Cook’s Constructions P/L v Stork Food Systems Aust P/L [2008] QSC 186
SUPREME COURT OF QUEENSLAND
CITATION: Cook’s Constructions P/L v Stork Food Systems Aust P/L
[2008] QSC 186
PARTIES: COOK’S CONSTRUCTIONS PTY LTD
ACN 004 782 558
(plaintiff)
v
STORK FOOD SYSTEMS AUSTRALIA PTY LTD
ACN 007 298 633
(defendant)
FILE NO/S: S10993 of 2001
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 22 August 2008
DELIVERED AT: Brisbane
HEARING DATE: 4 February 2008
JUDGE: Martin J
ORDER: 1. Leave granted to Plaintiff amend its statement of
claim in the manner sought
2. Plaintiff pay the costs of the defendant thrown
away by the defendant to be assessed on an
indemnity basis
CATCHWORDS: PROCEDURE – SUPREME COURT PROCEDURE –
QUEENSLAND – PLEADING – AMENDMENT –
application to amend statement of claim once trial has
commenced – where there is no explanation for failure to
plead amendment earlier – where amendment changes the
plaintiff’s case on a central issue.
ESTOPPEL – FORMER ADJUDICATION AND
MATTERS OF RECORD OR QUASI RECORD –
FORMER ADJUDICATION – ISSUE ESTOPPEL –
GENERAL MATTERS – where there had been pre-trial
orders relating to pleadings – whether decision set out a
concluded view as to the proper construction of a sub-
contract.
Cook’s Constructions Pty Ltd v Stork Food Systems Australia
Pty Ltd [2004] QSC 066, considered
Castillon v P&O Ports Ltd [2007] QCA 364, applied
-- 1 of 17 --
2
State of Queensland v J L Holdings Pty Ltd (1996-1997) 189
CLR 146, applied
COUNSEL: D J Digby QC, with S R Grahame, for the plaintiff
K E Downes, with S B Hooper, for the defendant
SOLICITORS: Clarke & Kann, as town agents for McPherson & Kelley, for
the plaintiff
McCullough Robertson for the defendant
[1] I gave leave to the plaintiff to amend its statement of claim on the sixth day of this
trial. These are my reasons for doing so.
[2] On the fifth day of a trial estimated to last 15 days, the plaintiff seeks leave to amend
its statement of claim. This is not the first such application made for amendment. It is,
at least, the tenth time the plaintiff has formally sought to amend its pleading, the most
recent application being on 31 January this year.
[3] The amendments which are sought are in two broad categories:
(a) Major – in that the plaintiff seeks to amend paragraph 7 to plead
(both substantively and in the particulars) that the quantity of
earthworks the subject of the claim is to be measured by reference to,
among other things, the commencing surface as shown in electronic
format on a digital terrain model based total station data produced by
Peter Robinson & Associates.
(b) Minor – in that the plaintiff seeks to amend paragraphs 16, 44, 119
and attachment ‘C’ by inserting references to additional drawings.
[4] All of the amendments sought are opposed but it is fair to say, I think, that the
opposition is focused mainly on the major amendments sought. What I have described
as “minor amendments” will not cause any prejudice which cannot be adequately
remedied by an appropriate costs order. Therefore, I give leave to amend paragraph 16,
44, 119 and attachment ‘C’ in the form presented to the Court on 8 February 2008.
[5] The opposition to the major amendments is substantial. The defendant relies on:
(a) issue estoppel;
(b) the history of the litigation;
(c) the lateness of the amendments;
(d) that the amendments changed the plaintiff’s case on a central issue;
and
(e) there is no acceptable explanation for the failure to plead this
amendment earlier.
Issue Estoppel
[6] In order to understand this argument it is necessary to return to the statement of claim
in the form it had on 26 April 2002. Paragraph 6 of the Further Amended Statement of
Claim relevantly provided as follows:
-- 2 of 17 --
3
“In accordance with the terms set out in paragraph 4 above, Cook’s
undertook the bulk earthworks, raw water/evaporation pond gravel
paved area and site roads works in the following quantities:
(a) 12,635 cubic metres of Engineered Fill for Plant Site Bulk
Earthworks
(b) 126,947 cubic metres of bulk excavation of raw
water/evaporation pond
(c) 87,503 cubic metres of engineered fill of raw water/
evaporation pond
(d) 28,536 square metres of sub-based type 2 laid on site roads
(e) 23,638 square metres of sub-based type 2 laid on gravel
paved areas.”
[7] The defendant sought particulars of the statement of claim and with respect to that
paragraph particulars were sought, among other things, of the method of calculation of
the quantity, rate, amount paid and so on.
[8] In response to that request, the plaintiff stated:
“The particulars of the quantities as set out in the letter from Cook’s
to Stork dated 6 November 2000 and the drawings attached thereto.
A copy of the letter and the drawings are in the possession of the
plaintiff’s solicitors and are available for inspection by prior
appointments. A summary of the quantities and rates with references
to relevant drawings is attached hereto and marked ‘A’. The
documents which were attached to that letter consist of a series of
survey certifications by Peter Robinson and a number of as built
drawings of various parts of the site.”
[9] In a further letter from the plaintiff’s solicitors of 17 April 2002, it was stated that:
“The plaintiff notes that the plaintiff has provided copies of
summaries of quantities and plans prepared by Peter Robinson for
each of the items claimed in the corresponding paragraphs of the
FASC. Each plant has dimensions set out, so that the defendant is
provided with the location and the type of material and the quantity
removed. The documents relied on by Peter Robinson to prepare
those summaries and plans are evidence and in accordance with the
matters set out in paragraph 9A above, the plaintiff is not required to
particularise same. The documents will be available through the
process of disclosure.”
[10] The defendant continued to attempt to extract further particulars from the plaintiff and
eventually brought the application before Moynihan SJA which was heard on 18
November 2002. The defendant sought a number of orders with respect to the whole of
the pleading but for the purposes of this application only the parts of the decision
relating to the application to strike out particulars based on a failure to provide
sufficient information will be considered. The approach to this issue by Moynihan SJA
can be seen in the following extract from his reasons in Cook’s Constructions Pty Ltd v
Stork Food Systems Australia Pty Ltd [2004] QSC 066.
-- 3 of 17 --
4
“Relevant Contractual Terms.
[26] The subcontract consists of an instrument of agreement with
a number of sets of documents identified as C, D, E, F, G,
H, I, J,K, L and M exhibited to it. Provisions of the
subcontract which are particularly relevant to the issues
arising on the Application are set out below.
[27] Exhibit C is a collection of subcontract schedules. Exhibit
D is the General Conditions of Subcontract.
[28] Clause 3 of Exhibit D to the subcontract provides:
3 NATURE OF SUBCONTRACT
3.1 Performance and Payment
The Subcontractor shall execute and complete the
work under the Subcontract;
Stork shall pay the Subcontractor;
(a) for work for which Stork accepted a lump
sum, the lump sum;
(b) for work for which Stork accepted rates, the
sum ascertained by measurement and
determination of the quantities in accordance
with Clause 3.2 and multiplying the quantity
so measured and determined of each section
or item of work carried out under the
Subcontract by the rate accepted by Stork for
the section or item adjusted by any additions
or deductions made pursuant to the
Subcontract
3.2 Quantities.
Quantities in a Bill of Quantities or Schedule of Rates are
estimated quantities only.
A direction shall not be required to be given by Stork’s
Representative by reason of the actual item required to
perform the Subcontract being greater or less than the
quantity shown in the Bill of Quantities or Schedule of
Rates.
Unless otherwise stated within the contract, “actual
quantities” shall mean those quantities measured in
accordance with Australian Standard 1181-1982, as
amended from time to time, from the lines, dimensions and
limits shown on the relevant Contract plans and drawings.
Quantities over and above the actual quantities as a result of
oversupply, over excavation or any other similar reason by
the Subcontractor will not be included in the actual
quantities and the Subcontractor agrees that Stork is not
required to pay for these quantities over and above the actual
quantities.
3.3 Adjustment for Actual Quantities – Schedule of
Rates
-- 4 of 17 --
5
Where otherwise than by reason of a direction of
Stork’s Representative to vary the work under the
Subcontract, the actual quantity of an item required
to perform the Subcontract is greater or less than the
quantity shown in the Schedule of Rates;
(a) where Stork accepted a lump sum for the
item, the difference shall be valued under
clause 45.5 as if it were varied work directed
by Stork’s Representative as a variation;
(b) where Stork accepted a rate for the item, the
rate shall apply to greater or lesser quantities
provided that where limits of accuracy are
stated in the Annexure the rate shall apply to
the greater or lesser quantities within the
limits and quantities outside the limits shall
be valued under Clause 45.5 as if they were
varied work directed by Stork’s
Representative as a variation.
If a Schedule of Rates omits an item which should have
been included, the item shall be valued under Clause 45.5 as
if it were extra work directed by Stork’s Representative as a
variation
[29] Clause 2 of Exhibit C to the subcontract provides:
2.0 Measurement for Payment
The Subcontractor shall execute the work under the
Subcontract and fulfil all Subcontractors obligations
there under, and Stork shall pay the subcontractor of
the measured quantity of each item of the work
performed under the Subcontract as certified by Stork
at the appropriate rate in the Subcontract Schedule
part A – “subcontract Price Schedule and Bill of
Quantities”.
All items shall be measured net in-situ to the profiles
and dimensions shown on the Drawings or described
in the Scope of work and Specification and
Subcontractor shall allow for wastage in the rates for
the net quantities given in the Subcontract Schedule
Part A – “Subcontract Price Schedule and Bill of
Quantities”.
Upon issue by Stork of the `Approved for
Construction’ Drawings for the work and prior to
construction of work covered by the Drawings, Stork
and Subcontractor shall jointly review the Drawings
and agree on the rate items applicable to the work
shown on the Drawings.
Measurement of work shall be made in accordance
with the conditions set out hereunder.
2.1 Civil Works.
2.1.1 Excavation (General)
-- 5 of 17 --
6
(a) The volume measured for the excavation of a
structure or foundation shall be the volume
which is to be either occupied by or vertically
above any part of the structure or foundation,
or in accordance with Clause 2.1.2 for
drainage or culverts, and shall not include for
working space or planking and strutting for
structural excavation which shall be allowed
for by the Subcontractor and included in the
unit rate.
(b) All excavations have been given in cubic
metres.
(c) Rates for excavations shall include for:
(i) Land or machine excavation as found
expedient or required by the nature of
the work or the prevailing Site
conditions in any material
encountered other than brick or
concrete and whether above or below
the ground water levels occurring at
site.
Rippable rock is defined as rock that
can be ripped out by a dozer of 300
kW engine power and matching
single tooth hydraulic ripper at the
rate of 25 m3/hour solid or more and
shall include boulders up to 0.8 m3 in
volume or boulders that can be picked
out and removed without further
breaking up.
Solid rock is defined as rock that
cannot be ripped out as defined above
or boulders that cannot be picked out
without further breaking up, but
requires to be broken up by rock
breaker, jackhammer or other
approved means.
(ii) Levelling and compacting bottoms of
excavations where required by the
Scope of Work, Specifications and
Drawings.
(iii) Increase or decrease in bulk material
(iv) Keeping the excavations free from
water by construction of temporary
drainage ditches, pumping, bailing or
any other method necessary to ensure
that work can proceed at all times
having particular regard to the Site
water table
-- 6 of 17 --
7
(v) Provision of water for structural
requirements and for dust
suppression.
(vi) Trim, prepare and hand dig bottom of
excavations as necessary.
(vii) Removal of surplus excavated
material from Site, unless otherwise
specified.
(d) Where excavations are in or adjacent to roads
or structure the rates shall include all
measures required to maintain the structural
integrity of the excavated face.
[30] Clause 45 of Exhibit D to the subcontract deals with
variations:
45 VARIATIONS
45.1 Stork’s Representative may direct the
Subcontractor to:
(a) increase, decrease or omit any part of the
work under the Subcontract
(b) change the character or quality of any
material or work;
(c) change the levels, lines, positions or
dimensions of any part of the work under the
Subcontract;
(d) execute additional work; and/or
(e) demolish or remove material or work no
longer required by Stork.
The Subcontractor shall not vary the work under the
Subcontract except as directed by Stork’s Representative or
approved in writing by Stork’s Representative under Clause
45.
The Subcontractor is bound only to execute as variation
directed rectification work referred to in Clause 42.
45.2 Proposed Variations
Upon receipt of a notice in writing from Stork’s
Representative advising the Subcontractor of a
proposed variation under Clause 45, the
Subcontractor shall advise Stork’s Representative, in
writing within 5 days, whether the proposed variation
can be effected. If the variation can be effected, the
Subcontractor shall;
(a) advise Stork’s Representative of the effect
which the Subcontractor anticipates that the
variation will have on the construction
program and time for Substantial
Completion; and
(b) provide an estimate of the cost (including
delay costs, if any) of the proposed variation.
-- 7 of 17 --
8
Stork shall reimburse the Subcontractor for the
reasonable costs of complying with the requirements
of Clause 45.2.
45.3 Pricing the Variation
Unless Stork’s Representative and the Subcontractor
agree upon the price for a variation, the variation
directed or approved by Stork’s Representative under
Clause 45.1 shall be valued under Clause 45.5.
Stork’s Representative may direct the Subcontractor
to provide a detailed quotation of the work of a
variation supported by measurements or other
evidence of cost.
45.4 Variations for the Convenience of the Subcontractor
If the Subcontractor requests Stork’s Representative to
approve a variation for the convenience of the
Subcontractor, Stork’s Representative may do so in
writing. The approval may be conditional.
Unless Stork’s Representative otherwise directs in the
notice approving the variation, the Subcontractor shall
not be entitled to
(a) an extension of time for Substantial
Completion; or
(b) extra payment;
in respect of the variation or anything arising out of the
variation which would not have arisen had the
variation not been approved.
Stork’s Representative shall not be obliged to approve
a variation for the convenience of the Subcontractor.
45.5 Valuation
Where the Subcontract provides that a valuation shall
be made under Clause 45.5, Stork shall pay or allow
the Subcontractor, or the Subcontractor shall pay or
allow Stork, as the case may require, an amount
ascertained by Stork’s Representative as follows:
(a) if the Subcontract prescribes specific rates or
prices to be applied in determining the value,
those rates or prices shall be used;
(b) if Clause 45.5(a) does not apply, the rates or
prices in a Priced Bill of Quantities or
Schedule of Rates shall be used to the extent
that it is reasonable to use them;
(c) to the extent that neither Clause 45.5(a) or
45.5(b) apply, reasonable rates or prices shall
be used in any valuation made by Stork’s
Representative;
(d) in determining the deduction to be made for
work which is taken out of the Subcontract,
the deduction shall include a reasonable
amount for profit and overheads;
[31] Finally, Exhibit D provides:
-- 8 of 17 --
9
16 LEGISLATIVE REQUIREMENTS
16.1 Complying with Legislative Requirements
Subcontractor must at all times comply with all
Legislative Requirements, and is responsible for
obtaining all necessary approvals and consents to
enable the Works to be constructed.
For the purpose of this contact, Legislative
Requirements includes the following requirements;
(a) Acts of the Commonwealth;
(b) Acts and Ordinances of the State or Territory
in which the work under the Subcontract or
any part thereof is carried out;
(c) Ordinances, regulations, by-laws, orders and
proclamations under the Acts and
Ordinances;
(d) Persons acting in the exercise of statutory
powers enabling them to give directions
affecting the work under the subcontract.
Legislative Requirements includes:
(a) Acts, Ordinances, regulations, by-laws,
orders, awards and proclamations of the
Commonwealth and the State or Territory in
which work under the Subcontract or any part
thereof is being carried out;
(b) Certificates, licences, consents, permits,
approvals and requirements of government or
local government organisations having
jurisdiction in connection with the carrying
out of the work under the Subcontract;
(c) Fees and charges payable in connection with
the foregoing and which are generally
applicable in the State of Queensland or the
shire of Banana;
[32] The plaintiff’s claims are largely for work done under the
contract. It is not however clear if some claims are for work
outside the subcontract. If they are, the plaintiff must
identify them and plead the basis of justification for
payment.
[33] The plaintiff must identify the contractual provisions under
which the claim is made including, for example, those by
which the quantities and rates claimed are set. It must also
plead facts establishing that the contractual requirements for
payment have been complied with.
[34] Some claims are for variations. The subcontract (cl 45.2 of
Exhibit D) provides to the effect that on receiving a notice
of proposed variation the plaintiff is to advise whether it
could be effected. If it can the plaintiff is to advise of any
effect on the progress of the contract and provide an
-- 9 of 17 --
10
estimate of the cost (including any delay costs) of the
proposed variation.
[35] The clause concludes by providing that the defendant will
reimburse the plaintiff for the “reasonable costs of
complying with the requirements of cl 45.2”. In my view,
this reference does not refer to the cost of carrying out of the
variation itself. I mention this because where the Statement
of Claim refers to “reasonable” costs it cannot be referrable
to this clause and the basis for each reasonable cost claim
must be pleaded.
[36] The pricing of variations is provided for by cl 45.3. This
provides that in the absence of agreement “upon the price of
the variation” it is to be valued under cl 45.5. If agreement
is relied on, it seems it is not in most cases, it must be
pleaded.
[37] Clause 45.5 provides that the defendant is to pay an amount
ascertained by its representative on the following basis:
(a) if the subcontract prescribes specific rates or prices
they are to be used;
(b) if it does not the rates or prices on a priced bill of
quantity of schedule of rates are to be used to the
extent to which it is reasonable;
(c) if neither (a) nor (b) applies reasonable rates or
prices are to be used.
In other words, “reasonable rates” are payable only when (a)
or (b) do not apply. If the plaintiff is suing for an amount
ascertained by the defendant’s representative it must plead
and particularise that. If the plaintiff does not accept that an
ascertainment is appropriate it must plead and particularise
that basis for that contention. If there is no “ascertained”
amount the plaintiff must plead and particularise the basis
for the claim notwithstanding there is no “ascertained”
amount.
[38] The subcontract (cl 2 of Exhibit C) provides as to
measurement for payment for work done under the
subcontract. Put shortly, payment is for work “measured in-
situ” to the profiles and dimensions shown in the relevant
“Drawings or described in the Scope of Work and
Specification”.
[39] It is essential, for example, that the plaintiff gives sufficient
particulars to enable the defendant to investigate whether the
quantities claimed are “actual quantities” in terms of cl 3.1
of Exhibit D to the subcontract. The defendant is not, for
example, required to pay for excavation over and above
“actual quantities”.
-- 10 of 17 --
11
[40] In terms of determining quantity, the relevant considerations
are those in cl 2 of Exhibit C. For the purposes of pleading
the claim the plaintiff must identify, for example, the
“Drawings” on the “Approved for construction Drawings”
referred to in the clause. It is not sufficient, for example, to
identify documents calculating the quantities actually
excavated or claimed on plans and drawings referred to,
those quantities or their calculation.”
[11] It is argued for the defendant that the decision of Moynihan SJA determined that the
proper construction of the subcontract requires that the plaintiff cannot rely upon
drawings other than for-construction drawings or the calculation of quantities derived
from such drawings for the purposes of establishing the quantity of work performed by
it so as to give rise to an entitlement to payment under the subcontract. As a result, it is
submitted, an issue estoppel arises and the plaintiff is precluded from amending its
pleading and from arguing to the contrary of Moynihan SJA’s decision.
[12] Whether an issue estoppel can arise out of an interlocutory decision and, if so, under
what conditions, has been the subject of recent consideration in the Court of Appeal. In
Castillon v P&O Ports Ltd [2007] QCA 364, Holmes JA (with whom Wilson J agreed)
examined the relevant decisions touching upon this issue. She said:
“ [49] The fact that a determination is made in the course of
interlocutory proceedings is not conclusive of whether it may give
rise to an issue estoppel. The seminal statement of the law relating to
issue estoppel is that made by Dixon J in Blair v Curran (1939) 62
CLR 464):
‘A judicial determination directly involving an issue of
fact or of law disposes once for all of the issue, so that it
cannot afterwards be raised between the same parties or
their privies. The estoppel covers only those matters
which the prior judgment, decree or order necessarily
established as the legal foundation or justification of its
conclusion, whether that conclusion is that a money sum
be recovered or that the doing of an act be commanded
or be restrained or that rights be declared. The distinction
between res judicata and issue estoppel is that in the first
the very right or cause of action claimed or put in suit
has in the former proceedings passed into judgment, so
that it is merged and has no longer an independent
existence, while in the second, for the purpose of some
other claim or cause of action, a state of fact or law is
alleged or denied the existence of which is a matter
necessarily decided by the prior judgment, decree or
order.’ (At 531-532)
[50] Issue estoppel in an interlocutory context was raised and
discussed in the Carl Zeiss Stiftung v Rayner & Keeler Ltd decisions,
in a series of applications in the English courts, concerning, at least
in part, an East German council’s authority to instruct solicitors on
the plaintiff’s behalf. In his speech in Carl Zeiss Stiftung v Rayner &
-- 11 of 17 --
12
Keeler Ltd (No 2)( [1967] 1 AC 853 at 935) Lord Guest identified the
requirements of issue estoppel:
“(1) that the same question has been decided; (2) that the
judicial decision which is said to create the estoppel was
final, and (3) that the parties to the judicial decision or
their privies were the same persons as the parties to the
proceedings in which the estoppel is raised or their
privies.”
(A formulation adopted by the High Court in Kuligowski v
Metrobus). ((2004) 220 CLR 363 at 373)
[51] Lord Guest expanded on the quality of finality: it meant “final
and conclusive on the merits”([1967] 1 AC 853 at 935). In the case
before the House of Lords, the appeal was, ultimately, from a
decision of Cross J, dismissing a summons to stay proceedings and
holding that the council was the proper body to authorise the
plaintiff’s passing off action. The question was raised as to whether
an earlier decision by a West German court in an action seeking
restraining orders, that the council lacked authority to represent the
plaintiff, created an estoppel. The plaintiff was entitled, Lord Guest
said, to raise a change of circumstances affecting its capacity to sue;
the West German decision was therefore not final and conclusive.
[52] In Carl Zeiss Stiftung v Rayner & Keeler Ltd & Others (No 3),
([1969] 3 All ER 897) the question had evolved; it was now whether
the decision of Cross J affirming the council’s capacity to give
instructions on the plaintiff’s behalf created an issue estoppel.
Buckley J distinguished between an interlocutory order which
involves no final decision of any issue, because something remains
to be determined before the decision is effected or because it is
subject to alteration by the court or tribunal making it (as, for
example, an interim injunction); and a decision which, although
interlocutory, is final and binding. (At 910). To the extent that it
concerned the authorisation of the plaintiff’s action, the relevant
determination did have the necessary final and binding quality; the
defendants could not have sought another stay of the action on that
ground and they conceded as much; but it did not bear directly on the
issues raised by the litigation before Buckley J so as to give rise to an
estoppel.
[53] The second of Buckley J’s indicators of lack of finality, that the
decision is subject to subsequent alteration, begs the question of how
one determines what decisions may be revisited. It shares the
circularity which bedevils attempts in many of the authorities to
articulate when a decision possesses the necessary finality to create
an issue estoppel: if a further application may be made, the decision
is not final, but whether a further application may be made depends
on whether an issue estoppel arises.
[54] Lord Guest’s tripartite test was applied by the House of Lords in
“The Sennar” (No 2), ([1985] 2 All ER 104) with some further
-- 12 of 17 --
13
consideration of what constituted a decision “on the merits” in the
context of issue estoppel:
‘a decision on the merits is a decision which establishes
certain facts proved or not in dispute, states what are the
relevant principles of law applicable to such facts and
expresses a conclusion with regard to the effect of
applying those principles to the factual situation
concerned.’ (At 111).
On those criteria, a Dutch Court of Appeal’s decision that an
exclusive jurisdiction clause in a bill of lading applied to the
appellants’ claim, although procedural insofar as it was a decision
concerning that court’s jurisdiction, was nonetheless a decision on
the merits. It created an issue estoppel which barred the appellants
from proceeding in an English court.
[55] Closer to home, the New Zealand Court of Appeal, in Joseph
Lynch Land Co Ltd v Lynch ([1995] 1 NZLR 37) accepted, at least in
principle, that an interlocutory judgment could found a subsequent
issue estoppel; the question was,
“concerned not so much with the character of the earlier
decision, ie whether it should be regarded as final or
interlocutory . . .[but] rather whether in the circumstances
it is reasonable to regard the earlier decision as a final
determination of the issue which one of the parties now
wishes to raise.” (At 43)
That said, the Court urged caution in coming to the conclusion that
an estoppel had been created by a decision given in an interlocutory
context.
[56] In Makhoul v Barnes ((1995) 60 FCR 572) the full Federal Court
described as “too broadly expressed” the proposition (expressed by a
single judge in an earlier decision) that the determination of an issue
determined in interlocutory proceedings could not give rise to an
issue estoppel. The Court referred to Carl Zeiss Stiftung (No 3) and
Joseph Lynch Land Co as indicating that the correct approach was to
consider whether the earlier decision ought to be regarded as a final
determination of the issue, rather than focussing on the nature of the
proceedings. (At 583)
[57] In Santos v Delhi Petroleum Pty Ltd ([2002] SASC 272) Lander J,
with whom the other members of the South Australian Full Court
agreed, considered the question. It was relevant, but not decisive, his
Honour said, that the decision was made in an interlocutory
application. The question must be answered:
‘[not] by reference to whether the application is
interlocutory or otherwise but by reference to the order
itself and whether it amounts to a final determination such
that it is not only impractical to bring the issue before the
court but impermissible.’ (At para [400])
An issue resolved on an interlocutory application could, if it finally
determined the issue between the parties, give rise to an issue
estoppel. That view was cited with approval by the New South Wales
-- 13 of 17 --
14
Court of Appeal in Inasmuch Community Inc v Bright. ([2006]
NSWCA 99 at [60])
[58] Decisions made for the purpose of determining whether an order
is final rather than interlocutory so as to give a right of appeal are
not, as Handley JA, writing extra-curially has pointed out, (Handley
K, “Res Judicata: General Principles and Recent Developments”
(1999) 18(3) Aust Bar Rev 214) necessarily of assistance. As much
can be seen from the rationale given in Carr v Finance Corporation
of Australia Ltd (No 1) ((1981) 147 CLR 246 at 248) for the
approach taken in that context. Gibbs CJ observed that the test in
Licul v Corney, ((1976) 180 CLR 213) of whether the judgment or
order appealed from finally determined the rights of the parties,
required the court to have regard to the legal, as opposed to the
practical, effect of the judgment. Otherwise uncertainty would result,
and in some instances the court would have to investigate the facts
and the course of the proceeding in order to determine the practical
effect of the order;
‘an inquiry quite inappropriate when the only issue is
whether a right of appeal exists.’ ((1981) 147 CLR 246 at
248)
Mason J similarly regarded the disadvantage of having to undertake
‘an examination of the grounds on which the application
to set aside was made, the grounds on which it was
refused and the formation of a judgment as to the impact
of the grounds of refusal on the prospects of bringing a
second application’ (At 256)
as militating against such an approach to classification in
determining whether an appeal lay as of right. But such an exercise
is, in contrast, appropriate in determining whether an issue estoppel
exists; then, it is necessary to consider precisely what was decided
and its actual effect in binding the parties.”
[13] I do not accept that the decision of Moynihan SJA falls into any of the categories
which will support an issue estoppel. It was not necessary for Moynihan SJA to decide
what the proper construction of the relevant part of the contract was and I do not, on a
careful examination of his reasons, find that he did make any such decision as to the
proper construction of the relevant clauses.
[14] In [38] of his reasons he refers to the subcontract providing as to the measurement for
payment for work done under the subcontract. He said:
“Put shortly, payment is for work ‘measured in-situ’ to the profiles
and dimensions shown in the relevant ‘Drawings or described in the
Scope of Work and Specification’.”
[15] His Honour then goes on to say that it is essential that the plaintiff give sufficient
particulars to enable the defendant to investigate whether the quantities claimed are
“actual quantities” in the terms of the subcontract. Further, he said, that “In terms of
determining quantity, the relevant considerations are those in cl 2 of Exhibit C.” His
-- 14 of 17 --
15
Honour did not, in my view of what he said, set out a complete exposition of the
meaning of clause 2 of Exhibit “C” to the subcontract. His Honour does not, for
example, say that a pleading on this part of the action cannot refer to matters other than
the “approved for construction drawings”. He says, rather, that such a pleading must
identify those drawings but he does not go on to say that there is a particular limit. In
my view that is because his Honour was not attempting to set out a concluded view as
to the proper construction of the relevant parts of the subcontract.
The history of the litigation, the lateness of the amendments, a change in case and
the failure to explain
[16] The matters referred to in the above subheading are all matters upon which the
defendant is entitled to make strong complaint about the conduct of the plaintiff.
[17] The plaintiff has known since, at least, 2005 that the defendant’s case was, on this part
of the claim, that the material pleaded by the plaintiff did not allow for the necessary
calculations to be done to determine the relevant quantities. The defendant has not
made a secret of that and has consistently attacked the statement of claim in this
respect on that basis.
[18] Reference was made to an order of Byrne J made on 12 July 2005 concerning the
statement of claim. So far as is relevant that order provided:
“In relation to paragraph 6, 17, 30, 54, 79, 124 and 193 of the draft
statement of claim, the Plaintiff file and serve, as soon as possible,
but in any event within 45 days, particulars of the profiles and
dimensions relied upon it as the basis for the calculation of each of
the quantities alleged and each of those paragraphs by reference to
each for-construction drawing from which each of the measured
profiles and dimensions were taken.”
[19] It was submitted by Mr Digby QC that the court “had in that respect prescribed the
way in which it required those particulars to be put forward”, namely only the
provision of particulars of the for-construction drawings to which the quantities have
been measured, and that there was “something of a prohibition upon referring to or
relying upon any other drawing than the for-construction drawing”.
[20] Justice Byrne’s order, set out above, does not restrict the plaintiff in how it may plead
its case. As with Moynihan SJA’s reasons, referred to above, the order of Byrne J
provides the minimum which is required for the pleading. It does not, in any sense,
purport to restrict the plaintiff in the proper provision of particulars beyond those set
out in the order.
[21] I was referred to a number of cases by both parties. The most well known decision of
them is State of Queensland v J L Holdings Pty Ltd (1996-1997) 189 CLR 146. The
plaintiff relied on the often cited passages in the joint reasons of Dawson, Gaudron
and McHugh JJ where they said:
-- 15 of 17 --
16
“Case management is not an end in itself. It is an important and
useful aid for ensuring the prompt and efficient disposal of litigation.
But it ought always to be borne in mind, even in changing times, that
the ultimate aim of a court is the attainment of justice and no
principle of case management can be allowed to supplant that aim.”
[22] As this is a case in which both parties are corporations and the dispute is over a
substantial building project what their Honours said at 154-155 is also relevant:
“The majority in the Full Court considered that costs are not these
days considered the "healing medicine" they once were. They referred
to the speech of Lord Griffiths in Ketteman v Hansel Properties Ltd
… and the decision of this Court in The Commonwealth v Verwayen
… . In Ketteman Lord Griffiths said [at 220]:
"justice cannot always be measured in terms of money and in
my view a judge is entitled to weigh in the balance the strain
the litigation imposes on litigants, particularly if they are
personal litigants rather than business corporations, the
anxieties occasioned by facing new issues, the raising of false
hopes ... "
In this case, which is of a commercial nature, the litigants are on the
one side a developer and on the other side government, and there is
nothing which would indicate any personal strain which would justify
the conclusion that costs are not an adequate remedy for prejudice
caused by the amendment sought to the pleadings.”
[23] And further, at 155:
“Justice is the paramount consideration in determining an application
such as the one in question. Save in so far as costs may be awarded
against the party seeking the amendment, such an application is not
the occasion for the punishment of a party for its mistake or for its
delay in making the application. Case management, involving as it
does the efficiency of the procedures of the court, was in this case a
relevant consideration. But it should not have been allowed to prevail
over the injustice of shutting the applicants out from raising an
arguable defence, thus precluding the determination of an issue
between the parties.”
[24] This trial was on the Supervised Case List of this court. The Practice Direction
governing the conduct of cases on that list (No. 6 of 2000) provides for the making of
directions for the conduct of interlocutory steps. Clause 15 of the Practice Direction
provides:
15. Non-compliance with a direction may, on the application of a
party or on the court's own motion, result in:
. an order pursuant to rule 371(2);
. a non-complying party being deprived of the costs of late
compliance;
-- 16 of 17 --
17
. a non-complying party may be ordered to pay the other
party's costs thrown away by non-compliance which may be
fixed and payable forthwith;
. the non-complying party may be ordered to pay as a sanction
an administration charge of $75.00;
. the Supervised List Manager may be directed to write
directly to the non-complying party informing that party of
the non-compliance and any orders made in respect of it;
. the matter may be listed for trial notwithstanding non-
compliance.
[25] It has become clear, during the conduct of this trial, that the plaintiff has ignored many
of the directions given during the reviews conducted pursuant to the Practice Direction.
[26] The failure to comply with directions, together with other matters (late disclosure, late
supply of expert’s reports), has understandably frustrated the defendant in defence of
the claim and in the pursuit of its defence and counterclaim. Nevertheless, the
application is one which can be dealt with by the defendant (no prejudice was
asserted), but it is made against a history which justifies an order for costs on an
indemnity basis.
[27] The plaintiff has leave to amend its statement of claim in the manner sought. It must
pay the costs of the defendant thrown away by the defendant to be assessed on an
indemnity basis.
-- 17 of 17 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2008/186