Crossan v Central Highlands Regional Council & Anor [2010] QPEC 10 (2010) QPELR 499
1-1
PLANNING AND ENVIRONMENT COURT [2010] QPEC 10
JUDGE RACKEMANN
P & E Appeal No 1498 of 2009
ANDREA CROSSAN Appellant
v
CENTRAL HIGHLANDS REGIONAL COUNCIL Respondent
and
CHIEF EXECUTIVE, DEPARTMENT OF TRANSPORT Co-Respondent
AND MAIN ROADS
and
CHIEF EXECUTIVE, DEPARTMENT OF ENVRIONMENT Co-Respondent
AND RESOURCE MANAGEMENT
BRISBANE
16/02/2010
Mr W. Cochrane for the Appellant
Mr S. Ure for the Respondent
ENVIRONMENT AND PLANNING – STRIKE OUT APPLICATION – whether
application was a type which could be made under the IPA – preliminary approval to
override planning scheme – where it was described in broad terms – where applications
described as one for rezoning – whether misdescription able to be cured by s4.1.5A
-- 1 of 17 --
1-2
HIS HONOUR: In August 2007 the appellant, through its
consulting surveyors and town planners, made a development
application for a preliminary approval to override the
planning scheme, and for a development permit for
reconfiguring a lot, in accordance with a certain master plan.
That plan was the subject of a change, consequent upon an
information request. The application was the subject of an
acknowledgment notice. It was publicly notified, assessed and
decided by the council, which refused the application. By
this proceeding the appellant challenges that decision.
Today's hearing is to determine a point raised by the
respondent at a preliminary stage. The respondent now asserts
that the application was not one of kind which could be made
under the Integrated Planning Act, and that the council was
wrong to accept and decide it. It was submitted for the
respondent that the appeal should be struck out, on that
limited ground.
The aspect of the application which is controversial, is the
application for a preliminary approval under section 3.1.6 of
the IPA. That section provides, in part, as follows:
"3.1.6 preliminary approval may override a local planning
instrument
-- 2 of 17 --
1-3
(1) this section applies if –
(a) An applicant applies for a preliminary approval; and
(b) Part of the application states the way in which the
applicant seeks the approval to vary the effect of
any local planning instrument for the land.
...
(2) Subsection (3) applies to the extent that the application
is for –
(a) Development that is a material change of use; and
(b) The part mentioned in subsection(1)(b)
(3) If the preliminary approval approves the material change
of use, the preliminary approval may, in addition to the
things an approval may do under part 5, do either or both
of the following for development relating to the material
change of use –
(a) state that the development is –
(i) Assessable development (requiring code or
impact assessment); or
(ii) Self assessable developments; or
(iii) Exempt development.
(b) identify any codes for the development."
An application of the kind described in that section has two
-- 3 of 17 --
1-4
parts. Firstly, the part which seeks a preliminary approval
for development, and secondly, the part which requests to vary
the effect of the planning scheme. The respondent asserts
that the application in this case:
(i) did not identify any development for which a
preliminary approval was sought and
(ii) sought a variation to the scheme of a kind not
recognised by the Act.
It was submitted that the application, insofar as it sought a
preliminary approval, was not of a kind permitted by the Act,
and that the application for a development permit for
reconfiguration fell consequentially, since it relied upon the
granting of the preliminary approval. Much of the argument was
therefore taken up with an analysis of what "development" (if
any) was applied for, and whether the level of detail provided
in the application was sufficient in that regard.
The proposed use of the land was described in part A of form 1
as: "Change of land use and urban subdivision." That is
relatively uninformative. The particulars of the proposal are
contained in the consultant's planning report and a plan of
development which accompanied the application and which were
referred to in item 25 of part A of form 1
-- 4 of 17 --
1-5
The master plan, which was lodged with the application, shows
the proposed road and subdivision layout. It also has a
description of the use intended in respect of various
precincts within the development. The development is to
comprise seven precincts or areas. The uses to be made of
those precincts were described as follows:
(i) large lot housing;
(ii) medium lot housing;
(iii) small lot housing;
(iv) retirement village;
(v) mix of commercial and community uses;
(vi) parkland and drainage reserve; and
(vii) rural balance parcel.
The proposed future land uses were further described in
section 2.1.1 of the consultant's report which provided:
"The Master Plan provides a fully integrated and functional
urban design, catering for the diverse living needs of the
Emerald community. The residential component provides a range
of allotment sizes from small (450 m² to 599 m²), residential
parcels to a mix of predominantly 600 m² and 800 m² residential
parcels. The resulting range of lot sizes will ensure a
diverse housing market meeting the needs of a wide range of
people. In particular the number of small lots provides an
opportunity to create affordable land parcels, which are in
-- 5 of 17 --
1-6
short supply within Emerald area.
In addition, the proposal intends to create a large
Residential Accommodation parcel intended for the future land
use of a retirement village. This retirement, although not
applied for within this application, will ultimately provide a
vitally needed facility for the aged care of persons within
the Emerald shire. The facility will provide care for elderly
persons who can maintain their sense of independence, whilst
still providing for the level of care to facilitate their
standard of living.
The proposal also provides a sizeable Commercial parcel,
which can be utilised for a wide range of commercial uses,
which are demanded by the increased residential density of the
proposal and the neighbouring residential communities, in
addition to the lack of commercial space available within
Emerald's town centre commercial precinct. It is expected
that this commercial node will be anchored by a supermarket
facility and accompanied by a number of specialty retail
shops. As the final intent of this node is not realised at
this time, the parcel has been designed to ensure that
sufficient area and dimensions are provided to ensure numerous
options are available for the building area, vehicle parking,
manoeuvring and effective landscape treatments to ensure a
high level of urban design is achieved.
-- 6 of 17 --
1-7 ORDER
Finally, the proposal also provides a number of open
space parcels. The majority of these parcels serve a function
of either drainage reserves or provide vegetative buffers for
the surrounding rural lands. However, Proposed Park Lot 100
provides a large useable recreational area for the enjoyment
of the future residents. The proposal intends for this park
lot to contain a mix of passive and active recreational areas,
providing for the diverse needs and wants of the future
residential community. In addition, the central location of
the proposed park Lot 100 ensures that all proposed
residential parcels are within easy walking distance from this
facility. The exceptional location of this park is
accentuated by the exceptional access afforded to this park by
completely surrounding the parcel by road.
Proposed Park Lots 101 & 102 have been designed to
accommodate a vegetated buffer to the rural lands to the east
of the site. This area will be specifically planted to ensure
that odours and spray drift from existing or future farming
activities undertaken on adjoining rural lands will not impact
upon the amenity and health of future residents of the
development.
Finally, a large balance parcel has been proposed to
include the remainder of the development site. This balance
parcel will maintain the existing zoning designation of Rural.
-- 7 of 17 --
1-8 ORDER
This parcel will include a 40m wide vegetated buffer to
protect the urban development from the agricultural activities
of the balance rural parcel. The intent of providing the
agricultural buffer on this balance parcel rather than within
the urban development is to provide temporary protection of
the estate which, if or when the balance parcel is converted
to urban uses, can be removed and further developed, thereby
continuing the integrated development initiated by this master
plan."
It is evident that the appellant, in making its application,
put forward a proposal which was at a reasonably detailed
level in terms of the subdivision layout but which described
the proposed use of the various precincts at a fairly broad
level, in that future purchasers of allotments would have the
choice of applying for different particular types of uses.
The proposal is that the range of uses for which development
permits might later be sought, is to be determined by
reference to amended tables of assessable development for the
commercial precinct, and for the residential accommodation
precinct(those amended tables of assessable development were
set out in the consultants' report) and otherwise are to be
determined by reference to the provisions of the town plan
applicable to various precincts within the Town zone. So, for
example, the Large Lot housing precinct is to be governed by
-- 8 of 17 --
1-9 ORDER
the provisions which otherwise apply to the residential
precinct of the Town zone.
It is, of course, not uncommon for master planning to occur
and to be the subject of approvals at a time before the
precise use of each and every allotment is known. The evident
purpose of the application was to obtain approval to create a
subdivision which could then be put to uses of the kind
described in the legend and more particularly by reference to
the nominated provisions, rather than the land's development
potential being limited by the provisions which apply to the
currently prevailing Rural zone.
Prior to the commencement of the Integrated Planning Act a
developer would have pursued this strategy by seeking to
rezone the land from its current Rural zone and to include it
in another zone or zones under the town plan. With the
commencement of IPA the ability to apply for a rezoning
disappeared, but that did not prevent a similar result being
achieved. The IPA introduced provisions for an application
for preliminary approval and indeed, one which could override
the local planning instrument. Hence, instead of changing the
town plan to change the colour on the scheme maps, so as to
rezone the subject land, with the introduction of the IPA, one
was able to apply for an approval which would give development
rights which were in conflict with the prevailing zone. One
-- 9 of 17 --
1-10 ORDER
could therefore achieve development rights inconsistent with
the prevailing zone without having to apply for a rezoning.
This was recognised in the explanatory notes to clause 3.1.6
as it was originally enacted, which said in part, "This clause
overcomes the need to rezone the land as a first step in the
development process."
The explanatory notes to section 3.1.6, as it was initially
enacted, also contemplated the use of that provision to obtain
an approval for a development which was still at a conceptual
level. It said, in part:
"If a large master planned housing estate is proposed on land
currently zoned rural, this clause allows a preliminary
approval to be given approving development to the extent
stated in the approval. For example, it may identify
different development precincts, broad land use intentions for
each of those precincts and the major infrastructure networks
for the estate."
That is what the appellant did in this case. It put forward a
master planned urban development, for which it sought
preliminary approval, and identified different development
precincts and stated the broad land use intentions for each of
those precincts.
-- 10 of 17 --
1-11 ORDER
One of the potential difficulties with 3.1.6, as originally
enacted was that it only allowed an application for a
"material change of use requiring impact assessment".
Similarly, section 3.1.5 spoke of a preliminary approval
approving "assessable development". It is difficult to see how
the explanatory notes’ reference to a description of "broad
land use intentions" can sit with the requirement to identify
a particular form of assessable development, for which
approval is sought. The provisions were, however,
subsequently amended by the Integrated Planning and Other
Legislation Amendment Act 2003.
The amendments deleted the reference to “assessable” in
describing the development which needed to be the subject of
the preliminary approval. The explanatory note to section
3.1.5 was as follows:
"Clause 45 amends section 3.1.5. Subsection (1) is
amended to provide that a preliminary approval approves
“development”, rather than “assessable development.” This
reflects the fact that one of the uses of the preliminary
approval process is to allow participants to seek
approval, not of development specifically defined under a
planning scheme, but of a concept, such as a “shopping
centre” or “industrial estate”...the current wording
implies that the preliminary approval process may only be
-- 11 of 17 --
1-12 ORDER
used for development that is clearly assessable under the
scheme..."
The reference to the preliminary approval process being used
to seek approval of a "concept" rather "development
specifically defined under a planning scheme" confirms that in
seeking a preliminary approval for a martial change of use one
does not have to be able to descend to nominating a form of
development specifically defined under the planning scheme as
assessable development.
That explanatory note is complemented by the explanatory note
to section 3.1.6 which, in part, provides as follows (my
underlining):
"Clause 46 replaces and substantially changes section
3.1.6 to facilitate a range of key reforms to the
preliminary approval process, particularly as it relates
to larger "conceptual" approvals and staged or "layered"
approvals.
In summary, the reforms in the Bill for preliminary
approvals are:
...
" A preliminary approval for material change of use may vary
the effect of the planning scheme for any aspects of
-- 12 of 17 --
1-13 ORDER
development related to the material change of use. For
example, a preliminary approval for a material change of use
for "master plan community" may vary assessment requirements
that will include codes for building work associated with the
material change of use (e.g. for building height, bulk or
density), or associated reconfiguration (e.g. through lot size
or other characteristics). A preliminary approval for other
development may vary the operation of the scheme only for that
aspect of development. For example, a preliminary approval
for building work may substitute a new code for the work based
on the innovative approach that nevertheless still achieves
the objects of the planning scheme."
It was submitted, on behalf of the respondent, that for the
application to be valid it needed to specify the particular
uses for which approval was to be sought. I understood that
submission to be one which related to specifying the
particular forms of assessable development as defined in the
planning scheme. It was said that, without such specificity,
it will be difficult for the council to assess potential
impacts. In my view, however, in light of the amendments to
the provisions of the IPA, and consistently with the
explanatory notes thereto, a development application for
preliminary approval does not have to descend to describing
the material change of use for which preliminary approval is
sought by reference to terms defined in the planning scheme.
-- 13 of 17 --
1-14 ORDER
In this case, the development is at a conceptual level. The
material clearly not only described that concept in general
terms, but proceeded to ascribe different intents to different
precincts within the development and went on to give
descriptions, albeit fairly broad descriptions, of the use
which was proposed for each of those precincts. It manifested
an intention for the effect of the planning scheme to be
varied in its application to the land, so that the provisions
applicable to the various precincts within the development
would be the same as those which would have applied if the
land had been in a different zone and precincts under the town
plan. As I have already noted, the application was
subsequently the subject of a change which changed the plan of
development slightly, but not in ways which are material to
the consideration of the matter which falls for determination
today. In my view, an application, to that effect, is a
competent application for preliminary approval under section
3.1.6.
The respondent points to the fact that the application was
poorly described. Instead of describing the application as one
for a preliminary approval for the uses described in the
master plan together with a request to vary the effect of a
planning scheme, so as to apply the provisions which are
otherwise applicable in other precincts, it instead was
-- 14 of 17 --
1-15 ORDER
described, in the application material, as an application to
rezone the land from the Rural zone to the Town zone and, in
particular, to certain precincts within the Town zone.
As I have already acknowledged, the IPA does not permit an
application to be made to exclude land from one zone and
include it in another, although section 3.1.6 makes that
unnecessary because, as I have already observed, it permits an
approval to be given which varies the effect of the local
planning instrument, without the need for a rezoning.
The respondent placed some reliance on the decision of Robin
QC in Lagoon Gardens Pty Ltd v Whitsunday Regional Council and
Others [2009] QPEC 66. That was a case in which his Honour
ultimately held that an application was “too shrouded in
uncertainty or ambiguity” to qualify as an application for
“development.”
In that case a development permit had been given for a
material change of use described as “from rural protection
zone to part urban residential and part open space zones.” A
development permit, as opposed to a preliminary approval, is
something which is given in respect of assessable development.
His Honour was understandably concerned at a lack of precision
about the particular form of assessable development which the
development permit authorised to occur.
-- 15 of 17 --
1-16 ORDER
A preliminary approval, as I have already noted, is not
limited to assessable development and further, it does not
authorise assessable development to occur. Before any material
change of use in fact occurs, a development permit authorising
assessable development will have to be sought and granted. The
decision in Lagoon Gardens is distinguishable.
The rezoning description used in various parts of the material
was unfortunate and wrong. In determining what the
application was for, the application documents, including the
material that was included with them, need to be construed as
a whole and objectively. In my view, when one has regard to
the whole of the material it is evident that what was being
sought was a preliminary approval under section 3.1.6, to vary
the effect of the local planning instrument in respect of a
proposal, which was not simply a change of zone, as one would
have applied for it under the preceding legislation, but for a
development as depicted in the master plan and as described in
the supporting report. To the extent that the misdescription
in the documents caused any non-compliance with the
requirements of section 3.2.1, and to the extent that those
defects were not otherwise cured by the assessment manager's
acceptance of the application, then I am prepared to exercise
the discretion under section 4.1.5A to excuse any non-
compliance.
-- 16 of 17 --
1-17 ORDER
The same applies with respect to the description in the public
notification, which also referred to rezoning. The description
in the application, whilst literally wrong, was unlikely to
have materially misled those who were viewing the application,
as to the nature of what was proposed. Anyone excited by that
public notification, of course, had the ability to view the
application, including the attached report, which, I think,
made the development concept, for which approval was being
sought, relatively clear.
My conclusion that it would be appropriate to apply 4.1.5A, in
the event that a requirement had not been complied with,
follows from my satisfaction of the matters in subsection 1(b)
of that section. It is also on the basis that the
application, properly construed, was an application under
section 3.1.6 (albeit misdescribed,) rather than an
application for rezoning properly so called. I accept Mr Ure's
point that, if the application had been one which was not
possible to make under the Act, then it would have been
inappropriate to apply section 4.1.5A. However, I have
reached a different conclusion. Accordingly, I determine the
preliminary point against the respondent.
-----
-- 17 of 17 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2010/010