Cook's Construction Pty Ltd v Stork Food Systems Australasia Pty Ltd [2009] QCA 75 (2009) 254 ALR 661
SUPREME COURT OF QUEENSLAND
CITATION: Cook's Construction P/L v SFS 007.298.633 P/L (formerly
trading as Stork Food Systems Australasia P/L) [2009]
QCA 75
PARTIES: COOK'S CONSTRUCTION PTY LTD
ACN 004 782 558
(plaintiff/appellant)
v
SFS 007.298.633 PTY LTD (FORMERLY TRADING AS
STORK FOOD SYSTEMS AUSTRALASIA PTY LTD)
ACN 007 298 633
(defendant/respondent)
FILE NO/S: Appeal No 9301 of 2008
SC No 10993 of 2001
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 3 April 2009
DELIVERED AT: Brisbane
HEARING DATE: 26 February 2009; 27 February 2009
JUDGES: Keane and Fraser JJA and Daubney J
Separate reasons for judgment of each member of the Court,
each concurring as to the orders made
ORDER: 1. Appeal dismissed
2. Appellant to pay the respondent's costs of the appeal
on the standard basis
CATCHWORDS: RESTITUTION – MISTAKE: RESTITUTION ARISING
FROM A PLAINTIFF'S MISTAKEN ACTIONS –
RECOVERY OF MONEY PAID UNDER MISTAKE –
RELEVANT PRINCIPLES – where appellant and respondent
related as sub-contractor and contractor – where appellant
warranted to respondent that appellant licensed builder –
where respondent paid to appellant moneys for services
rendered on that basis – where appellant not licensed builder
– where respondent claimed against appellant for moneys had
and received insofar as respondent paid appellant on mistaken
belief as to appellant's entitlement under contract – where
appellant claimed respondent's action should fail insofar as
the respondent did not disprove the appellant's entitlement to
reasonable remuneration under s 42(4) of the Queensland
Building Services Authority Act 1991 (Qld) – whether
-- 1 of 46 --
2
respondent's action for moneys had and received
maintainable
RESTITUTION – GENERAL PRINCIPLES – restitutio in
integrum – where appellant claimed respondent not entitled to
claim for moneys had and received insofar as respondent
cannot restore appellant to pre-transaction position – whether
restitutio in integrum element of respondent's claim for
moneys had and received
EVIDENCE – BURDEN OF PROOF, PRESUMPTIONS,
AND WEIGHT AND SUFFICIENCY OF EVIDENCE –
GENERALLY – SUFFICIENCY – where appellant claimed
respondent's claim for moneys had and received reduced by
appellant's claim for reasonable remuneration under s 42(4)
of the Queensland Building Services Authority Act 1991
(Qld) – where appellant claimed respondent's claim failed
insofar as it did not particularise appellant's reasonable
remuneration to be deducted from claimed amount – whether
burden of proof held by appellant or respondent with respect
to demonstrating reasonable remuneration on the evidence
INTEREST – RECOVERABILITY OF INTEREST –
AWARD OF INTEREST ON DEBTS AND SUMS
CERTAIN – OTHER MATTERS – where trial judge
awarded interest against appellant from date of last payment
by respondent – where appellant claimed interest should not
be awarded because respondent received value for money –
whether interest should be awarded
APPEAL AND NEW TRIAL – GENERAL PRINCIPLES –
POINTS AND OBJECTIONS NOT TAKEN BELOW –
WHEN NOT ALLOWED TO BE RAISED ON APPEAL –
COURSE OF CONDUCT AT TRIAL – where three of the
appellant's contentions on appeal were not litigated at trial –
where respondent argued that it would have met these
contentions with evidence if they had been run at trial and, as
such, that the appellant should not now be permitted to raise
these contentions on appeal – where appellant answered this
by arguing that the respondent had counterclaimed only the
full amount of what it had paid and that the evidence that the
respondent claims it would have led would not have
supported that counterclaim in any case – whether the
appellant should be permitted to raise these contentions on
appeal
Queensland Building Services Authority Act 1991 (Qld), s 42,
s 43
Queensland Building Services Authority Amendment Act
1999 (Qld), s 21
Retail Tenancies Reform Act 1998 (Vic), s 8
Supreme Court Act 1995 (Qld), s 47
Uniform Civil Procedure Rules 1999 (Qld), r 150
-- 2 of 46 --
3
Alati v Kruger (1955) 94 CLR 216; [1955] HCA 64, cited
Australia & New Zealand Banking Group Ltd v Westpac
Banking Corp (1988) 164 CLR 662; [1988] HCA 17, cited
Bank of New South Wales v Murphett [1983] 1 VR 489, cited
Barclays Bank Ltd v W J Simms Son & Cooke (Southern) Ltd
[1980] QB 677, cited
Batchelor v Burke (1981) 148 CLR 448; [1981] HCA 30,
cited
Chugg v Pacific Dunlop Ltd (1990) 170 CLR 249; [1990]
HCA 41, cited
Clarke v Dickson (1858) 120 ER 463, cited
Cook's Construction Pty Ltd v Stork ICM Australia Pty Ltd
[2004] QSC 66, cited
Cook's Construction P/L v Stork Food Systems Aust P/L
[2008] QSC 179, cited
Cook's Construction P/L v Stork Food Systems Aust P/L
[2008] QSC 220, cited
Coulton v Holcombe (1986) 162 CLR 1; [1986] HCA 33,
cited
David Securities Pty Ltd v Commonwealth Bank of Australia
(1992) 175 CLR 353; [1992] HCA 48, cited
Flett v Deniliquin Publishing Co Ltd [1964-5] NSWR 383,
cited
Gino D'Alessandro Constructions Pty Ltd v Powis [1987]
2 Qd R 40, cited
Haines v Bendall (1991) 172 CLR 60; [1991] HCA 15, cited
Iezzi Constructions Pty Ltd v Watkins Pacific (Qld) Pty Ltd
[1995] 2 Qd R 350; [1994] QCA 49, cited
Kiriri Cotton Co v Dewani [1960] AC 192, cited
Lejo Holdings Pty Ltd v Deutsche Bank (Asia) AG [1988]
2 Qd R 30, cited
Marshall v Marshall [1999] 1 Qd R 173; [1997] QCA 382,
cited
Mayfair Trading Co Pty Ltd v Dreyer (1958) 101 CLR 428;
[1958] HCA 55, cited
Ovidio Carrideo Nominees Pty Ltd v The Dog Depot Pty Ltd
(2006) V ConvR 54-713; [2006] VSCA 6, cited
Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221;
[1987] HCA 5, cited
Roxborough v Rothmans of Paul Mall Australia Ltd (2001)
208 CLR 516; [2001] HCA 68, cited
Sutton v Zullo Enterprises Pty Ltd [2000] 2 Qd R 196; [1998]
QCA 417, cited
Suttor v Gundowda Pty Ltd (1950) 81 CLR 418; [1950] HCA
35, cited
Vadasz v Pioneer Concrete (SA) Pty Ltd (1995) 184 CLR
102; [1995] HCA 14, cited
Vines v Djordjevitch (1955) 91 CLR 512; [1955] HCA 19,
cited
Water Board v Moustakas (1988) 180 CLR 491; [1988] HCA
12, cited
-- 3 of 46 --
4
Whisprun Pty Ltd v Dixon (2003) 200 ALR 447; [2003] HCA
48, cited
COUNSEL: J K Bond SC, with P D Hay, for the appellant
K E Downes SC, with S R R Cooper, for the respondent
SOLICITORS: HWL Ebsworth for the appellant
McCullough Robertson for the respondent
[1] KEANE JA: The respondent's predecessor in title was a contractor engaged in the
construction of an ammonium nitrate plant at Moura in central Queensland. By an
agreement in writing made in June 1998 ("the subcontract"), the respondent
engaged the appellant as its subcontractor to undertake the construction of
earthworks and concrete works for the project.
[2] Between July 1998 and April 2000 the appellant made claims for progress payments
for work done under the subcontract which were certified for payment and paid.
The total amount paid during this period was $15,528,924.03.
[3] In March 2001 the appellant commenced proceedings against the respondent
claiming payment of moneys unpaid for work done under the subcontract.
[4] On 17 August 2001 the respondent filed a defence which resisted the appellant's
claim for further payment. The respondent also made a counterclaim for the
recovery of some of the money paid by it to the appellant under the contract.
[5] The respondent's case was that, under s 42(3) of the Queensland Building Services
Authority Act 1991 (Qld) ("the Act"), the appellant was "not entitled to any
monetary or other consideration for" carrying out that part of the subcontract works
which were "building work" within the meaning of the Act because it was not
licensed under the Act. In consequence, so it was said, the appellant was not
entitled to payment for building work for which it had not been paid and, further,
the respondent was entitled to recover the payments made by it for building work as
having been made by mistake as to the appellant's entitlement. The principal basis
on which the appellant resisted this contention was that none of the work in question
was "building work" for which a licence was required under the Act.
[6] On 22 August 2008 the learned trial judge gave judgment for the appellant on its
claim and for the respondent on its counterclaim. The amount recoverable by the
respondent in respect of payments to the appellant for building work was
$9,893,796.54. This sum vastly exceeded the amount recovered by the appellant on
its claim in the action. On 18 September 2008 his Honour consolidated the
judgments on claim and counterclaim and, after including an award of interest upon
the balance in favour of the respondent, gave judgment for the respondent in the
sum of $15,216,484.16.
[7] At first blush it may seem surprising, to say the least, that the appellant should be
required to disgorge payments made for work actually performed for the
respondent. Mr Bond of Senior Counsel who appeared with Mr Hay of Counsel for
the appellant on the appeal (neither Counsel appeared at first instance) was disposed
to describe this outcome as "scandalous". I would not disagree with this
description. I do not, however, agree that this epithet is warranted by any aspect of
the learned trial judge's determination of the issues of law or fact tendered to him
-- 4 of 46 --
5
for decision by the parties. The unhappy outcome of the case becomes
understandable when regard is had to the way in which the case was litigated below.
[8] The notice of appeal originally filed by the appellant raised many grounds. The
three grounds of appeal which were pressed on the hearing of the appeal relate in
varying ways to the operation of s 42 of the Act. It is fair to say that none of the
arguments agitated by the appellant in this regard were advanced at first instance.
[9] The appellant also argued that interest should not have been awarded on the moneys
paid to it by the respondent. As to this last point, which was argued below, the
respondent argued that the appellant had not appealed against this aspect of the
judgment, but it is tolerably clear that the notice of appeal is in wide enough terms
to encompass this argument.
[10] It is now common ground that much of the work which the appellant carried out
was " building work" within the meaning of the Act. It is accepted that, contrary to
the requirements of the Act, and in breach of the terms of the subcontract, the
appellant was not licensed to carry out building work under the Act.
[11] I shall discuss the arguments agitated by the parties on the appeal directly; but first
I shall set out the terms of s 42 of the Act and summarise the judgment at first
instance insofar as the learned trial judge's findings and conclusions are material to
the arguments raised on appeal.
Section 42 of the Act
[12] Prior to October 1999, s 42 of the Act provided:
"(1) A person must not carry out, or undertake to carry out,
building work unless that person holds a contractor’s licence
of the appropriate class under this Act.
…
(3) A person who carries out building work in contravention of
this section is not entitled to any monetary or other
consideration for doing so.
…
(7) A person who contravenes this section commits an offence."
[13] With effect from 1 October 1999,1 s 42 was relevantly amended to provide:
"(3) Subject to subsection (4), a person who carries out building
work in contravention of this section is not entitled to any
monetary or other consideration for doing so.
(4) A person is not stopped under subsection (3) from claiming
reasonable remuneration for carrying out building work, but
only if the amount claimed–
(a) is not more than the amount paid by the person in
supplying materials and labour for carrying out the
building work; and
(b) does not include allowance for any of the following–
(i) the supply of the person’s own labour;
1 Section 42 was amended by s 21 of the Queensland Building Services Authority Amendment Act
1999 (Act No 43 of 1999). Section 21 came into force on 1 October 1999 by virtue of s 1 of SL
1999 No 226 made by the Governor on 30 September 1999.
-- 5 of 46 --
6
(ii) the making of a profit by the person for
carrying out the building work;
(iii) costs incurred by the person in supplying
materials and labour if, in the circumstances,
the costs were not reasonably incurred; and
(c) is not more than any amount agreed to, or
purportedly agreed to, as the price for carrying out
the building work; and
(d) does not include any amount paid by the person that
may fairly be characterised as being, in substance, an
amount paid for the person’s own direct or indirect
benefit.
…
(9) A person who contravenes this section commits an offence.
(10) Subsection (4) applies to building work carried out on or
after 1 July 1992, unless the entitlement to payment for the
carrying out of the building work was …"
The judgment at first instance
[14] The subcontract provided for a lump sum payment to the appellant of
$8,753,389.83. The subcontract also contained a schedule of rates to be applied in
the valuation of variations to the works and the assessment of claims by the
appellant for progress payments. The subcontract provided for the certification of
claims for progress payments on account of the price payable under the subcontract.
[15] Mr Peter Jewell was retained by the respondent as its Senior Project Manager for
the Moura project. It was Mr Jewell who certified that the appellant was entitled to
be paid progress payments under the subcontract.
[16] The learned trial judge found that Mr Jewell would not have certified as payable
amounts claimed for building work had he not been under the mistaken belief that
the appellant held the necessary licence required under the Act2 and as, indeed, it
had promised by cl 16 of the subcontract. In this regard, his Honour said: 3
"Stork called Mr Peter Jewell on this issue. He was 'Stork's
representative' for the purposes of the Subcontract but he was not an
employee of Stork. He was also the person who was responsible for
certifying the payments by Stork to CCPL. His evidence was that:
(a) when he certified those payments, he expected the
plaintiff to hold all licences it was required to hold
do the contract works within Queensland;
(b) if he had discovered that the plaintiff did not hold the
licences it was required to hold, he would have taken
legal advice and acted in accordance with that
advice: 'I would have adjusted their payment
accordingly in relation to the legal advice I was
given'; and
2 Cook's Construction P/L v Stork Food Systems Aust P/L [2008] QSC 179 at [345] – [346].
3 [2008] QSC 179 at [344] – [346].
-- 6 of 46 --
7
(c) during the course of the Subcontract he did not
discover that the plaintiff did not hold any licence
that it was supposed to hold.
Mr Jewell was cross-examined on this area:
'Among the many things you might have done is it
correct to say that had you discovered that one of your
subcontractors was not appropriately licensed under that
Act, you nevertheless would have insisted on the
subcontractor continuing to perform its work under the
subcontract?-- No.
Well, let's look at it from a different angle. Had you
discovered that the subcontractor was unlicensed is it
your evidence that you would have stopped it then and
there from continuing to work under its subcontract?--
Until they were licensed, yes.'
Stork was, through its representative, mistaken as to its obligation to
pay CCPL. It is clear from his evidence that had he discovered that
CCPL was unlicensed he would have stopped it from working and
taken legal advice."
[17] At trial the principal basis on which the appellant resisted the respondent's
counterclaim was that the work in question was not building work within the
meaning of the Act. Not surprisingly, this issue was resolved against the appellant
and, as I have noted, the appellant does not now seek to reopen this issue.
[18] At trial, the appellant also sought to defeat the respondent's counterclaim by
invoking the provisions of s 42(4) of the Act with a view to establishing an
entitlement to reasonable remuneration for the work which it had actually performed
for the respondent. The learned trial judge found that "there is no evidence upon
which the provisions of s 42(4) can act." 4
[19] The learned trial judge proceeded on the footing that s 42(4) of the Act allows the
making of a claim by an unlicensed builder for reasonable remuneration even
though the unlicensed builder is denied an entitlement to payment under its contract
by operation of s 42(1) and s 42(3) of the Act. Consistently with the evident policy
of the Act, however, s 42(4) provides that a claim by an unlicensed builder for
reasonable remuneration may not include a component for the supply of either the
builder's own labour or the making of a profit by the builder, or the costs of
materials and labour supplied not reasonably incurred. In this way the amended Act
ameliorates in a limited way the position of an unlicensed builder which has
actually provided valuable services to its customer. The outcome in this case,
which would otherwise be an affront to basic ideas of justice, is understandable on
the basis that the appellant did not prove its claim to reasonable remuneration in
conformity with the strictures in s 42(4) of the Act. In a system of justice which is
adversarial in nature, responsibility for this failure lies with the appellant.
[20] It is apparent that the formulation of the appellant's claim paid scant regard to
s 42(4) of the Act. In this regard, the learned trial judge said: 5
4 [2008] QSC 179 at [316].
5 [2008] QSC 179 at [290] – [291].
-- 7 of 46 --
8
"… Stork argues that while CCPL pleads that s 42(3) of the QBSA
Act operates subject to s 42(4) it does not claim any entitlement to
reasonable remuneration pursuant to that subsection. That is not quite
correct. In paragraph 39 of CCPL’s second amended reply and
answer, it pleads, in [39], as follows:
'Further to paragraph 37 hereof if it did undertake
building work as defined by the QBSA Act, which is not
admitted but for the reasons set out in paragraphs 26 to
36 hereof specifically denied, pursuant to s 42(4) of the
QBSA Act it is entitled to reasonable remuneration for
carrying out the building work.'
That is not, of course, a pleading of a claim. It is only the pleading of
an entitlement which is a prerequisite to the making of a claim. It
does not descend to any particularity; it does not identify any amount
that might be claimed. Also, any such claim should be in the
Statement of Claim."
[21] The presentation of the appellant's claim at trial exhibited some unusual features. In
this regard the learned trial judge observed:6
"The plaintiff came closest to making a formal claim in the final oral
submissions made on the last day of the trial. Mr Digby QC, for
CCPL, said:
'Your Honour will be aware that in paragraph 39 of the
reply the - can I call it a defence for the moment, your
Honour?-- the defence under clause 42(4) of the QBSA
is raised by the plaintiff. Your Honour is also aware,
having presided over the trial, that the case [has
proceeded] on the basis of evidence being put forward by
both parties and tested in relation to what would be an
appropriate reasonable remuneration: Mr Same's report
on the part of the plaintiff and Miss Janine Smith's report
on the part of the defendant.
Now, we're not sure precisely how this point in the
opening is put and whether it [is] said that
notwithstanding that - the question of reasonable
remuneration is raised in the reply the plaintiff puts
forward and has been addressed in the evidence and in
submissions, including opening submissions -- the
defendant is saying at the end of the day [that] your
Honour is precluded from applying the provisions of
clause 42(4) because of the matter arising not as a
positive claim, but as a reply to the counterclaim which is
put forward in our learned friend's [pleadings].
If that were how the matter was put, then we would seek
leave to draft that same paragraph in the reply into the
statement of claim [if there needs] to be a positive
allegation to enable your Honour to deal with 42(4) of
6 [2008] QSC 179 at [292] – [294] (citation footnoted in original).
-- 8 of 46 --
9
the QBSA and the particulars of the reasonable
remuneration that is advanced would be by reference to
the report of Mr Same from […] KNP.'
That was a curious submission given the requirements of the
Uniform Civil Procedure Rules and the remarks and reasons of
Moynihan SJA in his decision given on 16 March 2004 (almost four
years to the day before Mr Digby QC made his submission) where,
in respect of the same point, he said:
'[55] The claims do not seem to me to be pleaded in
terms of a claim under s 42(4) of the Act. The point
needs to be clarified. Any claim under s 42(4) should be
properly pleaded in the statement of claim. In an earlier
round of pleadings the plaintiff pleaded (in an amended
reply of 2 November 2001), a claim under s 42(4). There
is, however, correspondence suggesting that such a claim
is not being pursued. (Cook's Construction Pty Ltd v
Stork ICM Australia Pty Ltd [2004] QSC 066).'
Notwithstanding the unsatisfactory nature of the pleading on this
point, the plaintiff called evidence, without objection, ostensibly on
the topic of reasonable remuneration."
[22] The appellant adduced evidence from a forensic accountant, Mr Norman Same, with
a view to establishing some external standards by reference to which reasonable
remuneration for the appellant's work could be assessed. The appellant also relied
upon evidence from a quantity surveyor, Mr Rodney Alsop. The respondent called
a forensic accountant, Ms Janine Smith. The learned trial judge found that he
derived no assistance from this evidence for a number of reasons including the
unavailability of supporting documents to establish primary facts,7 the absence of
evidence of market prices for the work,8 Mr Same's lack of qualifications to express
an expert opinion as to reasonable remuneration,9 and the absence of an assessment
as to whether reasonable remuneration was more than the amount actually
charged.10
[23] The evidence of Mr Same was of no assistance in the assessment of the amount of
the appellant's claim. In this regard, the learned trial judge said:11
"The evidence from Mr Norman Same was contained in a written
report. It is of no assistance, for two reasons. First, notwithstanding
the importance of this issue, the plaintiff did not instruct Mr Same
until mid-December 2007 – some two months before the trial and
some eight years after the events in question. It is not surprising,
given the delay by the plaintiff in dealing with this issue, that
important documents upon which Mr Same might have been able to
rely in his report were unavailable. Mr Same noted in [5] of the
summary of his opinion:
7 [2008] QSC 179 at [302].
8 [2008] QSC 179 at [302].
9 [2008] QSC 179 at [304] – [305].
10 [2008] QSC 179 at [310].
11 [2008] QSC 179 at [302] – [303].
-- 9 of 46 --
10
'5.1 My ability to accurately calculate the expenditure
that qualifies as reasonable remuneration for carrying out
building works as defined at 1.2 is limited as Cook’s
could not locate:
(a) project costing work papers or estimates
relating to the ANP project.
(b) third party invoices or statements detailing
costs of various items purchased for the ANP
project.
(c) any other supporting documentation or work
papers that would assist in confirming the
expenses incurred.
5.2 Allocated overheads are apportioned by project
revenue as a percentage of company revenue. This
allocation has not yet been tested.'
Further, his conclusion on the profit and loss statements provided to
him by CCPL was based on that company’s general ledger and no
verification was possible which distinguished the project the subject
of this action and any other project undertaken by CCPL at that time.
Thus, there was no way of identifying costs and expenses which
were solely related to the project, let alone any individual part of the
project.
Secondly, although Mr Same says that he had been 'instructed to
calculate the amount, in accordance with section 42(4) of the Act,
that Cook’s is entitled to claim as reasonable remuneration for
carrying out building works assuming all the work alleged to be
'building work' as defined by the act was 'building work' for the
project conducted on behalf of Stork …', he did not undertake that
exercise. In his calculation of reasonable remuneration he recreated a
profit and loss statement for the project rather than for any of the
parts of the undertaking alleged to be building work. This
conclusion, accurate or not, does not allow any opinion to be formed
as to the reasonable remuneration of each of the items of 'building
work'. It did not refer to any 'external standard' to define the
quantum."
[24] Mr Same's evidence could not be related to the "building work" in question. His
Honour said: 12
"Mr Same … admitted, he was not an expert in determining
reasonable costs associated with building work. Further, no effort
was made in that report to identify the reasonable remuneration for
any one of the individual claims made by CCPL alleged by Stork’s to
be 'building work'. Instead, Mr Same provides four alternative
amounts which, he says, could be reasonable remuneration for
carrying out all of the building work under the Subcontract.
At [6.25] of his report, Mr Same says:
12 [2008] QSC 179 at [310] – [313].
-- 10 of 46 --
11
'In order to calculate the reasonable remuneration that
Cook’s is entitled to, I have recreated a profit and loss
statement for the project based on the ANP profit and
loss statements concluded on above in 6.4.'
He then sets out profit and loss statement in which he arrives at a
conclusion relating to the 'reasonable cost of project'. At the foot of
the table there is a note:
'The reasonable cost of project also equals the sum of
total expenses per general ledger plus total other
expenses.'
The conclusion is irresistible that the figure referred to by Mr Same
in his report as being the 'reasonable cost of project' is, indeed, his
assessment of the cost of the entire undertaking engaged in by CCPL.
There is nothing to suggest that he has in any way attempted to
provide any amount which is able to be related to either any single
one of the 'building work' claims or all of them. That conclusion is
supported by the response by counsel for CCPL during final
submissions where he agreed that Mr Same based his report on the
entire project."
[25] The learned trial judge remarked upon the dismal attempt made by the parties to
address in the evidence the reasonable cost of the items of building work for which
remuneration was claimed. His Honour said:13
"It is unfortunate that no attention was given by two of the witnesses
called on this topic, to the fact that, in a case such as this, it will be
necessary to identify the work the subject of contention and, then, to
assess the reasonable remuneration in respect of each item (Hansen v
Mayfair Trading Co Pty Ltd [1962] WAR 148; Re Allison, Johnson
& Foster Ltd; ex parte Birkenshaw [1904] 2 KB 327). Each claim
should have been the subject of an individual assessment by those
witnesses, if they were otherwise qualified."
[26] As to the evidence of Mr Alsop, the learned trial judge said:14
"Mr Alsop’s report, like others tendered by the plaintiff, was only
made available during the trial. He was first engaged in mid
December 2007 and he says he was retained to 'present an indication
of the fair value of the works, based on the Contractual
Documentation and Other matters made available to me.' Why he
was asked to consider 'fair value' rather than 'reasonable
remuneration' was not explained. It was not a concept which was
pleaded. It is not a term found in the QBSA Act.
In re-examination, Mr Alsop said that, in his opinion, there is no
difference between a reasonable rate and the concept of a fair value.
That may well be correct, but it does not deal directly with the
concept of 'reasonable remuneration', of which a rate may only be
one part of the assessment.
13 [2008] QSC 179 at [304].
14 [2008] QSC 179 at [306] – [308].
-- 11 of 46 --
12
His report is called in aid for other claims which are considered
elsewhere, but on the issue of 'reasonable remuneration' it is of no
assistance for the following reasons:
(a) Some of the documents upon which he relied
were not in evidence, namely:
(i) Report of Simon Tormey &
Associates, Chartered Quantity
Surveyors, 16 August 2005;
(ii) Claim for Differences following Stork
April Assessment, undated;
(iii) file marked Miscellaneous Documents
including 'Notes on Major differences
between Cook's April Progress Claim
and Stork's Assessment' and two
affidavits of Warren Eddie;
(iv) the drawings (listed in Appendix B)
which were supplied to Mr Alsop.
(b) Mr Alsop relied upon measurements obtained
using a digitiser but it was not established that
the plans he used were those which were
pleaded or in evidence.
(c) It cannot be determined from his report
whether he used the profiles or dimensions
marked up on the pleaded drawings.
(d) When he expressed a view with respect to the
'building work' claims he referred to the 'value'
of each item and not the 'reasonable
remuneration' for each item."
[27] It was not argued on the appeal that any of these observations by the learned trial
judge were affected by error of fact or law.
[28] His Honour accepted the abstract proposition that a contract, though unenforceable
by a builder as a source of a right to payment for its work, might be referred to as
evidence of reasonable rates for the purpose of calculating reasonable remuneration
under s 42(4) of the Act.15 But in the circumstances of this case, the subcontract
provided no assistance in the assessment of reasonable remuneration for the
building work the subject of the counterclaim. In this regard, the subcontract was
concerned with, and gave a price and rates for, work which included, but did not
consist solely of, "building work" within the meaning of the Act. More importantly,
the subcontract rates clearly included an element of profit to the appellant: there
was evidence that the appellant's rates for some of the building work under the
subcontract were higher than the rates quoted to the appellant by subcontractors
engaged by the appellant to actually do the work; and the appellant was a
commercial, not a charitable, enterprise.
[29] His Honour concluded:16
"I was invited by the plaintiff to engage in an exercise whereby I
would compare the reasonable remuneration assessed by Mr Same
15 [2008] QSC 179 at [295].
16 [2008] QSC 179 at [314] – [315].
-- 12 of 46 --
13
($16.153 million) with the amount paid to the plaintiff ($16.425
million) and that I could then order a reimbursement of the defendant
by the plaintiff in an amount equal to the difference between those
two figures. Other means of arriving at the 'reasonable remuneration'
for the total of the items included in the 'building work' were also
suggested in submissions, but none of them could overcome the
principal problem – no attempt had been made to assess 'reasonable
remuneration'.
Another argument was advanced that CCPL, having made a loss on
the entire operation, should be able to claim anything that was
expended by CCPL as 'reasonable remuneration'. Apart from the
doubtful integrity of that as an accounting exercise, it does not
necessarily follow that the making of a loss means that the amount
charged was reasonable. History is replete with instances of
businesses making losses even when their prices were unreasonably
high."
[30] The learned trial judge awarded the respondent $5,526,148.20 by way of interest
pursuant to the discretion conferred by s 47 of the Supreme Court Act 1995 (Qld).
In making this award the learned trial judge rejected the appellant's submission that
interest should not be awarded as it would give the respondent a windfall.17 His
Honour said: 18
"The plaintiff argued that the defendant was not entitled to any
interest. It submitted that Stork had not suffered damage, loss or
injury by reason of CCPL being unlicensed under the Queensland
Building Service Act but that Stork had received a very substantial
windfall gain. It was submitted that Stork had the benefit of the
building works performed by CCPL but will not be required to pay
for them. I do not accept that Stork 'had the benefit of the building
works'. It was a contractor, not the principal. As I have observed
earlier in these reasons, it is possible that Stork has not been paid by
the principal for the relevant work. It must also be observed that the
amount of the counterclaim which might, on a preliminary reading,
seem extraordinarily large compared to the claim of the plaintiff,
must be viewed in the light of the finding that the plaintiff failed to
prove any amount by which it could be afforded reasonable
remuneration as contemplated under the Queensland Building
Services Authority Act. Had such evidence been provided then it
would have been likely that the counterclaim would have been
substantially diminished."
The arguments on appeal
[31] The appellant's first submission on the appeal is that the respondent's counterclaim
should have been dismissed by the learned trial judge because the respondent failed
to prove that the progress payments for the building work were made under a
mistaken belief that the appellant was not entitled to receive the payments made to
it. The appellant's point here is that, although Mr Jewell caused the payments to be
made on the basis of his mistaken belief that the respondent was obliged to make
17 Cook's Construction P/L v Stork Food Systems Aust P/L [2008] QSC 220 at [42].
18 [2008] QSC 220 at [42].
-- 13 of 46 --
14
the progress payments under the subcontract, the respondent failed to show that the
appellant was not entitled to any reasonable remuneration in accordance with
s 42(4) of the Act.
[32] The appellant's second submission is that the learned trial judge erred in failing to
reject the counterclaim because the respondent was unable to make restitutio in
integrum of the benefit it had received from the appellant's work.
[33] The third submission pressed for the appellant on appeal is that the learned trial
judge erred in concluding that there was "no evidence upon which the provisions of
s 42(4) can act."19 The appellant says that because there was a claim of some, albeit
unquantified, value under s 42(4) of the Act, the respondent's claim was bound to
fail in toto. Alternatively, the appellant contends that on any view of the evidence,
there was a sufficient basis for a claim which might be made out in conformity with
s 42(4) of the Act. In this latter regard the appellant contends that reference to the
terms of the subcontract and to the certifications by the respondent's own
representative allows a calculation of reasonable remuneration within the meaning
of s 42(4) of the Act.
[34] The parties to the appeal are at odds as to the incidence of the onus of proof of the
appellant's entitlement to reasonable remuneration in accordance with s 42(4) of the
Act. The respondent says that this dispute is of academic interest only because, by
its pleadings, the appellant assumed the burden of proving its entitlement to
reasonable remuneration under s 42(4) of the Act. The appellant simply failed to
make out its claim, and that conclusion is sufficient to dispose of the appeal. The
respondent also says that it was for the appellant to make good the claim which it
asserted for reasonable remuneration in conformity with the requirements of s 42(4)
of the Act, rather than for the respondent to negative the appellant's entitlement
under s 42(4).
[35] The appellant's fourth argument is that the learned trial judge's exercise of the
discretion to award interest miscarried in that his Honour failed to appreciate that
the respondent "obtained from the appellant the value which it had contracted to
obtain; never returned what it had obtained and never contended that the value was
not worth what it paid."
[36] As the first three arguments concern s 42 of the Act, it is convenient to address now
the true operation of s 42 of the Act.
The operation of s 42 of the Act
[37] Section 42(1) renders illegal the making and performance of a contract for building
work by an unlicensed builder. It is the conduct of the builder which is struck at.
The provision is plainly intended to operate for the benefit of the other party to the
building contract.
[38] It is clear from the terms of s 42(3) and s 42(4) that neither provision purports to
create a right of action to recover money in any person. Rather, each subsection is
concerned to regulate a cause of action for payment which is assumed to have
arisen, either under contract or under the principles of the common law which
permit claims for payment for work done at the request of another. These common
19 [2008] QSC 179 at [316].
-- 14 of 46 --
15
law claims have been variously described as claims for quantum meruit or in
quasi-contract or to prevent unjust enrichment.20
[39] Section 42(3) is, in terms, concerned to sterilise any claim which might otherwise
be made under a contract or under the common law by an unregistered builder.
Section 42(4) is concerned to impose limitations upon the right of action at common
law which it preserves against the sterilising effect of s 42(3). Without s 42(4), the
entitlement of an unregistered builder to payment which would, apart from the Act,
arise upon the performance of work by the builder, would be defeated by s 42(1)
and s 42(3).
Section 42(4) and the onus of proof
[40] In my opinion, the course taken by the appellant below in assuming the onus of
proof of its claim pursuant to s 42(4) of the Act was correct. The language of
s 42(3) and s 42(4) of the Act is a clear statement of legislative intention that an
unlicensed builder may recover payment for building work carried out in
contravention of s 42(1) and contrary to s 42(3), but only to the extent that it proves
a claim in conformity with s 42(4). As I have said, no right of action is conferred by
s 42(4) of the Act. Rather, s 42(4) assumes the existence of a common law right to
remuneration which it preserves against the operation of s 42(3) while at the same
time imposing conditions upon the availability and extent of that right. Unless the
builder has a good claim conforming to these conditions, the builder's right to
reasonable remuneration cannot avail the builder against the operation of s 42(3).
[41] It is true that, as the appellant argues, the operation of s 42(3) of the Act is qualified
by s 42(4). But it is also clear that s 42(4) permits an unlicensed builder to claim
"reasonable remuneration for carrying out building work, but only if the amount
claimed" satisfies the criteria in paragraphs (a) to (d). It is only the amount of the
claim so quantified that the builder may recover despite s 42(3). Absent a good
claim so quantified, the operation of s 42(3) is, for practical purposes, unqualified
by s 42(4). If the legislature had intended that s 42(3) as amended should read
"Subject to the absence of any claim under subsection (4)", so as to cast the burden
of disproof of any claim for reasonable remuneration on the other party to the
contract, it could easily have said so.
[42] In my respectful opinion, it is important that the concern of the courts to avoid an
unjust outcome in a particular case should not distort the operation of a statute
intended to encourage the licensing of builders by disadvantaging unlicensed
builders and advantaging consumers of building services at their expense. It is
hardly surprising that the legislature should have left the burden of proving a claim
for reasonable remuneration on the builder. What would have been surprising
would have been a provision which cast the burden of disproof of an unlicensed
builder's claim on the consumer of building services. What is most surprising, of
course, is the failure of the builder in this case to adduce evidence capable of
proving a claim for an amount of reasonable remuneration in conformity with
s 42(4) of the Act.
[43] Ordinarily, the law expects that "he who asserts must prove". There is a number of
textual indications that this expectation has not been altered in the case of s 42(4) of
the Act. First, as I have already said, s 42(4) contemplates the making of a
20 Cf Gino D'Alessandro Constructions Pty Ltd v Powis [1987] 2 Qd R 40 at 54 – 56; Pavey &
Matthews Pty Ltd v Paul (1987) 162 CLR 221.
-- 15 of 46 --
16
quantified claim by an unlicensed builder. There can be no doubt that where the
builder is making a claim to recover payment of reasonable remuneration which has
not been paid by the other party, the builder bears the onus of proving the amount to
which it is entitled in conformity with s 42(4). There is no indication in the text of
s 42 that the onus of proof shifts to the other party (and becomes an onus of
disproof) if progress payments have been made under the contract which s 42(1)
and (3) have sterilised. It would be distinctly odd if the onus of proof of a claim
under s 42(4) were to be altered by the fortuitous circumstance of the making or
non-making of a progress payment by the other party to the contract.
[44] Secondly, the evident policy of the Act is to improve building standards and to
protect the interests of those who depend on the provision of services by builders.
To this end the Act requires builders to be licensed. It is unlikely that the legislature
intended to cast upon persons to whom building services are provided, many of
whom will be unsophisticated consumers, the onus of establishing the reasonable
remuneration payable to the unlicensed builder in conformity with s 42(4). This is
especially so when one bears in mind the practical reality that the information
necessary to formulate such a claim in conformity will be in the possession of the
builder.
[45] The appellant's submission, as it ultimately emerged under the pressure of argument
on the appeal, was that the introduction of the words "subject to subsection (4)" in
s 42(3) by the 1999 amendments had the effect that, so long as there was some
apparent basis for a claim by an unlicensed builder for reasonable remuneration for
building work – even though that claim might be unquantified – the other party to
the transaction could not enforce a claim under s 42(3) for the recovery of money
paid to the unlicensed builder. The appellant argued that, although its claim in this
case might not have been quantified by the evidence which it adduced, nevertheless
it was sufficiently apparent that it had a real basis for a claim to some amount in
conformity with s 42(4) that the respondent could not enforce a claim for recovery
of payments made for the work, unless the respondent itself discharged the burden
of proving that the amount properly claimed by the appellant in conformity with
s 42(4) was less than the amount of payments already made by the respondent. In
that event the respondent would be entitled to recover only the amount of any
balance whereby the payments made by it overstepped the amount properly due to
the builder by way of reasonable remuneration.
[46] This submission has the attraction of affording a plausible basis whereby the
apparent injustice of the outcome in this case might be avoided. Fundamental to
this submission, however, is the proposition that a person who has paid an
unlicensed builder for building work is obliged to discharge the onus of proof of the
amount properly recoverable by the unlicensed builder in accordance with s 42(4) as
a condition of a claim for the recovery of the amount paid to an unlicensed builder.
As I have endeavoured to explain, that proposition derives no support, either from
the text of s 42, or from the policy of the section.
[47] For these reasons, I conclude that it is only to the extent that a claim for reasonable
remuneration is made out by the builder in conformity with s 42(4) that the
operative effect of s 42(3) upon the rights and liabilities of the parties is affected.
The operation of s 42(3)
[48] It is convenient now to consider more closely the legal effect of s 42(3) upon the
rights and liabilities of the parties to a contract which involves the performance of
building work.
-- 16 of 46 --
17
[49] In Marshall v Marshall,21 McPherson JA identified the entitlement in the payer to
recover moneys paid to an unlicensed builder as the reciprocal of the builder's
disentitlement to receive the payment. On this analysis, no other fact, such as, for
example, mistake on the part of the payer, is necessary to give rise to the payer's
cause of action for recovery of the moneys paid. McPherson JA said:
"In my opinion, the effect of s. 42(3) is to prevent an unlicensed
builder, in proceedings of any kind, from recovering the price or any
part of it payable under a contract for building work carried out in
contravention of the section. Taken by itself, that might perhaps not
prevent a builder from receiving money voluntarily paid by the other
party. The terms of s. 42(3) are, however, very wide. A person who
carries out work in contravention of s. 42 is 'not entitled' to any
'monetary consideration' for doing so. According to the ordinary
meaning of those words, a person receives a 'monetary consideration'
for carrying out work if he is paid for doing it. The sum of $51,000
paid by the plaintiff to the defendant satisfies that description.
Counsel were unable to refer the Court to authority bearing in any
relevant way on the meaning of 'entitled' in a context like this. But
s. 42(3) expressly declares it to be money to which the recipient is
'not entitled', which can only mean that it is money to which he
has in law no right or title. If that is so, there is no identifiable
basis on which he can, as against the person who paid it, claim to
keep or retain it or its equivalent." (emphasis added)
[50] This reasoning is to the same effect as that of Brennan J in David Securities Pty Ltd
v Commonwealth Bank of Australia:22
"… when a plaintiff has paid money for a consideration that has
totally failed, the defendant's unjust enrichment consists in his
retaining money which, when the consideration fails, he no longer
has any right to retain (Fibrosa Spolka Akcjna v Fairbairn Lawson
Combe Barbour Ltd [1943] AC at 65). Enrichment is unjust because
the defendant has no right to receive or, as the case may be, to retain
the money or property which the plaintiff has paid or transferred to
him (Restitution lies when property has passed: Barclays Bank v W J
Simms Ltd [1980] 1 QB 677 at 689. If mistake affects the passing of
the property, the plaintiff may be entitled to proprietary remedies)."
[51] It is, I think, a compelling consideration that in the 10 years since the decision in
Marshall v Marshall was delivered by this Court, the legislature has not expressed
its disapproval of, or an intention to alter, the legal effect which McPherson JA
attributed to the operation of s 42(3). The appellant says that this is not so because
s 42(3) is now expressed to be subject to s 42(4), but when the legislature
introduced s 42(4) into the Act, it did not seek to alter the juridical operation of
s 42(3) as explained by McPherson JA. The amendments introduced in 1999 served
to limit the circumstances in which s 42(3) would operate by subjecting the scope of
the operation of s 42(3) to cases where s 42(4) conferred on the unlicensed builder
the right to payment of an amount calculated in accordance with its provisions. But
s 42(4) was not expressed to alter the consequences of the operation of s 42(3) in
those circumstances where its operation was unaffected by s 42(4).
21 [1999] 1 Qd R 173 at 176.
22 (1992) 175 CLR 353 at 393 (citations footnoted in original).
-- 17 of 46 --
18
[52] In Pavey & Matthews Pty Ltd v Paul,23 Deane J said of the disentitling statute there
in question:
"The section does not make an agreement to which it applies illegal
or void. Nor do its words disclose any legislative intent to penalise
the builder beyond making the agreement itself unenforceable by
him against the other party."
[53] Section 42 of the Act exhibits a clear intention to render illegal both the making and
the performance of a contract by an unlicensed builder insofar as building work is
concerned. Section 42(3) makes it clear that the consequence of a contravention of
s 42(1) by an unlicensed builder is that the builder is unable to recover payment for
unlicensed building work. Those consequences include the recovery of payments
made to the builder by the other party to a contract for unlicensed building work.
[54] In Marshall v Marshall McPherson JA gave, by reference to the text and legislative
history of s 42(3) of the Act – which at that time had not been amended by the
measures which incorporated the current s 42(4) – compelling reasons for the
conclusion that the Act was intended to disentitle an unlicensed builder from
receiving or retaining any payment on any basis for any building work performed
by it. His Honour's reasons in this regard were approved by this Court in Sutton v
Zullo Enterprises Pty Ltd. 24 It is worth setting out at length the passage from
Marshall v Marshall because it will be seen that it was at this aspect of his Honour's
reasons that the 1999 amendments were directed. McPherson JA said: 25
"There are several, and I consider, persuasive reasons for adopting
such an interpretation of s. 42. First, there is the history of the
legislation. The corresponding provision of the Builders’
Registration and Home-owners’ Protection Act 1979, which was
repealed by the current Act of 1991, was s. 53(2)(d). It originally
provided that a person who was not a registered builder should not be
'entitled to recover by action in a court a fee or charge under a
contract to perform building construction for another…'. In Gino
D’Alessandro Constructions Pty Ltd v. Powis [1987] 2 Qd.R. 54, it
was held that, in that form, s. 53(2)(d) did not prevent recovery, as a
debt due and owing, for money for work done, or, as the High Court
preferred to regard it, as restitution for unjust enrichment. See Pavey
& Matthews Pty Ltd v. Paul (1987) 162 C.L.R. 221. After that
decision, s. 53(2)(d) was revised by amending it to provide that a
person not a registered builder should not:
'(d) be entitled to claim, sue for or otherwise
recover … any fee, charge, damages or other
reward of whatever nature in respect of the
building construction performed or agreed to
be performed.'
However, in Mostia Constructions Pty Ltd v. Cox [1994] 2 Qd.R. 55,
White J. held that, even in that form, s. 53(2)(d) did not specifically
preclude recovery of the amount of the builder’s outlays on labour
and materials the benefit of which had been accepted by the party
who had requested them.
23 (1987) 162 CLR 221 at 262.
24 [2000] 2 Qd R 196 at 204 [8], 206 [16].
25 [1999] 1 Qd R 173 at 176 – 178.
-- 18 of 46 --
19
Section 42 is thus the third attempt by the legislature to make its
meaning clear. On this occasion it may be credited with having
intended to cast the net as widely as possible. An unlicensed builder
is, as s. 42(3) now provides, not entitled to any monetary
consideration for carrying out building work. A principal object of
the legislation, both in its original and in its current form, is to
prevent unlicensed builders from doing certain kinds of building
work. Substandard workmanship and materials are, plainly enough, a
principal target of the statutory prohibition: see s. 3(a)(i). Preventing
incompetent and unlicensed builders from doing building work, and
penalising them if they do so, is one method of achieving that object.
On occasions, however, even competent builders make mistakes and,
having done so, sometimes become insolvent or for other reasons are
not worth suing for the loss sustained. One object of the legislation
was, as I suggested in Gino D’Alessandro Constructions v. Powis
[1987] 2 Qd.R. 40, 54–56, to establish and maintain the insurance
scheme, which is now contained in Part 5 of the Act. It is funded by
premiums paid by building contractors, from which claims by
building owners or 'consumers' can be satisfied: cf. Pavey &
Matthews Pty Ltd v. Paul (1987) 162 C.L.R. 221, 229.
Under the statutory scheme, a building contractor must, before
commencing residential construction work, pay to the Queensland
Building Services Authority the appropriate insurance premium:
s. 68(1). When an insurance premium is paid in respect of residential
construction work, a certificate of insurance issues: s. 69(1). The
insurance policy comes into force if a consumer (meaning a person
for whom the building work is carried out) enters into a contract for
the performance of residential construction work, in which event the
contract is imprinted with a licensed contractor’s licence card
endorsed to show that the licensee may lawfully enter into contracts
to carry out residential construction work: see s. 69(2). It is true that
s. 69(2) applies whether or not an insurance premium has been paid
or an insurance certificate has issued: s. 69(3). It would nevertheless
go far to diminish the funding available for the statutory insurance
scheme if unlicensed builders were able to receive and retain money
for doing residential construction work without complying with these
provisions and with the licensing requirements of the Act. The
insurance fund would be progressively depleted without receiving
many of the premiums that were intended to form its source.
Another reason for concluding that an unlicensed builder is by
s. 42(3) not entitled to receive or retain money paid for doing
building work is to be found in analogy with other legislation of a
comparable kind. The Act obviously has a regulatory function of
which the main object is to protect building owners or 'consumers'
from incompetent or dishonest builders: cf. the statutory objects
stated in s. 3(b). In Cornelius v. Phillips [1918] A.C. 199, a statutory
prohibition against money lending otherwise than at the lender’s
registered address was held to render the contract unenforceable. In
Mayfair Trading Co. Pty Ltd v. Dreyer (1958) 101 C.L.R. 428,
449–450, Dixon C.J., with whom McTiernan J. agreed, held that a
-- 19 of 46 --
20
money lender, who, in contravention of the statutory prohibition
rendering the loan unenforceable, had succeeded having it repaid,
was liable to disgorge the payment received. The money, said the
learned Chief Justice, was 'obtained, paid over and retained without
lawful authority, and there could be no answer on the facts to a
simple claim on the part of the plaintiffs in a common money count.
This is true of a count for money had and received …'. The
prohibition being intended to protect the class of borrowing
consumers, a person belonging to that class was entitled to recover
moneys or securities transferred in pursuance of the illegal
transaction: Bonnard v. Dott [1906] 1 Ch. 740. As an exception to
the general rule of law, the fact that a transaction is illegal does not
disbar a person whom the legislation is intended to protect from
recovering money paid over in pursuance of the transaction. See
Kiriri Cotton Co. v. Dewani [1960] A.C. 192, on which Mr Logan
for the respondent plaintiff relied in this appeal."
[55] Subsection 4 of s 42 of the Act was introduced in 1999, pursuant to the Queensland
Building Services Authority Amendment Act 1999 (Qld). The Explanatory Note to
the Bill stated:
"Until the 1998 decision of the Court of Appeal in Zullo Enterprises
& Ors v Sutton [1998] QCA 417 (15 December 1998), it was thought
that s 42, which makes the carrying out or undertaking to carry out of
building work unlawful, did not prevent unlicensed contractors
recovering their costs under the common law of contract. The Zullo
decision held that unlicensed contractors were prevented from
recovering anything at all, and held the prospect that unlicensed
contractors could be successfully sued for recovery of any moneys
paid for prior performance. This potentially allows considerable
injustice, such as deliberate recruiting of subcontractors from
interstate and legally escaping from any obligation to pay for work
performed.
Unlicensed contracting will, of course, remain an offence committed
by the contractor, but the principle that a builder or owner should
not be able to enrich themselves through signing on unlicensed
contractors is enshrined in this clause.
This clause amends s 42(3) and inserts a new subsection 42(4) to
provide an unlicensed contractor with a limited statutory right to
recover money which would otherwise be unavailable because of
the Zullo decision. The new provisions will allow an unlicensed
contractor to claim reasonable recovery of moneys actually
expended for the supply of materials and labour, other than the
contractor’s own labour and profit. Existing subsections 42(4) to
(6) are renumbered.
The new provision in s 42(4)(iii) also prevents an unlicensed
contractor unreasonably incurring costs and claiming for
recovery under this provision.
-- 20 of 46 --
21
S 42(4)(c) prevents an unlicensed contractor recovering any more
under this provision than the contract price.
S 42(4)(d) is designed to attack any scheme entered into by the
unlicensed contractor, for example employing the contractor’s child
or the charging of a management fee by a company of which the
contractor is a beneficial shareholder, to use this new provision to
gain personal profit from unlicensed contracting." (emphasis added)
[56] The purpose of the amendment was explained further in the Second Reading Speech
for the Queensland Building Services Authority Amendment Bill 1999 (Qld), in
which the Minister said:
"The Bill also remedies the potential for unfairness which emerged
last year following a Court of Appeal decision in Zullo Enterprises
and Others versus Sutton. The intention of the regulatory scheme has
always been that building contractors be licensed. It is not the
intention, therefore, that builders and developers have incentives to
engage unlicensed contractors. The court found that, contrary to
previous belief, the Act prevents an unlicensed building contractor
from recovering any money at all under a contract. This opens the
door for unjust enrichment of unscrupulous developers and builders,
potentially encouraging them to engage unlicensed contractors.
The Bill rectifies this situation by allowing unlicensed
contractors to recover any moneys that they have reasonably
spent while performing building work. But unlicensed
contractors cannot recover any profit or receive any more than
the contract price specified in the purported contract. They will
also be penalised for the offence of operating without a licence. In
addition, building contracts are required to include the licence
number of the contracted party." (emphasis added)
[57] It is apparent from these excerpts from the extrinsic materials that the 1999
amendments were not directed to dissatisfaction with the juridical nature of the
operation of s 42(1) and s 42(3) of the Act as explained in Marshall v Marshall, but
were concerned to limit the scope of the operation of these provisions by reference
to a limited right to reasonable remuneration in an unlicensed builder. Subject to an
entitlement in the builder under s 42(4), s 42(3) operated, both to deny a claim by an
unlicensed builder for payment for building work, and to oblige the builder to
disgorge payments received by it for the work. The extrinsic materials show that
the mischief at which the 1999 amendments to the Act were directed was the denial
of all remuneration to an unlicensed builder. The amendments were not concerned
to alter the operation of s 42(3) so as to allow an unlicensed builder to retain any
payments made to it by the other party. The operation of s 42(3) was to be limited
only to the extent that the builder was entitled to reasonable remuneration in
conformity with the criteria in s 42(4). Beyond the amount of that entitlement, the
consequences of s 42(3) were to be unaltered.
[58] On the analysis of McPherson JA referred to in the passage cited in paragraph [38]
above, mistake on the part of the payer as to its obligation on the payee's entitlement
is not an essential element of the builder's disentitlement to receive or retain
payment or the payer's reciprocal entitlement to recover. On this analysis, unless
-- 21 of 46 --
22
the respondent was in pari delicto with the appellant, the respondent was entitled to
recover the moneys paid by it to the appellant as moneys had and received by the
appellant to the use of the respondent.
[59] It may well be that a payer who knowingly engaged an unlicensed builder to carry
out building work in contravention of s 42 would be held to be in pari delicto with
the builder so as to be outside the class of persons for whose benefit a right of
recovery is made available in consequence of the operation of s 42(3) of the Act. So
far as the present case is concerned, that would mean that, even if the respondent's
payments were not made by mistake, on no view of the pleadings or the evidence
could it be held that the respondent was in pari delicto with the appellant. The
appellant had given the respondent an express contractual promise that it, the
appellant, held all necessary licences, and there was no suggestion in the appellant's
pleadings that the respondent knew that the appellant was unlicensed. In the case
made by the appellant at trial there was, to adopt the words of McPherson JA,
simply no identifiable basis on which it could, as against the respondent, claim to
keep or retain the payments made by the respondent or their equivalent.
Summary as to the operation of s 42 of the Act
[60] In summary then, the entitlement of the respondent to recover the moneys paid by it
by virtue of s 42(3) was circumscribed only insofar as the appellant was able to
make out a right to recover an amount for reasonable remuneration in conformity
with s 42(4) of the Act. Section 42(4) permits the builder that amount from the
moneys paid to it. In this way s 42(4) remedies the mischief at which the 1999
amendments to s 42 were directed. But the entitlement of the unlicensed builder to
recover or retain moneys paid to it is limited to the amount of reasonable
remuneration claimed in conformity with the requirements of s 42(4) of the Act.
This view of the operation of s 42(3) and s 42(4) has implications of relevance for
the issues on the appeal. First, the onus of proving the amount of a claim in
conformity to s 42(4) is upon the unlicensed builder who claims the entitlement.
And secondly, to insist upon a more extensive limitation upon the payer's right of
recovery, for example, one based on its inability to make restitutio in integrum –
whether in money or money's worth – is to introduce a qualification upon the
payer's right of recovery which is consequential upon the operation of s 42(3). That
qualification urged by the appellant cannot be accepted: its acceptance would
defeat the operation of s 42(3).
[61] Whether or not, and the extent to which, the appellant was entitled to resist the
respondent's counterclaim on the basis of the appellant's entitlement to reasonable
remuneration depended upon its ability to make good a claim to reasonable
remuneration in conformity with s 42(4) of the Act. That, in turn, depended upon
the formulation and proof of a claim for reasonable remuneration in conformity with
s 42(4) of the Act. Considerations of convenience also favour this view. To the
extent that the appellant was required to address the specific requirements of s 42(4)
of the Act in propounding its claim, these requirements related to matters peculiarly
within its own knowledge.
[62] In my respectful opinion, for the reasons set out above and which are derived from
the statutory text and considerations of principle, policy and practical convenience,
the onus was upon the appellant to make good a claim for an amount of reasonable
remuneration under s 42(4) of the Act. Absent proof of such an entitlement, the
respondent's counterclaim was bound to succeed. This conclusion reflects the text
-- 22 of 46 --
23
and structure of s 42 and gives effect to the intention discernible from the relevant
extrinsic evidence of legislative intention.
The appellant's first argument: Mistake as to liability
[63] The appellant argues that the respondent's cause of action for repayment of the
moneys the subject of the counterclaim could not be established without proof that
the moneys were not payable under s 42(4) of the Act. Without such proof, it could
not be said, so the appellant argues, that the payments were made under a mistake as
to the appellant's entitlement to receive them. The appellant's argument is that if it
were the case that the appellant had, in truth, an entitlement to reasonable
remuneration under s 42(4) of the Act, then, although Mr Jewell may have been
mistaken in his belief that the appellant was entitled to be paid under the provisions
of the subcontract, the appellant was nevertheless entitled to retain the moneys as
reasonable remuneration and they were not paid because of a mistake as to its true
entitlements. The appellant refers to the following passage from the reasons of
Mason CJ, Deane, Toohey, Gaudron and McHugh JJ in David Securities Pty Ltd v
Commonwealth Bank of Australia:26
"… the payer will be entitled prima facie to recover moneys paid
under a mistake if it appears that the moneys were paid by the
payer in the mistaken belief that he or she was under a legal
obligation to pay the moneys or that the payee was legally
entitled to payment of the moneys. Such a mistake would be
causative of the payment." (emphasis added by the appellant)
[64] The appellant also refers to an earlier statement in the joint judgment where their
Honours said: 27
"For the reasons stated above, the rule precluding recovery of
moneys paid under a mistake of law should be held not to form part
of the law in Australia. In referring to moneys paid under a mistake
of law, we intend to refer to circumstances where the plaintiff
pays moneys to a recipient who is not legally entitled to receive
them. It would not, for example, extend to a case where the
moneys were paid under a mistaken belief that they were legally
due and owing under a particular clause of a particular contract
when in fact they were legally due and owing to the recipient
under another clause or contract." (emphasis added by the
appellant)
[65] The appellant's submission under this heading is that a prima facie case for the
recovery of moneys paid by mistake requires not only a causative mistake as to a
matter of fact or law which leads to the making of the payment, but the payer must
also negative the possibility that the payee might be entitled to the payment by
reason of a matter other than the mistaken matter of fact or law. The authorities are
not entirely clear upon this point, but it can be seen that the observations of the High
Court in David Securities upon which the appellant relies do not provide clear
support for the appellant. That is because the High Court's observations were
directed to the case where the payee's entitlement to the payment in question was
established by the same charter of rights operating upon the same facts as revealed
that the payment was caused by mistake. That was not the case here. The payments
26 (1992) 175 CLR 353 at 378.
27 (1992) 175 CLR 353 at 376.
-- 23 of 46 --
24
made by the respondent were made solely on the footing that it was to discharge the
appellant's entitlement to a progress payment under the subcontract. Not only did
Mr Jewell not advert to the possibility that the appellant's claim reflected reasonable
remuneration for the building work performed by the appellant, Mr Jewell had no
power or authority to certify for payment in that regard.
[66] In Barclays Bank v W J Simms Son & Cooke (Southern) Ltd,28 Robert Goff J
deduced the following propositions from the authorities:
"(1) If a person pays money to another under a mistake of fact which
causes him to make the payment, he is prima facie entitled to recover
it as money paid under a mistake of fact. (2) His claim may
however fail if (a) the payer intends that payee shall have the money
at all events, whether the fact be true or false, or is deemed in law to
so intend; or (b) the payment is made for good consideration, in
particular if the money is paid to discharge, and does discharge, a
debt owed to the payee … by the payer … or (c) the payee has
changed his position in good faith, or is deemed in law to have done
so."
[67] In David Securities the High Court referred to this passage with evident approval
while expanding the scope of recovery permitted for mistake to mistake of law. In
Bank of New South Wales v Murphett,29 Starke J, with whom King J agreed, treated
the passage as confirming that it is the payee who must establish an entitlement to
payment apart from the mistake which caused the payment as a matter of defence to
the claim for recovery. It is not necessary to attempt to state a general rule here. It
is, I think, sufficient to say that in this case the appellant's only entitlement to retain
the payments made to it depends on the proof of a claim for an amount of
reasonable remuneration in conformity with s 42(4) of the Act. That onus is, in my
respectful opinion, clearly cast by the Act upon the unlicensed builder, ie the
appellant in this case.
[68] The appellant argues that the changes made to the legislation and the extrinsic
material cited above reveal legislative dissatisfaction with the position achieved in
Zullo (and, necessarily, the earlier decision of Marshall v Marshall). As I have said,
however, what is apparent, both from the text of the amended section and the
extrinsic material, is that there was no attempt to alter that aspect of the operation of
s 42(3) identified in the analysis of McPherson JA as the reason why the payer may
recover from the unlicensed payee money paid as the reciprocal of the unlicensed
payee's disentitlement and the absence of any pleaded basis upon which that
disentitlement might be overcome.
[69] It will be apparent that I consider that the appellant's argument must fail because it
misunderstands the relationship between s 42(3) and s 42(4) of the Act, and the
necessary ingredients of the cause of action for recovery of the payments made to
the appellant. The appellant's argument also involves a departure from the case
made by the appellant at trial.
[70] At trial, the appellant did not attempt to rely upon the absence of a belief on
Mr Jewell's part that the appellant had no rights under s 42(4) of the Act as a ground
on which the counterclaim should fail. Mr Jewell was never asked to consider the
28 [1980] QB 677 at 695.
29 [1983] 1 VR 489 at 492.
-- 24 of 46 --
25
possibility that, although the appellant had no contractual entitlement, he might
nevertheless have authorised payment on the basis that the appellant might be able
to establish a claim for reasonable remuneration under s 42(4) of the Act. Simply to
frame the question which was never asked of Mr Jewell is to demonstrate the
extreme artificiality of the appellant's point. It is entirely unlikely that Mr Jewell
would, for a moment, have considered that he might properly certify progress
claims for payment outside the contract on the basis that they represented
reasonable remuneration. Mr Jewell's authority and obligation to certify derived
from the contract as he clearly understood. The appellant did not attempt at trial to
establish the contrary.
[71] In any event, I consider that, as the second passage cited above from the reasons in
David Securities shows, moneys paid under a mistaken belief that the payer was
under a legal obligation to pay would be recoverable unless the payee had, in truth,
an entitlement to the moneys. That passage was speaking of a demonstrated
entitlement, not merely an arguable case, to obtain the moneys. The appellant failed
to demonstrate its entitlement when it had the opportunity to do so.
Restitutio in integrum?
[72] The appellant argues that the respondent's inability to restore to the appellant the
work performed by the appellant for the respondent's benefit, or its failure to offer
to make an equivalent monetary restitution was fatal to the respondent's
counterclaim. The submission is that the respondent's counterclaim is a
restitutionary claim which is barred if restitutio in integrum is not possible.30 In this
regard, the appellant invokes a number of statements by academic authors such as
that in The Law of Restitution by Goff and Jones 31 where the learned authors say:
"The essence of the limiting principle that restitutio in integrum must
be possible is that it would be inequitable to require the defendant to
make restitution if he cannot be restored to his original position. Its
application is not confined to the rescission of transactions or to
transactions for the recovery of money paid. Indeed, a similar
principle underlies the defences of change of position and payment
over."
[73] There are a number of points to be made about this submission. The first is that the
only decisions which support the necessity for restitutio in integrum are concerned
with cases of rescission of contract, and the respondent's counterclaim does not
depend upon the exercise of a right to rescind the subcontract. Accordingly, no
question of a mutual restoration of the parties to their pre-contractual position
arises.
[74] Secondly, the respondent's cause of action was to recover moneys paid by the
respondent to the appellant in circumstances where it was a consequence of s 42(3)
of the Act that those moneys were recoverable by the respondent.32 Since the
respondent's counterclaim arose by virtue of the terms of the Act, the question
whether restitutio in integrum was a condition of the appellant's liability to refund
the moneys to which it has no title was to be determined against the appellant as a
matter of legislative intention. As Dixon CJ explained in Mayfair Trading Co Pty
30 Clarke v Dickson (1858) 120 ER 463; Alati v Kruger (1955) 94 CLR 216 at 223 – 224; Vadasz v
Pioneer Concrete (SA) Pty Ltd (1995) 184 CLR 102.
31 2002, Sweet & Maxwell, London at [1-084].
32 Roxborough v Rothmans of Pall Mall Ltd (2001) 208 CLR 516 at 544 – 545.
-- 25 of 46 --
26
Ltd v Dreyer,33 while principles of equity may require restitutio in integrum as a
condition of making orders to restore parties to their respective pre-transactional
positions, that position may be altered by the terms of the legislation which allows
the transaction to be impugned. To argue that the absence of restitution (in money
or money's worth) is fatal to the respondent's counterclaim is necessarily to ignore
that s 42(3) of the Act affords the basis for the recovery of money paid by any
owner to an unlicensed builder. To the extent that s 42(4) ameliorates the position
of the builder, it is an exhaustive statement of that amelioration.
[75] A third point was made by the respondent in answer to the appellant's submission
under this heading. The respondent's failure or inability to make restitutio in
integrum was not raised below on the appellant's behalf, by way of defence in
answer to the respondent's counterclaim or otherwise. If it had been raised, then, so
the respondent argues, that would have opened up issues as to the value of the work
performed by the appellant for the respondent. The respondent was itself a
contractor, and the value of the appellant's work to it cannot be measured by the
value of the building work to the owner of the project. The respondent did not
address these issues of valuation. It is said that it would be contrary to basic
considerations of natural justice to allow the appellant to advance on appeal
arguments which assume a resolution favourable to the appellant of issues which
were never even argued at trial.34
[76] Since it is apparent that the appellant's argument under this heading must fail, it is
unnecessary to resolve this argument in favour of the respondent in order to dispose
of this aspect of the appellant's challenge to the judgment.
The evidence satisfied the requirements of s 42(4) of the Act
[77] The appellant's principal submission under this heading was that the possibility of a
claim under s 42(4) of the Act was sufficiently apparent in this case to defeat the
respondent's counterclaim. This submission must be rejected for the reasons I have
already given in relation to the operation of s 42 of the Act.
[78] The appellant also submits that if regard is had to the terms of the subcontract, and
Mr Jewell's certifications, it can be seen that the requirements of s 42(4) of the Act
are satisfied in relation to the payments made by the respondent to the appellant. At
trial the appellant did not contend that Mr Jewell's certification provided a basis
from which a claim for reasonable remuneration could be assessed in conformity
with s 42(4) of the Act. The appellant invites this Court to make findings of fact
which the learned trial judge was not invited to make. That invitation is not
attractive.
[79] The appellant contends that the learned trial judge should have regarded the contract
price (and the rates of payment which it applied) as evidence of reasonable
remuneration for the building work performed by the appellant. It is said that his
Honour should have regarded Mr Jewell's certifications of the appellant's claims for
payment as reasonable measures of the value of the work certified as payable. It is
said that in the absence of some evidentiary basis for reaching a different
conclusion, this process would have yielded a figure for reasonable remuneration.
[80] The appellant says that his Honour should then have considered whether there was
an evidentiary basis for concluding that these amounts should be reduced by
33 (1958) 101 CLR 428 esp at 452 – 456.
34 Cf Coulton v Holcombe (1986) 162 CLR 1 at 7 – 8.
-- 26 of 46 --
27
reference to the criteria in s 42(4); and because the respondent had neither pleaded
nor proved a positive case for the application of any of the subparagraphs of s 42(4),
the learned primary judge should have concluded that the certified payments
represented reasonable remuneration in accordance with s 42(4) for the building
work in question. The appellant's submission did not attempt a quantification of the
appellant's claim for reasonable remuneration save to contend that the amounts
certified by Mr Jewell as progress payments under the contract represented an
accurate quantification of the appellant's claim in conformity with s 42(4) of the
Act.
[81] There are a number of difficulties with the arguments urged by the appellant under
this heading. The first is that the subcontract rates were struck on the basis that the
subcontract included building work as well as other work. Further, the contract
rates cannot sensibly be regarded as not including an allowance for the appellant's
profit. Finally, and most importantly, the onus of proof that the reasonable
remuneration claimed by the appellant conforms with the subparagraphs of s 42(4)
is upon the appellant. The appellant simply failed to adduce any guidance which
might have brought its claim within s 42(4), and particularly paragraphs (a) and (b).
[82] Accordingly, this aspect of the appeal fails.
Interest
[83] Section 47 of the Supreme Court Act provides:
"Interest up to judgment
(1) In any proceedings in respect of a cause of action that arises
after the commencement of the Common Law Practice Act
Amendment Act 1972 in a court of record for the recovery of
money (including proceedings for debt, damages or the
value of goods) the court may order that there shall be
included in the sum for which judgment is given interest at
such rate as it thinks fit on the whole or any part of that sum
for the whole or any part of the period between the date
when the cause of action arose and the date of the judgment.
…"
[84] In the proceedings below, it was accepted by the appellant that the date at which the
calculation of interest should begin was the date of the last payment by the
respondent, ie April 2000. On the appeal, no different date was suggested. The
only basis on which the award of interest was challenged on the appeal was that the
learned trial judge erred in principle in that, because the respondent received value
for its payments to the appellant, the learned trial judge should not have made an
order for the payment of interest. The appellant's argument is to the effect that the
respondent was not relevantly out of pocket by reason of its payments because it
received value for money.
[85] The appellant's argument fails to appreciate that the award of interest under the
legislation is intended to compensate the party who makes a successful claim for the
recovery of money for being out of pocket in respect of moneys which the other
side should have repaid. It was on this basis that the learned trial judge proceeded.
[86] There was, in my respectful opinion, nothing unorthodox in the approach of the
learned trial judge to the exercise of the discretion reposed in him by s 47 of the
-- 27 of 46 --
28
Supreme Court Act. The award of interest was made in respect of the period after
which the cause of action successfully asserted by the respondent arose.
[87] Accordingly, this aspect of the appellant's argument must be rejected.
Conclusion and orders
[88] The appeal should be dismissed.
[89] The appellant should pay the respondent's costs of the appeal on the standard basis.
[90] FRASER JA: Between about July 1998 and April 2000 the appellant ("CCPL")
carried out earthworks and concrete works for the respondent ("Stork") under a
subcontract made in June 1998. CCPL’s subcontract work formed part of the work
for the construction of an ammonium nitrate plant in Central Queensland which
Stork had itself contracted to carry out. Pursuant to the terms of the subcontract
Stork made progress payments totalling $15,528,924.03 to CCPL for its work.
[91] In proceedings in the Trial Division CCPL pursued further claims for payment
under or for breach of the subcontract. One of Stork’s defences pleaded that some
of CCPL’s claims were for "building work" within the meaning of that expression in
s 42 of the Queensland Building Services Authority Act 1991 (Qld) ("the QBSA
Act"), that CCPL did not hold the necessary contractor's licence under the QBSA Act
when it contracted to perform and performed the work, and that the effect of s 42(3)
was that CCPL had no lawful entitlement to make those claims.
[92] The effect of s 42 of the QBSA Act was at the heart of the issues at trial and it is also
critical to the new arguments advanced for CCPL in this appeal. In the following
extract I have italicised the amendments made by s 21 of the Queensland Building
Services Authority Amendment Act 1999, which commenced on 1 October 1999:
"(1) A person must not carry out, or undertake to carry out,
building work unless that person holds a contractor’s licence
of the appropriate class under this Act.
(3) Subject to subsection (4), a person who carries out building
work in contravention of this section is not entitled to any
monetary or other consideration for doing so.
(4) A person is not stopped under subsection (3) from claiming
reasonable remuneration for carrying out building work,
but only if the amount claimed--
(a) is not more than the amount paid by the person in
supplying materials and labour for carrying out the
building work; and
(b) does not include allowance for any of the following-
(i) the supply of the person’s own labour;
(ii) the making of a profit by the person for
carrying out the building work;
(iii) costs incurred by the person in supplying
materials and labour if, in the circumstances,
the costs were not reasonably incurred; and
-- 28 of 46 --
29
(c) is not more than any amount agreed to, or
purportedly agreed to, as the price for carrying out
the building work; and
(d) does not include any amount paid by the person that
may fairly be characterised as being, in substance,
an amount paid for the person’s own direct or
indirect benefit.
. . .
(9) A person who contravenes this section commits an
offence.35
(10) Subsection (4) applies to building work carried out on or
after 1 July 1992, unless the entitlement to payment for the
carrying out of the building work was—
(a) before the commencement of this section, decided
by—
(i) a court; or
(ii) the tribunal; or
(iii) an arbitrator or another entity authorised to
make a binding decision about the
entitlement; or
(b) before 2 March 1999, the subject of—
(i) a claim or counter claim filed in a court; or
(ii) an application made to the tribunal; or
(iii) a reference to an arbitrator or another entity
authorised to make a binding decision about
the entitlement; or
(c) provided for as a term of a binding agreement
entered into before the commencement of this
subsection, but only if the binding agreement—
(i) is between—
(A) 1 or more consumers and 1 or more
building contractors; or
(B) 1 or more building contractors and 1
or more other building contractors;
and
(ii) was entered into to resolve a dispute between
some or all of the parties to the binding
agreement; and
35 The amending Act renumbered subsection (7) as subsection (9).
-- 29 of 46 --
30
(iii) is not the contract for the carrying out of the
building work as originally entered into, or
as entered into and as subsequently varied.
. . ."
[93] CCPL admitted that it did not hold the necessary licence, but the other elements of
Stork’s defence were in issue.
[94] Stork also counterclaimed for the recovery from CCPL of so much of Stork's
progress payments under the subcontract as was for "building work". Stork alleged
that it had made those payments in the mistaken belief that it was obliged to do so,
that CCPL was lawfully entitled to receive them, and that CCPL had complied with
a term of the subcontract requiring CCPL to comply with Queensland legislation.
[95] The relevant work, which was a substantial part of the subcontract works, largely
comprised concreting and related works forming part of the foundational structures
of a building. It included the construction of footings, pedestals and reinforced
piers, together with works including formwork, backfilling, concreting and
screeding, and excavation.36 Unsurprisingly, the trial judge rejected CCPL's
contention that this did not constitute "building work". In relation to the
counterclaim, the judge found that Stork had paid CCPL $9,983,796.54 for
"building work".
[96] The issues in this appeal relate to CCPL’s pleaded contention that CCPL was
entitled to the "reasonable remuneration" for carrying out "building work" which
s 42(4) allows as an exception to the operation of s 42(3). CCPL assumed the onus
of proving that entitlement by its expert evidence. The issue that was litigated was
summarised by CCPL’s senior counsel at the trial:
"[Mr Digby Q.C.] Your Honour will be aware that in paragraph 39 of the
reply the – can I call it a defence for the moment, your Honour? The
defence under clause 42.4 of the QBSA is raised by the plaintiff. Your
Honour is also aware, having presided over the trial, that the case has
proceeded on the basis of evidence being put forward by both parties and
tested in relation to what would be an appropriate reasonable
remuneration; Mr Same's report on the part of the plaintiff and
Miss Janine Smith's report on the part of the defendant."
[97] The trial judge found fundamental deficiencies in CCPL’s pleading of a claim under
s 42(4)37 and, more significantly, in the expert evidence adduced to support it,38 and
concluded that there was "no evidence upon which the provisions of s 42(4) can
act".39 The trial judge therefore rejected CCPL’s contention that it was entitled to
payment for its building work in accordance with s 42(4), with the result that CCPL
failed on some of its claims on that ground and Stork was entitled to succeed on its
counterclaim.
[98] After a twelve day trial the trial judge upheld CCPL's contractual claims to the
extent only of $132,657.70, and gave judgment for Stork on its counterclaim for
36 Cook's Construction P/L v Stork Food Systems Aust P/L [2008] QSC 179 at [341].
37 The trial judge noted that the deficiencies in CCPL’s pleading remained even though they had been
pointed out in a judgment four years before the trial commenced: [2008] QSC 179 at [293], referring
to Cook's Construction Pty Ltd v Stork ICM Australia Pty Ltd [2004] QSC 66 at [55].
38 [2008] QSC 179 at [302] – [317].
39 [2008] QSC 179 at [316].
-- 30 of 46 --
31
restitution for its payments to CCPL for "building work" for $9,983,796.54.40 In a
subsequent judgment the trial judge assessed the interest payable on each of those
sums, vacated the original orders, set off CCPL’s entitlement against Stork’s
entitlement, and gave judgment for the balance in favour of Stork of
$15,216,484.16.41
[99] CCPL now challenges so much of that judgment as reflects Stork's success on its
counterclaim.
[100] The result of the trial, that Stork was found to be entitled to recover its counterclaim
of nearly $10 million of the subcontract price it paid CCPL, together with some
$5 million as interest on that sum, without being required to give any credit for the
value of the work CCPL performed to earn the price, is so surprising as to justify
concern that CCPL may have been the victim of a miscarriage of justice. CCPL
invoked this view in the course of its arguments in the appeal. However CCPL did
not identify any flaw in the trial judge’s reasons for rejecting CCPL’s arguments at
trial, and I have concluded both that the new points CCPL argued in this appeal are
not now open to it and that they must be rejected in any event. If Stork was the
beneficiary of an unmerited windfall, that is a consequence of CCPL’s failure to
prove the claim for reasonable payment for "building work" which is permitted by
s 42(4) of the QBSA Act and which it advanced at the trial.
The issues in the appeal
[101] It remains common ground that CCPL did not hold the necessary contractor’s
licence and CCPL does not challenge the trial judge’s finding that Stork paid CCPL
$9,983,796.54 for "building work". CCPL also does not dispute that the expert
evidence upon which it relied at trial to make out a claim for reasonable
remuneration in conformity with s 42(4) lacked probative value for the reasons
given by the trial judge.
[102] CCPL’s counsel confined CCPL’s grounds of appeal to four contentions. Those
contentions may be summarised as follows: (1) Because Stork had not proved that
there was no amount of reasonable remuneration to which CCPL was entitled under
s 42(4) of the QBSA Act, Stork had not proved that it made the progress payments
because of a relevant mistaken belief; (2) It was fatal to Stork’s claim that it neither
made "counter-restitution" for the value to it of CCPL’s building work nor negated
the need to do so by proving that CCPL’s work had no value; (3) The trial judge
erred by failing to regard the progress certificates as sufficient evidence that the
certified amounts were reasonable remuneration in terms of s 42(4); (4) The trial
judge erred in awarding interest on Stork's counterclaim.
[103] The first three of those contentions were not raised at the trial. Stork argued that
CCPL should not be permitted to advance them for the first time on appeal. It may
facilitate an understanding of my reasons for accepting that argument if I first give
my reasons for concluding that each of the three new contentions lacks merit in any
event.
CCPL’s first contention: because Stork had not proved that there was no
amount of reasonable remuneration to which CCPL was entitled under s 42(4)
40 Cook's Construction P/L v Stork Food Systems Australia P/L [2008] QSC 179.
41 Cook's Construction P/L v Stork Food Systems Australia P/L [2008] QSC 220.
-- 31 of 46 --
32
of the QBSA Act, Stork had not proved that it made the progress payments
because of a relevant mistaken belief.
[104] The evidence showed that Stork paid $13,562,238 (out of total payments under the
subcontract of $15,528,924) before the commencement of the amendments to s 42
on 1 October 1999. Assuming in CCPL's favour that all of the progress payments
totalling $1,966,686 made after 1 October 1999 were for "building work", the total
amount of the progress payments made by Stork for "building work" before
1 October 1999 was $8,017,110.54.
[105] Fastening on those facts, Stork argued that, even if CCPL’s first contention were
accepted in relation to the payments it made after the amendments commenced, the
contention should nevertheless be rejected in relation to the much larger amount it
paid before the amendments commenced. Stork argued that although s 42(10)
entitled CCPL to make a claim falling within s 42(4) in relation to "building work"
it had done before the commencement of the amendments, s 42(10) was not
expressed in such broad terms as retrospectively to correct the mistaken nature of
Stork's belief when it paid for that work.
[106] In the way I analyse the issues that question does not fall for decision. I will discuss
CCPL’s first contention on the footing that the amended form of s 42 applied in
relation to Stork’s counterclaim to recover payments made before the amendments
commenced in the same way that it plainly applied in relation to payments made
after the commencement.
[107] Stork’s counterclaim was based upon the principle that a payment made by mistake
is "one of the categories of case in which the facts give rise to a prima facie
obligation to make restitution, in the sense of compensation for the benefit of unjust
enrichment, to the person who has sustained the countervailing detriment".42 Since
David Securities Pty Ltd v Commonwealth Bank of Australia43 the principle has
applied also to mistakes of law: "…the payer will be entitled prima facie to recover
moneys paid under a mistake if it appears that the moneys were paid by the payer in
the mistaken belief that he or she was under a legal obligation to pay the moneys or
that the payee was legally entitled to payment of the moneys." 44
[108] The trial judge found that Stork had established the following pleaded elements of
its counterclaim:
"(a) the work which is the subject of the Counterclaim was
'building work' within the meaning of the QBSA Act; and
(b) the payments made by the defendant to the plaintiff included
payment for such 'building work';
(c) the payments for such 'building work' comprised 'monetary
or other consideration' within the meaning of section 42(3)
of the QBSA Act; and
(d) the defendant made the payments in the mistaken belief that:
42 Australia & New Zealand Banking Group Ltd v Westpac Banking Corporation (1988) 164 CLR 662
at 673, per Mason CJ, Wilson, Deane, Toohey and Gaudron JJ.
43 David Securities Pty Ltd v Commonwealth Bank of Australia (1992) 175 CLR 353.
44 David Securities Pty Ltd v Commonwealth Bank of Australia (1992) 175 CLR 353 at 378, per Mason
CJ, Deane, Toohey, Gaudron and McHugh JJ.
-- 32 of 46 --
33
(i) it was obliged to do so;
(ii) the plaintiff was lawfully entitled to receive them;
and
(iii) the plaintiff had complied with clause 16.1 of
Exhibit D to the Subcontract (being the admitted
express term of the Subcontract requiring the
plaintiff to comply with Queensland legislation)." 45
[109] CCPL's first contention accepted that if Stork had proved each of those pleaded
elements of its claims it was entitled to retain its judgment, but CCPL contended
that Stork had not proved the fourth element.
[110] Stork made its progress payments pursuant to clause 47 of the subcontract. Under
that clause, at specified intervals CCPL was obliged to deliver progress claims for
payment which identified the value of work carried out by it up to the time of the
progress claim and the amount it claimed was due. Within seven days thereafter
"Stork’s Representative" was to issue to CCPL a progress payment certificate
stating (amongst other things) the payment which in that person’s opinion was to be
made by Stork to CCPL. Subject to presently irrelevant exceptions, within 30 days
after the issue of such a progress certificate Stork was obliged to pay CCPL an
amount not less than that shown on the progress certificate. Clause 26 obliged
"Stork's Representative" to act honestly and fairly and to arrive at a reasonable
measure of work and time.
[111] The subcontract identified Stork’s subcontracted project manager, Mr Jewell, as
"Stork's Representative". Mr Jewell duly issued progress certificates in response to
progress claims submitted by CCPL in apparent conformity with the terms of the
subcontract and Stork duly paid the amounts shown on those progress certificates as
payable by it, as the subcontract apparently obliged Stork to do. The trial judge’s
reasons for concluding that Stork had proved that it made the payments because of a
relevant mistaken belief are contained in the following passage of his Honour’s
reasons:
"[344] Stork called Mr Peter Jewell on this issue. He was 'Stork’s
representative' for the purposes of the Subcontract but he
was not an employee of Stork. He was also the person who
was responsible for certifying the payments by Stork to
CCPL. His evidence was that:
(a) when he certified those payments, he expected the
plaintiff to hold all licences it was required to hold to
do the contract works within Queensland;
(b) if he had discovered that the plaintiff did not hold the
licences it was required to hold, he would have taken
legal advice and acted in accordance with that
advice: 'I would have adjusted their payment
accordingly in relation to the legal advice I was
given'; and
45 [2008] QSC 179 at [326].
-- 33 of 46 --
34
(c) during the course of the Subcontract he did not
discover that the plaintiff did not hold any licence
that it was supposed to hold.
[345] Mr Jewell was cross-examined on this topic:
'Among the many things you might have done is it
correct to say that had you discovered that one of
your subcontractors was not appropriately licensed
under that Act, you nevertheless would have insisted
on the subcontractor continuing to perform its work
under the subcontract?-- No.
Well, let's look at it from a different angle. Had you
discovered that the subcontractor was unlicensed is it
your evidence that you would have stopped it then
and there from continuing to work under its
subcontract?-- Until they were licensed, yes.'
[346] Stork was, through its representative, mistaken as to its
obligation to pay CCPL. It is clear from his evidence that
had he discovered that CCPL was unlicensed he would have
stopped it from working and taken legal advice."
[112] Stork did not call any officer or employee, or indeed any witness, to give evidence
that when it paid the amounts shown on the progress certificates it was not aware
that CCPL did not hold a contractor’s licence under the QBSA Act, but in paragraph
[346] of the reasons, the trial judge attributed to Stork Mr Jewell's belief to that
effect. During the appeal CCPL abandoned a challenge to that conclusion. CCPL
also conceded that Mr Jewell's evidence, extracted in cross-examination, that he
would have stopped CCPL from continuing the work had he discovered that CCPL
was unlicensed, proved that Stork would not have paid CCPL but for Stork's
mistaken belief that CCPL was licensed. And although CCPL argued in its written
submissions that it was debatable whether, as the trial judge also found, Stork made
the payments because it mistakenly believed it was obliged to pay the amounts
shown on the certificates, in the end CCPL did not challenge that finding.
[113] Accordingly the evidence of Mr Jewell, read in light of the subcontract, the
evidence of CCPL's submission of progress claims, Mr Jewell's issue of progress
certificates in response to those progress claims, and Stork's payment of the
amounts of those progress certificates, must be regarded as justifying an inference
that Stork made its payments because it believed that CCPL held the necessary
licence, that the subcontract obliged Stork to make the payments, and that CCPL
was entitled to receive the payments.
[114] CCPL concedes that it did not hold the necessary licence when it entered into the
subcontract and when it did the work and was paid for it, that Stork had no
contractual obligation to make the payments, and that CCPL had no contractual
entitlement to receive them.
[115] CCPL contends that this was insufficient to establish Stork’s entitlement to recover
the money it had paid. CCPL’s point is that Stork failed to prove that there was no
amount of reasonable remuneration to which Stork was entitled under s 42(4). The
argument focused upon the qualification upon the disentitling effect of s 42(3)
wrought by the introductory phrase "[s]ubject to subsection (4)". CCPL's
-- 34 of 46 --
35
submissions characterised the permitted claim to reasonable remuneration as "the
statutory right pursuant to s 42(4)". It contended that the effect of s 42(3) and
s 42(4) was to preserve out of the full panoply of rights which might otherwise have
existed only the right to payment of reasonable remuneration for the work, to
subject that right to the constraints set out in s 42(4)(a) - (d), and otherwise to
negate the existence of any rights to payment. That description of the statute
informed CCPL's proposition that the better view of the intersection between
restitutionary principle and the operation of s 42(3) and s 42(4) was that the
injustice of CCPL's retention of the payments could not be regarded as proved
without proof that the amount paid exceeded the amount of the entitlement provided
under s 42(4).
[116] Section 42, in its unamended form, was considered in two decisions of this Court,
Marshall v Marshall46 and Sutton v Zullo Enterprises Pty Ltd.47
[117] In Marshall v Marshall this Court upheld a trial judge's decision that an owner was
entitled to recover payment she had made to an unlicensed builder for "building
work" in accordance with her apparent contractual obligation. As the judgments in
that case confirm, s 42(3) plainly prevented the unlicensed builder from recovering
the price under the building contract. Pincus JA and de Jersey J (as the Chief
Justice then was) affirmed the trial judge's reasoning, following David Securities
Pty Ltd v Commonwealth Bank of Australia,48 that the moneys were repayable
because the owner had paid them in the mistaken belief that she was contractually
obliged to do so.49 McPherson JA rejected the builder's appeal on the same basis50
and on the further ground that the owner was entitled to recover her payments
because the effect of s 42 was that the unlicensed builder had no right to claim,
keep, or retain the money as against the owner and she was a member of the class of
persons intended to be protected by s 42. 51
[118] It was not necessary there to decide whether s 42(3), unlike the legislation
considered in other cases such as Pavey & Matthews Pty Ltd v Paul,52 precluded an
unlicensed contractor from recovering anything outside the contract for the
reasonable value of its work, but in Sutton v Zullo Enterprises Pty Ltd this Court
held that s 42(3) prevented the unlicensed builder both from recovering any part of
the contract price and from recovering anything by way of restitution for the work
done. In so concluding, McPherson JA and Pincus JA held that such claims were
barred because they were for "any monetary consideration" within the meaning of
s 42(3).53
[119] The legislature responded by enacting s 21 of the Queensland Building Services
Authority Amendment Act 1999, which commenced on 1 October 1999. The
mischief at which the amendments was aimed was the injustice in the former
legislative denial to unlicensed contractors of any right to claim any remuneration
by way of restitution for work carried out at the other contracting party's request and
46 [1999] 1 Qd R 173.
47 [2000] 2 Qd R 196; [1998] QCA 417.
48 (1992) 175 CLR 353.
49 [1999] 1 Qd R 173 at 180.
50 [1999] 1 Qd R 173 at 178-179.
51 [1999] 1 Qd R 173 at 176-178, citing Mayfair Trading Co Pty Ltd v Dreyer (1958) 101 CLR 428 at
449-450, per Dixon CJ and Kiriri Cotton Co v Dewani [1960] AC 192.
52 (1987) 162 CLR 221.
53 [2000] 2 Qd R 196 at [8]-[9] per McPherson JA; at [17]-[21] per Pincus JA.
-- 35 of 46 --
36
in the expectation of payment. The purpose of the Bill for that Act was described in
the Minister's second reading speech:
"The Bill also remedies the potential for unfairness which emerged
last year following a Court of Appeal decision in Zullo Enterprises
and Others versus Sutton. The intention of the regulatory scheme
has always been that building contractors be licensed. It is not the
intention, therefore, that builders and developers have incentives to
engage unlicensed contractors. The court found that, contrary to
previous belief, the Act prevents an unlicensed building contractor
from recovering any money at all under a contract. This opens the
door for unjust enrichment of unscrupulous developers and builders,
potentially encouraging them to engage unlicensed contractors.
The Bill rectifies this situation by allowing unlicensed contractors to
recover any moneys that they have reasonably spent while
performing building work. But unlicensed contractors cannot
recover any profit or receive any more than the contract price
specified in the purported contract. They will also be penalised for
the offence of operating without a licence. In addition, building
contracts are required to include the licence number of the contracted
party."
[120] A similar explanation emerges from the Explanatory Notes for the Bill for the
amending Act:
"Until the 1998 decision of the Court of Appeal in Zullo Enterprises
& Ors v Sutton [1998] QCA 417 (15 December 1998), it was thought
that s42, which makes the carrying out or undertaking to carry out of
building work unlawful, did not prevent unlicensed contractors
recovering their costs under the common law of contract.54 The Zullo
decision held that unlicensed contractors were prevented from
recovering anything at all, and held the prospect that unlicensed
contractors could be successfully sued for recovery of any moneys
paid for prior performance. This potentially allows considerable
injustice, such as deliberate recruiting of subcontractors from
interstate and legally escaping from any obligation to pay for work
performed. Unlicensed contracting will, of course, remain an
offence committed by the contractor, but the principle that a builder
or owner should not be able to enrich themselves through signing on
unlicensed contractors is enshrined in this clause.
This clause amends s42(3) and inserts a new subsection 42(4) to
provide an unlicensed contractor with a limited statutory right to
recover money which would otherwise be unavailable because of the
Zullo decision. The new provisions will allow an unlicensed
contractor to claim reasonable recovery of moneys actually expended
for the supply of materials and labour, other than the contractor’s
own labour and profit. Existing subsections 42(4) to (6) are
renumbered.
54 The expression "the common law of contract" was apparently intended as a reference to a
restitutionary claim.
-- 36 of 46 --
37
The new provision in s42(4)(iii) also prevents an unlicensed
contractor unreasonably incurring costs and claiming for recovery
under this provision.
S42(4)(c) prevents an unlicensed contractor recovering any more
under this provision than the contract price.
S42(4)(d) is designed to attack any scheme entered into by the
unlicensed contractor, for example employing the contractor’s child
or the charging of a management fee by a company of which the
contractor is a beneficial shareholder, to use this new provision to
gain personal profit from unlicensed contracting."
[121] Those notes described s 42(4) as conferring a "limited statutory right", but that
terminology appears not to have been a precise description of its legal effect. The
immediately following words ("which would otherwise be unavailable because of
the Zullo decision . . .") reveal, in conformity with the text of the amendments, that
the intention was only to reverse the effect of that decision in so far as it prevented
an unlicensed contractor from making the claim described in s 42(4).
[122] The extrinsic evidence is not entirely consistent or clear in this respect, but it is at
least not inconsistent with what I think is the literal and natural meaning of s 42 in
its amended form. Contrary to CCPL’s thesis, the amendments did not create a
statutory right in the unlicensed contractor as a qualification upon the payer’s
common law right to recover money paid to the contractor for "building work" in
the mistaken belief that the contractor was contractually entitled to such payment.
Rather, the amended section merely excepts a contractor’s common law claim for
reasonable remuneration, if it falls within the limits described in s 42(4), from the
otherwise universal destruction wrought by s 42(3) upon any right in an unlicensed
contractor to payment for "building work": "A person is not stopped under
subsection (3) from claiming reasonable remuneration…".
[123] Consistently with the statutory exclusion of the usual contractual entitlement to
profit and the cost of the "person’s own labour",55 the reference in s 42(4) to
"reasonable remuneration" suggests that the character of the permissible claim is
non-contractual and that it is, or at least includes, the common money count for
work done, or a quantum meruit.56 The amended form of s 42 thus permits the
unlicensed contractor to make a common law claim outside the contract and as an
exception to the general preclusion of any claim in s 42(3), provided that the claim
falls within the limits imposed by s 42(4). The section then leaves it to the common
law to define the circumstances in which any such claim will succeed.
[124] Section 42 operates in that way whether or not the contractor has received any
payment purportedly made pursuant to the contract. In either case the exception in
s 42(4) applies only where the unlicensed contractor makes a claim of the character
and for the amount permitted by that provision. That must be so because the
presence or absence of payment is not expressed as a criterion upon which the
destructive operation of s 42(3) depends. Thus, where the unlicensed contractor
cannot invoke the exception it may be obliged to disgorge any payment it has
received purportedly under the contract and contrary to the statute. There is no hint
55 The trial judge found that this did not exclude a corporation claiming the cost of its employee’s
labour: Cook's Construction P/L v Stork Food Systems Aust P/L [2008] QSC 179 at [309](b).
56 Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221 at 251, 253 per Deane J.
-- 37 of 46 --
38
in the amendments or the extrinsic evidence that the legislative intention was to
reverse that aspect of the decisions in Marshall v Marshall and Sutton v Zullo
Enterprises Pty Ltd.
[125] The fact that the elements in paragraphs (a)-(d) of s 42(4) form part of the
description of a claim for reasonable remuneration which may be made by an
unlicensed contractor as an exception to the disentitling effect of s 42(3) suggests
that the unlicensed contractor bears the burden of proving compliance with each of
the paragraphs of s 42(4).57 It must also be borne in mind that s 42 renders an
unlicensed contractor who contravenes s 42(1) guilty of an offence but it does not
stigmatise a person who, like Stork, pays the unlicensed contractor in ignorance of
the sterilising effect of s 42(3) and in the mistaken belief that the contract requires
the payment. It seems highly unlikely that the legislative intention was to throw the
onus upon the innocent party to prove the absence of a valid counter claim by the
guilty party, the unlicensed contractor, who had no entitlement to receive payments
made on the mistaken footing that they were due to it under the contract. The
unlikelihood of such a legislative intention is emphasised by the manifest difficulty
the innocent party would face in framing and proving a claim that the contractor
was entitled to no reasonable remuneration, or to a particular amount of reasonable
remuneration calculated in accordance with s 42(4), a claim that ordinarily would
require proof of matters exclusively within the contractor’s knowledge.
[126] That construction of s 42 then informs the answer to the question whether Stork
made its payments under such a mistaken belief as entitled it to recover the
equivalent amount in its restitutionary claim.
[127] The question whether Stork paid under such a mistake must be answered at the time
when it made the payments.58 It seems very difficult to sustain the proposition that
Stork was not mistaken when it made its progress payments, when CCPL had not by
then purported to make any claim of the kind contemplated by s 42(4). CCPL was
disposed to argue that its progress claims might be regarded as claims of the kind
described in s 42(4), but this departs both from the reality of the situation and the
manner in which the litigation was conducted. The progress claims did not purport
to claim "reasonable remuneration" or otherwise conform to s 42(4). They were
manifestly claims for payment made under and measured in accordance with the
provisions of the subcontract. They thus differed markedly in their basis and
measure from a claim described in s 42(4). Furthermore, CCPL did not plead or
point to evidence that Mr Jewell was authorised by Stork to receive on its behalf
any claim other than a progress claim under the subcontract. On the evidence, the
first claim given to Stork that arguably was made in conformity with s 42(4) was
made (or, perhaps more accurately, suggested) in CCPL's reply. That document
was filed many years after the last of Stork's payments.
[128] What is left is CCPL’s contention that it might have made a claim for reasonable
remuneration before Stork made its payments. CCPL argued that it was plainly
entitled to recover some amount of reasonable remuneration in accordance with
s 42(4) so that, even if (as the trial judge found) it had failed to prove the amount to
57 Chugg v Pacific Dunlop Ltd (1990) 170 CLR 249 at 257 per Dawson, Toohey and Gaudron JJ and
Vines v Djordjevitch (1955) 91 CLR 512 at 519-520.
58 "From the point of view of the person making the payment, what happens after he or she has
mistakenly paid over the money is irrelevant, for it is at that moment that the defendant is unjustly
enriched": David Securities Pty Ltd v Commonwealth Bank of Australia (1992) 175 CLR 353 at 385.
-- 38 of 46 --
39
which it was entitled Stork had failed to prove that CCPL’s receipt of the
contractual payments was unjust.
[129] The proposition that CCPL possessed any entitlement conforming to s 42(4) is not
self-evidently correct. To give one example of a possible obstacle, if it was an
element of CCPL’s claim for reasonable remuneration that Stork benefited as a
result of CCPL having performed part of the work which Stork had contracted to
perform for its principal, then Stork might deny the claim on the ground that CCPL
failed to prove that Stork was itself paid for CCPL’s work. (That was the trial
judge’s tentative conclusion when CCPL’s "windfall" argument was advanced in
opposition to Stork’s claim for interest.59 ) I do not mean to express a view upon the
merits in that respect: it would not be easy to do so in light of the fact, remarked
upon by the trial judge,60 that CCPL’s pleading merely asserted an entitlement in
accordance with s 42(4) and did not plead the material facts supporting that
assertion. It does strike me, however, that there is a real difficulty in the way of
accepting that CCPL was entitled to recover any amount as reasonable remuneration
in circumstances in which it, the party most likely to be able to frame and prove the
entitlement to and quantum of such a claim, comprehensively failed to do so. But
even if it be assumed in CCPL’s favour that it was entitled to some amount I would
not accept its argument.
[130] CCPL invoked the following passage in the joint judgment of Mason CJ, Deane,
Toohey, Gaudron, and McHugh JJ in David Securities Pty Ltd v Commonwealth
Bank of Australia:
"In the light of our view that the decision in South Australian Cold
Stores [(1957) 98 CLR 65] can in this Court be justified on a
narrower basis and that the traditional rule was not necessary to the
decision, there is no other decision of this Court which constrains us
to adopt the traditional rule. For the reasons stated above, the rule
precluding recovery of moneys paid under a mistake of law should
be held not to form part of the law in Australia. In referring to
moneys paid under a mistake of law, we intend to refer to
circumstances where the plaintiff pays moneys to a recipient who is
not legally entitled to receive them. It would not, for example,
extend to a case where the moneys were paid under a mistaken
belief that they were legally due and owing under a particular
clause of a particular contract when in fact they were legally due
and owing to the recipient under another clause or contract.
[Barclays Bank Ltd. v W. J. Simms Son & Cooke (Southern) Ltd.,
[1980] Q.B. 677, at p. 695, per Robert Goff J: 'Of course, if the
money was due under a contract between the payer and the payee,
there can be no recovery on this ground.']." 61
[131] CCPL argued that this passage requires the conclusion that a prima facie entitlement
in Stork to recover moneys paid under mistake arose only if it proved that it was
under no liability to CCPL to pay the same amount of money by way of restitution
measured in accordance with s 42(4).
59 Cook's Construction P/L v Stork Food Systems Australia P/L [2008] QSC 220 at [18] - [19].
60 Cook's Construction P/L v Stork Food Systems Aust P/L [2008] QSC 179 at [291].
61 (1992) 175 CLR 353 at 376. I have added the emphasis.
-- 39 of 46 --
40
[132] Stork’s mistake that CCPL held the necessary contractor’s licence was a mistake of
fact in respect of which that passage has no apparent application, but the passage
does not assist CCPL for more fundamental reasons. It describes a situation in
which it is proved that the money which the payer claims to recover was due and
owing when it was paid. It does not answer the decisive question in this appeal,
which concerns the onus of proof.
[133] That question is discussed later in the same judgment in a way that is opposed to
CCPL’s contention. Mason CJ, Deane, Toohey, Gaudron, and McHugh JJ
considered and rejected an argument that a plaintiff should be required to prove that
the retention of the moneys by the recipient would be unjust in all the circumstances
before recovery should be granted. Their Honours regarded a claim by a recipient
that the moneys were due on a basis other than that which motivated the payment as
a circumstance which the recipient might raise to seek to rebut the payer's prima
facie entitlement to restitution:
"The fact that the payment has been caused by a mistake is sufficient
to give rise to a prima facie obligation on the part of the respondent
to make restitution. Before that prima facie liability is displaced, the
respondent must point to circumstances which the law recognizes
would make an order for restitution unjust [Westpac Banking
Corporation (1988) 164 CLR, at p 673]. There can be no restitution
in such circumstances because the law will not provide for recovery
except when the enrichment is unjust. It follows that the recipient
of a payment, which is sought to be recovered on the ground of
unjust enrichment, is entitled to raise by way of answer any
matter or circumstance which shows that his or her receipt (or
retention) of the payment is not unjust.
The two 'defences' upon which the respondent relies in this Court are,
first, that the payments by the appellants were made for good
consideration and, secondly, that in reliance upon receipt of the
payments the respondent, in good faith, changed its position to its
detriment. In the context of a mistake case, these 'defences' were
included in the well known formulation of Goff J in Barclays Bank.
His Lordship stated [(1980) Q.B., at p 695]:
'(1) If a person pays money to another under a mistake of
fact which causes him to make the payment, he is prima
facie entitled to recover it as money paid under a mistake of
fact. (2) His claim may however fail if (a) the payer intends
that the payee shall have the money at all events, whether
the fact be true or false, or is deemed in law so to intend; or
(b) the payment is made for good consideration, in
particular if the money is paid to discharge, and does
discharge, a debt owed to the payee (or a principal on
whose behalf he is authorised to receive the payment) by
the payer or by a third party by whom he is authorised
to discharge the debt; or (c) the payee has changed his
position in good faith, or is deemed in law to have done
so.'" 62
62 (1992) 175 CLR 353 at 379-380. I have added the emphasis.
-- 40 of 46 --
41
[134] That view of the onus of proof was applied in subsequent passages in the joint
judgment:
"In this case, the Bank must prove that the appellants are not entitled
to restitution because they have received consideration for the
payments which they seek to recover."63
"It might be said to order restitution in the present case would, in the
absence of any other defences, confer something in the nature of a
windfall upon the appellants at the expense of the respondent. This
possible result flows from the fact that, having proved mistake, the
appellants are prima facie entitled to recovery and the respondent
bears the onus of proving why an order for restitution would be
unjust." 64
[135] Those statements echoed the earlier statement in the joint judgment in Australia &
New Zealand Banking Group Ltd v Westpac Banking Corporation that "[b]efore
that prima facie liability [to make restitution] will be displaced, there must be
circumstances (eg, that the payment was made for good consideration such as the
discharge of an existing debt. . .) which the law recognises would make an order for
restitution unjust." 65 The same view of the onus of proof, similarly applying Robert
Goff J’s influential dictum in the Barclays Bank case, had earlier been adopted in
Bank of New South Wales v Murphett.66
[136] More recently, the elements of a claim for restitution were described in a way that
bears upon the present issue in Ovidio Carrideo Nominees Pty Ltd v The Dog Depot
Pty Ltd. 67 The legal issues were similar to those here: the payee contended that a
payer’s claim for restitution of payments made in the belief that it was contractually
obliged to do so should fail because the payee was entitled to "counter restitution";
and the payer’s belief was mistaken because a statute precluded any contractual
obligation or entitlement but it did not preclude "counter restitution" in favour of the
payee.
[137] In that case a tenant paid rent in the belief that it was liable to pay it under its lease.
The tenant was mistaken because the effect of the statute68 was that the tenant was
not liable to pay the rent when, as was the case, the landlord had neglected to give
the tenant a specified disclosure statement. There were two limbs to the landlord’s
argument in the appeal. It argued first that the tenant's claim for restitution for an
amount equal to the rent which it had paid under its mistake was defeated by a
defence of good consideration (the tenant’s exclusive use and occupation of the
premises in return for its payments). Secondly, it argued that the landlord had an
available counter-claim for restitution in respect of the tenant's use and occupation
of the premises in an amount equal to the amount of the tenant's claim.
[138] The landlord's appeal succeeded. In relation to the second limb of the landlord's
argument, Nettle JA concluded that the landlord's entitlement to sue for "counter
restitution" was "pro tanto an answer to a claim for restitution", so that it followed
that to that extent the landlord's retention of the monies paid as rent would not be
63 (1992) 175 CLR 353 at 383.
64 (1992) 175 CLR 353 at 384.
65 (1988) 164 CLR 662 at 673 per by Mason CJ, Wilson, Deane, Toohey, and Gaudron JJ.
66 [1983] 1 VR 489, at 492 per Starke J and at 495-496 per Crockett J, King J concurring.
67 (2006) Vic ConvR 54-713; [2006] VSCA 6.
68 Retail Tenancies Reform Act 1998 (Vic), s 8(2)(b).
-- 41 of 46 --
42
unjust.69 More relevantly for present purposes, in the course of considering the
landlord's first argument Nettle JA referred to a passage in David Securities v
Commonwealth Bank of Australia70 for the proposition that "a claim for money had
and received lies only as upon a total failure of consideration", referred to Gummow
J's explanation in Roxborough v Rothmans of Pall Mall Australia Ltd71 that in this
context "total failure of consideration" looked to the benefit bargained for by the
payer rather than any benefit which might have been received in fact, and
concluded:
"[The tenant] claims that it paid rent under the lease in the mistaken
belief that it was bound in law to pay it, and therefore, because of
mistake, it is entitled now to recover it. But, as has been seen, in order
to succeed in that claim the [tenant] must establish that it paid the rent
as upon a total failure of consideration. And, in effect, that
necessitates acceptance of the proposition that, whatever the benefit
the respondent might have received from the use and occupation of
the demised premises, the respondent did not receive the benefit
which it bargained. In my view the respondent has not succeeded in
establishing that it did not receive the benefit for which it bargained."
[139] The incidence of the onus of proof was not there in issue,72 but that way of
expressing the applicable principles arguably supports CCPL’s first contention. In a
separate judgment, Chernov JA discussed the decisions I have touched upon,
ANZ Banking Group Ltd v Westpac Banking Corporation, David Securities Pty Ltd
v Commonwealth Bank of Australia, and Roxborough v Rothmans of Pall Mall
Australia Ltd, and concluded that "once a prima facie entitlement to restitution is
made out by the payer, it is for the payee to show that it would not be unjust or
unconscionable for it to retain the money if the payer is to be denied restitutionary
relief."73
[140] It will be apparent from what I have already written that I would respectfully accept
Chernov JA’s analysis of the applicable principles, which throws the onus upon the
payee to justify its receipt by proof of its own claim for "counter restitution" against
the payer. The remarks in the joint judgment in David Securities Pty Ltd v
Commonwealth Bank of Australia concerning total failure of consideration (or a
total failure of a severable part of the consideration) did not concern the elements of
a prima facie entitlement to recover payments made by mistake. They concerned
instead the elements of a defence that the payee gave consideration for the mistaken
payment. That flowed from the rejection earlier in the joint judgment of the payee's
proposition that the payer must prove "unjustness" over and above the mistake.74
CCPL’s first contention is an attempt to revive that rejected view of the basis of a
restitutionary claim founded on mistake.
[141] I conclude that, as is reflected in the terms of s 42, the onus lay upon CCPL to rebut
Stork’s prima facie entitlement to recover money "which in justice and equity
69 [2006] VSCA 6 at [47].
70 (1992) 175 CLR 353 at 382.
71 (2001) 208 CLR 516. at 555.
72 [2006] VSCA 6 at [4], [8] and [47].
73 [2006] VSCA 6 at [20].
74 (1992) 175 CLR 353 at 378-380.
-- 42 of 46 --
43
belongs to [Stork]" 75 by proving the fact and amount of any entitlement in CCPL to
reasonable remuneration in conformity with s 42(4). CCPL did not prove any such
entitlement. It follows that CCPL failed to displace the prima facie presumption
that CCPL’s enrichment by the amount of the payments should be regarded as
unjust.76
[142] Stork filed a notice of contention under which it advanced an alternative argument.
It argued that it was entitled to succeed irrespective of whether it had established
that it made its payments by mistake, so that CCPL’s first contention was irrelevant.
This argument invoked the cause of action for moneys had and received which
McPherson JA decided in Marshall v Marshall was available in these
circumstances: s 42 prohibited an unlicensed contractor from carrying out and from
undertaking to carry out building work, such an unlicensed contractor was not
entitled to any monetary or other consideration for carrying out that building work,
and s 42 was designed to protect a class of persons of whom the payer was one.
This argument has real substance, but I would not base my decision upon it because
that way of putting Stork’s counterclaim was not litigated at the trial and I have in
any event rejected CCPL’s first contention for other reasons.
CCPL’s second contention: it was fatal to Stork’s claim that it neither made
"counter-restitution" for the value to it of CCPL’s building work nor negated
the need to do so by proving that CCPL’s work had no value.
[143] CCPL's argues that the facts that, as it contends, restitutio in integrum for the
benefit Stork received was impossible and that Stork neither made
"counter-restitution" nor negated the need to do so, were fatal to Stork's
restitutionary claim.
[144] The legal propositions underlying this argument are that an obligation upon a
claimant to make "counter-restitution" to a recipient, where that is possible, is a
condition or limiting principle applicable to a claim for moneys paid by mistake and
that where such "counter-restitution" is impossible the original restitutionary claim
must fail. CCPL put the argument in another way, which seems to amount to the
same thing, namely that any prima facie obligation to make restitution which Stork
established was displaced when CCPL pointed to the existence of a valuable, albeit
unquantified, right conforming with s 42(4) which the law recognises would make
unjust the order for restitution sought by the claimant.
[145] As authority for those propositions CCPL relied upon Clarke v Dickson,77 in which
Crompton J stated the principle under consideration in the following terms:
"When once it is settled that a contract induced by fraud is not void,
but voidable at the option of the party to the fraud, it seems to me to
follow that, when that party exercises his option to rescind the
contract, he must be in a state to rescind; that is, he must be in such a
situation as to be able to put the parties into their original state before
the contract."
[146] Clarke v Dickson and the other authorities cited by CCPL for the same proposition78
all concerned the rescission of executed contracts. No authority was cited which
75 Bullen and Leake's Precedents of Pleadings, 3rd Ed (1886), p 44, quoted by Gummow J in Roxburgh
v Rothmans of Pall Mall Australia Ltd (2001) 208 CLR 516; [2001] HCA 68 at [88].
76 Australia & New Zealand Banking Group Ltd v Westpac Banking Corporation (1988) 164 CLR 662,
at 673; David Securities Pty Ltd v Commonwealth Bank of Australia (1992) 175 CLR 353 at 379.
77 (1858) 120 ER 463.
78 Alati v Kruger (1955) 94 CLR 216; Vadasz v Pioneer Concrete (SA) Pty Ltd (1995) 184 CLR 102.
-- 43 of 46 --
44
supports the application of that principle to claims for the recovery of money paid
by mistake. The absence of authority is not necessarily fatal to the argument, but
this is not an appropriate occasion for an examination of the extensive academic
comment on this issue. A requirement that Stork must offer "counter restitution" in
favour of CCPL as a condition of the validity of Stork’s claim where CCPL has not
proved its claim would conflict with the policy reflected in s 42: an unlicensed
contractor is not to be remunerated for "building work" except by way of reasonable
remuneration measured in conformity with s 42(4) pursuant to a claim made and
proved by the unlicensed contractor. That the principle propounded by CCPL
would conflict with the statutory policy is sufficient reason to reject its application
in this case.79
CCPL's third contention: the trial judge erred by failing to regard the progress
certificates as sufficient evidence that the certified amounts were reasonable
remuneration in terms of s 42(4).
[147] Whilst, as I have mentioned, CCPL does not challenge the trial judge's rejection of
the expert evidence bearing upon its claim under s 42(4), CCPL does contend that
the trial judge erred by failing to regard the certificates by Mr Jewell as constituting
evidence that the certified amounts were reasonable remuneration for the work
concerned.
[148] A flaw in CCPL’s argument is that the progress certificates did not distinguish
"building work" from other work included within particular certificates. The
certificates could, at best, provide evidence only that the gross amounts in each of
them were prima facie reasonable valuations under the terms of the subcontract;
they could not provide evidence that the amounts attributable to "building work",
which amounts were not separately identified, were reasonable. Furthermore, the
application of the subcontract rates to the anticipated quantities of work was
presumably expected to produce a profit in CCPL's hands, which is of course not
recoverable under s 42(4). Whether, in the events which occurred, the progress
payments did include profit was not proved, but there is no basis for assuming that
they did not. That being so it does not avail CCPL to point to authority80 that the
progress certificates might constitute some evidence of a claim for restitution under
the common law unaffected by the limitations imposed by s 42(4).
Are CCPL’s first three contentions open to it in this appeal?
[149] I return to Stork’s argument that CCPL should not be permitted to maintain its first
three contentions because none of them were litigated at the trial. Stork invoked the
principle that in an appeal of this character a party ordinarily should not be
permitted to raise a new point if, had the point been raised at trial, it might possibly
have been met by additional evidence at the trial or the opponent might have
conducted its case differently.81
[150] CCPL’s pleading contained no hint of the contentions which it now advances. It
may be, as CCPL argued in the appeal, that its pleaded denial of Stork’s allegation
79 Mayfair Trading Co Pty Ltd v Dreyer (1958) 101 CLR 428 per Dixon CJ at 449-450 and 456; Lejo
Holdings Pty Ltd v Deutche Bank (Asia) AG [1988] 2 Qd R 30 at 34, per Macrossan J.
80 See Flett v Deniliquin Publishing Co Ltd [1964-5] NSWR 383; Pavey & Matthews Pty Ltd v Paul
(1987) 162 CLR 221 at 252, 257; Gino D’Alessandro Constructions Pty Ltd v Powis [1987] 2 Qd R
40 at 58-59; Iezzi Constructions Pty Ltd v Watkins Pacific (Qld) Pty Ltd [1995] 2 Qd R 350 at 355.
81 Suttor v Gundowda Pty Ltd (1950) 81 CLR 418 at 438; Coulton v Holcombe (1986) 162 CLR 1 at
7-9.
-- 44 of 46 --
45
that it paid CCPL by mistake was sufficiently broad to have permitted CCPL to
argue the first contention at trial, but that denial was hardly sufficient to encompass
the second contention.82 Despite the deficiencies in CCPL’s pleading of a claim for
reasonable remuneration, CCPL’s third contention, which is merely an evidentiary
point, was available to CCPL once it was permitted to litigate a claim in accordance
with s 42(4), at least unless it was permitted to litigate that claim only on the footing
that it confined the evidence upon which it relied to its expert evidence.
[151] What is important here though are not merely the pleadings but the parameters of
the contest as they were defined by the parties’ conduct of the trial.83 Stork pointed
to various statements made on behalf of CCPL before and during the trial which
were inconsistent with its first three contentions. The effect of those statements was
that CCPL proposed to meet the counterclaim by reliance upon its denial that the
relevant work constituted "building work" and by proving an alternative claim, by
expert evidence, for reasonable remuneration in conformity with s 42(4). That
accords with the description of what was litigated by CCPL’s own senior counsel at
trial, which I quoted in the first section of these reasons.
[152] Those were the issues litigated and lost at trial by CCPL. The three contentions
advanced for CCPL in the appeal were not litigated.
[153] Stork’s affidavit evidence established that had any of CCPL’s first three contentions
been pleaded or raised at trial Stork would have taken various interlocutory steps,
including seeking disclosure and non-party disclosure from others, and it would
have adduced evidence bearing upon those contentions. CCPL argued in response
that Stork counter claimed only the full amount of what it had paid and that the
further evidence Stork identified would not have supported that counter claim, but
might only have supported a different claim for a smaller amount, namely the
amount of its counterclaim reduced by the amount of any entitlement in CCPL to
reasonable remuneration measured in accordance with s 42(4).
[154] That is not to deny, however, that had CCPL raised these points at trial Stork might
have adduced evidence to avoid being exposed to the result for which CCPL
contends in this appeal, namely the complete failure of Stork’s counterclaim. Such
a result would be manifestly unjust to Stork. CCPL’s argument that (if it be
assumed that there is substance in its new arguments) the result at trial was unjust to
it carries much less weight. That result is a consequence of its own failure to
establish the case it determined to litigate at the trial. As was pointed out in Coulton
v Holcombe,84 it is "fundamental to the due administration of justice that the
substantial issues between the parties are ordinarily settled at trial."
[155] Had I thought that there was merit in CCPL’s new points, I would have concluded
that the injustice caused to Stork by allowing the points to be raised for the first time
in this appeal could be met only by ordering a new trial. That is itself a reason for
refusing to allow the new points to be litigated for the first time in the appeal.85
82 CCPL was obliged to specifically plead in its answer to Stork's counterclaim any matter which CCPL
alleged made Stork’s counterclaim not maintainable or which if not specifically pleaded might take
Stork by surprise: UCPR r 150(4).
83 Whisprun Pty Ltd v Dixon (2003) 200 ALR 447 at 461, Water Board v Moustakas (1988) 180 CLR
491 at 497.
84 (1986) 162 CLR 1 at 7, per Gibbs CJ, Wilson J, Brennan J and Dawson J.
85 Whisprun Pty Ltd v Dixon (2003) 200 ALR 447 at 461.
-- 45 of 46 --
46
CCPL's fourth contention: interest
[156] The trial judge exercised the discretion conferred by s 47 of the Supreme Court Act
1995 (Qld) to award interest of $5,526,148.20. No question is raised by CCPL
concerning the rate or period adopted by the trial judge in awarding interest.
Rather, CCPL repeats the submission rejected by the trial judge86 that Stork should
be denied interest because Stork had not sustained a loss but had received a
windfall.
[157] CCPL relies upon the principle referred to by Gibbs CJ in Batchelor v Burke that
"… interest should not be awarded… [where] the respondent has not suffered any
financial detriment from a practical point of view".87 In Batchelor v Burke it was
held that interest should not be awarded under s 30C(1) of the Supreme Court Act
1935 (SA) in respect of the portion of an award of damages in favour of a worker
representing earnings lost before trial which were replaced by the payment of
compensation. That is not analogous with this case, in which Stork has been held
entitled both to retain whatever (unproved) value it may have derived from CCPL's
building work whilst at the same time being entitled to judgment for the amount it
paid for that work. In those circumstances it cannot be said that, in the period
between when Stork's cause of action arose and judgment, Stork received anything
by way of replacement for the amount withheld from it. That same feature dictates
the view that the interest awarded by the trial judge conforms with the fundamental
principle that interest is awarded to restore rather than to improve a plaintiff's
position.88
[158] CCPL has not established that the trial judge's discretion to award interest
miscarried.
Disposition and orders
[159] I would dismiss the appeal with costs.
[160] DAUBNEY J: It is clear, for the reasons given by Keane JA and Fraser JA, with
each of whom I respectfully agree, that this appeal must fail.
[161] Without unnecessarily rehearsing the matters so comprehensively dealt with in each
of their Honours’ judgments, I would only re-affirm my view that the argument
sought to be advanced by the appellant to the effect that, in the circumstances of this
case, the onus lay at trial not on the appellant to prove its claim but on the
respondent to disprove that the appellant had a valid claim in reliance on s 42(4) of
the Queensland Building Services Authority Act 1991 (Qld) is not only counter-
intuitive but, as has been demonstrated in their Honours’ judgments, is neither
consistent with a proper construction of the legislation nor with the public policy
considerations underpinning it.
[162] I would also expressly associate myself with the observations made by Keane JA in
paragraph [7] of his judgment.
[163] The appeal must be dismissed with costs.
86 Cook's Construction P/L v Stork Food Systems Aust P/L [2008] QSC 220 at [42].
87 (1981) 148 CLR 448.
88 Haines v Bendall (1991) 172 CLR 60, at 72 per Mason CJ, Dawson, Toohey and Gaudron JJ.
-- 46 of 46 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2009/075