Crowther v State of Queensland [2009] QPEC 31
PLANNING & ENVIRONMENT COURT
OF QUEENSLAND
CITATION: Crowther v State of Queensland [2009] QPEC 31
PARTIES: CLAIRE CROWTHER
Applicant
v
THE STATE OF QUEENSLAND
Respondent
FILE NO/S: 1556 of 2008
DIVISION: Original jurisdiction
PROCEEDING: Application for enforcement orders
ORIGINATING
COURT: Planning & Environment Court Queensland
DELIVERED ON: 6 May 2009
DELIVERED AT: Brisbane
HEARING DATE: 13 March 2009; 27 April 2009
JUDGE: Alan Wilson SC DCJ
ORDER: 1 That clause 2(a) of the order made by this court on
3 December 2008 be amended by inserting the
words, ‘… or by decommissioning the air
compressors in H Block’
2 That the applications filed by the applicant on 3
March and 21 April 2009 be dismissed
3 That the respondent pay the applicant’s costs of
and incidental to the application filed 3 March
2009 limited to the applicant’s filing fees for that
application and the affidavits filed by her in
respect of it
CATCHWORDS: ENVIRONMENT AND PLANNING – POLLUTION –
NOISE POLLUTION AND CONTROL – where compliance
with court order to remedy environmental nuisance is sought
– whether provisions of a court order associated with noise
were breached
Environmental Protection Act 1994 s 440
Environmental Protection Regulation 1998 s 6Z
Cases considered:
Crowther v State of Queensland [2003] QPELR 346
-- 1 of 5 --
2
COUNSEL: Claire Crowther in person
G B Wilshier, solicitor, for the respondent
SOLICITORS: Crown Law for respondent
[1] There has been long running litigation between Ms Crowther and the State as the
operator of Yeronga TAFE College, which began with Crowther v State of
Queensland [2003] QPELR 346. The present application has its genesis in
proceedings Ms Crowther brought last year in which she satisfied his Honour Judge
Robin QC that noise emanating from activity and operations at the college
constituted breaches of s 440 of the Environmental Protection Act 1994 and s 6Z of
the Environmental Protection Regulation 1998.
[2] The first involved a finding that noises from the college constituted an
environmental nuisance; the second, a specific breach of a regulation limiting the
hours upon which air-conditioning equipment might be used if it exuded noise
above a certain level.
[3] The order made by his Honour was not perfected and filed until 5 January 2009,
more than a month after it was pronounced on 3 December 2008. It contains, first, a
declaration that the court is satisfied offences had been committed by noise
emissions contrary to s 440, and s 6Z. Paragraph (2) then sets out specific orders
that the TAFE College carry out the following works:
(a) Reduce noise emissions emanating from an air-compressor in Block
H by the installation of acoustic absorbative treatments by 28
February 2009;
(b) Refasten the loose louvre blades exterior to the mezzanine exhaust
fans in Block G to prevent rattle by 23 December 2008; and
(c) Limit the operating time to the toilet exhaust fan in Block A to
between the hours of 7am and 10pm Monday to Friday and 8am to
4pm on Saturday, by 23 December 2008 and provide the court and
the appellant by 28 February 2009 with a report from the acoustic
expert, Mr King, or another suitably qualified acoustic expert as to
the progress achieved in carrying out those works.
[4] Order 3 prohibited the college from using air-conditioning equipment, including
compressors, during certain specified times if they emitted sounds above a specified
level. Order 4 required the respondent to keep written records about the operation
of all this equipment outside certain specified times. The final order granted liberty
to apply.
[5] Neither the court nor Ms Crowther were provided with a report from Mr King by 28
February 2009. Mr Wilshier who appeared for the State said, and I accept, that the
oversight was his – he thought the order required the works to be completed by that
date, with the report to follow1 .
1 Transcript, p 1-33.1-5.
-- 2 of 5 --
3
[6] On 3 March 2009 Ms Crowther filed a further application in a pending proceeding
seeking compliance with the orders of 3 December 2008, and costs. That
application was heard on 13 March 2003. Ms Crowther cross-examined the
acoustics expert Mr King, and each party made submissions. I reserved my
decision. Then, on 21 April 2009, Ms Crowther filed a further application in a
pending proceeding seeking an order for ‘verbatim (sic) compliance to orders of 3
December 2008 of Planning & Environment Court’.
[7] This application was supported by assertions that, since the hearing on 13 March,
there had been occasions on various days when noise had been detected, and
observations of the stacks at Block H made, suggesting that a compressor was
operating. On 21 April 2009 Ms Crowther filed an affidavit to the effect that she
had heard noises emanating from Block H on 26, 30 & 31 March, and 2, 7, 8, 9, 14,
15 & 16 April 2009, and observed signs that the stacks were in fact operational.
She said that the stack lids ‘…evidents (sic) the usage of a compressor as necessary
to effect each booth’s activity. Each booth is connected to the extraction stacks’.
[8] At the hearing of Ms Crowther’s further application on 27 April 2009 she filed, by
leave, a further affidavit from a neighbour, Mr Rebetzke, to the effect that he had
made similar observations on 12 & 31 March 2009.
[9] At the hearing on 13 March a further report was produced from Mr King2 . He had
conducted an additional inspection on 6 March, with specific reference to the
matters set out in clause 2 of the order of 3 December 2009 and observed:
(a) that the two air compressors in Block H had been decommissioned
with all permanent electrical wiring to each compressor physically
disconnected from the mains supply. Each compressor had also been
fitted with ‘do not operate’ tags. He was confident they had been
permanently disconnected and there was, therefore, now no need for
the acoustic installation works referred to in clause (a) of the order;
(b) the louvre blades in the Block G exhaust fan plant room had been
rectified with timber wedges and adhesive with the result, in his
opinion, that the matter had been ‘appropriately addressed’ and the
‘noise issue removed’; and
(c) His inspection of the electrical switch panel on Level 3 of Block A
revealed a timer had been installed for the roof level exhaust fan
which he tested and satisfied himself that the set operating times
were compliant with the court order.
[10] At the hearing on 13 March the Crown was given leave to file a cross-application
for an order that paragraph 2(a) of the order of 3 December be amended by inserting
the words ‘…or by decommissioning the air-compressors in H Block’.
[11] Ms Crowther delivered additional written submissions at the hearing on 27 April.
They are, intending no disrespect, a little difficult to follow but appear to involve
the following assertions:
2 Exhibit 1.
-- 3 of 5 --
4
(a) that there has been non-compliance with paragraph 2 of the Order of
3 December 2008;
(b) that unacceptable noise continues to emanate from Block H;
(c) that this noise may be related to ‘extraction’ and the stacks; and,
(d) that there should be some ‘refinement’ of the existing order.
[12] There has been, it is true, non-compliance in strict terms with the order of 3
December 2008 but the evidence of Mr King, corroborated by photographs and
invoices from contractors who performed the decommissioning works and the like,
is persuasive that steps have been undertaken which achieved the same ends as
those to which the order was directed, and that was done in a timely way. It is
appropriate, in those circumstances, to vary the earlier order in the way Mr Wilshier
seeks.
[13] As to the question of the operation of the extraction stacks, a difficulty is that they
were not addressed in the order made on 3 December 2008 and the evidence about
noise from them is confusing. During Ms Crowther’s cross-examination of Mr
King on 13 March he said that it was unlikely the extraction stacks or fans were
functioning or emitting noise because they were required to operate at such times as
spray painting was being conducted on the ground floor of Block H, and if the air
compressors there had been decommissioned and could not supply air to the ground
floor it was unlikely the stacks would be used3 .
[14] Later, however, he admitted he did not know what might now be occurring on the
ground floor of Block H. Ms Crowther tendered a document apparently presented
to his Honour Judge Robin QC at the hearing which led to his order last year 4
which, she said, showed that levels of noise from the extraction stacks were much
the same as those from the compressors. As I understood her submissions she
thereby sought to establish that offensive noises from, or associated with, the stacks
at a level which led Robin QC DCJ to make Order 2(a) should, therefore, lead to a
similar order in respect of the extraction fans/stacks.
[15] The difficulty with that submission is that, as his Honour’s Reasons delivered 27
October 2008 show, he specifically considered the two extraction fans and stacks in
Block H, 5 but was not persuaded to go beyond the orders he actually made and
particularly said, at page 26, that there is ‘…no evidence before the court to indicate
what more specific orders the court might usefully pronounce’. He had before him
the document which became exhibit 2 in this hearing. No new evidence has been
adduced, in Ms Crowther’s subsequent applications, to show noise from the
extraction fans or stacks offends the legislation.
[16] In summary, either the question of noise from the stacks has already, then, been
determined or the evidence does not presently establish breaches of the relevant
provisions associated with that noise.
3 T1-17.27-34.
4 Exhibit 2 on 13 March 2009.
5 Reasons, p3.
-- 4 of 5 --
5
[17] It will be ordered that paragraph 2(a) of the order made by this court on 3 December
2008 be amended by inserting the words, ‘… or by decommissioning the air
compressors in H Block’; and, in the face of the established technical breach of
order no. 2, that the respondent pay the applicant’s costs of and incidental to the
application filed 3 March 2008 limited to the applicant’s filing fees for that
application and the affidavits she subsequently filed in the matter (an order
volunteered by Mr Wilshier). The application of that date, and the further
application filed 21 April 2009, are otherwise dismissed.
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2009/031