AGL Sales (Qld) Pty Ltd v Dawson Sales Pty Ltd & Ors [2009] QCA 262
SUPREME COURT OF QUEENSLAND
CITATION: AGL Sales (Qld) P/L v Dawson Sales P/L & Ors
[2009] QCA 262
PARTIES: AGL SALES (QUEENSLAND) PTY LIMITED
ACN 121 177 740
(plaintiff/respondent)
v
DAWSON SALES PTY LTD
ACN 087 886 913
(first defendant/first appellant)
ANGLO COAL (DAWSON) LIMITED
ACN 100 155 342
(second defendant/second appellant)
MITSUI MOURA INVESTMENT PTY LTD
ACN 088 091 356
(third defendant/third appellant)
FILE NO/S: Appeal No 2520 of 2009
Appeal No 4390 of 2009
SC No 10731 of 2007
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 4 September 2009
DELIVERED AT: Brisbane
HEARING DATE: 5 August 2009; 6 August 2009
JUDGES: Muir, Fraser and Chesterman JJA
Separate reasons for judgment of each member of the Court,
each concurring as to the orders made
ORDERS: 1. Appeal dismissed with costs.
2. Appeal against the costs orders is dismissed.
CATCHWORDS: CONTRACT LAW – GENERAL CONTRACTUAL
PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS – where agreement
between appellants and respondent whereby appellants to
provide specified quantities of coal seam gas to the
respondent – where appellants were unable to provide the
specified quantity due to the productivity of some wells being
lower than expected – where the appellants consequently
attempted to reduce the amount it was required to provide
under clause 14 of the agreement – whether the situation
relied upon by the appellants falls within the definition of a
-- 1 of 41 --
2
‘Force Majeure Event’ in Schedule 1 – whether a valid
curtailment notice was given under clause 14.1 of the
agreement – whether the appellants failed to discharge their
onus of proof under clause 14.8 of the agreement
PROCEDURE – COSTS – DEPARTING FROM THE
GENERAL RULE – OTHER CASES – FAILURE IN
PORTION OF A CASE – where respondent was awarded
costs at trial – where appellants were given leave by trial
judge under s 253 Supreme Court Act 1995 (Qld) to appeal
the costs order – where appellants argue that respondent was
unsuccessful at trial in relation to a large portion of its
argument and should only receive part of its costs – whether
respondent acted reasonably in the way it framed its case
regarding the interpretation of the relevant agreement –
whether respondent acted reasonably in not applying for
summary judgment – whether the respondent should only
have been awarded a portion of its costs at trial
Supreme Court Act 1995 (Qld), s 253
Andre & Cie. S.A. v ETS. Michel Blanc & Fils [1977]
2 Lloyd’s Rep 166, distinguished
Australian Broadcasting Commission v Australasian
Performing Right Association Ltd (1973) 129 CLR 99; [1973]
HCA 36, cited
BHP Coal Pty Ltd and Ors v O & K Orenstein & Koppel AG
and Ors (No 2) [2009] QSC 64, considered
Bremer Handelsgesellschaft Schaft m.B.H. v Vanden Avenne
Izegem P.V.B.A. [1978] 2 Lloyd’s Rep 109, considered
Coulton v Holcombe (1986) 162 CLR 1; [1986] HCA 33,
applied
Di Carlo v Dubois & Ors [2004] QSC 041, applied
Emanuel Management Pty Ltd (in liquidation) & Ors v
Foster's Brewing Group Ltd & Ors and Coopers & Lybrand
& Ors [2003] QSC 484, applied
Homburg Houtimport BV v Agrosin Private Ltd (The
Starsin) [2004] 1 AC 715; [2003] UKHL 12, considered
House v The King (1936) 55 CLR 499; [1936] HCA 40,
applied
Mannai Investment Co Ltd v Eagle Star Life Assurance Co
Ltd [1997] AC 749, cited
Oshlack v Richmond River Council (1998) 193 CLR 72;
[1998] HCA 11, cited
Re Golden Casket Art Union Office [1995] 2 Qd R 346;
[1994] QCA 480, cited
Suttor v Gundowda Pty Ltd (1950) 81 CLR 418; [1950] HCA
35, applied
Thorpe Nominees Pty Ltd v Henderson & Lahey [1988] 2 Qd
R 216, cited
Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR
165; [2004] HCA 52, applied
-- 2 of 41 --
3
V. Berg & Son Ltd v Vanden Avenne-Izegem PVBA [1977]
1 Lloyd’s Rep 499, distinguished
Waterman v Gerling Australia Insurance Co Pty Ltd (No 2)
[2005] NSWSC 1111, cited
COUNSEL: G A Thompson SC, with S R R Cooper, for the appellants
P L O’Shea SC, with S E Brown, for the respondent
SOLICITORS: Mallesons Stephen Jaques for the appellants
Brian Bartley & Associates, as town agents for Gilbert &
Tobin Lawyers, for the respondent
[1] MUIR JA: The central questions for determination in this appeal concern the
proper construction of the force majeure provisions in a gas supply agreement dated
28 February 2003 between Energex Retail Pty Ltd, as purchaser, and Moura Sales
Pty Ltd, as supplier, acting as agent for Anglo Coal (Moura) Ltd and Mitsui Moura
Investment Pty Ltd, which companies owned and operated the Moura mine. Moura
Sales Pty Ltd changed its name to Dawson Sales Pty Ltd ("Dawson") and is the first
appellant in these proceedings. The second and third appellants, Anglo Coal
(Dawson) Ltd and Mitsui Moura Investment Pty Ltd, are the present mine owners.
The respondent, AGL Sales (Qld) Pty Ltd, ("AGL") replaced Energex Retail Pty
Ltd, as a party to the Agreement, in December 2006.1
[2] Recital "C" to the Agreement provided:
"The Parties acknowledge that this Agreement is based on the Coal
Mine Owners' further development of the Gas production and
gathering systems that access the Gas Field in order to generate a
consistent production profile, and the ongoing assessment of
remaining Gas Field reserves and future deliverability, and the
provision of development and production information in accordance
with this Agreement are fundamental and essential terms of this
Agreement."
[3] I gratefully adopt the statement of facts in Chesterman JA's reasons. I will give
reasons in respect of only three of the issues for determination on the appeal: the
construction of paragraph (h) in the definition of "Force Majeure Event"; whether a
valid notice was given under Clause 14.1 of the Agreement and whether the
appellants failed to discharge their onus of proof under Clause 14.8 of the
Agreement. Counsel for the appellants properly conceded that failure on any one of
these issues would result in the failure of the appeal.
[4] It is also useful to repeat the following passage from the reasons dealing with the
factual background to the Agreement and matters giving rise to the present dispute2:
"When the Agreement was made in 2003, Dawson was extracting
gas from a parcel of land within the Moura mining lease called
Hillview. But wells have a limited life, at least because there is only
so much gas which can be extracted from any one location. And
having regard to the increasing MDQ during the life of the
1 By notice given pursuant to the Energy Assets Restructuring and Disposal Act 2006 (Qld), published
in the Gazette on 1 December 2006.
2 AGL Sales (Qld) Pty Limited v Dawson Sales Pty Ltd & Ors [2009] QSC 8 at [30] - [31].
-- 3 of 41 --
4
Agreement, Dawson well knew that it would have to drill wells
beyond Hillview in order to meet its commitments.
The land called Ridgedale is alongside Hillview. Dawson
commenced exploratory work on Ridgedale at the end of 2004. The
first of the production wells on Ridgedale was drilled by 13 June
2005 and began to produce gas from December 2005. Dawson
attempted to drill 15 production wells in Ridgedale. Two of them,
being the wells numbered RG (Ridgedale) 3 and RG 13, did not
produce any gas. … five of them produced some gas but their
production had ceased by the time of the Curtailment Notice in July
2007. The other wells were still producing then, although in each
case the production had been less than Dawson had expected. So
each of these 15 wells was either never productive or was less
productive than Dawson had forecast. In each case the problem is
said to have been the difficult and unforeseen geological conditions
which were encountered."
Consideration of paragraph (h) in the definition of Force Majeure Event
[5] It is convenient to set out the relevant parts of Clause 14 of the Agreement and the
definition of "Force Majeure Event".
[6] Clause 14 of the Agreement relevantly provided:
"14 CURTAILMENT
14.1 Curtailment by Moura Sales for Force Majeure
14.1.1 Moura Sales may Curtail provision of Services if,
because of a direct Force Majeure Event, it cannot
do, absolutely or in part, something it has to do
under this Agreement (the 'Affected Obligation'),
when it has to do it. If a Force Majeure Event occurs,
Moura Sales must without delay issue a Notice to
ENERGEX setting out:
a) what the Affected Obligation is;
particulars of the event (to the extent Moura Sales
knows them);
b) its estimate of the reduction in Service
capacity, in particular amending the MDQ
under this Agreement over the Suspension
Period; AND
c) its estimate of the duration of its inability to
perform the Affected Obligation.
14.1.2 The Affected Obligation is suspended from the date
the Notice is given until Moura Sales is able, after
the exercise of all reasonable diligence, Good
Engineering and Operating Practice and the
employment of all reasonable means to remedy or
abate the Force Majeure event as expeditiously as
-- 4 of 41 --
5
possible, to perform the Affected Obligation (this
period is the 'Suspension Period').
14.1.3 A Force Majeure Event or circumstances affecting
the performance under this Agreement by Moura
Sales shall not relieve Moura Sales of liability in the
event, and to the extent, that the negligence or failure
to use Good Engineering and Operating Practice by
Moura Sales or the Coal Mine Owners caused or
contributed to its failure to perform under this
Agreement or in the event of its failure to use all
reasonable endeavours including the expenditure of
reasonable sums of money and the application of
proven technology to remedy the situation and to
remove the event or circumstances giving rise to the
Force Majeure Event in an adequate manner with all
reasonable despatch.
14.2 Suspension for Third Party Force Majeure
…
14.3 Curtailment by Moura Sales due to Off-Specification
Gas
…
14.4 Curtailment by Moura Sales due to Maintenance
…
14.5 Notice when the Suspension Period ends
Upon completion of Maintenance activities under clause
14.3, or as soon as the Suspension Period under clause 14.1
ends, Moura Sales must, as soon as reasonably practicable,
issue a Notice to ENERGEX. The Suspension Period ends
when Moura Sales, making reasonable efforts, is able to
perform the obligation again, not when it gives the Notice.
14.6 Service Charges during Curtailment
So long as Service is Curtailed under clauses 14.1, 14.3 or
14.4, Service charges will be calculated on the basis of the
quantities of Gas actually delivered to ENERGEX on a Day.
14.7 Affected Party must rectify the situation if possible
During the Suspension Period Moura Sales must make
reasonable efforts to place itself in a position to perform the
Affected Obligation (but Moura Sales is not obliged to settle
any strike, lock out, boycott, work ban or other labour
dispute or difficulty).
14.8 Termination
If the Suspension Period lasts for more than 3 months,
neither Party can terminate this Agreement, but either Party
-- 5 of 41 --
6
may, upon the expiry of that 3 months period, by Notice in
writing to the other Party reduce the MDQ by the average
quantity of Gas unable to be delivered or utilised on a Day
over the Suspension Period and the Parties respective
obligations under this Agreement will apply to that reduced
MDQ for the remainder of the Term, effective immediately
on Notification. The Authorised Officers of both Parties
shall implement any necessary changes to MDQ pursuant to
this clause by endorsing a variation to Schedule 2."
[7] The term 'Force Majeure Event' is defined in Schedule 1 of the Agreement as
follows:
" 'Force Majeure Event' means any event or circumstance, or
combination of events or circumstances, not within the control
of a Party, and which by the exercise of Good Engineering and
Operating Practice, and seeking in good faith to comply with its
contractual and other obligations by the expenditure of
reasonable sums of money and the application of proven
technology widely known to and generally available for use by
persons in the gas industry, that Party is not able to prevent or
(for the time being) overcome, including, without limiting the
generality of the foregoing:
(a) an act of God including, but not limited to, landslide,
earthquake, flood, wash-out, lightning, storm and action
of the elements;
(b) strike, lock-out, ban or other industrial disturbance;
(c) act of a public enemy, terrorism, war, sabotage, blockade
or insurrection, riot or civil disturbance, arrests and
restraints of rulers and peoples;
(d) fire or explosion including radio-active and toxic
explosion;
(e) epidemic or quarantine;
(f) order of any court or tribunal or the order, act or omission
or failure to act of any government or Government
Agency having jurisdiction;
(g) failure to obtain or retain any necessary consent or
approval of a Government Agency (despite timely and
reasonable endeavours to obtain same);
(h) unpredicted, sudden and material deterioration in
productivity of more than one well or failure of wells,
equipment or plant breakdown or failure that causes full
or partial interruption of the delivery of Gas by Moura
Sales under this Agreement;
(i) the total or partial inability of a Party to receive or have
quantities of Gas which are available for supply or
delivery transmitted through the Queensland Gas Pipeline
-- 6 of 41 --
7
or the Moura Mine Pipeline because of an event of Force
Majeure excusing non-performance by the owners or
operators of the Queensland Gas Pipeline or the Moura
Mine Pipeline, as the case may be under a clause in a
relevant gas transportation agreement;
(j) shortages of labour or essential materials, failure to secure
contractors and delays of contractors;
(k) any breach of contract by, or an event of Force Majeure
affecting a person contracting with ENERGEX (‘Third
Party Contractor’), which prevents ENERGEX doing
something that it has to do under this Agreement where
ENERGEX has taken all necessary, reasonable and
practical action within a reasonable time to obtain
performance of the Third Party Contractor’s relevant
obligation whether by the Third Party Contractor or
another person; or
(l) any order, direction, or requirement under laws relating to
Aboriginal heritage or native title;
but does not include:
(a) full or partial interruption of the delivery of Gas by
Moura Sales due to failure or unpredicted and sudden
deterioration in productivity of a single well, or the failure
or breakdown of a single piece of equipment or plant,
including compressors, pumps, Gas measurement
equipment, and gathering lines;
(b) full or partial interruption of the delivery of Gas by
Moura Sales due to failure or unpredicted and sudden
deterioration in productivity of a single dehydration unit
if such failure or unpredicted and sudden deterioration
could have been prevented by the exercise of Good
Engineering and Operating Practice;
(c) ENERGEX’s loss of customers, loss of market share or
reduction in demand for Gas;
(d) a Party’s lack of funds or inability to obtain or use funds;
or
(e) changes in market conditions relevant to the
transportation and/or the purchase and sale of Gas."
[8] Paragraph (h) is not without obscurity. It is not clear why the words "unpredicted,
sudden and material deterioration" qualify "productivity of more than one well" and
not "failure of wells, equipment or plant breakdown."3 Nor is the meaning of
"failure" and "full or partial interruption" immediately obvious. Take "failure of
wells". The words, in their everyday meaning, are capable of encompassing the
exhaustion of winnable gas in the wells as well as the breakdown or collapse of the
structure of wells or their otherwise becoming inoperable. It is not suggested that
"failure" has a particular meaning in the relevant industry.
3 A construction accepted by the parties.
-- 7 of 41 --
8
[9] In order to come within paragraph (h) any "deterioration in productivity" of wells
must be "unpredicted, sudden and material." It is thus apparent that mere
"deterioration in productivity" of wells does not constitute "failure of wells". Nor
can the inability of wells to ever produce sufficient quantities of gas to warrant their
use as producing wells constitute "failure". Paragraph (h) is concerned with
something happening to or in respect of supplying wells, other than "deterioration in
productivity," which interrupts the flow of gas.
[10] To "interrupt" something which is occurring is normally to stop it temporarily. The
Compact Oxford Dictionary new edition defines "interrupt" as, inter alia, "to break
in upon; to break the continuity (of something) in time; to break off; to hinder the
course or continuity of, cause to cease or stop." Here the words "full or partial"
before "interruption of the delivery of Gas" suggest that an "interruption" of
delivery may be a complete suspension or merely a reduction of supply, albeit a
temporary one. However, the word "interruption", even when prefaced by "partial"
is not apt to describe any diminution in supply, however slight. The context also
makes that conclusion apparent. The parties had in mind an event or circumstance
which would interrupt supply to such an extent that the operation of Clause 14.1
would be triggered.
[11] The object of contractual construction is to "ascertain and give effect to the
intentions of the contracting parties".4 The meaning of contractual terms "is to be
determined by what a reasonable person would have understood them to mean".5
The words under consideration take colour not merely from the remainder of
paragraph (h) but from the context in which they are found. As Gibbs J explained
in Australian Broadcasting Commission v Australasian Performing Right
Association Ltd:6
"It is trite law that the primary duty of a court in construing a written
contract is to endeavour to discover the intention of the parties from
the words of the instrument in which the contract is embodied. Of
course the whole of the instrument has to be considered, since the
meaning of any one part of it may be revealed by other parts, and the
words of every clause must if possible be construed so as to render
them all harmonious one with another."
[12] As events within paragraph (h) are Force Majeure Events and activate the operation
of Clause 14.1, it is necessary to consider what light, if any, the provisions of
Clause 14 throw on the meaning of paragraph (h).
[13] The appellants contend that Clause 14.1.1 should not be construed as requiring the
issuing of a notice before the event of force majeure relied on actually interrupts the
delivery of gas under the Agreement. The reason advanced was that it is only when
interruption of delivery occurs that Dawson could not do "absolutely or in part,
something it has to do under this Agreement (the 'Affected Obligation')". It was
submitted that as the effect of the Notice is that the Affected Obligation is
suspended "from the date the Notice is given (Clause 14.1.2), it would make no
commercial sense if the Affected Obligation was suspended before there was any
interruption of the delivery of gas under the Agreement. Additionally, it was
submitted that the fact that some of the particulars required to be included in the
4 Homburg Houtimport B.V. v Agrosin Private Ltd (The “Starsin”) [2004] 1 AC 715 at 737.
5 Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165 at [40].
6 (1973) 129 CLR 99 at 109.
-- 8 of 41 --
9
Notice could not be given if no obligation of Dawson's had been affected at the date
of the Notice shows that there is no necessary link between the happening of a
Force Majeure Event and the requirement to give notice.
[14] The submissions ignore the language of Clause 14.1 which directs that "If a Force
Majeure Event occurs, Dawson must without delay issue a Notice" to the
respondent. The Notice must: set out the "Affected Obligation" i.e. what it is that
Dawson is obliged to do under the Agreement but cannot do; estimate the reduction
in the gas able to be supplied, where gas supply is affected; and, in such a case,
estimate the duration of its inability to supply the full amount of gas required. The
particulars assume the existence of an "Affected Obligation", as does Clause 14.1.2.
Under Clause 14.1.2 the "Affected Obligation" is suspended from the giving of the
notice until Dawson is able to resume supply "after the exercise of all reasonable
diligence … and the employment of all reasonable means to remedy or abate the
Force Majeure Event as expeditiously as possible …"
[15] The obligation on Dawson under Clause 14.7 to "make reasonable efforts to place
itself in a position to perform the Affected Obligation" is imposed "During the
Suspension Period" which commences on the date the Notice is given. Clause 14.8
also applies by reference to the Suspension Period. Clauses 14.1.1, 14.1.2, 14.7 and
14.8 assume that a notice will not be given under Clause 14.1.1 unless a "direct
Force Majeure Event" has resulted in an "Affected Obligation".
[16] Consequently, matters relied on to constitute a relevant "failure of wells" must be
such that the gas able to be delivered in consequence of the alleged failure becomes
less than the volume required to be delivered under the Agreement. Where the
amount able to be delivered before the failure is already less than that which
Dawson is contractually bound to deliver, the alleged failure must result in a further
reduction in the gas able to be supplied.
[17] The word "interrupts", particularly when regard is had to Clause 14.1, suggests that
there must be a direct temporal and causative connection between the alleged failure
and the interruption. Dawson can avail itself of its rights under Clause 14.1 only in
respect of a "direct Force Majeure Event."
[18] The appellants argued that because of the words "combination of events or
circumstances" in the definition of Force Majeure Event, paragraph (h) applies
where there are separate well failures at different times which combine to cause a
"full or partial interruption" in gas supply. The contention cannot be accepted. It
ignores the operation of the second paragraph (a) in the definition and the
considerations which support the existence of a temporal connection. Also, as the
respondent submits, paragraph (h) is an example of an event or circumstance, or
combination of events or circumstances, which comes within the definition. The
consequence of this is that the introductory words of the definition just quoted do
not apply to expand the operation of paragraph (h). This is not to say that the
balance of the introductory words, which impose qualifications on the events or
circumstances which meet the definition, do not apply. Although attracted to the
view that the words do apply so that their requirements must be met before Dawson
can have the benefit of an event within paragraph (h), I do not find it necessary to
decide the point.
[19] It is difficult to see how if, as the appellants contend, the words "any event or
circumstance, or a combination of events or circumstances" apply to paragraph (h)
the other introductory words of the definition do not also apply. If the introductory
-- 9 of 41 --
10
words of the definition apply, it is accepted by the appellants that they have not
satisfied their onus of proof and the appeal must fail.
[20] It was also argued on behalf of the appellants that there is "no necessary temporal
connection required by cl 14.1.1 between the relevant deterioration or failure of the
wells and Dawson being unable to do, absolutely or in part, something it has to do
under the Agreement." The word 'because' in the phrase 'because of a direct Force
Majeure Event' in Clause 14.1.1, it was submitted, requires only a causal
connection. That argument, it is said, is assisted because the events listed in
subparagraphs (f), (g), (l) and (j) are not events which would necessarily have an
immediate effect on the ability of Dawson to supply gas under the Agreement. This
argument fails to have sufficient regard to the provisions of Clause 14 which have
been explained in some detail earlier. It also fails to focus sufficiently on the
language of paragraph (h).
[21] Another argument put forward was that the Agreement did not require Dawson to
"curtail provision of Services" by invoking Clause 14.1.1 and the Agreement
provided for the payment of a Remedy amount in the event that there was a shortfall
in delivery of gas under the Agreement. The primary judge dealt with this argument
as follows:7
"However, on any view of the Agreement, the effect of a Force
Majeure Event must be disabling: it must have the result that
Dawson cannot, absolutely or in part, perform the Affected
Obligation, i.e. the obligation to supply gas. There is no choice
which Dawson is given to reduce or not to reduce the gas supply.
This is because cl 14 is engaged only where the agreed quantity
cannot be supplied. The words “[Dawson] may Curtail provision of
Services” are not a reference to alternative courses open to Dawson,
but instead mean that Dawson is permitted to not supply that which it
cannot supply because of the Force Majeure Event. The absence of
such a discretion is confirmed by the mandatory terms of the second
sentence of cl 14.1.1, whereby Dawson must without delay issue a
notice if a Force Majeure Event occurs."
I am in respectful agreement with those views.
[22] It is now necessary to consider the facts alleged by the appellants to invoke the
operation of paragraph (h). In their pleadings, the appellants relied on the facts and
circumstances set out in their notice under Clause 14.1.1. The Notice, couched in
vague terms, was as follows:8
'Gas Sales Agreement – Curtailment Notice
Moura Sales Pty Limited ABN 97 087 886 913 (Moura
Sales)hereby gives notice of Curtailment pursuant to clause
14.1.1 of the Agreement dated 28 February 2003 originally
entered between Moura Sales and Energex Retail Pty Limited
ABN 97 078 848 579 (Energex) as agent for Allgas Energy Ltd
ABN 54 009 656 446 (the Agreement).
In accordance with clause 14 of the Agreement, Moura Sales
advises:
7 AGL Sales (Qld) Pty Limited v Dawson Sales Pty Ltd & Ors [2009] QSC 8 at [38].
8 AGL Sales (Qld) Pty Limited v Dawson Sales Pty Ltd & Ors [2009] QSC 8 at [24].
-- 10 of 41 --
11
Affected Obligation
The Affected Obligations are the obligations of Moura Sales
under clause 5.4, clause 9.1.1, clause 9.3 and clause 10.
Particulars of the event
The particulars of the event, to the extent Moura Sales knows
them, are:
• In developing 15 new wells at Ridgedale, Moura Sales has
encountered unpredicted and substantial geological
problems;
• The geological problems are most prominently severe
structuring and faulting of lateral drill holes at various
levels;
• Structuring and faulting problems has caused both drilling
difficulties and closing of lateral drill holes at Ridgedale;
• Of 15 wells drilled at Ridgedale, 2 have been abandoned due
to the extent of the difficulties encountered with the loss of
the considerable cost of development of these wells;
• Due to the drilling difficulties and closing of lateral drill
holes, recovery of Gas from the Ridgedale wells has been
materially less than was forecast prior to the commencement
of development of these wells;
• Attempts to resolve the impacts of structuring and faulting
problems in accordance with obligations under the
Agreement, have been ongoing but not successful to date
and on current analysis may not be successful;
• Wells which have failed to produce to date may well have to
be abandoned depending on the outcome of ongoing
measures to remedy within the terms of the Agreement;
• The Ridgedale wells were developed following analysis of
the Gas field and particularly the Hillview wells;
• The Ridgedale wells were planned to come into production
to meet projected contractual obligations;
• The problems encountered in developing the Ridgedale
wells were unexpected and unpredicted, particularly having
regard to the geological information available to Moura
Sales at the time;
• Moura Sales has undertaken all stages of investigation and
development of the Ridgedale wells in accordance with
proven technology and practice as widely known to and
generally available for use in the gas industry;
• Moura Sales has expended approximately $15,000,000.00 in
developing the Ridgedale wells;
• For developed wells at Hillview, the Gas available for
recovery is less than initially predicted due to unexpected
difficulties in production;
-- 11 of 41 --
12
• Without limiting the above, the circumstances are such that
there has been an unpredicted, sudden and material
deterioration in productivity of more than one well and a
failure of wells;
• Moura Sales has exercised Good Engineering and Operating
Practice at all times;
• Moura Sales has sought to act in good faith to comply with
its contractual and other obligations by the expenditure of
reasonable sums of money and the application of proven
technology widely known to and generally available for use
by persons in the gas industry.
The events and circumstances are beyond the control of Moura
Sales.
Moura Sales has not been able to overcome these events
notwithstanding the exercise of Good Engineering and Operating
Practice and seeking in good faith to comply with its contractual
and other obligations by the expenditure of reasonable sums of
money and the application of proven technology widely known
to and generally available for use by persons in the gas industry.
Estimate of reduction in service capacity
Moura Sales estimates the reduction in Service capacity of 8,000
Gj per Day and in particular amends the MDQ to 10,000 Gj per
Day over the Suspension Period.
Estimate of duration
Moura Sales estimates the duration of its inability to perform the
Affected Obligations as 14 months from the date of this notice.
We reserve all other rights, remedies and claims under the
Agreement and this notice is in addition to and without prejudice
to any such rights, remedies or claims."
[23] The Notice described difficulties encountered with the wells developed in the
Ridgedale Field and, although it did not say so expressly, it implied that the inability
to supply arose because less than the predicted quantities of gas were able to be
produced from the Ridgedale wells. It was asserted, somewhat obscurely, that:
"For developed wells at Hillview, the Gas available for recovery is
less than initially predicted due to unexpected difficulties in
production."
There was then the assertion: "Without limiting the above, the circumstances are
such that there has been an unpredicted, sudden and material deterioration in
productivity of more than one well and a failure of wells."
[24] The fact that Dawson was unable to meet its gas supply obligations because the
Ridgedale wells never produced gas in quantities sufficient to enable it to do so,
does not give rise to an event within paragraph (h). Although the introductory
words of the Force Majeure Event definition may apply in such circumstances, it
could not be said that a general and prolonged failure of this kind "interrupted" the
delivery of gas.
-- 12 of 41 --
13
[25] The primary judge observed of the Notice:9
"The generality of this Curtailment Notice, and of the defendants’
submissions as to what constitutes the Force Majeure Event, results
from these flaws in their case. They have failed to identify a certain
occurrence, in the sense of an event or circumstance, or events or
circumstances acting in combination, having an immediate
consequence upon Dawson’s performance at that point in time."
[26] It was noted that in their pleadings that the appellants did not specify what it was
that constituted the Force Majeure Event and that in their final submissions the
appellants put the matter in the following terms:
"76. The Defendants’ primary submission is that the failure of more
than one well (subparagraph (h)) was a sufficient event or
circumstance to satisfy the definition of a Force Majeure Event.
77. Alternatively, the definition of Force Majeure Event is satisfied
by:
(i) the failure of more than one well and/or the unpredicted, sudden
and material deterioration in productivity of more than one well;
(ii) the presence of low angle thrust faulting, shearing of the coal
within the seams and/or the presence of coal fines within the seams,
either alone or in combination with the events and circumstances
described above; or
(iii) encountering low angle thrust faulting, shearing of the coal
within the seams and/or the presence of coal fines within the seams,
either alone or in combination with the events and circumstances
above."
[27] The primary judge further explained the case presented by the appellants at first
instance as follows:10
"In their case, the defendants have not attempted to identify an
occasion which represents an interruption in the delivery of gas. Nor
have they sought to prove the extent of the diminution in Dawson’s
capacity from, in aggregate, the failures of certain wells; other than
perhaps by reference to Dawson’s forecasts of production. Even
then, these alleged failures would not account for the 8 TJ/day by
which the MDQ was purportedly reduced by the Curtailment Notice
…"
[28] Another difficulty with the appellants’ case, identified by the primary judge, was
that the "deterioration in productivity" of the wells in the Ridgedale Field was based
on a comparison of actual production against forecast production. The primary
judge pointed out that "deterioration in productivity in paragraph (h) required a
comparison of actual productivity at two points in time, not a comparison of
forecast productivity with actual productivity". Counsel for the appellants made a
last ditch attempt, on the hearing of the appeal, to establish that on the trial the
appellants had proved an "unpredicted, sudden and material deterioration in
9 AGL Sales (Qld) Pty Limited v Dawson Sales Pty Ltd & Ors [2009] QSC 8 at [43] – [44].
10 AGL Sales (Qld) Pty Limited v Dawson Sales Pty Ltd & Ors [2009] QSC 8 at [44].
-- 13 of 41 --
14
productivity of more than one well". This was done by reference to the
deterioration in production of wells RG1, RG8, RG10, RG12 and RG14 over
different selected periods.
The following table shows the periods selected, well production at the
commencement and conclusion of each period and the percentage by which
production declined over the selected periods:
[29] The period selected for RG8 was the 20 day period from 19 June 2007 to 9 July
2007 and the preceding 20 day period from 29 May 2007 to 19 June 2007. There
was no material deterioration in production in the later period compared with the
earlier. Reliance was placed, however, on a 27 per cent decline in daily average
production between 1 January 2007 to 19 June 2007. No evidence was pointed to
with a view to establishing that this decline was unpredicted. Nor could the decline
be regarded as "sudden". Reference to RG8 thus does not assist the appellants’
case, even if it was permissible to look at this one well in isolation.
[30] The decline in production of RG14, like all of the other declines, was not
established to be "unpredicted" and the figures produced do not establish that the
decline in production relied on was either "sudden" or "material". The well
produced 0.1924 TJ on 9 July. It had produced between 0.1 and 0.2 TJ per day in
April 2007. The figures for this and the other wells must be considered in light of
-- 14 of 41 --
15
the evidence that production from wells was capable of fluctuating significantly and
could be expected to diminish over time.
[31] The reasons note that production from RG1 gradually declined after March/April
2006 and that production continued to decline in 2007 "at least until the end of June
2007". The primary judge pointed out also that there was no evidence of its output
from 9 to 24 July 2007. The primary judge was unable to be satisfied that there was
any sudden and material decrease which interrupted, in part, the delivery of gas in
the sense of paragraph (h). None of the evidence referred to by counsel for the
appellants falsified this conclusion.
[32] The reasons point out there was no evidence of production from RG10 in June 2007
or for RG12 from 3 to 8 July 2007. Both wells were in production on 9 July 2007.
As the primary judge noted, the July production figures for RG10 "were generally
higher than they had been for most of its life." The primary judge traced the
production history of RG12 and concluded that production had declined from 20
November 2006 "but not suddenly". On the date of the Notice, RG12 produced
0.222 TJ and this was after cessation of production for five days. Again, the
evidence relied on by counsel for the appellants does not demonstrate any error in
the primary judge's findings that no sudden deterioration in productivity was
established for RG10 and RG12.
[33] The appellants therefore failed to demonstrate that the primary judge should have
found an "unpredicted, sudden and material deterioration in productivity of more
than one well." The appellants have thus failed to establish an "unpredicted, sudden
and material deterioration in productivity of more than one well." They failed also
to show any relevant "failure of wells". There is another reason why the ground
under consideration cannot succeed. The arguments just considered were not part of
the case advanced before the primary judge which the respondents were called on to
meet. Senior counsel for the respondent submitted, and I accept, that had such a
case been advanced, there were matters which the respondent would have wished to
investigate and in respect of which it may have adduced further evidence. The
appellants cannot now be permitted to change the course of their argument so
substantially.
Was there a valid or effective Force Majeure Notice?
[34] The primary judge held that Dawson did not give the Notice without delay but
found it unnecessary to decide whether the delay rendered the Notice ineffective.
Whether delay in issuing a notice under Clause 14.1 after the occurrence of a Force
Majeure Event renders the Notice ineffectual depends on the proper construction of
that clause. Considerations which support the conclusion that delay in issuing a
notice does not have an invalidating effect are:
(a) Clause 14.1.2, which provides for the suspension of the "Affected
Obligation", is not expressed to be conditional upon the giving of the Notice
"without delay".
(b) "The generality of the words 'without delay' tells against [the respondent's]
contention: if a condition were intended a definite time limit would be more
likely to be set."11
11 See Bremer Handelsgesellschaft Schaft M.B. H. v Vanden Avenne Izegem P.V.B.A. [1978] 2 Lloyd’s
Rep 109 per Lord Wilberforce at 113.
-- 15 of 41 --
16
[35] The matters which support the contrary conclusion are:
(a) The "Affected Obligation" is suspended from the date the Notice is given,
not from the date of the Force Majeure Event (Clause 14.1.2);
(b) The suspension continues to operate until Dawson, exercising reasonable
diligence and employing all reasonable means to remedy or abate the Force
Majeure Event as expeditiously as possible, is able, "after the exercise of
all reasonable diligence, Good Engineering and Operating Practice", to
perform the Affected Obligation.12
(c) Dawson's obligation under Clause 14.7, to "make reasonable efforts to
place itself in a position to perform the Affected Obligation" only exists
during the "Suspension Period";
(d) The right to terminate given by Clause 14.8 is exercisable only by reference
to the term of the suspension period;
(e) The requirement in Clause 14.1.1 that the Notice must set out the Affected
Obligation; particulars of the Force Majeure Event; an estimate for the
reduction in Service capacity, in particular amending the MDQ … over the
Suspension Period; and estimate the duration of the inability to perform
the Affected Obligation.
[36] An obvious purpose of the particulars required to be specified in the Notice is to
inform the respondent promptly of the likely extent and duration of the interruption
to the supply of gas under the Agreement to enable it to take whatever steps might
be available to it to minimise the damage, if any, likely to be caused by the
interruption. Other such purposes are to enable the Notice to provide a timely basis
for co-operation between the parties in minimising the adverse consequences of the
shortfall and to provide a basis upon which the respondent can act in order to assess
whether Dawson is complying with its obligations under Clause 14.1.2, or in
determining whether there may be cause to consider the application of Clause
14.1.3.
[37] If the obligation to issue a notice without delay is not a requirement of a valid notice
and failure to comply merely gives rise to a claim for damages for breach of
contract, the purpose of the Notice and of the particulars will be substantially
defeated. Not only that, but by being free to select the timing of the Notice,
Dawson would have the ability to determine when it was to assume obligations
under Clauses 14.1.2 and 14.7. Dawson would also have the potential to select the
three month period specified in Clause 14.8 so as to influence the reduction in MDQ
which best suited its interests. It is surely unlikely that, having regard to the
considerations just discussed, the contractual intention would have been that a
notice not given in a timely way would nevertheless be effective. In my view the
Notice was of no legal effect.
[38] Another argument advanced by the respondent was that the Notice was defective for
want of particularity. Again, the primary judge found it unnecessary to determine
this question. It is unnecessary for this Court to decide the question and in view of
my conclusion that the Notice was ineffective, nothing will be served by a
consideration of a further ground of invalidity.
12 Gas Sales Agreement Cl 14.1.2.
-- 16 of 41 --
17
Did the appellants discharge their onus of proof under Clause 14.8?
[39] The appellants challenged the primary judge's conclusion that the appellants failed
to prove "the average quantity of Gas unable to be delivered" within the meaning of
Clause 14.8 of the Agreement. The appellants argued at first instance and on appeal
that where a Force Majeure Event occurred, Dawson was relieved of any liability
for the entire shortfall in its supply rather than, as the primary judge held, the
shortfall constituted by the gas which could not be delivered because of the Force
Majeure Event. The construction favoured by the appellants could not conceivably
accord with the contractual intention of the parties: it would be capable of
producing bizarre results quite unconnected with the conventional operation of a
Force Majeure provision. If, for example, Dawson had consistently been supplying
only one-half of the gas required to be supplied under the contract prior to a Force
Majeure Event which reduced the quantity able to be supplied by Dawson by a
further one-tenth of the contracted volume, Dawson may be entitled under Clause
14.8 to reduce the MDQ by 60 per cent. That would be so even if Dawson's
inability to deliver the one-half was caused by matters which did not attract the
operation of the Force Majeure provisions. The primary judge's conclusion in this
respect was plainly right.
Conclusion
[40] For the above reasons, I agree that the appeal should be dismissed with costs. I also
agree that, for the reasons given by Fraser JA, Dawson's appeal against the costs
orders should be dismissed.
[41] FRASER JA: I have had the advantage of reading the reasons for judgment of Muir
JA and Chesterman JA concerning the substantive appeal (CA 2520 of 2009). I
gratefully accept and will not repeat their Honours’ expositions of the factual
background, material contractual provisions, and issues at trial and in the appeal.
[42] I agree with Muir JA’s reasons for the conclusion that the substantive appeal should
be dismissed with costs. I also agree with Chesterman JA’s conclusion that a
further ground on which this appeal should be dismissed is that, on the proper
construction of the Gas Supply Agreement, the general requirements in the
introductory words of the definition of “Force Majeure Event” must be satisfied if
any of the things described in paragraph (h) of that definition is to qualify as such an
event. (The appellants accepted that their appeal must fail if that construction were
adopted.) My principal reasons for preferring that construction are that it is the
natural and literal meaning of the contractual text and it makes commercial sense (a
topic upon which Chesterman JA has elaborated), but I also record my specific
agreement with paragraphs 72-76 and 81-89 of Chesterman JA’s reasons.
[43] The substantive appeal was brought by the defendants against a judgment in favour
of the plaintiff after a 20 day trial.13 The trial judge subsequently heard argument
about costs and on 7 April 2009 ordered that the defendants pay the plaintiff’s costs
of the proceedings, including any reserved costs to be assessed.14 On the same day,
the trial judge granted an application by the defendants for leave to appeal against
that costs order pursuant to s 253 of the Supreme Court Act (Qld) 1995. What
follows are my reasons for concluding that this costs appeal should be dismissed.
13 AGL Sales (Qld) Pty Ltd v Dawson Sales Pty Ltd & Ors [2009] QSC 8.
14 AGL Sales (Qld) P/L v Dawson Sales P/L & Ors (No 2) [2009] QSC 75.
-- 17 of 41 --
18
[44] The defendants' contention before the trial judge was that the plaintiff should have
no more than 20 per cent of its costs assessed on the standard basis. The defendants
argued that most of the trial was unnecessarily taken up with factual issues relating
to "Good Engineering and Operating Practice" (the expression in the Gas Supply
Agreement, in the introductory, general words of the definition of "Force Majeure
Event" and in cl 14.13) and that the plaintiff was unsuccessful in much of that
contest.
[45] I will summarise the trial judge's reasons for rejecting that argument:
(a) First, the trial judge concluded that the plaintiff was not unreasonable
in presenting a case which was wider than was necessary for the
interpretation of the Gas Sales Agreement upon which the plaintiff
succeeded. The trial judge’s reasons for that conclusion were as
follows:
(i) Whilst the plaintiff succeeded on the basis of an
interpretation of the contract which made the factual enquiry
about Good Engineering and Operating Practice unnecessary,
had the defendants' arguments as to the interpretation of cl 14
and the definition of “Force Majeure Event” been upheld, the
plaintiff would have had to advance the case that it was the
defendants' fault that they could not supply gas in accordance
with the contract requirements.
(ii) Although the plaintiff failed on many components of its case
about Good Engineering and Operating Practice, the plaintiff
succeeded on what was probably its principal argument,
which was that the defendants had failed to undertake proper
exploration at Ridgedale. Depending upon who bore the onus
of proof that might have been sufficient for the plaintiff to
succeed (had it failed on its interpretation argument). On the
trial judge's findings,15 the incidence of the burden of proof
depended not only upon the proper interpretation of the
definition of Good Engineering and Operating Practice, but
also upon whether the alleged force majeure event was within
the general words of the definition and not within the specific
inclusion of paragraph (h). Accordingly, the factual enquiry
might have been decisive in the plaintiffs' failure even if the
plaintiff was not able to prove that the defendants' failures to
employ good practice were a cause of its inability to supply
gas.
(iii) As to the components of the plaintiff’s case about Good
Engineering and Operating Practice upon which the plaintiff
failed, there was no suggestion that they were advanced in
bad faith or that they were so irrelevant to the real issues as to
warrant some special order as to costs.
(b) Secondly, the trial judge concluded that the plaintiff was not
unreasonable in failing to apply for summary judgment upon the
basis of its propounded interpretation of the Gas Supply Agreement.
15 [2009] QSC 8 at [73].
-- 18 of 41 --
19
The trial judge reasoned that it was not unreasonable for the plaintiff
instead to proceed to trial because:
(i) The plaintiff would have had considerable difficulties in
seeking summary judgment at an early stage of the
proceedings because it then did not know much of the
relevant facts, including which were the wells involved in the
force majeure event asserted by the defendants, what had
been the history, and whether there had been any
simultaneous failure of wells.
(ii) Whilst it is possible that a late application for summary
judgment might have been made after disclosure, the trial
judge might or might not have been persuaded to hear a late
summary judgment application, given that it might have
taken more than a day to hear and it might have delayed the
ultimate determination of the proceeding by the prospect of
an appeal.
[46] The trial judge applied the principle which his Honour had earlier formulated in
BHP Coal Pty Ltd and Ors v O & K Orenstein & Koppel AG and Ors (No 2),16 that
ordinarily the fact that a successful plaintiff fails on particular issues does not mean
that the plaintiff should be deprived of some of its costs, although it may be
appropriate to award costs of a particular question or part of a proceeding where that
matter is definable and severable and has occupied a significant part of the trial.17
The trial judge observed that the plaintiffs’ arguments about good engineering and
operating practice were analogous to a common law claim in negligence, in which a
plaintiff usually does not lose some of its costs where it succeeds in proving
negligence in some but not all respects: as McHugh J explained in Oshlack v
Richmond River Council:18:
"The primary purpose of an award of costs is to indemnify the
successful party. If the litigation had not been brought, or defended,
by the unsuccessful party the successful party would not have
incurred the expense which it did."
[47] The correctness of the principle applied by the trial judge is not in issue in this
appeal. The defendants do not contend that the trial judge misapprehended the
correct principle: indeed, in their written outline of submissions they endorse the
principle in the terms in which the trial judge expressed it.
[48] Rather, the grounds specified in the notice of appeal are simply that the trial judge
erred in reaching the two conclusions I have mentioned, that the plaintiff was not
unreasonable in presenting a case wider than was necessary to interpret the Gas
Sales Agreement and that the plaintiff was not unreasonable in failing to apply for
summary judgment. The notice of appeal goes on to assert that the trial judge erred
in concluding that there was no demonstrated basis for departing from the ordinary
rule as to costs, but that adds nothing to the two earlier grounds, which are
themselves pitched at such a high level of generality as to be of no real assistance in
identifying the particular error for which the defendants contend.
16 [2009] QSC 64.
17 [2009] QSC 64 at [8], adopting the words of Brereton J in Waterman v Gerling Australia Insurance
Co Pty Ltd (No 2) [2005] NSWSC 1111 at [10].
18 (1998) 193 CLR 72 at 97.
-- 19 of 41 --
20
[49] Ordinarily, the questions to be agitated in an appeal brought by leave against a
discretionary costs order would be identified in the primary judge’s reasons for the
grant of leave. The Court does not have the benefit of a transcript of the trial
judge’s reasons for granting leave, but it was asserted both in the amended notice of
appeal and in oral submissions that the trial judge accepted the defendants’
argument that it was appropriate for leave to be given because of the defendants'
appeal against the substantive judgement.
[50] It appears then that this was not an appropriate case for the grant of leave to appeal.
After reviewing the relevant authorities, Chesterman J observed in Emanuel
Management Pty Ltd (in liquidation) & Ors v Foster's Brewing Group Ltd & Ors
and Coopers & Lybrand & Ors19 that:
". . . the cases make it clear that leave should not be given unless
there is an arguable case that, applying the principles of House v The
King the discretion will be overturned on appeal. That means there
must be an arguable case that the judge committed an error of law, or
misapprehended the facts or that the result is inexplicably
inconsistent with the facts."
[51] The mere fact of an appeal against a substantive order is not a ground for the grant
of leave to appeal against a discretionary costs order which was made
consequentially upon the substantive order. Where an appeal against a substantive
order succeeds leave is not required for this Court to exercise its own discretion as
to any appropriate, consequential revision of the costs order, but such leave is
required where the substantive appeal fails.20 The rationale for the usual
requirements for the grant of leave to appeal is as applicable in the latter case as it is
where there is no appeal against the substantive order. Mackenzie J pointed this out
in Di Carlo v Dubois21:
"[4] Although there will be occasional cases where leave to
appeal becomes otiose because the appeal against the
substantive judgment succeeds, with consequent setting
aside or varying of the order for costs, the requirement that
leave be obtained in case the substantive appeal fails is
logically based. The appeal in a case where consequential
setting aside or varying of the costs order occurs is
conceptually different from an appeal against an exercise of
discretion. Once the appellant must establish grounds for
setting aside a discretionary judgment, there is no reason to
distinguish between a case where the issue becomes of that
kind because a substantive appeal is dismissed and one
where no issue is taken with the substantive judgment but it
is alleged that the costs order is erroneous in principle.
[5] The requirement that leave be obtained implies, firstly, that
leave is not given merely for the asking. By analogy with
other instances where leave to appeal is necessary, a
plausible basis for arguing that there are some prospects of
19 [2003] QSC 484 at [41].
20 Thorpe Nominees Pty Ltd v Henderson & Lahey [1998] 2 Qd R 216; Re Golden Casket Art Union
Office [1995] 2 Qd R 346.
21 [2004] QSC 041 at [4]-[5].
-- 20 of 41 --
21
success must be demonstrated. Secondly, because the
judgment as to costs is a discretionary judgment it would be
necessary to identify some prospect of success on an
argument that there was a demonstrable error in principle, or
on an argument that the order was so unreasonable that it
could not have been properly made."
[52] The grant of leave to appeal against the costs order did not relieve the defendants of
the burden of establishing, not merely that the judges of the Court of Appeal might
have formed a different view from that of the trial judge, but that the trial judge
made an error in the exercise of the discretion of the kind described in House v The
King.22 The defendants have failed even to identify, much less to establish, an error
of that character. The defendants’ written outline of argument, which was not
elaborated upon orally, merely asserted that the trial judge erred in the manner
described in the broad grounds of appeal. The argument did not identify any
asserted error of principle or which, if any, aspect of the trial judge’s reasons for the
challenged conclusions were said to be wrong or why. Nor did the defendants argue
that the result was so unreasonable as to justify the conclusion that the discretion
must have miscarried. In short, the defendants have not demonstrated any arguable
error in the trial judge’s reasons for concluding that the costs order was a proper
application of the principles stated by his Honour and the validity of which the
defendants accept. There is thus no reasonable basis for a conclusion that the
discretion miscarried.
[53] I would dismiss the defendants’ appeal against the costs orders (CA 4390 of 2009).
[54] CHESTERMAN JA: The appellants (collectively “Dawson”) were the defendants
in an action heard in the Commercial List. The respondent (“AGL”) was the
plaintiff which obtained a declaration that:
“The matters set out in the letter from (Dawson) to (AGL) dated 9
July 2007 do not constitute a Force Majeure Event as defined under
the Gas Sale Agreement ... and do not entitle (Dawson) to curtail the
supply of gas (in whole or in part) under clause 14 of that
Agreement.”
[55] The facts out of which the dispute arose were succinctly identified by the trial
judge:
“[1] The plaintiff (“AGL”) purchases coal seam gas from the
first defendant (“Dawson”). The gas is extracted from the
Moura Coal Mine and is supplied to AGL under a written
contract made in February 2003. Dawson contracted to supply
the gas on behalf of the owners of the mine who are the second
and third defendants.
[2] The parties are in dispute as to the amount of gas which must be
supplied under the Agreement. It provides for the supply of
certain quantities, but it also provides that in some
circumstances, described as a “Force Majeure Event”, Dawson
may supply less gas.
[3] Dawson says that it has encountered unforeseen difficulties in
extracting gas at Moura, due to the particular geology of part of
22 (1936) 55 CLR 499.
-- 21 of 41 --
22
its field, and that the relevant events and circumstances
constitute a Force Majeure Event. In July 2007 Dawson
purported to temporarily reduce its supplies pursuant to the
force majeure provisions of the Agreement. In December 2007
it purported to permanently reduce its supplies.
[4] AGL says that for several reasons, these provisions have no
operation in the circumstances which have occurred and that
Dawson is in breach of the Agreement by failing to supply the
quantities originally agreed. It claims that there has been no
Force Majeure Event, that Dawson did not follow the
requirements of the Agreement in giving its notices reducing its
supplies and that in any case, by reason of the terms of the force
majeure provisions, Dawson is precluded from relying upon the
suggested Force Majeure Event because, in effect, it is
Dawson’s fault that it has been unable to extract sufficient gas.
That last matter has resulted in an extensive factual inquiry
within this trial. Otherwise the questions are ones of the proper
interpretation of the Agreement for which the relevant facts are
largely undisputed.”
[56] His Honour then identified the relevant terms of the gas sale agreement
(“Agreement”) and explained their significance:
“[5] The Agreement was made in February 2003 between Energex
Retail Pty Ltd as buyer and Dawson, then called Moura Sales
Pty Limited, as seller. In 2006, AGL was substituted as the
buyer.
[6] The Agreement was for an initial term expiring on
1 January 2008, with options to the buyer to extend for a further
five years and then a further two years. AGL has extended the
term so that at present, it is to expire on 1 January 2013.
[7] The quantity of gas to be delivered is to be no more than the
“Maximum Daily Quantity” (or “MDQ”), as specified in a
schedule to the Agreement. The agreed MDQ was initially
3,000 gigajoules per day, gradually rising to 11,000 per day in
the 2006 calendar year, 16,000 per day in the next 16 months
and from 1 May 2007, 18,000 gigajoules per day.
[8] Within those upper limits, the quantity of the gas to be
delivered is according to what is “nominated” by the buyer.
Clause 10.1 provides that the buyer may nominate any quantity
of gas for delivery on any day, provided that the seller is not
obliged to deliver more than the MDQ. The buyer is to submit
various forecasts (monthly, weekly and daily forecasts) of its
requirements. The daily forecast, described as the “Daily
Nomination”, is a notification of the buyer’s required amount of
gas to be delivered on the following day. Dawson is permitted
to deliver day by day a quantity within a certain range of the
Daily Nomination. However, each month it must supply the
sum of the Daily Nominations for that month. By cl 5.1.2,
Dawson is not required to supply gas other than from that area
-- 22 of 41 --
23
defined as the “Gas Field”. Accordingly, it was not obliged to
make up any shortfall by buying gas from other fields.
[9] Regardless of what is nominated by the buyer, it is obliged to
pay for a certain minimum quantity. In effect, the buyer has to
pay for at least 80 percent of the aggregate of the MDQs for
that month.
[10] As it was likely that the buyer would require at least the
quantity for which it was in any event obliged to pay, in
practical terms Dawson knew that it had to supply, over time, at
least 80 percent of the MDQ and that it had to be prepared to
supply, if required, the whole MDQ. That affected, or should
have affected, Dawson’s program for the exploration and
extraction of this gas. The adequacy of that program and its
implementation was a matter of considerable evidence and
debate, to which I will return.”
[57] Clause 14 of the Gas Sale Agreement (“Agreement”) is of particular importance. It
provided:
“14. CURTAILMENT
14.1 Curtailment by Moura Sales for Force Majeure
14.1.1 (Dawson) may Curtail provision of Services if,
because of a direct Force Majeure Event, it cannot
do, absolutely or in part, something it has to do under
this Agreement (the “Affected Obligation”), when it
has to do it. If a Force Majeure Event occurs,
(Dawson) must without delay issue a Notice to
(AGL) setting out:
a) what the Affected Obligation is;
particulars of the event (to the extent (Dawson)
knows them);
b) its estimate of the reduction in Service capacity,
in particular amending the MDQ under this
Agreement over the Suspension Period; AND
c) its estimate of the duration of its inability to
perform the Affected Obligation.
14.1.2 The Affected Obligation is suspended from the date
the Notice is given until (Dawson) is able, after the
exercise of all reasonable diligence, Good
Engineering and Operating Practice and the
employment of all reasonable means to remedy or
abate the Force Majeure Event as expeditiously as
possible, to perform the Affected Obligation (this
period is the “Suspension Period”).
14.1.3 A Force Majeure Event or circumstances affecting
the performance under this Agreement by (Dawson)
-- 23 of 41 --
24
shall not relieve (Dawson) of liability in the event,
and to the extent, that the negligence or failure to use
Good Engineering and Operating Practice by
(Dawson) or the Coal Mine Owners caused or
contributed to its failure to perform under this
Agreement or in the event of its failure to use all
reasonable endeavours including the expenditure of
reasonable sums of money and the application of
proven technology to remedy the situation and to
remove the event or circumstances giving rise to the
Force Majeure Event in an adequate manner with all
reasonable despatch.
...
14.5 Notice when the Suspension Period ends
Upon completion of Maintenance activities under clause 14.3,
or as soon as the Suspension Period under clause 14.1 ends,
(Dawson) must, as soon as reasonably practicable, issue a
Notice to (AGL). The Suspension Period ends when
(Dawson), making reasonable efforts, is able to perform the
obligation again, not when it gives the Notice.
...
14.7 Affected Party must rectify the situation if possible
During the Suspension Period (Dawson) must make
reasonable efforts to place itself in a position to perform the
Affected Obligation (but (Dawson) is not obliged to settle any
strike, lock out, boycott, work ban or other labour dispute or
difficulty).
14.8 Termination
If the Suspension Period lasts for more than 3 months, neither
Party can terminate this Agreement, but either Party may,
upon the expiry of that 3 months period, by Notice in writing
to the other Party reduce the MDQ by the average quantity of
Gas unable to be delivered or utilised on a Day over the
Suspension Period and the Parties respective obligations under
this Agreement will apply to that reduced MDQ for the
remainder of the Term, effective immediately on Notification.
The Authorised Officers of both Parties shall implement any
necessary changes to MDQ pursuant to this clause by
endorsing a variation to Schedule 2.”
[58] Force Majeure Events are defined in a schedule to the Agreement. The definition is:
““Force Majeure Event” means any event or circumstance, or
combination of events or circumstances, not within the control of a
Party, and which by the exercise of Good Engineering and Operating
Practice, and seeking in good faith to comply with its contractual and
other obligations by the expenditure of reasonable sums of money
-- 24 of 41 --
25
and the application of proven technology widely known to and
generally available for use by persons in the gas industry, that Party
is not able to prevent or (for the time being) overcome, including,
without limiting the generality of the foregoing:
(a) an act of God including, but not limited to, landslide,
earthquake, flood, wash-out, lightning, storm and action of the
elements;
(b) strike, lock-out, ban or other industrial disturbance;
(c) act of a public enemy, terrorism, war, sabotage, blockade or
insurrection, riot or civil disturbance, arrests and restraints of
rulers and peoples;
(d) fire or explosion including radio-active and toxic explosion;
(e) epidemic or quarantine;
(f) order of any court or tribunal or the order, act or omission or
failure to act of any government or Government Agency having
jurisdiction;
(g) failure to obtain or retain any necessary consent or approval of
a Government Agency (despite timely and reasonable
endeavours to obtain same);
(h) unpredicted, sudden and material deterioration in productivity
of more than one well or failure of wells, equipment or plant
breakdown or failure that causes full or partial interruption of
the delivery of Gas by (Dawson) under this Agreement;
(i) the total or partial inability of a Party to receive or have
quantities of Gas which are available for supply or delivery
transmitted through the Queensland Gas Pipeline or the Moura
Mine Pipeline because of an event of Force Majeure excusing
non-performance by the owners or operators of the Queensland
Gas Pipeline or the Moura Mine Pipeline, as the case may be,
under a clause in a relevant gas transportation agreement;
(j) shortages of labour or essential materials, failure to secure
contractors and delays of contractors;
(k) any breach of contract by, or an event of Force Majeure
affecting a person contracting with (AGL) (‘Third Party
Contractor’), which prevents (AGL) doing something that it has
to do under this Agreement where (AGL) has taken all
necessary, reasonable and practical action within a reasonable
time to obtain performance of the Third Party Contractor’s
relevant obligation whether by the Third Party Contractor or
another person; OR
(l) any order, direction, or requirement under laws relating to
Aboriginal heritage or native title;
but does not include:
-- 25 of 41 --
26
(a) full or partial interruption of the delivery of Gas by (Dawson)
due to failure or unpredicted and sudden deterioration in
productivity of a single well, or the failure or breakdown of a
single piece of equipment or plant, including compressors,
pumps, Gas measurement equipment, and gathering lines;
(b) full or partial interruption of the delivery of Gas by (Dawson)
due to failure or unpredicted and sudden deterioration in
productivity of a single dehydration unit if such failure or
unpredicted and sudden deterioration could have been
prevented by the exercise of Good Engineering and Operating
Practice;
(c) (AGL’s) loss of customers, loss of market share or reduction in
demand for Gas;
(d) a Party’s lack of funds or inability to obtain or use funds; OR
(e) changes in market conditions relevant to the transportation
and/or the purchase and sale of Gas.”
[59] The trial judge noted these further facts:
“[30] When the Agreement was made in 2003 Dawson was
extracting gas from a parcel of land ... called Hillview. ...
wells have a limited life ... And having regard to the
increasing MDQ during the life of the Agreement, Dawson
well knew that it would have to drill wells beyond Hillview
in order to meet its commitments.
[31] ... Ridgedale is alongside Hillview. Dawson commenced
exploratory work on Ridgedale at the end of 2004. The first
of the production wells on Ridgedale was drilled by 13 June
2005 and began to produce gas from December 2005.
Dawson attempted to drill 15 production wells in Ridgedale.
Two ... did not produce any gas. ... five ... produced some
gas but their production had ceased by the time of the
Curtailment Notice in July 2007. The other wells were still
producing then, although in each case ... production had
been less than ... expected. So each of these 15 wells was
either never productive or was less productive than ...
forecast. In each case the problem is said to have been the
difficult and unforeseen geological conditions ...
encountered.”
[60] Dawson contends that the difficulties it encountered in extracting gas from the
Ridgedale wells constituted an FM Event as defined and that it was accordingly
entitled to curtail the supply of gas required under the Agreement. It gave a
Curtailment Notice to AGL by letter dated 9 July 2007, which read:
“Gas Sales Agreement – Curtailment Notice
(Dawson) hereby gives notice of Curtailment pursuant to clause
14.1.1 of the Agreement dated 28 February 2003 originally entered
between (Dawson) and (AGL) ... (the Agreement).
-- 26 of 41 --
27
In accordance with clause 14 of the Agreement, (Dawson) advises:
Affected Obligation
The Affected Obligations are the obligations of (Dawson) under
clause 5.4, clause 91.1.1, clause 9.3 and clause 10.
Particulars of the event
The particulars of the event, to the extent (Dawson) knows them, are:
• In developing 15 new wells at Ridgedale, (Dawson) has
encountered unpredicted and substantial geological problems;
• The geological problems are most prominently severe
structuring and faulting of lateral drill holes at various levels;
• Structuring and faulting problems has caused both drilling
difficulties and closing of lateral drill holes at Ridgedale;
• Of 15 wells drilled at Ridgedale, 2 have been abandoned due
to the extent of the difficulties encountered with the loss of
the considerable cost of development of these wells;
• Due to the drilling difficulties and closing of lateral drill
holes, recovery of Gas from the Ridgedale wells has been
materially less than was forecast prior to the commencement
of development of these wells;
• Attempts to resolve the impacts of structuring and faulting
problems in accordance with obligations under the
Agreement, have been ongoing but not successful to date and
on current analysis may not be successful;
• Wells which have failed to produce to date may well have to
be abandoned depending on the outcome of ongoing
measures to remedy within the terms of the Agreement;
• The Ridgedale wells were developed following analysis of
the Gas field and particularly the Hillview wells;
• The Ridgedale wells were planned to come into production to
meet projected contractual obligations;
• The problems encountered in developing the Ridgedale wells
were unexpected and unpredicted, particularly having regard
to the geological information available to (Dawson) at the
time;
• (Dawson) has undertaken all stages of investigation and
development of the Ridgedale wells in accordance with
proven technology and practice as widely known to and
generally available for use in the gas industry;
• (Dawson) has expended approximately $15,000,000.00 in
developing the Ridgedale wells;
-- 27 of 41 --
28
• For developed wells at Hillview, the Gas available for
recovery is less than initially predicted due to unexpected
difficulties in production;
• Without limiting the above, the circumstances are such that
there has been an unpredicted, sudden and material
deterioration in productivity of more than one well and a
failure of wells;
• (Dawson) has exercised Good Engineering and Operating
Practice at all times;
• (Dawson) has sought to act in good faith to comply with its
contractual and other obligations by the expenditure of
reasonable sums of money and the application of proven
technology widely known to and generally available for use
by persons in the gas industry.
The events and circumstances are beyond the control of (Dawson).
(Dawson) has not been able to overcome these events
notwithstanding the exercise of Good Engineering and Operating
Practice and seeking in good faith to comply with its contractual and
other obligations by the expenditure of reasonable sums of money
and the application of proven technology widely known to and
generally available for use by persons in the gas industry.
Estimate of reduction in service capacity
(Dawson) estimates the reduction in Service capacity of 8,000 Gj per
Day and in particular amends the MDQ to 10,000 Gj per Day over the
Suspension Period.
Estimate of duration
(Dawson) estimates the duration of its inability to perform the
Affected Obligations as 14 months form the date of this notice.
We reserve all other rights, remedies and claims under the Agreement
and this notice is in addition to and without prejudice to any such
rights, remedies or claims.”
[61] The particular events or circumstances with which the litigation was concerned were
said to be within subparagraph (h) of the definition of Force Majeure Events:
“Unpredicted, sudden and material deterioration in productivity of
more than one well or failure of wells, equipment or plant breakdown
or failure that causes full or partial interruption of the delivery of Gas
by (Dawson) under this Agreement.”
Dawson submitted that the poor gas flow from the Ridgedale wells fell within the
designation “unpredicted, sudden and material deterioration in productivity of more
than one well or failure of wells”.
[62] The trial judge found, and gave substantial reasons for finding, that the inadequate
productivity of the Ridgedale gasfield exploited by Dawson to supply gas under the
Agreement was not an FM Event as described in subparagraph (h).
-- 28 of 41 --
29
[63] One notes that the definition of FM Event in the Agreement contained what might
be called a general description of such an event followed by 12 examples or
illustrations which are said to be “included” in the definition, “without limiting its
generality”. The trial judge did not consider whether the general description of an
FM Event found in the introductory part of the definition had been satisfied.
Dawson submitted that example (h) was a stand-alone definition and that whether or
not the low productivity of the gas field was an FM Event was to be determined by
reference to the terms of subparagraph (h) only. The trial judge expressed the
tentative view that this was the correct approach but that it was “unnecessary to
resolve this question ... because of (his) conclusions that for other reasons there was
no Force Majeure Event.”
[64] By notice of contention AGL submits the general description of an FM Event must
be satisfied where a party to the Agreement relies, as Dawson does, on any of the
described circumstances in subparagraphs (a) to (l). It submitted more particularly
that Dawson had to establish not only that there had been a failure of wells, or
unpredicted sudden material deterioration of productivity in wells, but that as well
the failure or deterioration was:
(a) not within Dawson’s control;
(b) not one which Dawson was able to prevent or (for the time being)
overcome:
(i) by the exercise of good engineering and operating practice, and
(ii) seeking in good faith to comply with its contractual and other
obligations by
A. the expenditure of reasonable sums of money, and
B. the application of proven, or widely known, generally
available, technology.
[65] Dawson’s submission was that:
“Where the event relied upon to curtail the supply of gas under the
Agreement is one of those identified in subparagraphs (a) to (l) of the
definition of FM Event it is unnecessary to establish the general
requirements found in the beginning of the definition.”
The submission continued:
“The first part of the definition is a general provision defining what
will constitute a sufficient event or circumstance ... to constitute an
FM Event. It is cast widely to extend to any event or circumstance
which has the further characteristics described ...
The definition then recognises a number of specific events and
circumstances which are accepted for the purposes of the Agreement
as being FM Events. ...
... The events and circumstances identified in subparagraphs (a) to (l)
are specific events that the parties have agreed are to be taken to be
events or circumstances which are ‘not within the control of a party
... .’
-- 29 of 41 --
30
The general words are taken to have been satisfied once one of the
specific events has been established.”
[66] The relevant facts have been found by the trial judge and are not now in contest.
The appeal turns on the proper construction of the Agreement. It may be shortly
determined if AGL’s submissions are accepted because it was found that Dawson
had not exercised good engineering and operating practice in its attempt to exploit
the Ridgedale gasfield so that it could not satisfy the definition of an FM Event if
what was called “the general requirements” of the definition applied to
subparagraph (h).
[67] A brief examination of subparagraph (h) is enough to show that it describes or
contains three categories of events, any one of which may qualify as an FM Event.
They are:
1. Unpredicted, sudden and material deterioration in productivity of more
than one well;
2. Failure of wells;
3. Breakdown or failure of plant or equipment.
Each must cause full or partial interruption to the delivery of gas under the
Agreement. The effect of exclusion (a) is that the breakdown of plant must effect
more than one item, unless it be a dehydration unit and the terms of exclusion (b) are
satisfied. The appeal is not concerned with a breakdown of plant.
[68] If Dawson’s submissions are accepted any breakdown or failure in plant or
equipment, and any failure of wells, which causes an interruption to the delivery of
gas, will be an FM Event. This is so regardless of the cause of the failure or
breakdown. An act of deliberate sabotage by Dawson’s employees would qualify as
an FM Event as would the failure of critical plant because of gross neglect in the
maintenance of the plant.
[69] Such a construction gives an absurdly wide ambit to the meaning of an FM Event.
The absurdity disappears if one requires the general description of an FM Event to
apply to the events or circumstances described in (h). On this basis a failure of
wells, or breakdown or failure of equipment or plant, or the unpredicted, sudden and
material deterioration in productivity of wells will be FM Events (assuming they
caused interruption to gas delivery) only if they were not within Dawson’s control,
could not have been prevented by the exercise of good engineering practice by
Dawson acting in good faith to comply with its contractual obligations by the
expenditure of reasonable amounts of money and the application of proven
technology.
[70] Other examples would share the absurdity if Dawson’s construction were accepted.
Example (g) is:
“Failure to obtain or retain any necessary consent or approval of a
Government agency (despite timely and reasonable endeavours to
obtain same)”.
The proviso applies only to obtaining consents, not retaining them.
If the introductory words of the definition did not apply then the failure of a
contracting party, perhaps the deliberate failure, to comply with the conditions of a
-- 30 of 41 --
31
consent or approval so that it lapsed or was cancelled would be an FM Event. If,
however, the failure to retain the consent or approval must be beyond the control of
the party exercising good practice and acting in good faith to comply with its
contractual obligations to qualify as an FM Event the clause will have a sensible
operation.
[71] The events described in (j) provide another example. Shortages of labour, materials
or contractors are, on Dawson’s construction, FM Events even though it was within
Dawson’s control to prevent them, by hiring staff or buying materials. The
curiosity that a party may by its own default, perhaps wilful default, bring about an
FM Event is avoided by requiring the described events to satisfy the general
requirements.
[72] Dawson’s answer to these objections is to point to clause 14.1.3 of the Agreement
which is said to prevent it taking advantage of its own inactivity or wrongdoing.
The clause provides that an FM Event affecting Dawson’s performance under the
Agreement shall not relieve it of liability:
“... in the event and to the extent that the negligence or failure to use
good engineering and operating practice ... caused or contributed to
its failure to perform or in the event of its failure to use all reasonable
endeavours ... to remedy the situation ... with all reasonable
despatch.”
[73] The answer is inadequate for three reasons. The first is that clause 14.1.3 is not
concerned with defining what is, or is not, an FM Event but with limiting the
contractual consequences of an FM Event. Should an FM Event occur Dawson is
not relieved from its obligation to perform the Agreement to the extent that, and in
the event that, it did not use appropriate practice to prevent the occurrence of the
FM Event, or to overcome it once it occurred. One must look beyond clause 14.1.3
itself, to the definition, to see whether there has been an FM Event.
[74] The second reason is that, according to Dawson’s submission, the onus on proving
that it did not use good practice etc, and so caused or contributed to the occurrence
of the FM Event, or delayed overcoming the effect of the FM Event by negligent
inaction, is on AGL, the party remote from the gas field and its operation and thus
in a poor position to know what caused the event and what Dawson did in response
to it.
[75] AGL did not accept that clause 14.1.3 cast an onus on it to prove whether Dawson’s
negligence or failure to use good practice caused or contributed to its failure to
perform the Agreement or the extent to which it could not perform it because of its
negligence or failure. It submitted that Dawson should prove the negative. The
point of construction is fairly arguable both ways. It is not necessary to resolve the
question. Assuming Dawson’s submission to be correct, the operation of clause
14.1.3 when combined with Dawson’s preferred definition of an FM Event, would
make the Agreement work lopsidedly in favour of Dawson. Any failure of wells, or
of plant or equipment, (having the described result) however caused and no matter
how preventable would be an FM Event unless AGL, a stranger to Dawson’s
operations, could prove that it had been negligent or failed to exercise good
engineering and operating practice.
[76] This construction is likely to lead to unsatisfactory and inconvenient results. I
cannot accept it.
-- 31 of 41 --
32
[77] The third reason is that if the general requirements of the definition did not apply to
the particular examples given, there would be no obligation upon a party seeking to
rely upon an FM Event to have acted in good faith to comply with its contractual
obligations. Dawson could by acting in bad faith bring about a failure of plant and
equipment (example (h)); or fail to hire contractors or dismiss staff (example (j));
or breach the conditions of a consent or approval to bring about its cancellation
(example (g)); and in each case rely on the consequences as an FM Event.
[78] In this regard clause 14.1.3 will not assist. It makes no mention of good faith. Once
an FM Event (however defined) occurs Dawson is not relieved from its contractual
obligations “in the event and to the extent” that its negligence or failure to use good
practice caused or contributed to its lack of performance or in the event that it did
not use all reasonable endeavours to remedy the situation and remove the event or
circumstances giving rise to it “with all reasonable despatch.” The clause does not
apply to a situation in which the event has been caused or continued by bad faith.
[79] Dawson seeks to avoid this consequence by arguing that the Court would imply an
obligation to act in good faith into clause 14.1.3 of the Agreement. The answer is
unsatisfactory. It requires ignoring an express obligation to act in good faith found
in the opening words of the definition and then supplying the want by implying such
a term.
[80] The parties cannot have intended that Dawson’s obligation to deliver gas should
abate in circumstances where its bad faith caused it to be unable to make the
deliveries. The absurdity is removed if one requires the general requirements of the
condition to be satisfied as well as the particular description of FM Events found in
the examples (a) to (l).
[81] The trial judge expressed the tentative opinion that the terms of subparagraph (k)
and the exclusion (b) indicated that the general requirements did not apply because,
if they did, parts of those subparagraphs would be unnecessary.
[82] The point is that subparagraph (k) provides that any breach of contract by, or an FM
Event affecting, a third party contracting with AGL which prevented AGL
performing its part of the Agreement is itself an FM Event if AGL had:
“... taken all necessary reasonable and practical action within a
reasonable time to obtain performance of the third party contractor’s
... obligation”.
Exclusion (b) is the failure or unpredicted and sudden deterioration in productivity
of a single dehydration plant:
“... if such failure or ... deterioration could have been prevented by
the exercise of good engineering and operating practice.”
[83] There is substantial though not complete overlap, between these qualifications and
the terms of the general requirements that an FM Event occurs only where the party
seeking to rely upon it had exercised good engineering and operating practice, acted
in good faith and spent reasonable amounts of money applying proven technology.
The repetition of the similar qualification would be unnecessary if the general
requirements applied to these examples.
[84] AGL argues that the inclusion of the repetitious condition does not indicate the
general requirements were meant to be excluded. It argues there is something
-- 32 of 41 --
33
peculiar to the subject matter of subparagraph (k) and exclusion (b) so as to make it
appropriate to include a special qualifying circumstance similar though not identical
to part of the general requirements.
[85] I do not find the submission particularly persuasive. There is, with respect,
substance in the trial judge’s observation but it does not outweigh the considerable
indications I have described which, in my opinion, make it clear that the general
requirements of the definition must apply to the particular illustrations found in the
subparagraphs, (a) to (l).
[86] In my opinion the general words of the definition, the general requirements as they
were called, must be satisfied if an event which leads to a failure to supply
contractual amounts of gas is to qualify as an FM Event entitling Dawson to give a
Curtailment Notice.
[87] The trial judge found that Dawson had not used good engineering and operating
practice in its exploration and development of the Ridgedale gas field. His Honour
said:
“If these general words of the definition apply, the onus would be
upon (Dawson) to prove that by the use of seismic exploration ... (it)
would not have been able to prevent the relevant occurrence. In
effect (Dawson) must prove that seismic exploration would not have
revealed sufficient information to make the drilling of these wells so
risky that it would not have occurred. Because the extent of the
problems which would have been revealed remains a matter of
speculation, it cannot be said that more probably than not the seismic
exploration would not have made a difference to what Dawson did or
ought to have done at Ridgedale.”
[88] The finding was not challenged on appeal: Dawson expressly accepted it and the
consequence that if the general requirements applied it had failed to prove that the
events or circumstances which it contended were an FM Event was not preventable
by the exercise of good engineering and operating practice by the expenditure of
reasonable sums of money and the application of proven, widely-known, generally
available technology.
[89] The appeal should be dismissed on this ground.
[90] The trial judge noted that the:
“... Curtailment Notice described the FM Event in several ways and
in broad terms, rather than identifying anything which was said to be
a single occurrence. (Dawson’s pleading does) not specify what it
was which constituted the FM Event. In their final submissions
(Dawson) put the matter in these terms:
“The ... primary submission is that the failure of more than one
well ... was a sufficient event or circumstance to satisfy the
definition of an FM Event.
Alternatively, the definition ... is satisfied by:
(i) the failure of more than one well and/or the unpredicted,
sudden and material deterioration in productivity of more
than one well;
-- 33 of 41 --
34
(ii) the presence of low angle thrust faulting, shearing of the
coal within the seams and/or the presence of coal fines
within the seams ...
(iii) ...”
[91] The reference to thrust faulting, shearing and coal fines is to geological conditions
encountered in the Ridgedale gas field which reduced or prevented the extraction of
gas from the coal seams.
[92] The trial judge pointed out that Dawson gave only one Curtailment Notice:
“... according to which the FM Event was constituted by many
occurrences at different times over a period which, on any view,
extended for more than a year. ... (Dawson’s) case ... relies upon the
entirety on what happened at Ridgedale throughout that period.”
[93] The trial judge also found:
“[67] ... Because of the way in which (Dawson) put (its) case, the
date of occurrence of the FM Event for which they
contended is not easy to identify. If the failures of wells
were regarded as, in total, the FM Event then the last ...
failed on 23 May 2007. Even the period between then and 9
July 2007 would ... constitute a delay. Alternatively, if there
was an FM Event in ... encountering ... geological
conditions, then ... this had occurred at least by ... June and
July of 2005 ... . the giving of the Curtailment Notice did
not coincide with any particular event ... . On any view ... if
there was an FM Event Dawson did not give the Curtailment
Notice without delay”.
[94] The facts summarised in these observations give rise to a point which was not
decided at first instance but which was the subject of submissions on appeal. It is
that the Curtailment Notice, not having been given “without delay” as clause 14.1.1
requires was invalid. The giving of a prompt notice was said to be a necessary
condition for a valid notice.
[95] Whether clause 14.1.1 takes effect as a condition precedent so that the lack of notice
given without delay precludes Dawson from relying upon the failure of Ridgedale
gas field as an FM Event depends, obviously, on what the parties intended to be the
effect of the clause. It is a question of construction to be answered in the orthodox
manner: by examination of the language of the clause and its commercial purpose
both to be assessed against the background facts known to both parties when the
Agreement was made. See Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219
CLR 165 at 179.
[96] The language of clause 14 bespeaks urgency. Dawson “may curtail ... services if ...
it cannot do ... something it has to do ... when it has to do it”. If an FM Event
occurs, “Dawson must without delay issue a notice” setting out what it cannot do;
the extent of its incapacity; the length of incapacity.
[97] By clause 14.1.2 the obligation which Dawson cannot perform is suspended from
the giving of the notice but only until Dawson can, after exercising all reasonable
-- 34 of 41 --
35
diligence, good practice and all reasonable means “as expeditiously as possible”,
overcome or abate the FM Event.
[98] The effect of the provisions is that when Dawson cannot perform one or more of its
obligations under the Agreement because of the occurrence of an FM Event it must
without delay give notice of its inability and then employ all reasonable diligence
and good practice and take all reasonable means to recover its ability to perform the
Agreement, as expeditiously as possible. The Notice of Curtailment has two
effects: it suspends Dawson’s obligation to perform the Agreement and obliges it to
do everything it reasonably can as quickly as possible to put itself in a position
where it can perform the Agreement.
[99] In this scheme a notice issued a substantial period after the occurrence of the FM
Event would be incongruous. To be efficacious to commence the suspension period
and initiate Dawson’s obligations to remedy or abate the FM Event as expeditiously
as possible the notice must be issued “without delay”, which I would take to mean
as soon as it becomes obvious that the FM Event has prevented, or will prevent,
performance.
[100] The commercial purpose for giving the Curtailment Notice would seem to be to
allow AGL to assess whether the event was in fact an FM Event and whether if it
were it had been brought about by Dawson’s negligence or failure to use good
practice (clause 14.1.3) and so judge the extent to which Dawson was relieved of its
obligation to supply gas.
[101] The gas which AGL bought from Dawson was on-sold by it to consumers and other
suppliers. Its contracts with its buyers would be at risk if the supply of gas to it
from Dawson were curtailed. It may, in that event, be obliged to buy gas from other
suppliers. The giving of notice without delay of an interruption to supply would
permit AGL promptly to assess the situation and make arrangements to honour its
contracts to sell gas to its buyers.
[102] The commercial purposes of the notice could be seriously affected if Dawson were
not obliged to give it promptly after an FM Event. AGL would not know whether
and to what extent the FM Event (of which it would remain ignorant) had affected
Dawson’s capacity to sell gas to it and its need to obtain alternative supplies of gas.
[103] Dawson’s submissions treat the words “without delay” as superfluous. It regards
clause 14.1.1 as allowing the giving of a Curtailment Notice any time after an FM
Event prevented its performance of the Agreement. This overlooks the imperative
mood “must without delay issue a notice” and makes nonsense of the obligation to
overcome the FM Event as quickly as possible.
[104] Both the text of clause 14 and the commercial context of the Agreement lead to the
conclusion that a Curtailment Notice will not be valid unless issued without delay
after the occurrence of an FM Event.
[105] I would construe clause 14 as meaning that unless a Curtailment Notice be given
without delay it is not a notice for the purposes of the clause and does not have the
effect of suspending Dawson’s obligation to deliver gas.
[106] Although the construction of contractual terms is in every case to be essayed by an
examination of the particular contractual text and context, authorities on similar
clauses may assist. They may show an approach to a certain type of clause. In
Bremer Handelsgesellschaft Schaft M.B.H. v Vanden Avenne Izegem P.V.B.A.
-- 35 of 41 --
36
[1978] 2 Lloyd’s Rep 109 the House of Lords considered inter alia a contract for
the sale of soya bean meal. The relevant clause provided that the sellers should not
be responsible for delay in shipment of the goods occasioned by specified “Force
Majeure” events with the qualification:
“If delay in shipment is likely to occur for any of the above reasons,
shippers shall give notice to their buyers by telegram, telex or
teleprinter or by similar advice within seven consecutive days of the
occurrence or not less than 21 consecutive days before the
commencement of the contract period whichever is later. If after ...
such notice an extension to the period ... is required shippers shall
give further notice not later than 2 days after the contract period of
shipment ...”
[107] Lord Wilberforce, with whom Lord Keith agreed, said (116):
“If the force majeure notice was defective ... and any defect was not
waived ... then the question arises whether the sellers are entitled to
the protection of the clause. The existing authorities ... support the
view that they are not, on the ground that cl 22 is a complete
regulatory code in the matter of force majeure, and that accurate
compliance with this stipulation is essential to avoid commercial
confusion in view of the possibility of there being long strings of
buyers and sellers. I agree with these decisions.”
[108] Lord Salmon said (125):
“Before leaving cl 22 I should make it plain that, in my view, the
condition as to the time in which notice had to be served was a
condition precedent to the efficacy of this notice. I cannot agree with
the argument on behalf of the sellers that the breach of this condition
would entitle the buyers only (a) to recover any damages caused by
the breach or (b) to treat the notice as a nullity, if they could prove
that they had suffered serious prejudice by the notice having been out
of time.”
[109] One of the authorities to which Lord Wilberforce referred was V. Berg & Son Ltd v
Vanden Avenne-Izegem P.V.B.A. [1977] 1 Lloyd’s Rep 499. The case involved the
same Force Majeure clause. The contract in question was for the sale of sweet
potato slices. Loading was delayed because of torrential rain in Shanghai. The
sellers did not give notice within the time stipulated for in the Force Majeure clause.
The Court of Appeal held this to be fatal to the seller’s attempt to avoid liability for
late delivery. Lord Denning MR said (503):
“It is sufficient, in my view, that the sellers did not do what was
necessary to be able to avail themselves of the force majeure clause.
Their notices were not sufficient to satisfy it. ... The answer to the
question ... is that the sellers are liable.”
Roskill LJ said (504):
“I rest my decision ... on the view that there has not been any proper
compliance with the provisions of what has become known as the
fourth sentence in the force majeure clause ... . The fourth sentence
-- 36 of 41 --
37
... requires the shippers to give their further notice not later than two
days after the last day of the contract period of shipment ...”.
[110] Another authority cited was Andre & Cie S.A. v ETS. Michel Blanc & Fils [1977]
2 Lloyd’s Rep 166. Ackner J said (177):
“Traders attach great importance to the giving of the correct notices
stipulated by (the Force Majeure clause) including the notices which
have to be given when shipment is delayed or prevented, because
failure to observe the rules prescribing notices jeopardises the
viability of string transactions.”
[111] That concern that timeous notice be given to protect parties in a “string” of sales is
not, perhaps, relevant to the Agreement, though AGL had on-sold gas. Lord
Wilberforce’s description of the Force Majeure clause relevant to those cases as “a
complete regulatory code in the matter of Force Majeure, and that accurate
compliance ... is essential to avoid commercial confusion” is, I think, apposite.
More generally, contractual notices which one party may give another unilaterally
altering the rights of the parties to the contract must comply strictly with the terms
which govern the giving of notice. An example is Mannai Investment Co Ltd v
Eagle Star Life Assurance Co Ltd [1997] AC 749. The principle just stated is
expressed by Lord Steyn at 773. See also Lord Goff (who dissented) at 755. The
case concerned a break clause in a lease but “such notices belong to the general
class of unilateral notices served under contractual rights” (per Lord Steyn at 768).
[112] Clause 14 sets out the circumstances in which Dawson will be relieved from its
contractual obligations. The suspension of those obligations is a matter of
considerable importance to AGL and those who buy gas from it. The right
conferred on Dawson to give a curtailment notice affects AGL’s rights to buy gas
and may expose it to liability. The Agreement is to run for a long time and the
amounts of gas and money which change hands pursuant to its terms are
considerable. The parties are to be taken to have intended that the alteration of
obligations in such a contract which may have such consequences should be
permitted only in the precise circumstances the parties themselves specified.
Relevantly that means that unless a Curtailment Notice be given without delay it
will be invalid.
[113] I would therefore construe clause 14.1.1 as requiring a Curtailment Notice to be
given without delay if it is to bring about the consequences described in the
succeeding subclauses. Such a construction accords with the “Force Majeure”
cases, and the general principal that contractual rights may only be altered
unilaterally in the precise manner provided for in the contract. The Notice was not
given without delay. It did not therefore have the effect of suspending Dawson’s
obligations to supply the amounts of gas nominated by AGL.
[114] On this ground too, the appeal should be dismissed.
[115] There remains to consider the ground on which the trial judge found against
Dawson, i.e. that it had not demonstrated that the deficiency in production of gas
from Ridgedale fell within the description of an FM Event found in subparagraph
(h) of the definition. It is not necessary for the outcome of the appeal to discuss the
point but because it was the subject of extensive argument and founded the basis for
the judgment in the Trial Division, I should address it.
[116] The trial judge reasoned:
-- 37 of 41 --
38
“[35] (Dawson’s) case, like the Curtailment Notice, does not
attempt to identify any point in time when there was this
occurrence of an FM Event. Rather their case is that by the
time of the ... Notice, an FM Event had occurred by a
combination of events and circumstances over a period. On
their case, no distinct occurrence must be demonstrated,
because an FM Event might be constituted by considering
together a sequence of distinct happenings. ...
[36] A further element of the ... argument is that cl 14 does not
require the FM Event to have an immediate impact on the
delivery of gas. ...
[37] In my view, what is relied upon as an FM Event must be
something with an immediate effect upon Dawson’s capacity
to supply and thereby upon its then performance. Clause
14.1.1 provides that ‘if an FM Event occurs (Dawson) must
without delay issue a (Curtailment) Notice’. Contrary to
(Dawson’s) argument this could mean only that the notice is
to be issued without delay from the occurrence which is said
to constitute the FM Event. ...
[38] ...the effect of an FM Event must be disabling: it must have
the result that Dawson cannot, absolutely or in part, perform
the ... obligation of supplying gas. ... This is because cl 14 is
engaged only where the agreed quantity cannot be supplied. ...
[39] This requirement of an immediate effect of the FM Event is
illustrated by para (h) ... which refers to the deterioration in
productivity of more than one well or the failure of wells
causing ‘full or partial interruption of the delivery of Gas. …
…
[42] ...this argument involves a misinterpretation of ... para (h).
What is referred to ... is the failure of wells rather than the
failures of wells. ... to fall within the specific inclusion ...
what must occur for several wells, by a failure or an
unpredicted, sudden and material deterioration in productivity,
are events which operate in combination to cause a certain
interruption of the delivery of gas.
[43] The generality of this Curtailment Notice and of (Dawson’s)
submissions as to what constitutes the FM Event results from
these flaws in their case. They have failed to identify a certain
occurrence in the sense of an event or circumstance, or events
or circumstances acting in combination, having an immediate
consequence upon Dawson’s performance at that point in
time. ...
[44] ...(Dawson has) not attempted to identify an occasion which
represents an interruption in the delivery of gas. Nor (has it)
sought to prove the extent of the diminution in Dawson’s
capacity from ... the failures of certain wells; other than ... by
reference to Dawson’s forecasts of production.
...
-- 38 of 41 --
39
[46] ...The ‘deterioration in productivity’ ... involves a comparison
of ... actual productivity at two points in time. It does not
involve a comparison of ... forecast productivity with ... actual
productivity.”
[117] Dawson took issue with these reasons. It argued that “the opening words of the
definition of FM Event comprehend that (it) may be a combination of events or
circumstances. The words ‘failure of wells’ are apt to describe separate failures of
wells brought about by different events. There is no indication that the words
‘unpredicted sudden and material deterioration in productivity of more than one
well’ should be confined to a deterioration resulting from a single occurrence or
event or that the failure of one well must necessarily coincide in time with another”.
The submission continued that the trial judge’s focus on the requirement for there to
be an interruption in the flow of gas did not give effect to the words of subparagraph
(h) which did not require that the failure of wells cause an interruption in the flow of
gas from particular wells. Nor was it necessary that wells should first come to
production before they could fail. It was a mistake to read “failure” where it
appears in the subparagraph as requiring a singular event: the word should be taken
to include the plural form, failures.
[118] Dawson complains that the construction favoured by the trial judge imposes
extremely limited operation on subparagraph (h). It submits that production wells
may fail progressively and to exclude progressive failure of wells unduly restricts
the operation of subparagraph (h) to a failure of wells caused by a single event
effecting several wells at the same time.
[119] Dawson also submits that the trial judge was wrong to conclude that an FM Event
must necessarily have an immediate effect upon its capacity to supply gas. It points
to the illustrations of FM Events found in subparagraphs (f), (g), (j) and (l) as being
circumstances where the effect of the event may be delayed.
[120] This last submission overlooks the language of clause 14 which I mentioned when
dealing with the efficacy of the Curtailment Notice. The notice must be issued
without delay upon the occurrence of an FM Event; the suspension of obligations
occurs immediately upon the giving of notice; Dawson must work “as expeditiously
as possible” to overcome the effect of the FM Event and must act “with all
reasonable despatch”. These provisions are incompatible with the notion that there
may be a substantial lapse of time between an FM Event, inability to supply gas,
and the giving of notice suspending the obligation to do so.
[121] Dawson also challenges the trial judge’s conclusion that an FM Event must be
disabling. Dawson submitted that the Agreement did not require it to curtail the
supply of gas should an FM Event occur by invoking the procedure set out in clause
14. It was said to follow that there might be non-disabling FM Events. It is no
doubt true that Dawson did not have to give a notice after an FM Event occurred. It
may have continued on in breach of contract or supplied gas from alternative
sources. If, however, it did invoke clause 14 it could only be on the basis of an FM
Event which made it impossible for it to supply the contracted amounts of gas.
[122] Dawson criticises the trial judge’s reliance on the need for the FM Event defined in
subparagraph (h) to bring about an interruption to the supply of gas. His Honour
thought this connoted an immediate effect of the FM Event. Dawson submits that
“there is no necessary temporal connection between (the event) and the interruption
-- 39 of 41 --
40
of ... the delivery of gas. The connection is a causal one. The interruption may
occur after the FM Event.”
[123] In my opinion the natural meaning of the words support the trial judge’s conclusion.
The FM Event must interrupt the supply of gas. That does suggest immediacy.
There is a flow of gas which is interrupted, broken off, which ceases. The word to
my mind does suggest a close connection in time between the event and the
interruption.
[124] It is conspicuously noteworthy that in its attempt to bring the insufficient supply of
gas from Ridgedale within the definition of an FM Event, Dawson was obliged to
import the introductory words of the general requirement into subparagraph (h).
This is the main thrust of its submission as I summarised it in paragraph [63].
Dawson was obliged to argue that the unpredicted, sudden and material
deterioration in productivity of more than one well, or the failure of wells, could be
constituted by a combination of events or circumstances so that a failure of wells
may in fact be the separate failures of a number of wells brought about by different
events at different times, and the unpredicted, sudden and material deterioration in
productivity of more than one well may occur by the separate decline in
productivity in a number of wells from different geological causes at different
times.
[125] Reliance on that part of the general definition of an FM Event is essential because
Dawson’s case was, as its submissions confirm, that the underperformance of all of
the wells at Ridgedale over a year or so is the FM Event. There was no failure of
wells or one occasion on which there was a sudden etc. deterioration in productivity
of wells which had an immediate impact upon Dawson’s capacity to deliver the
nominated quantities of gas.
[126] Dawson’s need to apply part of the general requirements of the definition of an FM
Event shows how completely untenable its construction of subparagraph (h) is. It
imports that part of the general requirements which it needs but steadfastly objects
to the application of the whole of the general requirements to subparagraph (h).
That is Dawson contends that an FM Event is:
“Any ... combination of events or circumstances, including
‘unpredicted, sudden and material deterioration in productivity of
more than one well or failure of wells, ...that causes full or partial
interruption of the delivery of gas’”
but also contends that the events or circumstances, may have been within the control
of Dawson and might have been prevented by the exercise of good practice etc.
[127] It is neither possible nor sensible to pick and choose between parts of the general
definition of FM Event. Either the whole applies to the examples given in
subparagraph (l) (as I have concluded) or each must be taken as self-contained.
[128] If self-contained the appeal fails because subparagraph (h) will not apply without
the aggregation of events and circumstances to constitute the failure or deterioration
in productivity of wells. If the general requirements of the definition apply to (h)
the appeal fails because Dawson, as the trial judge found, did not exercise good
engineering and operating practice.
-- 40 of 41 --
41
[129] I do not accept Dawson’s complaint that this construction of the Agreement unduly
restricts the operation of clause 14. Coupled with the definition of FM Event the
clause has wide scope. Any event or circumstance or combination thereof which
was beyond Dawson’s control and could not have been prevented by good
engineering practice in the honest endeavour to perform the Agreement by the
expenditure of reasonable amounts of money applying established technology
which prevents Dawson from supplying gas, will relieve it of the contractual
obligation to do so.
[130] The problem for Dawson, as found by the trial judge, is not that the Agreement is
unfairly restrictive but that Ridgedale was inadequately investigated and none of the
production wells yielded the expected quantities of gas. The entire field was a
failure which became apparent over several years as unproductive wells were
drilled. To have succeeded in the action, and to succeed on appeal, Dawson must fit
these facts into the contractual definition of an FM Event. For the reasons given by
the trial judge it is an impossible task.
[131] Dawson very belatedly sought to meet this objection to its case by producing, for
the first time on appeal, schedules drawn from the evidence which purport to show a
substantial reduction in the average daily production of gas from the Ridgedale
wells in the month or so prior to the Notice of Curtailment and, separately, in the six
months prior to the notice. The purpose of the schedules was to show that there had
been a sudden (if six months or even one month be sudden) deterioration in
production of more than one well at about the same time (January to July 2007).
AGL objected to the receipt of the schedules because they raised a different factual
case to that argued at trial. Because the new case was one which might have been
met by evidence which was not adduced or examined at trial because Dawson’s case
had not been framed in that way, the point cannot be raised now. See
Suttor v Gundowda Pty Ltd (1950) 81 CLR 418 at 439; Coulton v Holcombe (1986)
162 CLR 1 at 7-8).
[132] For these many and manifold reasons the appeal should be dismissed with costs.
There was a second appeal, brought pursuant to leave given by the trial judge,
against the orders for costs made at the conclusion of the trial. That appeal should
be dismissed for the reasons given by Fraser JA.
-- 41 of 41 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2009/262