Arnold Electrical & Data Installations Pty Ltd v Logan Area Group Apprenticeship/Traineeship Scheme Ltd [2008] QCA 100
SUPREME COURT OF QUEENSLAND
CITATION: Arnold Electrical & Data Installations P/L v Logan Area
Group Apprenticeship/Traineeship Scheme Ltd
[2008] QCA 100
PARTIES: LOGAN AREA GROUP
APPRENTICESHIP/TRAINEESHIP SCHEME
LIMITED
ACN 010 799 809
(plaintiff/respondent/cross-applicant)
v
ARNOLD ELECTRICAL & DATA INSTALLATIONS
PTY LTD
ACN 056 068 896
(defendant/applicant/cross-respondent)
FILE NO/S: Appeal No 10788 of 2007
Appeal No 10942 of 2007
DC No 106 of 2007
DIVISION: Court of Appeal
PROCEEDING: Application for Leave s 118 DCA (Civil)
ORIGINATING
COURT: District Court at Brisbane
DELIVERED ON: 2 May 2008
DELIVERED AT: Brisbane
HEARING DATE: 15 April 2008
JUDGES: McMurdo P, Fraser JA and Lyons J
Separate reasons for judgment of each member of the Court,
each concurring as to the orders made.
ORDER: Applications for leave to appeal by both parties are
dismissed in each case with costs to be assessed on the
standard basis
CATCHWORDS: APPEAL AND NEW TRIAL – APPEAL – PRACTICE
AND PROCEDURE – QUEENSLAND – WHEN APPEAL
LIES BY LEAVE OF COURT – GENERALLY – where
s 118(3) of the District Court of Queensland Act 1967 (Qld)
confers a general discretion on the Court of Appeal to grant
or refuse leave to appeal – where the Court of Appeal held
that the primary judge erred in construing the contract –
where the argument relied upon to demonstrate that error
before the Court of Appeal was not raised before the trial
judge – where the evidence placed before the trial judge was
unclear – where the pleadings at the trial did not identify any
material facts to support the claim – where the quantum in
-- 1 of 11 --
2
issue was relatively small – where the matter had already
been litigated in two courts – whether leave to appeal should
be granted in the circumstances
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS – OTHER
MATTERS – where the contract contained a ‘change clause’
– where the change clause referred to an ‘award rate’ – where
the term ‘award rate’ referred to labour costs – where the
relevant labour costs were changed by an ‘enterprise
bargaining agreement’ – whether, on a correct interpretation
of the contract, the change effected by the ‘enterprise
bargaining agreement’ amounted to a change of the ‘award
rate’ for the purposes of the contract
EVIDENCE – ADMISSIBILITY AND RELEVANCY –
OPINION EVIDENCE – EXPERT OPINION – IN
GENERAL – where the defendant alleged that its witness
was an expert – where the witness relied upon facts which
were not identified and proved or admitted – whether the
evidence had any probative effect
EVIDENCE – ADMISSIBILITY AND RELEVANCY – IN
GENERAL – OBJECTIONS – where evidence was tendered
that allegedly proved various material facts – where no
objection was made – whether because of the absence of an
objection to its tender the evidence had probative effect
PROCEDURE – SUPREME COURT PROCEDURE –
QUEENSLAND – PROCEDURE UNDER RULES OF
COURT – PLEADING GENERALLY – where there was a
dispute as to the applicable rate of labour cost to be applied –
where the defendant contented that a particular applicable
rate of labour applied – where the plaintiff pleaded an
explanation for its denial of the defendant’s contention –
where the defendant submitted that the denial in the
plaintiff’s pleadings was insufficient – where the defendant’s
pleadings did not allege any facts to support the contention –
where the defendant submitted that r 166 of the Uniform Civil
Procedure Rules 1999 (Qld) had the effect that the
insufficient reply amounted to a deemed admission – whether
the insufficient reply amounted to a deemed admission by the
plaintiff of the defendant’s contention
District Court of Queensland Act 1967 (Qld), s 118(2)
Industrial Relations Act 1990 (Qld)
Industrial Relations Act 1999 (Qld), s 136(2)
Uniform Civil Procedure Rules 1999 (Qld), r 149(1)(b),
r 149(1)(c), r 149(3)(a), r 157(a), r 166
-- 2 of 11 --
3
ACI Operations Pty Ltd v Bawden [2002] QCA 286, cited
Cohen & Co v Ockerby & Co Ltd (1917) 24 CLR 288;
[1917] HCA 58, followed
Gollin & Co Ltd v Karenlee Nominees Pty Ltd (1983) 153
CLR 455; [1983] HCA 38, cited
Groves v Australian Liquor, Hospitality and Miscellaneous
Workers’ Union & Anor [2004] QSC 142, cited
Hughes v National Trustees, Executors and Agency Co of
Australasia Ltd (1979) 143 CLR 134; [1979] HCA 2, cited
Magburry Pty Ltd v Hafele Australia Pty Ltd (2001) 210 CLR
181; [2001] HCA 70, followed
Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR; [2004]
HCA 35, followed
R v Ping [2006] 2 Qd R 69; [2005] QCA 472, cited
Suttor v Gundowda Pty Ltd (1950) 81 CLR 418; [1950]
HCA 35, cited
Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR
165; [2004] HCA 52, followed
Worchild v Petersen [2008] QCA 26, cited
COUNSEL: D R Kent, with A R Fitzsimons, for the
plaintiff/respondent/cross-applicant
N H Ferrett for the defendant/applicant/cross-respondent
SOLICITORS: Hall Payne Lawyers for the plaintiff/respondent/cross-
applicant
Woods Prince Lawyers for the defendant/applicant/cross-
respondent
[1] McMURDO P: Both applications for leave to appeal should be refused with costs
for the reasons given by Fraser JA.
[2] FRASER JA: Logan Area Group Apprenticeship/Traineeship Scheme Limited
("the plaintiff") obtained a judgement in the Magistrates Court against Arnold
Electrical & Data Installations Pty Ltd ("the defendant") for $12,834.53. The
plaintiff's claim was made under a labour supply contract made in 1998 pursuant to
which the plaintiff “hired” electrical apprentices to the defendant at an hourly rate
until late 2003.
[3] The defendant pleaded various defences and counterclaimed $89,621.98 by way of
restitution on the basis that the plaintiff had overcharged the defendant that amount
during the currency of the contract. The Magistrates Court dismissed the
defendant’s counterclaim with costs.
[4] The District Court allowed an appeal by the defendant against the plaintiff’s
judgment but refused the defendant's appeal against the dismissal of its
counterclaim.
-- 3 of 11 --
4
[5] Each of the plaintiff and the defendant now seek leave to appeal to this Court
pursuant to s 118(3) of the District Court of Queensland Act 1967 (Qld). The
provision confers a general discretion on this Court to grant or refuse leave to
appeal which is exercisable according to the nature of the case1 . That discretion is
not circumscribed, but leave will usually be granted only where an appeal is
necessary to correct a substantial injustice to the applicant and there is a reasonable
argument that there is an error to be corrected.2
Plaintiff's application
[6] The contract described the hourly rates to be charged by the plaintiff (in the contract
called "GTA") in the following terms:
"The hourly rate charged by GTA covers base pay, sick pay, annual
leave (including 17.5%), gazetted holidays, TAFE block release,
occupational superannuation, workers compensation insurance,
award fares & travel if applicable to trade and includes the award
tool allowance.
The hourly rate does not include site allowances, additional travel
over standard award rate.
In case of wet days the first wet day will be charged at the normal
charge out rate to your account, subsequent consecutive wet days
provided the apprentice telephones the office before 8.30am will be
paid by Group Training."
[7] The particular provision (which I will call the "change clause") pursuant to which
the plaintiff's claim was made provided:
"If an award rate is changed and backdated whilst the
apprentice/trainee is with you the amount will be charged to your
account for the relevant period."
[8] The Magistrate found that when that contract was made there was a State award
pursuant to which the plaintiff paid its apprentices and that the plaintiff invoiced the
defendant throughout the period of the contract with reference to the rates set out in
that award.
[9] It is now common ground that, as the Magistrate found, on 26 May 2003 the
provisions of that award, insofar as they applied to regulate the plaintiff's
obligations to its employed apprentices whilst they were employed at the
defendant’s workplace, were replaced by a certified agreement (also known as an
1 ACI Operations P/L v Bawden [2002] QCA 286.
2 Worchild v Petersen [2008] QCA 26; Monte Carlo Caravan Park P/L v Curyer [2006] QCA 363;
[2007] 2 Qd R 57; Pickering v MacArthur [2005] QCA 294; Rigney v Littlehales [2005] QCA 252;
Pugin v WorkCover Queensland [2005] QCA 66 at [15]; [2005] 2 Qd R 37 at 40;
Labaj v Brown [2005] QCA 54.
-- 4 of 11 --
5
“Enterprise Bargaining Agreement” or “EBA”) entitled "Arnold Electrical & Data
Installations Pty Ltd Certified Agreement 2003."
[10] Subsection 136(2) of the Industrial Relations Act 1999 (Qld) had the effect that the
plaintiff was obliged to pay those apprentices at the rates stated in the certified
agreement from 26 May 2003 until the termination of the contract between the
plaintiff and the defendant in November 2003. When the plaintiff discovered in
November 2003 that the certified agreement had been made some six months earlier
it made additional payments to those of its apprentices who had worked at the
defendant’s workplace in that period to make up the difference between the award
rates the plaintiff had paid them and the higher rates payable under the certified
agreement.
[11] The Magistrate decided that the plaintiff was entitled to recover those additional
costs to it pursuant to the change clause. That decision was set aside in the District
Court. The critical reasoning was contained in the following paragraph of the
primary judge’s reasons:
"As at 17 August 1991 payment of the apprentices the subject of the
agreement was regulated by the State Award. No EBA [meaning
"enterprise bargaining agreement", ie the Certified Agreement] was
then in existence and there was no evidence to indicate that the term
"award" was envisaged by the parties to encompass anything other
than award rates. In particular there was nothing to indicate that any
instrument, such as a Certified Agreement, was in any way within
the contemplation of the parties. Clearly, in my view, the terms
"EBA" and "award" cannot be regarded as being interchangeable.
The basis of the hiring agreement in this case was that the appellant
should be obliged to pay a share of the expenses associated with the
particular apprentices determined according to the length of the
period of hiring. In my view, on a proper construction of the
agreement those charges are to be calculated in accordance with the
relevant award and not in accordance with the subsequently
introduced Certified Agreement. In my view, those matters which
can properly be the subject of charge are those matters expressly
provided for in the written agreement."3
[12] The plaintiff seeks leave to appeal to argue that the primary judge erred in that
construction of the parties' contract.
[13] The construction of the contract is to be determined by what a reasonable person in
the parties’ position would have understood it to mean having regard to its text, the
surrounding circumstances known to them, and the purpose and object of the
transaction it embodies.4
3 Arnold Electrical & Data Installations P/L v Logan Area Group Apprenticeship/Traineeship Scheme
Limited [2007] QDC at [6].
4 Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451 at [22]; [2004] HCA 35;
Toll(FGCT) P/L v Alphapharm P/L (2004) 219 CLR 165 at [40]; [2004] HCA 52.
-- 5 of 11 --
6
[14] Although the text is ambiguous, on a literal construction it is not "the award" which
is required to be changed before the clause operates but the "award rate"; and the
change clause does not require that the award rate be changed or backdated by
another award. Literally construed, the change clause applies whenever the rate
specified in the award is increased by any mechanism (only increases were
contemplated, at least in the express terms).
[15] The contrary view is open, but the apparent aim of the change clause also suggests
that it should not be construed so narrowly as to exclude reference to increases in
labour costs effected by any mechanism having the force of law. In a labour supply
agreement under which the supplier recovers from its customer essentially only the
supplier's labour costs it is to be expected that the parties will provide for increases
to the rate of recovery commensurate with statutorily mandated increases in those
costs. Otherwise the supplier will be out of pocket and the “hirer” will receive an
unmerited windfall.
[16] The surrounding circumstances point in the same direction. The relevant
background information that may be used to inform the proper construction of a
contract includes not only that which the parties subjectively knew but also that
which was reasonably available to the parties in the situation in which they found
themselves at the time of the contract, including matters of law.5 The legislation
current when the contract was made, the Industrial Relations Act 1990 (Qld), gave
the force of law not only to "awards" but also to "industrial agreements".6 The
prospect of future amendments to the industrial relations legislation must also have
been within the contemplation of a reasonable person in the parties’ position. The
parties must be taken to have appreciated when the contract was made that awards
were not the only means by which the effect of law might be given to future
increases in labour costs. In this case there was no evidence contradicting that
expectation.
[17] I accept both that the construction I prefer creates some tension with the contractual
references to the “award” and that the construction propounded by the defendant (in
effect, that the change clause covers only labour cost increases reflected in a new or
amended award) is certainly open on the text. Nevertheless, I would reject the
defendant’s construction for the reasons I have given: it reads the contract in a
"narrow spirit of construction" of a kind long condemned by the courts.7 Numerous
authorities establish that the construction which is adopted must accord with
commercial efficacy and commonsense.8 The manifest unreasonableness of the
defendant’s approach to which I have referred is emphasised by the fact that the
5 Maggbury P/L v Hafele Australia P/L (2001) 210 CLR 181 at [11] per Gleeson CJ, Gummow and
Hayne JJ; [2001] HCA 70.
6 Industrial Relations Act 1990 (Qld), Pt 10, Div 1 (Awards), Div II (Industrial Agreements).
7 Cohen & Co v Ockerby & Co (1917) 24 CLR 288 at 300 per Isaacs J; [1917] HCA 58; see also, for
example, Upper Hunter County District v Australian Chilling & Freezing Co Ltd
(1968) 118 CLR 429 at 437; [1968] HCA 8.
8 See, for example, Gollin & Co Ltd v Karenlee Nominees P/L (1983) 153 CLR 455 at 463;
[1983] HCA 38; McCann v Switzerland Insurance Australia Ltd (2000) 203 CLR 579 at [22];
[2000] HCA 65.
-- 6 of 11 --
7
increases in the plaintiff’s labour costs flowed from an agreement to which the
defendant was, but the plaintiff was not a party.
[18] In fairness to the primary judge it must be pointed out that in the District Court, the
appellant’s argument was the different one that the term “award” was broad enough
to encompass a certified agreement. It was that argument which the primary judge
was concerned to reject in the passage quoted earlier. The argument which I regard
as much more substantial is that, on a literal and purposive construction, the change
clause is not confined to changes to the award itself or changes made by a new
award: it comprehends also increases in the plaintiff’s labour costs brought about by
other means that similarly have the force of law, including by certified agreements.
[19] The point concerns only the proper construction of a written contract and it was not
submitted that this new argument might have been met by additional evidence. It
follows that if leave to appeal were granted it might fairly be contended that it
would be “not only competent but expedient, in the interests of justice”9 to entertain
the new argument.
[20] But it does not follow that the fact that the argument relied upon in this Court is new
is irrelevant. The plaintiff’s failure to put this argument either to the Magistrate or
in the District Court is a factor opposed to the grant of leave.10 I would add that the
parties’ failure to adduce evidence at trial concerning the surrounding circumstances
which I have mentioned lessens the significance of any decision in this litigation as
a precedent concerning the proper construction of this contract.
[21] That the amount in issue is relatively small and the matter has already been litigated
in two courts also weigh against leave being granted. Furthermore, the construction
point was not the only reason given by the primary judge for setting aside the
plaintiff's judgment. His Honour also found that the Magistrates Court erred in
finding that the plaintiff was entitled to be paid an “administrative cost” (that
amount being included in the invoices with reference to which the plaintiff’s claim
was calculated):11
"There is one further matter to consider, that being the finding by the
Magistrate that the respondent was entitled to be paid an
administrative cost. This finding seems to have been based upon a
concession made by the witness Arnold during cross-examination.
In my view that concession represents no more than a statement of
opinion by the witness. As the High Court observed in Toll (FGCT)
Pry Limited v Alphapharm Pry Limited and Ors (2004) 219 CLR 165
at 179 "(it) is not the subjective beliefs or understandings of the
9 Connecticut Fire Insurance Co v Kavanagh [1892] AC 473 at 480, quoted with approval in
Suttor v Gundowda P/L (1950) 81 CLR 418 by Latham CJ, Williams and Fullagar JJ at 438;
[1950] HCA 35; and, in a different context, in Crampton v R (2000) 206 CLR 161 by Gleeson CJ at
[12] and by Gaudron, Gummow and Callinan JJ at [50]; [2000] HCA 60.
10 Cf Monte Carlo Caravan Park P/L v Curyer [2007] 2 Qd R 57 at [21] per Keane JA (Jerrard and
Holmes JJA agreeing); [2006] QCA 363.
11 Arnold Electrical & Data Installations P/L v Logan Area Group Apprenticeship/Traineeship
Scheme Limited [2007] QDC at [9].
-- 7 of 11 --
8
parties about their rights or liabilities that govern their contractual
relations". The written agreement here makes express provision for
those items which may be subject of permissible charge but these do
not include any allowance for administration costs. The finding of
the Magistrate in this regard cannot in my view be sustained."
[22] That the plaintiff included in its invoices an "administrative" charge of 25 cents per
hour emerged in cross-examination of the plaintiff’s operational manager,
Mr Taylor. The plaintiff's admission of the defendant's pleaded allegation that the
contract entitled the plaintiff to charge for the items expressly described in the
contract, coupled with the plaintiff’s failures to plead facts supporting its argument
that it was also entitled to charge for "administration" and to give particulars of that
charge, render it doubtful that the plaintiff was entitled to sustain this charge on the
pleadings upon which it went to trial.12 It is not clear that it was even open to the
plaintiff to argue, as it successfully did before the Magistrate, that the contract did
not comprehensively identify the permissible charges so that it was entitled to
charge the administration fee.
[23] On that construction question, the apparent status of the plaintiff as a non-profit
company acting within a governmental scheme is a fact that might well prove to be
relevant to the proper construction of the contract. The Court was told of that fact
in general terms during argument but no evidence was led about it at trial. If leave
to appeal were granted for the purpose of deciding that question, this Court’s
decision would therefore not necessarily govern any future cases on the same form
of contract.
[24] If, as the primary judge concluded, the charge was unsustainable, the amount of the
plaintiff’s claim (if otherwise successful) theoretically might be sustained in a
reduced amount, but the overall financial impact of the charge appears not to have
been quantified either by the pleadings or by the evidence. Whether that exercise
could now be done with reference to the evidence led at trial was not made clear;
whether it would be appropriate to proceed in that way despite the deficiencies in
the pleadings is doubtful. What is clear is that deduction of the charge would
further reduce the already small amount in issue in the proposed appeal.
[25] It also emerged in argument that the plaintiff's claim under the change clause was
premised on the view that the apprentices were doing "construction" work in terms
of Schedule B of the certified agreement and not "services" in terms of Schedule C
of that agreement. (Much the same issue arose on the counterclaim in the context of
an apparently similar division in the former award: I return to this below.) The rate
for "other construction work" was higher than it was for "service work". The
evidence on behalf of the plaintiff was that it used the charge out rate for "other
construction work" because the majority of its apprentices were doing construction
work.
12 Cf Uniform Civil Procedure Rules 1999 (Qld), rr 149(1)(b), 149(1)(c), 149(3)(a), 157(a).
-- 8 of 11 --
9
[26] It may well be that the plaintiff was correct in charging in that way but the evidence
before the Magistrate on the point was quite unclear. This issue was not raised by
the pleadings. The plaintiff did not plead any material facts in support of its claim
(exposed during cross-examination) to recover this cost.
[27] There are therefore a number of factors opposed to the grant of leave, but the
plaintiff contends that the decision of the District Court, particularly that aspect of it
concerning the construction of the change clause, sets an important precedent
because this contract was in its standard form. Its counsel stated from the bar table
(without objection) that there might still be a very large number of such contracts
still in force. That is open to serious doubt, as the plaintiff’s counsel properly
recognised, because no other claim has been made against the plaintiff even though
it wrote a form letter to all of its “customers” in late 2003 seeking to impose a new
form of contract. Furthermore, for the reasons I have given the District Court
decision should not be regarded as having the effect as a precedent which the
plaintiff feared.
[28] For these reasons, although in my respectful opinion the primary judge’s
construction of the change clause in the contract was wrong (for reasons not agitated
in argument before his Honour), I am not persuaded either that there is a substantial
argument that the actual decision to set aside the judgment in the plaintiff’s favour
was incorrect or that an appeal is necessary to correct any substantial injustice. I
would therefore refuse the plaintiff's application for leave to appeal.
Defendant's application
[29] The defendant's counterclaim was premised on its contention that the plaintiff had
calculated its invoices with reference to the "construction” rate in the former award
when the plaintiff should have only charged the lesser "service rate" under that
award. The Magistrate dismissed the counterclaim because he was not persuaded
that the evidence showed that the apprentices should have been paid at the lesser
rate and because of his Honour’s conclusion that for the period after commencement
of the certified agreement the award did not apply.
[30] The primary judge refused the defendant's appeal against the dismissal of its
counterclaim. His Honour concluded:
"Although there was some generalised evidence before the court as
to the type of work done by the appellant company, there was no
detailed evidence as to precisely what sort of work was carried out
by the apprentices or as to what proportion of their work could
properly be described as construction as opposed to service work.
The state of the evidence was such in my view that the Magistrate's
finding that he was unable to determine which of the service or
construction rates should have been charged was one which was
reasonably open to him." 13
13 Arnold Electrical & Data Installations P/L v Logan Area Group Apprenticeship/Traineeship Scheme
Limited [2007] QDC at [8].
-- 9 of 11 --
10
[31] In my respectful opinion his Honour’s decision was correct for those reasons.
[32] On behalf of the defendant it was submitted that the necessary evidence was
supplied by Mr Arnold, who swore that it was the service rate that "applied" to the
work that his company was doing. It was submitted that he had an extensive
knowledge of and expertise in the industry. So much may be accepted but the
difficulty remains that only the vaguest description of the work done by the
apprentices was given. It was described as "generally commercial, electrical and
data installations". Even the award itself was not in evidence.
[33] It is far from being clear that there was any question upon which expert evidence of
the character relied upon by the defendant was admissible. But if this was a proper
subject for expert evidence Mr Arnold’s evidence was of no value because the facts
upon which it was premised were not identified. No matter what qualifications are
possessed by an expert witness, opinion evidence lacks probative value if the facts
upon which it is based are not both identified and proved or admitted.14
[34] Contrary to another submission made on behalf of the defendant, the admission at
trial without objection of the defendant’s four volumes of analyses of the plaintiff’s
invoices prepared on the premise reflected by Mr Arnold’s evidence did not provide
the missing evidence of the underlying facts. It was not submitted that these
volumes of material contained any information about the precise nature of the work
done by the apprentices or as to the precise terms of the award. The submission is
also not easy to reconcile with the conduct of the defendant’s counsel in making it
plain when he tendered those documents that it was proposed to prove them by
Mr Arnold’s evidence. As I have already indicated, it transpired that Mr Arnold’s
evidence did not prove the facts necessary to support the counterclaim. In those
circumstances, the documentary evidence is not to be treated as having probative
effect it otherwise lacked merely because of the absence of objection to its tender.15
[35] The defendant’s counsel sought to overcome this difficulty by arguing that the
defendant was entitled to rely upon a deemed admission under UCPR r 166 that the
service rate was the correct rate. It was contended that the plaintiff’s pleaded
explanation for its denial of the defendant’s allegation that it overpaid the plaintiff
(that it was not true) was insufficient.16 These submissions must be rejected. The
rule is concerned with allegations of facts in pleadings. The allegation of an
overpayment asserted a conclusion based on various matters that were not pleaded.
The defendant’s counterclaim did not allege any of the facts (as to the nature of the
work done by the apprentices and the terms of the award) required to support the
conclusion (which was also not pleaded) that the service rate was applicable.
Rule 166 cannot be called in aid of a claimant who fails to plead or prove the
material facts required to support the claim.
14 R v Ping [2006] 2 Qd R 69 at [43]-[46]; [2005] QCA 472.
15 Cf Hughes v National Trustees, Executors and Agency Co of Australasia Ltd (1979) 143 CLR 134 at
153; [1979] HCA 2.
16 Cf Groves v Australian Liquor, Hospitality and Miscellaneous Workers’ Union [2004] QSC 142 at
[15]
-- 10 of 11 --
11
[36] There is another reason why this pleading point is an inappropriate basis for the
grant of leave to appeal. The defendant’s counsel did not take the point when he
tendered the documentary evidence and undertook to prove it through the witness at
the trial. That conduct was wholly inconsistent with his proposition, not made until
final submissions at the trial, that the fact of the overpayment was not in issue.
[37] Further, in light of my conclusion that the proper construction of the contract
permitted the plaintiff to charge at the rates expressed in the certified agreement, the
defendant's counterclaim also suffers from the fatal deficiency that it was calculated
with respect to the different award rates.
[38] In my opinion the defendant has failed to advance any reasonable argument that the
primary judge erred in dismissing the defendant's appeal from the decision of the
Magistrate. I would therefore refuse the defendant’s application for leave to appeal.
[39] I would order that the applications for leave to appeal by both parties be dismissed,
in each case with costs to be assessed on the standard basis.
[40] LYONS J: I have had the advantage of reading the reasons of Fraser JA. I agree
with his Honour’s reasons and with the orders proposed.
-- 11 of 11 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2008/100