About Scaffolding Pty Ltd v Howard Thompson Construction Pty Ltd [2008] QDC 295
DISTRICT COURT OF QUEENSLAND
CITATION: About Scaffolding Pty Ltd v Howard Thompson Construction
Pty Ltd [2008] QDC 295
PARTIES: ABOUT SCAFFOLDING PTY LTD
(Plaintiff-Respondent)
and
HOWARD THOMPSON CONSTRUCTION PTY LTD
(Applicant - Defendant)
FILE NO: D492/08
PROCEEDING: Application
DELIVERED ON: 10 December 2008
DELIVERED AT: Southport
HEARING DATE: 5 December 2008
JUDGE: C.F. Wall Q.C.
ORDERS: Application dismissed with costs to be assessed on the
standard basis unless agreed.
CATCHWORDS: Practice and Procedure – Security for costs – corporation –
few assets but trading profitably – whether security should be
provided.
LEGISLATION: Corporations Act 2001 Section 1335(1)
Uniform Civil Procedure Rules Rules 670, 671 and 672
CASES: Bell Wholesale Company Limited v Gates Export
Corporation (1984) 2FCR1
Buckley v Bennell Design and Constructions Proprietary
Limited (1974) 1ACLR 301
Harpur v Ariadne Australia Limited (1984) 2 QR 523
Nambour Valley Estates Proprietary Limited v Henebery
Holdings Proprietary Limited [2007] QSC 393
COUNSEL Applicant - P D Hay
Respondent - S Anderson
SOLICITORS: Applicant - DLA Phillips Fox
Respondent – Platinum Lawyers
-- 1 of 9 --
2
DISTRICT COURT
CIVIL JURISDICTION
JUDGE C.F. WALL QC
No 492 of 2008
ABOUT SCAFFOLDING PTY LTD Plaintiff/Respondent
and
HOWARD THOMPSON CONSTRUCTION PTY LTD Defendant/Applicant
SOUTHPORT
..DATE 10/12/2008
JUDGMENT
-- 2 of 9 --
3
HIS HONOUR: This is an application by the defendant for an order that the plaintiff
provide security for the defendant's costs of $55,000, or such other amount as the Court
thinks fit.
The plaintiff claims from the defendant $144,056.42, being the balance owing under a
contract made on the 15th of August 2007, whereby the plaintiff supplied labour and
materials to erect, and later dismantle, scaffolding on a building being constructed by the
defendant. The total contract price was $318,532, plus GST. The defendant denies that it
is liable to pay anything to the plaintiff and seeks to set off about $35,000, being for work
it carried out which was required to be done by the plaintiff, which the plaintiff didn't do.
The plaintiff denies this.
The application was dealt with on the papers with no deponent being required for cross-
examination.
In his affidavit, filed by leave, Mr Thompson, the director of the plaintiff company,
deposes as follows in paragraphs 9, 11, 12 and 13:
"9. I refer to the Defence filed by the Defendants in this matter and say that it is
defended on the basis that work was done more slowly than was allowed for in the
contract or in the alternative that work was done without prior approval. There is
no allegation that work was defective.
11. The basis of About Scaffolding's claim is that About Scaffolding Pty Ltd was
employed to erect scaffolding during the construction of two buildings known as
Sphere Development on Musgrave Avenue in Southport, Queensland. The
contract price was $318,532.00 plus GST. A flat rate of $48.00 per hour plus GST
per man for extra work was also to be paid. The Plaintiff alleges that the
Defendant agreed to pay two thirds of the contract price or $212,354.66 for the
erection of the scaffolding and one third of the contract price for the dismantling of
the scaffolding. The price that is claimed is $144,056.42 plus interest and costs.
-- 3 of 9 --
4
The additional amounts are pursuant to extra duties pursuant to site directions
which were attached to the Statement of Claim as an extra too. (sic)
12. It is the case for the Plaintiff that difficulties arose when it was directed to
construct the scaffolding and then were not provided with adequate room when it
was time to dismantle the scaffolding. Difficulties also arose when the Defendant
continued to use the scaffolding after dismantling began. On one occasion the
Defendant dismantled scaffolding without reference to the Plaintiff and left the
scaffolding in a pile which required that the Plaintiff move the scaffolding into an
area where it was safe to operate.
13. I attach as Exhibit 'DWT5' to this affidavit photographs of the worksite. The
first of these photographs shows an area where the Defendant had removed the
bottom level of the scaffolding while it was still erected. This was unsafe and
required that extra time be taken to reconstruct the scaffolding to make it safe.
Page 2 shows that on a date when About Scaffolding had been told to dismantle
the scaffolding, trade people at the work site where still using the scaffolding.
Page 3 shows that About Scaffolding was not provided with a clear area around the
scaffolding so that dismantling of the scaffolding could be undertaken in a safe
manner. These photographs are offered in support of the Claim and Statement of
Claim against the Defendant that while it did the work of constructing and
dismantling the scaffolding the Defendant has not operated within the terms of the
contract by causing the dates of the schedule be (sic) disrupted."
In response, the defendant's solicitor, Ruth Hatten, deposes as follows in her affidavit filed
by leave:
"12. In the very limited time I've had to speak to our client, I have not been able to
obtain proper instructions in respect of the affidavit of Daniel Warwick Thompson.
-- 4 of 9 --
5
On 4 December 2008, I had a telephone conversation with Riaz Khan of the
Defendant who has briefly looked at the affidavit and has instructed that the
Defendant's initial response is as follows:
12.1 In reference to the allegation in paragraph 12 that the Defendant did
not provide the Plaintiff with adequate room when it was time to dismantle
the scaffolding, during the dismantling of scaffold on both buildings E1/E2
and E3/E4, the Defendant did provide adequate room and also provided
barrier tape and erected barrier tape to isolate the zone being used to drop
scaffold in.
12.2 In reference to the allegation in paragraph 12 that the Defendant
continued to use the scaffolding after dismantling began, the Defendant
issued site instructions to the Plaintiff in regard to the use of scaffolding by
other contractors (Document 8).
12.3 In reference to the allegation in paragraph 12 that the Defendant
dismantled scaffold and left in a pile, (sic) the Defendant says that this is an
unsubstantiated claim.
12.4 The first photograph referred to in paragraph 13 does not correspond
to Mr Thompson's comments. If Mr Thompson is meant to refer to the
third photograph, the Defendant believes that this scaffolding could have
been removed prior to the photo or removed by a subcontractor. It was not
removed by the Defendant.
12.5 The second photograph shows scaffold being erected, not dismantled.
The stair access has been built allowing access to level 3 where the person
is shown. The Defendant can not determine from the photograph whether
-- 5 of 9 --
6
he is a scaffolder or a ticketed scaffolder and either way, if the scaffold is
complete, there should be signage at the base of the stairwell.
12.6 The third photograph referred to in paragraph 13 does not match Mr
Thompson's comments. In any event, the Defendant repeats and relies on
paragraph 9.1 above."
It is not possible, on this application, to resolve the factual dispute between the parties, but
it does appear that the plaintiff did erect and dismantle scaffolding for the defendant and
would therefore appear to have a prima facie claim against the defendant.
The plaintiff was registered in Queensland on the 23rd of April 2007. It is not in
liquidation and receivers and managers have not been appointed. It trades and does so
profitably. Daniel Thompson is its sole shareholder and director. Its paid-up capital is
minimal and in the 2007/2008 financial year, the company's employee expenses were
$190,927.95, most of which was paid to Mr Thompson and his wife, out of a total income
of $722,934.96.
The main reason for the application seems to be that the company has little or no assets
and made a nett loss in the 2007/2008 financial year of $53,589.24.
Mr Thompson deposes that the company will be able to pay a costs order if one is made
against it from its own income, from its own resources. Costs of the defendant are
estimated by the defendant's solicitor at between about $48,000 and about $69,000. The
plaintiff's solicitor considers this estimate to be excessive.
I accept the evidence of Mr Thompson. He deposes as follows, in paragraph 7 of his
affidavit:
-- 6 of 9 --
7
"7. The company has suffered impecuniosity to some extent because the Defendant
has refused to pay the progress claims made as set out in the Claim and Statement
of Claim."
The company hires scaffolding from a third party and uses it in its business. It has a
vehicle but little equity in it. It does not need much in the way of owned assets to carry on
its business. Its balance sheet, for the financial year ended 30th of June 2008, indicates
assets of $46,890.84 and liabilities of $78,559.83. Its profit and loss statement for the
same period indicates total income of $722,934.96, costs of sales $549,214.08 and gross
profit of $173,720.88. Expenses were $226,618.97 (including employment expenses of
$190,927.95), resulting in a nett loss for the period of $53,589.24, taking into account also
other expenses of $691.15.
Mr Thompson deposes that in the 2007/2008 financial year he was paid $2,207 per week
as project manager for the contract with the defendant, from the 15th of August 2007 until
July 2008 and his wife was paid $1,254 per week as administration officer for the same
period and I think in respect of the same contract.
The relevant statutory provision is section 1335(1) of the Corporations Act 2001 and the
relevant rules are rules 670, 671 and 672 of the Uniform Civil Procedure Rules. I am not
satisfied that there is reason to believe that the plaintiff will not be able to pay the
defendant's costs if ordered to pay them. I am not satisfied that there is a real chance that
the plaintiff will be unable to pay the defendant's costs in those circumstances. It is not
the case that because a company has only limited assets, it is for that reason alone,
impecunious. All relevant circumstances must be considered.
I agree with Ms Anderson for the plaintiff that the plaintiff trades essentially as a hirer of
scaffolding, which it then re-hires and erects and dismantles and as such, there is no need
for much in the way of assets or stock in trade. I also agree that a substantial amount of
-- 7 of 9 --
8
the plaintiff's liabilities are related to its work for the defendant, the subject of its claim.
As at the 1st of December 2008, it owed Boral Scaffold Hire $66,000 and the Australian
Tax Office $48,766.87. Ms Anderson said these were related to the work it performed for
the defendant. Mr Hay, for the defendant, did not disagree. Whilst these are liabilities the
plaintiff would have incurred in any event, its earnings would be higher and its
profitability greater, but for the present proceeding.
The plaintiff's claim amounts to little less than 20 per cent of its 2007/2008 gross profit of
almost $723,000. The company clearly does work for other customers and would already
appear to have an income stream even though it is only a relatively recently incorporated
business.
I should mention some of the authorities relied upon by the defendant. In Bell Wholesale
Company Limited v. Gates Export Corporation (1984) 2FCR1, the company ordered to
provide security for costs had issued capital of two shares of $1 each and its only asset
was $2. It was the trustee of a family trust and did not trade. It was common ground that
it had no assets it could use to satisfy any judgment for costs in favour of the appellant.
In Buckley v. Bennell Design and Constructions Proprietary Limited (1974) 1ACLR 301,
the respondent to the application was impecunious. It was not ordered to provide security
for costs.
Harpur v. Ariadne Australia Limited (1984) 2 Queensland Reports 523, indicates that the
lack of means of a plaintiff company and its likely inability to meet an order for costs will
frequently lead to an order for security. Such an order was not made against the three
plaintiff companies there because they had no claim independent of that of the fourth
individual plaintiff, a man of substantial means, and were joined only as a means of
establishing his rights.
-- 8 of 9 --
9
In Nambour Valley Estates Proprietary Limited v. Henebery Holdings Proprietary Limited
[2007] QSC 393, the fact of the appointment of receivers and managers to the plaintiff
combined with the fact that success by the plaintiff in the proceeding would largely benefit
a secured creditor who had chosen not to offer security for costs, mainly influenced the
decision to order security.
In all of the circumstances, the defendant has not, in my view, established that there is
reason to believe that the plaintiff will not be able to pay the defendant's costs if ordered to
pay them. The defendant's application will therefore be dismissed, with costs to be
assessed on the standard basis unless agreed.
...
HIS HONOUR: Notwithstanding that the affidavit of Daniel Thompson was not sworn
until the 4th of December 2008 and provided after then to the solicitors for the defendant,
the affidavit of Mr Thompson was filed by leave on the application and that occurred
without any objection by Mr Hay to that course.
The determining factor, in my view in this case, is the fact that the defendant has failed in
its application and in those circumstances, I really can't see any reason for departing from
the normal rule that costs should follow the event. So, for those reasons, Mr Hay, I will
not depart from the order I just made.
-- 9 of 9 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2008/295