Exceptional Sunrise P/L v Jones & Anor [2008] QSC 190
SUPREME COURT OF QUEENSLAND
CITATION: Exceptional Sunrise P/L v Jones & Anor [2008] QSC 190
PARTIES: EXCEPTIONAL SUNRISE PTY LTD ACN 093 828 785
(plaintiff)
v
DAVID FRANCIS JONES and BETTY NEVA JONES
(defendants)
FILE NO/S: BS No 9155 of 2007
DIVISION: Trial Division
PROCEEDING: Trial
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 26 August 2008
DELIVERED AT: Brisbane
HEARING DATE: 21 August 2008
JUDGE: de Jersey CJ
ORDERS: 1. Dismiss the originating application filed 12 October
2007;
2. Declare that the defendants lawfully terminated their
contract with the plaintiff dated 17 May 2004 at or about
8:32 am on 3 September 2007;
3. Order that caveat number 710974374 in respect of lot 1
on registered plan 94961, County of Stanley, Parish of
Burpengary, title reference 16514032, be removed;
4. Order that the plaintiff pay the defendants’ costs of and
incidental to the proceeding as follows;
a) up to an including 12 March 2008, to be assessed on
the standard basis, and
b) after 12 March 2008, to be assessed on the
indemnity basis
Grant liberty to apply for variation of that costs order
within seven days, should the plaintiff be so advised
5. Order that the operation of this judgment be stayed
until 4pm on 2 September 2008 or until further earlier
order
CATCHWORDS: CONTRACT FOR SALE OF LAND – conditional on
development approval – right of termination by purchaser on
non-fulfilment, to be exercised by a particular time – not
exercised – further right in vendor to terminate in that
circumstance – purchaser purported to waive the condition,
but after the cut off date – whether that denied vendor the
-- 1 of 9 --
2
right of termination subsequently exercised
Donaldson v Bexton [2007] 1 Qd R 525; [2006] QCA 559,
cited
Gange v Sullivan (1966) 116 CLR 418, considered
COUNSEL: T J Bradley for the plaintiff
M K Stunden for the defendants
SOLICITORS: Holding Redlich for the plaintiff
Phillips & Lowes Solicitors for the defendants
[1] de Jersey CJ: The plaintiff and the defendants entered into a contract in writing,
dated 17 May 2004, providing for the defendants’ sale to the plaintiff of land
comprising lot 1 in Delaney Road, Burpengary, for the sum of $900,000. The
contract is in the form of the fifth edition of the Real Estate Institute of Queensland
and Queensland Law Society “contract for houses and land”.
[2] Special condition 3 rendered the contract subject to the plaintiff’s obtaining a
development approval. That was not forthcoming. The defendants contend that
they validly terminated the contract. The plaintiff contends that it had previously
waived the benefit of the special condition, and that the contract remained on foot.
The plaintiff lodged a caveat over the land. It seeks a declaration that it has an
equitable interest in the land sufficient to support that caveat, and an order for the
specific performance of the contract. The defendants seek a declaration that they
lawfully terminated the contract, and an order for the removal of the caveat.
Contractual provisions
[3] In its original form, the contract included these special conditions, among others:
“3. This contract is subject to and conditional upon the Buyer/s
obtaining from the local Authority and/or any other relevant
authority within 4 months, after satisfying Special Condition
1.a Development Approval which is wholly satisfactory to
the Buyer/s. In the event that all such approvals are not
obtained or not accepted by the local Authority having
jurisdiction either orally from a representative/s of the local
Authority or in writing from the local Authority, within this
period and the Buyer/s has applied for a Development
Approval, the period to obtain such approval shall be
extended by two further months.
…
6. It is agreed between the parties that Special Condition 3. is
for the sole benefit of the Buyer/s and may be waived by the
Buyer/s at any time on or before the completion date of this
Contract of Sale.
…
9. The date for completion of this contract will be 30 days after the
date that the Buyer/s advises the Seller in writing that it has
Development Approval.”
-- 2 of 9 --
3
[4] The parties amended the contract on or about 17 November 2004, replacing those
special conditions numbered 3, 6 and 9 with a new special condition 3 as follows:
“3 Contract Conditional on Development Approval
3.1 This contract is conditional upon the Buyer obtaining
development approval upon terms wholly satisfactory to the
Buyer by 29 April 2005 (“the Approval Date”).
3.2 In the event that the Buyer does not obtain a satisfactory
development approval by the Approval Date the Buyer may
terminate the Contract and any deposit paid will be refunded
to the Buyer by the deposit holder. The notice pursuant to
this clause must be given by the Seller by 1:00pm on the
Approval Date.
3.3 If the Buyer has not provided notice pursuant to clause 3.2
the Seller will be entitled to terminate this Contract and any
deposit must be refunded to the Buyer by the deposit holder.
3.4 If the Buyer obtains satisfactory development approval the
Buyer must give notice to the Seller by 1:00pm on the
Approval Date.
3.5 If the Buyer provides notice pursuant to clause 3.4 the date
for settlement will be 30 days after the date upon which
notice is given to the Seller.
3.6 The Buyer is entitled to waive the benefit of special
condition 3. If the Buyer waives the benefit of special
condition 3 the date for settlement will be 30 days after the
date the Seller receives written notice of the waiver of
special condition 3.
3.7 This is an essential term of the Contract.
3.8 This clause is for the benefit of the Seller and Buyer.”
[5] The “approval date” under cl 3.1 was changed from time to time by agreement, and
then on 14 August 2007, the defendants offered a further extension on these terms:
1. The Approval date for the purposes of cl 3.1 be Friday 31
August 2007;
2. the time for the Buyer’s notice under cl 3.2 be by 1:00pm on
Friday 31 August 2007;
3. the time for the Buyer’s notice under cl 3.4 2 be by 1:00pm
on Friday 31 August 2007;
4. the date for settlement under cl 3.5 be 14 days after the date
upon which notice is given to the Seller;
-- 3 of 9 --
4
5. the date for settlement under cl 3.6 be 14 days after the date
the Seller receives the Buyer’s written notice of its waiver of
Special Condition 3;
6. in all respects time to remain of the essence;
7. clauses 3.7 and 3.8 to remain in place;
8. if the contract does not proceed to settlement all payments
made by the Buyer to the Seller including the deposit [to be]
non-refundable, and in that regard the references in Special
Condition 3 to any deposit being refunded to the Buyer by
the deposit holder [to] be amended as detailed in [the
plaintiff’s solicitor’s] correspondence of 25 January 2006.
[6] The plaintiff agreed to amend the contract accordingly, save that the period under
paras 4 and 5 above was to be set at 30 not 14 days. The defendants accepted that
modification on 15 August 2007.
Relevant subsequent events
[7] What then transpired may conveniently be taken from the plaintiff’s counsel’s
outline. There was no dispute about relevant matters of fact.
[8] On 28 August 2007 the plaintiff, by its then solicitor, sought a further extension of
the Approval Date. At about 12:32 pm on 31 August 2007 the defendants, by their
then solicitors, rejected that proposal.
[9] At 2:06 pm on 31 August 2007, the plaintiff’s solicitor sent an email to the
defendants’ solicitors saying:
“My client waives the benefit of Special Condition relating to
Development Approval. Settlement is now scheduled for 30 days
from today.”
[10] At about 8:32 am on 3 September 2007 the defendants’ solicitors sent a fax to the
plaintiff’s solicitor. It was erroneously dated 3 August 2007. It read:
“With reference to the above matter we note that advice was not
received from your client with respect to this contract within the
specified time.
Accordingly, this contract is now at an end.”
[11] At 11.14 am on 3 September 2007 the plaintiff’s solicitor forwarded his 31 August
email to the email address of Mr Gregory Lane, the principal of the defendants’
solicitors then responsible for the transaction. At 11.43 am the plaintiff’s solicitor
-- 4 of 9 --
5
then sent a fax to the defendants’ solicitors, apparently attaching a copy of the email
of 31 August 2007. The letter stated, in part:
“My client will be seeking relief against forfeiture by an order for
specific performance notwithstanding your client’s election to
terminate which my client disputes.”
[12] Later on 3 September 2007 the plaintiff’s solicitor sent another fax to the
defendants’ solicitors:
“Given that you have not withdrawn the purported termination, I will
[be] filing a caveat tomorrow morning.
I do find it extraordinary that if the deadline was 1:00 pm on 31
August 2007, why no advice was given to me on the afternoon of 31
August 2007 rather than on the morning of 3 September 2007.”
The same text was also sent by email at 5:01 pm that day.
[13] At about 10:21 am on 4 September 2007 the defendants’ solicitors sent a fax to the
plaintiff’s solicitor, saying:
“We again draw your attention to the amended Clause 3 of the
Special Conditions, detailed in our correspondence to you of the 14th
August 2007, and in particular the times stipulated in clauses 3.2 and
3.4 of the amended Clause 3.
The specific requirements of the time for the giving of notice were
again repeated at the foot of the second page of our correspondence
of 14 August 2007.
Clearly, your e-mail advice of the 31st instant was delivered after the
specific time agreed to between the parties and therefore is not in
compliance with the agreed terms of the contract (as amended), and
as such our client has terminated the contract.”
[14] On 6 September 2007 the plaintiff lodged a caveat over the title to the property
claiming:
“An equitable interest in the land as a purchaser under a Contract of
Sale dated 17th May 2004 in which the Caveator is the buyer and the
Caveatee is the seller.”
The caveat forbids the registration of any instrument affecting the property until the
caveat is withdrawn.
Issues
[15] The issues which arose, with respect to special condition 3, were these:
(a) whether the defendants’ attempt at termination on 3 September 2007
amounted to an effective termination, or whether it should be regarded as
-- 5 of 9 --
6
no more than an erroneous assertion that the contract had been terminated
automatically because the plaintiff did not give notice under cl 3.2;
(b) whether prior to the defendants’ attempt at termination the plaintiff had
effectively waived the benefit of special condition 3, by the 2:06 pm email
of 31 August 2007.
[16] Matter (b) raised two more particular questions:
(i) whether a waiver under cl 3.6 had to be communicated by 1 pm on
31 August 2007: the plaintiff’s “fallback” position was that a
waiver was to be implied from the plaintiff’s not having given the cl
3.2 notice; and
(ii) whether a waiver could in any event be communicated by means of
email, bearing in mind cl 10.4 of the “terms of contract”, which
provides:
“10.4 Notice
(1) Notices under this contract must be in writing and
may be given by a party’s solicitor;
(2) Notices are effectively given if:
(a) delivered or posted to the other party or its
solicitor; or
(b) sent to the facsimile number of the other
party or its solicitor.
(3) …
(4) Notices sent by facsimile will be treated as given
when the sender obtains a clear transmission report.
(5) …
(6) Notices or other written communications by a party’s
solicitor (for example, varying the Inspection Date,
Finance Date or Settlement Date) will be treated as given
with that party’s authority.”
Observations on special condition 3
[17] Whereas the contract originally gave the plaintiff the right to waive the requirement
for the development approval at any time up to the completion date, and provided
that the condition was for the sole benefit of the plaintiff, the new special condition
provided that the condition was for the benefit of both parties, and fixed 1 pm on 31
August 2007 as the cut off time by which the plaintiff might terminate the contract
for want of the development approval. The new condition also fixed that as the time
by which the obtaining of any approval “must” be notified to the defendants.
-- 6 of 9 --
7
[18] Accordingly, while cl 3.1 spoke of obtaining development approval by 31 August,
the subsequent clauses 3.2 and 3.4, refined that position by specifying 1 pm on that
date as the time by which the position in relation to development approval was to be
regarded as established one way or the other, so that the consequent rights in the
parties then crystallized and were known.
[19] When cl 3.8 contemplated benefit to the defendants, the parties presumably
envisaged the benefit to the defendants in knowing the potential fate of the contract
by 1 pm that day, and of course the potential benefit of the defendants being able to
terminate the contract under cl 3.3.
[20] To answer a submission advanced by Mr Bradley who appeared for the plaintiff, I
think it unlikely that the parties contemplated, as potentially significant, the period
from 1 pm on 31 August to the following midnight. To counter a contention that a
potential benefit might be waived only while it remained outstanding or current, Mr
Bradley submitted that because a development approval could theoretically have
been forthcoming between 1 pm and midnight on 31 August, the plaintiff could
effectually waive the benefit of a right to terminate (for want of development
approval) at any time after 1 pm but before midnight, so that the purported waiver at
2:06 pm was effectual. But as I have said, the parties apparently intended that the
issue of the development approval be resolved one way or the other by no later than
1 pm on 31 August. That is, I consider, the necessary conclusion to be drawn from
clauses 3.2 and 3.4 read in conjunction with 3.1. One must read special condition 3
as a whole, not in piecemeal fashion.
Analysis
[21] The benefit which the plaintiff purported to waive, by the 2:06 pm email, was the
right to terminate the contract under special condition 3.2 because development
approval had not been obtained. But to exercise that right to terminate, the plaintiff
was obliged to give notice of termination by 1 pm on 31 August. That was not
done. The right to terminate was consequently lost at that time, and by 2:06 pm,
there was nothing left to waive. The purported waiver by the 2:06 pm email was
therefore of no effect.
[22] Because, prior to 1 pm on 31 August, the plaintiff had not waived the benefit of
special condition 3 or given notice of termination under cl 3.2, the defendants
gained a right to terminate the contract under cl 3.3. They purported to exercise that
right by the fax sent at 8:32 am on 3 September 2007, which read:
“…we note that advice was not received from your client with
respect to this contract within the specified time. Accordingly, this
contract is now at an end.”
[23] That amounted to the defendants’ avoidance of the contract, by exercise of the right
to terminate under special condition 3.3 consequent upon the absence of notice from
the plaintiff under cl 3.2. Nothing had happened in the meantime to deprive the
defendants of that right to terminate.
-- 7 of 9 --
8
[24] As to the form of the fax, it was not necessary for the defendants to use the word
“terminate”. Stating that the contract was “now at an end”, having correctly
identified the anterior circumstances establishing the right to terminate, amounted to
a clear avoidance of the contract. At 10:21 am on 4 September the defendants’
solicitors by fax reaffirmed that termination.
[25] Donaldson v Bexton [2007] 1 Qd R 525, paras 1, 8, 36, 42, 47, 51, 52, 55, 63,
supports the conclusion that these defendants were not deprived of their right to
avoid the contract, a right which crystallized at 1 pm on 31 August, by the
plaintiff’s subsequent attempt at waiver, an attempt made prior to the defendants’
termination three days later. See also Gange v Sullivan (1966) 116 CLR 418, 443
per Windeyer J. I do not consider that the present position is distinguishable from
that which obtained in Donaldson v Bexton on the bases advanced by Mr Bradley.
The critical point is the one advanced by Mr Stunden, who appeared for the
defendants, that “although cl 3.6 did not express any time by which waiver had to
be made, it can be construed sensibly to be exercisable at the latest by the time fixed
for the fulfilment of cl 3.1 by reference to cl 3.2 and 3.4, namely 1 pm”. In other
words, you cannot “waive” a benefit after that benefit has ceased to exist. As said
by Jerrard JA in Donaldson v Bexton, supra, para 8, “after the date for completion of
the condition had passed, waiver became irrelevant. There was nothing to waive…”
[26] Mr Bradley submitted, however, that an implied waiver of the right to terminate was
to be drawn from the very circumstance that the plaintiff did not give notice under cl
3.2, that “waiver” therefore having occurred at 1 pm on 31 August.
[27] Accepting for argument that a waiver may ordinarily be implied from the conduct of
a party, that mere failure would not in this case warrant an inference of waiver. The
plaintiff may have been hedging its bets, hoping either that development approval
would be forthcoming, or that, with time possibly ceasing to be of the essence, the
plaintiff might derive a further subsequent opportunity for termination should no
approval ultimately eventuate.
[28] That said however, any waiver in this case needed to be communicated by notice, in
writing, in conformity with cl 10.4. That is because special condition 3.6 requires
“written notice of the waiver” to be given to the defendants. That had to be
accomplished by 1 pm on 31 August – and was not.
Conclusion
[29] I conclude that the defendants lawfully terminated the contract at or about 8.32 am
on 3 September 2007. It follows that the plaintiff’s claim for specific performance
must be dismissed, and the caveat removed.
[30] It has been unnecessary for me to deal with the submission that the communication
of the “waiver” by email was, because that medium was used, ineffectual. (The
submission did I feel gain strength from the requirement in special condition 3.6
that “written notice of the waiver” be given, and the absence, in cl 10.4, of any
reference to email communication.)
-- 8 of 9 --
9
Orders
[31] There will be orders as follows:
1. dismiss the originating application filed 12 October 2007;
2. declare that the defendants lawfully terminated their contract with the
plaintiff dated 17 May 2004 at or about 8.32 am on 3 September 2007;
3. order that caveat number 710974374 in respect of lot 1 on registered plan
94961, County of Stanley, Parish of Burpengary, title reference 16514032,
be removed;
4. order that the plaintiff pay the defendants’ costs of and incidental to the
proceeding as follows:
a) up to an including 12 March 2008, to be assessed on the standard basis;
and
b) after 12 March 2008, to be assessed on the indemnity basis.
Grant liberty to apply for variation of that costs order within 7 days, should
the plaintiff be so advised.
5. order that the operation of this judgment be stayed until 4pm on 2 September
2008, or until further earlier order.
-- 9 of 9 --