Cameron v Cavric Pty Ltd t/a Cavalier Homes Mackay [2010] QCAT 114
1
CITATION: Cameron v Cavric P/L t/a Cavalier Homes Mackay
[2010] QCAT 114
PARTIES: Jennifer May Cameron
V
Cavric Pty. Ltd. trading as Cavalier Homes Mackay
APPLICATION NO: BD010-09
MATTER TYPE: Building matters
HEARING DATE: 8th , 9th and 17th March 2010.
DECISION OF: K. Geraghty, Member
DELIVERED AT: Brisbane
ORDERS MADE: As per Order
CATCHWORDS:
1 Whether an agreement to terminate a contract was such as to relinquish
any rights to claim damages as a result of breach of that contract.
2. Consideration of the effect of “betterment” in the assessment of damages,
when a better house was built by the applicant in mitigation of her loss
when the house that the applicant originally contracted for was not built.
3. Whether damages for notional loss of rent for the period of delay in the
completion of the construction of a house should take into account interest
that would have been paid on borrowings when the ability to pay off the
when the interest on the borrowings has merely been delayed.
-- 1 of 23 --
2
CITATIONS: Haines v Bendall (1991) 172 CLR 60 at page 63
Cattanach v Melchior 215 CLR 1 at paragraph 101
Hyder Consulting (Aust) Pty Ltd v. Wilh Wilhelmsen
Agency Pty. Ltd.
The Maersk Colombo [2001] 2 Lloyd’s Rep 275
Consort Express Lines Ltd v J-Mac Pty Ltd (2006)
232 A.L.R. 341 at [14]
Port Kembla Coal Terminal Ltd v Braverus Maritime
Inc (2004) 140 FCR 445 at 542 [485]-[486] per Hely
J
Harbutt’s Plasticine v Wayne Tank and Pump Co
Limited [1970] 1 QB 447 at 473
Pegler v Want (UK) Ltd [2000] All E.R. 260
Hyder Consulting (Aust) Pty Ltd v Wilh Wilhelmsen
Agency Pty Ltd [2001] N.S.W.C.A. 313
v Rodier [2006] N.S.W.S.C. 282 Campbell J
observed at [143]
Paper Australia Pty Ltd v Ansell Ltd [2007] V.S.C.
484
Davidson v JS Gilbert Fabrications Pty Ltd
APPEARANCES and REPRESENTATION (if any)
Applicant: Ms C.M. Muir, instructed by McKays Solicitors
Respondent: Ms S.D. Anderson, instructed by Macrossan and
-- 2 of 23 --
3
INTRODUCTION
1. The applicant claims $73,945.00 damages plus interest for an alleged breach of a
building contract by the respondent, a duly licensed builder. The defence denies
any breach, but alleges that there was a termination by consent of the building
contract on the basis that the respondent would pay to the applicant the sum of
$12,750.00 by the applicant as a deposit. It is said that the agreement to terminate
by consent was an accord and satisfaction.
2. Therefore the task for the Tribunal is to determine whether there was a breach of
the building contract; to determine whether there was an agreement to terminate
the contract by consent whereby the parties relinquished any rights they had to sue
for damages; to determine what the legal consequences are of any such
termination; and in the event that the respondent is liable for damages, to assess
the quantum of those damages.
THE APPLICANT’S EVIDENCE
3. The applicant was a real estate sales person who became a real estate agent
in or about February 2007. In the course of her occupation, she had arranged
to sell “spec” houses built by the respondent. She was also buying land and
building houses on such land for rental purposes. At the same time, the
applicant was running a curtain and blinds business known as “Curtain Fairy”.
4. On 27 July 2007 the parties entered into a “QC1 2000 New Home Construction
Contract” for the respondent to build a house “the Cambridge 24” on land
owned by the applicant at Lot 21 Lenesha Drive, Mackay (“Lenesha Drive”) to
specification for a price of $255,000.00 including GST (“the contract”).
5. Amongst other things, the contract provided for construction to start within
twenty-one days of Council approval of the plans; for practical completion in
186 days; window furnishings, turf and fencing were excluded from the
specifications.
6. The applicant says that she never actually saw the specifications and assumed
that the “finish” would be the same as other houses the respondent had built of
the same design and which she had become familiar with through her sales
-- 3 of 23 --
4
activities, and in particular, a house at Companion Way, Mackay; and another
house situated at Firefly Crescent, Mackay in respect of which the applicant
had also entered into a building contract with the respondent for the respondent
to build. The respondent’s witness, Mr Hewitt, who was the respondent’s
project manager at the relevant time, agreed that the specifications for Lenesha
Drive were the same as for the other houses.
7. It is not in dispute that the respondent knew before entering into the contract
that the applicant’s intention was to rent the home once it was completed.
8. The applicant paid a deposit of $12,750.00 to the respondent on 11 September
2007, more than six weeks after the signing of the contract, although the
contract provided for that to be paid upon the signing of the contract (Clause
4.2). The applicant said that the reason for the late payment was simply that
she paid the deposit when she got an invoice from the respondent requesting
payment. She also paid the deposit on the Firefly agreement on the same day,
the Firefly contract having also been entered into on 27 July 2007. It would
appear from the evidence of Mr Hewitt, who dealt with the applicant, that he
was unaware that the deposit had not been paid on the signing of the contract,
and assumed that it had been paid on that date.
9. The applicant proposed to pay the progress payments stipulated by the
contract by draw- downs from her mortgage on her residential home. Thus an
actual mortgage of the Lenesha Drive property was not necessary, but she
would still have to pay interest to the lender on the draw-downs, at the home
loan interest rate charged by the lender from time to time.
10. Although construction of the home did not start, it seems that the applicant did
not begin pressing for construction to begin until about October 2007. The
applicant says that she observed that no work had commenced and that on
many occasions after October she asked Mr Hewitt when construction would
commence and was given various explanations for the delays, including that
they were waiting on Council approval, or that they were required to attend to
urgent work in Moranbah following a storm/natural disaster.
11. The applicant says that she was reluctant to push the issue too much because
she was selling the respondent’s spec built houses and did not want to
jeopardise that source of income. Further, she had contracted to buy a
property at Nebo Road on 5 October 2007 for $255,000.00 with possession to
occur on 12 November 2007, for the purpose of operating a real estate agency
-- 4 of 23 --
5
with a partner from those premises. The partnership did not eventuate and she
contracted to sell the property on 7 January 2008 for a sale price of
$292,000.00, with settlement to occur on 4 February 2008. She used the draw-
down facility from her private residence to pay for Nebo Road. She says she
would still have borrowed money for progress payments had the construction of
Lenesha Street commenced, but it would have cost her more. She would still
have bought the Nebo Road property even if the construction of Lenesha Drive
had already started. Nevertheless, she was not pushing for the construction of
Lenesha Drive to start once she had contracted to sell Nebo Road and she was
anticipating the receipt of the purchase on 4 February 2008, so that she could
avoid her lender drawing up a mortgage document, and incurring extra cost.
Once she had the money, she did begin to push harder for construction to start.
12. The applicant agrees that she did ask Mr Hewitt to hold off for a month until the
sale of Nebo Road, that is to hold off during January 2008.
13. However, construction of Lenesha Drive still did not commence after the
beginning of February 2008. The applicant says that in about April 2008 she
recalls speaking with Mr Hewitt on the telephone about when construction
would commence, and in fact she said to him words to the effect “if you don’t
want to build my house, just say so”; and that he replied “we have a contract
and we have to build it” or words to that effect. The applicant then says that
there were further queries with respect to the commencement of construction
made by her to Mr Hewitt and that there were further brush-offs between May
and July 2008.
14. The applicant says that on 24 July 2008 the administration/office clerk for the
respondent, Dee Borellini, phoned to ask for the applicant’s bank details to
deposit money for blinds that Curtain Fairy had supplied to the respondent;
and also for the respondent to pay the applicant’s advertising fees. The
applicant gave two separate bank account numbers, one for the blinds and one
for the advertising fees and that these payments were deposited into her
accounts on the same day. Annexure “C” to the Statement of Claim shows a
deposit made by the respondent on 24 July 2008 in one of the applicant’s bank
accounts.
15. Then, on 25 July 2008, the applicant says that during a conversation with Mr
Hewitt about the Firefly house (and other matters) Mr Hewitt mentioned that he
wanted to pull out of the Lenesha contract, but he moved quickly onto another
issue and there was no further discussion on that subject. She says that this
conversation took place on the telephone.
-- 5 of 23 --
6
16. The applicant then rang her solicitor to get legal advice about the delays in
starting construction and it was recommended to her that she contact the
builder to see if Lenesha Drive had received Council approval and was ready
for construction.
17. On 25 or 26 July 2008 the applicant rang Mr Hewitt and asked if the plans had
been to Council and she says that he advised her that they had been to
Council.
18. On 28 July 2008 (a Monday) the respondent deposited $12,750.00 into her
bank account (that being the amount of her deposit for the contract). However,
the applicant says she was not aware of that straight away and it was only a
few days later when she saw her bank statement that she realised that the
money had been paid. The applicant says that she immediately rang Mr Hewitt
but could not get hold of him. On 1 August 2008 she eventually was able to
speak with him on the phone to enquire about the refund of her deposit. She
says that she told Mr Hewitt that (the respondent) could not pull out of a
contract like that, and that she was getting legal advice, and he responded “you
do what you have to do”.
19. On 4 August 2008 the applicant emailed a letter to the respondent (a letter
which had been drawn up on the advice of her solicitors). That letter is
attachment “B” to the applicant’s written statement which is Exhibit 4. It queries
the basis for the return of the deposit and requests that construction proceed
and threatens a claim for damages. The respondent did not respond to this
letter.
20. Again on 2 September 2008 the applicant sent a letter to the respondent
demanding that work commence and reserving the right to claim damages;
again there was no response.
21. On 16 October 2008 pursuant to the provisions of the contract, the applicant
served a Notice to Remedy Breach on the respondent. There was no response
again, and on 31 October 2008 a Notice to End Contract was served on the
respondent.
-- 6 of 23 --
7
EVIDENCE OF MR HEWITT
22. Mr Hewitt gave evidence on behalf of the respondent. He said that shortly after
the signing of the contract, the applicant asked him to hold off commencement
for a month because the applicant was considering building a duplex at
Lenesha Drive because of the odd shape of the land and that he held off
lodging the plan with the Council for this reason. (The applicant denies this,
although admitting that she did discuss the possibility of a duplex on the land
without specifically asking Mr Hewitt to hold off).
23. Mr Hewitt says that the applicant gave him the go-ahead to commence building
the house one month after signing the contract but he was working out west at
the time, and the contract “got lost in the system”.
24. Mr Hewitt says that for two months, the applicant called him about
commencement of Lenesha Drive, but he was out of town and told her so. He
said that there was a terrible storm at Tieri on 15 October 2007 which damaged
or destroyed all or most of the 580 homes in Tieri, and from that time onwards
until October 2008 he spent the majority of his time there only being available in
Mackay early on Monday mornings and late on Friday afternoons. Further, the
respondent’s office staff spent most of their time handling Tieri matters; and
the respondent’s sub-contracting tradesmen spent most of their time, at least
for the next six to ten weeks, in Tieri. As a consequence, all of the
respondent’s house construction in Mackay stalled.
25. In his written statement (Exhibit 6) Mr Hewitt says that he was at Shinn Street
Mackay working on a job shortly thereafter (the statement does not say after
what but appears to imply that it was shortly after the two months when he
received calls from the applicant about the commencement of construction). It
says that at this time the applicant approached him in person and said words to
the effect “Dave, what’s going on? I just want to move on”; and that he replied
to the effect of “ The plans haven’t gone into Council. Look we have stuffed
you around.”; and the applicant said “If you don’t want to build it, just let me
know so I can find someone else”. Mr Hewitt then said words to the effect of
“To be honest, we just don’t have the resources with all the things going on out
west, I would be more than happy to refund your deposit so we can all move
on.” He says that the applicant then replied “I am happy with that Dave, at least
I know where I stand and we can all move on from here”. Mr Hewitt
remembered that he was working with Promina board at this time.
26. Mr Hewitt says that he then telephoned Dee Borellini straight away and asked
her to refund the deposit to the applicant, and that Borellini rang him back half
-- 7 of 23 --
8
an hour later asking what account to pay the money into, and that he told her to
ring the applicant and find out which bank account. Later on that same day,
Dee telephoned Mr Hewitt and confirmed that the deposit had been repaid.
27. Mr Hewitt goes on to confirm that some days later the applicant rang him to the
effect that he could not end the contract like that and that the applicant was
going to sue. Mr Hewitt says that he then said “you and I both agreed that we
would refund your deposit and that would be it, but you do what you think you
need to do”.
28. Mr Hewitt recalled receiving a letter from the applicant complaining about the
return of the deposit. He denied telling the applicant that the plans had been
submitted to Council.
EVIDENCE OF DEANNE BORELLINI
29. Ms Borellini recalled that on about 24 July 2008 she spoke to the applicant on
the telephone and was provided with details of a bank account for money to be
paid into for blinds. Ms Borellini did not remember anything about advertising
fees.
30. Ms Borellini goes on to say that at about the same time the applicant advised
her that she wanted her deposit back in respect of the Lenesha Drive property.
She says that she advised the applicant that she would need to speak to Mr
Hewitt before doing so.
31. She then telephoned Mr Hewitt and told him of her conversation with the
applicant. Mr Hewitt said that he wanted to check with the company’s lawyers
before authorising the refund and said that he would ring back, and a short time
later he did ring back and authorised that refund.
32. Ms Borellini goes on to say that on or about 25 July 2008 she phoned the
applicant to ask which of the two bank accounts she should deposit the money
into and was told which one.
-- 8 of 23 --
9
33. Both versions of the applicant and Mr Hewitt about the circumstances of the
refund of the deposit were put to her and she denied them both and still backed
what she said.
34. It may be noted here that her evidence was quite at variance with Mr Hewitt’s
evidence, as Mr Hewitt says that the applicant spoke to him personally about
the refund of the deposit and he rang Ms Borellini asking her to make the
refund. When Ms Borellini’s version was put to him, he denied that that had
happened.
35. Ms Borellini also produced a computer printout of the Shinn Street job (exhibit
18) which showed it commencing on 5 August 2007 and continuing through to
27 June 2008. She pointed out that on 10 June 2008 there was an entry
“Promina 60 Sheet Stramit, Delivery” and said that this meant that the Promina
sheets had left the factory (either at Brisbane or at Townsville) and would take
one to two weeks to arrive on site.
36. I note that Exhibit 18 also makes reference to Promina board on 9 August 2007
and 24 August 2007.
37. The applicant in her evidence produced a diary note dated 6 November 2007
showing that she visited the Shinn Street site with a potential buyer, Rod Ewin,
on that day. She said that at this time she had authority to sell Shinn Street,
but did not have that authority in June 2008. She further said that 6 November
2008 was the last time she had gone to the Shinn Street site although she had
been to the site once or twice before 6 November to see Mr Hewitt about
getting his signature for another property or properties. She thought that this
would have been in October but it seems somewhat unlikely that she would
have been able to see Mr Hewitt on a building site in Mackay subsequent to 15
October 2008 because from that time onwards he was “out west”
FINDINGS ON LIABILITY
38. Both the applicant and Mr Hewitt were very vague about dates. The applicant’s
written statement (Exhibit 4) signed on 12 June 2009 and was therefore made
nearly a year after the events while Mr Hewitt’s written statement (Exhibit 6)
was signed on 26 June 2009. Their oral evidence was given close to two years
after the relevant events. I would infer that their recollections of conversations
are not necessarily 100% accurate.
-- 9 of 23 --
10
39. Both the applicant and Mr Hewitt appeared to give evidence in a frank manner.
I therefore look to the surrounding circumstances. I note that the applicant’s
undisputed actions once the deposit was transferred to her bank account on 28
July 2008 (which she did not know about for a few days) were consistent with
her contentions. She rang Mr Hewitt (according to her on 1 August 2008 after
trying to contact him earlier) and Mr Hewitt confirms that she made a call less
than five days after repayment of the deposit, saying that she was going to sue,
although the versions of that conversation are a little different.
40. The applicant also sent the letter of 4 August 2008 (Attachment “B” to Exhibit 4)
which is consistent with her version and was written at a time when her memory
was fresh; it indicates that she had sought legal advice.
41. On the other hand, Mr Hewitt’s evidence does not hang together. The defence
was insistent that the relevant conversation about the deposit took place in mid-
June and this is said to be corroborated by Exhibit 18 with respect to Promina
being delivered on 10 June 2008. Mr Hewitt says that immediately after that
conversation at Shinn Street he asked Dee Borellini to refund the deposit and
the repayment of the refund was confirmed by Ms Borellini as occurring that
very day. In fact the refund undisputedly occurred on 28 July 2008 more than a
month after the conversation Mr Hewitt alleges. Further, Mr Hewitt did not
respond to the letters (Attachments “B” and “C” to Exhibit 4) as might have
been expected if he did consider that there had been an agreement absolving
the respondent of liability.
42. I do not accept Ms Borellini’s evidence which is denied by both the applicant
and Mr Hewitt. This evidence does somewhat taint the defence case.
43. The respondent’s Counsel during the hearing expressed some derision at the
applicant’s version that the refund was repaid without any discussion.
However, as mentioned, even on Mr Hewitt’s evidence, the refund was made
quite out of context of any discussions. I think it quite feasible that repaying the
deposit was an attempt to fob off the applicant, realising that the respondent
had no real prospect of getting the construction of Lenesha Drive started by
reason of their other commitments, and hoping that the applicant would just go
away. Mr Hewitt in my view was probably engaging in a self justification
exercise after the event.
44. Therefore on the balance of probabilities, I accept the applicant’s evidence.
Accordingly, there was no agreement that the applicant relinquish her right to
-- 10 of 23 --
11
sue for damages for breach of contract. As to Mr Hewitt’s version, I find it
unlikely that either the applicant or Mr Hewitt were legally sophisticated enough
to enter into an agreement whereby the applicant relinquished her right to sue
for damages. I think that at no stage did the applicant have any intention of
doing that. Put at its highest, I think that Mr Hewitt’s position was that he
interpreted the return of a deposit as being a termination of the contract and
that in his view, once the contract was terminated that was the end of it.
45. Even if I accepted Mr Hewitt’s evidence in total about the circumstances of the
repayment of the deposit, in my view that would not be sufficient to enable me
to find that there was an agreement by the applicant to relinquish her claims for
damages. I note that in paragraph 16 of Mr Hewitt’s written statement, he says
that in his telephone conversation with the applicant (the one on or about 1
August 2008) that “you and I both agreed that we would refund your deposit
and that would be it”; but I consider that at best this was simply referring to his
personal interpretation of the arrangement between himself and the applicant –
again, in my view, it would not be sufficient to constitute an agreement to
relinquish the right to claim damages.
46. In my opinion, the terms of the contract would have to be such as to establish a
clear intention to bring all obligations to an end, and just to say “we can all
move on from here” or even to say “that will be it”, in my view does not
establish any clear intention at all. In my view it is more consistent with a
proposition that the applicant was then free to get another builder to construct
her house, and from the respondent’s point of view, it was free of the obligation
to build a house which they had no time or resources to do. Further, in my
opinion simply returning the applicant’s own money, which was the
respondent’s obligation to do anyway since it had done absolutely nothing, is
not consideration for such an agreement as alleged by the respondent.
47. I therefore find that the respondent did breach the contract by failing to build the
house, and that the applicant is entitled to damages.
ASSESSMENT OF DAMAGES
48. Damages for breach of contract should be assessed in a sum which, so far as
money can do, will put the injured party in the same position as he or she would
have been in if the contract had not been performed, e.g. Haines v Bendall
(1991) 172 CLR 60 at page 63. It is not in dispute that the applicant, as soon
as there was no response to the services of the notices on the respondent,
began to look for other builders to build a house on the subject land. She tried
-- 11 of 23 --
12
to get quotes from other builders for the original plan, but was told (correctly)
that that plan was copyright.
49. Accordingly, as she could not get the exact house that the respondent was
supposed to have built, she got a number of quotes from builders for similar
houses, and the cheapest quote was obtained from Peter Thorne Builders
(“Thorne”) on 19 November 2008 for $297,945.00 including GST. The
applicant duly contracted with Thorne to have that house built and it was
completed on or about 13 August 2009.
50. As part of her damages claim, the applicant claims loss of rent during the
period between which the house to be built by the respondent should have
been completed, and the completion of the Thorne house. Further, the
applicant claims the difference in price between the two contracts.
CLAIM FOR RENT
51. Both parties agree on a period of 57 weeks over which notional rent should be
calculated and agree that the gross rent should be based on $500.00 per week.
Accordingly, both parties calculate a sum of $28,500.00.
52. From this sum, both parties agree that landlord’s insurance of $594.72 should
be deducted; and they further agree that the sum of $2,806.00, being the
interest saved by the delay, ought to be deducted. This leaves a claim of
$25,098.83 which the applicant maintains is the appropriate measure of
damages for loss of rent.
53. The respondent also says that interest of $18,812.36 would have been paid by
the applicant over the relevant period, and that should be deducted as well
leaving a loss to the applicant of $6,286.47.
54. This appears to me to be a correct application of the principle of compensation
of putting the applicant in the same position as she would have been in if the
contract had been performed. However, the applicant’s submission is that such
an approach fails to recognise that the delay in payment of interest is not a
saving and that the applicant is ultimately not better off as it just delays the
applicant’s ability to pay off the interest earlier.
-- 12 of 23 --
13
55. As I understand the submission, it means that for a number of years into the
future (it is unknown when) the applicant would have her profits from the rental
home reduced by interest payments, but once the interest payments were
completed, she would obtain the full benefit of the amount of the rent at least
insofar as no interest would be deducted. With respect to the Thorne house,
that position when greater profits could start to be made, would be reached one
year later than it ought to have been. Thus 10, 15 or 20 years down the track
(whatever it may be) the applicant will have one less year in which to earn profit
from the rental home without any deduction of interest. If the profit from the
rental payments after the deduction of landlord’s insurance was then (in round
figures) $27,905.00, the applicant will lose $27,905.00 in 10, 15 or 20 years
time or whatever the case may be.
56. Of course it is not known how long the applicant might have to pay interest on
the loan; whether at the present time she is, or in the future she may start,
paying off the principal and therefore reduce the interest and so on. Thus it is a
situation where I have to assess damages using a “broad axe”, e.g. Cattanach
v Melchior 215 CLR 1 at paragraph 101.
57. I assess the applicant’s loss in this regard to be $10,000.00 being very roughly
the present value of a loss of $18,812.00 in 10 to 15 years time. Accordingly, I
would deduct the amount of $8,812.00 (in round figures) from $25,098.00 (in
round figures) which leaves a loss of $16,286.00 for which the respondent
should compensate the applicant.
DIFFERENCE IN CONTRACT PRICE FOR THE CONSTRUCTION OF THE
HOUSE
58. Certified valuer, Darren Palmer, was asked to look at the respective plans of
the house that the respondent was going to build, and the house Thorne did
build, and provide variances in prices. In his report dated 3 August 2009 he
identified a number of factors which he said made the Thorne home superior to
the respondent’s home.
59. In paragraph 7.2 of the Report (Exhibit 7), Mr Palmer said that “after analysing
the separate building contracts, the following variances were established. The
Thorne built residence is consideration superior over the Cavalier residence for
the following reasons:
a. Living are being 13 square metres larger;
b. Garage being 4.5 square metres larger;
c. Ceiling heights are 2.7 metres (Cavalier 2.4 metres);
d. External walls solid core filled;
e. 30 square metres of additional concrete driveway;
-- 13 of 23 --
14
f. Additional paving;
g. An upgrading to tiling and increased areas inclusive of tiles
throughout the garage area;
h. Additional air-conditioning;
i. Dishwasher installed;
j. Additional electrical work;
k. Turf to yards;
l. Security screen windows.”
Mr Palmer went on to say in that report that he considered that those variances
warranted a higher contract price in the vicinity of $40,000.00.
60. In his oral evidence, Mr Palmer priced the additional air-conditioning as
$3,500.00; the dishwasher $800.00; and the value of “upgraded” security
screening as $1,200.00. He priced the living areas of the respondent built
house at $1,220.00 per square metre, while the living area of the Thorne built
house was $1,202.00 per square metre. The cost of garages and outdoor
areas were the same at $1,000.00 per square metre and $450.00 per square
metre respectively. Overall he identified $48,521.00 as the value of the
superior features of the Thorne built house over the respondent built house.
61. A bundle of documents that Mr Palmer used in preparing his report was
tendered in evidence. One of those documents indicated the ceiling variances
added $14,000.00 to the price; that tiles to the garage cost an extra $2,000.00;
lining to the garage an extra $1,500.00; extra paths an extra $1,500.00; the
driveway $8,100.00; the turf was $1,500.00 and front door $500.00. All in all
these variances added up to $37,900.00.
62. Mr Palmer conceded that none of the values were exact but were the median of
a “band” of values derived from analysis of many homes that had been built
and valued in the area.
63. The applicant did admit that she specifically asked Thorne to build higher
ceilings at 2.7 metres high instead of 2.4 metres high. Further, the applicant
admitted that she asked Thorne to do extra tiling in the garage although she
said that because of a contact that she had she was able to get more tiles than
were needed for the original house for the same price. Again, she conceded
that turf was an extra for the Thorne house and that she did ask Thorne for
additional paving around the house.
-- 14 of 23 --
15
64. She disputed that in fact the driveway as constructed by Thorne was different in
size to the one referred to in the respondent’s specifications as she measured it
as being 10.5 metres long and 5.6 metres wide, expanding to 6.2 metres wide.
She said there was in fact no space for a larger driveway.
65. The applicant was not aware of any difference in the external walls with the
Thorne house as compared to the respondent’s house, that is she did not know
anything about the Thorne house having solid core filled external walls. She
understood that the security screen windows and the dishwasher were features
that were supposed to be installed in the respondent’s house.
66. With respect to additional electrical work, the applicant said that she had certain
extra electrical work done independently of the Thorne contract, and paid for it
herself. Otherwise it is not clear to me exactly what the difference was between
the electrical work in the Thorne house and the electrical work proposed for the
respondent’s house.
67. The applicant understood that security screen windows, dishwasher and the
air-conditioning was the same as or similar to what she was supposed to have
got with the respondent’s house.
68. The respondent submitted that the applicant had not suffered any loss
whatsoever in having to pay extra for the Thorne house because she had
chosen many of the additions herself, and apart from that, she had purchased a
superior product and in effect had got proper value for her money.
69. The applicant’s submissions framed the issue as being one of “betterment” and
set out the following authorities establishing legal principles for “betterment”:
a. “As Shelter JA explained in Hyder Consulting (Aust) Pty Ltd v.
Wilh Wilhelmsen Agency Pty. Ltd.
“In my opinion, if a defendant negligently damages
or destroys the plaintiff's property and there is no
evidence that the plaintiff had any reasonable
choice other than to replace or repair what had
been damaged or destroyed, the cost of
replacement or repair, provided it is not
-- 15 of 23 --
16
extravagant, is recoverable as damages. In each
case it is a question of fact.”
b. To similar effect is the English decision in The Maersk Colombo
[2001] 2 Lloyd’s Rep 275, where the English Court of Appeal
considered whether the measure of damages in relation to a
damaged crane should be the cost of replacement or the
diminution in its value. In considering this question, the Court
rejected any distinction in approach between contract or tort,
between damage to and or chattels or between cases of exact or
approximate replacement.
c. The approach adopted was one which applied the compensation
principle, subject to a requirement for reasonableness.
Relevantly, the court accepted the following propositions.
“(1) …
(4) If the claimant intends to replace the
chattel, and if the market or resale value as
assessed is inadequate for that purpose,
then the higher replacement value may, in
the event, be the appropriate measure of
damages.
(5) When and if replacement value is claimed,
the claimant can only succeed to the extent
that the claim is reasonable; that is, that it
reflects reasonable mitigation of its loss.
(6) The claim will ordinarily be reasonable if it is
reasonable to replace the chattel and the
cost of replacement is reasonable.”
d. In repairing or replacing a chattel, there are often practical
difficulties in obtaining an exact replacement for the chattel which
was damaged or destroyed. The question which then arises is
whether some deduction from the replacement cost is to be
allowed for any “betterment” to the plaintiff.
e. There is no general rule requiring such a deduction to be made:
see Consort Express Lines Ltd v J-Mac Pty Ltd (2006) 232 A.L.R.
341 at [14]:
“[14] The principle identified by these authorities
establishes that a tortfeasor must bear the cost of
replacement or repair of the plaintiff’s property
where that has been damaged or destroyed by the
tortfeasor’s negligence. And the quantum of that
cost is not diminished by any betterment of the
plaintiff’s property as a result of the repairs which
-- 16 of 23 --
17
the plaintiff achieves provide that the plaintiff does
not act extravagantly: Port Kembla Coal Terminal
Ltd v Braverus Maritime Inc (2004) 140 FCR 445
at 542 [485]-[486] per Hely J.”
f. As Hely J explained in Port Kembla Coal Terminal Ltd v Braverus
Maritime Inc (2004) 140 FCR 445 at [486]-[487]:
“486 Subject to questions of extravagance, there
is no rule that requires a plaintiff to account
for any advantage or betterment which the
plaintiff has obtained by repairing an old
article with new materials or by acquiring a
new article for old in the case of a
replacement after total loss, although any
savings or profits which the plaintiff makes
by use of the new article must be brought to
account. In particular, no allowance for
betterment is made merely because the
property which is repaired or replaced might
last longer than the property which was
damaged or destroyed by the defendant’s
negligence: Optus Networks Pty Ltd v
Leighton Contractors Pty Ltd [2002]
NSWSC 450 at [1387]- [1388].
487 The rationale for this approach was
explained by Dr Lushington in The Gazelle
(1884) 2 Wm Robb 279; 166 ER 759 (at
Wm Robb 281; ER 760):
“If [the injured] party derives
incidentally a greater benefit than
mere indemnification, it arises only
from the impossibility of otherwise
effecting such indemnification
without exposing him to some loss or
burden, which the law will not place
upon him.’
g. Or, as Widgery LJ put it in Harbutt’s Plasticine v Wayne Tank and
Pump Co Limited [1970] 1 QB 447 at 473:
“Nor do I accept that the plaintiffs must give credit
under the heading of “betterment” for the fact that
their new factory is modern in design and
materials. To do so would be the equivalent of
forcing the plaintiffs to invest their money in the
-- 17 of 23 --
18
modernizing of their plant which might be highly
inconvenient for them.”
h. In Pegler v Want (UK) Ltd [2000] All E.R. 260 (a case referred to
with approval by Clarke LJ in the “Maersk Colombo”) it was said:
“The mere fact that party purchasing a substitute
product acquires something with a longer life
span, or which is more modern, or has additional
features than the original would have had does not
require an allowance for betterment, still less
recovery limited to the financing cost of acquiring
the replacement early: Harbutts’ Plasticine v
Wayne Tank; Bacon v Cooper Metals [1982] 1 All
ER 397; Dominion Mosaciacs v Trafalgar Trucking
[1990] 2 All ER 246. In particular, where there is
no ready second hand market for goods, or where
there might be uncertainty as to the reliability of
such goods, no credit need be given for the fact
that a new and up-to-date replacement has been
purchased: Moore v DER Ltd [1971] 1 WLR
1476.”
i. There is no difference of approach between contract and tort.
j. There are, of course, some circumstances in which it is
appropriate for a deduction for betterment to be made. The
primary category of case is one of “extravagance”, meaning a
situation where the plaintiff unreasonably chooses a course which
results in betterment.
k. As Shelter JA explained in Hyder Consulting (Aust) Pty Ltd v Wilh
Wilhelmsen Agency Pty Ltd [2001] N.S.W.C.A. 313:
“[30] Several considerations are material. The
most significant is whether there is
evidence that the plaintiff had a reasonable
choice between adopting a less expensive
course of repair or reconstruction which
would mitigate its damage and the course it
chose which would not. A plaintiff may
decide for good business reasons to use
the occasion not merely to repair or rebuild
but to improve its facilities. To adapt the
words of Dr Lushington the question is
whether on the evidence a greater benefit
than mere indemnification could be avoided
without exposing the plaintiff to some loss
or burden.
-- 18 of 23 --
19
In my opinion, if a defendant negligently
damages or destroys the plaintiff’s property
and there is no evidence that the plaintiff
had any reasonable choice other than to
replace or repair what had been damaged
or destroyed, the cost of replacement or
repair, provided it is not extravagant, is
recoverable as damages. In each case it is
a question of fact.”
l. The evidential burden of establishing betterment is on the
Respondent.
m. In Roberts v Rodier [2006] N.S.W.S.C. 282 Campbell J observed
at [143]:
“Once the plaintiff has discharged the onus of
proving an amount which will remedy his or her
damage, the onus of adducing evidence is on the
defendant to prove both the presence of any
betterment, and also its quantum: J & B Caldwell
Ltd v Logan House Retirement Home Ltd [1999]
2 NZLR 99 at 110; Monroe Schneider
Associates (Inc) v No 1 Raberem Pty Ltd (1991)
33 FCR 1 at 29; Optus Networks Pty Ltd v
Leighton Contractors Pty Ltd & Ors [2002]
NSWSC 327 at [1402]-[1407].”
n. Similar observations were recently made by Bongiorno J in Paper
Australia Pty Ltd v Ansell Ltd [2007] V.S.C. 484 (a case in which
the cost of replacement of damages machinery with a modern
equivalent having greater capacity was allowed without deduction
for betterment).
o. The difficulties faced by a defendant in satisfying the evidential
burden was considered by the Full Court in Davidson v JS Gilbert
Fabrications Pty Ltd, when considering the question of measure
of damage the court said:
“Whilst the respondent must show that he acted
reasonably not only in his own interests but also in
the interests of the appellant – Jansen v Dewhurst
(supra) 426 – however, the court will not scruitinise
his conduct with an eye focused for criticism for he
is the victim of the appellant’s negligent conduct
and placed in the difficult position of making a
choice. Where he has been “placed in a position
of embarrassment the measures which he may be
driven to adopt in order to extricate himself ought
not to be weighted in nice scales at the instance of
-- 19 of 23 --
20
the party whose (conduct) has occasioned the
difficulty. It is often easy after an emergency has
passed to criticise the steps which have been
taken to meet it, but such criticism does not come
well from those who have themselves created the
emergency. The law is satisfied that the party
placed in a difficult situation by reason of the
breach of a duty owed to him has acted
reasonably in the adoption of remedial measures
and he will not be held disentitled to recover the
cost of such measures merely because the party
in breach can suggest that other measures less
burdensome to him might have been taken.
Banco de Portugal v Waterlow [1932] A.C. 452,
456 cited in Moore v D.E.R. Ltd [1971] 1 W.L.R.
1476; (1971) 3 All E.R. 517 C.A.”
70. I accept those submissions as to the legal principles involved in “betterment”. I
would also have thought that the legal principles relating to mitigation of
damages would be equally apposite, but I do not see any appreciable
difference between the legal principles relating to either concept – a person
acting to mitigate their loss only need act reasonably.
71. I find that the applicant did act reasonably in contracting to get a home as
similar as she could to the original home to be built by the respondent. It was
not possible by reason of copyright considerations to get exactly the same
home with exactly the same floor area, sizes of rooms, air-conditioning, size of
garage etc. Therefore I find that the fact that the living and garage areas of the
Thorne house are marginally bigger, does not mean that the applicant acted
unreasonably. Further, I find it reasonable that the applicant did not pore over
the plans for the respondent’s house and the plans for the Thorne house and
compare them, and compare specifications (the applicant did not even have the
respondent’s specifications), and then have plans and specifications redrawn,
presumably at greater expense. Therefore I do not find that it was
unreasonable of her to have solid core filled external walls in the Thorne house;
nor do I find it unreasonable if in fact there was additional electrical work in the
plans and/or specifications of the Thorne house; nor do I find it unreasonable if
in fact the screen windows specified for the Thorne house were of better quality
than the proposed screen windows for the respondent’s house; nor do I find it
unreasonable to have better air-conditioning.
72. However I do find that the applicant chose to have certain extras added to the
Thorne house which were not the result of simply having a different plan and
specifications. Accordingly I do not find that the respondent should be
-- 20 of 23 --
21
responsible for the extra cost caused by the applicant requesting higher
ceilings, additional paving, tiling in the garage, and turf to the yard.
73. I accept Mr Palmer’s evidence as to the extra cost involved in those items:
a. Ceiling variances - $14,000.00
b. Garage tiling - $ 2,000.00
c. Extra paths - $ 1,500.00
d. Turf - $ 1,500.00
$19,000.00
74. I accept that the driveway with respect to the Thorne house is not as large as
described by Mr Palmer. I do not think it is reasonable to expect that the
applicant should have picked up the fact that (if it be the fact) that the
dimensions of the driveway in the Thorne plan were greater than was
necessary or that she should have negotiated a lower price. Nor do I think it
reasonable to suggest that she has a remedy against Thorne by way of suing
him. It is doubtful whether she could succeed, but in any event, the cost of
legal action would obviously outweigh any benefit to her.
75. Accordingly I find that the applicant is entitled to recover damages of
$23,945.00 being the difference in the contract price of the Thorne house and
the contract price of the respondent’s house of $42,945.00 less $19,000.00 for
the additions deliberately chosen by the applicant for the Thorne house.
NEGATIVE GEARING
76. It was submitted by the respondent that because the applicant’s financial affairs
were so arranged that she was able to obtain the benefits of “negative gearing”
with respect to tax, that this must therefore show that in fact she was not
making any profit from the rental of the house at Lenesha Drive. However, the
fact is that evidence was adduced as to what the applicant’s interest costs were
and her other costs including insurance and it was established that the
applicant was making a profit. Therefore the general observation by the
applicant that she was negatively geared does not stand up in the face of the
actual evidence; in all probability she has other financial affairs (e.g. she has a
business and least one other rental house) the totality of which results in a
negative gearing benefit to her.
SALE OF NEBO ROAD
77. I have referred to the buying and selling of the Nebo Road property in
paragraph 11 of these reasons. In the end result the applicant made a profit of
$23,066.00 out of that Nebo Road property.
-- 21 of 23 --
22
78. The respondent submits that the applicant should account for this profit by
deducting it from her damages claim as the delay in the construction of the
house enabled her to buy Nebo Road.
79. However the applicant’s evidence was that although she used the draw-down
facility on her residential home to buy the Nebo Road property, she was still
intending to pay, and would have paid, the cost of the construction of the
Lenesha Drive house (had it been commenced), but that she would have to
have gone to some extra expense to do so, by arranging for her lender to
prepare appropriate mortgage documents to secure the loan for the Lenesha
Drive house.
80. The reason for asking for the 1 month delay in construction of the Lenesha
Drive house (as referred to previously) was simply to save herself the cost of
having mortgage documents prepared as she knew that settlement of the Nebo
Road property was to occur in early January 2008 and she would then have the
benefit of the off-set facility on her residential home to pay for the Lenesah
Drive house.
81. I accept the applicant’s evidence in this regard and I find that there is no causal
connection between the respondent’s failure to construct the Lenesha Drive
house and the applicant’s decision to buy and then sell the Nebo Road
property. Therefore I do not deduct the profit that the applicant made from the
Nebo Road transaction from her damages.
CONCLUSION
82. I therefore propose to order that the respondent pay to the applicant the sum of
FORTY THOUSAND TWO HUNDRED and THIRTY ONE DOLLARS
($40,231.00) for breach of contract.
83. The applicant sought interest on the deposit monies in the amount of $971.48,
relating to the applicant having lost the use of that money between 11
September 2007 and 28 July 2008. The respondent did not dispute the
calculation of this amount of interest by the applicant.
-- 22 of 23 --
23
84. The applicant also sought interest on the capital loss, for which calculations
were provided based on the claimed capital loss of $42,945.00 from 13 August
2009 to 12 March 2010. The calculation results in a claim of $1,396.18. Since I
have found that the capital loss claimable from the respondent is not
$42,945.00, but $23,945.00, I calculate that the interest on a pro-rata basis is
$778.00. I add another $100.00 to that to account for a period of approximately
two weeks from 12 March 2010 up to the date of judgment.
85. By reason of this matter having commenced prior to the commencement of the
Queensland Civil and Administrative Tribunal on 1 December, 2009, but the
hearing not actually occurring until subsequent to the commencement of QCAT,
the cost provisions of the Commercial and Consumer Tribunal Act 2003 still
apply – see Owen v The Adams Group Pty. Ltd. [2010] QCAT 10. However,
both the parties in this case agree that costs should follow the event, as I
understand it, particularly because of the complexity of the matter, including
complexity as to the calculation of damages.
There also seems to be agreement that if there was a situation where one party
was partially successful, costs should be awarded on a pro-rata basis. In any
event, if there was no such agreement in fact between the parties, it is my view
that the respondent did have partial success in its defence and that it is fair and
reasonable that costs be awarded on an approximate pro rata basis. In my
view, an appropriate proportion would be allowing 60% of the applicant’s costs
of and incidental to this action to be assessed on the lowest District Court Scale
-- 23 of 23 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2010/114