Barlow v Body Corporate for Hi Surf [2010] QCAT 55
1
CITATION: Barlow v Body Corporate for Hi Surf [2010]
QCAT 55
PARTIES: GEOFFERY ARTHUR BARLOW
v
BODY CORPROATE FOR HI SURF CTS
11533
APPLICATION NUMBER: KL054-09
MATTER TYPE: Other civil disputes matters
HEARING DATE: 23 February 2010
HEARD AT: Brisbane
DECISION OF: Mr J Allen
DELIVERED ON: 23 February 2010
DELIVERED AT: Brisbane
ORDERS MADE: The contribution schedule for the community
titles scheme known as “Hi Surf CTS 11533”
be adjusted such that the contribution
schedule lot entitlement for each and every
lot be the number allocated to the lot in the
following table.
Lot Number in
BUP3632
Contribution schedule lot
entitlement
1 98
2 95
3 85
4 91
5 101
6 95
7 85
8 95
9 102
10 95
-- 1 of 15 --
2
11 85
12 95
13 102
14 95
15 85
16 95
17 102
18 95
19 85
20 95
21 102
22 95
23 85
24 95
25 102
26 95
27 85
28 95
29 102
30 95
31 85
32 95
33 102
34 95
35 85
36 95
37 102
38 95
39 85
40 95
41 102
42 95
43 85
44 95
45 102
46 95
47 85
48 95
49 102
50 95
51 85
52 95
53 102
54 95
55 85
56 95
57 102
58 95
59 85
60 95
61 102
62 95
63 85
64 95
65 102
-- 2 of 15 --
3
66 95
67 85
68 95
69 102
70 95
71 85
72 95
73 102
74 95
75 85
76 95
77 102
78 95
79 85
80 95
81 102
82 95
83 85
84 95
85 102
86 95
87 85
88 95
89 102
90 95
91 85
92 95
93 102
94 95
95 85
96 95
97 102
98 95
99 85
100 95
101 102
102 95
103 85
104 95
105 103
106 100
CATCHWORDS: Application to adjust contribution schedule;
Body Corporate and Community
Management Act 1997 sections 46 to 49
APPEARANCES and REPRESENTATION (if any):
This matter was heard on the papers by agreement of the parties in accordance
with section 32 of the Queensland Civil and Administrative Tribunal Act 2009
-- 3 of 15 --
4
REASONS FOR DECISION
1. The applicant, Mr Geoffrey Arthur Barlow is one of the owners of Lot 106
on BUP 3632, being one of the lots contained in the Community Titles
Scheme called Hi Surf Community Titles Scheme 11533 (“Hi Surf”). The
application is for a Contribution Schedule adjustment pursuant to section
48 of the Body Corporate and Community Management Act 1997 (“the
BCCM Act”) which was filed with the former Commercial and Consumer
Tribunal on 28 August 2009.
2. The respondent to this application is the Body Corporate for Hi Surf as
required by section 48(2) of the BCCM Act.
3. The respondent filed a defence to the application dated 18 September
2009.
4. Pursuant to section 256 of the Queensland Civil and Administrative
Tribunal Act 2009 (“QCAT Act”) the Queensland Civil and Administrative
Tribunal (“Tribunal ”) has jurisdiction to deal with this matter as it was
commenced in a former tribunal, the Commercial and Consumer Tribunal
and was a pending proceeding before that tribunal, at the commencement
of the Tribunal. In accordance with section 271 of the QCAT Act, the
Tribunal has the functions of and can only make a decision in relation to
the matter which the Commercial and Consumer Tribunal could have
made.
EVIDENCE
5. The applicant provided a report dated 25 August 2009 by Ms Kaylene
Arkcoll of Leary & Partners Pty Ltd described as Contribution Lot
Entitlement Analysis for Hi Surf CTS 11533 (“L & P Report”).
6. The respondent advised the Commercial and Consumer Tribunal by letter
dated 20 November 2009 that it did not intend to engage an independent
expert to prepare a report (or otherwise give evidence) in respect of the
current contribution schedule.
7. The Tribunal received a submission by e-mail dated 29 October 2009 from
Ms Juanita Walls.
THE LAW
8. The contribution schedule lot entitlement for a lot is in accordance with
section 47(2) of the BCCM Act the basis for calculating the lot owner’s
share of amounts levied by the body corporate, unless …otherwise
provided in the Act and the value of the lot owner’s vote on an ordinary
resolution if a poll is conducted. There is a separate interest schedule lot
entitlement which in accordance with section 47(3) of the BCCM Act is the
basis for calculating the lot owners share of the common property, the lot
owners interest on termination of the scheme including the lot owner’s
-- 4 of 15 --
5
share in body corporate assets and the unimproved value of the lot for
rating and tax purposes.
9. By section 46 (7) of the BCCM Act the respective contribution lot
entitlements must be equal, except to the extent to which it is just and
equitable in the circumstances for them not to be equal. This section on its
face applies to schemes for which development approval is given after the
commencement of the section which was on 4 March 2003.
10. The owner of a lot in a community title scheme may apply for an order for
adjustment of a lot entitlement schedule under section 48(1) of the BCCM
Act. The order of the Tribunal in regard to the contribution schedule must
in accordance with section 48(5) of the BCCM Act be consistent with the
principle that the respective lot entitlements should be equal, except to the
extent to which it is just and equitable in the circumstances for them not to
be equal.
11. Section 49 of the BCCM Act sets out the matters which the Tribunal may
and may not have regard to for deciding if it is just and equitable in the
circumstances for the respective lot entitlements not to be equal. By
section 49(4) of the BCCM Act the Tribunal may have regard to
a. How the community titles scheme is structured; and
b. The nature, features and characteristics of the lots included in the
scheme; and
c. The purpose for which the lots are used.
12. This is not an exhaustive list as in accordance with section 49(3) of the
BCCM Act the matters the Tribunal may have regard to for deciding a
matter are not limited to the matters stated in this section.
13. The matters which the Tribunal may not have regard to are set out in
section 49 (5) of the BCCM Act and are any knowledge or understanding
the applicant had, or any lack of knowledge or misunderstanding on the
part of the applicant, at the time they entered into a contract to buy the lot
about the lot entitlement for the lot owned by the applicant or other lots
included in the community titles scheme; or the purpose for which a lot
entitlement is used.
14. The leading decision in respect of applications under section 48 of the
BCCM Act is that of Chesterman J with whom the two other Court of
Appeal judges agreed in Fischer & Ors v Body Corporate for Centrepoint
Community Title Scheme 7779 [2004] QCA 214. In his judgment
Chesterman J distilled the following principles:
a. At para [26], a contribution schedule should provide for equal
contributions by apartment owners, except insofar as some
apartments can be shown to give rise to particular costs to the body
corporate which other apartments do not.
-- 5 of 15 --
6
b. At para [26], That question, whether a schedule should be adjusted,
is to be answered with regard to the demand on the services and
amenities provided by the body corporate to the respective
apartments, or their contribution to the costs incurred by the body
corporate. More general considerations of amenity, value or history
are to be disregarded. What is at issue is the ‘equitable’ distribution
of the costs.
15. Chesterman J stated that there were a number of reasons for that
conclusion. The first being the Explanatory Notes which accompanied the
Act which inserted section 46(7) of the BCCM Act and the content of the
Second Reading speech when the bill for it was debated. He had already
noted at para [10] that it was the act as amended which contained the
relevant law. This is important as under the Act before amendment it was
not a requirement under section 46(1) of the BCCM Act that that
contribution schedule lot entitlements be equal.
16. At para [28] Chesterman J quoted from the explanatory note as follows:
The change is intended to reinforce the concept that usually all lot owners
are equally responsible for the cost of upkeep of common property.
However, it is recognised that there are many valid instances where the
contribution schedules do not have to be equal. The amendment provides
that usually the numbers in this schedule are equal, unless it can be
demonstrated that it is just and equitable for there to be inequality.
The need for differences is best shown by examples.
….
Example 3 - in a basic scheme, if all the lots are residential lots ranging in
size from a small lot to a penthouse, the contribution schedule lot
entitlement would generally be equal. However, the contribution schedule
may be different if the penthouse has its own swimming pool and private
lift. The contribution schedule should recognise this type of difference. The
other lots in the scheme despite being of differing size or aspect would be
expected to have equal contribution schedule lot entitlements.
17. At para [29] Chesterman J quoted from the second reading speech as
follows
The issue of the nature of the contributions schedule for a body corporate
scheme has created some discussion. The guiding principle for both
setting and adjusting the contribution schedule is that it involves the
equitable sharing of the costs of operating and maintaining the common
property. These costs should be borne in proportion to the benefit, not in
proportion to the unit’s value. It is not a contribution linked to an ability to
pay, but as a payment for services… There is not an argument..against
the fact that, in terms of costs related to a property’s value – costs such as
rates and insurance – owners whose properties are worth more should
pay more. But when we are talking about those parts of a property where
the benefits are shared more or less equally, we cannot apply the same
formula.
-- 6 of 15 --
7
18. In referring to the effect of the insertion of section 46(7) of the BCCM Act
in 2003 having regard to the Explanatory Notes and Second reading
speech in respect of the amendments Chesterman J said at para [30],
These materials make it tolerably plain that the Act is intended to produce
a contribution lot entitlement schedule which divides body corporate
expenses equally except to the extent that the apartments
disproportionately give rise to those expenses, or disproportionately
consume services. That determination can only be made by reference to
factors which have a financial impact or consequence on the body
corporate. It cannot be affected by factors which go to an apartment’s
value or amenity.
19. Secondly, in support of his conclusion in para [26] Chesterman j stated at
para [31] that, the nature of a contribution lot entitlement schedule itself
suggests that the allocation of lot entitlements is to be made on the basis
of the impact that individual apartments make upon the costs of operating
and running a community titles scheme. Contribution lot entitlements
determine the apartment’s share of the outgoings. The starting point is
that the entitlement should be equal. A departure from that principle is
allowable only where it is just, or fair, to recognise inequality. The
departure must take as its reference point the proposition, from which it
departs, that apartment owners should contribute equally to the costs of
the building. The focus of the inquiry is the extent to which an apartment
unequally causes costs to the body corporate.
20. At para [32] Chesterman J sets out a third consideration that if this
principle not be the applicable one then there is no basis on which
applications for adjustment of contribution lot entitlements can consistently
be made. As the evidence in this application shows, if the inquiry is limited
to the extent to which an apartment creates costs, or consumes services,
above or below the average, one can readily determine what the
contribution lot entitlement should be.
21. At para [33], Chesterman J stated, I would construe section 49 of the Act,
and in particular subsection (4), as meaning those identified matters to
which a court may have regard are to be regarded only to the extent, if
any, that they affect the cost of operating a community titles scheme.
DISCUSSION OF THE EVIDENCE
22. The tribunal notes from her curriculum vitae that the author of the L & P
Report, Ms Kaylene Arkcoll has qualifications in quantity surveying and
applied law and has 18 years experience in this area. The Tribunal
accepts that Ms Arkcoll has appropriate qualifications and experience in
regard to the matters addressed in the report.
23. The L & P report sets out the details of the structure of Hi Surf noting that
there are 106 lots in the scheme including a management lot. The scheme
includes a basement - level A which contain exclusive use car spaces for
each of the lots, lift landings, a refuse room store rooms and plant rooms.
-- 7 of 15 --
8
There is a ground level - level B which includes the main foyer with
attached porte cochere, lift lobbies and an indoor pool area and includes a
spa, saunas and male and female toilet/changing rooms. It also contains
the lot 1 (the manager’s lot) which includes an on-title reception office and
lots 2 to 4. Level C contains a common lift lobby as well as 3 lots. Lots 2 to
73 are located on these levels (this is incorrect in accordance with the
plans, Level C contains lots 5 to 8). Levels D - AA each contain a common
lift lobby as well as 4 lots. Lots 9 to 104 are located on these levels. Level
BB contains lot 105 and 106, which is the applicant’s lot. Levels CC and
DD contain the roof and rooftop plant rooms. The external common
property facilities for Hi Surf include an external driveway, paving, an
outdoor swimming pool and spa area, a children’s playground area, a
BBQ and billiards table shelter adjacent to the pool and play ground
areas, a gymnasium building, a tennis court area, water features and
extensive pathways and landscaping.
24. Ms Arkcoll at section 3 of the L & P report notes that, “His Surf was
registered as BUP 3632 on 21 March 1980. Under the strata legislation of
the time, the manner in which lot entitlements for a Building Unit Plan
were allocated was completely at the discretion of the registering
developer. As a result, it was common to find that the entitlement
allocations were influenced by market value factors such as the area of
the unit, the number of bedrooms in the lot, or the height of the lot up a
unit tower. The schedule for Hi Surf appears to have been influenced at
least partly by floor area and the height of the lot up the tower. For
example, lot 5 has 90 entitlements while the identically designed lot 101
which is located 24 levels higher up the tower has 118 entitlements.”
25. Ms Arkcoll then in section 4 states that “when a contribution schedule has
been automatically created using a pre BCCM Act entitlement schedule, it
may not be consistent with the current “cost impact” principle of section
46(7)” She then goes on to give her analysis of the relevant provisions of
the BCCM Act and a discussion of the decision in Fischer & Ors v Body
Corporate for Centrepoint Community title Scheme 7779 [2004] QCA 214.
26. Ms Arkcoll then states “Our analysis takes into account only those lot
related factors that have the potential to directly affect the cost to the body
corporate of providing the services itemised in the administrative budget
and sinking fund. In our analysis of expense items we have used the
legislative default position of ‘all costs shared equally’ unless compelling
evidence is present to prove that for a specific cost item a more just and
equitable allocation can be calculated and should be applied. This
requires proof that a significant variation in cost impact exists and that
there is an appropriate method to establish its monetary value over a
reasonable future time period. Having analysed each of the expense
items, we will recommend the default ‘all contributions entitlements equal’
unless, in our opinion, the total costs allocated to each lot varies
sufficiently for justice and equity to demand an unequal entitlement
schedule.”
-- 8 of 15 --
9
27. The L & P Report then discusses the approach to particular items of body
corporate expenditure as follows:
a. At 5, it is unusual for most purely administrative costs to be
apportioned other than equally.
b. At 5.1, The costs of insurance are limited to public liability, office
bearers liability and personal accidents) as the costs of other
building related insurance are shared in accordance with the interest
schedule
c. At 6, If all lot owners have an equal right to access and use the
common areas and facilities we will by default treat them as equally
responsible for the expenses of running and maintaining these
facilities. We only consider departing from the principle of equal
responsibility if (relevantly):
i. Special usage rights (such as exclusive use agreements)
restrict a lot’s ability to use a common area or facility;
ii. Particular common property areas or infrastructure are directly
designed to provide an additional benefit to particular lots;
iii. Something about the lot’s use directly increases or decreases
the costs associated with the common (communal) areas and
facilities; or
iv. Something about the physical design of the lot directly
increases or decreases the cost to maintain that lot’s structure.
d. At 6, In our opinion, when people elect to purchase a lot in a
particular development they do not have the right to automatically
reduce their contribution merely because they choose not to use
certain communal facilities or are not forced to do so by the
scheme’s design (eg contributions to emergency stair maintenance
by an owner on the ground floor).
e. The body corporate for Hi Surf provides a wide range of services to
the lot owners. If:
i. The same service is provided to all the lots or all the lots obtain
the same benefit from a service to the common property (for
example pest control or power for lighting of the common
areas), and
ii. The design or use of the individual lot is unlikely to predictably
affect the cost of providing the service
We have apportioned the cost of the equally between the lots.
f. We have also allocated a number of repair and maintenance items
equally because they are of an unpredictable nature and it is not
possible to forecast with any degree of long-term certainty if or how,
they may be affected by lot specific factors.
-- 9 of 15 --
10
28. In regard to exclusive use areas consideration was given to the exclusive
use car parks in the basement and an exclusive use roof top area which
was granted to lot 106. Each lot has an exclusive use car park and while
there several which may be large enough for two cars the basement was
considered a low maintenance area the major item of maintenance being
the garage door opener which had an annual cost of $1.67 per lot. In
regard to the roof top area, it was stated that by-law 30 requires the
owner of lot 106 to maintain and keep in good condition the said area. The
report states that the body corporate is responsible for external painting to
the slab edges and a small amount of wall, perimeter balustrade and roof
membrane in regard to the roof top area. Painting and balustrading are
dealt with further below.
29. At 6.2, the L& P report considers the impact of variations in lot design on
body corporate expenditure and concludes that external painting,
maintenance and replacement of the balustrades and window
replacement should be treated unequally. Whereas the roof, lifts and fire
protection system should be treated equally. Specific mention is made of
lot 106 in respect of the roof and windows. In the case of the roof while it
is treated as an equal expense it is noted that if an owner or occupier of
lot 106 damages the roof membrane the body corporate has the right to
charge the owner directly for repairs.
30. In regard to windows the replacement area of body corporate glazing on
the exterior of each lot was measured and the costs apportioned
accordingly. Glazing to the common property building areas has been
shared equally between the lots. It was noted that the body corporate is
responsible for replacement of windows situated in a lot boundary wall.
This means that windows and doors inside the lot balconies are the
private responsibility of the lot owners. So Lot 3 and other lots of the
same design had no window cost allocation. Lot 106 had only a small
number of windows which are situated in the lot boundary wall and it has
only a $171.48 annual window allocation. By comparison lot 105 has a
cost allocation of $1,130.49 and lots of the same size as lot 5 have a cost
allocation of $1,130.49.
31. The area of external painting and concrete spalling for each lot was
measured and the cost of the lot related painting and concrete spalling
was apportioned accordingly. Painting to the exterior of the common
property building areas and external common property has been shared
equally between all the lots. It was noted that the painting of the fire
ledges around the perimeter of the building is included in the common
property as BUP 3632 shows these ledges are common property. It was
also noted that because the external lot walls are extensively glazed the
size of the lots has less impact on the cost of lot painting than many
owners may expect The quantity of equally shared painting to common
areas (particularly because of the fire ledges and external retaining walls
and fences) also comprises a higher than typical proportion of the total
painting in this scheme.
-- 10 of 15 --
11
32. The length of balustrade on each lot was measured and the cost of
maintaining and replacing the lot balustrade was apportioned accordingly.
The balustrade quantity for lot 106 included that around its exclusive use
area. It was noted that even though Lot 106 is paying 4.56 times the
balustrade allocation of lot 105 and 2.37 times the painting allocation of lot
105, its total external maintenance cost is lower as a result of the window
allocation, which translates into a lower contribution entitlement.
33. In regard to the lifts and fire protection systems it was stated that all of the
lots in Hi Surf have reason to use the lifts to access either their lot or the
basement, Consequently we have shared the administrative and sinking
fund costs equally.
34. At 6.3, the L& P report discusses the impact of variations in usage on
body corporate expenditure. The L & P Report noted that the majority of
items in the administrative and sinking fund forecast are not affected by lot
occupant numbers or usage levels and that lot related usage variation are
a valid consideration only if the usage variations will directly alter the cost
of body corporate expense and that if we can reliably predict and quantify
a lot use pattern that substantially affects the cost of maintaining these
items, we considered apportioning these expenses accordingly.
35. The L & P Report noted that Hi Surf contains 106 units with a mix of 1, 2
and 3 bedrooms. Having considered the typical residential lot usage for Hi
Surf and similar developments, the report recommends an equal
allocation of the usage level affected expense items between the lots as:
a. There appears to be at most a 2 bedroom difference in the design of
the lots,
b. In this style of development, the number of bedrooms does not
predetermine the exact number of people who will occupy a lot (a
one bedroom lot may typically be occupied by between 1 and 2
people while a three bedroom unit is likely to be occupied by
between 2 and 4 people, the Australian Bureau of statistics’ 2006
Census shows that on the Gold Coast the difference in average
occupancy between 1 and 3 bedroom units is 0.96 people.
c. The ‘days per year’ occupancy rate of long term residency lots and
short term residency lots is likely to be different, as will the usage
patterns of the occupants in these lots,
d. None of the use affected items except the lift power comprise a large
enough percentage of the total budget for a minor variation in
apportionment to potentially affect our scheduled recommendation
and the deterioration of many of these items will also be due
substantially to other factors such as age and exposure to the
elements; an
e. The cost impact on these items of a 1 or 2 person difference in
usage would be minor and difficult to calculate authoritatively,
leaving the result open to ongoing challenge.
-- 11 of 15 --
12
The report then states, it is our opinion that using the default legislative
apportionment of “all lots equally” is unlikely to be any more unequal or
inequitable than the results that would be achieved by attempting to apply
an unequal allocation.
36. The conclusion to the L & P report states that based on our inspection of
the site and the information provided to us; it is our opinion that the current
contribution schedule for Hi Surf is not just or equitable. And that based
on the information currently available, we believe that the contribution
schedule recommended in Part B: Table 5 is a just and equitable
reflection of the cost impact of each of the lots on the body corporate.
There is a variation of $766.42 between the highest and lowest cost
allocations in our analysis. In our opinion, this is too large to allow us to
reasonably recommend an equal entitlement schedule. It is noted that
upon checking Table 5 the variation between the highest and lowest
contribution is $1,196.17. It is noted that the contribution schedule also
determines
37. Table 1 of the L & P Report sets out the administrative budget expense
inclusions. This is based on the actual expenses of the body corporate for
the years ended 30 April 2007 to 30 April 2009 and the budget for the
year ended 30 April 2010, with some adjustments where average
historical costs are used. These items have been extracted from copies of
income and expenditure and expenditure statements and proposed
annual budgets annexed to the report. Table 2 of the L & P Report then
sets out the allocation methodology for administrative fund expenses
items. In accordance with the body of the report these are all allocated
equally. The contribution for each lot is stated to be $6,072.83. When the
figures are checked this statement is incorrect and the correct amount per
lot is $4,354.11. This is not consequential as the error is not carried
through to the calculation of the recommended entitlement schedule.
38. Table 3 of the L & P report sets out the allocation methodology for sinking
fund expenses. The sinking fund expense items have been taken from a
GK Consulting Sinking Fund forecast for the body corporate dated 23 May
2008, which is annexed to the report. In accordance with the body of the
report these items are allocated equally except fro the painting of the
building façade, allowance for future concrete spalling, window
replacement, replace balustrade to building. The equal items comprised
$92,751.17 which is an amount of $875.04 per lot. The items based on
quantity per lot are $110,136.67 and they are dealt with in table 4 of the
report. Some items were excluded being the final payment of a painting
contract and a future faced refurbishment.
39. Table 4 of the L & P Report sets out the quantity per lot for those items of
sinking fund expenditure which are allocated unequally. These
calculations were based on measurements taken by Ms Arkcoll in respect
of such things as the length of balustrade per lot, areas of windows per lot,
area of painting per lot. Included here is an amount for the share of
common window glazing and painting of exterior common areas. This
-- 12 of 15 --
13
table highlights the matters raised in the report about the characteristics of
the lot design affecting the amount for window replacement in respect of
various lots. There is a clear pattern where on most floors the lowest
amount to be allocated is $436.96 and the highest $1,534.27. It is noted
that while the total amount considered for unequal allocation was
$110,136.67 the total amount allocated was $109,984.28 this is
mentioned in the report as being due to rounding errors.
40. Table 5 of the L & P Report sets out the cost impact assessments and
recommended entitlement schedule. The lowest contribution is $5,648.56
in respect of lots with fewer than average windows to be replaced with the
highest being for lot 105 at $6,844.73. The variation is then $1,196.17 and
if allocated equally the body corporate fees would be $6,266.70 which is
$618.14 greater than the lowest amount under the recommended
contribution schedule.
41. The Respondent provided a defence dated 18 September 2009 to the
application admitting that the L & P Report finds that the current
contribution schedule for Hi Surf is not just and equitable. The
Respondent did not accept the findings or recommendations of the L & P
report and did not admit the current contribution schedule is not just and
equitable. The respondent reserved its right to commission an expert to
publish a report in respect of the validity or otherwise of the methodology
adopted in the L & P Report in respect of the recommended new
contribution schedule, the validity or otherwise of the L & P Report
generally and whether or not the current contribution schedule for Hi Surf
is just or equitable.
42. As mentioned above the Respondent’s solicitor advised by letter dated 20
November 2009 that the Respondent neither supports nor opposes the
orders sought by the applicant and does not intend to engage an
independent expert to prepare a report (or otherwise give evidence) in
respect of the current contribution schedule.
43. There was one submission from a lot owner, though they only identified
that they were the owners of a ground floor lot. The matters they raised
were the increase in their levies by 49.9% and the decrease in Mr
Barlow’s levies by 51.3% describing this as discriminatory and
preposterous. Stating that it seemed unjust that their small one bedroom
apartment incurs such an enormous increase in levies, whilst the
penthouse enjoys such an enormous decrease in levies, while all other
units are minimally affected. They further state that they are not able to
use the elevator as each floor is key locked and most times we walk from
the car park because the two elevators are busy with the constant use
from the higher floors. They also mentioned that their privacy has become
less since purchase with pool boundary fence and barbecue tables
moving closer to our balcony and during recent renovations and large
arrivals to the foyer lifts, our access was regularly blocked and very noisy.
-- 13 of 15 --
14
CONCLUSION
44. The community management statement for Hi Surf, a copy of which is
found in Part F of the L & P Report sets out the contribution and interest
schedule lot entitlement for the body corporate. The contribution and
interest entitlements for each lot are the same, which is in accordance
with the comments made in the L & P Report and are not equal. It is noted
that the body corporate was registered on 21 March 1980 and at that time
there was no requirement that the contribution schedule be equal unless it
is just and equitable in the circumstances for them not to be equal in
accordance with section 46(7) of the BCCM Act. In fact at that time there
was only one schedule for both contribution and interest purposes.
Following the introduction of the BCCM Act separate contribution and
interest schedules were created but the individual lot entitlements were
duplicated in both schedules. In accordance with section 48 of the BCCM
Act a lot owner may make application for the contribution schedule to be
adjusted. In accordance with section 48(6) of the BCCM Act the Tribunals
order must be consistent with the principle that the respective lot
entitlements should be equal, except to the extent to which it is just and
equitable in the circumstances for them not to be equal. Mr Barlow as
owner of Lot 106 in Hi Surf has made such an application and he has
requested that the contribution schedule be adjusted in accordance with
the L & P Report.
45. The L & P Report has analysed the body corporate of Hi Surf in terms of
both its administrative and sinking fund expenses and the physical
characteristics of the lots and lot usage for the body corporate, The report
has been framed on the basis that the expenses should be allocated
equally unless it can be shown that there is a measurable variation of cost
to the body corporate based on lot specific characteristics. The Tribunal is
satisfied that the methodology used in the L & P Report is in accordance
with the BCCM Act as interpreted by Chesterman J in Fischer & Ors v
Body Corporate for Centrepoint Community title Scheme 7779 [2004]
QCA 214. The Respondent did not provide any material to refute the
methodology of the report or the figures used in calculating the
recommended contribution schedule. The L & P Report as required starts
on the basis that expenses should be allocated equally and does so for
the majority of expenses. Where though differences in the impact of unit
design affect the cost to the body corporate in respect of lots these have
been measured and allocated unequally. This applies to external painting
and concrete spalling, window replacement, balustrade replacement in all
of these cases the differences could be physically measured and
variations calculated with some precision.
46. The issues raised by the owner of the ground floor lot do not take account
of the requirement in the BCCM Act that lot entitlements for the
contribution schedule should be equal is the starting point for
consideration and then it is where differences can be measured that the
question of whether it is just and equitable for them to be unequal is
answered. The fact that some lot owners do not use certain body
-- 14 of 15 --
15
corporate facilities is not something which can be taken into account
unless they are excluded from the use of that facility. Clearly with the lift
its use from the basement to the ground floor is available and if an owner
on the ground chooses to use the stairs then that is not a matter going to
whether the lot owner should contribute to the lifts. Questions of privacy
would tend to go to amenity and while these are matters which could be
taken up with the body corporate are not matters in accordance with the
decision of Chesterman J which can be considered in regard to the
contribution schedule.
47. The contribution schedule for Hi Surf is currently unequal and possible
justifications for this inequality are set out in the L & P Report as reflecting
such things as floor area and the position of lots in the building. While floor
area of a lot may be reflected in such things as the external area to be
painted and the costs for windows the height of a lot in a building should
not affect the amount of body corporate levies which a particular lot owner
pays. The Tribunal accepts that the L & P Report has properly identified
the expenses of the body corporate and where they should be allocated
equally and where they should be allocated on an unequal basis in
accordance with the requirement that they be allocated equal unless it is
just and equitable to allocate them unequally. The tribunal is satisfied that:
a. The present contribution schedule is not equal;
b. The present contribution schedule is not just and equitable;
c. A contribution schedule in terms of the recommended contribution
schedule set out in Table 5 of the L & P Report would be just and
equitable.
ORDER
48. The tribunal will make an order that the contribution schedule for Hi Surf
be adjusted so that the respective contribution lot entitlements recorded in
the Community Management Statement be in accordance with the lot
entitlements set out in the recommended contribution schedule column of
Table 5- Cost impact Assessment & Recommended Entitlement Schedule
of the L & P Report.
49. The Tribunal notes that the body corporate for Hi Surf must in accordance
with section 48(10) of the BCCM Act as quickly as possible following the
making of this order lodge a request to record a new Community
Management Statement reflecting the adjustments ordered.
-- 15 of 15 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2010/055