Director-General of the Environmental Protection Agency v Hamcor Pty Ltd & Ors [2010] QPEC 1 (2010) QPELR 416
PLANNING & ENVIRONMENT COURT OF
QUEENSLAND
CITATION: Director-General of the Environmental Protection Agency v
Hamcor Pty Ltd & Ors [2010] QPEC 1
PARTIES: TERRY WALL, DIRECTOR-GENERAL OF THE
ENVIRONMENTAL PROTECTION AGENCY
(applicant)
v
HAMCOR PTY LTD
ACN 010141 429
(first respondent)
WILLIAM MARTON HAYWARD
(second respondent)
DONALD CHARLES HAYWARD
(third respondent)
ANNA MARIE HAYWARD
(fourth respondent)
TERRENCE ARTHUR ARMSTRONG
(fifth respondent)
FILE NO/S: BD 3154 of 2006
DIVISION: District Court
PROCEEDING: Trial
ORIGINATING
COURT: District Court at Brisbane
DELIVERED ON: 14 January 2010
DELIVERED AT: Brisbane
HEARING DATE: 13 January 2009
JUDGE: Robin QC DCJ
ORDERS: As per judgment
CATCHWORDS: ENVIRONMENTAL PROTECTION ACT 1994 –
amendment of enforcement orders dealing with contaminated
site requiring mediation
COUNSEL: M Hinson SC for the applicant
J Hunter SC with W Cochrane for the respondents
SOLICITORS: Crown Law for the applicant
Everingham Lawyers for the respondents
[1] HIS HONOUR: The Court makes an order in terms of the
initialled draft. It is ordered that:
-- 1 of 6 --
2
1. The Respondents must use their best endeavours to
discharge water collected in the Binary dams in
accordance with the order of Judge Robin QC dated 6
August 2009 and paragraphs 22 and 23 of the order
of Judge Rackemann dated 10 October 2007 (as
varied) (the terms of which are set out below in
the Appendix) including, but not limited to,
utilising the Respondents' trade waste agreement
with Moreton Bay Regional Council to remove water
in the Binary Site dams as soon as such water
achieves the water quality discharge levels under
that agreement and there is a sufficient volume of
water to justify a discharge;
2. Notwithstanding paragraph 5 of the order of Judge
Robin QC dated 6 August 2009 and paragraphs 22 and
23 of the order of Judge Rackemann dated 10 October
2007 (as varied) (the terms of which are set out
below in the Appendix), where contaminated water
is, in the opinion of the Applicant or its
authorised agents, likely to be or is being
released or removed from the Binary Site other than
in accordance with the above mentioned orders due
to an inability of the Binary Site infrastructure
to cater for any influx of water or other material,
the Respondents or their agents shall:-
(a) At the direction of the Applicant (including
direction as to the volume to be discharged)
and under the Applicant's specific
supervision, be permitted to pump stormwater
from the Binary Site dams (the dams on Lot 69
on CP867910 and Lot 101 on CP895174) to the
Applicant's Site dam (the large treatment dam
on Lot 15 on SP102757) on the terms specified
in paragraphs 3 and 4;
(b) Not be specifically required to remove
contaminated stormwater from the Binary Site
dams by a regulated waste transport vehicles
to a waste management facility except where
the Applicant's Site dam can not be made
available to receive such contaminated
stormwater.
3. The Respondents will pay all costs associated with
pumping, receiving and disposing of contaminated
stormwater received into the Applicant's Site dam
from the Binary Site dams, being:-
(a) The costs of hiring and operation for any
pumps and associated equipment to allow
pumping and controlled and safe discharge to
occur;
(b) An amount of $3.00 per kilolitre of water
pumped from the Binary dams (payable to
-- 2 of 6 --
3
Applicant) the volume of which will be
calculated in accordance with the formula "V =
t x d max " where:
(i) V = the volume of water pumped;
(ii) T = time that the control valve on the
pipe is open (which is to be located on
the Applicant's Site and to be operated
only by the Applicant or its authorised
agents) and water is being discharged
through it;
(iii) D max = the pump manufacturers maximum
pumping rate specified in the design
specifications of the pump used.
(c) Any additional treatment or testing costs
required for water pumped from the Binary Site
dams to achieve the water quality discharge
levels in accordance with Applicant's trade
waste agreement with Moreton Bay Regional
Council current at the time of the discharge
to trade waste;
(d) The cost to the Applicant of discharging from
the Applicant's Site dam the water received
from the Binary dams in accordance with
Applicant's trade waste agreement with Moreton
Bay Regional Council current at the time of
the discharge to trade waste.
4. Paragraph 2 of this order is effective until 1 June
2010.
5. On 2 June 2010, and as quickly as is reasonably
practicable thereafter, the Respondents will at its
own cost drain water then remaining in the
Applicant's Site dam (whether or not that water was
pumped into the Applicant's Site dam from the
Binary Site dams) and dispose of such water under
the supervision of the Applicant:-
(a) Where any such volume of water is able to be
disposed of in accordance with Applicant's
trade waste agreement with Moreton Bay
Regional Council current at the time of the
discharge to trade waste, in accordance with
that agreement (to remove doubt this may be
carried out by the Applicant on the
Respondents' behalf); or
(b) In accordance with paragraphs 22 and 23 of the
order of Judge Rackemann dated 10 October 2007
(as varied); or
(c) By pumping into the Binary dams is such dams
then exist and satisfy the standards in
paragraphs 15, 16 and 17 of the order of Judge
Rackemann dated 10 October 2007 (as varied).
6. The Applicant will:-
-- 3 of 6 --
4
(a) Use its best endeavours to discharge from the
Applicant's Site dam water pumped from the
Binary Site dams in accordance with
Applicant's trade waste agreement with Moreton
Bay Regional Council current at the intended
time of the discharge to trade waste as soon
as such water achieves the water quality
discharge levels under that agreement and
there is a sufficient volume of water to
justify a discharge;
(b) Invoice the Respondents for any costs
mentioned in paragraph 2 hereof as soon as
practicable after the cost has been incurred,
and in the case of the cost mentioned in
paragraph 3(b), as soon as practicable after
the water is received in the Applicant's Site
dam.
7. All costs recoverable by the Applicant from the
Respondents in accordance with this order are
recoverable as a debt due and payable to the State
of Queensland.
8. In the event that a Remediation Action Plan is not
approved by Applicant for the Binary Site by 31
January 2010, the Respondents have liberty to apply
upon 3 days notice to the Applicant to seek a
variation of these orders.
Appendix
Paragraph 5 of Order of Judge Robin QC dated 6 August
2009.
"The Respondents or their agents must not wilfully
or negligently release or remove contaminated
stormwater from dams, sumps or associated conduits
on the land the subject of these proceedings other
than in accordance with paragraphs 22 or 23 of the
order of His Honour Judge Rackemann dated 10
October 2007 (as varied) unless otherwise
authorised by the Applicant or the local
government."
Paragraph 22 of Order of Judge Rackemann dated 10
October 2007 (as varied).
"For the purposes of this Order, any removal
and/or transport of the material (including
solids, liquids, sludges, tanks, demolished
building materials, contaminants, contaminated
stormwater or contaminated materials) from the
land, must only be carried out by a regulated
waste transporter holding all approvals required
by the Environment Protection Act 1994."
-- 4 of 6 --
5
Paragraph 23 of Order of Judge Rackemann dated 10
October 2007 (as varied).
"For the purposes of this Order, any materials
(including solids, liquids, sludges, tanks,
demolished building materials, contaminants,
contaminated stormwater or contaminated materials)
removed from the land, must only be taken to a
waste management facility holding all approvals
required by the Environmental Protection Act 1994
for the storage, treatment, disposal, recycling or
reuse of the materials."
[2] The circumstances underlying this proceeding and the
hearing set down for yesterday and today are dramatic.
The first respondent operated a chemical plant at an
industrial estate at Narangba, known by the name Binary.
Given the nature of activities there, it's unsurprising
that the applicant was fairly closely involved in
monitoring circumstances from the outset.
[3] A catastrophic fire occurred in the first respondent's
premises on the 25th of August 2005 which resulted in
consternation regarding possible consequences of toxins
which had become relatively uncontrolled for the
environment and indeed, for human health.
[4] The Court became involved by way of making enforcement
orders under section 507 and following of the
Environmental Protection Act 1994; detailed orders were
made by Judge Rackemann on the 10th of October 2007 and
varied by me on the 6th of August 2009.
[5] The processes which have led to identification of the
appropriate ways remediate the site to render it
available for future use have been protracted.
[6] It has been much more than a case of identifying
materials on site which are problematic and arranging
their removal to places of safe storage. Until that
removal occurs, there is concern about the effect of
storm waters in large storm events which wash materials
off the site, if dam storage on it proves inadequate,
via waterways, the principal of which has been called
Tributary D, which shortly connect with Hayes Inlet.
Fortunately, the applicant’s department has dam storage
on an adjoining site of its own which may be used in
need, on a costs recovery basis.
[7] There is considerable scientific disagreement as to the
appropriateness of the concerns expressed by the
applicant. The simple proposition that storm waters, in
large rainfall events, may be a blessing as they produce
dilution is challenged. In this context, in heavy
-- 5 of 6 --
6
rainfall events, materials that are usually “safely”
located may be dispersed, exacerbating the situation.
[8] The Court has responsibilities under the legislation
referred to, to be satisfied of certain matters, going
to its jurisdiction and identification of orders, if
any, appropriate to be made. The provisions, in my view,
impose a continuing obligation. Keeping the situation
under review is obviously appropriate in the
circumstances such as the present, as things may change
and the parties' best judgment as to how to deal with
circumstances may change.
[9] The Court has been relieved of having to adjudicate upon
the matters of difference between the parties which
involve some important scientific questions. A detailed
“consent order” has been worked out of considerable
negotiation. Nonetheless, the Court ought not to make
orders as a means of resolving the situation, unless
satisfied that orders the parties agree on fall within
the range of what the Court might consider appropriate.
There's no difficulty in that regard at present.
[10] There will be orders in terms as set out above. There is
plainly going to be required a good deal of monitoring
that does not appear likely to involve the Court in the
close supervision of conduct of parties which the Court
normally tries to avoid.
[11] The Court is available for future recourse to it, which
may be necessary. As circumstances which may lead to
the Court's involvement, acknowledged in today's order,
include the non-finalisation of the remediation action
plan by the end of this month and also the situation
envisaged as rising on the 2nd of June 2010. That's all
thanks.
-----
-- 6 of 6 --