Actell Glass Pty Ltd v MKM Group Pty Ltd & Anor [2010] QCAT 62
CITATION: Actell Glass Pty Ltd v MKM Group Pty Ltd & Anor [2010]
QCAT 62
PARTIES: ACTELL GLASS PTY LTD
V
MKM GROUP PTY LTD
AND
MLADEN MICHAEL KLJAIC
APPLICATION NUMBER: BD445-07
MATTER TYPE: Building Matters
HEARING DATE: 07.09.09, 08.09.08, 09.09.09, 10.09.09 and 17.09.09
HEARD AT: Brisbane
DECISION OF: Mr Paul Favell
DELIVERED ON: 16 March 2010
DELIVERED AT: Brisbane
ORDERS MADE: The Tribunal orders the second respondent to pay
$120,693.08 ($95,414.44 plus $25,278.64) to the
applicant by 4pm on 2 April 2010.
CATCHWORDS: Domestic Building Contract- defective work- variations-
APPEARANCES AND
REPRESENTATION:
Mr M. Ambrose of Counsel instructed by TVP Law for the
first and second respondent.
Mrs W. Csukardy director of the applicant.
-- 1 of 39 --
REASONS FOR DECISION
Introduction
1. On or about 31 November 2006 the applicant, Actell Glass Pty Ltd (“Actell”),
and the first respondent, MKM Group Pty Ltd (“MKM”), agreed in writing that
Actell would supply and install glazing and related products at a residential
property at 95 Gibraltar Drive, Isle of Capri for $89,650.00 plus GST.
2. The applicant contends that the agreement was constituted by plans provided
by the second respondent, Mr Michael Kljaic (“Kljaic”), to Actell in or about
October 2006 a revised quote submitted by Actell to MKM on or about 13
November 2006 and an acceptance from MKM to Actell dated 1 December
2006.
Factual Background and Claims
3. The applicant is in the business of supplying and installing glass windows,
doors and related framing. The first respondent is a builder and the second
respondent is the director of the first respondent.
4. In or about late November 2006, the applicant and the first respondent
entered into a ‘Housing Subcontract Agreement’ in standard QMBA form (as
it was in May 2005) to carry out certain works for an agreed contract price of
$98,615.00 (GST inclusive) at a property located at 95 Gibraltar Drive, Isle of
Capri situated on the Gold Coast. The Principal to which the first respondent
had contracted was the Kljaic Family Trust and it is not in contest that there
was a formal written contract in that regard.
5. The written subcontract agreement between the first respondent and the
applicant is dated November 2006.
6. The applicant seeks to hold the second respondent responsible for any
liability of the first respondent under the contract by reason of the guarantee
forming part of a credit application. The applicant contends that Kljaic
guaranteed the obligations of MKM under the agreement.
7. The applicant contends that it commenced installing the products in the week
commencing 5 February 2007.
8. The applicant contends that variations totalling $64,873 plus GST were
requested. The applicant contends that on or about 31 May 2007 it
completed the works and the variations.
9. The applicant has been paid $9,861.50 in respect of invoice 46228 (progress
claim 1) and $22,305.36 in respect of invoice 46263 (progress claim 2).
Otherwise claims for payment of $79,359.94, $41,618.50 and $16,830.00
have not been paid. (progress claim 3 and variations 5 and 6)
-- 2 of 39 --
Applicants claim
10. The applicant claims $137,808.44 together with interest at the rate of 10%
per annum from 31 May 2007. In written submissions that claim was put at
$180,324.42. Associated costs of $28,066.93 (which were made up of legal
costs, application costs, costs of reports and witness expenses) were also
claimed and a sum of $250,000.00 “restitution” was claimed but later
abandoned.
Respondent’s response and counterclaim
11. In response to the applicants claim the first respondent says it is not indebted
to the applicant and makes a counterclaim.
12. The first respondent counterclaims that the glazing works required to be
carried out by the applicant under the agreement:
(a) are not practically complete;
(b) were not carried out in a proper and tradesmen like manner;
(c) were not carried out in accordance with the plans and
specifications as required under the Agreement; and/or
(d) were not carried out in accordance with Australian Standards.
13. The first respondent further claims that substantial rectification and
reconstruction works are / were required to be undertaken to complete the
glazing works in accordance with the agreement as set out under the item
numbers below.
Item 1: Front door
14. The first respondent claims that the existing front door installed by the
applicant does not comply with the Australian Standard AS 1288, 2006.
15. MKM claims that the door is required to be removed and reinstalled with
15mm toughened glass.
16. MKM also claims that the fixed glass panel beside the door has not been
sealed in place and requires sealing.
Item 3: Stacker sliding door frame alignment with windows above in courtyard
17. MKM claims that the applicant has failed to align the vertical mullions of the
“stacker” sliding dors in both locations in the Courtyard off the formal lounge
with the vertical mullions of the fixed glass windows coupled above the sliding
doors.
18. MKM claims that the horizontal transoms in the fixed sashes of the
courtyard/corridor high light windows do not align and that there are signs of
water ingress.
-- 3 of 39 --
19. MKM claims that the existing frames are required to be removed and new
frames manufactured and installed.
Item 4: Tops of Stacker Sliding Door Frames in Courtyard incomplete
20. MKM claims that the applicant failed to fit finishing plates with a purpose-
made stop which has left an open section at the top of the end plate of these
frames.
21. It is claimed that finishing plates are required to be fitted.
Item 5: Office Sliding Door
22. MKM claims that the applicant failed to fit the handle on the external face of
the closing mullion.
23. MKM further claims that the applicant failed to fit the top of the door with
interlocking blocks, stop blocks and end caps to the stop blocks.
24. It is claimed by MKM that the applicant failed to remove excess sealant used
in the frame/wall junction.
25. MKM claims that these works are required to be completed.
Item 6: Dining Room Sliding Door
26. MKM claims that the head margins between the cover plates and the door
frame are not parallel and require straightening to achieve even/parallel
margins.
Item 7: Laundry Sliding Door Frame
27. MKM contends that the applicant failed to fit the cover plate to the right-hand
end stile of the sliding door correctly which has resulted in a large gap at its
head.
28. MKM claims that the applicant failed to clean excess sealant used on the
frames at the wall junctions.
Item 8: Rear Hopper Window
29. MKM claims that the lower section of the hopper window shows an ”out of
parallel” against the sill section of the frame when in the closed position and
requires rectification.
Item 9: Fixed Window at Rear Elevation
30. MKM claims that visible calcium staining was left at the coupling bar along
the sill section as a result of water being trapped in the extrusion and
weeping out via the joint.
31. It says this requires rectification as well as reinstating the damage to the face
of the aluminium.
-- 4 of 39 --
Item 10: Kitchen Sliding Door
32. MKM claims that the applicant installed an incorrect sill profile to the sliding
door which does not allow water to drain externally.
33. The sill is required to be replaced with the correct extruded section.
Item 11: Family Room Window and Door Stiles do not line up
34. MKM claims that the applicant has failed to align the sliding door frames to
the rear elevation of the family room with the mullions of the window/wall
section directly above.
35. It is claimed that the existing frames are required to be removed and new
frames manufactured and installed.
Item 12: Family Room “Stacker” Sliding Doors
36. MKM contends that the applicant has cut the tops off each stiffening vertical
mullion in the sliding doors at differing heights and at differing angles.
37. It is contended that this defect applies to every door set throughout the
dwelling.
38. MKM claims that the applicant has poorly placed a screw fixing adjacent to
one of the handles of this “stacker” sliding door which has protruded out
through the side of the closing mullion.
39. The mullions of this “stacker” sliding door do not correspond in vertical
alignment with the mullions of the window joinery directly above.
40. It is claimed that the existing frames are required to be removed and new
frames manufactured and installed in order for these defects to be rectified.
Item 13: Cantilevered Bedroom Windows
41. MKM contends that the windows installed by the applicant leak water and
require wet sealing to stop water penetration.
Item 14: Gym Sliding Door
42. MKM submits that the door is prevented from fully engaging into the jamb by
a “D” type door handle that hits the frame when the door is closed.
43. It is claimed that the correct door stops have not been installed to prevent the
handle hitting the frame.
Item 15: Automatic-Opening Garage Sliding Door
44. MKM claims that glazing panels to the head of the frame installed by the
applicant have not been fully completed in the beading area which work
requires completion.
Item 16: Master Bedroom Windows and Doors
-- 5 of 39 --
45. MKM asserts that the lever handles to the hopper sash windows in this room
supplied and installed by the applicant are black coated units which are
inconsistent with the rest of the house (where clear anodised units are
installed) and should be changed.
46. MKM claims that the applicant has failed to install “interlock” blocks and the
correct door stoppers.
47. It is claimed that removal of the face fitted door stops installed by the
respondent will need repair as screw fixing holes will be left when the proper
stoppers are fitted.
Item 17: Daughters Bedroom Windows
48. MKM asserts that the lever handles to the hopper sash windows supplied and
installed by the applicant in this room are back coated and inconsistent with
the rest of the house (where clear anodised units are installed).
Item 18: Nursery Stacker Sliding Doors
49. It is claimed that the applicant has failed to fit the external door handles
causing the door to be difficult to operate from the outside.
50. The applicant has also failed to fit integrated door stops designed to match
the joinery in this room.
Item 19: Roof Top Terrace
51. MKM claims that the joins in the sill sections and the head sections of the
“stacker” sliding door frame to the rear elevation of the roof top terrace are
out of alignment and not flush.
52. The vertical stiffening mullions on these “stacker” sliding doors have been
trimmed in length (on site) by the applicant and MKM submits that the finish
at their top is uneven and cut on differing angles.
Item 20: Stacking Sliding Door System corresponding with a defect identified by
Gary Holmes, Branch Manager in the report and quotation of G. James Glass &
Aluminium dated 13 January 2009].
53. The stacking sliding door systems installed by the applicant at the premises
were generally installed back to front.
54. Presently these stacking door systems all slide internally leaving exposed
weep holes and air pressure holes.
55. It is submitted that in order to rectify this defect the door systems should be
reversed so that the doors slide externally and the door threshold will cover
the weep holes and air pressure holes.
Item 21: various remaining defects identified in the Report of Robert A Hancock &
Associates (not including Items 1 to 20)
-- 6 of 39 --
56. The costs to undertake the rectification and reconstruction works as
estimated by Gary Holmes Branch Manager for G James Glass & Aluminium
in his report and quotation dated 13 January 2009 are as follows:
Item
Number(s)
Item Description Cost GST Total
1 Front Door $5,025.00 $502.50 $5,527.50
3, 11 and
12
Stacker Sliding Doors
Frame Alignment:
- courtyard frames
- canal front frames
$18,840.00
$14,200.00
$1,884.00
$1,420.00
$20,724.00
$15,620.00
10 & 20 Stacking Sliding Door
Systems
$6,600.00 $660.00 $7,260.00
13 Cantilevered Bedroom
Windows
$2,400.00 $240.00 $2,640.00
4, 5, 6, 7, 8,
9, 14, 15,
16, 17 and
18
“various items” $4,850.00 $485.00 $5,335.00
$51,915.00 $5,191.50 $57,106.50
57. The first respondent claims against the applicant the full costs of the
rectification and reconstruction works ($57,106.50) as a debt due by the
applicant to the first respondent.
58. The first respondent also claims, as against the applicant, liquidated
damages at $500.00 per day, for each day after the date for completion of the
glazing works in accordance with clause 2 of the Agreement. The first
respondent asserts that the date for practical completion was, as agreed, on
or about 5 March 2007.
59. The first respondent also claims as against the applicant the following
additional costs (trade costs) incurred by the first respondent as a direct
consequence of incomplete works, delay in completion of works, the
applicant’s re-fitting of window frames and failure by applicant to carry out the
works in a proper and tradesman like manner:
(a) External rendering $11,600.00
(b) Scaffolding for an extra six (6) weeks $11,827.20
(c) Mobile scaffolding $ 2,304.94
-- 7 of 39 --
(d) Waterproofing work to windows $ 2,560.00
(e) Protection of bottom window sills $ 2,425.50
(f) Labour to clean site (2 days total) $ 600.00
(g) Cleaners $ 300.00
(h) Gold Coast Door Control $ 3,245.00
(i) Commercial Windows Qld $ 2,574.00
(j) Commercial Windows Qld $ 3,498.00
(k) Unique Carpet Care & Pest Management $ 1,452.00
$42,386.64
60. Following the rectification and reconstruction works required as itemised
above, the first respondent estimates that additional trade costs will be
incurred by the first respondent to effect repairs required to the window and
door surrounds as follows:
(a) Re-tiling around doors and windows $ 7,000.00
(b) External and Internal rendering $12,000.00
(c) Gyprock (plasterboard) $ 2,500.00
(d) Painting $ 1,200.00
(e) Waterproofing $ 2,000.00
(f) Scaffolding for 4 weeks for rendering and
gyprock work $11,500.00
(g) Cleaning $ 2,000.00
$38,200.00
61. The first respondent contends that in or about December 2007, water leaks
appeared in the ceiling of the family room of the premises at the Gibraltar
Site. The first respondent asserts that the source of the water leak was the
tracks of the sliding glass doors of the upper level roof terrace of the
premises (“the tracks”).
62. The first respondent claims that the tracks, as installed by the applicant, had
been fitted in such a manner that the external upper edge of the tracks was
higher than the internal upper edge of the tracks. It is claimed that this
manner of installation inclined water to flow away from the drain hole in the
external side of the track and flow back into the mortar bed underneath the
tracks.
-- 8 of 39 --
63. The first respondent asserts that the installation of the tracks and generally
the installation of the frame of the glass doors of the roof terrace caused
water to ‘pond’ and flow into the mortar bed of the premises, rather than
through the drain hole in the side of the track.
64. It is also submitted that the tracks had a saw cut in the base that also allowed
water to flow freely into the mortar bed.
65. The tracks (sills) installed by the applicant had a vertical structure/fin
underneath the track. It is claimed by the first respondent that when the
tracks had been installed by the applicant, this vertical fin had been forced
hard down into the waterproof membrane causing it to rupture.
66. The first respondent claims that from the mortar bed, the leaking water
permeated the ruptured membrane and made its way through the concrete
slab into the family room below.
67. The first respondent claims that in December 2007 and in around July 2008
rectification works were required to be undertaken by the first respondent and
its sub-contractor All Metal Works Pty Ltd to repair the damage caused by the
water leaks and to remove and reinstall the glass, window and door frames.
68. It is claimed that the rectification worked undertaken by the first respondent in
December 2007 included:
(a) Jack hammering tiles to top floor balcony
(b) Re-waterproofing, re-bedding, re-tiling, re-sealing new tiles
(c) Moving furniture and erecting scaffold
(d) Removal of all panels and bulkhead
(e) Removal of damaged plasterboard
(f) Cut through Bondec to determine source of leak
(g) Replacement and re-installation of damaged plasterboard
(h) Re-painting
(i) Re-installation of down lights
(j) Dismantling scaffold
(k) Cleaning of site and moving furniture
69. The rectification works undertaken by All Metal Works Pty Ltd in July 2008
included removal of glass and window and door frames to top level of house
and the re-installation of complete system.
70. The cost of the repairs undertaken by the first respondent was $16,500.00
71. The cost of repairs undertaken by All Metal Works was $36,062.40.
-- 9 of 39 --
72. The first respondent claims that the installation of the tracks and generally the
installation of the frames of the glass doors of the roof terrace undertaken by
the applicant under the Agreement was not carried out:
(a) In a proper and tradesman like manner;
(b) In accordance with the plans and specifications as required under
the Agreement; and/or
(c) In accordance with Australian standards.
73. The first respondent claims against the applicant the costs of the rectification
works required to repair the damage caused by the water leaks at
$52,562.40.
The First Respondent’s Second Counterclaim – the Calabro Way Site
74. In or about July 2006, the parties entered into a Commercial Subcontract
Agreement for the supply and installation of windows and doors in
commercial units located at the Calabro Way Site (“the Calabro Way
Agreement”).
75. The first respondent asserts that in so far as the Calabro Way Agreement
was in writing it is evidenced by the following:
(a) A revised quotation from Actell to MKM dated 7 June 2006; and
(b) A Commercial Subcontract Agreement signed by Actell on 7 June
2006 and signed by MKM on 10 June 2006.
76. The scope of the works for the Calabro Way Agreement was supply and
installation of wall commercial windows and entry doors all in accordance
with plans, specifications and revised quotation 4 dated 7 June 2006 (“the
Calabro Way Works”).
77. The price of the Calabro Way Works was $99,560.00 plus GST.
78. The first respondent asserts that it was a condition(s) of the Calabro Way
Agreement that the Calabro Way Works be undertaken:
(a) Pursuant to the terms of the Commercial Subcontract Agreement;
(b) In accordance with the plans and specifications;
(c) In an appropriate and skilful way;
(d) With reasonable care and skill;
(e) In a proper and workmanlike manner; and
(f) To the satisfaction of the applicable Australian standards.
79. In accordance with the Calabro Way Agreement, and from or about August
2006, Actell undertook the Calabro Way Works.
-- 10 of 39 --
80. All monies invoiced by Actell to MKM in respect of the Calabro Way Works
were paid by MKM.
81. The first respondent asserts that the Calabro Way Works are defective as the
windows and doors installed by Actell at the Calabro Way Site are not
properly sealed and leak water.
82. Accordingly, the first respondent asserts that the Calabro Way Works were
not undertaken by Actell:
(a) Pursuant to the terms of the Commercial Subcontract Agreement;
(b) In accordance with the plans and specifications;
(c) In an appropriate and skilful way;
(d) With reasonable care and skill;
(e) In a proper and workmanlike manner; and/or
(f) To the satisfaction of the applicable Australian standards.
83. The first respondent asserts that work is required to fix the water leaks and
that, despite demand, the applicant has failed or refused to attend the
Calabro Way Site to rectify the water leaks.
84. The first respondent claims against the applicant payment of the sum of
$20,639.30, being costs of undertaking the rectification work required at the
Calabro Way Site.
85. In all, the counterclaims amount to $190,255.54 plus liquidated damages.
Reply and answer
86. In response to the defence of the respondent, the applicant claims:
(a) The matters alleged at paragraphs 1-12 inclusive, 16 of the
Defence are irrelevant to the determination of these proceedings;
(b) In relation to paragraph 14(b), the works commenced in the week
commencing 5 February 2007;
(c) In relation to paragraph 15(d), the Statutory Declaration referred
to is not attached to the defence served on the applicant;
(d) The admissions both express and implied in the defence are
adopted;
(e) The matters contained in the applicant’s Statement of Claim are
otherwise repeated and adopted.
87. In answer to the counterclaim of the respondent, the applicant claims:
(a) In relation to the work performed by the applicant at the Gibraltar
Drive, Township Drive, Lemana Lane and Calabro Way sites, the
-- 11 of 39 --
work was not defective in the manner alleged by the respondents
or at all except as identified in the report of Jeffrey Hills &
Associates dated 4 July 2008 filed in these proceedings (I note
only the Calabro Way counterclaim is pursued by the
respondents);
(b) In relation to paragraphs 20 and 21 and the costs of rectification
works identified in the report of Robert A Hancock & Associates
dated 2 July 2007, those costs are not referable to any breach of
contract, negligence or other legal liability of the applicant and
further, those costs are unreasonable to attend to the defects
alleged by the respondents;
(c) In relation to paragraph 24:
1. the contract did not contain a provision for the payment
of $500.00 for liquidated damages;
2. the contract was not subject to practical completion by
5 March 2007 or any agreed timetable at all and
further, the respondents required numerous variations
to the original contract which could not have been
completed by 5 March 2007 in any event.
(d) In relation to paragraphs 25 and 26, the amounts claimed are
unreasonable and the need to incur any such cost is not
referrable to any breach of contract, negligence or other legal
liability of the applicant to the respondents;
(e) In relation to paragraphs 27 to 37, any leaks in the ceiling alleged
by the respondents are not referrable to any work performed by
the applicant and the works referred to in paragraphs 28 and 29
allegedly causing the leaks were performed by the respondents,
not the applicant;
(f) In relation to the allegations in paragraph 13, there was no failure
or refusal to attend the Township Drive site to rectify any water
leaks;
(g) In relation to the cost of rectification of alleged defective works
contained at paragraph 14 on page 7, the amounts claimed are
unreasonable and the applicant relies on the report of Jeffrey
Hills;
(h) In relation to the allegation in paragraph 22, the works at the
Lemana Lane site were not defective and relies on the report of
Jeffrey Hills (I note this claim was not pursued by the
respondents);
(i) In relation to the costs of defective repair work alleged at
paragraph 30, the costs alleged are unreasonable and relies on
the report of Jeffrey Hills;
-- 12 of 39 --
(j) In relation to the allegation at paragraph 42, it did not perform any
defective work at the Calabro Way site;
88. In relation to the costs of repair works claimed at paragraphs 46 and 47, the
amounts claimed are unreasonable and relies on the report of Jeffrey Hills
Evidence
89. The Applicant relied upon the evidence of Jeffrey Hills (ex 1), Jack Perovic
(ex 4), David Snow (ex 6), Ken Elsdon and Robert Csukardy (ex 7).
90. The respondents relied upon the evidence of Michael Klaic (exs 8 and 9),
Bevin Sim (exs 12 and 13), a quote from G. James (ex 15), Robert Hancock
(exs 16 and 17), Josip Brkic (ex 18), Troy Aherns, Leslie Simmons (ex 19,
Davor Erceg (ex 20) and Alan John Herbert (ex 21) as well quotes from
Commercial windows (Mr Van Hoven) (exs 22 and 23), a report from BSA (ex
11) and various photos.
91. The Tribunal also had a joint experts report (ex 2).
92. As well as the issues outlined above some matters arose or we emphasised
during the hearing. They included: the extent of the contract; was there a
construction timetable?; were there any remedies for delay?; were variations
made and if so how?; did defects or mistakes attributed to the applicant
cause other matters to be rectified?; were the applicants responsible for the
leaks?; was a steel beam required?; is there any common ground from the
experts?; were the applicants banned from the site and if so when?; was any
lock out reasonable and a breach of contract?; did the applicants delay and if
so did they breach the contract?; was the motor commissioned and was it
faulty? and was the water proof membrane in tact when the windows were
put in?.
93. David Snow, a director of the applicant whose statement became exhibit 6
gave evidence and was cross examined. His evidence establishes the credit
application and the contractual documentation relied upon. During his
evidence he pointed out clauses 2a and 2b of the subcontract which refer to
the start and completion of the work. He pointed out that although the words
“as per construction programme” were used there was no construction
programme.
94. The works to be carried out under the subcontract which was between the
applicant and the first respondent was described in the subcontract as
“supply and install Aluminium commercial windows and doors to the above
project all in accordance with plans specifications and quotation (revised) 13-
11-06 including clear anodised frames blue glass” (ex 5 to exhibit 6).
Matters Raised by the Applicant
95. The applicant relies on the report of Jeffrey Hills (“Hills”). Mr Hills commented
on the report provided by the BSA. Much of that report was as observed by
Hills. The applicant outlines the main points therein as follows:
-- 13 of 39 --
(a) Hills described in detail how the roof top leak could have occurred
due to differential shrinkage of the slab. He drew it on the white
board (Exhibit 5). Hills gives a written explanation on page 11 and
12 of Exhibit 1 of the problems and issues he had with Hancock’s
report (Exhibit 17) regarding the leak to the roof terrace. One of
the points he makes is ‘I am concerned that the conclusion
reached by Hancock may be construed as slightly biased and not
that of an independent observer given the available evidence’;
(b) Hills agreed in his oral evidence that the house was only Certified
for two levels, but Kljaic built a third level enclosed roof terrace
that was not on the certified plans;
(c) Hills confirmed that the front entry door complied with 1288-2006
Australian Glass and Glazing Standards;
(d) Hills gave a costing to re-align the stacker door mullions with the
fixed windows above as $1,500.00 per opening. There are three
openings in the house;
(e) Hills said it was unnecessary to remove the roof-top terrace
doors, fixed glass and frames;
(f) Hills said the waterproofing was the responsibility of the builder
and the area under the sill becomes saturated due to seepage
through the tile bed. A cut in the sill would not have caused water
to leak through the roof;
(g) The respondent’s costing to remove the roof terrace doors was
$36,036.00. Hill’s costing was two men for two days at $45.00 an
hour = approximately $1,500.00, including one extra day for
contingencies the total max cost was $2,250.00. He said the
respondent’s invoice was unrealistic;
(h) Hills said $2,500.00 for a door lock was excessive;
(i) Hills stood by his costing of $6,000.00 to complete the work
recommended by the BSA report;
(j) Hills noted that Hancock failed to raise at the expert’s conclave
items that he perceived to be defective in his first report in July
2007;
(k) Hills stood by his statement relating to Kljaic’s admission to him
that a plank was placed on the window sill by external workers
and hence causing the damage;
(l) Hills confirmed the opening for the dining room sliding door was
the responsibility of the builder to ensure it was square;
(m) Hills confirmed that a window schedule was not provided and that
had one been provided, doubt over the sliding door aligning with
the fixed window above may not have happened. Actell complied
with industry standards;
-- 14 of 39 --
(n) Hills confirmed he had not seen a head contract;
(o) On the day that Hills attended the Calabro Way site, it was raining
and he only saw evidence of water leaks on 3 windows. He said
this could be repaired with a tube of silicone and a ladder.
With regard to Hancock’s report, the applicant asserts:
(p) Hancock did not notice that the Approved Building plans were
only for a two storey house when a three storey house was
actually constructed;
(q) The Housing Subcontract Agreement Hancock refers to did not
match the quotes he was given and he failed to mention this is his
report;
(r) The formula based on the ‘rate per square metre of glazing to be
replaced similar to the original rate per square metre for the cost
to install the glazing’ was based on an incorrect document;
(s) The quote prepared for the three storey residence upon which the
contract was formed had more square metres than the first two
quotes dated 3 October 2006 and 23 October 2006 and a
different price. Hancock’s calculation of price per square metre for
installation was incorrect and, consequently, his quote for
$45,000.00 to $50,000.00 was incorrect;
(t) Mr Jack Perovic (“Perovic”) also disputed the defect list;
(u) The report of Jeffrey Hills (“Hills”) found:
i. That to ‘rectify and replace the necessary works to comply
with the requirements of the BSA summary would be of the
order of $6000 plus GST. The costings by Hancock are
considered commercially unrealistic’
ii. The conclusion reached by Hancock may be construed as
slightly biased and not that of an independent observer given
the available evidence;
iii. Hancock failed to raise at the expert’s conclave items that he
perceived to be defective in his first report in July 2007;
(v) The saw cut that allowed water caught in the track on the roof to
flow freely into the mortar bedding beneath the track and make its
way through the damaged section of the waterproof membrane
and through the concrete slab to the room below was not there
when Hancock did his first report. Hancock admitted that the cut
was not mentioned in his first report. Hancock agreed that this cut
was visible. Even though Hancock considered the cut serious
enough to put in his later report, it had not been fixed nearly a
year later.
96. With regard to Kljaic’s Statutory Declaration, the applicant asserts:
-- 15 of 39 --
(a) The conversation at the signing of the contract between Kljaic and
Mr Elsdon did not happen as alleged because Mr Elsdon testified
that the contract was signed by the parties separately via post.
This was confirmed by the letter dated 1 December 2006 and the
signing dates on the subcontract agreement, which are four days
apart;
(b) There was no agreement made to pay for window protection
because Mr Brkic testified that he commenced work on site on 19
March 2007 and rendering could not be done before the windows
were installed;
(c) The glazing work begun in late February 2007 to early March
2007 because Mr Brkic testified that he commenced work on site
on 19 March 2007 and rendering could not be done before the
windows were installed. This is further evidenced by Mr Stibbard’s
invoice stamped and dated 9 March 2007 and the fact that Kljaic
agreed that he had to have seen the frames or sills installed to
then make contract with Mr Stibbard and organise the window
protection work;
(d) Kljaic’s constant threats of $500.00 a day liquidated damages
were not reasonable as there was no construction schedule on
which to base the claim. This was confirmed by Mr Snow and Mr
Elson’s oral testimonies;
(e) Kljaic’s claim that he was not happy with the work the applicant
was doing on site is illogical considering that he signed DS
attachment 22;
(f) Kljaic changed his story by first denying that the applicant was on
site in February 2007 and then asserting that he did not think that
10% of the work had been done in February when questioned by
the applicant as to why he sent the facsimile dated 12 March
2007;
(g) Kljaic relied on the facsimile dated 12 March 2007 to comply with
item 4cii of the Subcontract Agreement. The applicant questions
why, given the importance of the document, Kljaic failed to include
this document with his Exhibit 8 Stat Dec- Index of
Correspondence and make reference to it in his Statutory
Declaration;
(h) Kljaic failed to include in his Statutory Declaration the facsimile
dated 12 March 2007 sent to him by Actell and when questioned
by the applicant, gave an explanation of how his accounts
department must not have received it before the end of the month
and if they had he would have paid it;
(i) Kljaic’s claim that he responded immediately to the claim that
there were overdue accounts is untrue. The account was first
brought to his attention on 12 March 2007 and he failed to
respond to his overdue account until 22 March 2007;
-- 16 of 39 --
(j) Kljaic signed a personal guarantee on a Credit Application and, in
particular, paragraph 3 under the Terms of Payment meant that
the Facsimile dated 12 March 2007 could be considered as
though the applicant’s were in anticipation of him breaching the
contract. Thus, MKM being overdue on an account on a previous
job affected this contract;
(k) Kljaic’s statement that ‘not one single piece of aluminium window
was fixed into the house at that time’ was untrue because the
applicant proved that it was on site at that time, installed and
delivered the material. This was evidenced by Kljaic paying the
account on 4 April 2007 even though Kljaic stated that he only
paid the account to keep the peace;
(l) Kljaic only paid 10% of the account because TVP Law advised
him to do so. The applicant asserts that this is evidenced by the
numerous facsimiles from Kljaic to TVP Law on 3 April 2007;
(m) Kljaic did not pay the applicant’s account in time because his
account was in overdraft, as evidenced by Kljaic’s bank
statements in Exhibit 8;
(n) Kljaic’s denial that the steel beam was installed in accordance
with the original plans because the transom, used to install a
single 5.9 meter floor to ceiling glass like curtain, wall would be in
the way of the rolling automatic curtains is untrue and he did
authorise the variation. The series of events surrounding the
installation of the steel beam and evidence provided by Perovic
are correct. Mr Perovic and Mr Elsdon both testified that the job at
Calabro Way was not the same application as the Gibraltar Drive
job. Calabro Way was fixed glass and a hinged door. Gilbraltar
Drive was fixed glass and stacker doors. Mr Elsdon denied saying
that he could do the same works on the Gilbraltar Drive site as he
did at the Calabro Way site;
(o) Delays in the project were due to Kljaic requesting changes. This
is evidenced by Perovic’s statement which, the applicant asserts,
has shown to be reliable;
(p) Kljaic’s statement is unreliable because he initially says in Exhibit
8 para 68 that the meeting on site on 27 April 2007 was with Mr
Snow only, but changes in Exhibit 9 para 25 say that Mr Robert
Cskardy was there. The applicant submits that Snow gives an
accurate account of the meeting on site on 27 April 2007. This is
confirmed by Mr Csukardy’s testimony and statement;
(q) Kljaic’s assertion that ‘vertical mullions in the floor to ceiling glass
walls and the void panels did not line up’ would not have existed if
Kljaic had supplied a window schedule to the applicant. Hill’s
report responds to Kljaic’s statement by stating ‘as there was no
specification or details contained in the plans the contractor has
adopted industry standard and made the doors uniform. By
-- 17 of 39 --
default however as the door mullions are larger than the windows
above, the framing does not align’;
(r) Kljaic admitted in testimony that he forwarded a defect list to his
solicitors, TVP Law, but not to the applicant despite constant
requests. The applicant asserts that this was in breach of
paragraph 17b of the Contract;
(s) Kljaic admitted in testimony that did not follow 18b of the Contract
which states that ‘if conciliation in accordance with Condition
18(a) is unsuccessful, then a domestic building dispute must be
referred to the Queensland Building Tribunal for resolution’;
(t) Kljaic’s statement that ‘in the second week of June 2007 I had
instructed TVP Law to engage a consultant to inspect and report
on the works…about one (1) week later, in about mid June 2007, I
had a call from Robert’ is unreliable and untrue. The applicant
asserts that Kljaic stated in this telephone conversation ‘don’t you
dare set a foot on site. I don’t owe you anything’ and that
Csukardy’s version of the conversation is correct;
(u) Kljaic asked Mr Alan Herbert (“Herbert”) to make the statement
concerning the vertical fin rupturing the waterproof membrane to
prove this case and increase his counterclaim. The applicant
asserts that Herbert’s statement is impossible considering that the
sill had no fin on it. Kljaic changed his statement to it being
screws and packers that broke the membrane. Kljaic admitted
that he had not taken any photographs to prove his find, had not
called out a building expert to confirm it, had not informed Bevan
Sim (“Sim”) when he did his report in November 2008 that he had
done major rectification work to the roof top terrace in July 2008
and had not informed Hill that he continued having leaks in early
2008. Herbert could not show where on the photographs the sill
being installed back to front had caused water to run back into the
room. The applicant asserts that Herbert’s statement is a lie
because it is never mentioned in any of the four expert reports
and Mr Glen Van Hoven (“Van Hoven”) from Commercial
Windows Queensland testified that all the sills were installed the
right way;
(v) Herbert could have only changed his statement regarding the
membrane if he was told by someone who was at the hearing
what to say and the truthfulness of his statement is called into
question because Herbert testified that he put things in his
statement that Kljaic had told him about and he had not
personally seen. Herbert said when he was signing his statement,
which he admits he signed at TVP Law, he didn’t read the
statement properly and ‘vertical fin’ should read ‘vertical screw’;
(w) The following invoices listed in Kljaic’s counterclaim were untrue:
i. The work on the Roof Top terrace invoice did not happen and
the invoice is a fake and made up to increase MKM’s
-- 18 of 39 --
counterclaim. This is evidenced by Mr Ambrose’s failure to
cross-examine Kljaic and Herbert about the claim;
ii. The invoice from Josip & Frankso Brkic. This is evidenced by
Mr Brkic’s testimony that this was not the invoice he had given
to MKM for payment and that it was not his handwriting ‘GST
INCL’;
iii. The invoice from Yacht Access Pty Ltd. This is evidenced by
the fact that the hire finished on 2 May 2007 and the invoice
was not submitted until 27 June 2007. the applicant asserts
that the ‘description’ is not correct and that this invoice is for
another job;
iv. The invoice from Oldfield Access Pty Ltd. This is evidenced by
Brkic’s testimony that he was using scaffold to finish the
rendering and the fact that the applicant had paid for its own
scaffolding;
(x) The letter from Kljaic in Exhibit 9 ‘MMK 04’ claiming that damage
to the roof was caused by Actell is untrue. The applicant asserts
that Kljaic and Herbert made up the story about seeing fins or
screws go through the waterproof membrane. Hancock admitted
‘the waterproof membrane was damaged in places but it was not
possible to establish if the visible damage had occurred at the
time of the installation of the sliding door track or at the time of
removing the mortar bed to establish the cause of the leak
through to the living room below.’ Hills testified that it is the
builder’s responsibility to waterproof. Thus it was Kljaic’s
responsibility to waterproof and the applicant should not be liable
to pay for repairs to something that it did not damage;
(y) The assertion in MMK 04 that roof repairs were done over the
‘Xmas break closure time’ is untrue considering that the leak
occurred on or about 12 December 2007. Further, Kljaic lists the
scope of the works but fails to supply any proof of costings;
(z) Kljaic created his own problems by not allowing the applicants on
site to make repairs. The applicant asserts that, had Actell been
allowed on site, all the works would have been finished before the
bill was due on 30 June 2007;
(aa) Kljaic admitted in his testimony that, even by his standards, 85%
of the work was completed but he only paid the applicant for 30%
of the work. He did not obtain a BSA report by an independent
assessor, instead he relied on the report by Hancock which has
now been proved to be inaccurate. He did not follow the dispute
process as required by the contract.
Submissions of the Respondents
97. The first respondent denies that Michael Kljaic (the second respondent)
entered into the Agreement because the second respondent was not a party
-- 19 of 39 --
to the contract. The respondents submit that there is a significant and fatal
hurdle that the Tribunal does not have power under its authorising Act to
grant judgment in favour of the claimant which does not form part of the
building contract the subject of the proceedings. The respondents rely on
Eckersley v Medical Board of Queensland [1998] 2 QdR 453 and National
Parks and Wildlife Service v Stables Perisher Pty Ltd [1990] 20 NSWLR 573
to assert that, as a specialist tribunal, the Commercial and Consumer
Tribunal’s jurisdiction is limited by statute. The respondents submit that
although such an interpretation may result in ‘a multiplicity of proceedings’
that is merely part of the ‘price to be paid for the advantages of having such
Tribunals.’1
98. The first respondent submits that works did not commence on site on 15
February 2007, but in fact commenced in late February when the applicant
started delivery glass and some aluminium framing to the Gibraltar site.
99. The first respondent contends that the works were not completed by the
applicant.
100. The first respondent submits that the applicant’s defect list is incomplete and
is not a proper list of all the defects, rectification and reconstruction works
required.
101. The first respondent does not dispute the first four items on the variation
claim but disputes the following variations asserted by the applicant:
(a) Variation No. 5 is for ‘change windows and doors facing water to
no steel beam revert back to having steel beam’ at a cost of
$37,835.00 plus GST. The respondents assert that the variation
has never been the subject of any written variation or direction
from the first respondent and it was conceded by the witnesses
for the applicant in cross-examination that none of the contractual
requirements with respect to variations has been complied with;
(b) Variation No. 6 is for ‘change sliding doors to low profile sill re-
order and re-manufacture sliding doors’ in the amount of
$15,300.00 plus GST. The respondents assert that the variation
has never been the subject of any written variation or direction
from the first respondent and it was conceded by the witnesses
for the applicant in cross-examination that none of the contractual
requirements with respect to variations has been complied with.
102. The first respondent submits that the applicant has not discharged its onus of
proof with respect to proving that Variation No. 6 was directed by, and indeed
was a variation from the contract works for the first respondent.
103. The first respondent submits that, with respect to Variation No. 5, if the
applicant has proceeded to install the transom without obtaining direction or
clarification from the first respondent, then that is not a matter for which the
first respondent can be held accountable. Further, despite its obvious cost
and inconvenience, nowhere in writing is there a claim or request for a
1 Nix & Dunn v Pittwater Council (1994) 84 LGERA 199.
-- 20 of 39 --
variation to cover that cost, and certainly nowhere in writing is there a
direction from the first respondent. The respondents thus submit that there
has been an abject failure by the applicant to comply with the relevant
provisions of the Subcontract.
104. The first respondent submits that the claim for Variation No. 5 in fact is no
different from the purported variation with respect to Claim No. 6, and that is
that the applicant has made assumptions and done work in the absence of
having any direction from the first respondent for the works to be undertaken.
The respondents assert that when the direction or clarification was obtained
the applicant then sought to claim what in fact was the original cost under the
contract as a variation from the work which they had done without proper
authorisation.
105. The first respondent submits that the inclusion of the clause requiring written
variations is to avoid the situation where a builder effectively becomes an
insurer for a subcontractor’s erroneous carrying out of works other than in
accordance with the scope of works under the contract.
106. Using the variations to recalculate the total contract price, the respondent’s
submit that $111,526.80 is the total contract price being the original contract
price of $98,615.00 (GST inclusive) plus the agreed variations 1 to 4 with a
combined value of $12,911.80 (GST inclusive).
107. That amount is undisputed by the first respondent as being the total contract
price, had the works been fully installed and completed. The respondents
assert that there are two primary bases of disputing the claim by the
applicant. The first is that variations 5 and 6 with a combined total of
$58,448.50 (GST inclusive) were not variations under the contract for which it
is liable. Secondly, that the works done by the applicant on the property were
incomplete and, additionally, were defective.
108. The first respondent has counterclaimed as a set-off against the applicant’s
claim the cost of completing the contract works that should have been
completed by the applicant and rectifying defects.
109. Following the Tribunal hearing in September 2009, the first and second
respondents delivered joint submissions on 14 September 2009.
110. With regards to the evidence of Mr Perovic (“Perovic”), the respondents
assert:
(a) Perovic’s evidence was ‘a little hazy’ in some respects, though
whenever there was a point material to the applicant’s case, his
memory seemed to improve. Mr Perovic has a vested interest
from a professional perspective with respect to allegations that
the work was not carried out in a proper and workmanlike
manner, or was otherwise slow and disruptive to other trades;
(b) Perovic’s evidence concerning the conduct of the works should
not be accepted in the absence of corroborating evidence.
Perovic mostly responded to questioning about Hancock’s first
report with a denial that the defect as alleged existed, or at the
-- 21 of 39 --
existence of the item identified by Hancock was not a defect but
was uncompleted work. The respondent asserts that it was not
put to Hancock in cross-examination that the items identified by
him in his first report did not exist. Hancock provided photographic
evidence of many of the defects. The respondent asserts that
Perovic’s denials are inconsistent with the defects identified by Mr
MacGregor of the Queensland Building Licences Authority and as
predominantly agreed to in the joint expert reports of Sim,
Hancock and Hills. The respondent asserts that the assertion of
incomplete work is unfounded considering correspondence dated
31 May 2007, wherein the applicant stated, in effect, that the work
under the contract had been completed and requested a list of
defects;
(c) Perovic does not give any evidence in relation to the claim for
Variation No. 6 which appears as Exhibit 18 to the statement of
Snow and describes the works claimed as ‘changes sills of sliding
doors to low profile sills re-order and manufacture sliding doors
door fit’ for an amount of $16,830.00 including GST. The
respondent asserts that Perovic does not speak of either the work
undertaken or the alleged direction to make any such variation.
The respondent submits that there was no direction to vary, as
alleged by Snow, because an examination of the facsimile at
Exhibit 17, and in particular the second paragraph thereof, clearly
shows that there was no such direction for a variation to be made.
The respondent asserts that the facsimile recounts a sample of a
sill being shown, some dissatisfaction with the proposed sill being
voiced and an alternative product being shown and that when that
alternative product was found to be a domestic sill rather than a
commercial sill (the basis upon which the contract had been
entered into) the original sill was accepted and included in the
work. Further, the recipient of the facsimile, Mr Eldson, did not
provide evidence supporting the existence of any such variation.
The respondents note that Exhibit 17 was created some
significant time after the event having been apparently ‘over
looked’ and that Snow gave evidence that he went through the
records and spoke to Mr Eldson to enable him to create the
invoice but Mr Eldson denied that he had spoken to anyone about
the creation of an invoice subsequent to the contract work being
carried out; and
(d) Perovic’s statement in relation to the claim for Variation No. 5
which appears as Exhibit 16 to the statement of Mr Snow should
not be accepted. The respondents assert that there is a serious
conflict in the evidence about how the use or suggested use of
the transom came about, as well as the move to the steel beam.
The respondents assert that by reason of the lack of detail in the
plans there is no plan that the applicant has pointed to which
shows a steel beam being utilised in the relevant areas and that
the plans clearly show there is a break between the doors below
and the windows above and that something is to be in that area.
The respondents assert that the evidence that it was not a lack of
-- 22 of 39 --
strength in the suggested transom that resulted in it not being
used, but rather its shape which would have inhibited the use of
blinds on the inside of the windows, is inconsistent with Perovic’s
statement at paragraph 9. Furthermore, the respondents assert
that there is no good evidence why the first respondent would
have proceeded along such a course in the face of such obvious
expert advice about the lack of capacity of the transom. The
respondent notes that despite Perovic’s suggestion that both he
and Mr Eldson had expressed such a concern, that concern did
not appear from the evidence of Mr Eldson and is contrary to the
statement of Snow contained within paragraph 19, in which a
transom that would be satisfactory for such a use in terms of
compliance with weight and wind loadings had in fact been
identified by the applicant. The respondent submits that where
there was discussion about the use of the transom, it is unlikely
that such a discussion would have taken place in the absence of
any mention of the most recent use of the transom in a job
between the two parties to discuss whether, and if so, how, that
previous design could be used on the current project. The
respondent submits that the more likely scenario is that put
forward by Kljaic that the applicant suggested a transom could be
used, however, when he saw it, it was apparent that it would not
work with the internal workings of the blinds and so a steel beam
was used instead.
111. The first respondent submits that, with regards to quantum, the following
matters appear to be without contention on the evidence:
(a) The matters identified in Hancock’s first report as being defects
existing as at 2 July 2007; and
(b) The defects noted in the report of Mr MacGregor and the
subsequent expert’s conclave.
112. With respect to the leak appearing in the vicinity of the roof top terrace, the
respondents rely on the evidence of Hancock that for the ‘substantial
differential slab movement’ to be the sole cause one would expect to see a
crack or cracks approximately 3mm in width, of which there is no evidence
before the Tribunal of the existence of such cracks. Thus, the respondents
assert that the cause of the leak is nothing more than a supposition on the
part of the applicant.
113. The first respondent relies on the following quotes in support of its claim for
rectification costs:
(a) Commercial Windows Queensland Pty Ltd quote in the amount of
$49,802.50 inclusive of GST from Mr Glenn Van Hoven to
undertake repairs to ‘all windows where leaking occurs at
transoms, remove fixed glass panels, seal transome ends, drill
drain holes and wet seal glass to all rails. Replace trims so they
align with walls throughout project, remove frames and cut down
where floor finishes do not meet door sills and refit’. The
-- 23 of 39 --
respondents note that Mr Van Hoven gave evidence of work he
had actually undertaken and for which accounts had been sent;
(b) G.J. James Glass and Aluminium quote in the amount of
$57,106.50 including GST from Mr Gary Holmes to provide
glazing services to the Gibraltar Drive site. The respondents note
that the amount quoted is around (though slightly above) the
estimate provided by Mr Hancock to undertake works. The
respondents assert that the applicant’s failure to cross-examine
Mr Holmes on the basis that he had not complied with the formal
requirements under the Tribunal rules with respect to expert
evidence was unfounded because Mr Holmes was not held out to,
and does not purport to provide an expert report and, to the
extent that it may be relevant, he provided his relevant expertise
within the industry for the purposes of providing the quote. The
respondents assert that Mr Holmes provided the quote based on
an inspection undertaken of the premises as to what his company
would charge to do the work set out therein and that he had
extensive and exclusive experience in the provision of glazing
services to provide the quote. The respondents assert that
because the quote Mr Holmes provided was not wrong or
overstated or otherwise open to attack, the quote was effectively
uncontested;
(c) G.J. James Glass and Aluminium quote in the amount of
$15,928.00 including GST from Mr Gary Holmes to provide
glazing services to the Calabro Way site. The respondents assert
that there was clear evidence from Mr Van Hoven that where the
evidence of leaking was relied upon by him, he was of the view
that those leaks were related to the windows and/or frames and
not from another source and that this evidence was uncontested.
The respondents submit that Mr Van Hoven was an honest
witness who was responsive to questions and gave an honest
recollection and appraisal of the works and quotes; and
(d) All Metal Works quote in the amount of $36,062.40 including GST
to undertake work related to the roof top terrace doors and
windows and more particularly the removal of the doors, windows
and frames, the removal of the pollock (I note the use of this term
by Mr Herbert during his evidence with respect to material which,
as shown on the photographs, may be ‘alpolic’ cladding) as which
was required for that part of the roof top terrace where the pollock
adjoined the window and door framing, and the replacement of
the frames, windows, doors and pollock. The respondents note
that the evidence of Mr Herbert with respect to the pollock was
that once removed it could not be reused and entire new sections
had to be reordered and replaced. The respondents note that the
applicant, during cross-examination, alleged that the invoice
provided by All Metal Works was, in effect, a fraud and that the
works set out therein was not in fact carried out. The respondents
submit that there is no evidence before the Tribunal that would
allow such a conclusion to be drawn. The respondent notes that
-- 24 of 39 --
the assertion was put to Mr Herbert and denied. The respondents
assert that Mr Herbert’s evidence, whilst successfully challenged
in some respects, was in reality that of an honest witness as Mr
Herbert readily made concessions when confronted with
suggestions as to the source of his evidence and did not seek to
defend his position in an unreasonable manner. The respondent
submits that there is no basis on which the Tribunal would accept
that the whole of Mr Herbert’s evidence ought to be rejected.
114. The first respondent concedes that much of the evidence given by Mr Herbert
with regards to what was seen on site during the course of the frame removal
work was hearsay, he having admitted to not having seen it himself but to
have been told that information by his workmen on site. The respondents
assert, however, that even the evidence is limited to what Mr Herbert was
told, it is not inconsistent with that provided by Mr Kljaic during which, under
cross-examination, he gave evidence of being present when the sill was lifted
and seeing physical signs of screws having penetrated through the
waterproofing into the concrete to hold the stackers in place.
115. The respondents submit that the factual bases for the first respondent’s
counterclaim are made out because the existence of defects and the cost of
rectifications, even leaving aside the All Metal Works invoice, were not
seriously in contest.
Discussion
116. On the evidence available I am not satisfied that the applicants caused the
roof top leak. The evidence given concerning the work done purporting to
correct work done by the applicants on the roof top level was unsatisfactory
and at times I was left with the impression that much of the evidence given
on behalf of the respondents was an unreliable attempt at reconstruction. I
am not satisfied that the applicants are responsible for the leaking.
117. Some of the evidence given was given by witnesses who had no direct
knowledge of the matters they were giving evidence about. For example the
evidence of Mr Herbert was in that category. His statement is exhibit 21. He
gave evidence about the rectification of windows and doors and the
replacement of apolic cladding however he was not on the site. He did not
carry out the work. Despite saying he could produce invoices for the ‘pollock’
cladding (which may be ‘alpolic’ cladding) replacement claimed none were
produced. He was generally unable to comment on issues which had been
claimed by the respondents such as whether the sill tracks were back to front
or whether there had been puncture/s in the sills or tracks. He said he had
been told by Mr Kljaic that there had been various punctures and that one
section of a sill had been put on back to front and there were holes in the
membrane. He said he got some of his information from Mr Kljaic and some
from his staff. In my view he was an unreliable witness and I do not find his
evidence credible. I my view if the work claimed was done the amount
estimated by Mr Herbert was excessive. In my view his evidence concerning
any need to replace pollock or apolic cladding is not reliable or credible. I find
it incredible in the light of the evidence given by Mt Kljaic that “vertical fin” in
the statement of Mr Herbert was meant to be “vertical screw”.
-- 25 of 39 --
118. Given the nature of the defects claimed and the allegations concerning fins
on a sill or later screws and packers causing a membrane breach I would
have expected evidence of same. In my view none was forthcoming.
119. I accept the evidence of Mr Van Hoven that the sills were installed in the
correct manner. I also accept the evidence that the weep holes were an
indication of correct installation.
120. In respect of any need to remove the roof terrace doors and reinstall them I
prefer the costings of Mr Hill and I accept his evidence in that regard. I found
Mr Hills evidence to be given in a forthright manner. It was credible.
121. As to the claim for liquidated damages, I find there is no basis for it. There
was no construction schedule provided and there was no trigger for
liquidated damages. I do not accept the evidence of Mr Kljaic in this regard
nor the claim made. I accept the evidence of the applicant about delays and
variations and I find that much of the delay was because of changes made
and a lack of a window schedule. I found the assertion by Mr Kjlaic during his
evidence that he used liquidated damages claims as a wake up call
disingenuous. Further I accept the evidence of Mr Hills that that there was a
lack of specification and detail in the plans.
122. As to the claim made that Mr Kljaic is to be held liable for the liability of the
first respondent I find that the credit application document is not part of the
building contract entered into. The contract makes no reference to it. It may
be that the credit application and attachments do amount to an enforceable
guarantee but that is a matter for another place as this Tribunal only has
jurisdiction to deal with matters it is empowered to deal with under the
Commercial and Consumer Tribunal Act 2003 or an empowering Act. The
Tribunal is not empowered to deal with any question of a guarantee as the
circumstances exist here.
123. As to the respondent banning the applicant from the site I find that it had no
right to do so and when it did it was repudiating the contract. There was no
timetable incorporated into the contract. The complaints about the applicant
causing delays in my view are without a proper basis. Any delays were in my
view because of Mr Kljaic making changes or requesting work to be redone
to accommodate other trades. I note the evidence concerning the state of the
financial affairs of the respondent at the time and a lack of liquidity.
124. There is no doubt that the works were not completed by the applicant. I my
view the reason for that is that that the second respondent wrongfully
prevented them from completing the work. I accept that approximately 85%
of the work had been completed.
125. The respondent does not dispute the first four items of the variations claimed
but disputes variations 5 and 6. They are disputed on the basis that there
was no written variation. Clause 5 of the contract deals with variations and
requires them to be in writing. Part 7 of the Domestic Building Contracts Act
2000 also deals with variations and requires them to be in writing. Section 84
gives a right to a building contractor to recover an amount for a variation in
certain circumstances.
-- 26 of 39 --
126. Section 84(4) provides:
(4) The tribunal may approve the recovery of an amount by a building contractor
for a variation only if the tribunal is satisfied that-
(a) either of the following applies-
(i) there are exceptional circumstances to warrant the conferring of an
entitlement on the building contractor for recovery of an amount for the
variation;
(ii) the building contractor would suffer unreasonable hardship by the operation
of subsection (2)(a) or (3)(a); and
(b) it would not be unfair to the building owner for the building contractor to
recover an amount.
127. I accept the evidence of Mr Snow concerning the requests by Mr Kljaic for
changes. In my view the fact that the contractual requirements were regularly
not complied with, the variations were required by the owner who was also
the director of the first respondent, the work was done and was in excess of
$53,135 (when the initial value of the contract was $98,615) there is an
entitlement for recovery of a variation amount. I am also satisfied in those
circumstances that the applicant would suffer unreasonable hardship by the
operation of subsection (2)(a) or (3)(a) of section 84. I am also satisfied that
given the work was done and the materials supplied it would not be unfair to
the building owner for the applicant to recover an amount. If those works
were defective then that is a matter which impacts on the “amount” to be
recovered.
128. I accept the evidence of Mr Perovic. I found his evidence to be credible and
the manner in which he gave it genuine. He was prepared to accept
responsibility for mistakes which he admitted were his. His statement is
exhibit 4. His evidence in my view corroborated that of Mr Snow and Mr
Elsdon.
129. The statement of Mr Perovic is Exhibit 4. He gave evidence concerning the
installation of the glazing at Gilbraltar Drive. I have taken into account the
submissions of the respondents concerning his evidence (as I have earlier
set out) and based on my observation of him during his oral evidence and
during cross examination, I find him credible. It is feasible that work regarded
by others as defective could consistently be regarded by Mr Perovic as
unfinished. I accept his evidence and his account of conversations had with
Mr Kljaic. I find that Mr Kljaic was making constant changes as described by
Mr Perovic. As to the use of a steel beam or a transom (variation 5), I accept
that there is no steel beam shown on the plans but I accept that there was a
change in the use of a steel beam and then another change as outlined by
Mr Perovic, such change caused by Mr Kljaic.
130. There are defects identified by Mr Hancock in his first report as existing at 2
July 2007 that do not seem to be in dispute.
-- 27 of 39 --
131. There are also defects noted in the report of Mr MacGregor and the experts’
conclave joint report which are not disputed.
132. It is appropriate to deal with each of the items set out in the BSA report in
turn
133. Item 1 Front Door. All the experts agree. The installation of the “pivot-
hinged” front door has been finished by the owner. The cylinder lock into the
door handle stands proud of the external face and the cover plate at the
bottom pivot hinge is not fitted correctly and is not the correct type. They are
defects but not done by the applicant.
134. Item 2 “Stacker “ sliding Doors- formal lounge. All the experts agree. The
doors have been finished by the respondent using non genuine parts and as
a result the doors do not operate as easily as they should. They are defects
but not done by the applicant.
135. Item 3 “ Stacker “ sliding door frame not aligned to windows directly
above All experts agree that the plans show the upper and lower vertical
mullions/frames of the fenestrations to be in alignment and the configuration
of some openings have changed from the plans. All agree that the glass
panels in the sliding doors to the lower section are of equal width. and the
glass panels in the upper section are of equal width but different width to the
sliding door panels below due to different frame or mullion thicknesses
resulting in the misalignment of the frames/mullions. The BSA, Hancock and
Sim agree that in order to comply with the plans the width of the upper glass
panels should have been adjusted. Hill disagrees and says that if the above
was done the glass panels would be of unequal width and thus not comply
with the plans. He does not regard it as a defect. All agree that aesthetic
rectification is required.
136. Item 4 Tops of Stacker sliding door frames incomplete. All the experts
agree. A gap can be seen at the top of the end panel of the frames and a
finishing plate incorporating a purpose made stop has not been fitted.
137. Item 5 Office sliding door All the experts agree The respondent has
attempted to make doors operational but the applicant is responsible for the
fitment of the missing door handle, interlocks blocks, proper door stops and
cleaning the frames of excessive sealant at the frame/wall junction. That is
incomplete work by the applicant.
138. Item 6 Dining room Sliding Door The respondent carried out work to the
door. The head margins between the cover plates and the door frame are not
parallel. All agree that the opening is not square which is the respondent’s
obligation but the applicant had an obligation to bring that to the respondent’s
attention so that it could be rectified. All agree that a single piece purpose
made aluminium cover plate would be acceptable
139. Item 7 Laundry sliding door frame All the experts agree The cover plate to
the right-hand end stile of the door exhibits a large gap at its head. That and
the need to clean excessive sealant at the wall junctions is incomplete work.
-- 28 of 39 --
140. Item 8 Rear Hopper Window All the experts agree that the sill is not level
and should be rectified.
141. Item 9 Fixed window at Rear Elevation All the experts agree. There is slight
calcium staining at the coupling bar along the sill section from water being
trapped in the extrusion and weeping out via the joint. The applicant should
rectify and reinstate the damage to the face of the aluminium.
142. Item 10 Window/wall Breakfast room All the experts agree. The large
window /wall section fitted between two external walls show varying margins
on the side moulds against the rendered walls. This is not defective or
incomplete for the purpose of the inspection.
143. Item 11 Window and Door Stiles do not line up. The experts had the same
views as set out with respect to item 3.
144. Item 12 Family Room Stacker sliding doors. The experts had the same
views as set out with respect to item 3.
145. Item 13 Cantilevered Bedroom windows The experts agreed that if the
window leaks it should be repaired however whilst the window leaked into
the timber floor during the construction phase it has been rectified and no
apparent defect is noted.
146. Item 14 Gym Sliding Door All the experts agree. The “D” type door handle
hits the frame when the door is closed which prevents the door fully
engaging into the jamb. The correct door stops have not been installed.
That is incomplete work.
147. Item 15 Automatic Opening Garage Sliding Door The experts agree that
glazing panels to the head of the frame have not been fully complete in the
beading area.
148. Item 16 Master Bedroom Window and Doors The experts agree that the
lever handles to the hopper sash windows are black coated units which are
inconsistent with the clear anodised units in the rest of the hose. The
“interlock” blocks and the correct door stoppers have not been installed.
Once the incorrect door stops have been removed, the face will need repair
due to the screw fixing holes.
149. Item 17 Daughters Bedroom Windows The experts agree that the lever
handles to the hopper sash windows are black coated units which are
inconsistent with the clear anodised units in the rest of the house.
150. Item 18 Nursery Stacker Sliding Doors The experts agree that the
external door handles are incorrectly fitted causing the door to be difficult to
operate from the outside. The fitted door stops are not the integrated door
stops designed to match the joinery.
151. Item 19 Roof Top Terrace The experts agree that the joins in the sill and
head sections of “stacker” sliding door frame are out of alignment and not
flush. This may or may not involve the total removal and replacement of the
door frame. Localised work on the frame is the preferred option. The finish
-- 29 of 39 --
at the top of the vertical stiffening mullions on these “stacker” sliding doors
is uneven and cut on differing angles.
152. Mr Jeffrey Hills (“Hills”) is an expert engineer who gave evidence for and on
behalf of the applicant. Exhibit 1 contains his report with respect to the
following matters:
(a) Whether or not the works carried out by Actell complied with the
relevant contracts and applicable government and industry
standards. Hills found that:
i. The BSA’s comments and conclusions were consistent with
his site observations, save for items 1, 3 and 5, being works
considered to be defective;
ii. He disagrees that the need to rectify in Items 3, 6, 8, 11 and
12(c) lay with the subcontractor;
iii. These works were not completed nor repaired due to the
inability of the contractor to access the site; and
iv. If the contractor had access to the site the defects and
incomplete works would normally be rectified as part of the
final site works by the subcontractor.
(b) Whether or not the defects alleged by MKM were in fact defects
when assessed against the requirements of the relevant contracts
and government and industry standards. Hills found that:
i. The standard on which any claim of defective and incomplete
work is to be measured against is the assessment as
completed by the Queensland Building Services Authority.
This BSA report is a complete and exhaustive summary; and
ii. Apart from items 1, 3 and 5, the remaining items are
confirmed as being defective and/or incomplete works.
(c) Whether or not the amounts claimed by MKM for rectification
works were reasonable and, if not, what would be appropriate
amounts to be allowed in favour of MKM for those works. Hills
found that:
i. The cost to rectify the items contained in the BSA report
would be $6,000 plus GST;
ii. The cost to rectify the items contained in the BSA report, save
the items objected to, would be $2,800 plus GST; and
iii. As noted in the BSA report, works have been undertaken by
the owner. The incorrect works would need to be rectified as
part of the BSA list.
-- 30 of 39 --
(d) Whether or not the findings contained within Mr Hancock’s report
dated 2 July 2007 were, in his view, accurate. Hills found as
follows:
i. Labelling and Certificates: Compliance with the standard is
required which involves a sticker on the frame and a Form 16
confirming compliance with the standard;
ii. Shop Drawings: Standard practice is that all specifications
and requirements are produced by the architect in a window
schedule layout. Details for matching are contained in a
separate specification document or specifically included on
the architects plans. Detail is grossly lacking in the window
and door specification in the original contract which created
uncertainty as to the detail required. The subcontractor has
completed the works in accordance with normal building
standards and industry practice. If the contractor had been
allowed access to the site the incomplete and defective works
would have been completed;
iii. Defects List: The defects list has been incorporated into the
inspection by the BSA. The BSA report is the reference
document for this matter and no further comment is required.
Refer to Inspection Summary of the BSA and comments as to
agreement or disagreement with that summary; and
iv. Costing of Rectification: To rectify and replace the necessary
works to comply with the requirements of the BSA summary
(excluding the objections) would cost $6,000 plus GST.
(e) Whether or not the findings contained within Mr Hancock’s
additional report dated 12 December 2007 were, in his view,
accurate. Hills found as follows:
i. This report deals with the water penetration from the roof top
to the internal family room;
ii. The roof area consists of an external balcony that is reached
from an internal room that is stepped up from the external
balcony slab. Glazing incorporating sliding doors have been
installed to enclose the room;
iii. Water penetration occurred in or around December 2007;
iv. Hancock attributes the water penetration to the glazing
installation;
v. A step down in the slab is provided to prevent water entering
the internal room of the dwelling;
vi. The balcony floor, the upstand and the area just inside the
room should have been waterproofed;
-- 31 of 39 --
vii. Water leaks occurred in November / December 2007. Glazers
were ordered from the site in June 2007
viii. The tiled area and grout underneath the sliding doors will be
subjected to flooding and saturation being externally placed.
The underlying water proof barrier is provided to prevent
water penetration. It is therefore irrelevant that the track is not
perfectly level and drains back into the grout area;
ix. Hancock comments that contractors must either accept or
reject the work of the previous trade before working over it
and therefore the glazers accepted there were no defects
before commencing their work. Following this reasoning, the
tiler who commenced work after the glazers accepted their
work as being defect free;
x. The water proofing failed. The exact cause of this failure is
unknown. It is not uncommon for the slab to shrink
differentially causing stresses, which if not adequately
provided for in the water proofing, will result in failure of the
water proofing after building completion. This is very common
in high rises; and
xi. There is no evidence to conclude unequivocally that the
glazers damaged any part of the water proofing on the deck. It
is highly unlikely that the glazers were responsible given the
time delay between completion of the building and water
penetration. There are numerous more realistic scenarios
which may have led to the failure of the membrane.
(f) The claims of Water Penetration to Other Buildings. Hills found as
follows:
i. Inspections were conducted at 30 Township Drive, Burleigh
Heads and also Corner Calabro Way and Ern Harley Drive,
West Burleigh;
ii. Mr Klajiac indicated that it was not necessary to conduct an
inspection at 48 and 49 Lemana Lane, North Burleigh;
iii. The complexes visited were commercial factories constructed
of tilt up concrete walls on concrete slabs with sheet metal
roofs. Glazing has been installed into openings within the
walls;
iv. No specific windows were identified as suffering from water
penetration save for one at 30 Township Drive, Burleigh
Heads. One window here was identified as leaking. This
window faces south and it is probable that during extreme
weather events water penetration occurs between a small gap
in the rubber seals;
-- 32 of 39 --
v. During the inspection it was raining and there was no physical
evidence of water penetration observed in either of the
complexes;
vi. A number of tenants at Ern Haryley Drive did confirm that
during extreme weather events minor water leaks occurred;
vii. The window frames were assessed and it was found that
minor shrinkage of the rubbers may have occurred at the top
of the frame causing the mitre to open. This is typical of
rubber deterioration in an exposed environment. Windows
facing south are exposed to driving weather and windows
facing east or west are exposed to sun damage. The upper
corners of the windows are the area where water penetration
can occur when the rubbers shrink with this window design.
Remedial work involves sealing the mitre with silicon;
viii. The glazing contractor is liable for leaks occurring within 6
years of construction. After this the sealing would be
undertaken as maintenance;
ix. It is recommended that any leaking windows are accurately
identified so that remedial works through sealing of the
rubbers could be completed; and
x. The cost to complete the sealing of affected windows would
be minimal with a one off window costing as little as $50. The
estimate of rectification cannot be provided until the extent of
the leaks has been identified.
153. I accept the majority of the Hills report with the exception of the need to
adhere to the plans, which I comment on later.
154. Robert A Hancock is an expert architect who gave evidence for the
respondents. Exhibit 16 is his advice with respect to the glazing installation
at 95 Gibraltar Drive and his report on the finish and standard of
workmanship involved in the fabrication and installation of the aluminium
frame doors and windows. He also gave an opinion as to whether the
supply and installation of the aluminium commercial windows and doors
had been completed. He reported that generally all aluminium doors and
windows are in place in the building and that there are several
inconsistencies about installation in particular the junction between the jam
and head frame. He prepared a separate schedule which is attached to the
report headed door and windows defect schedule.
155. He also noted that none of the doors and windows had been labelled in
accordance with the Australian standard AS2047. That standard required
the window assemblies for housing to be labelled in a certificate in
accordance with clause 8.3 provided so that the window labels could then
be checked against the requirement of the standard to see if they conform
to the quotations of the 3 rd October 2006 and 23rd October 2006. He
commented that it was normal practice for the subcontract aluminium
fabricator to submit the shop drawings to the building contractor showing
-- 33 of 39 --
various information and said that had the shop drawings been supplied
most of the problems between the glazier and the building contractor could
have been eliminated. He concluded that whilst work and defects remain
outstanding the glazing subcontract could not be considered as having
reached practical completion and that in this case some of the glazing work
that had been installed would have to be replaced or at least partially
replaced. He gave an opinion of probable cost to carry out rectification work
based on a casual specialist tradesman at a rate of $60 per man hour for
some tasks and / or a rate per square metre of glazing to be replaced
similar to the original rate per square metre for the cost to install the glazing
as between $45,000 to $50,000.
156. Exhibit 17 is Mr Hancock’s report with respect to the glazing installation on
the rooftop terrace at 95 Gibraltar Drive and a report on the possible cause
of the leak coming from the ceiling in the family room directly below the
rooftop terrace.
157. His inspection of the upper level roof terrace and rumpus room and in
particular the sliding door on the eastern side of the rumpus room was done
when two workers had removed the section of the floor tiling approximately
one tile wide to three quarters of the length of the sliding door
approximately above the area where water was appearing in the ceiling of
the family room below. He said the sliding door track had been placed into
the upper edge of the structural concrete slab in approximately 50mm
above the step down level of the structural concrete floor to the external
balcony. That part of the track not supported by solid concrete beneath it
was roughly supported by pieces of broken tiles and an extension of the
mortar bed that served as bedding for the ceramic tiles to the exterior of the
deck. He said that the cross section of the silt track sloped back into the
interior. The track had been fitted in such a manner that the external upper
edge of the track was higher than the internal upper edge. He said that
water was inclined to flow away from the drain hole in the external side of
the track and back into the water bed underneath the track. The water proof
membrane of unknown manufacture had been applied to the structural
concrete slab and was visible in places where the water bed had been
removed. He said that the water proof membrane was damaged in places
but it was not possible to establish if the visible damage had occurred at the
time of the installation of the sliding door track or at the time of the removing
the water bed to establish the cause of the leak through the living room
below. He also identified a saw cut in the bottom side of the track that
allowed water caught in the track to flow freely into the water bedding
beneath the track. With water flowing back away from the balcony area
there was a tendency for water to pond beneath the track and finally make
its way through a damaged section of the waterproof membrane and
eventually through the concrete slab to the room below. He said that the
damage to the waterproof membrane can only be the responsibility of the
glazier because prior to a trade moving on to an area on site to work over
another trade that is here where the water proofers have to finish their
section of the project prior to the glaziers moving in and working over the
waterproofing then the second trade must either accept or reject the work of
the previous trade before working over it and covering it over.
-- 34 of 39 --
158. He summarised his findings as:
1) “The glaziers installed the frame sloping back into the room causing
water to flow in that direction rather than through the drain hole on the
side of the track to the exterior tile surface;
2) The track had a saw cut in the base that allowed water to flow freely
into the mortar bed; and
3) By the fact that the glazier had installed the sliding doors to the
rumpus area then it is accepted and understood that the work of the
water proofer was up to standard and accepted by the glazier but was
then damaged by the glazier during their installation of the sliding
glass doors.”
159. I note that no breach of the membrane attributable to the applicant is
identified and I note the alternative causes of leaking available.
160. Mr Bevan Sim an architect provided a report which is exhibit 12 concerning
the construction at 95 Gibraltar Drive. He addressed some of the items in
the BSA report and admitted others on the basis that there was an
agreement between the BSA and Mr Hills concerning some items. As to
item 3 the stack of sliding door frame not aligned to the windows directly
above he agreed with the BSA report that the non-alignment is defective
work but he also agreed with the Hills report that should the door mullions
be made to align with the window mullions above there would be non-
alignment of the mullions of the sliding sashes with the fixed members
when in the open position. In his opinion, the solution is to change the
spacing of the fixed windows to the high light above to align with the
mullions of the sliding door. In addition the horizontal transoms in the fixed
sashes of the courtyard corridor highlight windows do not align. He said that
there were signs of water ingress which would be rectified by default during
the re-spacing of the fixed window mullions.
161. As to item number 6 the dining room sliding door he agreed with the BSA
report that the item represents defective work but he also agreed with the
Hills report that the trueness of the opening was not the responsibility of the
window installer.
162. He made the same comments with respect to items number 11 and 12 as
he did with respect to item number 3.
163. As to item number 13, cantilevered bedroom windows, he observed
evidence of minor leaking to the retreat windows which he said should be
rectified.
164. In his conclusion he said that the items in 2.1 to 2.20 (of his report) that the
BSA report identifies as requiring rectification (with the exception of item
2.6) should be rectified by the window installer. With regard to item 2.6
more information was required prior to assigning responsibility. With regard
to items 2.3, 2.12 and 2.13 in his opinion the fixed window mullions should
be made to align with the door styles rather than the sliding doors made to
align with the window mullions. With respect to the cost of rectification he
-- 35 of 39 --
recommended that the scope of works for such rectification be forwarded to
a licensed contractor to prepare a quotation.
165. Mr Sim also gave a report (exhibit 13) with respect to works at lots 13-15
Calabro Way West Burleigh. His inspection of the site did not involve water
testing and was limited to the observation of the staining of the transoms,
efflorescence on adjoining concrete floor and water damage to adjacent
materials due to previous rain. He said the windows have been constructed
using the extrusions equal to or very similar to those which were illustrated
in his attachment b which was a popular extrusion where a curtain wall
exterior appearance is required thus minimising the amount of framing
viewed from the exterior. Because of the design there are smaller drainage
galleries should any water penetrate the frames via the glazing beads and /
or joins in the frames.
166. He said due to this high exposure of the frames, the junctions of the heads,
transoms and sills to the jams must be sealed with a durable gasket and
stroke or sealant to ensure water tightness. There is evidence that the
sealant used is of poor quality and is showing early (less than 2 years)
signs of drying out and shrinking. He said that for the joints to be water tight
prior to assembly all faces need to be squared and deburred to present a
surface equal to that of the extruded surface. Some of the joints inspected,
particularly the transom / jamb junctions feel like they are raw cut edge.
167. He commented that there was very minimal step down from the internal
floor slab to the car park level however any water entering the frames by
way of the locations he identified may be less likely to back up and enter
the building at ground level if there were weep holes in the sub sill and a
greater height differential between the floor and car park surfaces.
168. He was unable to accurately pinpoint the causes of the water ingress but
thought that it was from the windows.
169. It was his opinion that the joints of the transoms and the jambs need to be
made more watertight and to achieve that would require the disassembly of
the windows which may also result in the need to replace some members
as any facing up of existing members might effectively shorten the member
and thus increase the gap that needs to be sealed. He says that by default
that operation would involve the replacement of the glazing beads so that
any problems existing with the beads would be automatically addressed. He
said that with the regard to the sills / sub sills there should be available a
stop end similar but larger to allow the water to be contained within the sub
sill and then discharge via loopholes.
170. I have accepted the evidence of Hills in this regard and I do not accept that
there is the need for the rectification as set out by Mr Sim and quoted for in
the CWQ quote.
171. The scope of works which he mentioned are set out in the CWQ quote.
172. That quote which was initially exhibit B for identification was for $15,928.
And it was for the “Calabro Way Factories”.
-- 36 of 39 --
173. Exhibit 15 is a quote from G James Glass and Aluminium and was in
respect of the frameless door at 95 Gibraltar Drive. The author of the report
was of the opinion that the existing front door is a 10 mm toughened glass
frameless door which does not comply with Australian standards in that the
glass required for the doors to be 15 mm thickened glass. The cost to
rectify the front entry door would be $5,025 excluding GST. I note that the
joint experts do not hold the applicant responsible for this defect.
174. Where the stacking doors did not align with the fixed glass windows above
the rectification for that was estimated by G James Glass and Aluminium to
be $18,840 excluding GST for the court yard frames and $14,200 excluding
GST for the canal front frames.
175. For the stacking sliding door system G James Glass was of the belief that
they were installed back to front because at the moment they slide internally
and there are exposed weepholes and air pressure holes. They are of the
view that if those systems were reversed then the doors slide externally and
the door threshold cover the weepholes and air pressure holes. To rectify
that system to all three levels the cost would be $6,600 excluding GST. To
rectify two of the mitred fixed glass frames to level two requiring wet sealing
to stop wall penetration would be $2,400 excluding GST and to tie up the
other small issues such as sliding stops, interlocks, thresholds, addressing
the awning window and assorted glazing beads to the garage area would
be $4,850 excluding GST. For this matter I have accepted the evidence of
the joint experts and the Hills report.
176. Evidence was given by Dagor Erceg (exhibit 16) to the effect that he carried
out work on the site at 95 Gibraltar Drive as a plumber and although there
seem to be difficulties with the applicant coming to the site that difficulty did
not hold up his work.
177. Leslie John Simmons (exhibit 19) was a licensed electrical contractor who
did work at the Gibraltar Drive site. The effect of his evidence was that
Actell frustrated him in the way they were carrying out their work and that
the installation of the windows on the site dragged out much longer than it
should have. I do not accept that Mr Simmons has the expertise to give that
evidence and I do not intend to act on it.
178. Josip Brkic was a solid plasterer who worked on the Gibraltar Drive site.
The effect of his evidence was that he couldn’t remember window fitters
being on the site when he came to the site on 19 th March 2007. He says
problems with the windows slowed down his work on the site and he
couldn’t do external rendering on some walls because the windows hadn’t
been installed. He said that when the job was finished he was asked by the
second respondent to re-render some areas because the window frames
had been taken out and put back in and damaged some of the render.
When that was required to be done the render had to be applied to the
whole wall. The extra work that was involved he said amounted to $11,600.
179. Allan John Herbert the owner and operator of All Metal Works Pty Ltd gave
evidence that on several occasions he saw window fitters from Actell
bashing aluminium frames with hammers trying to make them fit in the
spaces. He did not approve of that practice and was critical of the need for
-- 37 of 39 --
such a practice. He however did not see any distortion caused by the
practice. He gave evidence that there was poor workmanship and lack of
performance by the window fitters on site. And that because of the delays
that occurred in window fitting he was delayed in completion of the metal
work. He estimates that the construction of the house probably took another
2 months because of the delays he says were caused by the installation of
the windows. He also gave a tax invoice for the removal of glass and
window and door frames to the top level of the house and re-installation in
sum of $36,062.40.
180. Commercial Windows Queensland Pty Ltd through their estimator Glenn
Van Hoven gave a quote for $49,802.50 to “repair all windows where
leaking occurs at transoms. Renew glass panels, seal transom ends, drill
drain holes and wet seal glass to all rails. Replace trims so they align with
walls throughout the project, renew frames and cut down where floor
finishes do not need seals and refit – scaffolding is required for all this work
to be supplied by MKM – working platforms required at each working level.”
181. For the work at the Calabro Way factories the quote was for $15,928.
182. I accept that the contractual documents are as described by Mr Snow. In
my view the contract does have various elements of uncertainty. I accept
the evidence of Mr Snow. Most of his statement was supported by exhibits
and I found his account of conversations credible.
183. I do not accept the evidence of Mr Kljaic where it conflicts with the evidence
given on behalf of the applicant. I found his evidence to be unconvincing
and I found that where the evidence conflicts I could not rely upon it. The
evidence of Mr Herbert confirmed my view of my reluctance to accept the
evidence of Mr Kljaic. I am of the view that the evidence of Mr Herbert was
contrived and not supported in any way by evidence of work done or any
apparent problems when it could have been so supported by those who did
the work, if real work occurred.
184. In the main I find the submissions made on behalf of the applicant
compelling and convincing and in accord with the evidence I heard, read
and observed.
185. I accept the costing of Mr Hills that to rectify the items in the BSA report an
amount of $6,000.00 plus GST. Whilst I have otherwise accepted the report
of Mr Hills, I accept that with respect to item 3 there has been a departure
from the plans and I accept that in order to comply with the plans the width
of the upper glass panels should have been adjusted. In that regard the
costings by G. James Glass should be accepted.
186. Where I have not accepted the Hills report is the alignment of the fixed
glass windows. He does not seem to have included such in his estimate for
rectification. In that regard, I accept the evidence of G. James Glass so that
the rectification costs are $18,840.00 excluding GST and $14,200.00
excluding GST, namely $20,724.00 and $15,620.00 (Total $36,344.00).
187. As to the need for rectification work to be carried out at Calabro Way, I do
not accept that the rectification work is as extensive as quoted on by
-- 38 of 39 --
Commercial Windows Queensland. I accept the evidence of Mr Hills and
that the minor leaks found could be rectified by the sealing of the metre with
silicon and that the cost to complete the sealing of affected windows would
be minimal, say for example, one off windows as little as $50.00.
188. In my view, the claim made by the applicant for total contract plus variations
of $169,975.30 should be allowed minus the amount of $32,166.86 paid
less an amount of $6,000.00 for rectification/completion of glazing work at
Gibraltar Drive and less $50.00 for rectification of leaks at Calabro Way and
less $36,344.00 for the alignment rectification.
189. The second respondent shall pay to the applicant the sum of $95,414.44.
190. Under clause 4(e) of the subcontract, the subcontractor is entitled to
interest on the unpaid balance of any overdue progress payment including
any part of a progress claim wrongfully withheld by the builder either at the
rate set out in clause 5 of the schedule (which has an amount inserted) or
at the rate of 10% a year plus the rate comprising the annual rate as
published by the Reserve Bank of Australia for 90 day bills for each day the
amount is unpaid whichever is the higher. The applicant informed me that
90 day bill rate applicable was 3.6%. The applicant claims 13.6% interest
since 31 May 2007. A claim was made for a payment of the contract and
variations 1 – 4 on 30 May 2007.
191. I allow interest on the unpaid portion of the progress claims of $66,448.14
($98,615.00 contract sum minus $32,166.86 payments made) from 31 May
2007 at the rate of 13.6%, namely interest in the amount of $25,278.64.
192. The Tribunal orders the second respondent to pay $120,693.08
($95,414.44 plus $25,278.64) to the applicant by 4pm on 2 April 2010.
-- 39 of 39 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2010/062