Cook’s Constructions Pty v Stork Food Systems Aust Pty [2008] QSC 179
SUPREME COURT OF QUEENSLAND
CITATION: Cook’s Constructions P/L v Stork Food Systems Aust P/L
[2008] QSC 179
PARTIES: COOK’S CONSTRUCTIONS PTY LTD
ACN 004 782 558
(plaintiff)
v
STORK FOOD SYSTEMS AUSTRALIA PTY LTD
ACN 007 298 633
(defendant)
FILE NO/S: S10993 of 2001
DIVISION: Trial Division
PROCEEDING: Trial
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 22 August 2008
DELIVERED AT: Brisbane
HEARING
DATES:
4, 5,6,8, 11, 12,13, 15, 16,18,19 and 22 February 2008
JUDGE: Martin J
ORDER: On the claim: Judgment for the plaintiff in the sum of
$132,657.70 with interest.
On the counterclaim; judgment for the defendant in the
sum of $9,983,796.54 with interest.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
CONSTRUCTION OF PARTICULAR CONTRACTS AND
IMPLIED CONDITIONS – OTHER MATTERS –
interpretation of a clause for measuring quantities – whether
quantity of work claimed had been measured in accordance
with the contract.
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT – where a
clause of the contract required a party to give notice of a
claim for breach of the sub-contract within 14 days – where
no notice was given – whether the provision of progress
claims satisfied that clause.
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – OTHER MATTERS – where
Plaintiff did not hold a licence under the Queensland
Building Services Authority Act 1991 – whether work
-- 1 of 81 --
2
completed by the plaintiff was ‘building work’ within the
meaning of the Act – whether the ‘building work’ the
defendant had paid for was paid by mistake.
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION – where
plaintiff is entitled to ‘reasonable remuneration’ under the
Queensland Building Services Authority Act 1991 for work
completed – appropriate methods for calculating reasonable
remuneration – relevance of expert reports in determining
reasonable remuneration.
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT – whether
the contract was a lump sum or schedule of rates contract.
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMUNERATION –
AMOUNT – whether rates and quantities claimed for work
were claimed in accordance with the subcontract.
EVIDENCE – miscellaneous matters – rule in Browne v
Dunn – where party did not cross examine on conflicting
evidence in expert reports where such reports had been
provided to the opponent in advance of the trial.
EVIDENCE – miscellaneous matters – rule in Jones v Dunkel
– whether adverse inferences could be drawn from a party
not calling witnesses in relation to matters which only formed
part of the background ‘factual matrix’ of the case.
Queensland Building Services Authority Act 1991
Queensland Building Services Authority Amendment Bill
1999
Queensland Building Services Authority Regulation 1992,
s 3A s 42(4)
B P Refinery (Westernport) Pty Ltd v Hastings Shire Council
(1977) 180 CLR 266
Bartier v Kounza Investments Pty Ltd [2003] QSC 390
Browne v Dunn (1893) 6 R 67
Codelfa Constructions Pty Ltd v State Rail Authority of New
South Wales (1982) 149 CLR 337
Cook’s Construction Pty Ltd v Stork ICM Australia Pty Ltd
[2004] QSC 066
Cook’s Constructions Pty Ltd v Stork Food Systems Australia
Pty Ltd [2008] QSC 186.
Decor Ceilings Pty Ltd v Cox Constructions Pty Ltd (No 2)
(2007) 23 BCL 347; [2005] SASC 483
Flett v Deniliquin Publishing Co Ltd [1964-5] NSWR 383
Gino D’Alessandro Constructions Pty Ltd v Powis [1987] 2
Qd R 40
-- 2 of 81 --
3
Hansen v Mayfair Trading Co Pty Ltd [1962] WAR 148
Iezzi Constructions Pty Ltd v Watkins Pacific (Qld) Pty Ltd
[1995] 2 Qd R 350
In the matter of Stork ICM Australia Pty Ltd; Stork ICM
Australia Pty Ltd v Stork Food Systems Australasia Pty Ltd
[2006] FCA 1849
Interline Hydrocarbon Inc v Prenzil Pty Ltd [2005] QSC 109
Makita (Australia) Pty Ltd v Sprowles (2001) 52 NSWLR
705
Marshall v Marshall [1999] 1 Qd R. 173
Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221
Pownall v Conlan Management Pty Ltd (1995) 12 WAR 370
Price v John Holland (Constructions) Pty Ltd (1985) 59
ALJR 844
Re Allison, Johnson & Foster Ltd; ex parte Birkenshaw
[1904] 2 KB 327
Smith v Commonwealth of Australia (2006) NSWSC 689
Trade Practices Commission v Arnotts Ltd (No. 5) (1990) 21
FCR 324
West v Mead [2003] NSWSC 161
Zullo Enterprises Pty Ltd v Sutton [2000] 2 Qd R. 196
COUNSEL: D J Digby QC, with S R Grahame and J D Wilson, for the
plaintiff
K E Downes, with S B Hooper, for the defendant
SOLICITORS: Clarke & Kann, as town agents for McPherson & Kelley, for
the plaintiff
McCullough Robertson for the defendant
-- 3 of 81 --
4
TABLE OF CONTENTS
Background ......................................................................................................................... 5
The Subcontract ................................................................................................................. 5
CCPL’s claim ...................................................................................................................... 6
Defence and Counterclaim ................................................................................................ 6
Construction of the Subcontract ....................................................................................... 7
The rule in Browne v Dunn .............................................................................................. 14
The Rule in Jones v Dunkel ............................................................................................. 17
The Defences ..................................................................................................................... 18
The Prescribed Notice Defence........................................................................................ 18
Defence relating to Alleged Errors in the Bill of Quantities......................................... 21
The Queensland Building Services Authority Act Defence............................................. 26
Quantities of footings ..................................................................................................... 28
Pedestal Claim ................................................................................................................ 29
Corrocem claim .............................................................................................................. 30
Suspended slabs.............................................................................................................. 30
Prill storage building ...................................................................................................... 31
The Claims ........................................................................................................................ 32
(i) The Bulk Earthworks Claim........................................................................... 32
(ii) The Road Reconstruction Claim .................................................................... 34
(iii) The Contour Drains Claim ............................................................................. 35
(iv) The Lime Stabilization of Site Roads Claim.................................................. 36
(v) The Boxing Out for Roadworks Claim .......................................................... 37
(vi) The Asphalt on Site Roads Claim................................................................... 38
(vii) The Quantities of Footings Claim................................................................... 38
Item 6.4.45 Steam Reformer Footings .................................................................. 39
Item 6.4.64 Turbine Generator Building ............................................................... 40
Item 6.4.65 Ammonia Storage Pipe Supports and Steam Reformer Pipe Supports 40
Item 6.7.8 Nitric Acid Plant Building Slabs ........................................................ 40
Duplication of Claim? ................................................................................................ 40
(viii) The Pedestal Claim .......................................................................................... 41
(ix) The Pedestal Reconciliation Claim................................................................. 47
(x) The Corrocem Claim ....................................................................................... 48
(xi) The Suspended Slabs Claim............................................................................ 52
(xii) The Prill Storage Building Structures Claim ................................................ 55
Formwork to base slab ............................................................................................... 56
Rate for formwork to nib walls................................................................................... 57
Rate for formwork to walls ......................................................................................... 57
Rate for concreting base slab ..................................................................................... 57
Rate for concreting walls ........................................................................................... 57
(xiii) The Crushed Rock to Substations 1 and 2 Claim ......................................... 57
(xiv) The Ammonia Spill Standby Claim ............................................................... 58
Recovery under s 42(4) QBSA Act.................................................................................. 60
The accountants’ evidence ............................................................................................ 64
The Counterclaim............................................................................................................. 67
What is the work in Appendix B? .................................................................................. 72
Is that work “building work”? ........................................................................................ 72
Was that work paid for by Stork?................................................................................... 79
If the work was paid for, was that payment made by mistake?...................................... 79
Conclusion ......................................................................................................................... 79
Schedule of Claims and Defences.................................................................................... 81
-- 4 of 81 --
5
Background
[1] In June 1998 Cook’s Constructions Pty Ltd (“CCPL”) and Stork ICM Australia Pty Ltd
entered into an agreement (“the Subcontract”) whereby CCPL agreed to undertake the
construction of earthworks and concrete works (“the works”) in relation to the
construction of an ammonium nitrate plant at Moura in central Queensland.
[2] On 14 December 2006 Lindgren J ordered1 , among other things, that:
(a) the property of Stork ICM Australia Pty Ltd was to be
transferred to and become the property of Stork Food
Systems Australasia Pty Ltd (“Stork”);
(b) all liabilities of Stork ICM were to be transferred to and
become the liabilities of Stork; and
(c) Stork ICM was to be deregistered without winding up
pursuant to s 413(1)(c) of the Corporations Act 2001 (Cth);
and
(d) All legal proceedings pending by or against Stork ICM were
to be continued by or against Stork.
[3] The ammonium nitrate plant, the subject of this action, is a processing plant that
manufactures ammonium nitrate in prill form. Prill is the pellet form which is the end
product manufactured by the plant. The plant reforms natural gas to produce hydrogen
which reacts with nitrogen extracted from the air and forms ammonia. The ammonia is
then combined with nitric acid, which is also produced by the plant, to form the
ammonium nitrate prill. That prill is then used in the manufacture of fertilisers and
explosives.
The Subcontract
[4] The Subcontract as pleaded by CCPL is admitted by Stork. The Subcontract is
constituted by the following documents:
(a) Instrument of Agreement for Civil Subcontract Number QNP-001;
(b) Exhibit C: Subcontract Schedules;
(c) Exhibit D: General Conditions of Subcontract.
(d) Exhibit E: Annexures to General Conditions of Subcontract
including:
(i) Annexures to the General Conditions of Subcontract Part A;
(ii) Annexures to the General Conditions of Subcontract Part B,
Quality system Requirements;
(iii) Annexures to the General Conditions of Subcontract Part C,
Safe System of Work Statement;
(iv) Annexures to the General Conditions of Subcontract Part D
Subcontractors Consent Deed;
(e) Exhibit F: Scope of Work;
(f) Exhibit G: Engineering Specifications;
(g) Exhibit H: Drawings;
(h) Exhibit I: Environmental Management Plan;
(i) Exhibit J: Geotechnical Investigation;
(j) Exhibit K: Contract Works Insurance;
1 In the matter of Stork ICM Australia Pty Ltd; Stork ICM Australia Pty Ltd v Stork Food Systems
Australasia Pty Ltd [2006] FCA 1849.
-- 5 of 81 --
6
(k) Exhibit L: Health and Safety Risk Assessment;
(l) Exhibit M Project Construction Agreement.
CCPL’s claim
[5] The plaintiff’s claim is made up of 14 separate items identifying aspects of the works
undertaken by it, the plaintiff says, at the request of Stork. Those claims can, in turn, be
categorised under four general headings.
(a) Claims made pursuant to identified terms of the
Subcontract:
(i) the Bulk Earthworks claim, and
(ii) the Ammonia Spill Standby claim,
(b) Claims made pursuant to variations under the Subcontract:
(iii) the Road Reconstruction claim,
(iv) the Contour Drains claim,
(v) the Lime Stabilization of Site Roads claim,
(vi) the Boxing Out for Roadworks claim, and
(vii) the Asphalt on Site Roads claim;
(c) Claims made pursuant to clause 5.4 of Exhibit D of the
Subcontract i.e. “Bill Error” claims:
(viii) the Quantities of Footings claim,
(ix) the Pedestal claim,
(x) the Corrocem claim,
(xi) the Suspended Slabs claim,
(xii) the Prill Store claim,
(xiii) the Crushed Rock to Substations claim; and
(d) Claims made under separate, albeit related agreements:
(xiv) the Pedestal Reconciliation Agreement.
[6] CCPL brings further or alternative claims in respect of the Bulk Earthworks claim, the
Road Reconstruction claim, the Quantity of Footings claim, the Pedestal claim, the
Corrocem claim, the Suspended Slabs claim, the Prill Storage claim and the Crushed
Rock to Sub Stations claim pursuant to clause 3.1 of Exhibit D of the Subcontract.
Under that clause Stork was obliged to pay CCPL for the work undertaken an amount
ascertained by: measurement and determination of actual quantities (determined in
accordance with clause 3.2 of Exhibit D of the Subcontract), and multiplying the
quantity so measured and determined by the rate accepted by Stork in accordance with
clause 3.3(b) of Exhibit D of the Subcontract.
Defence and Counterclaim
[7] Stork raises a number of issues related to the terms of the subcontract which, it pleads,
demonstrate:
(a) That CCPL, not having given a prescribed notice under clause 51.1
of Exhibit D to the subcontract cannot recover any of the claims:
paragraphs 6A-6D Fourth Further Amended Defence and
Counterclaim (“FFADC”).
(b) That CCPL cannot rely on errors in the bill of quantities and so Stork
is not liable to pay certain claims: paragraph 6E-6I FFADC.
(c) That CCPL did not lodge a final payment claim and, therefore, is
barred from making a claim for work done prior to December 1999:
paragraphs 7-13 FFADC.
-- 6 of 81 --
7
[8] Stork also pleads that:
(a) that, as CCPL did not hold the relevant licence under the Queensland
Building Services Authority Act 1991 (“QBSA Act”), it is not entitled
to any monetary or other consideration for that part of the work said
by Stork to be “building work” as that term is defined in the QBSA
Act;
(b) that CCPL did not measure the work performed in accordance with
the subcontract and, as a result Stork has no obligation to make any
payment where the claim relies upon measurement being performed
in accordance with the subcontract;
(c) particular defences to each of the heads of claim; and
(d) that the proper construction of the subcontract has already been
determined and that the plaintiff is estopped from arguing otherwise
by the decision in Cook’s Construction Pty Ltd v Stork ICM
Australia Pty Ltd. 2
[9] By way of counterclaim, Stork alleges:
(a) that certain of the work performed by the plaintiff was “building
work” within the meaning of the QBSA Act; and
(b) that, as the plaintiff did not comply with the QBSA Act; then
(c) CCPL was not lawfully entitled to claim or receive any payments in
relation to the building work; and that
(d) Stork, having mistakenly made payments to the plaintiff, is entitled
to a refund of the amounts paid by it for the building work.
[10] Before dealing with various claims I need to determine the proper construction of that
part of the Subcontract upon which some of the claims rely and, also, some of the
evidentiary issues raised by CCPL.
Construction of the Subcontract
[11] An issue which consumed a substantial part of the trial in both evidence and
submissions was the proper construction of the Subcontract, in particular, clause 2 of
Ex C. CCPL submitted3 that it was “of critical importance”. That may be an
understatement. Interlocutory skirmishes between the parties prior to the trial
frequently involved CCPL’s pleadings (especially on this point) and Stork consistently
expressed the view that those pleadings did not accord with the subcontract as properly
construed.
[12] The final version of the statement of claim (the Fourth Further Amended Statement of
Claim “FFASC”) was not reached until about the fifth day of the trial. It will assist to
understand the argument if an example of the pleading is set out.
[13] Under the heading “Bulk Earthworks, Raw Water/Evaporator Pond, Gravel Paved
Areas and Site Roads” it is pleaded, in paragraph 7:
“In accordance with the terms set out at paragraph 6 above, and
clause 3.2 of Exhibit D of the construction agreement, Cook’s
undertook the Bulk Earthworks, Raw Water/Evaporator Pond Gravel
Paved Area and Site Roads works in the following quantities, as
determined by reference to the method of measurement set out in
2 [2004] QSC 066.
3 Paragraph 9 of CCPL’s Final Submissions.
-- 7 of 81 --
8
clauses 2.0 and 2.1.3 of part A Subcontract Price Schedule and Bill
of Quantities, Exhibit C to the construction agreement:
(a) 12,635m3 of Engineered Fill for Plant Site Bulk Earthworks
to the final surface as defined in AS 1181-1982 as shown on
for-construction drawing SU-CS-00-D-0050 rev 5; SU-CS-
00-D-0051 rev 4 and SU-CS-00-D-0052 rev 0 from the
commencing surface as defined in AS 1181-1982 as shown
in electronic format on a Digital Terrain Model based Total
Station data produced by Peter Robinson & Associates.
PARTICULARS
The profiles and dimensions of the final surface as defined
in AS 1181-1982 relied on to calculate the quantity of
13,635 m3 of Engineered Fill for Plant Site Bulk
Earthworks are shown on SU-CS-00-D-0050(5), SU-CS-00-
D-0051(4) and SU-CS-00-D-0052(0) with the northerly
marked in orange, the easterly marked in yellow, the batter
slopes marked in pink, the reduced levels marked in blue
and the dimensions marked in purple. The profiles and
dimensions of the commencing surface as defined in AS
1181-1982 are as shown in electronic format on the Digital
Terrain Model based Total Station data produced by Peter
Robinson & Associates and provided to Stork in the course
of the works.”
[14] The clauses which are relevant to this discussion are:
“2.0 MEASUREMENT FOR PAYMENT
The Subcontractor shall execute the work under the Subcontract
and fulfil all Subcontractors obligations thereunder and Stork shall
pay the Subcontractor for the measured quantity of each item of the
work performed under the Subcontract as certified by Stork at the
appropriate rate in the Subcontract Schedule Part A - "Subcontract
Price Schedule and Bill of Quantities".
All items shall be measured nett in-situ to the profiles and
dimensions shown on the Drawings or described in the Scope of
Work and Specification and Subcontractor shall allow for wastage
in the rates for the nett quantities given in the Subcontract Schedule
Part A "Subcontract Price Schedule and Bill of Quantities".
Upon issue by Stork of the 'Approved for Construction' Drawings
for the work and prior to construction of work covered by the
Drawings, Stork and Subcontractor shall jointly review the
Drawings and agree on the rate items applicable to the work shown
on the Drawings.
Measurement of work shall be made in accordance with the
conditions set out hereunder.
3.1 Performance and Payment
The Subcontractor shall execute and complete the work under the
Subcontract.
-- 8 of 81 --
9
Stork shall pay the Subcontractor;
(a) for work for which Stork accepted a lump sum, the lump
sum;
(b) for work for which Stork accepted rates, the sum ascertained
by measurement and determination of the quantities in
accordance with Clause 3.2 and multiplying the quantity so
measured and determined of each section or item of work
carried out under the Subcontract by the rate accepted by
Stork for the section or item,
Adjusted by any additions or deductions made pursuant to the
Subcontract.
3.2 Quantities
Quantities in a Bill of Quantities or Schedule of Rates are estimated
quantities only.
A direction shall not be required to be given by Stork's
Representative by reason of the actual quantity of an item required to
perform the Subcontract being greater or less than the quantity
shown in the Bill of Quantities or Schedule of Rates.
Unless otherwise stated within the Contract, 'actual quantities'
shall mean those quantities measured in accordance with
Australian Standard 1181-1982, as amended from time to time,
from the lines, dimensions and limits shown on the relevant
Contract plans and drawings.
Quantities over and above the actual quantities as a result of
oversupply, over excavation or any other similar reason by the
Subcontractor will not be included in the actual quantities and the
Subcontractor agrees that Stork is not required to pay for these
quantities over and above the actual quantities.”
(emphasis added)
[15] The argument put on behalf of CCPL was that the purpose of clause 2 was to ensure
that Stork only paid for the work that it contracted for; so that, if CCPL inadvertently
over-excavated a particular area, then Stork would not be required to pay for that over-
excavation – it would only pay “to” the dimensions and profiles on the plans. It was
submitted that that was made clear from the definition of “actual quantities” contained
in clause 3.2 of Ex D of the Subcontract.
[16] The basis of CCPL’s argument on the construction point was put during Mr Digby’s
opening when he said:4
“Now, what we say about that clause is that read just on its language, even
without the context which should assist our argument, it's simply saying
that you have to - leave the word "nett in situ" out for the moment - you
have to measure to the profiles and dimensions shown on the drawings.
Now, that is an unexceptional stipulation. What it means is that when
you're working out your measurements, the end point - and the word "to" is
4 T19-T20.
-- 9 of 81 --
10
used - the end point is what's shown on the construction drawings and that's
perfectly workable and perfectly logical because defines the extent to which
you are entitled to be paid.
What it does not say, and we say would be impractical and unworkable -
same thing, I suppose - and repugnant to the scheme of the contract to infer
is that you only measure the profiles and dimensions shown on the
drawings. That is, the for-construction drawings.
In our submission this clause clearly gives scope for the operation of what
one would expect to be the practical situation, that is that you draw upon a
survey, or perhaps another drawing if there was a drawing setting out the
precise details or sufficiently precise details of where you started or where
you stripped to, and then the profiles on the for-construction drawings to
work out the quantities that were relevant. It does not preclude that, and,
indeed, there's no inference, we think, can reasonably - no implication can
reasonably be read into clause 2 to say this somehow confines you to
having reference only in terms of a measurement to the for-construction
drawings. We concede, of course, that the for-construction drawings are a
crucial element of the measurement because they define the extent - they
define what you have got to do but they also define the extent to which you
can expect to be paid for any quantities.”
[17] The process of reasoning employed by CCPL then proceeds in this way:
(a) As the Australian Standard 1181-1982 is referred to in clause 3.2 one
needs to look at certain definitions. Those definitions are:
(i) Original surface: the surface before any work has been
carried out under the contract;
(ii) Commencing surface: (in relation to an item in a Bill of
Quantities) the surface before any work covered by the item
has been carried out;
(iii) Final surface: the surface indicated on the drawings to which
the work described in any item of the Bill of Quantities is
carried.
(b) The reference to the “profiles and dimensions shown on the
drawings” in clause 2 is a reference only to the “final surface”.
(c) Clause 2 should be interpreted as meaning that the quantity is
derived from measuring nett in-situ to the final surface.
(d) As a volume cannot be calculated without knowing three dimensions
then one needs to measure from the “commencing surface” to the
“final surface”.
[18] The reference to measuring from the “commencing surface” was supported by CCPL
by reference to the evidence of Peter Robinson whose firm was contracted in June
1998 to supply the survey management for CCPL’s work on the project. That firm was
also contracted by Stork to supply survey information (but not on these points5 ) for its
relevant interest in the project. Mr Robinson gave evidence that, in his experience,
earthworks are measured initially from the “original surface”, referred to as the
“natural surface” when the area has not been disturbed, to the “commencing surface”
5 T552/20.
-- 10 of 81 --
11
or the “strip surface”. The earthworks quantities, he said, are then measured from the
“commencing surface” to the “final surface”.
[19] CCPL is, then, arguing that the act of measurement referred to in clause 2 is to be
performed by reference not only to the profiles and dimensions shown on the drawings
but also to a measurement obtained through the use of an accepted procedure or
industry standard. In other words, CCPL argues that clause 2 operates by the drawings
providing the end point of a measurement while the beginning is provided by a
measurement obtained elsewhere.
[20] The example of the pleading which is set out above shows that CCPL relies upon the
profiles and dimensions of the “final surface” which is shown on identified plans, but
the “commencing surface” is identified as being drawn from data produced by Mr
Robinson pursuant to a method he described.
[21] The method for measurement which he used can be summarised in the following way:
(a) He measured the irregular original surface and the commencing or
strip surface by using surveying devices that measured the bearing,
distance and vertical angle to a reflective target using an infrared
beam. Such measurements were given unique names and stored in a
computer.
(b) When all the measurements were completed they were downloaded
into specialised surveying software which produced three-
dimensional information for each point using the height and relative
level of the total stations and combined that with the bearing,
distance and vertical angle to each observed point. The software
draws break lines between points with common names – break lines
are lines that define changes of grade, eg, the top and bottom of a
batter. Using that software the surveyor then creates a “digital terrain
model” which is, apparently, better known as a “triangulated
irregular network”. That digital terrain model provides the original or
commencing surface for the calculation of quantities.
(c) The surveyor then uses that digital terrain model which contains the
representations of both the strip surface and the final earthworks
surface to determine an accurate quantity.
[22] Mr Robinson said that the final earthworks surface was created using the dimensions
and profiles shown on the drawings. The result of the calculation made by Mr
Robinson, and upon which CCPL relies, was reached by the creation of virtual surfaces
using the software – the beginning virtual surface created by actual measurement of the
“commencing surface” and the end or “final” virtual surface created by transposing
measurements from the drawings.
[23] CCPL argued that this method was not only available, but also the only method which
complied with the sub-contract. This argument proceeded on the basis that the
drawings did not contain enough information to allow the calculation to be made, viz.,
that the drawings did not contain the details of the levels from which the quantity
should be measured. This was compared with what was said to be shown in the
drawings – the final surface – which was the level to which the quantity could be
measured.
[24] I do not accept that CCPL’s argument demonstrates the correct construction of clause
2.
-- 11 of 81 --
12
[25] Great weight is placed by CCPL on the use of the word “to” in clause 2 which
indicates, in the plaintiff’s construction, that the “profiles and dimensions shown on the
drawings” are only those which can be identified as final surfaces. The plaintiff then
draws from that an implication – an implication which was not pleaded – that one
should then apply an industry practice as described by Mr Robinson in order to
determine the measurement from which one would commence the calculation.
[26] Stork, on the other hand, says that one cannot draw from the use of the word “to” an
entitlement to measure quantities by reference to survey data.
[27] Whenever construction of a clause in a contract has to be undertaken it is always
sensible to construe such a clause in the light of the entire agreement.
[28] The documents which make up the Subcontract commence with the usual recitals
about the nature of the contract and that the Subcontract constitutes the entire
agreement. It also provides a means by which discrepancies or inconsistencies within
the entire document may be resolved. Clause 2 of the formal instrument of agreement
provides:
“The following Documents comprise the whole of the Subcontract
between the Parties, and in the advent (sic) should there be a
discrepancy or inconsistency between the Documents, the order of
precedence in which they are listed may be relied upon to resolve the
issue:
Formal Instrument of Agreement
Exhibit D – General Conditions of Subcontract
Exhibit E – Annexures to General Conditions of Subcontract
…
Exhibit C – Subcontract Schedules
…”
[29] Should there be a discrepancy or inconsistency in the documentation, it is appropriate
to consider other parts of the contract which have been agreed to have precedence over
identified parts of the contract.
[30] Exhibit D of the subcontract contains clause 3.2 (set out above) which provides, in
part:
“Unless otherwise stated within the Contract, 'actual quantities' shall
mean those quantities measured in accordance with Australian
Standard 1181-1982, as amended from time to time, from the lines,
dimensions and limits shown on the relevant Contract plans and
drawings.”
[31] As is obvious, there is no reference to survey measurements taken or any other
measurements which do not appear on any of the drawings or plans. There is reference
only to “quantities measured … from the lines…” etc. As both clause 2 and clause 3.2
are referring to measurement of the same matters there is an inconsistency between the
two clauses in that clause 2 does not refer to measurement “from the lines”. Clause 3.2
is in Exhibit D which has precedence over Exhibit C, which contains clause 2.
[32] The quantities sought to be claimed by the plaintiff are actual quantities as determined
by the contract. In the light of the provisions of clause 3.2, I consider it appropriate to
read clause 2 of Ex C as meaning that one has reference to the drawings and the
drawings only to determine the appropriate measurement.
-- 12 of 81 --
13
[33] The plaintiff, though, says that it is not possible to assess the quantity of work
undertaken by reference only to the drawings. That submission is not supported by the
evidence.
[34] In cross-examination Mr Robinson agreed that it was possible to measure volume from
contour lines on drawings. He said that it was an old method and not a very accurate
method but that it could provide an answer depending upon the degree of accuracy
required by the person seeking a calculation of volume.6
[35] Rodney Alsop gave evidence for the plaintiff. In cross-examination he agreed that
there were methods for measuring quantities apart from those used by Mr Robinson. 7
Gordon Worrell, a witness called by the defendant, said that one method of calculating
volume was by reference to contours which appear on a drawing. 8
[36] Gordon Leck, also called by the defendant, described the manner in which it was
possible, by reference to the drawings in this case to arrive at a calculation of quantity
by reference to the contour lines and other dimensions on the drawings.9
[37] It is likely that the method used by Mr Robinson would afford an accurate measure of
the quantities which were to be removed and which were, in fact, removed. However,
that is not a test which is applied anywhere in the subcontract. If it was impossible to
arrive at an acceptable means of calculating quantity by reference only to the drawings,
then the plaintiff might well have a case to argue for an implication of a particular term
or terms relating to such a means of calculation. The fact that a calculation which is
able to be performed may result in a less accurate conclusion is not, of itself,
something which would cause me to arrive at a different construction of the relevant
clauses. Parties are entitled to agree that a particular method shall be used to achieve a
particular result. In doing so, they may have reasons which are not expressed in the
contract for doing so.
[38] There are other factors which support the view I have reached:
(a) There is no reference in the subcontract or in the Australian Standard
to any requirement for any of the surfaces the subject of a calculation
to be measured by a surveyor apart from the measurements which
appear on a drawing;
(b) There is nothing in the subcontract which requires that Stork is to
pay in accordance with survey measurements taken by a surveyor;
(c) If it was the case that survey measurements were to be taken into
account when calculating volume then one would expect to see in the
contract a definition of the manner in which such survey
measurements were to be taken.
[39] The plaintiff did not plead that any industry standard or practice should be implied into
the contract. Had it done so, I would not have been minded to find any such
implication. Justice Mason’s observations in Codelfa Constructions Pty Ltd v State
Rail Authority of New South Wales10 are apposite in these circumstances:
6 T 558/29-T559/50.
7 T 598/35-T599/14.
8 T 686.
9 T 701/49-T703/19; T703/55-T705/10; T706/33-58; T707/25-37; T753/5-23; T756/17-21; and
T758/57-T759/21.
10 (1982) 149 CLR 337 at 346.
-- 13 of 81 --
14
“For obvious reasons the courts are slow to imply a term. In many
cases, what the parties have actually agreed upon represents the
totality of their willingness to agree; each may be prepared to take
his chance in relation to an eventuality for which no provision is
made. The more detailed and comprehensive the contract the less
ground there is for supposing that the parties have failed to address
their minds to the question at issue. And then there is the difficulty of
identifying with any degree of certainty the term which the parties
would have settled upon had they considered the question.”
[40] Further, the implication of such a term would not have satisfied the conditions
expressed in BP Refinery (Westernport) Pty Ltd v Hastings Shire Council11 and
adopted in Codelfa.12
[41] Stork submitted that I was bound to follow the decision of Moynihan SJA 13 on this
question. I have dealt with that argument in Cook’s Constructions Pty Ltd v Stork Food
Systems Australia Pty Ltd [2008] QSC 178.
[42] The proper construction of cl 2, then, is that it requires calculations to be done by
reference to the profiles and dimensions on the relevant plan and does not allow
reference to some other, unstated measure or means of measuring quantities. Thus, the
evidence from Mr Robinson on this point is irrelevant.
The rule in Browne v Dunn
[43] There are a number of occasions in CCPL’s written submission where it notes that
Stork did not cross-examine on matters contained in Mr Leck’s report. The effect of
this, it was argued, was that the part of Stork’s case which was not put should not be
accepted. The submission was based on the well known principle enunciated in
Browne v Dunn. 14 The rule in Browne v Dunn is often expressed as being the
requirement that a cross-examiner must put to a witness the nature of the case upon
which it is proposed to rely in contradiction of the witness’ evidence. While that is a
correct statement of the rule as it is often applied it is not a complete statement of the
fundamental principle upon which the rule operates.
[44] The basis for the rule has been expressed in the following way:
“The underlying principles are that, in view of the rule against case
splitting, which prohibits a party from calling fresh evidence after
that party's case has closed, it is unfair to a witness to deny the
opportunity of making any explanation open to the witness if a later
invitation to disbelieve or criticise the witness is to be made; that it is
unfair to the party calling the witness if the opportunity for the
witness to proffer an available explanation is denied.”15
[45] I respectfully adopt the analysis of the principles (in a manner relevant to this case)
which is provided by Campbell J in his reasons in West v Mead,16 where he says:
11 (1977) 180 CLR 266 at 282-283.
12 Codelfa at 347.
13 Cook’s Constructions Pty Ltd v Stork Food Systems Australia Pty Ltd [2004] QSC 066
14 (1893) 6 R 67.
15 Cross on Evidence, (Butterworths, Sydney, looseleaf) at [17435].
16 [2003] NSWSC 161.
-- 14 of 81 --
15
“[95] In Browne v Dunn at 70-71 Lord Herschell LC stated an
obligation of procedural fairness which counsel has when cross-
examining a witness who counsel intends to submit should not be
accepted:
‘If you intend to impeach a witness you are bound, whilst he
is in the box, to give him an opportunity to make any
explanation which is open to him; and, as it seems to me,
that is not only a rule of professional practice in the conduct
of a case, but is essential to fair play and fair dealing with
witnesses.’
[96] However, Lord Herschell LC said that there was no obligation
to raise such a matter in cross-examination where it is:
‘… perfectly clear that [the witness] has had full notice
beforehand that there is an intention to impeach the
credibility of the story which he is telling … All I am saying
is that it will not do to impeach the credibility of a witness
upon a matter on which he has not had any opportunity of
giving an explanation by reason of there having been no
suggestion whatever in the course of the case that his story is
not accepted.’
[97] In Allied Pastoral Holdings Pty Ltd v Federal Commissioner of
Taxation [1983] 1 NSWLR 1 Hunt J made a thorough review of later
cases applying Browne v Dunn, and concluded (at 26):
‘I remain of the opinion that, unless notice has already
clearly been given of the cross-examiner's intention to
rely upon such matters, it is necessary to put to an
opponent's witness in cross-examination the nature of the
case upon which it is proposed to rely in contradiction of his
evidence, particularly where that case relies upon inferences
to be drawn from other evidence in the proceedings.’
In the present case, the serving of Ms West's affidavit in chief gave
notice to Ms Mead and her advisers that Ms West proposed to rely
upon the matters contained in para181. Ms Mead took the
opportunity, in her own affidavit in response, specifically to reply to
that allegation. Documents exchanged between the parties to
litigation before the commencement of the trial are able to give
notice that a witness's account of events will be challenged in
particular ways, so that there is no breach of Browne v Dunn if
the witness' account is not challenged in cross-examination. -
Marelic v Comcare (1993) 121 ALR 114 at 120 (pre trial exchange
of medical reports gives adequate notice), Flower & Hart v White
Industries (QLD) Pty Ltd (1999) 163 ALR 744 at [52] (statement of
issues, stated case and service of documentary evidence can give
adequate notice), Stern v National Australia Bank Ltd (2000) 171
ALR 192 at [44] (adequate notice given by pleadings), Seymour v
Australian Broadcasting Commission (1977) 19 NSWLR 219 at 236
per Mahoney JA (adequate notice given by "the nature of the
defendant's case and the particulars given, and otherwise the conduct
of it"), In the Marriage of LC & TC (1998) 23 Fam LR 75 at [39]
(affidavits give adequate notice). Cross On Evidence, 6th Australian
edition, para [17460] footnote 12 says:
-- 15 of 81 --
16
‘… the rule in Browne v Dunn did not apply where all
parties were on notice of the evidentiary issues, eg by reason
of affidavits having been exchanged …’
[98] The consequence of these decisions is that the circumstances
in which Browne v Dunn will require matter to be put to a
witness in cross-examination will depend upon the nature of the
pre-trial preparation there has been, and whether that pre-trial
preparation has been sufficient to give notice to a witness of the
submission ultimately intended to be put to the court. An aspect
of this is that Browne v Dunn will require more extensive cross-
examination in a case where all the evidence is given orally, than is
necessary in a case where the substance of the evidence proposed to
be given by each side is notified in advance by affidavit or statement.
[99] Even when there has been an exchange of affidavits or
statements, the rule in Browne v Dunn will require a cross-
examining counsel to put to a witness the implications which
counsel proposes to submit can be drawn from the evidence, if
those implications are not obvious from the evidence, or from
other pre-trial procedures, or the course of the case. However, the
submission which Ms Bateman seeks to put on the basis of paragraph
181 of Ms West's affidavit in chief involves no drawing together of
strands of evidence to create some overall theory or inference of fact,
but is a submission as to the legal consequence that should be drawn
from the facts plainly asserted in para181. Nothing in the rule in
Browne v Dunn prevents her from putting that submission.”
(emphasis added)
[46] Mr Leck’s report (in its final form) was in CCPL’s possession from August 2007. The
opinions he expresses are clear and must have been well known to CCPL as two of its
witnesses – Mr Robinson and Mr Alsop – were called to give evidence which
commented upon Mr Leck’s conclusions. It follows from the analysis above, that
where Mr Leck expressed a view which was inconsistent with the case advanced by
CCPL then the rule in Browne v Dunn did not oblige counsel for Stork to put that to
the CCPL witnesses. Where the opposing side has notice of the evidence to be given, it
is only those implications which are not obvious from that evidence which need to be
put to the opponent’s witnesses.
[47] Other objections were made to statements made by Mr Leck in his oral evidence which
were otherwise not contained in his report. It was submitted that those statements
should be disregarded where they had not been put to the plaintiff’s witnesses. This is a
brave submission from a party which was so ill prepared that it was still tendering
reports, not having provided them before the trial, in the second week of the trial17 .
There were a few occasions when oral evidence was given by Mr Leck which had not
been put to the plaintiff’s witnesses. In most cases, it was responsive to earlier
evidence which had been given without any notice or without the notice required by
the Uniform Civil Procedure Rules. In any event, I have not found it necessary to base
any findings on such evidence.
[48] CCPL criticised Mr Leck’s evidence in many respects. In particular, it pointed to the
numerous occasions in his written report where he expressed his opinion on the
efficacy of the plaintiff’s pleadings and where he made statements which dealt with
17 Mr Alsop’s report, for example, was tendered on the ninth day of the trial.
-- 16 of 81 --
17
matters outside his areas of expertise. Those criticisms are not unfounded. Mr Leck
often came perilously close to partisan statements and, on occasion, strayed into areas
which would more properly be regarded as the province of submissions and arguments
to be made by counsel. While I accept that his evidence was not pristine so far as total
impartiality was concerned, I am confident that his technical observations were not
coloured and I have ignored those parts of his report which represent opinion he was
not qualified to give.
The Rule in Jones v Dunkel
[49] CCPL submits that adverse inferences should be drawn from the fact that Stork did not
call Messrs Clissold, Lindner or Mazur and only called limited evidence from Mr
Jewell. It places reliance on the so-called rule in Jones v Dunkel18 . I say “so-called”
because the principle enunciated in that case is subject to many exceptions and
variations. Nevertheless, the principle of general application is well-defined in Cross
on Evidence as follows:
“[the]unexplained failure by a party to give evidence, to call
witnesses, or to tender documents or other evidence or produce
particular material to an expert witness may, not must, in appropriate
circumstances lead to an inference that the uncalled evidence or
missing material would not have assisted that party's case. The rule
can operate against parties not bearing the burden of proof and
parties which do bear it as well. The appropriate circumstances exist
where it was within the power of the party to tender the evidence
which was not tendered …”19
[50] One of the exceptions to the general rule arises where there is a reasonable explanation
for the omission to call a witness. It has been put this way:
“The significance to be attributed to the fact that a witness did
not give evidence will in the end depend upon whether, in the
circumstances, it is to be inferred that the reason why the witness
was not called was because the party expected to call him feared
to do so. But there are circumstances in which it has been recognised
that such an inference is not available or, if available, is of little
significance. The party may not be in a position to call the witness.
He may not be sufficiently aware of what the witness would say to
warrant the inference that, in the relevant sense, he feared to call him.
The reason why the witness is not called may have no relevant
relationship with the fact in issue: it may be related to, for example,
the fact that the party simply does not know what the witness will
say. A party is not, under pain of a detrimental inference, required to
call a witness “blind”.20 (emphasis added)
[51] Most importantly, though, is that the rule only applies where there is an issue between
the parties. The matters raised by CCPL as being subject to the rule are all matters
which relate to evidence of oral directions, conversations, statements and so on. They
relate to matters which were not pleaded in support of the plaintiff’s cause of action.
There is no need to call a witness because, for example, he is referred to in
correspondence unless that correspondence is relevant to the pleaded issues. Similarly,
18 (1959) 101 CLR 298
19 At [1215]
20 Fabre v Arenales (1992) 27 NSWLR 437 at 449-50 per Mahoney JA
-- 17 of 81 --
18
simply because a document becomes an exhibit, it does not follow that a person
referred to in it should be called unless the reference to that person is relevant to the
issues as pleaded.
[52] CCPL called a reasonable amount of evidence from its witnesses about discussions
held between those witnesses and employees of Stork or about documents not
otherwise pleaded. That evidence was objected to on the basis that it did not relate to
the pleadings. The general response was that the evidence was part of the “factual
matrix” which allowed the court to understand the real issues. Parties are frequently
allowed to give such evidence. It is often helpful. But it does not follow that, just
because that evidence is given, the inference referred to in Jones v Dunkel can or
should be drawn.
[53] Evidence was received from Stork’s solicitor21 in which he explained why he had not
taken statements from the witnesses the subject of CCPL’s submission on this point.
He said, and it appears reasonable, that he had not thought that they could give relevant
evidence because of the manner in which CCPL pleaded its case. That explanation is,
in my view, strictly unnecessary as I consider that the inferences sought to be drawn
cannot be so drawn as the evidence in question was not relevant to the pleaded issues.
The Defences
[54] Stork pleaded three defences of a general nature. Each of them applied to more than
one of the claims. The findings with respect to these defences dictate the extent to
which further findings and calculations need be made with respect to some of the
claims. I will deal, then, with those defences first, before proceeding to consider each
of the claims.
The Prescribed Notice Defence
[55] The bulk of CCPL’s claim is in two parts: it seeks damages for breach of the
Subcontract constituted by the alleged failure to pay the amount claimed, and, in the
alternative, it seeks an order “pursuant to the Subcontract” (presumably cl 3.1 of
Exhibit D) that those sums be paid.
[56] Clause 51.1 of Exhibit D relevantly provides:
“Stork shall not be liable upon any claim by the Subcontractor in
respect of or arising out of a breach of the Subcontract unless
within 14 days after the first day upon which the Subcontractor could
reasonably have been aware of the breach, the Subcontractor has
given to Stork’s representative the prescribed notice.
….
The prescribed notice is a notice in writing which includes
particulars of all the following;
(a) the breach, act, omission, direction, approval or
circumstances on which the claim is or will be based;
(b) the provision of the Subcontract or other basis for the claim
or proposed claim; and
(c) the quantum or likely quantum of the claim.
This Clause 51.1 shall not have any application to;
21 Ex 61
-- 18 of 81 --
19
(a) any claim for payment to the Subcontractor of any
amount or amounts forming part of the Contract Sum;
(b) any claim for payment for a variation directed by
Stork’s Representative …” (Emphasis added)
[57] It is admitted that no prescribed notice alleging a breach of the subcontract was served
on Stork.
[58] Stork argued that cl 51.1 was mandatory and that a failure to observe its terms
prevented CCPL from making a claim after the relevant period elapsed. CCPL
countered by submitting that the non-damages claim was not affected by this clause
and the claims were otherwise excluded from the provisions of cl 51.1.
[59] The word “claim: is defined in cl 2 of Schedule D as:
“… including any claim, demand, action, proceeding or suit which
subcontractor (sic) may make or bring against Stork … relating to
the construction of the Subcontract or as to any fact, matter or thing
arising out of or in connection with the Subcontract or the work
under the Subcontract including (without limitation) any claim,
demand, action, proceeding or suit seeking payment of money, or
any costs, expenses, loss or damages on any ground whatsoever
including (without limitation) pursuant to the Subcontract, on a
quantum meruit, in quasi-contract, for unjust enrichment and insofar
as is permitted by law pursuant to any other principle of law.”
(emphasis added)
[60] Clause 51.1 will apply when a claim is made which is in respect of, or arises out of, a
breach of the Subcontract. To determine whether the clause applies requires the
identification of the character of each of the claims. Each claim made by CCPL is
premised on it having sought a progress payment and having only received a part
payment from Stork. The FFASC categorises the money sought as damages for breach
of contract or, alternatively, as payment in accordance with the Subcontract (or in the
pedestal reconciliation claim – a separate agreement).
[61] It follows, then, that CCPL’s claim for damages and its alternative claim for payment
in accordance with the Subcontract come within that definition as the first (obviously)
is a “claim … seeking … damages” and the second is a “claim … seeking payment of
money”. Therefore, each claim will be barred unless the exemption applies.
[62] It is submitted, though, by CCPL that the purpose of a provision (like cl 51.1) requiring
a contractor to give notice within a reasonable time of the occurrence of events that he
considers may entitle him to claim additional payment under the terms of the contract
“is to enable the owner to consider the position and its financial consequences …”
(Hudson’s Building and Engineering Contracts 11th ed, Sweet & Maxwell, 1995, para
4.132; see also Giles CJ, Australian Development Corporation Pty Ltd v White
Constructions (ACT) Pty Ltd & Ors (1996) 12 BCL 317 at 338)”. That is, no doubt,
correct; but it is also intended to bring matters to an end should no notice be given by
the appropriate date.
[63] A similar clause was considered by Philip McMurdo J in Bartier v Kounza Investments
Pty Ltd22 where his Honour concluded:
22 [2003] QSC 390.
-- 19 of 81 --
20
“I favour an interpretation which does require the builder to make a
final payment claim as a condition precedent to payment. Clause
27.1 is in mandatory terms and there is a good commercial purpose
in holding the parties to the timely performance of the steps set out in
cl. 27 and 28, because it promotes an expeditious determination of
their ultimate entitlements …”23
[64] I respectfully agree with that approach. That a notice of the type required in cl. 51.1 is
a prerequisite to recovery is supported by other authorities, dealing mainly with clauses
which require a notice before an extension of time can be given, which were
considered, and helpfully summarised, by Besanko J in Decor Ceilings Pty Ltd v Cox
Constructions Pty Ltd (No 2)24. He said:
“[66] There is no doubt that parties can, if they wish, make
compliance with a certain procedure a precondition to an extension of
time by reason of delay or disruption or a claim for loss and damage
resulting from delay or disruption. The question whether the parties
have done that is to be determined as a matter of the construction of
their contract. An intention to exclude the ordinary remedies arising
on a breach of contract must be expressed in clear and unmistakable
terms. (Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol)
Ltd [1974] AC 689 per Lord Diplock at 717–718; Mancorp Pty Ltd v
Baulderstone Pty Ltd (t/as Baulderstone Hornibrook) (No 2) (1992)
60 SASR 120).”
[65] Does the exemption apply? Clearly, it cannot apply to the claims for damages as it only
applies to a “claim for payment”.
[66] Are any of the claims made by CCPL claims for payment to the Subcontractor of any
amount or amounts forming part of the “Contract Sum”? The term “Contract Sum” is
not defined in the Subcontract. CCPL submitted that “the only sensible meaning that
can be given to the words “Contract Sum” is that it refers to the total sum due to the
subcontractor for undertaking the subcontract including any additions or deletions
thereto.”25 No further argument was advanced to support that contention.
[67] Stork referred to the definition (in cl 2 of Exhibit D) of “Subcontract sum” which
provides that that term relevantly means:
“(a) where Stork accepted a lump sum, the lump sum;
(b) where Stork accepted rates, the sum ascertained by
calculating the products of the rates and the corresponding
quantities in the Bill of Quantities or Schedule of Rates;
(c) where Stork accepted a lump sum and rates, the aggregate of
the sums referred to in paragraphs (a) and (b),
including provisional sums but excluding any additions or deductions
which may be required to be made under the Subcontract.”
23 At [40].
24 (2007) 23 BCL 347; [2005] SASC 483. See also Jennings Construction Ltd v Q H & M Birt Pty Ltd
(1986) 8 NSWLR 18; Opat Decorating Service (Aust) Pty Ltd v Hansen Yuncken (SA) Pty Ltd (1994)
11 BCL 360; Leighton Contractors Pty Ltd v South Australian Superannuation Fund Investment
Trust (1995) 12 BCL 38; Australian Development Corporation Pty Ltd v White Constructions (ACT)
Pty Ltd (1996) 12 BCL 317.
25 CCPL’s Closing Submissions [235].
-- 20 of 81 --
21
[68] The entire document governing the relationship between the plaintiff and the defendant
is the “Subcontract”. While it bears that name it is, of course, in ordinary parlance the
contract between them. The Formal Instrument of Agreement (which is the first part of
the document) also provides that:
“The Subcontract Sum is the lump sum of eight million seven
hundred and fifty three thousand three hundred and eighty nine
dollars and eighty three cents ($8,753,389.83) and excludes any
additions or deductions which may be required to be made under the
Subcontract.”
[69] In the absence of a definition I think that the term “Contract sum” should be read as the
sum arrived at by the calculations set out in the definition of “Subcontract sum” which
is the figure referred to in the paragraph above and which is set out on page 13 of Part
A of Exhibit C of the Subcontract. It follows, then, that the term excludes any additions
or deductions contrary to the submission of CCPL. As CCPL is not suing for any
amount contained within that sum (given that its claim is based on extra work) its
claim (subject to what is said below) is not excluded from the effect of cl. 51.1.
[70] CCPL argued that:
“Clause 51 is a notice provision only. Its purpose is to ensure that
Stork has proper notice of claims or potential claims in respect of or
arising out of a breach of the Subcontract within a reasonable time of
such claims arising. Provision of progress claims for work undertaken
under the Subcontract by Cooks satisfies that purpose; and is the very
reason for the exclusion contained in clause 51 relating to claims for
breaches for non-payment of amounts forming part of the contract
sum.” 26
[71] The provision of progress claims does not satisfy clause 51 because that clause is
concerned with notifications of breach of contract, not of demands made in the
ordinary course of the contract.
[72] Are any of the claims for payment based on a variation directed by Stork’s
Representative and, thus, excluded from cl 51.1? Yes, the claims made by the plaintiff
which are for payment for a variation are:
(a) Road Reconstruction;
(b) Contour Drains;
(c) Lime Stabilisation of Site Roads;
(d) Boxing Out for Roadworks; and
(e) Asphalt on Site Roads.
[73] It follows, then, that the claims, other than those referred to immediately above, the
pedestal reconciliation claim and the ammonia spill standby claim, are caught by
clause 51.
Defence relating to Alleged Errors in the Bill of Quantities
[74] Of the various heads under which CCPL makes claims, there are six in which the
entitlement to payment is alleged to arise because of an error in the “Priced Bill of
Quantities”. They are the:
(a) Footings,
26 [237] Plaintiff’s Written Submissions
-- 21 of 81 --
22
(b) Pedestals,
(c) Corrocem,
(d) Suspended Slabs,
(e) Prill Storage Building Structures, and
(f) Crushed Rock to Substations 1 and 2 claims
[75] The “Priced Bill of Quantities” is defined in cl 2 of Exhibit D as:
“… the Bill of Quantities priced and lodged by the Subcontractor
with Stork’s Representative and corrected where necessary from time
to time under Clause 5.3.”
[76] The claims rely upon errors alleged to exist in the Priced Bill of Quantities within the
meaning of cl. 5.4 of Exhibit D. Clause 5.4 relevantly provides:
“If the Priced Bill of Quantities is in error in that it:
(a) contains an incorrect quantity in relation to any item
included therein;
(b) contains an item which should not have been included
therein;
(c) omits an item which should have been included therein;
then;
(i) in the case of Clause 5.4(a) where the item is deficient
in quantity or in the case of Clause 5.4(c) upon
application in writing to Stork’s Representative by the
Subcontractor;
(ii) in the case of Clause 5.4(a) where the item is excessive
in quantity or in the case of Clause 5.4(b) upon
notification in writing to the Subcontractor by Stork’s
Representative,
the lump sum accepted by Stork for the execution of the whole of the
work to which the Bill of Quantities relates shall except when the
value of the error is less than $400, be adjusted by such amount as is
required to correct the error, determined in the manner provided by
Clause 45.6 for the valuation of variations as if the correction were a
variation under the Clause.
The Bill of Quantities shall be deemed to be in error as aforesaid to
the extent that the items and quantities included in it differ from
those required for the execution of the Works in accordance with the
drawings and specification referred to in the Subcontract, measured
in accordance with the method of measurement evidenced by the
Subcontract.”
[77] Stork submits that none of this is available to CCPL because there was not a Priced
Bill of Quantities within the meaning of cl 5.4. Stork’s argument, in summary, was:
“…that the plaintiff’s claims [, which are] premised upon an alleged
error in the Priced Bill of Quantities such that the lump sum accepted
by the defendant for the execution of the whole of the work [should
be adjusted] pursuant to clause 5.4 of Exhibit D [,] suffer from the
fatal flaw that no lump sum was accepted by the defendant for the
execution of the whole of the work. This was a schedule of rates
contract; this means that the defendant agreed to pay for quantities of
work measured from the Subcontract drawings at agreed rates. The
quantities in the Bill of Quantities were only ever estimates and so it
-- 22 of 81 --
23
is simply wrong to say that the defendant agreed to pay an identified
lump sum for the work to be performed.” 27
[78] In support of its argument Stork refers to some of the definitions in the Australian
Encyclopaedia of Forms and Precedents.
[79] A schedule of rates contract is described in the following way:
[1095] Schedule of prices or rates
“In this form of agreement, the contractor agrees to execute the
works for a price to be calculated according to the quantity of
material actually used at an agreed rate. Rather than submitting a
total price for the works, the contractor indicates rates per square
metre, cubic metre or some other form of quantity and is paid for the
actual amount performed.
“This form of contract is commonly used in civil engineering works,
particularly earth and road works where the precise volume or area is
not known before the work commences. Tenders will usually be
submitted on the basis of provisional quantities estimated by the
principal’s quantity surveyor, giving some basis for determining
the tender rates which will no doubt vary depending on the
order of magnitude of the amount of work involved. The total of
the provisional quantities multiplied by the tendered rates provides a
figure to be used in comparing tenders.
“The skill of tendering under such a contract relies on the contractor
estimating more accurately than the principal the amount of
quantities involved, so that the contractor’s rates can be
“manipulated” to result in a similar provisional tender amount to the
other contractors, but one which when the work is actually
performed will provide a greater reward.
“From the principal’s point of view, an accurate comparison of
tenders relies on the provisional quantities being reasonably
accurate.
“This form of contract has the advantage that the principal is to
pay for the amounts required (no more and no less) whereas
under a lump sum contract both the principal and the contractor take
the risk that their preliminary estimates were accurate.” (emphasis
added)
[80] A lump sum contract is described thus:
“[1090] Lump sum contract
In this form of agreement, the contractor commits himself or herself
to execute specified work for a stated “lump sum” or fixed amount.
The lump sum might in some circumstances be adjustable on
account of a rise or fall in the cost of labour and/or materials, or on
account of any variation to the works at the request of the principal,
27 Stork’s Closing Submissions at [12].
-- 23 of 81 --
24
or might include provisional allowances. But generally the
contractor is not entitled to claim further money over the stated
amount.”
[81] In order to determine into what category the Subcontract falls, an analysis of the
relevant provisions must be undertaken.
[82] One of the documents which makes up Exhibit C to the Subcontract is entitled
“Subcontract Price Schedules and Bill of Quantities”. When CCPL refers in its
pleading to the Priced Bill of Quantities it is referring to this document. It then alleges
that, for example, the for-construction drawings require work beyond that
contemplated by the tender process and, therefore, CCPL can have recourse to clause
5.4 for additional payment.
[83] The problem that immediately arises is that cl 3.2 of Exhibit D of the Subcontract
provides that:
“Quantities in a Bill of Quantities or Schedule of Rates are estimated
quantities only”.
[84] That provision is consistent with the definition of a schedule of rates contract set out
above.
[85] In order for CCPL to be successful in its claims for adjustment of the lump sum
pursuant to cl 5.4 it must, first, show that the Subcontract is a lump sum contract. That
requires further analysis of the terms of the Subcontract.
[86] Section 2 of Part A of Exhibit C, provides:
“The Subcontractor shall execute the work under the Subcontract and
fulfil all Subcontractor[‘]s obligations thereunder, and Stork shall
pay the subcontractor of the measured quantity of each item of the
work performed under the Subcontract as certified by Stork at the
appropriate rate in the Subcontract Schedule part A — “subcontract
Price Schedule and Bill of Quantities”.
All items shall be measured net in-situ to the profiles and
dimensions shown on the Drawings or described in the Scope of
work and Specification and Subcontractor shall allow for wastage
in the rates for the net quantities given in the Subcontract Schedule
Part A — “Subcontract Price Schedule and Bill of Quantities”.
Upon issue by Stork of the `Approved for Construction’ Drawings
for the work and prior to construction of work covered by the
Drawings, Stork and Subcontractor shall jointly review the Drawings
and agree on the rate items applicable to the work shown on the
Drawings.
Measurement of work shall be made in accordance with the
conditions set out hereunder.” (emphasis added)
[87] The emphasis on measurement and the application of stated rates to the measured
quantities is consistent with a schedule of rates contract.
[88] Consistent with that emphasis on the application of stated rates to measured quantities
is Clause 3.1 of Exhibit D which provides that the defendant must pay the plaintiff for
work for which the defendant accepted rates:
-- 24 of 81 --
25
“… the sum ascertained by measurement and determination of the
quantities in accordance with clause 3.2 and multiplying the
quantity so measured and determined of each section or item of
work carried out under the Subcontract by the rate accepted by
Stork for the section of item, adjusted by any additions or deductions
made pursuant to the Subcontract” (emphasis added)
[89] Similarly, cl 3.2 of Exhibit D provides, among other things, that:
“Quantities in a Bill of Quantities or Schedule of Rates are
estimated quantities only.
A direction shall not be required to be given by
Stork’s Representative by reason of the actual item required to
perform the Subcontract being greater or less than the quantity
shown in the Bill of Quantities or Schedule of Rates.
Unless otherwise stated within the contract, “actual quantities” shall
mean those quantities measured in accordance with Australian
Standard 1181–1982, as amended from time to time, from the lines,
dimensions and limits shown on the relevant Contract plans and
drawings.
Quantities over and above the actual quantities as a result of
oversupply, over excavation or any other similar reason by the
Subcontractor will not be included in the actual quantities and the
Subcontractor agrees that Stork is not required to pay for these
quantities over and above the actual quantities.” (emphasis
added)
[90] Further, cl 3.3 of Exhibit D provides, among other things, that:
“Where otherwise than by reason of a direction of
Stork’s Representative to vary the work under the Subcontract, the
actual quantity of an item required to perform the Subcontract is
greater or less than the quantity shown in the Schedule of Rates;
(a) where Stork accepted a lump sum for the item, the difference
shall be valued under clause 45.5 as if it were varied work directed
by Stork’s Representative as a variation;
(b) where Stork accepted a rate for the item, the rate shall apply to
greater or lesser quantities provided that where limits of accuracy are
stated in the Annexure the rate shall apply to the greater or lesser
quantities within the limits and quantities outside the limits shall be
valued under Clause 45.5 as if they were varied work directed by
Stork’s Representative as a variation.
….”
[91] During the course of construction there were, as might be expected, additions and
changes made to the original plan for the construction. When this occurred, the
evidence demonstrated that new bill items were introduced and agreed and allocated
new bill numbers. No evidence was adduced which showed that any of the extra or
new work was regarded as an error in Part A of Exhibit C of the Subcontract. On the
contrary, the parties appear to have agreed to treat them as a new bill item in Part A of
Exhibit C. In all the correspondence which was put before the court, I have been
unable to find any clear reference to an alteration of a lump sum payable to CCPL.
That clause 5.4 cannot be relied upon by the plaintiff is demonstrated by other parts of
the Subcontract.
-- 25 of 81 --
26
[92] There are further references to a Bill of Quantities which must be considered.
[93] Clause 2 of Exhibit D sets out the definitions of various terms. It provides that:
“ ‘Priced Bill of Quantities’ means the Bill of Quantities priced and
lodged by the Subcontractor with Stork’s Representative and
corrected where necessary from time to time under Clause 5.3.”
[94] Clause 5 of Exhibit D provides for three alternatives regarding the Bill of Quantities,
namely:
Alternative 1: A Bill of Quantities forms part of the Subcontract only to
the extent provided in the Subcontract.
Alternative 2: A Bill of Quantities shall not form part of the
Subcontract.
Alternative 3: A Bill of Quantities forms part of the Specification.
[95] Exhibit E provides that Alternative 1 applies. Accordingly, a Bill of Quantities forms
part of the Subcontract only to the extent provided in the Subcontract.
[96] Clause 5.2 of Exhibit D provides that, “where there is a Bill of Quantities”, then among
other things:
“(a) CCPL shall lodge it with Stork’s Representative before the
expiration of the time for lodgment stated in the Annexure or
such further time as may be directed by Stork’s
Representative from time to time;
(b) notwithstanding any other provision of the Subcontract, the
CCPL shall not be entitled to payment until CCPL has lodged
the Bill of Quantities.”
[97] Given the provisions of cl 5.2, the time for lodgment in a contract that had a Bill of
Quantities would be essential. But, in Exhibit E (which contains the Annexure to the
General Conditions of the Subcontract it is provided that; “The time for lodgment of
the priced copy of the Bill of Quantities” is “Not Applicable”.
[98] This designation of “Not applicable” in Exhibit E demonstrates that the Subcontract
does not provide for a Priced Bill of Quantities at all.
[99] Further, CCPL adduced no evidence to show that it did lodge a Bill of Quantities with
Stork’s Representative; and it is only if a Bill of Quantities is priced and lodged in
accordance with the Subcontract that the application of clause 5.4 can be justified.
[100] It follows, then, that the Subcontract is not a lump sum contract. It is a schedule of
rates contract. There is, then, no basis for the claims to which this defence applies.
The Queensland Building Services Authority Act Defence
[101] Stork raises the provisions of the Queensland Building Services Authority Act 1991
(“QBSA Act”) in two ways. First, as a complete defence to five of the claims made by
CCPL on the basis that the work done was “building work” within the meaning of the
QBSA Act and CCPL did not hold a relevant licence for that work. Secondly, Stork
makes a counterclaim for a refund of the amounts paid by it to CCPL for that “building
work”.
[102] At the relevant times, s 42 of the QBSA Act prohibited a person from carrying out
building work unless that person held a contractor’s licence of the appropriate class
-- 26 of 81 --
27
under the Act. If a person did carry out such work without the appropriate licence, the
Act denied them any entitlement to “monetary or other consideration” for doing so.
That denial was subject to a capacity to recover “reasonable remuneration” which,
effectively, excluded any profit margin from such a sum. Section 42 relevantly
provides: 28
“(1) A person must not carry out, or undertake to carry out,
building work unless that person holds a contractor’s licence
of the appropriate class under this Act.
(2) For the purposes of this section –
(a) a person carries out building work whether that
person carries it out personally, or directly or
indirectly causes it to be carried out;
(b) a person is taken to carry out building work if that
person provides advisory services, administration
services, management services or supervisory
services in relation to the building work; and
(c) a person undertakes to carry out building work if that
person enters into a contract to carry it out or
submits a tender or makes an offer to carry it out.
(3) Subject to subsection (4), a person who carries out building
work in contravention of this section is not entitled to any
monetary or other consideration for doing so.
(4) A person is not stopped under subsection (3) from claiming
reasonable remuneration for carrying out building work, but
only if the amount claimed –
(a) is not more than the amount paid by the person in
supplying materials and labour for carrying out the
building work; and
(b) does not include allowance for any of the
following—
(i) the supply of the person's own labour;
(ii) the making of a profit by the person for
carrying out the building work;
(iii) materials and labour if, in the circumstances,
the costs were not reasonably incurred; and
(c) is not more than any amount agreed to, or
purportedly agreed to, as the price for carrying out
the building work; and
(d) does not include any amount paid by the person that
may fairly be characterised as being, in substance, an
amount paid for the person's own direct or indirect
benefit.
…
(10) Subsection (4) applies to building work carried out on or
after 1 July 1992, unless the entitlement to payment for the
carrying out of the building work was ….”
28 Section 42 was amended by section 21 of the Queensland Building Services Authority Amendment
Act 1999 which inserted, among other things, subsections 4 and 10 into section 42. The effect of that
was to give s 42 (4) a retrospective effect such that it applies to the events dealt with in this action.
-- 27 of 81 --
28
[103] The definition of “building work” was contained in Schedule 2 of the QBSA Act. It
provided that “building work” means:
“(a) the erection or construction of a building; or
(b) the renovation, alteration, extension, improvement or repair
of a building; or
(c) the provision of lighting, heating, ventilation, air-
conditioning, water supply, sewerage or drainage in
connection with a building; or
(d) the demolition of a building; or
(e) any site work (including the construction of retaining
structures) related to work of a kind referred to above; or
(f) the preparation of plans or specifications for the
performance of building work; or
(g) any work of a prescribed kind;
but does not include work of a kind excluded by regulation from the ambit of
this definition.”
[104] The QBSA Act defined “building” as including “any fixed structure”29 . During the
times material to this action the Act did not define the meaning of the terms
“drainage”, “site work”, or “retaining structures”.
[105] It is contended by Stork that the following claims represent work which comes within
the definition of “building work” and for which a licence was required:
(a) Quantities of Footings;
(b) Pedestal claim;
(c) Corrocem claim;
(d) Suspended slabs; and
(e) Prill storage building structures.
[106] CCPL admits that it did not hold any relevant licence at the material times but denies
that any of its claims relate to the performance of “building work”.
Quantities of footings
[107] CCPL’s claim for quantities of footings only relates to certain footings which are set
out in Attachment C to the statement of claim. The evidence which was given about
those footings was to the effect that, in general, a footing is “generally considered to be
a bigger arrangement, [a] more substantial arrangement” than a pedestal.30 In order to
construct the footings, the plaintiff would need to excavate some earth, create
formwork, place reinforcement, pour the necessary amount of concrete and, on
occasions, backfill part of the excavation in order to bring the ground surface level
with the footing. Mr Eames, who gave evidence for CCPL, frequently referred to
footings as “concrete structures”.31
[108] A footing is a necessary and integral part of other items of construction. It is, by
definition, something which is created so that something else may be built. For
example, on this site, the footings which were built were to be used as the basis for
other structures on the site such as buildings, pedestals and suspended slabs. As they
formed the basis for other structures, the construction of the footings falls within the
29 Schedule 2, QBSA Act.
30 T 237.
31 T 230/20-31 and T231/51-58.
-- 28 of 81 --
29
definition of “the erection or construction of a building”, or “any site work (including
the construction of retaining structures) related to work of a kind referred to above”, or
both, as those terms are used in the definition of “building work”. I do not doubt that a
footing is a “fixed structure”.
[109] There is, in the definition of “building work”, an exclusion of certain work, namely,
“work of a kind excluded by regulation from the ambit of this definition”.
[110] Section 3A of the Queensland Building Services Authority Regulation 1992 provides
that the following work, among others, is excluded from the ambit of the definition of
“building work”:
“…
(t) the installation of manufacturing equipment or equipment
for hoisting, conveying or transporting materials or products
(including primary produce), but excluding the installation
of fixed structures providing shelter for the equipment;
…
(x) work consisting of earthmoving and excavating;
…”
[111] The exclusion in s 3A(1)(t) has no application under this head. Section 3A(1)(x) does
not, in my view, apply to the circumstances surrounding the claim for footings in this
case. The exclusion in s 3A(1)(x) is for work “consisting” of earthmoving and
excavating. The work in this case, though, consisted of more than just excavating. The
word which needs to be analysed is “work”. If one was to ask what work was involved
in the creation of footings, the answer would not simply be: “excavating”, but would
include all the other activities referred to above. For “work” to consist of “excavating”,
it means that a distinct and identifiable endeavour is made up solely of excavating.
That is what the word “consisting” requires in these circumstances. If it was to be
construed in any other way, then it would be inconsistent with the scope of work for
which a concreting licence is required pursuant to Part 5 of the Regulation. Clause 2 of
Part 5 of the Regulation provides that a concreting licence includes the scope of work
dealing with “excavation of footings” and the “placing and fixing of reinforcement to
footings”. It would be inconsistent with the provisions of the Act and the Regulation
for a licence to be required for work which was excluded from the definition of
“building work”.
[112] The work which makes up the footings claim constituted “building work” within the
meaning of the QBSA Act and, in the absence of the relevant licence, CCPL is not
entitled to monetary or other consideration for doing that work.
Pedestal Claim
[113] CCPL’s claim in this area related to the construction of “columns, piers and plinths”
being similar types of structures having a plan area of one square metre or less. These
were distinguished from footings on the basis they were very small structures which
actually became a part of the footings structures.32
[114] The construction of a pedestal required the erection of a steel cage (which is the
reinforcement inside the pedestal), the connection of that cage to a footing or other
supporting structure, the tying off of that reinforcement and then the building of timber
32 T 242/11-23 and T232/37-46.
-- 29 of 81 --
30
formwork into which the concrete would be poured. 33 Mr Eames said that plinths were
“actually part of the footing structure”34 . He also explained that: “A “plinth” is a
structure, dimensions of like of a pedestal, but placed upon an existing structure,
existing concrete structure. Whereas a pedestal is generally considered to be a separate
independent structure. The – both the idea of pedestals - the issue of pedestals and
plinths are closely related because of the likeness in the type of construction and the
quantity of work involved.”35
[115] The building of the pedestals involved the erection or construction of a fixed structure.
Even though, relative to other parts of the work, they were small structures they,
nevertheless, constituted “building work”. Those pedestals which were attached to
footings would come within the scope of work of a concreting licence (“placing and
fixing reinforcement to footings”) as well as coming within the general definition of
“building work”.
[116] The work which makes up the pedestals claim constituted “building work” within the
meaning of the QBSA Act and, in the absence of the relevant licence, CCPL is not
entitled to monetary or other consideration for doing that work.
Corrocem claim
[117] Corrocem was an additive used in the concrete placed in the ammonium nitrate
building. It acted as a means of protecting the concrete floor from the various corrosive
chemicals which were to be used in that building. There was considerable evidence as
to the effect of Corrocem as an additive and to the manner in which it needed to be
placed in a controlled temperature and not in the heat of the day. I can see no reason
why it would not be regarded as being part of the scope of work for a concreting
licence as it would certainly come within clause 2(7) of Part 5 of the Regulation as it
involved: “Placing, vibrating, levelling and finishing of concrete including all special
finishes”.
[118] It is pointed out by Stork that as the ammonium nitrate building was a “building”
within the meaning of the QBSA Act, the Corrocem claim would also be covered
because it relates to work which can be described as the erection or construction of a
“building”.
[119] The work which makes up the Corrocem claim constituted “building work” within the
meaning of the QBSA Act and, in the absence of the relevant licence, CCPL is not
entitled to monetary or other consideration for doing that work.
Suspended slabs
[120] The suspended slabs were required for two buildings on the site. Originally the
intention was that these slabs would be at ground level but, after the revision of for-
construction drawings, the slabs were to be erected several metres in the air supported
by columns. The manner in which they had to be built was described by Mr Eames in
the following way:
“There had to be scaffold towers built up to the height where the
suspended slab was to be placed. There was – fairly strong steel
33 T 372.
34 T 232
35 T 245-6
-- 30 of 81 --
31
bearers had to be put through. Formwork had to be placed across
those to support the suspended slab and the weight of the concrete till
it was set. … All the steel reinforcement had to be craned up into that
area. And additional to a slab on ground the sides were much higher
and had to be formed up.”36
[121] The suspended slabs and columns supporting them were obviously “fixed structures”.
They could also be considered as being a part of other fixed structures of which they
formed an integral component – the ammonia synthesis unit and the turbine generator
building.
[122] They also come within clause 2(6) of Part 5 of the Regulation: “Placing and fixing …
suspended slabs …”.
[123] The work which makes up the suspended slabs claim constituted “building work”
within the meaning of the QBSA Act and, in the absence of the relevant licence, CCPL
is not entitled to monetary or other consideration for doing that work.
Prill storage building
[124] As its name suggests, the prill storage building was a structure designed to store the
prill manufactured at the site before it was removed to be processed elsewhere. The
building was quite substantial. It was described as being “built like a fortress”.37 It was
built in that way because it was designed to resist the effects of an explosion – a
possibility given the nature of the prill.
[125] The building had a concrete floor of varying thicknesses. Its internal walls were six
metres in height, some 25 to 26.5 metres in length and 450 millimetres thick. The slab
was thickened in various places and there was a footing established for silo storage
together with a truck loading station.
[126] This is the only structure about which CCPL says anything in its submissions on this
point. It refers to the excavation of a substantial amount of earth as part of the
construction of the footing for the building and submits that such work comes within
the ambit of s 3A(1)(x) of the Regulation. However, for the reasons set out above, that
subsection does not apply when the excavation is a necessary part of a larger building
and is part of the construction of the building itself. CCPL also points to the “truck
loading station” as coming within the ambit of s 3A(1)(t) of the Regulation on the basis
that it is “installation of equipment for hoisting, conveying or transporting materials or
products …”. CCPL’s submission is that the truck loading station is a piece of
equipment into which prill is placed and from which it is removed and loaded into
trucks for transport out of the plant.
[127] As I understood the evidence, the truck loading station was an integral part of the prill
storage building and consisted of a concrete area in which trucks could wait in order to
be loaded. It did not include any equipment which would be used to hoist, convey or
transport materials. When this matter was argued before Moynihan SJA he gave
consideration to whether this work was “building work”. While, of course, a final
judgment was not given in those circumstances, his remarks fortify my conclusion that
the work done was not outside the definition of “building work”:38
36 T 279/10-30.
37 T 287.
38 Cook’s Construction Pty Ltd v Stork ICM Australia Pty Ltd [2004] QSC 066.
-- 31 of 81 --
32
“ [70] The prill store is essentially a building to store product of
the process for which the project works were built. There is
no occasion to doubt it is a building and that the plaintiff’s
work included aspects of its erection or construction; see
Multiplex Constructions Pty Ltd v Rapid Contracting Pty
Ltd (In Liquidation) (Shepherdson J (unreported) [1998]
QCA 10856/98). In that case, the erection of a prefabricated
panel as part of the construction of a building was sufficient
to satisfy s 42.
[71] The fact that earthworks and excavation were carried out to
prepare the building site, or that provision was made for
equipment to hoist and convey the prill does not make what
was otherwise building work become something else. That it
was necessary to store the prill and so to provide a store
building does not make it integral to the manufacture
process so as to except it from the Act. Finally, that the
plaintiff did not do all the building work for the prill store
does not change the character of the building work the
plaintiff carried out.”
[128] The work which makes up the prill store claim constituted “building work” within the
meaning of the QBSA Act and, in the absence of the relevant licence, CCPL is not
entitled to monetary or other consideration for doing that work.
The Claims
(i) The Bulk Earthworks Claim
[129] In paragraphs 6 to 15 of the FFASC the plaintiff sets out its claim with respect to bulk
earthworks. It claims that it performed work under this heading and made progress
claims in the sum of $851,017.21 but that Stork has only paid the sum of $708,119.76.
The plaintiff, therefore, is claiming the sum of $141,367.45 plus interest.
[130] The work performed under this heading involved the placement of fill, the excavation
of earth for the creation of ponds, the laying of particular types of sub-base on site
roads and the laying of a particular type of sub-base on gravel paved areas.
[131] In paragraph 7A of the FFASC, CCPL claims that Stork was obliged to pay it pursuant
to clause 3.1 of Ex D of the Subcontract. Clause 3.1 provides that for work for which
Stork accepted rates (of which this is one type of work) Stork was to pay CCPL a sum
ascertained by measurement and determination of the quantities in accordance with 3.2
and then by multiplying that amount by an identified rate. As is noted above, clause 3.2
requires that quantities are to be measured from the lines, dimensions and limits shown
on the relevant contract plans and drawings.
[132] The plaintiff’s claim in this area is based upon the calculations made by Mr Robinson
which have already been considered. CCPL relies upon his measured quantities of:
• 12,635 cubic metres for engineered fill
• 126,947 cubic metres for bulk excavation of raw water evaporation ponds
• 87,503 cubic metres for engineered fill on raw water evaporation ponds
[133] Mr Alsop, in his evidence, relies upon those measurements for his calculation. While
he says that the method used by Mr Robinson is an industry-acceptable method, there
-- 32 of 81 --
33
is, of course, no debate about whether it is an industry-acceptable method or not; the
debate was whether or not the use of that method was consistent with the Subcontract.
[134] One matter that is emphasised by Mr Alsop’s report is that he was unable to obtain any
printout of the actual levels obtained to undertake a “logic check” of those items. One
of the major problems with Mr Robinson’s report is that no one was able to check his
calculations because vital data was contained on an old computer which, shortly before
the trial, had ceased to function. Part of the difficulty here arises out of the very late
change in pleading by CCPL and the failure to disclose documents relevant to that
pleading at an earlier stage. As a result, neither Stork nor any of the experts were able
to assess or comment upon the accuracy of any of the calculations made by Mr
Robinson.
[135] Apart from the fact that Mr Robinson’s calculations are not made in accordance with
the requirements of the Subcontract, the weight which could be afforded to his
calculations was substantially reduced by the absence of material which justified his
conclusions and measurements. Ordinarily, in a case like this, one would expect
evidence to be given which followed the process of measurement from beginning to
end and in which the relevant records were proved so that an assessment of their
accuracy could be made.
[136] As the only computer which could operate the particular software used by Mr
Robinson in arriving at his conclusions was no longer working, it was impossible for
him to demonstrate the manner in which the program worked and, although he was
able to display in court the 12D model upon which he relied, that model did not contain
all of the data which he said had been entered into the program39 and, more to the
point, without the original total station data no one could verify the information
displayed by that 12 D model.40
[137] CCPL, in support of its claim that it has issued progress claims on this matter and
generally, relies upon Exhibit 2. Exhibit 2 consists of two lever arch folders containing,
in total, over 600 pages which appear to be progress claims and associated documents.
I was taken to some pages of that exhibit during submissions but I was told, in final
submissions, that I could “go through and see that they are all being paid for the
amount that the plaintiff and its surveyor are surveying and measuring and
acknowledged and formally paid by the defendant”. A submission which is, in essence,
an invitation to a judge to accept a large number of documents and to examine them in
order to determine whether or not a claim has been made out is an invitation I will not
accept. I agree with the remarks of Adams J in Smith v Commonwealth of Australia41
where, at [67] he said:
“The widespread habit of tendering vast quantities of paper and then
making submissions that refer in generalities to the evidence or parts
of it is quite inappropriate. It requires judges to trawl through the
material to assess which parts actually support the submissions and,
in effect, to construct the case that counsel has not done – or cannot
do. This is not a proper role for a judge to undertake.”
[138] As Mr Robinson’s evidence has not been accepted, and that was the only basis upon
which this claim was made, the claim is unsupported and must be dismissed.
39 T 555/45-54.
40 T 556/16-19.
41 (2006) NSWSC 689.
-- 33 of 81 --
34
(ii) The Road Reconstruction Claim
[139] This claim is pleaded in paragraphs 16 to 28 of the FFASC. It is a claim for
$14,998.20, being the balance of the amount owing from a claim of $71,036 for the
work performed between December 1999 and November 2000.
[140] The work that was required was to carry out reinstatement of various internal plant
roads.
[141] Mr Eames’ unchallenged evidence was that road reconstruction was required for two
reasons: first, because of a change in design and, secondly, because of the damage
which was occurring to completed works from heavy machines being run over roads
which were not intended to carry those heavy machines. Stork concedes that CCPL
was required to carry out those works pursuant to a site instruction and thus the work
amounted to a variation.
[142] Clause 45.1 of the Subcontract provides that CCPL shall not “vary the work under the
Subcontract except as directed by Stork’s Representative or approved in writing by
Stork’s Representative under clause 45.”
[143] The terms of the variation as set out in paragraph 17 of the FFASC are conceded to
have been established by Stork and the appropriate rate for the work done of $28 per
cubic metre is not in dispute. The dispute arises in three ways:
(a) Has the plaintiff proved that it performed work in an amount of 2,537 cubic
metres?
(b) Did CCPL claim $71,036 for that work?
(c) Has Stork only paid $56,037.08 leaving an outstanding balance of
$14,998.20?
[144] When the arrangements were made for the work to be done, it was agreed that:
“Payment will be made at machine excavation rates as per Table B4.
The surveyor will calculate quantities excavated and removed.
Payment will be on the calculated quantities as presented on his
certified sheets at the Table B4 rates.”42
[145] Mr Robinson’s calculations are contained in Ex 4443 and show an amount of 2,537
cubic metres as the relevant entry for this claim. The restrictions on the method of
measurement referred to above do not apply in this part of the claim. The variation
provided that the “surveyor will calculate quantities excavated and removed”. I accept
that CCPL has established that it performed work in an amount 2,537 cubic metres.
[146] Stork has paid CCPL $56,037.08.44
[147] What is not so clear is the amount which CCPL has claimed from Stork. In paragraph
21 of the FFASC, CCPL alleges that in or about the period November 1999 to April
2000 it claimed from Stork the sum of $71,036 or parts thereof in respect of the road
reconstruction works. It particularises seven progress claims in support of that
allegation. Those particulars are:
1. Item 3.7.1 of Progress Claim No. 18 dated 6 December 1999;
2. Item 3.7.1 of Progress Claim No. 19 dated December 1999;
42 Ex 44 – Letter CCPL to Stork 29.10.99, accepted by Stork by letter of 4.11.99.
43 Tab – Road Reconstruction, Certificate 30.3.00.
44 Admission by Stork in its final submissions at [302].
-- 34 of 81 --
35
3. Item 3.7.1of Progress Claim No. 20 dated 4 February 2000;
4. Item 3.7.1 of Progress Claim No. 21 dated 28 February 2000.
5. Item 3.7.1 of Progress Claim No. 22 dated 28 February 2000.
6. Item 3.7.1 of Progress Claim No. 23 dated 28 February 2000.
7. Item 3.7.1 of Progress Claim dated 6 November 2000.
[148] It is not easy to determine what is intended by those particulars. The references appear
to be incorrect. For example, progress claim No 18 (contained in Exhibit 2) is dated 9
November 1999. It may be that the schedule attached to the letter of 9 November 1999
is the source of the date as it appears to have been created at 8.37am on 6 December
1999. Similarly, progress claim No 22, which is attached to a letter dated 8 April
2000, appears to have been created at 2.57 pm on 28 February 2000 or, perhaps, that is
the date on which it was printed for some other purpose. Finally, there is a reference to
item 3.7.1 of a progress claim dated 6 November 2000. I have been unable to find any
such claim. It appears, from Exhibit 61, that what is described as “progress claim dated
6 November 2000” was, in fact, a letter from CCPL to Stork regarding claims made by
CCPL that there were overdue amounts for payment outstanding from Stork. It
contains a series of measurements by Mr Robinson with respect to the road works and
associated activities and in appendix B to the letter it is asserted that the amount of
$71,036 was the total cost of the project based on 2,537 cubic metres at $28 a cubic
metre. Those figures are inconsistent with the claims made in progress claim No 22 in
which it is claimed that 2,789 cubic metres were removed with a consequent cost (at
$28 a cubic metre) of $78,092.
[149] The figure of 2,789 cubic metres appears to be derived from a measurement contained
in a letter from Mr Robinson to CCPL of 30 March 2000.45 The figure of 2,537 cubic
metres appears to have been taken from another letter from Mr Robinson to CCPL of
31 October 2000.46
[150] It is not entirely clear but it is more likely than not that no progress claim was made
with respect to this issue in the sum of $71,036. The higher figure which appears in the
letter of 6 November 2000 does not correlate with the particulars provided with respect
to this part of the claim.
[151] The material which has been exhibited is unclear and does not support the assertion
that the amount claimed was, in fact, claimed. Nevertheless, as cl 51.1does not apply to
this claim, CCPL is not precluded from pursuing it. It has established its entitlement to
the sum of $14,998.20.
(iii) The Contour Drains Claim
[152] This claim is pleaded in paragraphs 29 to 41 of the FFASC. It is a claim for $3,290.69
being the balance of the amount owing from a claim of $17,064.14 for the work
performed constructing contour drains.
[153] The claim arises out of a variation requested by Stork for CCPL to excavate and
construct open earth contour drains in accordance with certain identified drawings.
[154] The plaintiff relies on Mr Robinson’s report to support its claim. He says that his
calculation – that the relevant volume was 4,331 cubic metres – was determined by
45 Exhibit 61, p 19.
46 Exhibit 61, p 18.
-- 35 of 81 --
36
surveying the original surface prior to excavation and then referencing that data to the
plans identified in the particulars pleaded on this part of the claim. 47 That method,
though, is not the method pleaded as the means of determining the relevant volume.
[155] The plaintiff also relies on Mr Alsop’s report48 but he, relying solely on the plans, only
confirms the length of the drains as being 2,779 metres and then calculates a minimum
theoretical volume (1,729 cubic metres) and a maximum theoretical volume (3,335
cubic metres). Thus, his theoretical maximum volume is about 1,000 cubic metres less
than that calculated by Mr Robinson.
[156] The plaintiff has not established that it performed the work to the extent pleaded or as
measured in the manner pleaded. This part of the claim fails.
(iv) The Lime Stabilization of Site Roads Claim
[157] This claim is pleaded in paragraphs 42 to 53 of the FFASC. It is a claim for $35,033.40
being the balance of the amount owing from a claim of $153,857.40 for the work
performed under this head.
[158] Pursuant to Variation 01849 dated 24 November 1998 Stork required CCPL to provide
additional labour, materials, equipment and consumables and to spread lime on the sub
base of the roads depicted on certain drawings. The mixing of lime into the sub base
provides a harder base.
[159] It was agreed that the price for the work was $10.60 a square metre for the supply,
mixing and spreading of the lime plus $2,500 for mobilisation.
[160] CCPL alleges that the amount for which it should be paid in accordance with the terms
of the variation is 14,279 square metres. Stork denies that and, in paragraph 40 of the
FFADC, pleads that “the quantity derived from the drawings as pleaded by the Plaintiff
in its statement of claim, and as measured in accordance with the Subcontract, is
13,318m2.”
[161] Thus, the area of debate (as with so much of this case) is about the particulars and the
manner of measurement. CCPL sought to explain the difference in the amount by
referring to Site Instruction 103 and to instructions given by Mr Clissold (Stork) to Mr
Eames (CCPL). Neither the site instruction nor the oral instructions were pleaded and
so CCPL cannot rely on them to justify its claim in excess of the amount of 13,318
square metres. That area appears, also, to have been agreed upon by Mr Robinson and
Mr Leck in their joint report50 after the deletion of the 813 square metres which was
the subject of the site instructions.
[162] It follows, then, that CCPL is entitled to succeed on the admitted area of 13,318 square
metres. The total owing, then, is $143,670.80 less the amount paid of $118,824, that is,
$24,846.80 and that is the amount which CCPL may recover.
47 Ex 34, p 18.
48 Ex 39, p 5.
49 Ex 44, Lime Stabilisation Tab.
50 Ex 36.
-- 36 of 81 --
37
(v) The Boxing Out for Roadworks Claim
[163] This claim is pleaded in paragraphs 54 to 65 of the FFASC. It is a claim for $3080
being the balance of the amount owing from a claim of $78,092 for the work
performed under this head.
[164] It is agreed on the pleadings that in late May or early June 1999 Stork requested CCPL
to vary the terms of the construction agreement and CCPL agreed to do so in order to
include work entailing the excavation of material between the bulk earthworks level
and the road box level. This was pursuant to what is referred to as variation 145. It is
also agreed that the rate for removal of earthworks arising from boxing out was $28 a
cubic metre. The defendant admits that it has paid CCPL the amount of $75,012 for
this work.
[165] As with so many of these claims Stork denies the quantity alleged by CCPL on the
basis that the claimed quantity “…cannot be measured from the drawings as pleaded
and particularised by the plaintiff”. Both parties agreed that the issues for
determination under this head are whether:
(a) CCPL’s quantities as claimed have been measured in accordance with the
method of measurement, and
(b) Did CCPL in fact carry out the variation in the quantity of 2,789 cubic
metres as shown on the for-construction drawings.
[166] In its submissions Stork argues that a fact in issue is whether variation 145 required the
plaintiff to carry out the works by reference to the for-construction drawings identified
in paragraph 56 of the FFASC. That is not an issue that arises on the pleadings.
Paragraph 56 pleads that the work was completed in the amount of 2,789 cubic metres
and that that amount was determined by reference to the method of measurement set
out in clauses 2.0 and 2.1.3 of part A of exhibit C to the Subcontract. Those clauses, in
turn, require reference to for-construction drawings as they are the drawings from
which measurements are to be taken under those clauses. It is not pleaded nor was it
proved that variation 145 required the plaintiff to carry out the works by reference to
those drawings. The document which was tendered with respect to variation 145 is a
letter from CCPL to Stork to 11 July 199951 which refers to the volume of detailed
excavation over and above the earthworks excavation removed when boxing out for
the roads. That variation request, though, is only in the amount of 1,450 cubic metres
and is supported by a certificate from Mr Robinson. In his report52 Mr Robinson says,
using the for-construction drawings, that the quantity which can be calculated from the
drawings is 2,789 cubic metres.
[167] There was no explanation for the difference between the amount claimed in the letter
of 11 July 1999 (variation request number 145) and the amount claimed in the
statement of claim. In the evidence of Peter Young53 he says that the quantity referred
to in that letter came “from Peter Robinson’s survey”. That is supported by the
annexure to that letter being the certificate from Mr Robinson on that item. Mr
Robinson did not explain how he came to that figure which is significantly less than
the quantity he arrived at by reference to the for-construction drawings. In his report54
Mr Robinson refers to some calculations relating to road reconstruction and says that
51 Ex 33, tab 1.
52 Ex 34, p 19.
53 T 477 l 48.
54 Ex 34 p 16.
-- 37 of 81 --
38
the claim related to “boxing out and removal of damaged material from site roads”. In
that part of his report he says that the quantity of material removed was 2,537 cubic
metres.
[168] Mr Leck, in his report,55 states that the claim involves the removal of material from
below the gravel placement level, mixing it with lime and replacing it in a compacted
form. He goes on to say that he cannot tell whether any duplication has occurred
without actual levels.
[169] In circumstances where a qualified surveyor has, at the time the work was undertaken,
certified that the amount of material involved in the boxing out work was 1,450 cubic
metres and then some eight years later arrives at a different figure, I think that it is
appropriate to accept the figure which was calculated at the relevant time. That means
that this claim must fail as the amount involved, according to the original estimation, is
less than the amount claimed by CCPL in these proceedings.
(vi) The Asphalt on Site Roads Claim
[170] This claim is pleaded in paragraphs 66 to 77 of the FFASC. It is a claim for $52,787.70
being the balance of the amount owing from a claim of $230,657.70 for the work
performed under this head.
[171] Stork concedes this claim.
(vii) The Quantities of Footings Claim
[172] This claim is pleaded in paragraphs 96 to 113 and in attachment C of the FFASC. It is
a claim for $7,991.50 being the balance of the amount owing from a claim of
$77,090.36 for the work performed under this head.
[173] It was a term of the agreement between the parties that CCPL would construct slab and
pile footings for the nitric acid plant buildings at the following rates and in the
following quantities:
Works Rates Quantities
Footing
Excavation
$32.16 109m3
Formwork $80.13 48m2
Concrete $490.57 108.5m3
[174] The plaintiff’s claim under this heading is expressed in the alternative. First, the claim
is made pursuant to clause 5.4 of Ex D of the Subcontract on the basis that the bill of
quantities is deemed to be in error for the purposes of that clause to the extent that the
items and quantities included in it differ from those required for the execution of the
footings work in accordance with the drawings and specifications referred to in the
Subcontract and measured in accordance with the method of measurement required in
the Subcontract. The error, according to CCPL, is that the bill of quantities contains an
incorrect quantity in relation to item 6.7.8 of the footings bill of quantities and omits
other items, being items 6.4.45, 6.4.49, 6.4.64, and 6.4.65. In consequence, CCPL
pleads that, upon application in writing to Stork, the lump sum accepted by Stork for
the execution of the whole of the work to which the bill of quantities relates should be
55 Ex 53.
-- 38 of 81 --
39
adjusted by such amount as required to correct the error determined in the manner
provided for by clause 45.5.
[175] In order to succeed on the claim relating to the bill error, CCPL must show that it
complied with the requirements of clause 5.4(c)(i) or (ii). Those subclauses require,
when a bill error is alleged, that an application in writing be made by CCPL to Stork’s
representative. The document identified as proving compliance with that requirement is
particularised in paragraph 103 of the FFASC. That document became Exhibit 15. It is
not a document which has any bearing on this part of the plaintiff’s claim. It relates
solely to the use of the additive Corrocem (which is dealt with elsewhere in these
reasons). It follows, then, that the claim based upon a bill error cannot be maintained.
[176] Secondly, the alternative form of the claim is that Stork had to pay CCPL (for work for
which it accepted rates) the sum ascertained by measurement and determination of the
quantities in accordance with clause 3.2 and by then multiplying the quantities so
measured and determined of each section or item of work carried out under the
Subcontract by the rate accepted by Stork for that section or item (see clause 3.1 of
Exhibit D of the Subcontract). It is then said that the footings constructed by CCPL as
measured in accordance with clause 2 of Part A of Exhibit C of the Subcontract
resulted in the total value of the constructed new footing quantities being $77,090.36.
CCPL then says that it applied to Stork for adjustment of the lump sum accepted by
Stork for the whole of the work to which the bill of quantities relates. In the particulars
of that part of the pleading Stork refers to a facsimile transmission dated 23 June 1999.
The only document bearing that date which is a facsimile transmission from CCPL to
Stork is Exhibit 15. It has no relevance to this claim. It relates solely to the claim
concerning the use of the additive Corrocem.
[177] There are five items described in Attachment C to the FFASC which are in issue. They
are:
Item 6.4.45 Steam Reformer Footings
Item 6.4.49 KO Drum (Air Separation Unit)
Item 6.4.64 Turbine Generator Building
Item 6.4.65 Ammonia Storage Pipe Supports, Steam Reformer Pipe
Supports
Item 6.7.8 Nitric Acid Plant Building (Slabs)
[178] On the plaintiff’s case, it was overpaid for Item 6.4.64 and so it need not be considered
further on this point.
[179] The parties differ as to the appropriate rates and the quantities involved for each of the
other items in the following ways.
Item 6.4.45 Steam Reformer Footings
[180] CCPL says that the quantity was 3.24 cubic metres at $55 a cubic metre with a cost of
$178.20. Stork says that the quantity was 3.46 cubic metres at $16.08 a cubic metre
with a cost of $55.64. There is an amount of $122.56 said by CCPL to be owing.
[181] With respect to the dispute about the quantity involved, I accept the evidence of Mr
Robinson. His report56 demonstrates that he referred to the pleaded plans in arriving at
his calculated volume. Mr Leck57 arrives at a different conclusion but differs by only
56 Ex 34, pp 21-22.
57 Ex 53, p 9 of Appendix B.
-- 39 of 81 --
40
.22 of a cubic metre. I accept Mr Robinson on the basis of his closer association with
the project and knowledge of the relevant plans.
[182] With respect to the appropriate rate, I accept Mr Leck who points out that there is a
specific rate in the Subcontract Schedule of Rates identifying it as “Reformer – Footing
Excavation”.58 That rate should apply in preference to the one promoted by Mr Alsop
who based his opinion on the view he held as to the need for hand excavation. That
was not a topic upon which there was sufficient evidence to justify his conclusion.
[183] Therefore, on this claim, I find that the appropriate quantity is 3.24 cubic metres and
the rate is $16.08 a cubic metre which means that CCPL was overpaid by Stork.
Item 6.4.64 Turbine Generator Building
[184] CCPL says that the quantity was 5.91 cubic metres at a rate of $55 per cubic metre.
Stork says that the quantity was 2.63 cubic metres at a rate of $32.16 per cubic metre.
The circumstances of this claim are very similar to those of the preceding claim. There
is a specific rate in the Schedule of Rates for “Ammonia Plant Building – Footing
Excavation”. I accept the volume calculated by Mr Robinson at 5.91 cubic metres and I
apply to it the rate identified by Mr Leck of $32.16 per cubic metre. It follows that the
plaintiff was overpaid for this item.
Item 6.4.65 Ammonia Storage Pipe Supports and Steam Reformer Pipe Supports
[185] With respect to this claim Stork contends that the relevant quantity is zero, because the
claim under this heading is duplicated in the claim under the heading of “Pedestals”.
Notwithstanding that, I find that the appropriate rate is $32.16 per cubic metre because
that is the relevant figure in the Subcontract Schedule of Rates and if I am wrong with
respect to the claim of duplication I find that Mr Robinson’s calculation is to be
preferred in the sum of 2.43 cubic metres. That, once again, results in a finding of
overpayment by the defendant.
Item 6.7.8 Nitric Acid Plant Building Slabs
[186] The issue under this claim relates only to quantities as there is an agreement on the
appropriate rate. The point of dispute here is that Mr Robinson assumed a constant 200
millimetre width of the relevant slab, whereas that does not coincide with the width of
the slab shown on the drawings. It was accepted by Mr Robinson that if the slab was
not 200 millimetres thick then his calculation could be wrong. 59 On this matter I prefer
the evidence of Mr Leck where he identifies a quantity of 121.06933 cubic metres. On
that basis, the plaintiff has, once again, been overpaid.
Duplication of Claim?
[187] It is submitted by Stork that there is a duplication of claims in respect of footings and
pedestals. That duplication is made out in Appendix D to Stork’s written submission
provided to me. On the findings which I have made above the duplication is something
which need not be pursued further. Likewise, on the findings I have made with respect
to the applicability of the QBSA Act it is something which need not be further pursued.
58 Ex 53, p 35.
59 T 580/54 – 581.
-- 40 of 81 --
41
[188] The result of the findings above is that the plaintiff has no entitlement to the claims it
makes for quantities of footings.
(viii) The Pedestal Claim
[189] This claim is pleaded in paragraphs 114 to 136 and attachments D, E and F of the
FFASC. It is a claim for $308,912.33 being the balance of the amount owing from a
claim of $515,406.59 for the work performed under this head.
[190] Pedestals are typically small blocks of reinforced concrete which are constructed on
slabs or pier foundations and which usually are the base for holding down bolts. At the
time of the tender process there was no item in the drawings or the Scope of Works (Ex
F to the Subcontract) which showed a pedestal (or pier, plinth or column) with a plan
area of one square metre or less.
[191] CCPL pleads60 that Stork issued it with for-construction drawings which included
reference to the construction of pedestals having a plan area of one square metre or
less. The particulars of those drawings are said to be contained in Attachment D to the
FFASC.
[192] CCPL then alleges that:
(a) the for-construction drawings contained specifications different from
the Bill of Quantities in that they required the construction of
pedestals having an area on plan of one square metre or less61 ,
(b) the Subcontract deemed the Bill of Quantities to be in error, and the
Bill of Quantities is in error, in that it contains incorrect quantities
and omits items, being pedestals with an area on plan of one square
metre or less, 62
(c) alternatively, clause 3.3 of the Subcontract permits valuation of an
item of work under clause 45.5 if the Schedule of Rates omits an
item,63
(d) between November 1998 and November 1999, the plaintiff
constructed pedestals with an area on plan of one square metre or
less in accordance with the Subcontract and the for-construction
drawings.64 The plaintiff alleges that full particulars of the pedestal
work, including quantities measured in accordance with the contract,
are set out in Attachment D and that the profiles and dimensions
relied upon to calculate those quantities are contained in specified
for-construction drawings as well as Attachment D,
(e) the plaintiff applied in writing for an adjustment of the lump sum
accepted by the defendant for the whole of the work to which the Bill
of Quantities relates,65
(f) the Subcontract required an adjustment to the Bill of Quantities to
correct the error as if the correct were a variation,66
(g) the amount required to correct the error in the Bill of Quantities is to
be determined in the manner provided by clause 45.5(b) of the
60 Para 115, FFASC.
61 Para 116, FFASC.
62 Para 117, FFASC.
63 Para 118, FFASC.
64 Para 119, FFASC.
65 Para 120, FFASC.
66 Para 121, FFASC.
-- 41 of 81 --
42
contract, and the relevant amount is $515,406 as particularised in
Attachment D67 (para 122),
(h) pursuant to the Subcontract the plaintiff claimed the sum of $515,406
in respect of the pedestal work, by progress claims 11-23,68
(i) the defendant has paid only $158,468 of the amount claimed by the
plaintiff for the pedestal work, 69
(j) the Subcontract required the defendant to pay the plaintiff the
amount of a progress certificate or progress claim within a prescribed
time,70
(k) in breach of the Subcontract (and the “Pedestal Variation”), the
defendant failed to pay the balance of the value of the pedestal work
within the prescribed time, and the plaintiff is entitled to the said
payment, 71 and
(l) the plaintiff has suffered loss and damage in the sum of $308,912,
being the difference between the amount it alleges to have claimed
and the amount it alleges the defendant has paid72 (para 136).
[193] Clause 5.4 of Attachment D provides:
“Errors in Bills of Quantities
If the Priced Bill of Quantities is in error in that it;
(a) contains an incorrect quantity in relation to any item
included therein; or
(b) contains an item which should not have been included
therein; or
(c) omits an item which should have been included therein;
then;
(i) in a case of Clause 5.4(a) where the item is deficient
in quantity or in the case of Clause 5.4(c) upon
application in writing to Stork's Representative by
the Subcontractor; and
(ii) in a case of Clause 5.4(a) where the time is
excessive in quantity or in the case of Clause 5.4(b)
upon notification in writing to the Subcontractor by
Stork's Representative,
the lump sum accepted by Stork for the execution of the whole of the
work to which the Bill of Quantities relates shall except when the
value of the error is less than $400, be adjusted by such amount as is
required to correct the error, determined in the manner provided by
Clause 46.5 for the valuation of variations as if the correction where
a variation under Clause 46.
The Bill of Quantities shall be deemed to be in error as aforesaid to
the extent that the items and quantities included in it differ from
those required for the execution of the Works in accordance with the
drawings and specification referred to in the Subcontract, measured
in accordance with the method of measurement evidenced by the
Subcontract.”
67 Para 122, FFASC.
68 Para 123, FFASC.
69 Para 124, FFASC.
70 Para 125, FFASC.
71 Para 126, FFASC
72 Para 136, FFASC
-- 42 of 81 --
43
[194] The reference to “Clause 46.5” is an error. There is no such clause. Mr Digby QC
suggested that there was a transposition of numbers and that it should be read as
“Clause 45.6”73 . I do not agree. Clause 45.6 deals with a variation omitting part of the
work – it does not provide a means of measurement. On the other hand, clause 45.5
clearly does set out a mechanism for determining value. I intend to read “clause 46.5”
as “clause 45.5”.
[195] Clause 45.5 provides:
“Valuation
Where the Subcontract provides that a valuation shall be made under
Clause 45.5, Stork shall pay or allow the Subcontractor, or the
Subcontractor shall pay or allow Stork, as the case may require, an
amount ascertained by Stork's Representative as follows;
(a) lf the Subcontract prescribes specific rates or prices to be
applied in determining the value, those rates or prices shall
be used;
(b) if Clause 45.5(a) does not apply, the rates or prices in a
Priced Bill of Quantities or Schedule of Rates shall be used
to the extent that it is reasonable to use them;
(c) to the extent that neither Clause 45.5(a) or 45.5(b) apply,
reasonable rates or prices shall be used in any valuation
made by Stork's Representative;
(d) in determining the deduction to be made for work which is
taken out of the Subcontract, the deduction shall include a
reasonable amount for profit and overheads;
(e) if the valuation is of an increase or decrease in a fee or
charge or is a new fee or charge under Clause 16.2, the value
shall be the actual increase or decrease or the actual amount
of the new fee or charge without regard to overheads or
profit;
(f) if the valuation relates to extra costs incurred by the
Subcontractor for delay or disruption, the valuation shall
include a reasonable amount for overheads but shall not
include profit or loss of profit;
(g) if Clause 12(b) applies, the percentage referred to in Clause
12(b) shall be used for valuing the Subcontractor's profit and
attendance; and
(h) daywork shall be valued in accordance with Clause 46.
When under Clause 45.3 Stork's Representative directs the
Subcontractor to support a variation with measurements and other
evidence of cost, Stork's Representative shall allow the
Subcontractor the reasonable cost of preparing the measurements or
other evidence of cost that has been incurred over and above normal
overhead cost.”
[196] Paragraph 115 of the FFASC pleads that Stork issued CCPL with for-construction
drawings which included reference to the pedestals and then particularised those
drawings in Attachment D to the pleading. A review of Attachment D reveals the
following:
73 T 786.
-- 43 of 81 --
44
(a) a number of the entries (for example: Steam Reformer Pedestal
MF007) have, in the column “Stork For-Construction DRWG No.”,
the notation “No plan”,
(b) there are entries in a column “Survey DRWG No.” but no claim is
made with respect to those drawings,
(c) the cost of construction of the pedestals is set out and those costs
appear to have been calculated from other entries which set out the
types of labour engaged (for example: labourer, tradesman etc), the
hours worked, the rate per hour and the cost of materials,
(d) the total claim of $515,406.59 appears to have been arrived at by
reference to the hours worked, the rates paid and the material used,
and
(e) that claim includes those pedestals for which no for-construction
drawing is identified.
The claim in paragraph 115 is inconsistent with the particulars attached to the
paragraph to the extent referred to above.
[197] As with most of the plaintiff’s claims, the argument is not about whether the work was
done but the manner in which it should be remunerated and the pleaded claim for that
remuneration and so I turn to the manner in which CCPL framed its claim.
[198] Paragraph 122 of the FFASC pleads:
“The amount required to correct the Bill Error, determined in the
manner provided by clause 45.5(b) for the valuation of variations as
if the correction were a variation under clause 45 of the construction
agreement is $515,406.59.
PARTICULARS
“The calculation of the sum of $515,406.59 set out in the Pedestal
Reconciliation attached hereto and marked ‘D’.”
[199] In submissions, CCPL also sought to rely upon its pleading in paragraph 118:
“Further, or in the alternative, there were terms of the construction
agreement:
(a) that Cooks’ would execute and complete the works under
the construction agreement (clause 3.1 Exhibit D);
(b) “works under the construction agreement” means the work
which the Subcontractor is or may be required to execute
under the construction agreement and includes variations,
remedial works, Constructional Plant and Temporary Works
(clause 2 Exhibit D);
(c) that Stork would pay Cooks for work for which it accepted
rates the sum ascertained by measurement and
determination of the quantities in accordance with Clause
3.2 and multiplying the quantity so measured and
determined of each section or item of work carried out
under the Subcontract by the rate accepted by Stork for the
section or item (clause 3.1 Exhibit D);
(d) “actual quantities” shall mean those quantities measured in
accordance with Australian Standard 1181-1982 as
amended from time to time from the lines, dimensions and
limits shown on the relevant Contract plans and drawings
-- 44 of 81 --
45
(clause 3.2 Exhibit D);
(e) Where Stork accepted a rate for an item the rate shall apply
to greater or lesser quantities (clause 3.3 Exhibit D);
(f) If a schedule of rates omits an item which should have been
included the item shall be valued under clause 45.5 as if it
were extra work directed by Stork’s Representative (clause
3.3 Exhibit D).”
[200] Stork argues that CCPL is confined by its pleading to a claim based upon cl 45.5(b),
that is, a claim which must be calculated by reference (to the extent that it is reasonable
to use them) to the rates or prices in a Priced Bill of Quantities or Schedule of Rates in
circumstances where the Subcontract does not prescribe specific rates or prices to be
applied. In other words, only the means of calculating compensation which have been
pleaded may be relied upon.
[201] CCPL, in response to that argument points to paragraph 118(f) of the FFASC which, so
far as is relevant, pleads the term of the construction agreement that if a schedule of
rates omits an item which should have been included the item shall be valued under cl
45.5 as if it were extra work directed by Stork’s Representative (cl 3.3 Exhibit D). It
was submitted that “the pleading's broad enough to communicate to the reader that in
this part, before we get to 45.5 (b), that the entitlement is said to be - to have the
omission valued under clause 45.5 full stop. The pleading then goes on and in
paragraph 122 pleads that the amount required to correct the bill error determined in a
manner provided by 45.5 (b) is $515,000.”74
[202] In other words, CCPL argued that the allegation it pleaded in paragraph 118(f) meant
that “the pleading's broad enough to carry a claim being advanced on the basis that
clause 45.5 or some component of it is the proper foundation for a - for compensation
for the omitted item.” 75
[203] I do not accept that submission. The allegation about the content of the agreement is
made but there is no further pleading to the effect that, based upon clause 45.5, CCPL
is entitled to payment of a particular amount. The only claim made is that contained in
paragraph 122 which specifically refers to cl 45.5(b). It follows, then, that the only
allegation to be met by Stork is that which makes the specific claim for an amount
calculated in accordance with a particular part of cl 45. If it were otherwise, CCPL
could have advanced a claim for any sum based on any of the parts of cl 45. To allow
that would be to reduce the purpose of pleadings – to identify and confine the issues –
to little more than talking points in an unregulated debate.
[204] The breadth of the plaintiff’s argument on this point was exemplified by the following
submission of Mr Digby QC:
“In our submission, your Honour, the contract operates more broadly
than to confine the plaintiff only to remuneration if there can be the
identification of both a specific quantity and the identification of a
specific rate, and in the operation of 5.4 as an example then through
the conduit of clause 45.5 your Honour is able to remunerate the
plaintiff on the basis what we have is a reasonable rate or reasonable
price if the evidence is available.”76
74 T 789/38.
75 T 789/44.
76 T 787/20.
-- 45 of 81 --
46
[205] It might well be correct to say that the contract “operates more broadly”, but, in order
for that to be a basis upon which a claim is made it would be necessary to plead that
the Subcontract should be construed in that way. This part of the plaintiff’s argument
betrayed, with respect, a conflation of the proper construction of the Subcontract and
the manner in which a claim under the Subcontract could be pleaded. One example of
that form of impermissible reasoning was the submission to the effect that one should
look at the Subcontract as a commercial document and provide a sensible construction
of the manner in which certain clauses should operate which was interwoven with a
submission about the pleading being an appropriate vehicle for allowing an assessment
of what was a fair or reasonable amount. 77
[206] In order that an opponent might be properly apprised of the case it has to meet it would
be necessary, in a case such as this, to plead the construction of the Subcontract upon
which a party intended to rely. It is not enough merely to advert to a clause in the
Subcontract and then to submit later that a particular view of the operation of that
clause should operate to allow a wider claim that that actually pleaded. That is what
CCPL seeks to do when it argues that it should be able to rest its claim on any part of
cl 45 even when it has identified (in para 122) a specific sub-clause as the one upon
which it makes its claim.
[207] I return to the pleaded case. As I have already pointed out, Attachment D to the
FFASC contains references to pedestals other than those contained on for-construction
drawings. In fact, Attachment D identifies 615 constructions said to be pedestals and
not all of them are identified as appearing on for-construction drawings. I disregard
those pedestals which are not on the for-construction drawings because they are not the
subject of the claim. The next restriction in the pleading is the allegation that the
pedestals in the attachment have a plan area of one square metre or less. Although
there was evidence that CCPL did construct pedestals of that size I have not found any
evidence to support the allegation that those listed in Attachment D fall within that
description. There was considerable evidence about their construction78 , the cost of
their construction79 , and the instructions and negotiations which took place about their
construction80 . As to the last point, there was no pleaded reliance on any negotiations,
conversations or correspondence.
[208] Mr Robinson gave evidence that he prepared a document in relation to the pedestals
that were constructed by CCPL during the course of the project.81 It was provided to
CCPL as part of the work that he was requested to do to locate the footings. He was
unable to say whether any of the items he identified formed part of the claim made by
CCPL for pedestals. He was cross-examined82 as to whether pedestals identified by
him and contained in the spreadsheet had plan areas in excess of one square metre. He
agreed that there were some. The plans which he used for the purposes of that exercise
were survey drawings as opposed to for-construction drawings. By way of example he
found, with respect to survey drawing 124F013 that one of the pedestals shown on that
drawing was in excess of one square metre in plan as were others identified by him in
his spreadsheet. Survey drawing 124F013 is also referred to in Attachment D to the
FFASC.
77 T 790/50 – 791/15.
78 T 243-245.
79 T 242, 271, 273, 341, 509; Ex 39.
80 T 248-273.
81 T 566.
82 T 567-569.
-- 46 of 81 --
47
[209] In Mr Alsop’s report83 he prepared a schedule which contained 611 pedestals. Of those,
230 were not contained in the claim made by CCPL and particularised in Attachment
D to the FFASC. He also expressed the view that an assessment based on “day works”
is an appropriate to fairly compensate a contractor for time spent on small items. That
was the alternate claim made by CCPL and, indeed, a reference to Attachment D
shows that the costs are calculated according to the number of hours expended in
construction by various categories of person together with rates which they, according
to CCPL, were paid. That raises another issue with respect to the pleading. In
paragraph 119 of the FFASC the plaintiff says that Attachment D to the FFASC
contains quantities measured in accordance with cl 2 of Part A of Exhibit C of the
Construction Agreement. It does not. It does not identify any quantities and it only sets
out, as referred to above, hours of labour and equipment and materials used. Although
there is reference in the particulars to paragraph 119 to for-construction drawings, the
particulars say that the profiles and dimensions are contained within both those
drawings and Attachment D. Attachment D does not contain any reference to profiles
and dimensions.
[210] The evidence adduced by CCPL would be sufficient to establish that a large number of
pedestals were built by it pursuant to directions given by Stork but there is insufficient
evidence to establish the number of pedestals built, the size of the pedestals built (in
particular, whether they were under one square metre in plan area), and the rates or
prices to be used so far as is reasonable to assess the cost.
[211] Further, Attachment D does not appear to apply the rates or prices as required by
cl 45.5(b). The source of the rates used in Attachment D was not identified. It appears
that they could not have come from tables B2 or B3 and the rate applied for survey
work was nearly 50% more than the applicable subcontract rate under table B1.
[212] Finally, the claim that is made by CCPL is a claim based solely on cl 45.5(b).
Paragraph 122 of the FFASC refers only to that clause and there is no claim for a
reasonable rate or price in the pleading. Even if there were, the details set out in
Attachment D for hours spent and materials consumed were not supported by any other
primary evidence.
[213] The claim by CCPL under this heading is dismissed.
(ix) The Pedestal Reconciliation Claim
[214] In paragraph 130 of the FFASC it is pleaded that Stork requested CCPL, and CCPL
agreed, to prepare day work sheets to detail evidence of the cost of construction of the
pedestal work. It is pleaded that this is the “Pedestal Reconciliation Agreement”. The
Pedestal Reconciliation is the document which makes up Attachment D to the FFASC.
In its pleading CCPL says that the Pedestal Reconciliation Agreement “is in writing
and is constituted by a letter from Stork to CCPL dated 9 January 2000”. That letter is
contained in Exhibit 44 and, excluding formal parts, provides:
“This is to confirm Stork’s verbal instruction for Cook’s to prepare
and submit, to Stork, day sheets in support of Cook’s proposed
average cost of $780 each, of pedestals construction. The day sheets
must show total labour and materials involved in the construction of
such pedestals.”
83 Ex 39.
-- 47 of 81 --
48
[215] The plaintiff then pleads84 that it was: “a term of the Pedestal Reconciliation
Agreement that Stork would pay for the reasonable cost of preparation of the Pedestal
Reconciliation”. That allegation is denied by Stork and understandably so. The
document said to constitute the agreement is very brief and contains no reference to
payment for anything. It contains no support for the allegation that Stork would pay the
reasonable cost of preparation.
[216] There is no other issue raised by the plaintiff, for example, such as an implied term,
which might give rise to a cause of action on this point.
[217] The plaintiff has failed to demonstrate an agreement either in the terms pleaded or
otherwise which would justify its claim for $34,307 as the balance of the cost of
preparation of the Pedestal Reconciliation.
[218] Had the plaintiff sought to amend its statement of claim to include an allegation that
there should be a term implied into the Agreement that Stork would pay the reasonable
cost of preparation, it would still be unable to recover the amount it claims because it
did not establish the necessary foundation for a finding that the amount claimed was in
fact reasonable. The claim for $44,308 was based on the time alleged to have been
taken to prepare the document. Attachment F to the FFASC contains what is called a
preparation work record for the reconciliation and it purports to show the hours taken
by each person involved together with what is said to be an appropriate rate. The
persons named, the hours alleged to have been worked and the evidence in support are
set out below:
Peter Robinson – 200.5 hours – although Mr Robinson gave evidence about the
manner in which he conducted a survey of the pedestals and other structures he
did not give any evidence about the number of hours he spent doing that.
Mr Sawyer – 34 hours – Mr Sawyer was not called.
Mr Hooper – 99.5 hours – Mr Hooper was not called.
Mr Wiseman – 178 hours – Mr Wiseman did give evidence of spending that
amount of time and preparation.85
Mr Howard – 12 hours – Mr Howard did not give any evidence on this point.
Mr Plail – 76 hours – Mr Plail was not called.
Mr Glasgow – 40 hours – Mr Glasgow was not called.
[219] At the most, then, the evidence supporting the time used to prepare the reconciliation
relates only to Mr Wiseman and amount claimed for him is $10,680.
[220] This claim is dismissed.
(x) The Corrocem Claim
[221] This claim is pleaded in paragraphs 137 to 153 and Attachment G of the FFASC. It is a
claim for $68,209.69 being the balance of the amount owing from a claim of
$161,148.69 for the work performed under this head. This claim arises out of the for-
84 Para 131 FFASC.
85 T 524.
-- 48 of 81 --
49
construction drawings which were issued for use in execution of the construction of the
footing for the ammonia nitrate building. Those drawings required the addition of the
additive Corrocem to the concrete in the footings the purpose of which was to enhance
the strength and corrosion resistance capacity of the concrete being used.
[222] It was agreed on the pleadings that the for-construction drawings required the use of
the quantity of Corrocem alleged by the plaintiff; that the plaintiff claimed the sum of
$161,148.69 in respect of these works; then, that Stork has only paid $92,939 in
relation to this part of the plaintiff’s claim.
[223] Stork accepts that the for-construction drawings relied upon by CCPL differ from the
bill of quantities but maintains that there is no priced bill of quantities within the
meaning of cl 5.4 of the Subcontract. I deal with the question of whether there is a
“priced bill of quantities” within the meaning of the Subcontract elsewhere in these
reasons.
[224] If the Subcontract does contain a priced bill of quantities and there is an error in it then,
in order that CCPL might be paid for additional work, CCPL must comply with cl
5.4(i) which requires an application in writing to Stork by CCPL. CCPL pleads that the
adjustment of the lump sum accepted for the whole of the work to which the bill of
quantities relates was made by a facsimile transmission of 23 June 1999. 86
[225] Stork argues that Exhibit 15 cannot be described as an application of the type alleged
by the plaintiffs in that it does not refer to a lump sum or an adjustment to the bill of
quantities, or an error in the bill of quantities. Mr Eddie gave evidence of the genesis of
Exhibit 15:87
“Mr Eddie, did you have occasion to speak to Mr Jewell about the
whole subject of rates in respect of Corrocem during the course of
the calendar year 1999 and, if so, tell us as best you can recall in
approximate terms when such a discussion took place and then we
will deal with the substance of it?-- Well, behind Tab 11 is a copy of
a facsimile that I sent to Peter Jewell on the 23rd of June, which
followed a meeting I had with him to discuss the issue. At that time
he had pointed out to me that we started out offering a rate of 643
and that went up to 703 and, you know, what was our position on it.
I told him I would go back and review it, which I did. I went back
and reviewed what the situation was and said that we had estimated
before we started work that it would cost us $643 and that we were
prepared to maintain that rate.
When you speak of ‘we’ in that context-----?-- Cook's Construction.
Right?-- On the second page of that letter is the detail of the break-
up of that estimate that I had done previously.”
[226] The letter, excluding formal parts, reads:
“Peter
Further to our meeting last week I make the following comments on
events around the additional cost of the corrocem additive:
86 Ex 15.
87 T 133-134.
-- 49 of 81 --
50
• On 15 February I submitted a rate of $643 extra over for the
incorporating the additive and placing the altered product. In the
submission I highlighted the reasons for the additional cost but did
not give a break-up of this cost.
• We commenced placing corrocem concrete on 4 March and
sometime after that we were apparently requested to substantiate our
claim of $643.
• Being after the event the records of actual performance were used in
our letters of 4 May and 2 June.
I would like to return to my original submission, which was our
estimated cost, and I am prepared to stand by it. The break-up of the
$643 is as follows:
1. Additional cost of incorporating additive
Concrete 32Mpa in concrete truck at site $132/m3
Corrocem concrete in track at site $504/m3
Additional cost per track m3 $132/m3
Allowance for wastage (15%) $ 56/m3
Subtotal $428/m3
Mark-up on material (7%) $ 30/m3
Subtotal $458/m3
2. Additional cost of placing corrocem concrete
Additional placing cost $ 70/m3
Additional finishing cost $ 25/m3
Aliphatic Alcohol $ 5/m3
Lights incl. fuel $ 15/m3
Subtotal $573/m3
On site overheads plus risk (say) $ 70/m3
TOTAL EXTRA OVER $643/m3
Peter if there is any aspect of this proposal that you would like to
discuss further I would appreciate you contacting me direct.”
[227] Exhibit 15 does not demonstrate the necessary compliance with cl 5.4. It does not refer
to a priced Bill of Quantities or an error or omission in that Bill. It makes no
application to Stork for an adjustment.
[228] Should my finding that there was no application for an adjustment be incorrect, I
should consider whether the amount claimed is reasonable.
[229] CCPL claims that a reasonable rate for Corrocem is $703.32 a cubic metre.88 Although
the estimate in Exhibit 15 is that the total extra over-cost would be $643 per cubic
metre, when the records were reconsidered CCPL says that the actual cost of placing
Corrocem is determined by the written records of those costs referred to in Attachment
G. 89
[230] Stork points out a number of problems with the manner in which CCPL has calculated
a “reasonable” rate for Corrocem. They are:
(a) The number of hours pleaded as being required to place the
Corrocem concrete is not supported. No documentary evidence was
provided to establish the hours asserted.
88 Para 145 and Attachment G of the FFASC.
89 T 132.
-- 50 of 81 --
51
(b) There is an inconsistency between the calculation of the additional
number of hours to place Corrocem above those required in relation
to untreated concrete. It appears to be based upon the premise that
untreated concrete would be placed at a rate of one cubic metre per
half a man hour. That appears to be inconsistent with the rate in table
B4 of Exhibit C to the Subcontract providing that the total cost of
placing a cubic metre of untreated concrete is $141 whereas applying
the “normal” rate relied upon by CCPL would result in a cost of
placing one cubic metre of untreated concrete at $27.50. That may
have an effect on the additional man hours said to have been required
for the placement of Corrocem but it is difficult to form a concluded
view on that in the absence of precise evidence dealing with it.
(c) There was evidence about the “necessity” for the Corrocem to be
placed at night in order to take advantage of cooler conditions.
Attachment G refers to “four night pours” but there is other evidence
which suggests there were five pours, or many pours.90 I could not
find any evidence which supports the entry of four night pours.
(d) CCPL claims the cost of placing concrete by pump. The concrete
would have required the use of a pump for placement regardless of
where Corrocem was an additive or not.91
(e) Attachment G asserts that the cost of Corrocem concrete was $504.
There is no evidence to support that. There are no invoices or
quotations or statement which support that figure. Mr Eddie gave
evidence about the cost of Corrocem. In answer to one question he
said that the purchase price of Corrocem per cubic metre was over
$500. In answer to a question shortly after that he said the cost of
buying the Corrocem was $400 a cubic metre.92 Other evidence was
given by Mr Howard who said that the cost of Corrocem basically
doubled the price of the concrete.93 If that was correct then, given
that the contractual rate for the supply of concrete was $165 a cubic
metre the extra cost would have been no more than that amount.
(f) Further, in Attachment G there is a 25 % uplift on the cost. There is
no basis for that. Mr Eames was not aware of any basis under the
contract for CCPL to be able to be paid 25% more than they paid for
something.94 Mr Young who created the claim with respect to
Corrocem concrete could not say where he got the figure of 25%.95
[231] Mr Alsop was called to give evidence on this point. His evidence was based upon
assumptions as to truck capacity and other performance issues which were not
supported by any evidence. He also refers to additional costs incurred by the supplier
in delivering the concrete to the site but no evidence was provided with respect to that.
His rate of $268.80 a cubic metre included allowances for which there was no support.
[232] Mr Leck gave evidence that a reasonable extra over-rate for Corrocem would be $30 a
cubic metre on the basis that the cost of silica fume (of which Corrocem was a type)
was $10 a cubic metre and some additional placing costs might be needed. His
90 Ex 14, T 275.
91 T 497.
92 T 145.
93 T 456.
94 T 361.
95 T 496.
-- 51 of 81 --
52
evidence was based upon a costing of silica fume. Corrocem was said to be a
particular brand of silica fume technology but the extract from Rawlinson’s
Construction Handbook 96 does not give sufficient particulars for me to be satisfied that
that is an appropriate amount.
[233] It follows that CCPL has not made out a reasonable rate for the placement of concrete
treated with Corrocem.
[234] In light of my finding that there was no application for an adjustment, this claim must
be dismissed.
(xi) The Suspended Slabs Claim
[235] This claim is pleaded in paragraphs 154 to 170 and attachment H of FFASC. It is a
claim for $171,809 being the balance of the amount owing from a claim of $520,465
for the work performed under this head. This claim arose out of a change from the
sketch provided to CCPL for its tender for work. The original sketch provided97
showed slabs to be constructed at ground level. The for-construction drawings which
were issued showed slabs which were to be constructed several metres in the air and,
of course, supported by columns. To construct that type of a slab it is necessary to put
scaffolding underneath a platform which acts as the form for the base of the concrete
slab.98 The slabs to be constructed were for the ammonia synthesis unit and the turbine
generator unit.
[236] CCPL pleads that because of the change between the original sketch and the
for-construction drawings the subcontract deemed the bill of quantities in error as it
omitted an item being the suspended slabs and columns. In the alternative, CCPL
pleaded that clause 3.3 of the Subcontract permitted valuation of an item of work under
clause 45.5 if the schedule of rates omitted an item.
[237] Stork denies that the bill of quantities is deemed to be in error or that CCPL is entitled
to an adjustment of the lump sum to correct the error.
[238] CCPL says that it applied in writing for an adjustment of the lump sum as required by
the Subcontract but this is denied by Stork.
[239] The other major area of disagreement is over the calculation of the amount claimed.
That calculation is set out in Attachment H to the FFASC.
[240] I turn first to the claim for an adjustment of the lump sum. It is one of the alternative
bases for the claim by CCPL. It relies upon three letters: two dated 6 August 1999 99
and a letter dated 22 September 2000.100
[241] The letters of 6 August 1999 are virtually identical so far as the details of the figures
are concerned. The first of the letters101 refers to the ammonia synthesis unit. The
opening paragraph of the letter reads:
“In an endeavour to simplify our claim and obtain consistency, we
suggest that the ammonia synthesis unit (item 6.4.48) be regarded as
96 Ex 57.
97 Ex 8.
98 T 135.
99 QANP 271 and QANP 273 – see Ex 44, tab “suspended slabs”.
100 Ex 5.
101 QANP 271.
-- 52 of 81 --
53
a type 6 structure. Accordingly the following rates for formwork and
concrete have been adjusted to reflect this type structure.”
[242] The other letter of the same date102 refers in similar terms to the turbine generator. In
neither letter is there a reference to the bill of quantities or the “lump sum”. There is a
reference to rates being “adjusted” but not a reference to the “lump sum” being
adjusted. In the written submissions from CCPL these letters are referred to as being in
a group of letters said to “canvass (albeit unsuccessfully) bases for rates for the
suspended slabs”. It is not argued in these submissions that they constitute an
application in writing in the sense required by the Subcontract.
[243] The other letter said to constitute an application for adjustment of the lump sum is the
letter of 22 September 2000.103 This letter commences:
“During the meeting on Friday 19 May 2000, you advised that Stork
would revisit it’s (sic) position in relation to Cook’s claimed rates
and a claimed soffit formwork areas for ammonia sysnthesis (sic)
and turbine generator suspended slab structures.
Cooks have had no response from Stork since the abovementioned
meeting regarding Stork’s position. Cooks therefore assume Stork
has accepted Cook’s rates as detailed in Cook’s letters QANP 271
dated 6/8/1999 and QANP 273 dated 6/8/1999 and require
immediate payment for the outstanding value for the progress claim
items 6.4.48 and 6.5.28, presented on the attached spreadsheet and
summarised below.”
[244] There is then a tabulation (the spreadsheet referred to was not tendered) and the
tabulation shows a claimed value for the ammonia synthesis slab of $172,509.09 and
for the turbine generator a value of $218,661.81. The letter claims that Stork has made
total payments of $291,925.27 leaving a balance outstanding of $99,245.63.
[245] No reference to this exhibit is made in the written submissions of the plaintiff or in the
oral submissions made on the final day. When the letter was tendered104 its author, Mr
Trende, was asked:
“But that’s another letter for demand to Mr Jewell for payment this
time in respect of suspended slabs? - - Correct.”
That characterisation is correct. It is not, nor was it ever argued to be, a letter seeking an
adjustment of the lump sum.
[246] As has been noted with respect to other claims, in order for any adjustment of the lump
sum to occur under clause 5.4 of the Subcontract there must be a request for an
adjustment. None of the letters referred to above constitute a request as required by
clause 5.4. It follows then that that clause has not been activated and the first ground
for the claim fails.
[247] In the alternative basis for the claim there a number of disputes. The next issue in
dispute is the area of “edge formwork” involved with the construction of the turbine
generator slab. This is a structure of approximately the same size as the ammonia
synthesis slab save that it had an upstand surrounding the slab for which extra edge
formwork was required. Mr Leck did not include the formwork for the upstands and so
he arrived at an area of 107 sq metres for the formwork for the turbine generator slab
102 QAN p 273.
103 Ex 5.
104 T 90.
-- 53 of 81 --
54
whereas Mr Alsop agreed with the claim in the FFASC105 that the formwork was 150
sq metres.
[248] The reason given by Mr Leck for not including the extra formwork was that, in his
experience, the upstand is not actually part of the slab. That is something which was in
his report which, as I have noted, was in the hands of the plaintiff for some months
before the trial began yet there was no cross-examination on that point. Given that the
relevant for-construction drawing shows that the upstand was a separate structure to
the slab, I accept Mr Leck’s evidence on this point.
[249] The next issue for consideration is the question of appropriate rates for the calculations
of the amounts. CCPL has calculated the amounts by reference to cl 45.5(c) which
means that they are relying upon “reasonable rates or prices”.
[250] CCPL contends that the applicable rate for formwork for columns is $311.60 a square
metre. Mr Leck says that $300 a square metre would be appropriate. Mr Leck agreed
that two reasonable people might arrive at different reasonable prices and that there
was nothing in the difference between him and Mr Alsop as it amounted to a difference
of about 3%.106 I accept Mr Alsop’s assessment of $311.60 a square metre as the rate
for formwork to the columns.
[251] The plaintiff contends that the applicable rate for concrete for the columns is $787.21 a
square metre. For the defendant, Mr Leck, says the applicable rate is $678.15 a square
metre. The manner of calculation of this rate is set out in Attachment H to the FFASC.
There are a number of internal difficulties with the manner in which that has been
calculated. There is, for example, an amount for the base rate for concrete being
“Schedule A + Cook’s margin”. This is not justified on the evidence. Mr Eddie could
not explain it. He said that he did not know what “Schedule A + Cook’s margin”
meant. 107 Mr Alsop said that it would be appropriate to claim a higher rate for concrete
used in columns, walls and plinths as industry handbooks indicate that the rates for
those items are not the same as the rate for slabs.
[252] The difficulty with this part of the plaintiff’s claims is one which permeates the
balance of the figures asserted by the plaintiff. In order to demonstrate that a rate is
reasonable there must be some evidence, other than that of an expert who relies upon
assertions for some of his evidence such as Mr Alsop does at page 13 of his report. It is
contended by Stork that the plaintiff has been inconsistent in Attachment H when there
is a reference to contractual rates as the basis for components of another rate. It is
argued that such a calculation is invalid because the allegation that a rate is relied upon
means that cl 45.5(c) cannot be the basis upon which the claim is made. I disagree. It is
open to CCPL in these circumstances to point to a rate or part of a rate as being a
reasonable component of another greater rate.
[253] In the end, though, on this part of the claim, CCPL has simply failed to set out why the
individual parts of the rate upon which it relies should be used to make up the greater
rate to which it asserts it is entitled.
[254] The next part of the claim is for soffit formwork for the suspended slab. CCPL seeks a
rate of $708.07 a square metre. This is said by Stork to be overgenerous because it
improperly incorporates the cost of formwork required for working space; the
105 Para 158.
106 T 722.
107 T 153.
-- 54 of 81 --
55
components of the claimed rate come from part B3 of Ex C to the contract (but there is
no evidence of any invoiced costs) and, as above, by referring to contractual rates there
is a contradiction with the claim for a reasonable rate. Mr Alsop says that a rate of
$680 to $720 a square metre is appropriate108 but goes no further than that. There was a
conflict between Mr Alsop’s assumptions and Mr Eames’ evidence as to the use of
steel supports. Mr Alsop assumed the use of a substantial steel framework whereas Mr
Eames’ evidence was that the structure was made up of steel columns and timber
beams. 109 I accept Mr Leck’s evidence on this point, that is, that $200 a square metre is
appropriate in light of his analysis.110
[255] With respect to the rate for the suspended slab-edge formwork, the difference is
between the rate claimed by CCPL of $233 a square metre and Mr Leck who said that
the applicable rate is $200 a square metre. There is a difference of approximately 15%
between those two figures. I do not think that that is a sufficient difference in these
circumstances to reject the plaintiff’s claim and I accept the amount it claims as
reasonable.
[256] The plaintiff contends that the applicable rate for the suspended slab is $678.15 a
square metre. This was accepted by Mr Leck.
[257] For the suspended slab concrete for the plinths, the plaintiff contends the applicable
rate is $704.65 a cubic metre. Mr Leck says that the appropriate rate is $678.15 a cubic
metre. Notwithstanding the arguments raised against the plaintiff’s claim on this point
by the defendant, the difference between the two figures is less than 5% and given Mr
Leck’s evidence about the applicable rate with a difference of less than 5% I accept
that this part of the claim by the plaintiff is reasonable.
[258] This claim would, but for the defences referred to earlier, succeed to the extent that the
total owing based on the findings set out exceeded the amount paid by Stork.
(xii) The Prill Storage Building Structures Claim
[259] This claim is pleaded in paragraphs 171 to 187 and Attachment I of the FFASC. It is a
claim for $420,466 being the balance of the amount owing from a claim of $1,784,123
for the work performed under this head.
[260] The representation of the prill store in the tender documents was as just a slab on the
ground. When the for-construction drawings were presented, there were, in addition to
the slab, walls up to six metres high surrounding an area in which the prill was to be
stockpiled.111 I accept that the for-construction drawings referred to in the reports of
Mr Alsop and Mr Leck show a requirement for the construction of walls in addition to
the slab.
[261] CCPL pleads that because of the admission of the extra building work, the Bill of
Quantities was deemed to be in error and the work was to be paid for in accordance
with the Subcontract. It alternatively claims a valuation of that work under cl 3.3. In
paragraph 177 of the FFASC, the plaintiff alleges that it applied to Stork for
adjustment of the lump sum by such amount as was required to correct the bill error.
No letter dated 13 December was put in evidence but there is a letter dated 12
108 Ex 39, p 17.
109 T 362.
110 T 722-723
111 T 137.
-- 55 of 81 --
56
December which carries the same reference, namely QANP 388. The copy of the letter
contained in Ex 44 behind tab “Prill store” of 12 December 1999 is not signed. It was
referred to in the evidence of Mr Eames as a draft and he says that he was “pretty well
certain” that the final version of the letter was sent on the 12th or the next day, the 13th
December. 112 That is likely, given that on 16 December 1999, Stork responded to a
letter dated 13 December and bearing the same reference number and advising CCPL
that its proposal was not acceptable to Stork. Further, in a letter of 13 December 1999,
Mr Eames withdraws his letter of 13 December 1999 “in the interest of less confusion
of the issue”. Whatever the circumstances of the sending of the letter, it did not
constitute an application in writing for an adjustment of the lump sum. It was framed in
terms of a variation and was in response to other correspondence relating to the prill
store storage building. .
[262] So far as the quantities claimed by the plaintiff are concerned, I address the issue of
formwork first. CCPL contends that the appropriate quantity of formwork for the slab
was 282.01 square metres. This is inconsistent, though, with Mr Robinson’s calculation
which, after deleting the portion concerning construction joints113 was 154.3 square
metres.114 That amount is also consistent with the calculation of Mr Alsop 115 where,
after deleting an area relating to additional external slabs which were not claimed by
the plaintiff, he arrives at a figure of 154.09 square metres. I accept that the appropriate
figure to adopt here is 154 square metres being the amount closest to that found by Mr
Alsop and Mr Robinson. The balance of the quantities claimed by the plaintiff is
accepted by the defendant.
[263] As with many of the other claims, a major disagreement exists with respect to the
appropriate rates to be applied.
[264] Mr Eames gave evidence about the construction of the prill store and the difficulties
which were encountered.116 He also said that CCPL required another $100 a cubic
metre on the rate it would ordinarily charge for placing the concrete because of the
difficulties involved.117
[265] While there is agreement on the measurement of many of the quantities, there is
complete disagreement as to the rates which should be applied to those quantities. I
will consider each in turn.
Formwork to base slab
[266] CCPL seeks to apply a rate of $212.77 on the basis that that is the contractual rate
applicable for formwork for “slab and walls”. This choice is supported by Mr Alsop.118
There is, though, no evidence as to why a rate applicable to “slab and walls” should be
applied to a slab alone. In his report, Mr Leck says 119 that the rate for formwork to the
base slab should be similar to the rate in 6.8.28 or the Table B4 rate, which are both
rates set out in the Subcontract relating to formwork for slabs. Although Mr Alsop had
112 T 291.
113 These could not be included because clause 2.1.4(b) of part A of Ex C to the Subcontract provided
that the rates for concrete should include such construction joints.
114 Ex 34, pp 31-32.
115 Ex 39.
116 T 285-289.
117 T 290.
118 Ex 39 p 14.
119 Ex 53 p 45.
-- 56 of 81 --
57
Mr Leck’s report and was asked to comment on it, he makes no reference to this
difference of opinion. Although neither expert descends into any particularity, Mr Leck
does provide some basis for accepting his assessment and I accept his rate of $80 a
square metre.
Rate for formwork to nib walls
[267] Mr Alsop supports the plaintiff’s claim for a rate of $212.77 a square metre on the
basis that it is an applicable for walls which are 200 millimetres thick and
500millimetres high. While there is evidence that some of the walls were 450
millimetres thick and about 6 metres high, there is no evidence about walls of the
thickness and height relied upon by Mr Alsop. Mr Leck says that the rate for formwork
to walls should be similar to the Table B4 rate for “form ply/metal sheeting” but gives
no justification for that. Mr Alsop’s figure is more closely associated with the type of
work and I accept it.
Rate for formwork to walls
[268] CCPL contends for a rate of $292.64 using a base rate of $212.77 a square metre
together with various other rates which bring it up to the higher amount. Of the
additional items claimed by the plaintiff some of them are incorrectly included as they
should already have been regarded as forming part of the original formwork rate, for
example, hire of solders, walkways, etc, a crane, formwork and so on. It seems to me
that the plaintiff has not justified the addition of the extra amounts on top of the base
rate. That base rate appears to be of more relevance than the rate asserted by Mr Leck
and I prefer that amount, namely $212.77 a square metre for formwork for the walls.
Rate for concreting base slab
[269] CCPL claims a rate of $663.03 a cubic metre. I do not understand why the rate for the
prill storage building itself ($490.57 in s 6.8.26 of Ex C) should not be the appropriate
rate. No evidence was called to justify the higher amount. Mr Leck applied a rate of
$529.85 a cubic metre and as this appears to be accepted by the defendant and is in
excess of the rate which appears to be otherwise specified for the building I accept the
higher rate.
Rate for concreting walls
[270] CCPL claims a rate of $733.45 a cubic metre. That is supported by Mr Alsop. Mr Leck
chooses a different figure but provides no support for it. CCPL in attachment I to the
FFASC pleads that the $733.45 figure is made up of items 6.5.25 from Schedule A and
adds to it another item pursuant to variation 046 and an additional figure for which
Table B3 is the reference. There is no evidence relating to variation 46 and I discard it.
I do not understand the reference to Table B3 and no evidence was called upon it. I
accept the rate set out in item 6.5.25, namely, $634.65 for this task.
[271] This claim would, but for the defences referred to earlier, succeed to the extent that the
total owing based on the findings set out exceeded the amount paid by Stork
(xiii) The Crushed Rock to Substations 1 and 2 Claim
[272] This claim is contained in paragraphs 204 to 228 of the FFASC. CCPL seeks the sum
of $11,354.76 for work associated with placement of crushed rock at Substation 1.
-- 57 of 81 --
58
[273] The evidence called on this topic was not consistent with the FFASC. Mr Eames’
evidence was that the claim was for the replacement of crushed rock which had already
been placed at the Substation and that this came about because the relevant electricity
authority required it.120 The FFASC pleads a case, not supported by the evidence, in
which there is no reference to replacement.
[274] This claim is very much like the other claims in which it is alleged that the relevant
item was omitted from the Bill of Quantities except that, in this case, CCPL contradicts
its own claim by pleading that such an item was contained in the Bill of Quantities121.
[275] The monetary part of the claim is constituted by allegations as to the hours engaged in
the task together with the quantity of crushed rock used122
. The only support for that
allegation is the letter written by Mr Eames of 18 February 2000123 to Stork which he
refers to as Variation 203. Mr Digby QC disavowed any claim based on a variation124
.
Nevertheless, CCPL referred to the refusal by Stork to agree to the variation in Stork’s
memorandum of 23 May 2000125
.
[276] There is no evidence to support the allegation that the for-construction drawings
included laying 150mm thick 20 mm aggregate (no fines) crushed rock at substations 1
and 2. Mr Leck says that the drawings alleged to contain that particular did not do so126
.
Mr Robinson agreed with that in the joint report127 and Mr Alsop made no comment on
it.
[277] The detail of the claim is supported to a limited extent by the evidence of Mr Eames
who said that the letter of 18 February 2000 set out his summary of the facts relating to
the crushed rock issue.128
[278] That letter, though, does not constitute an application for adjustment of a lump sum as
pleaded or at all.
[279] In the absence of evidence to support this part of the pleaded claim it must be
dismissed.
(xiv) The Ammonia Spill Standby Claim
[280] This claim is contained in paragraphs 229 to 243 and attachment J of the FFASC. It
relates to an ammonia spill which occurred on site on 18 January 2000. Stork directed
CCPL to evacuate the site and to submit time sheets reflecting the loss of hours of staff
and employee’s wages for payment by it. Pursuant to that direction, CCPL provided
the information required and claimed the sum of $40,025.
[281] CCPL’s claim is pleaded in two ways. First, it is pleaded as a claim made pursuant to
cl 47.1 of Exhibit D of the Subcontract. That pleading is based upon the direction given
by Stork being a direction under cl 39 of Exhibit D which gives rise to a capacity to
make the claim and, in the absence of payment, to make a claim for interest. Secondly,
120 T297.
121 Para 204 FFASC.
122 Para 211 FFASC.
123 Ex 44, Tab “Crushed Rock”.
124 T 296/45.
125 Ex 44, Tab “Crushed Rock”.
126 Ex 53.
127 Ex 36.
128 T 296
-- 58 of 81 --
59
and in the alternative, CCPL pleads that the request by Stork and the agreement by
CCPL to halt works as a result of the spill and to submit timesheets reflecting the loss
staff and employee’s wages and plant constituted an agreement.
[282] Stork submits that the claim as first pleaded has not been established because there was
insufficient or no evidence to demonstrate that CCPL incurred more cost than it
otherwise would have but for the suspension. It further is submitted that the evidence is
insufficient to demonstrate that the costs which are particularised in the pleading were
incurred as a result of the ammonia spill. That latter submission is correct. There was
no evidence led which could establish the assertion that CCPL incurred more cost than
it otherwise would have but for the suspension.
[283] On the alternative ground for the claim the evidence, though, is that Mr Jewell, on
behalf of Stork, issued a memorandum to CCPL and others to this effect:
With the recent disruptions on site re the Ammonia incident I require
all companies to submit timesheets reflecting the loss of hours as
listed below, these timesheets are to reflect staff, wages, employees
and plant.
Tuesday 18 th January = 2 hrs
Wednesday 19th January = 8 hrs
Thursday 20th January = 8 hrs
Friday 21 st January = 8 hrs
[284] In response to that Mr Eames, for CCPL, provided a letter referring to the shutdown
and attaching a schedule setting out expenses relating to both labour and plant.
[285] Mr Howard, for CCPL, gave evidence that after the spill Stork required everyone to
evacuate to a nearby depot outside the fenced area. During that time there was a mass
meeting at which safety on site was discussed and which was attended by
representatives from Stork and other contractors on site. He said that Stork
representatives – either Mr Jewell or Mr Mazur – said that “no one would be out of
pocket and that we would be reimbursed”.
[286] Mr Howard gave evidence that the timesheets sought by Stork were provided and that
they contained the details sought129 . There is no reason not to accept that those figures
were accurate.
[287] I find that there was an agreement between the parties with respect to the evacuation of
the site as a result of the ammonia spill. Stork required CCPL to remove all persons
from the site which had the inevitable consequence that none of the plant could be
used. In fact, CCPL could not use staff, subcontractors or plant as a result of Stork’s
directive. It would, though, have incurred some cost in having to pay for labour or
plant which could not be gainfully engaged. The evidence is sufficient to establish, on
the balance of probabilities, that the document purporting to set out the expenses
incurred by CCPL was accurate and did, in fact, represent the costs incurred both for
staff and plant. There is one entry in the schedule relating to lost wages which was not
explored in evidence. The last entry on the schedule is the name “Paul Robinson* 4”.
The only reference to “Paul Robinson” in the trial is in evidence by Mr Howard to the
effect that Paul Robinson was a concreting subcontractor who did work on footpaths
and similar types of structures. Given that the entry against his name is four times
129 T 463.
-- 59 of 81 --
60
greater than all the other entries, it is reasonable to conclude that it refers to four
employees of that subcontractor.
[288] I find that CCPL has proved its claim under this heading for the amount of $40,025.
Recovery under s 42(4) QBSA Act
[289] Section 42(4) provides that a person is not prevented under s 42(3) from claiming
reasonable remuneration but any such amount is subject to the following conditions:
(a) It cannot be more than the amount actually charged,
(b) It cannot include an allowance for:
(i) The supply of the person’s own labour,
(ii) The making of a profit by the person for carrying out the
building work,
(iii)Costs incurred by the person in supplying materials and labour
if the costs were not reasonably incurred.
(c) It cannot be more than an amount which was agreed to as the price for
carrying out the building work, and
(d) It cannot include any amount paid by the person that can be fairly
characterised as being, in substance an amount paid for the person’s own
direct or indirect benefit.
[290] In [209] of its written submission, Stork argues that while CCPL pleads that s 42(3) of
the QBSA Act operates subject to s 42(4) it does not claim any entitlement to
reasonable remuneration pursuant to that subsection. That is not quite correct. In
paragraph 39 of CCPL’s second amended reply and answer, it pleads, in [39], as
follows:
“Further to paragraph 37 hereof if it did undertake building work as
defined by the QBSA Act, which is not admitted but for the reasons
set out in paragraphs 26 to 36 hereof specifically denied, pursuant to
s 42(4) of the QBSA Act it is entitled to reasonable remuneration for
carrying out the building work.”
[291] That is not, of course, a pleading of a claim. It is only the pleading of an entitlement
which is a prerequisite to the making of a claim. It does not descend to any
particularity; it does not identify any amount that might be claimed. Also, any such
claim should be in the Statement of Claim.
[292] The plaintiff came closest to making a formal claim in the final oral submissions made
on the last day of the trial. Mr Digby QC, for CCPL, said:
“Your Honour will be aware that in paragraph 39 of the reply the -
can I call it a defence for the moment, your Honour? -- the defence
under clause 42(4) of the QBSA is raised by the plaintiff. Your
Honour is also aware, having presided over the trial, that the case
[has proceeded] on the basis of evidence being put forward by both
parties and tested in relation to what would be an appropriate
reasonable remuneration: Mr Same's report on the part of the plaintiff
and Miss Janine Smith's report on the part of the defendant.
Now, we're not sure precisely how this point in the opening is put
and whether it [is] said that notwithstanding that - the question of
reasonable remuneration is raised in the reply the plaintiff puts
forward and has been addressed in the evidence and in submissions,
including opening submissions -- the defendant is saying at the end
-- 60 of 81 --
61
of the day [that] your Honour is precluded from applying the
provisions of clause 42(4) because of the matter arising not as a
positive claim, but as a reply to the counterclaim which is put
forward in our learned friend's [pleadings].
If that were how the matter was put, then we would seek leave to
draft that same paragraph in the reply into the statement of claim [if
there needs] to be a positive allegation to enable your Honour to deal
with 42(4) of the QBSA and the particulars of the reasonable
remuneration that is advanced would be by reference to the report of
Mr Same from […] KNP.” 130
[293] That was a curious submission given the requirements of the Uniform Civil Procedure
Rules and the remarks and reasons of Moynihan SJA in his decision given on 16
March 2004 (almost four years to the day before Mr Digby QC made his submission)
where, in respect of the same point, he said:
“[55] The claims do not seem to me to be pleaded in terms of a claim
under s 42(4) of the Act. The point needs to be clarified. Any claim
under s 42(4) should be properly pleaded in the statement of claim.
In an earlier round of pleadings the plaintiff pleaded (in an amended
reply of 2 November 2001), a claim under s 42(4). There is,
however, correspondence suggesting that such a claim is not being
pursued.”131
[294] Notwithstanding the unsatisfactory nature of the pleading on this point, the plaintiff
called evidence, without objection, ostensibly on the topic of reasonable remuneration.
[295] It is an essential first step in any assessment under s 42(4) to determine the “reasonable
remuneration” for the particular item of “building work”. I was not addressed on what
the term “reasonable remuneration” means in that section. Although the terms are not
coincident in meaning, limited assistance can be obtained from consideration of some
of the many cases which deal with a claim for quantum meruit.132 An authority
frequently referred to in this area is Flett v Deniliquin Publishing Co Ltd 133 in which
Herron CJ said:
“In a case of quantum meruit the value of the services rendered is, as
the Latin expression implies, a claim for what the services
reasonably were worth. It is therefore properly assessed at the normal
market rate or price prevailing when the benefit was received. In
seeking a measure of reasonable reward, the parties’ ineffective
contract may be looked at for this purpose and in some cases the
degree of benefit conferred on the defendant may be taken into
account: Way v Latilla [1937] 3 All ER 739. But there must be
some evidence of a market or prevailing price. … [His Honour
described the inadequacy of the evidence.] … Put in another way,
there was no external standard to which the trial judge could
refer to define the quantum of the claim.”134 (emphasis added)
130 T 792-793.
131 Cook’s Construction Pty Ltd v Stork ICM Australia Pty Ltd [2004] QSC 066.
132 “the amount deserved”.
133 [1964-5] NSWR 383.
134 At 385-386. Ferguson J agreed. See also Horton v Jones [No. 1] (1934) 34 SR (NSW) 359 at 368.
-- 61 of 81 --
62
The use of a price stated in a contract as evidence, but as evidence only, on the question
of amount, was also confirmed in Pavey & Matthews Pty Ltd v Paul ,135 Gino
D’Alessandro Constructions Pty Ltd v Powis, 136 and Iezzi Constructions Pty Ltd v
Watkins Pacific (Qld) Pty Ltd.137
[296] Three witnesses were called on this topic. For the plaintiff, there was Mr Norman
Same, a forensic accountant from knp Solutions, and Mr Rodney Alsop, a quantity
surveyor. For the defendant, there was Ms Janine Smith, a forensic accountant from
Vincents.
[297] Before I consider the evidence on this issue, I should, briefly, revisit some of the basic
principles applicable to expert evidence because they appear to have been overlooked
with some of the reports which were tendered.
[298] It is trite law that for an expert opinion to be of any value the facts upon which it is
based must be proved by admissible evidence.138 In Trade Practices Commission v
Arnotts Ltd (No. 5), 139 Beaumont J reviewed a number of common law authorities and
concluded: “In my opinion, these authorities establish that there is a rule of evidence at
common law that, except in a straight-forward uncomplicated case, where the facts are
admitted and readily identified, the opinion of an expert is admissible only where the
premises, that is to say, the facts upon which his or her opinion is based, are expressly
stated.”140
[299] More recently, Heydon JA, in Makita (Australia) Pty Ltd v Sprowles, 141 undertook a
detailed examination of the law in this area and, notwithstanding that he was concerned
with the Evidence Act 1995 (NSW), the following principles are also applicable at
common law: 142
“[85] In short, if evidence tendered as expert opinion evidence is to
be admissible, it must be agreed or demonstrated that there is a field
of “specialised knowledge”; there must be an identified aspect of that
field in which the witness demonstrates that by reason of specified
training, study or experience, the witness has become an expert; the
opinion proffered must be “wholly or substantially based on the
witness’ expert knowledge”; so far as the opinion is based on facts
“observed” by the expert, they must be identified and admissibly
proved by the expert, and so far as the opinion is based on “assumed”
or “accepted” facts, they must be identified and proved in some other
way; it must be established that the facts on which the opinion is
based form a proper foundation for it; and the opinion of an expert
requires demonstration or examination of the scientific or other
intellectual basis of the conclusions reached: that is, the expert’s
evidence must explain how the field of “specialised knowledge” in
which the witness is expert by reason of “training, study or
experience”, and on which the opinion is “wholly or substantially
based”, applies to the facts assumed or observed so as to produce the
135 (1987) 162 CLR 221 at 252, 257.
136 [1987] 2 Qd R 40 at 58-59.
137 [1995] 2 Qd R 350 at 355.
138 Price v John Holland (Constructions) Pty Ltd (1985) 59 ALJR 844 at 846.
139 (1990) 21 FCR 324.
140 At 330.
141 (2001) 52 NSWLR 705.
142 See Interline Hydrocarbon Inc v Prenzil Pty Ltd [2005] QSC 109 at [14].
-- 62 of 81 --
63
opinion propounded. If all these matters are not made explicit, it is
not possible to be sure whether the opinion is based wholly or
substantially on the expert’s specialised knowledge. If the court
cannot be sure of that, the evidence is strictly speaking not
admissible, and, so far as it is admissible, of diminished weight.
And an attempt to make the basis of the opinion explicit may reveal
that it is not based on specialised expert knowledge, but, to use
Gleeson CJ’s characterisation of the evidence in HG v The Queen (at
428, [41]), on ‘a combination of speculation, inference, personal and
second-hand views, as to the credibility of the complainant, and a
process of reasoning which went well beyond the field of expertise’.”
(emphasis added)
[300] In this case, some of the experts (from both sides) made rather bald statements that
some rate or other matter was, in their opinion, reasonable. That is insufficient. It was
put by Anderson J in this way:
“Mr Adam gave oral testimony and attempts were made to lead from
him evidence that would show that he had personally verified the
data relied on for his estimates or had direct knowledge of the
matters relied on. In my opinion, his evidence did not go that far. If
anything it underlined the fact that he truly had relied on a range of
material reported to him or provided by others. No doubt he treated
the data he was given with appropriate circumspection and accorded
to it more or less reliability according to his own views about the
quality of it and of its provenance and no doubt in doing so, he called
upon his own personal experience. Whilst in one sense this
constitutes bringing his own judgment to bear on the task of
valuation, I do not think it overcomes the fundamental difficulty.
Expert opinion is to be judged like any other evidence. It must be
comprehensible and reach conclusions that are rationally based. The
process of inference that leads to the conclusions must be stated or
revealed in a way that enables the conclusions to be tested and a
judgment made about the reliability of them. This requirement is not
satisfied by evidence from an expert which says, in effect: “I have
examined the costings and estimates made by others and on the
strength of my own expertise and experience in the field I believe
them to be reasonable.”
“Such a forensic device overlooks the most important rule that it is for
the court to judge the reliability of evidence given in support of the
case. If an opinion relies on facts that must be proved or assumptions
that must be verified, it is to the court that they must be proved and
verified, not to the expert witness.”143
[301] In an article144 on the reform of law relating to expert evidence, Dr Freckelton SC
examined the reasoning in Makita and other cases and, in a conclusion with which I
respectfully agree, said:
“Under the common law, it is tolerably apparent that a failure to
prove the bases of an expert’s opinion would render the opinions
themselves inadmissible. (See R v Abadom [1983] 1 WLR 126 at
143 Pownall v Conlan Management Pty Ltd (1995) 12 WAR 370 at 389-90
144 Expert Evidence Law Reform (2005) 12 JLM 393.
-- 63 of 81 --
64
131, interpreting R v Turner [1975] 1 QB 834; Jeffrey v The Queen
(1991) 60 A Crim R 384 at 389; Bevan Investments Ltd v Blackhall
and Struthers (No 2) [1978] 2 NZLR 97 at 122; Forrester v HM
Advocate [1952] JC 28) There is much to be said for the
straightforwardness of such an approach as it precludes the expert
from functioning as the undisclosed conduit for others' views and for
facts that are incapable of effective evaluation.”
The accountants’ evidence
[302] The evidence from Mr Norman Same was contained in a written report. It is of no
assistance, for two reasons. First, notwithstanding the importance of this issue, the
plaintiff did not instruct Mr Same until mid-December 2007 – some two months before
the trial and some eight years after the events in question. It is not surprising, given the
delay by the plaintiff in dealing with this issue, that important documents upon which
Mr Same might have been able to rely in his report were unavailable. Mr Same noted
in [5] of the summary of his opinion:
“5.1 My ability to accurately calculate the expenditure that qualifies
as reasonable remuneration for carrying out building works as
defined at 1.2 is limited as Cook’s could not locate:
(a) project costing work papers or estimates relating to
the ANP project.
(b) third party invoices or statements detailing costs of
various items purchased for the ANP project.
(c) any other supporting documentation or work papers
that would assist in confirming the expenses incurred.
5.2 Allocated overheads are apportioned by project revenue as a
percentage of company revenue. This allocation has not yet been
tested.”145
Further, his conclusion on the profit and loss statements provided to him by CCPL was
based on that company’s general ledger and no verification was possible which
distinguished the project the subject of this action and any other project undertaken by
CCPL at that time.146 Thus, there was no way of identifying costs and expenses which
were solely related to the project, let alone any individual part of the project.
[303] Secondly, although Mr Same says that he had been “instructed to calculate the amount,
in accordance with section 42(4) of the Act, that Cook’s is entitled to claim as
reasonable remuneration for carrying out building works assuming all the work alleged
to be “building work” as defined by the act was “building work” for the project
conducted on behalf of Stork …”,147 he did not undertake that exercise. In his
calculation of reasonable remuneration he recreated a profit and loss statement for the
project rather than for any of the parts of the undertaking alleged to be building work.
This conclusion, accurate or not, does not allow any opinion to be formed as to the
reasonable remuneration of each of the items of “building work”. It did not refer to any
“external standard” to define the quantum.
145 Ex 42.
146 Ex 42, [6.4].
147 Ex 42, [2.2].
-- 64 of 81 --
65
[304] It is unfortunate that no attention was given by two of the witnesses148 called on this
topic, to the fact that, in a case such as this, it will be necessary to identify the work the
subject of contention and, then, to assess the reasonable remuneration in respect of
each item.149 Each claim should have been the subject of an individual assessment by
those witnesses, if they were otherwise qualified.
[305] The area of expertise which is relevant is that possessed by quantity surveyors. CCPL
called Mr Alsop. While Stork called Mr Leck, he did not give any evidence on this
point.
[306] Mr Alsop’s report,150 like others tendered by the plaintiff, was only made available
during the trial. He was first engaged in mid December 2007 and he says he was
retained to “present an indication of the fair value of the works, based on the
Contractual Documentation and Other matters made available to me.”151 Why he was
asked to consider “fair value” rather than “reasonable remuneration” was not
explained. It was not a concept which was pleaded. It is not a term found in the QBSA
Act.
[307] In re-examination, Mr Alsop said that, in his opinion, there is no difference between a
reasonable rate and the concept of a fair value.152 That may well be correct, but it does
not deal directly with the concept of “reasonable remuneration”, of which a rate may
only be one part of the assessment.
[308] His report is called in aid for other claims which are considered elsewhere, but on the
issue of “reasonable remuneration” it is of no assistance for the following reasons:
(a) Some of the documents upon which he relied were not in evidence,
namely:
(i) Report of Simon Tormey & Associates, Chartered Quantity
Surveyors, 16 August 2005;
(ii) Claim for Differences following Stork April Assessment,
undated;
(iii) file marked Miscellaneous Documents including ‘Notes on
Major differences between Cook’s April Progress Claim and
Stork’s Assessment’ and two affidavits of Warren Eddie;
(iv) the drawings (listed in Appendix B) which were supplied to
Mr Alsop.
(b) Mr Alsop relied upon measurements obtained using a digitiser but it
was not established that the plans he used were those which were
pleaded or in evidence.
(c) It cannot be determined from his report whether he used the profiles
or dimensions marked up on the pleaded drawings.
(d) When he expressed a view with respect to the “building work”
claims he referred to the “value” of each item and not the
“reasonable remuneration” for each item.
[309] If the “reasonable amount” can be determined, then the next steps are to assess it
against the criteria in s 42(4)(a)-(d):
148 Mr Same and Ms Smith.
149 Hansen v Mayfair Trading Co Pty Ltd [1962] WAR 148; Re Allison, Johnson & Foster Ltd; ex parte
Birkenshaw [1904] 2 KB 327.
150 Ex 39.
151 Ex 39 at p 1.
152 T 612/1-4.
-- 65 of 81 --
66
(a) Is the “reasonable amount” more than actually charged? If so, it
must, subject to any other reductions, be reduced to the amount
charged.
(b) Does the “reasonable amount” include any allowance for: supply of
the “person’s” labour; the making of a profit; or costs not reasonable
incurred in supplying labour and material? If so, it must be reduced
by such amounts.
CCPL raised the question of how the “supply of the person’s labour”
can be applied to the case where the builder is a corporation. The
Acts Interpretation Act 1954 provides 153 that “a reference to a person
generally includes a reference to a corporation as well as an
individual”. In this context, I think that “person” should be read as a
reference to an individual. It is, I think, intended to deny to an
unlicensed person any return for his or her own labour. To read
“person” as a corporation would be to deny the costs associated with
employment of workers. Section 42(4)(b)(i) should be read as not
having any effect so far as employees’ costs are concerned.
Unreasonable labour costs are dealt with in s 42(4)(b)(iii).
It is unnecessary to deal with s 42(4)(b)(ii) or (iii) except to note that:
without a definition of “profit” it would be difficult to assess that
exclusion; and the notion that costs unreasonably incurred should be
excluded from “reasonable remuneration” seems unnecessary as the
assessment of reasonable remuneration should have already excluded
any unreasonably incurred expense.
(c) Is the “reasonable remuneration” more than an agreed price? If so, it
must, subject to any other reductions, be reduced to the agreed price.
(d) Does the “reasonable remuneration” include any amount paid for the
person’s direct or indirect benefit? If so, it must be reduced by that
amount.
This is, in essence, an “anti-avoidance” provision designed to
preclude the use of a scheme to avoid the effect of s 42(4). In the
Explanatory Note accompanying the amending Bill154 the following
was said with respect to this sub-section: “it is designed to attack any
scheme entered into by the unlicensed contractor, for example
employing the contractor’s child or the charging of a management
fee by a company of which the contractor is a beneficial shareholder,
to use this new provision to gain personal profit from unlicensed
contracting.”
[310] Mr Same’s report did not attempt to take the first step because, as he admitted, he was
not an expert in determining reasonable costs associated with building work.155
Further, no effort was made in that report to identify the reasonable remuneration for
any one of the individual claims made by CCPL alleged by Stork’s to be “building
153 Section 32D.
154 Queensland Building Services Authority Amendment Bill 1999.
155 T 633/36-37.
-- 66 of 81 --
67
work”. Instead, Mr Same provides four alternative amounts which, he says, could be
reasonable remuneration for carrying out all of the building work under the
Subcontract.
[311] At [6.25] of his report, Mr Same says:
“In order to calculate the reasonable remuneration that Cook’s is
entitled to, I have recreated a profit and loss statement for the project
based on the ANP profit and loss statements concluded on above in
6.4.”
[312] He then sets out profit and loss statement in which he arrives at a conclusion relating to
the “reasonable cost of project”. At the foot of the table there is a note:
“The reasonable cost of project also equals the sum of total expenses
per general ledger plus total other expenses.”
[313] The conclusion is irresistible that the figure referred to by Mr Same in his report as
being the “reasonable cost of project” is, indeed, his assessment of the cost of the entire
undertaking engaged in by CCPL. There is nothing to suggest that he has in any way
attempted to provide any amount which is able to be related to either any single one of
the “building work” claims or all of them. That conclusion is supported by the response
by counsel for CCPL during final submissions where he agreed that Mr Same based his
report on the entire project.156
[314] I was invited by the plaintiff to engage in an exercise whereby I would compare the
reasonable remuneration assessed by Mr Same ($16.153 million) with the amount paid
to the plaintiff ($16.425 million) and that I could then order a reimbursement of the
defendant by the plaintiff in an amount equal to the difference between those two
figures. Other means of arriving at the “reasonable remuneration” for the total of the
items included in the “building work” were also suggested in submissions, but none of
them could overcome the principal problem – no attempt had been made to assess
“reasonable remuneration”.
[315] Another argument was advanced that CCPL, having made a loss on the entire
operation, should be able to claim anything that was expended by CCPL as “reasonable
remuneration”. Apart from the doubtful integrity of that as an accounting exercise, it
does not necessarily follow that the making of a loss means that the amount charged
was reasonable. History is replete with instances of businesses making losses even
when their prices were unreasonably high.
[316] It follows, then, that there is no evidence upon which the provisions of s 42(4) can act.
[317] Ms Smith did not advance any evidence by which the reasonable remuneration for any
of the items under consideration could be assessed. Ms Smith’s report was infected by
the same vices as Mr Same’s. She did not have the expertise to deal with the costs of
construction and her approach was on a whole of project basis.
The Counterclaim
[318] In paragraphs 106 to 112 of the FFADC Stork pleads a claim for the payment by CCPL
to Stork of the money received by CCPL from Stork for the “building work”.
156 T 793.
-- 67 of 81 --
68
[319] The claim is based on the allegations that CCPL was not licensed within the meaning
of the QBSA Act, that it impermissibly performed work for which it was not licensed,
and that Stork paid it for that work.
[320] Section 42(3) of the QBSA Act provides:
“Subject to subsection (4), a person who carries out building work in
contravention of this section is not entitled to any monetary or other
consideration for doing so.”
[321] The effect of s 42(3), together with the balance of s 42, was considered in Marshall v
Marshall .157 In that case, McPherson JA said:
“In my opinion, the effect of s. 42(3) is to prevent an unlicensed
builder, in proceedings of any kind, from recovering the price or any
part of it payable under a contract for building work carried out in
contravention of the section. Taken by itself, that might perhaps not
prevent a builder from receiving money voluntarily paid by the other
party. The terms of s. 42(3) are, however, very wide. A person who
carries out work in contravention of s. 42 is “not entitled” to any
“monetary consideration” for doing so. According to the ordinary
meaning of those words, a person receives a “monetary
consideration” for carrying out work if he is paid for doing it. The
sum of $51,000 paid by the plaintiff to the defendant satisfies that
description. Counsel were unable to refer the Court to authority
bearing in any relevant way on the meaning of “entitled” in a context
like this. But s. 42(3) expressly declares it to be money to which
the recipient is “not entitled”, which can only mean that it is
money to which he has in law no right or title. If that is so, there
is no identifiable basis on which he can, as against the person
who paid it, claim to keep or retain it or its equivalent.”158
(emphasis added)
[322] Whether the plaintiff could recover the amount she paid to the builder was considered
next. His Honour said:
“If she was not legally obliged to make the payment, but did so under
the mistaken belief that she was, then the money is recoverable in
restitutionary proceedings even though the mistake was one of law.
See David Securities Pty Ltd v. Commonwealth Bank of Australia
(1992) 175 CLR 353. The plaintiff here has a finding to that effect in
her favour. The mistake must, of course, be one without which the
payment would not have been made: Kelly v. Solari (1841) 9 M. &
W. 54, 58; 152 E.R. 24, 26. What Parke B. said there was directed to
a mistake of fact; but, given that, since the decision in David
Securities money paid under a mistake of law is now recoverable, the
same general principle must also apply to recovering a payment
made under a mistake of that kind. In determining whether or not the
mistake of law has that character here, it is, in my respectful opinion,
first of all necessary to determine whether the effect s. 42, and in
particular of s. 42(3), is to relieve the plaintiff of any legal obligation
to pay the price or any part of it. It is only if there was no such legal
obligation that the plaintiff can claim to recover her payment as
157 [1999] 1 Qd R 173.
158 At 176.
-- 68 of 81 --
69
money paid under a mistake of law. Once that is shown, it may not
be necessary to make the further inquiry whether s. 42(3) also has the
effect of denying the defendant the right to retain the money so paid.
The plaintiff may, on the authority of David Securities Pty Ltd v.
Commonwealth Bank (1992) 175 C.L.R. 353 be entitled without
more to recover the money paid. But if the payment was made in
pursuance not merely of a mistake of law but under an
agreement or transaction that was prohibited and made an
offence by statute, then the plaintiff needs to go the further
length of establishing that the statutory prohibition does not
preclude her from recovering what she has paid.
Far from preventing the plaintiff from recovering the sum paid to the
defendant for the building work carried out in contravention of the
statutory prohibition, s. 42(3) of the Act does, for the reasons already
given, enable her to recover that payment. If the defendant was not
entitled to any monetary consideration for carrying out building
work in contravention of s. 42, then, as I would interpret s. 42(3),
he is not entitled to retain the payment made to him for doing it.
Because the prohibition in s. 42 was enacted for the benefit of a
class of persons of whom the plaintiff is one, she is entitled to
recover the payment she made to the defendant. On that footing,
it may be that she would have been entitled to recover the whole of
the sum paid by her; but at trial and on appeal, she was prepared to
allow to the defendant the value of the work, which in effect involves
reducing the amount of $51,000 by the cost of rectifying the defects
or deficiencies in the work done by him.” 159 (emphasis added)
[323] Pincus JA and de Jersey J (as he then was) approached the matter in a more direct way
but, essentially, agreed with that statement of principle and said:
“The learned judge found that in making the payments totalling
$51,000, the respondent mistakenly believed that the first appellant
— the actual builder — “was entitled to payment by law and that she
was obliged to pay him”. On any reasonable construction of s. 42(3),
because the first appellant was not appropriately licensed, the
respondent was not obliged to pay him in accordance with her
apparent contractual obligation. Consistently with David Securities
Pty Ltd v. Commonwealth Bank of Australia (1992) 175 C.L.R. 353,
the judge would therefore have ordered the reimbursement of the
$51,000, but he deducted $16,672.50, being the true value of the
work done, which left the respondent with a judgment for
$34,327.50.” 160
[324] Further, their Honours said:
“The respondent was not however merely seeking the recovery of
moneys paid under an illegal contract. The judge accepted her other,
and primary, claim, which was that the moneys were repayable
because paid under a mistake. In light of David Securities and the
judge's finding of fact - which is unassailable - his conclusion
necessarily followed, and renders unnecessary any further
consideration of the precise scope of s.42(3). That is so because the
159 At 178-179.
160 At 180.
-- 69 of 81 --
70
respondent's mistake, as to her obligation to pay, was relevant on
any reasonable interpretation of sub-s(3), which plainly excused
her from any obligation to pay under the contract in these
circumstances.”161 (emphasis added)
[325] It follows, then, that Stork, if it can otherwise prove its claim, can recover the money it
paid to CCPL for work covered by the QBSA Act and for which CCPL was unlicensed.
[326] In order to succeed Stork must establish that:
(a) the work which is the subject of the Counterclaim was “building
work” within the meaning of the QBSA Act; and
(b) the payments made by the defendant to the plaintiff included
payment for such “building work”;
(c) the payments for such “building work” comprised “monetary or
other consideration” within the meaning of section 42(3) of the
QBSA Act; and
(d) the defendant made the payments in the mistaken belief that:
(i) it was obliged to do so;
(ii) the plaintiff was lawfully entitled to receive them; and
(iii) the plaintiff had complied with clause 16.1 of Exhibit D to
the Subcontract (being the admitted express term of the
Subcontract requiring the plaintiff to comply with
Queensland legislation).162
[327] CCPL makes particular reference to the identification in paragraph 107 of the FFADC
of the “building work”. That paragraph pleads:
“[107] Certain of the work performed by the Plaintiff under the
Subcontract was ‘building work’ within the meaning of the QBSA
Act as in force during the relevant period (‘the building work’).
Particulars
Further particulars of the building work are contained in document
133 filed on 2 June 2006.”
[328] It says, correctly, that document 133 has no greater status than that of a pleading and
then argues that:
(a) there is no evidence of the work involved in the “building work”;
(b) there is no evidence of the time at which the work was done;
(c) there is no evidence as to the applicable rate or rates;
(d) there is no evidence as to the extent of the work performed;
(e) there is no evidence to support the inclusion of some of the work as
part of the “building work” ; and
(f) there is no evidence of payment by Stork for the “building work”.
[329] The first step must be to determine whether Stork has proved that the work identified
in Document 133 was, in fact, done, and then, whether it was work for which CCPL
was unlicensed.
[330] I have determined in other parts of these reasons that the claims by CCPL with respect
to:
(a) quantities of footings;
161 At 180
162 Stork’s Written Submissions, para 650.
-- 70 of 81 --
71
(b) pedestals;
(c) Corrocem;
(d) suspended slabs; and
(e) the prill storage building structures
are claims for “building work” within the meaning of the QBSA Act.
[331] It will assist if I identify the provenance of Document 133. In various paragraphs of the
FFASC the plaintiff identifies a document entitled “Assessment of Approved
Payments” in the particulars of an allegation that Stork has paid a certain amount to
CCPL for work performed by CCPL 163 . In particular, CCPL refers to that document in
support of its allegations concerning the following claims:
(a) quantities of footings – paragraph 107;
(b) pedestals – paragraph 124;
(c) Corrocem – paragraph 147;
(d) suspended slabs – paragraph 164; and
(e) the prill storage building structures – paragraph 181.
[332] In January 2008, Stork’s solicitors sought a copy of that document from CCPL’s
solicitors. The document they provided is part of WGM-4 in Exhibit 61. That
document became Exhibit 24 in this trial.
[333] Exhibit 24 was identified by Mr Eames as the last progress claim made by CCPL 164 . It
records the payments alleged by CCPL to have been made by Stork for each item of
work undertaken by CCPL 165 . The document lists the work which was performed
under each particular type of work. For example, under the heading “Bulk Earthworks”
and the subheading “Plant Site Bulk Earthworks” it lists things such as: “Top Soil
Removal to 300mm depth”, “Bulk Excavation”, “Engineered Fill” and so on.
[334] Stork used a document similar to Document 133 as the basis for the particulars it
provided of paragraph 112(b) of its counterclaim in June 2006. It contains the same
information regarding quantity, unit rate and amount as Document 133/Exhibit 24. It
also contains columns headed “‘Building Work’ Direct” and “‘Building Work’
Allocation”. Those columns appear in the document which constitutes Appendix B to
Stork’s written submissions. But Stork only claims for the amounts under the heading
“‘Building Work’ Direct”.
[335] In its submissions on the counterclaim CCPL refers to Document 133 for its references
to various items in the counterclaim. Stork refers to the document in Appendix B. Both
of those documents are directly related to Exhibit 24. All those documents contain the
same references to items of work or material. As this a claim by Stork, I will refer to
the document that constitutes Appendix B. Appendix B only refers to work under the
heading “Footings”. Stork abandoned any claim to the variations noted on pages 45-50
of Appendix B and it makes no claim for other work found to come within the QBSA
Act such as pedestals, Corrocem and so on.
[336] The amount claimed by Stork for the whole of what it says is “building work” is
substantial – $9,983,796.54 – and a great deal more than the amount alleged by CCPL
to have been paid by Stork for the claims I have found to be “building work”. The
163 It is referred to in the particulars of paragraphs 10, 22, 35, 47, 59, 71, 107, 124, 135, 147, 164, and
181 FFASC.
164 T 368-369.
165 T 465.
-- 71 of 81 --
72
difference arises because the claims by CCPL are only for additional work it said was
required (usually) by changes made by the for-construction drawings. Thus, for
example, CCPL’s claim for the additional work under the heading of “Quantities of
Footings” was $77,090.36 (including the amount alleged to have been paid) whereas,
Stork’s counterclaim is for all of the payments made for “building work” entailed in
the footings.
[337] The issues which arise are these:
(a) What is the work in Appendix B?
(b) Is that work “building work”?
(c) Was that work paid for by Stork?
(d) If the work was paid for, was that payment made by mistake?
What is the work in Appendix B?
[338] CCPL argues that there is no proof that, whatever the work is in Appendix B, it was
work which was performed under the Subcontract. That is a submission which must
fail, given that Appendix B is drawn directly from Exhibit 24 which is the final
progress claim from CCPL for the work which it had performed166 . There was no other
contractual relationship between CCPL and Stork and Exhibit 24 is in the form used by
CCPL for other claims under the Subcontract. Although Stork pleaded that the work
was done under the Subcontract167 , that is not a necessary element of its cause of action
for repayment of the sum in question. Section 42 of the QBSA Act takes effect when
the work is done – the general, contractual basis for the work is irrelevant.
[339] The only work to which the counterclaim attaches is work which appears under the
heading “Footings”. It is work for which, according to CCPL, it has been paid by
Stork. Whether any of the items appear in the various schedules of the Subcontract168 is
irrelevant to the relief available to Stork. Similar irrelevant issues raised by the
Plaintiff include: when the work was done169 , what the appropriate rates were170 , and
the extent of the work performed.
Is that work “building work”?
[340] I have considered the meaning of the term “building work” as used in the QBSA Act
above. The plaintiff attacks this part of the counterclaim on the basis that Stork has not
demonstrated that each of the items under the heading “Footings” has been proved to
constitute “building work”. The objection goes on to say that there is no evidence as to
what work was involved in the Subcontract Footing items. That, as I have pointed out
above, is not to the point. Exhibit 24 demonstrates that CCPL did the work set out in
that document and Stork paid the amounts recorded in it. The point made by CCPL
which Stork must answer is whether the work recorded was “building work”. It is not
enough simply to assume that each item under the heading “Footings” is “building
work” because of the finding that the footings work the subject of the plaintiff’s claim
was “building work”. A closer analysis is needed.
166 T 368-369
167 Para 107, FFADC
168 Para 162-164, Plaintiff’s Written Submissions
169 In any case, it can only have been done during the period of the contract and before Exhibit 24 was
issued by CCPL.
170 It is the amount paid by Stork which is relevant.
-- 72 of 81 --
73
[341] Most of the items which are set out under “Footings” were the subject of evidence and
were extracted in Appendix E of Stork’s Written Submissions. For example:
Footings,
Pedestals
and Plinths
generally
Mr Eames gave the following evidence describing footings, pedestals and
plinths, and the nature of the work involved in their construction.
“The first difference which immediately comes to mind is the numerous
small pedestals and plinths that are shown on the drawing-----
Are they part of what you refer to as "footings"?-- Yes.
And where are they?-- Because they are actually part of the footing
structure.” (T232)
…
Can I ask you to say to his Honour, if you can, what it is that is the
distinguishing feature of a footing compared with a pedestal and vice
versa, how does his Honour distinguish between a pedestal and a
footing?-- Your Honour, a pedestal is in general terms a small
square or rectangular concrete arrangement which sits above a
surface to support the foot - or the leg of a structure. Whereas a
footing is generally considered to be a bigger arrangement, more
substantial arrangement upon which, you know, a large object
would sit rather than just a single or some type of leg
arrangement.” (T237)
…
MR DIGBY: ….. can you describe to his Honour what work is
involved in constructing that pedestal as well as supplying the
concrete?-- The work that's involved is the steel cage, the
reinforcing cage inside the pedestal, even though it's only small, still
has to be tied. The formwork - the formwork has to be placed -
formed up and placed around the outside of the steel work. The
holding down bolts which go into these pedestals had to be set up and
located very accurately. There was still a requirement for the surveyor
to come and survey them to make sure that everything was in exactly
the correct position. And then the concrete had to be brought in and
poured and vibrated into place.” (T243)
…
And what's - with the term "raised plinths", is that the same as or
related to or different from the pedestals that we've been talking about?-
- A "plinth" is a structure, dimensions of like of a pedestal, but
placed upon an existing structure, existing concrete structure.
Whereas a pedestal is generally considered to be a separate
independent structure. The – both the idea of pedestals - the issue
of pedestals and plinths are closely related because of the likeness
in the type of construction and the quantity of work involved.”
(T245-6)
….
And can you tell his Honour whether what we're looking at in those two
photographs [Exhibit 25] is a footing or a pedestal?-- Your Honour,
-- 73 of 81 --
74
that's a pedestal.
And if you can-----
HIS HONOUR: Isn't that below ground?-- Some of it is below
ground, your Honour, yes. The top of that structure, however, will be
above ground. Ground level in this case will be the underside of the
long timber supports which run across the - from left to right across the
photograph. And if you notice, the holding down bolts in the centre are
above that and the piece of white material - that white line which goes
around inside the box, that's actually called a plastic fillet, and that
would be above ground level too.
MR DIGBY: Mr Eames-----?-- This pedestal will be very close to
ground level at - on completion.
Mr Eames, looking at the components in the photographs, the framing
timbers and the plastic caps on the reinforcement one can see in the
lighter of the photographs, the more distant photograph, can you tell his
Honour what approximately the dimensions of this pedestal are?--
Your Honour, this pedestal appears to be somewhere in the order of
400 millimetres by 400 millimetres. Perhaps 450.
And can you take the two photographs separately? Taking, first of all,
if you would, Mr Eames, the photograph which is taken from the
further distance from the work involved?—
Yes.
And can you describe to his Honour - I don't want you to take long on
it, you've given general descriptions already, but can you describe for
his Honour generally the work involved in forming up the pedestal that
we can see in the photograph [Exhibit 25], for the transcript?-- Your
Honour, the work which would be involved in doing this particular
pedestal, the steel cage, which is the reinforcement which goes
inside, would be tied. The timber formwork would then be built.
The white corners, which are evident in the photograph, and the white
line around just below the piece of crossbracing template that
supports the holding down bolts are called the plastic fillets. They're
a 45 degree angle. They would have been placed intact into the
formwork. The whole lot would have then been surveyed and located
properly, and when the survey – during the survey location the whole
unit would have been moved around inside that excavation until it was
in the correct position. When it was in the correct position these small
pieces of reinforcing that are seen holding the bracing on the timber and
the supports' material for the timber are pinned down and then the
whole thing is rechecked. The piece of timber with the holding down
bolts in it are drilled at the right separation and then that's then placed
in - into the box with the holding down bolts in it. You can see a nut
above it. There will be another nut below that as well. That's then
located and the surveyor will then pinpoint the two that those two -
position of those two bolts. That's then nailed in, and then the
formwork is then inspected ready for the concrete to be placed.
And taking the photograph which is taken closer to the feature we're
looking at?-- Yes.
And looking into the void into which the concrete is to be placed, can
-- 74 of 81 --
75
you describe to his Honour what features we see there, for the
transcript? And what's involved in putting that together from the
contractor's point of view?-- From the contractor's point of view, your
Honour, the things to note here are the steel reinforcement, which are
the bars running left to right and up and down on the page. The white
plastic fillet that I referred to can be seen fairly clearly running top to
bottom on the left-hand side of the page. This piece of timber across -
which runs left to right across the page is the template which contains
the holding down bolts. And the reinforcement is held away from the
sides of the formwork by a plastic bar chair, which is - a bar chair is
that strange-shaped grey object that you can see on the left-hand side of
the photograph. ….
And, finally, can you describe to his Honour what is involved in
placing concrete in a small location like that?-- Your Honour, it's
basically impossible to - it's very difficult, it's not impossible, but it's
very difficult to get the concrete into a small area like that without
spilling it everywhere unless you put it in by shovel and so it has to be
generally placed by shovel and use a very small concrete vibrating tool
to vibrate the concrete to compact it and get rid of the air bubbles and
the voids in it.
And was the work you've just described, including the work relating to
the placement of concrete, typical of what was done in relation to the
pedestals that are the subject of the plaintiff's claim?-- That's correct.”
(T371-373).
Photographs 3 and 7 of Exhibit 23 shows pedestals (T364/25). The
photographs which are Exhibit 25 also show pedestals and formwork
(T371/2)
Ableflex Ableflex is a joint filler which is similar to silicon, the purpose of which is
to waterproof joints (Mr Howard at T469/52-55)
Additional
reinforcing to
Piers over
100kg / m3
Mr Eames gave evidence describing the work required for the construction
of a “Footing” and the use of reinforcing in the construction of footings and
pedestals. Mr Eames also gave the following evidence:
“… Probably the most significant - one of the significant differences,
other than what I have covered already, is that there - I cannot
remember the exact clause, but there is a requirement in the contract
document for the concrete footings to contain not more than 100 kilos
per cubic metre of concrete. Most of the footings that we did - not
all, sir, but most of them - contained significantly more than 100
kilos per cubic metre, which required additional effort to tie and
place the steel reinforcing prior to placing the concrete.
….
And is the sort of reinforcement you refer to as being called up a
normal or exceptional form of reinforcement?-- It's - 100 kilos per
cubic metre is, industry-wise, generally accepted as a rule of thumb
quantity. Some concrete structures, depending on their purpose, will
contain sometimes less than 100 kilos, sometimes more and sometimes
significantly more depending on their intended purpose and the
loadings you would expect to have in place on them.
What I'm seeking to have you explain, Mr Eames, is that you have said
-- 75 of 81 --
76
to his Honour in essence that some of the footings that we had to
build when the design was developed were more complicated
because they had a large amount of reinforcement in them; is that
what you're saying?-- A large amount of reinforcement and with
odd shapes in them. There was a lot more steel tying in them. The
example I gave you with the voids in it had to have steel work tied
around the voids. It's not just tying straight bars, there's a lot of
formwork which goes around it which has all got to be tied into place.”
(T235-6)
Backfill One of the uses for backfill was to fill a void or excavation made for the
purpose of positioning the formwork required for an underground
structure.(Mr Howard at T467/468)
Bearing
Plates
A form of Embedded Metalwork, as described below.
Blinding
Concrete
Blinding is “a mixture of sand and just straight sand and cement which
is placed on the bottom of the excavation. Its purpose is to stop the steel
work from being pushed through into the soil and mud underneath the
excavation. It provides a stable base upon which to construct the
formwork - sorry, my apologies, on which to construct the reinforcing, the
reinforcing steel.” (Mr Eames at T353)
Blockouts Blockouts can refer to formwork which is required to create a hole in the
concrete at the top of a pedestal, for example, to allow drainage (Mr Howard
at T466/47-53)
Cast in
Ferrules
Mr Howard gave the following evidence:
“MR HOOPER … A ferrule is a piece of metal tubing that gets cast
into concrete through which something such as an electrical cable can
later be passed?-- Yes, but unlikely, because most of the time the
ferrules were used to support the concrete formwork that was cast.
On that particular project no ferrules were used to pass an electrical
conduit through. (T470/14-22)
Compressible
Void Former
Mr Howard gave evidence that a compressible void former is used where a
slab is subject to differential loads, that is where the pressure applied to the
slab is not uniform, in order to distribute the load to specific support points
rather than directly to the ground at each load point. It can be placed
directly under a concrete floor slab (T466/12-16)
Concrete This refers to the concrete itself used to create the footings in question. Mr
Eames’ evidence regarding Footings describes the placement of concrete in
the footing structure.
Concrete
screed
Mr Howard explained that screeding refers to the standard finishing of a
concrete structure; “you screed the concrete with a screeding tool which is
just a standard finish.” (T469/47-49)
Embedded
metalwork
Mr Howard gave evidence that, in some cases, embedded metal work
involved a metal plate being positioned at the top of a pedestal, the purpose
of which was to prevent the wearing of the concrete at the top of the
pedestal by the structure positioned above it. (T466/32-40)
Footing
Excavation
The reference to “footing excavation” refers to excavation necessary to
construct the footing in question. Photograph 6 of Exhibit 23 shows footing
excavation (T364/36). Mr Eames gave the following evidence:
-- 76 of 81 --
77
“The difference between that footing and this one here is basically the
type excavation that you need to do to get that footing in and the
backfilling. This - because it has been excavated on an angle, to pour
that concrete footing would require you - would require the whole thing
to be placed in formwork, whereas with this type of footing
arrangement here, it will be dug into the ground and poured against the
surface of the ground” (T234-5)
… “When - your Honour, when we actually constructed a footing,
the excavations were dug or the formwork - and/or the formwork
placed, the steel work was tied and placed into the footing formwork
arrangement, the surveyor would then come and check the whole
construction before it was filled with concrete … (T238/16-22)
… “Can I ask you to go to the last of the documents you haven't
addressed in that part of the folder. It's a letter dated the 27th of
October 1999 in which you write to Mr Jewell about excavation of
concrete footings; do you have that document?— ...
… My question was what was the purpose of writing the letter?-- The
letter details the method that will be used for excavation for major
concrete footings to ensure that we - that Cook's are excavating to
a layer or to a depth where the in situ material provides for varying
capacities called for in the specification.” (T240-241)
Formwork In Mr Eames’ evidence regarding the work required for the construction of a
Footing, he described the use of formwork in the construction of footings
and pedestals. Mr Eames also gave the following evidence regarding the
nature of the formwork required in relation to footings:
“What other differences in the footings had to be built once in fact the
detailed design came down compared with the footings on drawing 001
in the contract, can you describe to his Honour?-- None of these
footing types on 001 have what's called blockouts or voids in the actual
concrete. They all appear to be a mass concrete footing. Now, several
of the footing types we did - for arguments, the ammonia synthesis unit
had octagonal shaped raised arrangements on top of the slab with an
octagonal void in the centre of it.
And how do you achieve that void?-- Well, it basically all has to be
formed up and poured in place.
And by reference to the drawing we were looking at, 0105, am I right in
assuming there's no detail of a void being put into the form?-- No,
there's no voids in that one, Mr Digby, but if you can bear with me for a
moment I will find the drawing that has the voids in it. The first
drawing relating to that is page 77 in the book of drawings. It's
drawing number SU-CS-10D-0057 and if you look at the plan view on
that drawing, you will see the eight octagonal raised sections with the
octagonal void actually formed up and taken out of the footing area.
And those features on that drawing 0057 that you've referred to that
need to have boxed formwork placed inside them to achieve the
void when you're pouring the concrete, they're footings, are they?--
Correct. I believe they are footings.” (T235)
HD Bolts “HD” refers to “hold down”. Mr Eames’ evidence described the use of
holding down bolts. Mr Eames also gave the following evidence:
-- 77 of 81 --
78
“When you formed these footings up, is it in the nature of a footing
that they would never have a bolt or a fixture cast into them, that was
a job for pedestals and things of that nature, was it?-- No, many of
those footings had bolts and fixtures cast into them. Some of the
footings that had a plinth arrangement on them where the height of
the plinth was insufficient to provide a proper embedment for the
holding down bolts on top of it, those holding down bolts would
actually have to be cast into the footing arrangement at the time of
the initial pour. (T238/40-52)
Hydrostatic
water relief
valve
Mr Howard gave evidence that a hydrostatic water relief valve “was for the
relief of water underneath a structure. … It was for the protection of the
concrete.” (T470/1-10)
Piers The piers referred to in section 6.1 of the particulars to the counterclaim
related to the construction of footings for the various structures referred to in
the remainder of section 6. The piers are listed separately in section 6.1
rather than by reference to the particular structure to which each related.
Piers are concrete columns which were placed into the ground for the
purpose of supporting the load of structures positioned above them (see
Howard’s evidence at T465/56 – 466/2). The piers differed in length and
diameter depending on the size and nature of the load they were required to
support.
Poly
Moisture
Barrier
Mr Howard gave the following evidence:
“Mr Howard, would you describe poly moisture barrier as being a
polythene sheeting which is laid down before concrete is poured in
order to stop ground water rising into the concrete?-- Not necessarily.
The plastic can be used to stop the moisture being leached out of the
ground and not sucking the moisture out of the concrete, and it can also
be used for water, but not always. Most of the time it is used to stop
the concrete from drying on the edge.” (T468/9-16)
Rebate
formwork
This is a particular type of formwork used to create an inlet in a concrete
structure for the purpose of joining that concrete structure with another
section of concrete (see Howard’s evidence at T469/28-31).
Supply &
Place Low
Heat
Concrete
Mr Howard described low heat concrete as being concrete that has been
changed so that it generates less heat (T467/1-9)
Templates A template is a typically a temporary measure used to hold something in
place, such as a hold-down bolt, whilst concrete is being poured (see
T470/25-30). Mr Eames’ evidence made reference to templates that
supported holding down bolts (T372/27).
Waterstop A waterstop is a means of preventing water transferring through joints, in a
water bound structure. (T468/24-26)
[342] The various items set out above are all consistent with the work described by Mr
Eames with respect to the construction of footings, pedestals, plinths and the like. It is
work consisting of the erection or construction of a building, or any site work
(including the construction of retaining structures) related to work of that kind. It
includes work for which particular licences are prescribed under the Queensland
-- 78 of 81 --
79
Building Services Authority Regulation 1992, such as concreting. It is all work which
is closely connected to, and necessary for, the construction of fixed structures and so is
“building work” within the meaning of the QBSA Act.
Was that work paid for by Stork?
[343] Exhibit 24 (a document created by CCPL) establishes that the work set out in
Appendix B was paid for by Stork in the amount of $9,983,796.54.
If the work was paid for, was that payment made by mistake?
[344] Stork called Mr Peter Jewell on this issue. He was “Stork’s representative” for the
purposes of the Subcontract but he was not an employee of Stork. He was also the
person who was responsible for certifying the payments by Stork to CCPL. His
evidence171 was that:
(a) when he certified those payments, he expected the plaintiff to hold
all licences it was required to hold do the contract works within
Queensland172 ;
(b) if he had discovered that the plaintiff did not hold the licences it was
required to hold, he would have taken legal advice and acted in
accordance with that advice: “I would have adjusted their payment
accordingly in relation to the legal advice I was given”173 ; and
(c) during the course of the Subcontract he did not discover that the
plaintiff did not hold any licence that it was supposed to hold174 .
[345] Mr Jewell was cross-examined 175 on this area:
“Among the many things you might have done is it correct to say that
had you discovered that one of your subcontractors was not
appropriately licensed under that Act, you nevertheless would have
insisted on the subcontractor continuing to perform its work under the
subcontract?-- No.
Well, let's look at it from a different angle. Had you discovered that
the subcontractor was unlicensed is it your evidence that you would
have stopped it then and there from continuing to work under its
subcontract?-- Until they were licensed, yes.”
[346] Stork was, through its representative, mistaken as to its obligation to pay CCPL. It is
clear from his evidence that had he discovered that CCPL was unlicensed he would
have stopped it from working and taken legal advice.
[347] The defendant has made out its counterclaim.
Conclusion
[348] The schedule attached to these reasons sets out the results of the various findings I
have made.
171 T 649-651.
172 T 650.
173 T 650.
174 T 650.
175 T 655-656.
-- 79 of 81 --
80
[349] I give judgment on the claim for the plaintiff in the sum of $132,657.70 with interest.
On some of the claims on which the plaintiff has succeeded interest will accrue in
accordance with the method admitted on the pleadings. The details are:
(a) Road reconstruction $ 14,998.20
(b) Lime stabilization of site roads $ 24,846.80
(c) Asphalt on site roads $ 52,787.70
(d) Ammonia spill standby $ 40,025.00
$132,657.70
[350] I give judgment on the counterclaim for the defendant in the sum of $9,983,796.54
with interest.
[351] I will hear the parties on the calculation of interest and on costs.
-- 80 of 81 --
81
Schedule of Claims and Defences
Does the
Prescribed
Notice Defence
apply?
Does the Lump
Sum Contract
Defence apply?
Does the QBSA
Act Defence
apply?
Claim Allowed/
dismissed
Yes No Yes No Yes No
Bulk earth works
claim
Dismissed X X X
Road reconstruction
claim
Allowed
$14,998.20
X X X
Contour Drains claim Dismissed X X X
Lime Stabilization of
Site Roads claim
Allowed
$24,846.80
X X X
Boxing Out for Road
works claim
Dismissed X X X
Asphalt on Site Roads
claim
Allowed
$52,787.70
X X X
Quantities of Footings
Claim
Dismissed X X X
Pedestal Claim Dismissed X X X
Pedestal
Reconciliation Claim
Dismissed X X X
Corrocem claim Dismissed X X X
Suspended Slabs claim Allowed X X X
Prill Store claim Allowed X X X
Crushed Rock to
Substations claim
Dismissed X X X
Ammonia spill
standby claim
Allowed
$40,025
X X X
-- 81 of 81 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2008/179