Bezzina Developers Pty Ltd v Deemah Stone (Qld) Pty Ltd & Ors [2008] QCA 213 [2008] 2 Qd R 495
SUPREME COURT OF QUEENSLAND
CITATION: Bezzina Developers P/L v Deemah Stone (Qld) P/L & Ors
[2008] QCA 213
PARTIES: BEZZINA DEVELOPERS PTY LTD ACN 079 373 470
(applicant/first respondent)
v
DEEMAH STONE (QLD) PTY LTD ACN 115 129 014
(first respondent/appellant)
MAX TONKIN
(second respondent)
HELEN DURHAM
(third respondent)
ADJUDICATE TODAY PTY LTD ACN 109 605 021
(fourth respondent)
FILE NO/S: Appeal No 9882 of 2007
BS No 6000 of 2007
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 1 August 2008
DELIVERED AT: Brisbane
HEARING DATE: 17 April 2008
JUDGES: McMurdo P, Keane JA and Fraser JA
Separate reasons for judgment of each member of the Court,
each concurring as to the orders made
ORDERS: 1. Allow the appeal and set aside the orders made on
7 November 2007
2. In lieu thereof order that the application for an
order of review and other relief filed by the first
respondent (matter no. BS 6000 of 2007) be
dismissed with costs to be assessed on the standard
basis
3. First respondent pay the appellant's costs of and
incidental to the appeal, save for the costs of the
appeal record, which should be borne by the
appellant
CATCHWORDS: ARBITRATION – CONDUCT OF THE ARBITRATION
PROCEEDINGS – POWERS, DUTIES AND DISCRETION
-- 1 of 20 --
2
OF THE ARBITRATOR – GENERALLY – where the first
respondent contended that the second respondent (an
adjudicator) had erred in law by failing to make a bona fide
attempt to value the work in a progress claim submitted to
him – where s 26 of the Building and Construction Industry
Payments Act 2004 (Qld) required the second respondent to
decide and not to inquire when making an adjudication
decision – where subsections (c) and (d) of s 26(2) required
the second respondent to consider the payment claim and
submissions as well as any payment schedules and any
submissions in support of it in adjudicating the dispute –
where the second respondent’s reasons for the adjudication
decision referred to the relevant background matters, parts of
the payment schedule, the first respondent’s failure to lodge
an adjudication response and the second respondent’s
understanding of several paragraphs of the schedule –
whether the second respondent failed to value the work in a
manner required by the Act
ARBITRATION – CONDUCT OF THE ARBITRATION
PROCEEDINGS – POWERS, DUTIES AND DISCRETION
OF THE ARBITRATOR – GENERALLY – where s 27 of
the Building and Construction Industry Payments Act 2004
(Qld) requires that where a subsequent adjudication occurs in
which work is valued that was valued in a previous
adjudication, the adjudicator must use the same value unless
the claimant or respondent satisfies the adjudicator concerned
that the value of the work has changed since the previous
decision – where the third respondent made a decision
regarding progress payment 12 submitted by the appellant –
where that decision was not released until 13 April 2007 –
where the second respondent made a decision on 4 April
2007 regarding progress payment 13 which included work
from progress payment 12 – where the second respondent’s
valuation of the work under progress payment 12 was higher
than the valuation of the third respondent – where the primary
judge found that the second respondent had erred in law in
failing to take into account the effect of s 27 upon his
obligation to value the work the subject of the payment claim
by giving it the same value as attributed to in the first
adjudication decision – where the primary judge found that
the error of law was sufficient to justify the exercise of the
jurisdiction under s 20(2)(f) of the Judicial Review Act 1991
(Qld) – where the primary judge found that the error of law
constituted a jurisdictional error that enlivened the power to
grant declaratory and injunctive relief and to set aside the
adjudication – whether s 27 of the Act required the second
respondent to value the work the subject of the payment
claim submitted to him by giving it the same value attributed
-- 2 of 20 --
3
to it in the first adjudication
ARBITRATION – CONDUCT OF THE ARBITRATION
PROCEEDINGS – POWERS, DUTIES AND DISCRETION
OF THE ARBITRATOR – GENERALLY – where s 27 of
the Building and Construction Industry Payments Act 2004
(Qld) requires that where a subsequent adjudication occurs in
which work is valued that was valued in a previous
adjudication, the adjudicator must use the same value unless
the claimant or respondent satisfies the adjudicator concerned
that the value of the work has changed since the previous
decision – where neither the appellant or the first respondent
informed the second respondent that the third respondent had
valued work the subject of the second respondent’s
adjudication – whether in the context of the statute as a
whole, the adjudicator is obliged to take into account an
earlier adjudication only where the adjudicator is informed of
the earlier adjudication decision
ARBITRATION – CONDUCT OF THE ARBITRATION
PROCEEDINGS – POWERS, DUTIES AND DISCRETION
OF THE ARBITRATOR – GENERALLY – where s 25(4)(a)
of the Building and Construction Industry Payments Act 2004
(Qld) granted an express power to seek further submissions
from the parties – where s 27 did not contain that express
power – whether the adjudicator was obliged to call for
further submissions concerning any prior adjudication
decision
Building and Construction Industry Payments Act 2004
(Qld), s 12, s 13, s 17(2), s 17(6), s 18(2), s 18(3), s 18(5),
s 21(1), s 21(3), s 21(3)(f), s 21(5), s 24(2)(c), s 24(3),
s 24(4), s 25(4)(a), s 27(2), s 25, s 25(3), s 25(4), s 26,
s 26(1), s 26(1)(a), s 26(2), s 26(3), s 27, s 27(2), s 29(2),
s 35(4), s 35(5)
Judicial Review Act 1991(Qld), s 20(2)(f)
Bezzina Developers P/L v Deemah Stone (Qld) P/L [2007]
QSC 286, varied
Cooper Brookes (Wollongong) Pty Ltd v Federal
Commissioner of Taxation (1981) 147 CLR 297; [1981] HCA
26, cited
Coordinated Construction Co Pty Ltd v J M Hargreaves
(NSW) Pty Ltd (2005) 63 NSWLR 385; [2005] NSWCA 228,
distinguished
D’Aguilar Gold Ltd v Gympie Eldorado Mining P/L [2008] 1
Qd R 56; [2007] QCA 158, cited
Halkat Electrical Contractors Pty Ltd v Holmwood Holdings
Pty Ltd [2007] NSWCA 32, distinguished
Intero Hospitality Projects P/L v Empire Interior (Australia)
P/L & Anor [2008] QCA 83, referred to
-- 3 of 20 --
4
JJ McDonald & Sons Engineering Pty Ltd v Gall [2005] QSC
305, cited
John Holland Pty Limited v Roads & Traffic Authority of
New South Wales & Ors (2007) 23 BCL 205;
[2007] NSWCA 19, distinguished
The Minister for Commerce(formerly Public Works &
Services) v Contrax Plumbing (NSW) Pty Ltd & Ors
[2005] NSWCA 142, distinguished
Newcastle City Council v GIO General Ltd (1997) 191 CLR
85; [1997] HCA 53, cited
Pongrass Group Operations Pty Ltd v Minister for Planning
(2007) 156 LGERA 250; [2007] NSWLEC 638,
distinguished
Prasad v Minister for Immigration and Ethnic Affairs (1985)
6 FCR 155, distinguished
Project Sky Blue Inc v Australian Broadcasting Authority
(1998) 194 CLR 355; [1998] HCA 28, followed
Rothnere v Quasar Constructions & Ors [2004] NSWSC
1151, cited
Semunigus v The Minister for Immigration and Multicultural
Affairs [1999] FCA 422, distinguished
Transgrid v Walter Construction Group [2004] NSWSC 21,
cited
COUNSEL: P G Bickford, with A B Wallace, for the appellant
G D Beacham for the respondents
SOLICITORS: Moray & Agnew for the appellant
Holding Redlich for the respondents
[1] McMURDO P: I agree with Fraser JA.
[2] KEANE JA: I agree with the reasons of Fraser JA and with the orders proposed by
his Honour.
[3] FRASER JA: On 4 April 2007 the second respondent made an adjudication
decision under the Building and Construction Industry Payments Act 2004 (Qld)
that the amount of a progress payment to be made by the first respondent
("Bezzina") to the appellant ("Deemah") was $655,978.91.
[4] Bezzina applied to the Supreme Court to review that decision under the Judicial
Review Act 1991 (Qld). The primary judge acceded to that application, set the
decision aside with effect from the date upon which it was made, referred the
relevant adjudication application back to the second respondent for consideration
according to law, and made consequential orders. Deemah appeals against those
orders.
Background
[5] Deemah contracted to supply and install stonework for Bezzina, the builder and
developer of a construction project in Surfers Paradise. Deemah's first 11 progress
-- 4 of 20 --
5
claims were duly paid by Bezzina. Disputes then arose concerning progress claims
12 and 13. It is progress claim no. 13 which is in issue in the appeal.
[6] Deemah invoked the provisions of the Building and Construction Industry
Payments Act 2004 (Qld) to recover progress payments under those claims. Section
7 of that Act states that its object is to ensure that a person is entitled to receive, and
is able to recover, progress payments if the person undertakes to carry out
construction work, or to supply related goods and services, under a construction
contract. That object is to be achieved, so s 8 of the Act provides, by granting a
statutory entitlement to progress payments and by establishing a procedure that
involves:
"8(b) …
(i) the making of a payment claim by the person
claiming payment; and
(ii) the provision of a payment schedule by the person by
whom the payment is payable; and
(iii) the referral of a disputed claim, or a claim that is not
paid, to an adjudicator for decision; and
(iv) the payment of the progress payment decided by the
adjudicator."
[7] Deemah's progress claim no. 12 was for $712,149.58. In response, Bezzina's
payment schedule contended that no money was due. In due course that claim was
referred to the third respondent (“the first adjudicator”) for decision.
[8] Deemah subsequently served progress claim no. 13 for $971,995.68 on Bezzina on
28 February 2007. That amount included the amount Deemah had claimed in
progress claim no. 12. That course is sanctioned by s 17(6) of the Act.
[9] On 14 March 2007 Bezzina served on Deemah a payment schedule that responded
to progress claim no. 13. It contended that no money was due. On 28 March 2007
Deemah made an adjudication application for progress claim no. 13. It was referred
to the second respondent (“the second adjudicator”) for decision.
[10] On 29 March 2007, the parties were advised that the first adjudicator’s decision was
ready for release upon payment of the adjudication costs. On 13 April 2007
Deemah paid the adjudication costs and the first adjudication decision was released
to the parties. The decision was that the amount of the progress payment for
progress claim no. 12 was $218,382.14. Neither party advised the second
adjudicator of the first adjudication decision. The reasons for that omission are not
explained in the evidence.
[11] On 4 April 2007 the second adjudicator made his adjudication decision in respect of
progress claim no. 13 that the amount of the progress payment for that claim was
$655,978.91. The second adjudicator’s valuation of so much of progress claim
no. 13 as had been included in progress claim no. 12 was higher than the valuation
of it in the first adjudication decision.
-- 5 of 20 --
6
[12] On 25 May 2007, following some payments by Bezzina, and allowing for other
adjustments for costs and interest, judgment for $528,665.90 was entered in favour
of Deemah against Bezzina. Subsequently, pursuant to an order of the Supreme
Court, Bezzina paid $528,725.57 into court.
The issues in the appeal
[13] The primary judge rejected Bezzina's challenge to the first adjudication decision
concerning progress claim no. 12. 1 That aspect of the decision was not challenged
in the appeal.
[14] In relation to the second adjudication decision, concerning progress claim no. 13,
the primary judge accepted Bezzina’s contention that the decision should be
reviewed on the ground that the adjudicator had contravened s 27(2) of the Building
and Construction Industry Payments Act 2004 (Qld) by failing to adopt the
valuation in the first adjudication decision for so much of the claim as had been
included in progress claim no. 12. Deemah challenges that conclusion.
[15] His Honour rejected Bezzina's contention that the adjudicator erred in law by failing
to make a bona fide attempt to value the work in progress claim no. 13. Pursuant to
a notice of contention, Bezzina seeks to support the judgment in its favour on the
ground that the primary judge erred in rejecting its application for judicial review on
this basis.
The valuation issue
[16] It is convenient to consider the valuation issue first. In order to appreciate
Bezzina’s argument on this issue it is necessary to explain in some more detail the
procedure for the recovery of progress payments set up by the Building and
Construction Industry Payments Act 2004 (Qld).
[17] Section 12 of the Act confers a statutory right to progress payments. Under s 13 the
amount of a progress payment is to be calculated under the relevant contractual
provision or, if there is no such provision, it is to be the value of the work or related
goods and services the subject of the progress claim. The criteria for that valuation
are specified in s 14.
[18] Subsection 17(2) provides that a payment claim must identify the construction work
or related goods and services to which the claimed progress payment relates and
must state the amount of the progress payment that the claimant claims to be
payable ("the claimed amount"). If the respondent replies to the payment claim by
serving a payment schedule on the claimant, s 18(2) requires the payment schedule
to state the amount of the payment, if any, that the respondent proposes to make
("the scheduled amount"). Subsection 18(3) provides that if the scheduled amount
is less than the claimed amount the schedule "must state why the scheduled amount
is less and, if it is less because the respondent is withholding payment for any
reason, the respondent's reasons for withholding payment".
[19] The effect of s 18(5) is that the respondent becomes liable to pay the claimed
amount if the claimant serves a payment claim and the respondent does not serve a
1 Bezzina Developers Pty Ltd v Deemah Stone (Qld) Pty Ltd [2007] QSC 286 at [19]-[26].
-- 6 of 20 --
7
payment schedule within the earlier of the time required by the relevant contract or
10 business days after service of the payment claim.
[20] Where the scheduled amount is less than the claimed amount, or where the
respondent does not pay the scheduled amount or the claimed amount by the due
date, s 21(1) entitles a claimant to apply for adjudication of its payment claim.
Subsection 21(2) provides that an adjudication application cannot be made unless
the claimant gives the respondent a notice of intention to make such application and
the notice states that the respondent may serve a payment schedule on the claimant
within five business days after receiving that notice.
[21] The details concerning adjudication applications are set out in s 21(3). Relevantly,
s 21(3)(f) provides that an adjudication application may contain the submissions
relevant to the application the claimant chooses to include.
[22] Similarly, s 24(2)(c) provides that any “adjudication response” may contain the
submissions the respondent chooses to include. Subsections 24(3) and (4) provide
that the respondent may give an adjudication response only if the respondent has
duly served a payment schedule and the adjudication response may only include as
reasons for withholding payment reasons already included in the earlier payment
schedule.
[23] The adjudication procedures are regulated by s 25. Subsection 25(3) requires an
adjudicator to decide an adjudication application within a very short time; s 25(4)
empowers an adjudicator to seek further submissions from the parties, hold a
conference, or inspect any matter to which the claim relates. I will return to these
provisions.
[24] Subsections 26(1) and (2) provide:
"(1) An adjudicator is to decide—
(a) the amount of the progress payment, if any, to be
paid by the respondent to the claimant (the
adjudicated amount); and
(b) the date on which any amount became or becomes payable;
and
(c) the rate of interest payable on any amount.
(2) In deciding an adjudication application, the adjudicator is to
consider the following matters only—
(a) the provisions of this Act and, to the extent they are
relevant, the provisions of the Queensland Building
Services Authority Act 1991, part 4A;
(b) the provisions of the construction contract from
which the application arose;
(c) the payment claim to which the application relates,
together with all submissions, including relevant
-- 7 of 20 --
8
documentation, that have been properly made by the
claimant in support of the claim;
(d) the payment schedule, if any, to which the
application relates, together with all submissions,
including relevant documentation, that have been
properly made by the respondent in support of the
schedule;
(e) the results of any inspection carried out by the
adjudicator of any matter to which the claim relates.
[25] Subsection 26(3) requires the adjudicator's decision to be in writing and to include
reasons for the decision, unless both parties asked the adjudicator not to include
reasons.
[26] Bezzina’s argument is that the second adjudicator contravened the obligation in
s 26(1)(a) "to decide … the amount of the progress payment …" by simply
accepting the sum claimed by Deemah rather than embarking upon a valuation of
the work. The primary judge rejected the same argument,2 correctly in my
respectful opinion, for the reason that the valuation of the relevant work was not in
issue.
[27] Bezzina's payment schedule referred to Deemah's progress claim no. 13, stated that
it was a payment schedule under the Act and then continued:
“We hereby advise you that the:-
Revised schedule amount due will be = nil
The reasons why the revised scheduled amount = nil are as follows:- ”
[28] There followed a detailed analysis of various matters claimed by Bezzina to require
deductions from the value Deemah had ascribed to the work in progress claim
no. 13.
[29] In the second adjudication decision, the adjudicator referred to relevant background
matters, the part of the payment schedule I have quoted, Bezzina's failure to lodge
an adjudication response, the adjudicator's understanding of several paragraphs that
followed the part of the schedule I have quoted (these paragraphs are not in issue
here), and continued:
"8 The payment schedule consists of a 17 page submission
setting out 'the reasons why the revised schedule amount
equals nil'. …"
[30] After pointing out that Bezzina had failed to lodge an adjudication response after
receiving Deemah's adjudication application, the adjudicator returned to the effect
of Bezzina's payment schedule:
2 Bezzina Developers Pty Ltd v Deemah Stone (Qld) Pty Ltd [2007] QSC 286 at [9], [10], [14], [27],
[28], [30] and [31].
-- 8 of 20 --
9
"15. As I indicated earlier, the payment schedule sets out the
Respondent's reasons for the scheduled amount being $nil.
In most cases, the Respondent indicated an amount that the
Respondent said should be deducted from the claimed
amount. In respect of some of the reasons, it was unclear
how much exactly the Respondent believed should be
deducted.
16. In the adjudication application, the Claimant attempted to
reconcile the deductions against the payment claim, but it
too, found the payment schedule to be unclear and it was
unable to always decipher the amount that the Respondent
proposed to deduct in relation to each reason. Nevertheless,
it seems to be clear that the Respondent's scheduled amount
is $nil, because the sum of the amounts that the Respondent
proposed should be deducted from each of the reasons,
results in deductions that exceed the claimed amount.
17. In the adjudication application, the Claimant responded to
each of the Respondent's reasons in turn. It is appropriate
that I follow this pattern and deal with each reason by
outlining the Respondent's submissions in the payment
schedule, the Claimant's reply to each reason and my
decision in respect of each reason."
[31] The adjudicator then assessed the validity of the reasons assigned by Bezzina for the
particular deductions. No complaint is made about that part of the adjudication.
[32] It is apparent that the adjudicator construed Bezzina's payment schedule as
implicitly admitting Deemah's valuation of the work, subject only to the particular
"reasons why the revised schedule amount = nil" which are then set out in the
schedule.
[33] That view finds significant support in the fact that, because Bezzina's payment
schedule stated as an amount of the payment it proposed to make an amount which
was less than the claimed amount, s 18(3) of the Act obliged Bezzina to "state why
the scheduled amount is less …"
[34] Whilst a particular adjudication might involve a valuation, the express obligation
imposed by s 26 is “to decide”, not “to inquire”. Paragraphs (c) and (d) of
subsection 26(2) required the second adjudicator, in deciding the adjudication
application, to consider the payment claim and submissions as well as any payment
schedule and any submissions in support of it. The valuation ascribed by Deemah
in its payment claim being implicitly admitted by Bezzina in its payment schedule,
the adjudicator was entitled to adopt Deemah’s valuation.
[35] Bezzina’s counsel referred to Coordinated Construction Co Pty Ltd v J M
Hargreaves (NSW) Pty Ltd.3 In that case, Hodgson JA expressed the "tentative
3 Coordinated Construction Co Pty Ltd v J M Hargreaves (NSW) Pty Ltd (2005) 63 NSWLR 385;
[2005] NSWCA 228.
-- 9 of 20 --
10
view" that an adjudicator was not entitled automatically to determine a progress
claim at the amount claimed by the claimant if a respondent to a payment claim did
not raise any relevant ground for denying or reducing it.4 His Honour was not there
concerned with a case such as this, where a respondent does raise relevant grounds
for denying a claim and confines the dispute to those particular grounds. Other
decisions relied upon by Bezzina are similarly distinguishable.5
[36] I would reject Bezzina's contention that the adjudicator erred in law in failing to
value the work in the manner required by the Act.
The claimed contravention of s 27
[37] Section 27 provides:
….
27 Valuation of work etc. in later adjudication application
(1) Subsection (2) applies if, in deciding an adjudication
application, an adjudicator has, under section 14,17
decided—
(a) the value of any construction work carried
out under a construction contract; or
(b) the value of any related goods and services
supplied under a construction contract.
(2) The adjudicator or another adjudicator must, in any
later adjudication application that involves the
working out of the value of that work or of those
goods and services, give the work, or the goods and
services, the same value as that previously decided
unless the claimant or respondent satisfies the
adjudicator concerned that the value of the work, or
the goods and services, has changed since the
previous decision."
[38] The primary judge found that the second adjudicator had erred in law in failing to
take into account the effect of s 27 upon his obligation to value the work the subject
of the payment claim by giving it the same value as attributed to it in the first
adjudication decision. His Honour held that this failure to comply with a statutory
procedure involved an error of law sufficient to justify exercise of the jurisdiction
under s 20(2)(f) of the Judicial Review Act 1991 (Qld).6 His Honour also held that
the second adjudicator's failure to take into account his statutory obligation under
s 27 constituted a jurisdictional error that enlivened the power to grant declaratory
4 Coordinated Construction Co Pty Ltd v J M Hargreaves (NSW) Pty Ltd (2005) 63 NSWLR 385 at
[51]; [2007] NSWCA 228; followed by Brereton J in Pacific General Securities Ltd v Soliman &
Sons Pty Ltd & Ors (2006) 196 FLR 388; [2006] NSWSC 13 at [82].
5 See, eg. Halkat Electrical Contractors Pty Ltd v Holmwood Holdings Pty Ltd [2007] NSWCA 32 at
[25] – [27].
6 Bezzina Developers Pty Ltd v Deemah Stone (Qld) Pty Ltd [2007] QSC 286 at [37].
-- 10 of 20 --
11
and injunctive relief and to set aside the judgment already obtained.7 Deemah
challenges these findings.
The meaning of “decided” and “decision” in s 27
[39] Deemah contended that for the purposes of s 27(2), the first adjudicator's decision
was not "decided" or a "previous decision" by the time of the second adjudication
decision. It was submitted that the value of the construction work was not
"decided" by the first adjudicator until her decision had been released to the parties
on 13 April 2007, which was after the date of the second adjudication decision. On
that view of the Act, s 27(2) did not in this case oblige the second adjudicator to
adopt the value used by the first adjudicator in the first adjudication decision.
[40] The authorities cited by Deemah's counsel in this respect are not on point: they
concerned differently worded statutes where the question whether there was a
“decision” before communication to the persons affected arose in different
contexts.8 The submission requires a meaning to be given to the term “decision” in
s 27(2) that differs from its meaning in other provisions, which draw a distinction
between the adjudicator’s decision and the communication of it to the parties. For
example, s 35(5) provides that s 35(4) does not apply only because an adjudicator
"refuses to communicate the adjudicator's decision" until the adjudicator's fees and
expenses are paid, and s 29(2) refers to the date "on which the adjudicator's decision
is served on the respondent". The obligation in s 25 (3) that an adjudicator must
“decide” an adjudication application as quickly as possible similarly should not be
construed as demanding release of the decision, because that would frustrate the
adjudicator’s right under s 35(5) to withhold release of the decision until the
adjudicator was paid. The appellant’s submission thus runs up against the
presumption that the same words in the same statute bear the same meaning.9
[41] There are therefore substantial difficulties in the way of accepting Deemah’s
submission that the proper construction of the words “decided” and “decision” in
s 27(2) requires the conclusion that it had no application in this case.
[42] I would, however, accept Deemah’s alternative contention that the same conclusion
is required for a different reason, namely that s 27(2) applies only where the
adjudicator is informed of the earlier adjudication decision.
The second adjudicator’s knowledge concerning the first adjudication decision
[43] The primary judge acknowledged that it is difficult to criticise the second
adjudicator for his omission to give the work examined by him the same value that
had been given to it by the first adjudicator when the parties had not brought the
result of the first adjudication to the attention of the second adjudicator. 10
7 Bezzina Developers Pty Ltd v Deemah Stone (Qld) Pty Ltd [2007] QSC 286 at [38].
8 Semunigus v The Minister for Immigration and Multicultural Affairs [1999] FCA 422 at [12], [18]-
[21]; [63]-[78], [103]-[105]; Pongrass Group Operations Pty Ltd v Minister for Planning (2007) 156
LGERA 250; [2007] NSWLEC 638 at 24-25.
9 D’Aguilar Gold Ltd v Gympie Eldorado Mining P/L [2008] 1 Qd R 56 at [26]; [2007] QCA 158.
10 Bezzina Developers Pty Ltd v Deemah Stone (Qld) Pty Ltd [2007] QSC 286 at [32].
-- 11 of 20 --
12
[44] His Honour observed though that, although the adjudicator was not aware of the
result of the first adjudication, he had been informed of the making of the first
adjudication application. Bezzina's counsel contended for a stronger finding, that
the second adjudicator, as a specialist with knowledge of the Act, should have
appreciated that there was probably an earlier adjudication decision on progress
claim no. 12 before he made the second adjudication decision. It is therefore
necessary to consider what the evidence reveals about the state of the second
adjudicator’s knowledge concerning the first adjudication.
[45] Bezzina's payment schedule in response to Deemah's progress claim no. 13 pointed
out that progress claim no. 13 incorporated progress claim no. 12 and that progress
claim no. 12 was the subject of an adjudication application to which Bezzina had
filed its response on 12 March 2007. Deemah's submissions in support of its
adjudication application acknowledged that its progress claim no. 12 was the subject
of a current adjudication application "which adjudication application has not been
decided." Deemah then referred to s 27 and summarised the circumstances
described in s 27(2) in which an adjudicator is not bound by a previous adjudication
decision. In conformity with s 21(5) of the Act, a copy of Deemah’s adjudication
application, which included its submissions, was served on Bezzina. Bezzina did
not serve any adjudication response to that application.
[46] The material before the second adjudicator therefore demonstrated that Bezzina and
Deemah were aware of the potential significance of s 27 if an adjudication decision
on progress claim no. 12 was delivered during the second adjudication process.
[47] Subsection 25(3) of the Act provides:
"(3) Subject to subsections (1) and (2), an adjudicator must
decide an adjudication application as quickly as possible
and, in any case—
(a) within 10 business days after the earlier of—
(i) the date on which the adjudicator receives the
adjudication response; or
(ii) the date on which the adjudicator should have
received the adjudication response; or
(b) within the further time the claimant and the
respondent may agree, whether before or after the
end of the 10 business days."
[48] That provision has a dual significance here. First, because the second adjudicator
was not told whether or not Bezzina and Deemah had agreed to extend the time
within which the first adjudicator was obliged to decide the first adjudication
application, it cannot be inferred that the second adjudicator knew the due date for
the first adjudication decision. Secondly, there being no agreement between
Deemah and Bezzina to extend the time for the second adjudication decision, the
second adjudicator was allowed only a very short period of time to give an
adjudication decision upon progress claim no. 13. Compliance with that time limit
-- 12 of 20 --
13
is important: amongst other things, failure to comply with it deprives the adjudicator
of any remuneration.11
[49] In these circumstances, and particularly because neither party at any time corrected
Deemah's submission that the earlier adjudication application had not been decided,
I conclude that, whilst the second adjudicator knew of the first adjudication
application, the second adjudicator did not know that there had been or that there
probably had been an adjudication decision about progress claim no. 12.
Construction of s 27(2)
[50] The issue then is whether the second adjudicator erred in law in failing to adopt the
valuation made in the first adjudication decision in circumstances in which the
second adjudicator did not know that there had been or that there probably had been
an earlier decision.
[51] The New South Wales decisions to which the Court’s attention was drawn12 do not
concern the proper construction of s 27. There are, however, general statements in
them that suggest that an adjudicator making a decision under the statutory
equivalent in New South Wales of s 26 is not obliged to take into account facts that
(like the earlier adjudication decision here) are not disclosed by either party to the
adjudicator.
[52] For example, in John Holland Pty Ltd v Road Traffic Authority of New South
Wales13 , Hodgson JA, referring to his reasons in Minister for Commerce v Contrax
Plumbing (NSW) Pty Ltd, said (I have added the emphasis):
"[48] However, it is to be noted that I said that the adjudicator was
required by pars.(a) and (b) of s.22(2) to consider matters “if
he or she thinks [they are] relevant to the construction of the
Act, the construction of the contract, and the validity of the
terms of the contract having regard to the provisions of the
Act”. To put this another way, I was saying that the
adjudicator should not ignore something which he or she
is aware of and also believes is of real relevance to issues
arising under pars.(a) and (b), simply because the matter
was not raised in submissions duly made by a respondent.
Of course, if the matter has not been so raised, there may be
questions of natural justice to the claimant that need to be
addressed, perhaps by calling for further submissions or by
arranging a conference; but that is another issue. However,
the requirement for natural justice to the claimant is a
11 Subsection 35(4) provides that an adjudicator is not entitled to be paid any fees or expenses if the
adjudicator fails to make a decision on the application within the time allowed by s 25(3), unless that
happens because the application is withdrawn or the dispute is resolved.
12 Coordinated Construction Co Pty Ltd v J M Hargreaves (NSW) Pty Ltd (2005) 63 NSWLR 385 at
[51] – [52]; [2005] NSWCA 228; Minister for Commerce v Contrax Plumbing (NSW) Pty Ltd [2005]
NSWCA 142 at [34] – [37]; John Holland Pty Ltd v Road Traffic Authority of New South Wales
(2007) 23 BCL 205; [2007] NSWCA 19 at [48] – [49].
13 John Holland Pty Ltd v Roads and Traffic Authority of New South Wales (2007) 23 BCL 205; [2007]
NSWCA 19 at [48] – [49].
-- 13 of 20 --
14
further reason why the adjudicator would not be required to
consider such matters under pars.(a) or (b) unless he or she
thought they were really material to issues arising under
those paragraphs.
[49] Thus, in my opinion, any requirement to consider such
matters which were not raised in submissions duly made
arises only after a threshold is crossed, involving both
awareness of the matters in question and a belief that
they are of real relevance. .."
[53] The Court’s attention was also drawn to decisions concerning a variety of different
statutes that suggest that a decision-maker might err in law by making a decision
without making enquiries about material not provided by the parties in particular
cases. In one decision, for example, it was said that there would be such an error
where “it is obvious that material is readily available which is centrally relevant to
the decisions to be made.”14
[54] It is not necessary to refer to the numerous other decisions on that topic to which the
Court was referred. The differences between s 27 and the statutory provisions
considered in those decisions render them of no real assistance in resolving the issue
here. It turns upon the proper construction of s 27.
[55] As to that, it seems most unlikely that the legislature intended that, in circumstances
in which neither party has informed the adjudicator of the earlier decision, the
adjudicator would be obliged to make enquires to discover if there is an earlier
decision, obtain a copy of it, and then prepare a decision that takes the earlier
decision into account. Such a result seems even more startling when it is recalled
that the adjudicator has no power to compel answers to enquires he or she might
make, the adjudicator has no power to compel production of any earlier decision,
and the adjudicator would lose the right to remuneration for undertaking the
adjudication if the taking of those additional steps led to the adjudicator failing to
make an adjudication decision within the very short period of time allowed by the
Act.
[56] The better view of s 27(2) is that it operates on the premise that one of the parties
will have informed the adjudicator of any relevant, previous adjudication decision.
That is suggested both by the proviso within s 27(2), which contemplates that the
claimant or respondent might satisfy the adjudicator that there has been a change in
the value of the work since the previous decision, and by the context in which s 27
appears in the Act.
[57] Where s 27(2) applies, it informs the manner in which the adjudicator is to perform
the function imposed by s 26(1) of deciding the amount of a progress payment. In
performing that function, s 26(2) requires the adjudicator to take into account only
the matters described in paragraphs (a)-(e) of that subsection. The only paragraphs
of that subsection that qualify as potential sources of knowledge in the adjudicator
14 Prasad v Minister for Immigration and Ethnic Affairs (1985) 6 FCR 155 at 170 per Wilcox J; See
also Luu v Renevier (1989) 91 ALR 39 at 49 per Davies, Wilcox and Pincus JJ.
-- 14 of 20 --
15
of a previous adjudication decision are paragraphs (c) and (d). Those paragraphs
contemplate that the parties will supply the necessary information for the task.
[58] It is a fundamental rule of statutory construction that the provision to be construed
must be understood in its context:
"The primary object of statutory construction is to construe the
relevant provision so that it is consistent with the language and
purpose of all the provisions of the statute. The meaning of the
provision must be determined “by reference to the language of the
instrument viewed as a whole.” In Commissioner for Railways
(NSW) v Agalianos Dixon CJ pointed out that "the context, the
general purpose and policy of a provision and its consistency and
fairness are surer guides to its meaning than the logic with which it is
constructed." Thus, the process of construction must always begin
by examining the context of the provision that is being construed." 15
[59] The context of s 27 to which I have referred confirms that its purpose is to impose
an obligation upon an adjudicator to take into account an earlier adjudication
decision only where the adjudicator is informed of that earlier adjudication decision.
[60] The result of the contrary construction of s 27, that it obliges an adjudicator to take
into account a fact of which the adjudicator remains unaware because the parties,
who both know the fact, have failed to tell the adjudicator of it, is appropriately
characterised as absurd. As Gibbs CJ pointed out in Cooper Brookes (Wollongong)
Pty Ltd v Federal Commissioner of Taxation, 16 the canons of construction are not
so rigid as to prevent a realistic solution in such a case. If it is right to say that the
construction I prefer may be adopted only by reading into s 27(2) words (such as
"… the same value as that previously decided in a decision made known to the
adjudicator unless the claimant or respondent …") then such words may be read
into the provision to give effect to the legislative purpose.17
The adjudicator’s power to seek further submissions
[61] One of the primary judge's reasons for reaching the conclusion that s 27(2) applied
in this case was that s 26(2)(a) obliged the adjudicator to take into account the
provisions of the Act (including s 27) and in that context had the power to ask for
further written submissions from either party under s 25(4)(a) of the Act. 18
[62] Paragraph (a) of s 26(2) (which I set out earlier in these reasons) undoubtedly
obliges an adjudicator to take s 27 into account but, in my respectful opinion, where
an adjudicator does not know that there has been or has probably been an earlier
15 Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355 at 381 [69]-[71];
[1998] HCA 28 (citations omitted).
16 Cooper Brookes (Wollongong) Pty Ltd v Federal Commissioner of Taxation (1981) 147 CLR 297 at
304; see also per Mason and Wilson JJ at 320-321; [1981] HCA 26.
17 cf Newcastle City Council v GIO General Ltd (1997) 191 CLR 85 at 113 per McHugh J; [1997]
HCA 53, a passage cited by the primary judge; see also per Muir JA in Ravenscroft v Nominal
Defendant [2007] QCA 435 at [33]-[48].
18 Bezzina Developers Pty Ltd v Deemah Stone (Qld) Pty Ltd [2007] QSC 286 at [34]-[36].
-- 15 of 20 --
16
adjudication the adjudicator is entitled to regard s 27 as having no potential
application.
[63] Subsection 25(4) provides:
"(4) For a proceeding conducted to decide an adjudication
application, an adjudicator—
(a) may ask for further written submissions from either
party and must give the other party an opportunity to
comment on the submissions; and
(b) may set deadlines for further submissions and
comments by the parties; and
(c) may call a conference of the parties; and
(d) may carry out an inspection of any matter to which
the claim relates."
[64] There would be obvious difficulties in any contention that the second adjudicator
made a reviewable error of law in failing to seek further submissions under that
provision, which confers a discretion upon the adjudicator.19 The primary judge did
not find that the adjudicator was obliged to exercise his discretion under s 25(4)(a)
to call for further written submissions and Bezzina does not contend for such a
finding in this appeal. Where, as in this case, the adjudicator does not know that
there is, or that there probably is, a prior adjudication decision, no occasion arises
for the exercise of the power to call for further submissions concerning any prior
adjudication decision.
[65] In my respectful opinion, an obligation to seek further submissions from the parties
on that topic should not be implied in s 27 when an express power to seek further
submissions exists in s 25(4)(a). Implying such an obligation would also create
practical difficulties in view of the very limited time available to adjudicators to
make decisions and the absence of compulsive powers to obtain any prior
adjudication. If the parties fail to inform the adjudicator of an earlier adjudication
decision, it seems too much to ask of the adjudicator that he or she should delay a
decision for the purpose merely of making enquiries and at the risk of losing any
right to remuneration.
[66] Had Bezzina been so minded it could have informed the second adjudicator that the
first adjudication decision had been made. It is true that s 24(4) prevents a
respondent from including in an adjudication response a reason for withholding
payment which was not included in the respondent's payment schedule, but Bezzina
had drawn the adjudicator's attention to the fact that progress claim no. 13 included
the amount claimed in progress claim no. 12. Deemah's submission, to which I
earlier referred, plainly enough construed that as an invocation of s 27 in the event
that the first adjudication decision was made before the second adjudication
19 cf Transgrid v Walter Construction Group Ltd [2004] NSWSC 21; Multiplex Constructions Pty Ltd v
Luikens [2003] NSWSC 1140; Abel Point Marina (Whitsundays) P/L & Anor v Uher [2006] QSC
295 per Wilson J at [20].
-- 16 of 20 --
17
decision. In these circumstances s 24(4), read in the light of s 27, would not have
prevented Bezzina from drawing the second adjudicator's attention to the first
adjudication decision. Further, Bezzina might have paid the first adjudicator’s fees
and expenses, obtained a copy of the decision, and provided it to the second
adjudicator. It was not obliged to do that, but its failure to do so tends to undermine
its complaint that the second adjudicator erred by failing to take the first
adjudication decision into account.
“Forum shopping”
[67] The primary judge also considered that the apparent purpose of s 27(2) was to
discourage "forum shopping" among adjudicators, and that this suggested that the
parliamentary intention might have been that a later adjudicator would take steps to
inform himself or herself whether there had been an earlier, relevant adjudication
decision. 20
[68] There are references to discouraging “adjudicator shopping” in some decisions,21
but in my respectful opinion that desirable aim does not justify the construction of
s 27(2) advocated by the respondent. Other provisions of the Act appear to be
designed for that purpose. Adjudicators are not selected by particular applicants but
by the “authorised nominating authority” to whom the applicant gives the
adjudication application.22 The elaborate scheme for the registration and control of
authorised nominating authorities in Part 4 of the Act appears to be designed to
achieve, amongst other aims, the exercise of their functions independently of the
wishes of individual claimants.
Errors in the adjudication decision
[69] The construction of s 27 advocated by Bezzina is also not justified by the
submission on its behalf that the effect of the second adjudicator having failed to
take into account the valuation in the first adjudication decision was an increase
over that valuation for the same work of $320,000. That figure is contentious, but it
is clear that the two valuations differ significantly. Both cannot be correct, but it is
not possible on the material available to the Court to say which is correct.
[70] Occasional discrepancies of this kind are an inevitable consequence of the very
short time frames allowed for claims, responses, and adjudication decisions and the
necessary limits on the information available to adjudicators. The precision aimed
for in litigation is not practically achievable under the Act. In Intero Hospitality
Projects Pty Ltd v Empire Interior (Australia) Pty Ltd23 , Muir JA (with whose
reasons Holmes JA and Chesterman J agreed), after referring to the second reading
speech for the Bill for the Act and summarising the regime under the Act, said:
" [51] It is apparent from the foregoing that the Act is intended to
provide a mechanism by which claims for payment under
construction contracts can be decided quickly, on an interim
20 Bezzina Developers Pty Ltd v Deemah Stone (Qld) Pty Ltd [2007] QSC 286 at [34]-[36].
21 Rothnere Pty Ltd v Quasar Constructions Pty Ltd [2004] NSWSC 1151 at [41]; John Goss Projects v
Leighton Contractors & Anor [2006] NSWSC 798 at [62].
22 Section 21(3)(b).
23 Intero Hospitality Projects Pty Ltd v Empire Interior (Australia) Pty Ltd [2008] QCA 83.
-- 17 of 20 --
18
basis and by which payment can be enforced even though a
dispute in respect of the right to payment is being litigated
or is subject to an alternative dispute resolution process. It
is apparent also that in making determinations under the Act
adjudicators will often lack the evidence upon which and the
time within which to make fully informed considered
determinations. That does not matter in the scheme of
things, as adjudicators’ determinations do not finally
determine parties’ contractual rights. That is left to the
courts or to alternative dispute resolution processes agreed
upon by the parties."
[71] For these reasons, and for the reasons I earlier gave, the potential difference
between the two valuations is not, in my view, a sufficient basis for construing s 27
as obliging an adjudicator to delay an adjudication for the purposes of seeking to
ascertain whether or not there has been an earlier adjudication that the parties have
not brought to the adjudicator’s attention.
Other construction issues
[72] The omission of any provision in the Act expressly dealing with a case of this kind
creates difficulties, whatever construction is adopted. For example, where an earlier
adjudication decision is brought to the second adjudicator’s attention only after the
second adjudication application has been served, compliance by the second
adjudicator with the rigorous time limit for making a decision might be put at risk if
the second adjudicator were required to take the first decision into account,
particularly if the parties wished to be heard about the effect of the earlier decision.
Another difficulty is that a third adjudicator is not given any clear guidance whether
he or she is obliged to adopt the first or the second adjudication where they provide
different valuations of the same work.
[73] Problems of that kind, however they be resolved, do not justify construing s 27 as
obliging the second adjudicator to take the first decision into account in
circumstances in which the parties have not brought it to the second adjudicator’s
attention. Such a construction would increase the risk of breaches of the time limits
for adjudications, contrary to the central object of the Act of securing prompt
progress payments. It would also increase the risk that matters outside adjudicators’
control might unfairly lead to the loss of their remuneration, thereby deterring
qualified persons from becoming adjudicators.
Conclusion
[74] For these reasons I would uphold the appellant’s contention that the primary judge
erred by concluding that the second respondent erred in law in failing to take into
account the first adjudication decision. It follows that, in my view, there was
neither an error of law sufficient to justify review under s 20(2)(f) of the Judicial
Review Act 1991 (Qld) nor any jurisdictional error of the character found by the
primary judge.
[75] In view of my conclusion that there was no error justifying judicial review, the
question whether the adjudication decisions here in issue were reviewable at all
-- 18 of 20 --
19
under the Judicial Review Act 1991 (Qld) does not arise in this appeal, in which
Deemah did not put in issue the primary judge’s conclusion that, as had been held in
decisions in the Trial Division,24 an adjudication decision is amenable to review
under Part 3 of the Judicial Review Act 1991 (Qld). I note also that the appeal falls
to be decided with reference to the law in force before the commencement of the
Justice and Other Legislation Amendment Act 2007 (Qld). From the
commencement of that Act, adjudication decisions are not reviewable under the
Judicial Review Act 1991 (Qld).25
Discretionary dismissal of the application
[76] Had I concluded that judicial review was available, the question would have arisen
whether this was an appropriate case for the exercise of the Court's power to dismiss
the application for judicial review pursuant to s 48 of the Judicial Review Act 1991
(Qld). Under that section, the Court is empowered, of its own motion, to dismiss an
application on the grounds that it would be inappropriate to grant the application.
[77] Bezzina failed to inform the adjudicator that Deemah’s valuation of the progress
claim was in dispute. It also failed to inform the second adjudicator of the first
adjudication decision even though, when its adjudication response was due on 4
April 2007, it had known for a week that the first adjudication decision had been
made and was available for release upon payment of the adjudication costs.
[78] It follows that Bezzina’s conduct contributed to what it contends were the errors of
law by the second adjudicator that justified judicial review of the decision on
progress claim no. 13. That being so, and having regard to the policy of the Act
referred to in Intero Hospitality Projects Pty Ltd v Empire Interior (Australia) Pty
Ltd,26 there is much to be said for the view that the application for judicial review
should have been dismissed even had Bezzina made out one of the errors of law for
which it contended.
Costs
[79] Costs should follow the event, save in one respect. The appeal record occupied
1,660 pages, of which only a very small fraction were referred to the Court or
otherwise relevant. There was no justification for a record comprising more than a
very slim folder of material. The costs of the record must also have been increased
by the mistakes which necessitated the late production of a supplementary volume
of some 80 pages. At the hearing of the appeal the appellant, through its counsel,
24 JJ McDonald & Sons Engineering Pty Ltd v Gall [2005] QSC 305; Roadtek v Davenport [2006]
QSC 47; State of Queensland v Epoca Constructions Pty Ltd [2006] QSC 324 at [16]-[35]; Abel
Point Marina (Whitsundays) Pty Ltd v Uher [2006] QSC 295 at [2]; ACN 060 559 971 Pty Ltd v
O'Brien [2007] QSC 91 at [16].
25 The Justice and Other Legislation Amendment Act 2007 (Qld), s 91, inserted “8 Building and
Construction Industry Payments Act 2004 (Qld), part 3, division 2’” into schedule 1 part 2 of the
Judicial Review Act 1991 (Qld). After the commencement of that amendment on 28 September 2007
(2007 SL No. 241), the Judicial Review Act 1991 (Qld) has no application to adjudication decisions:
see Judicial Review Act 1991 (Qld), s 18. In my respectful opinion, adjudications are no longer
reviewable under any part of the Judicial Review Act 1991 (Qld): cf Intero Hospitality Projects Pty
Ltd v Empire Interior (Australia) Pty Ltd [2008] QCA 83 at [61].
26 Intero Hospitality Projects Pty Ltd v Empire Interior (Australia) Pty Ltd [2008] QCA 83 at [51] –
[57].
-- 19 of 20 --
20
appropriately acknowledged that the responsibility for the state of the record lay
with it. For these reasons I would deny the appellant the costs of the record.
Disposition
[80] I would allow the appeal and set aside the orders made on 7 November 2007. In
lieu of those orders I would order that the application for an order of review and
other relief filed by the first respondent (matter no. BS6000 of 2007) be dismissed
with costs to be assessed on the standard basis. I would order that the first
respondent pay the appellant's costs of and incidental to the appeal, save for the
costs of the appeal record, which should be borne by the appellant.
-- 20 of 20 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2008/213