Bossichix Pty Ltd v Martinek Holdings Pty Ltd [2008] QSC 278
SUPREME COURT OF QUEENSLAND
CITATION: Bossichix Pty Ltd v Martinek Holdings Pty Ltd
[2008] QSC 278
PARTIES: BOSSICHIX PTY LTD ACN 096 494 683
(applicant)
v
MARTINEK HOLDINGS PTY LTD ACN 106 533 242
(respondent)
FILE NO/S: SC No 9872 of 2008
DIVISION: Trial Division
PROCEEDING: Originating Application
DELIVERED ON: 12 November 2008
DELIVERED AT: Brisbane
HEARING DATE: 13 October 2008
JUDGE: Mackenzie J
ORDERS: 1. It is declared that the applicant has validly
cancelled, pursuant to s 212 of the Body
Corporate and Community Management Act
1997 (Qld), the contract between the applicant
and the respondent headed “Rivage Sales
Contract” entered into on or about 22 July,
2005;
2. It is declared that the respondent must repay to
the applicant, pursuant to s 218 of the Body
Corporate and Community Management Act
1997 (Qld), the sum of $99,500 paid to the
respondent’s agent towards the purchase of the
proposed lot the subject of the Contract;
3. The respondent pay the applicant’s costs of and
incidental to the originating application to be
assessed.
CATCHWORDS: STATUTES – ACTS OF PARLIAMENT –
INTERPRETATION – where s 212 of the Body Corporate
and Community Management Act 1997 (Qld) provides that a
contract for the sale of a lot intended to come into existence
as a lot in a community titles scheme must provide that
settlement must not take place earlier than 14 days after the
seller advises the buyer that the scheme has been established
– where the contract provided that the settlement date was 14
days after notification of registration of the Building Format
Plan – where the contract did not contain a statement in the
terms specified in s 212 – whether the contract complied with
-- 1 of 7 --
2
s 212 – whether strict or substantial compliance with s 212 is
required – whether the buyer was entitled to cancel the
contract under s 212(3)
Building Act 1975 (Qld)
Body Corporate and Community Management Act 1997
(Qld), s 2, s 4(f), s 24, s 212
Land Titles Act 1994 (Qld), s 9A, s 115L
Boheto Pty Ltd v Sunbird Plaza Pty Ltd [1984] 2 Qd R 9,
cited
Deming No 456 Pty Ltd v Brisbane Unit Development
Corporation Pty Ltd (1983) 155 CLR 129; [1983] HCA 44,
considered
Hall v Jones (1942) 42 SR (NSW) 203, cited
MNM Developments Pty Ltd v Gerrard [2005] 2 Qd R 515,
cited
Petranker v Brown [1984] 2 NSWLR 177, cited
COUNSEL: S R Lumb for the applicant
R C Schulte for the respondent
SOLICITORS: McKays Solicitors for the applicant
Griffin Solicitors for the respondent
[1] MACKENZIE J: This application is concerned with whether clause 14.1 of a
contract for the sale of a building unit in a building called “Rivage” between the
applicant purchaser and the respondent developer complies with s 212 of the
Body Corporate and Community Management Act 1997 (Qld) (“BCCM”).
According to it, settlement of the contract was subject to the registration of both the
Building Format Plan by which the relevant lot would be created and the Certificate
of Classification for the building, within three years of the date of the contract.
[2] The contractual clause under consideration is as follows:
“The settlement date is the later of-
(a) 14 days after the Seller notifies the Buyer that the Building Format
Plan is registered; and
(b) Three days after the Seller notifies the Buyer that a Certificate of
Classification is issued for the building.”
[3] The term “Building Format Plan” is defined by clause 2.1 of the contract as
meaning the Building Format Plan that is registered to create the lot. “Community
Management Statement” is defined as meaning the Community Management
Statement to be registered with the building format plan. The draft Community
Management Statement, according to the definition, formed part of the Disclosure
Statement. The term “lot” was defined as meaning a lot within the Scheme.
“Scheme” was defined as meaning the community title scheme that would be
created on registration of the building format plan.
-- 2 of 7 --
3
[4] “Certificate of Classification” is defined in clause 2.1 as the Certificate of
Classification issued by the Authority (i.e. a body or person authorised by law to
give an approval or certificate the seller must obtain to perform its obligations under
the contract) that permits lawful occupation of the building for residential and/or
other lawful purposes as contained in the Development Approval for Rivage.
Although it is referred to in clause 14.1, this has no impact on the issues argued.
[5] It is convenient to mention that there are proceedings (SC No 113/08) in the
Mackay Registry of this court, commenced by the respondent against the applicant
and Bonnie Dean claiming damages and declarations which, it is common ground,
this application will resolve in some respects. Ms Dean is a director of the applicant
and a guarantor of its obligations under the contract. She has agreed to be bound by
the determination of these proceedings insofar as they are relevant to the Mackay
proceedings.
[6] By way of further background, the full deposit was eventually paid, but on
13 November 2007 the solicitors for the applicant wrote a letter to the respondent
containing the following:
“We note that the contract provides for settlement 14 days after
registration of the plan but does not state ‘settlement must not take
place earlier than 14 days after the seller gives advice to the buyer
that the scheme has been established or changed’ in accordance with
s 212(1) of the Body Corporate and Community Management Act
1997.
We further note that s 212(3) states that where there has been a
breach of s 212(1) the buyer may cancel the contract.
Our client elects to cancel the contract pursuant to s 212 and requests
that your client authorise the agent to release the deposit to our
client.”
[7] On 23 November 2007 the respondent rejected the contention that the contract
failed to comply with s 212 and elected to affirm the contract. On 31 March 2008
the respondent’s solicitors wrote to the solicitors for the applicant enclosing copies
of the Certificate of Classification and a registration confirmation statement
confirming that the building format plan had registered, and fixed the settlement
date as 14 April 2008. The applicant did not complete the contract on that date.
The respondent’s solicitors wrote to confirm that fact and terminated the contract on
that basis.
[8] It is said that there are three issues requiring analysis. The first is what s 212(1)
BCCM requires. The second is whether the contract contravened that requirement.
The third was whether the respondent was entitled to cancel the contract in reliance
on s 212 (3) of the Act.
[9] Section 212 provides as follows:
212 Cancellation for not complying with basic requirements
(1) A contract entered into by a person (the seller) with another
person (the buyer) for the sale to the buyer of a lot intended to come
into existence as a lot included in a community titles scheme when
-- 3 of 7 --
4
the scheme is established or changed must provide that settlement
must not take place earlier than 14 days after the seller gives advice
to the buyer that the scheme has been established or changed.
(2) Also, when the contract is entered into, there must be a proposed
community management statement for the scheme as established or
changed.
(3) The buyer may cancel the contract if—
(a) there has been a contravention of subsection (1) or (2); and
(b) the contract has not already been settled.
[10] Clause 14.1 fixes one of the possible triggering events of the obligation to settle the
contract as notification by the seller to the buyer that the Building Format Plan has
registered. The meaning of “Building Format Plan” for the purposes of the contract
is set out in paragraph [3] above. There is evidence in exhibit JM5 to Mr Martinek’s
affidavit that notification of the registration of the Building Format Plan and the
issue of the certificate of classification under the Building Act 1975 (Qld) was sent
to the applicant’s solicitors at 4:55pm on 31 March 2008. A copy of the registration
confirmation statement extracted from the records of the Registrar of Titles earlier
that afternoon was also sent at the same time. It contains a reference to the
Community Management Statement relating to the lot.
[11] Section 24 BCCM provides that the community titles scheme is established by:
(a) Registration under the Land Titles Act 1994 (“LTA”) of the plan of
survey for identifying the scheme land; and
(b) Recording by the Registrar of the first community management
statement for the scheme.
[12] By s 115L LTA, a community management statement takes effect when recorded by
the Registrar as a community management statement for the scheme (s 115L(3)). It
is part of the recording process that the Registrar records a community management
statement by recording a reference to it on the indefeasible title for each lot in the
scheme and for the common property (s 115L(1)(b)). Complementary to that, s 59
BCCM says that a Community Management Statement takes effect under s 115L(3)
LTA. For the purposes of LTA a “Building Format Plan” is one species of survey
plans. As the name implies, it defines land by reference to structural elements of a
building.
[13] Section 9A LTA authorises the Registrar of Titles to keep a Manual of Land Title
Practice. Amongst other things, it may include practices developed in the Land
Registry before or after the commencement of s 9A for the depositing and lodging
of instruments. Extracts from the Land Title Practice Manual (Queensland) were
made available to me. Of most relevance for present purposes is a paragraph
headed “Recording a First CMS Lodged with the Plan establishing a Community
Titles Scheme”. Since a Community Management Statement is not an instrument in
its own right, it enters the registration system by means of a Form 14 – General
Request. The Community Management Statement “must be lodged with every plan
of subdivision that establishes a community titles scheme.” It is said that the
request and the plan are registered on the existing indefeasible title and the
Community Management Statement is brought forward to the indefeasible title
created for the scheme common property. The titles created for the lots in the
-- 4 of 7 --
5
scheme are noted with a reference to the Community Management Statement
(which includes a unique identifying number). No separate notation as to a first or
subsequent Community Management Statement is made on the indefeasible titles
for the lots in the scheme.
[14] The applicant’s case is that there was a failure in two respects to comply with the
requirements of s 212. The first was that the contract did not expressly state that
“settlement must not take place earlier than” 14 days after the vendor gave notice to
the purchaser that, relevantly, the scheme had been established. The unambiguous
grammatical meaning of s 212 was that the contract had to expressly so provide.
Merely providing that settlement date was 14 days after the giving of advice that the
scheme has been established was not sufficient compliance.
[15] The second was that fixing a possible settlement date as 14 days after the date the
vendor notified the purchaser that the Building Format Plan had been registered did
not comply with s 212. The establishment of the Community Title Scheme required
more than registration of the Building Format Plan. What was required by s 212
was that the plan of subdivision be registered under LTA and also that the first
Community Management Statement be recorded by the Registrar of Titles. By
setting the date for settlement in the terms used, clause 14.1 of the contract made no
reference to the establishment of the Community Title Scheme or to the recording
of the Community Management Statement.
[16] The strict approach to provisions with evident consumer protection functions was
emphasised by the applicant. The consequence that the protection may extend to
giving the purchaser a right to terminate even for quite technical reasons and
whether or not the purchaser has suffered any material disadvantage, was, it was
said, well established. The applicant relied on a recent example of this approach in
MNM Developments Pty Ltd v Gerrard [2005] 2 Qd R 515 in which the Property
Agents and Motor Dealers Act 2000 (Qld) was the relevant legislation (and the
provision under consideration more directly prescriptive). This is not a novel
proposition.
[17] As evidence that history tends to repeat itself, Deming No 456 Pty Ltd v Brisbane
Unit Development Corporation Pty Ltd (1983) 155 CLR 129 is an earlier example
of the proposition that where there is a provision requiring a document or warning
to be given in the interests of consumer protection, there is a tendency to adopt a
“lowest common denominator” approach. The relevant provision in s 49 of the
Building Units and Group Titles Act 1980 had not been complied with in the way
required by the Act but had substantially been complied with elsewhere in the
contractual documents. Failure to give the statement required triggered a right to
terminate the contract within thirty days after the purchaser became aware of the
failure if his rights had been materially affected thereby. The fact of non-compliance
with the precise requirements of the Act was held to be critical by the majority in
the High Court. The substantial issue upon which the case turned was when the
reluctant purchaser had knowledge of the failure to comply with the requirements.
[18] In a later case, Boheto Pty Ltd v Sunbird Plaza Pty Ltd [1984] 2 Qd R 9 at 13, the
“surprising construction” by the High Court of the concept of when knowledge of
the non-compliance was gained was commented on by Lord Templeman, delivering
the opinion of the Privy Council. But the underlying approach to the effect and
consequences of a provision requiring a consumer to be given notice of a matter
-- 5 of 7 --
6
pertaining to the consumer’s rights remains operative. There is a premise that, at
least in a case where the requirement is not patently and directly complied with
elsewhere, it is not sufficient compliance with a statutory requirement of the kind in
s 212 BCCM even if a consumer might, by a process of interpretation of the
contract as a whole, and perhaps with knowledge the Registrar of Titles’ practice, be
able to discern what rights he, she or it had.
[19] That is the kind of argument which the respondent seeks to rebut. The argument
was prefaced by the observation that form had to prevail over substance for the
applicant to succeed. It is said that, construing clause 14.1 in light of the definitions
in clause 2.1, there was substantial compliance with the requirements of s 212(1).
Reading the contract as a whole, the creation of the “scheme” and the registration of
the Building Format Plan were inextricably linked. By notifying the buyer of the
registration of the Building Format Plan, the seller was notifying the buyer that the
scheme had been created. The philosophy in s 14A(1) of the Acts Interpretation Act
1954 (Qld) that the Act should be given an interpretation that best achieves its
purpose was also prayed in aid. Attention was drawn to s 2 BCCM which says that
the primary object of the Act is to provide for flexible and contemporary
communally based arrangements for the use of freehold land having regard to the
secondary objects.
[20] A secondary object in s 4(f) BCCM of providing an appropriate level of consumer
protection for owners and intending buyers of lots included in Community Title
Schemes was relied on. Its relevance was said to lie in the concept that the
“consumer protection” referred to reflected a balance between the rights of owners
and intending buyers. It is not immediately obvious that the object is directed at
some sort of relativity between sellers and intending buyers inter se, but in any
event it is more an aspirational statement than a statement governing or shedding
light on the issues to be decided. Reference was also made to s 4(c) BCCM which
seems to have marginal relevance.
[21] The respondent also relied on the inclusion of the term “basic limitation” in the
heading to Division 1 Part 2 BCCM of which s 212 is the first section for the
purpose of arguing that it was a mandatory minimum requirement that the contact
“provide that” settlement not take place until 14 days after the seller advised that the
scheme had been established. It was submitted that the contract did this, by
referring to the registration of the Building Format Plan. Some stress was placed on
the requirement that the contract “provide” that information. This was contrasted
with what were, implicitly, more prescriptive formulations, not used, to convey
what the requirement was, such as “a contract … must state” or “a contract … must
express …”.
[22] It may be interpolated that although clause 14.1 refers to the Building Format Plan
(defined in clause 2), there is no reference in clause 14.1 to the Community
Management Statement, the recording of which is one of the essential elements of
establishing a scheme. The definition refers to it being “registered” with the
Building Format Plan, but it was not suggested that there was any statement
elsewhere in the contract referring to its recording as one element of establishing the
scheme. In that sense, clause 14.1 omits to mention it. Clause 14.1 fixes the date of
settlement by reference to three events, the registration of the Building Format Plan,
the issue of the Certificate of Classification and the elapsing of a relevant time
calculated by reference to clause 14.1. The event that would trigger the obligation
-- 6 of 7 --
7
to settle does not equate to advice that, in all respects, the scheme has been
established. Without determining at what point it is relevantly “recorded”, it must
be acknowledged that because of Registrar of Titles’ practice, the Community
Management Statement will have been recorded, at worst, virtually
contemporaneously with registration of the plan of subdivision (which fits the
description of Building Format Plan as defined in clause 2). However, there is no
guarantee that that would be known to an average buyer and if it is accepted that the
requirement in s 212 is essentially a consumer protection provision, it has not been
complied with. It is not the fact that contemporaneous recording may occur that is
decisive. It is the fact that clause 14(1) does not adequately convey to the buyer that
more than registration of the Building Format Plan is necessary to establish the
Community Title Scheme and trigger the fixing of a time for settlement.
[23] With regard to an argument that the provision in s 212 is intended to achieve a
balance between the seller and the buyer of a unit, principally because the obligation
under s 212 is not placed on any particular person, the practical reality is that,
because all the detriment that might flow from non-compliance lies with the seller,
it would be imprudent for a seller to fail to ensure that the contract complies with
any prescriptive requirements. If they are not complied with, it is difficult to see
that the objective of s 212, of ensuring that a buyer is made aware of being protected
against being forced to settle a unit sale before the scheme is fully established or at
short notice once it is, is promoted by the kind of construction proposed by the
respondent.
[24] It is unnecessary to express any view on the question posed by the respondent as to
what might or might not invalidate a contract which is subject to s 212 BCCM in the
variant circumstances posed in argument. Nor is it necessary to express a conclusion
on the applicant’s argument summarised in paragraph [14] above. Each case will
depend on its own facts. Nor is it necessary to say more about the issue of some sort
of comity between the courts and Parliament raised in paragraph [39] of the
respondent’s written submissions, except to say that there may be different
approaches to it (see eg. Hall v Jones (1942) 42 SR (NSW) 203 at 208 (Jordan CJ);
Petranker v Brown [1984] 2 NSWLR 177 at 179 (Samuels JA)).
[25] It follows from what has been said that the applicant is entitled to the relief sought.
The formal orders are as follows:
1. It is declared that the applicant has validly cancelled, pursuant to s 212 of the
Body Corporate and Community Management Act 1997 (Qld), the contract
between the applicant and the respondent headed “Rivage Sales Contract”
entered into on or about 22 July, 2005;
2. It is declared that the respondent must repay to the applicant, pursuant to s 218
of the Body Corporate and Community Management Act 1997, the sum of
$99,500 paid to the respondent’s agent towards the purchase of the proposed lot
the subject of the contract;
3. The respondent pay the applicant’s costs of and incidental to the originating
application to be assessed.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2008/278