserted that the variation agreement is
“wrongful” and by paragraph 1, one can immediately discern that the dispute is
about the variation agreement, its construction and enforceability. It is also
alleged that the respondent is in breach of the variation agreement, the
variation agreement varied the original contract and there is no evidence to
show that the respondent terminated the varied contract. It then goes on to
assert that any right to terminate could only be exercised after the defective
work has been remedied in accordance with the variation agreement.
13. What is immediately apparent from the annexures is that the applicants claim is
based on the variation agreement, its validity, enforceability and/or application.
The claim does not relate to domestic building dispute within the meaning of
the Domestic Building Contracts Act or the Queensland Building Services
Authority Act. This issue was addressed by Mr Lohrisch in Janetvale Pty Ltd v
Cameron Platt1 in which he cited McGill DCJ in Anderton v Parks Horticultural
Services Pty Ltd2 wherein he said, inter alia:
“accordingly, in my opinion a dispute between the parties to a settlement
agreement about that agreement is not one within para (a) of the definition
of “domestic building dispute” merely because the dispute settled by
agreement what was within that definition, or because it would be
necessary to have regard to matters which occurred in the course of that
earlier dispute, or in the performance of domestic building work, in order to
resolve the dispute.
14. Here, the applicant has clearly framed the nature of the dispute in Annexure A
and Annexure B not, with respect to any specific allegations of defective
building work, but based on the variation agreement.
15. However in an Amended Statement of Claim filed in the Tribunal on 19
October 2010, the applicant did make a claim for defective building work,
particularised in paragraph 13, which refers to inadequate footing design. The
pleading further particularises the basis of the claim and relies on engineering
reports, it seems, from Baker Rossow Consulting Engineers and Reid
Construction. This problem with the foundations, became apparent it seems, in
2007 subsequent to the compromise agreement. He also alleges in paragraph
27 that:
The costs of now demolishing existing footings, foundations and initial
brickwork and to construct the house in accordance with original plans and
specifications (but not including any addition engineering or footing
redesign that may be found to be necessary after demolition) is the sum of
$310,000.00. The applicant therefore claims by way of damages for
breach of contract:
1 (2008) QCCTB26
2 District court 11 October 1996
-- 4 of 6 --
«CaseCode» / Page 5 of 6
(a) The sum of $9,250.00 already paid under the contract as mentioned
in paragraph 26 above;
(b) The difference between the contract price and the current quotation
price for the subject works which is:
$310,200.00 – $162,000.00 = $148,200.00
16. The claim in relation to the foundations was considered by the Member Favell
in his decision of 10 June 20093 but he had, reasonably, difficulty differentiating
that claim from the claim made in respect of the variation agreement. That, it
seems to me, is why he gave leave to replead.
17. Pleadings in this jurisdiction do not take on the same importance as they do
under the Uniform Civil Procedure Rules because the objects of the QCAT Act
are to ensure that amongst other things proceedings “are conducted in an
informal way that minimises costs to parties, and is as quick as is consistent
with achieving justice”. The Act also encourages self representation and with
that must come a broad approach by this Tribunal to the manner in which
claims or responses are “pleaded”. What however is essential, is a need for the
opposing party to be appraised of the case it has to meet, despite in not having
been put in a concise and succinct way that might be expected under the
UCPR.
18. Here the applicant has consistently maintained a claim of defective building
work in respect of the foundations. That claim arose, prima facie, subsequent
to the entry into the variation agreement, I should say that this is not the
occasion to make any final determination about when this claim arose. It is
sufficient for this application that the applicant says it arose in 2007. This was
recognised by Mr Favell and in the orders made by the former Tribunal. The
applicant should not be shut out of this claim for want of formality in the manner
in which his case is pleaded. The basis of this claim is pleaded in the amended
statement of claim and is particularised in reliance on expert reports.
19. In order to narrow the issues I propose to make directions confining the
applicant’s case to a determination of whether the foundation system
constructed by the respondent is defective or incomplete and what if any
damages flow from any positive finding in respect of this issue. The balance of
the pleaded claims will be struck out.
20. The Tribunal therefore directs as follows:
1. The hearing of this application shall be limited to paragraphs 1 -2, 13 – 21
and paragraphs 26 -27 inclusive of the Statement of Claim filed in the Tribunal
on 19 October 2010.
2. The balance of the Statement of Claim filed on 19 October 2010 is struck
out
2. The respondent file any response to the Statement of Claim by 28 May
2010.
3. The applicant file and serve any statements of evidence including expert
reports by 11 June 2010.
3 Paragraphs 12 and 25
-- 5 of 6 --
«CaseCode» / Page 6 of 6
4. The respondent file and serve any statements of evidence including expert
reports by 25 June 2010.
5. The application be listed for a compulsory conference on 30 June 2010.
6. The application be listed for further directions on 8 July 2010.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2010/127