Austral Plywoods Pty Ltd v Hvac Queensland Pty Ltd [2008] QDC 78
1
[2008] QDC 78
DISTRICT COURT
CIVIL JURISDICTION
JUDGE ROBIN QC
No 4128 of 2005
AUSTRAL PLYWOODS PTY LTD Plaintiff
and
HVAC QUEENSLAND PTY LTD Defendant
BRISBANE
..DATE 31/03/2008
ORDER
CATCHWORDS: Uniform Civil Procedure Rules r 161 - particulars
of defence not ordered where it appeared the defence was to be
amended - order that amended defence include a statement of
any oral term the defendant contended formed part of the
parties' agreement - plaintiff (which pleaded certain oral
terms denied or not admitted) should not be at risk of
different oral terms not pleaded being asserted.
-- 1 of 6 --
2 ORDER
1
10
20
30
40
50
60
HIS HONOUR: This is a plaintiff's application for further and
better particulars of the defence under rule 161. It is
something of a moveable feast because the defence is
apparently likely to be changed.
The plaintiff manufactures plywood. It encountered
difficulties in a drying process which was necessary to cure
the bonds between layers of the ply by the blowing of hot air
through pipes in some location where conveyor belts moved
through. The difficulty was that particles such as ash, which
came with the hot air produced by a furnace, clogged outlets.
According to the plaintiff in its statement of claim, the
defendant "agreed for reward to design, supply and install a
dust collection and extraction system."
The defence is a considerably longer document which, perhaps
significantly, appears to remove responsibility for design
from the defendant, which pleads an agreement to,
"manufacture, supply and install a dust collection and
extraction system."
The parties are agreed on what documents constitute the
written part of the agreement but not upon what constituted
the oral part, which the plaintiff said was contained in
conversations between its Mr Matthews and Mr Lubbers and the
defendant's Mr Goulden on two days. Particulars have been
given of terms agreed on in paragraph 6(a) and (b) of the
original statement of claim and paragraphs 6(a), (b), (c) and
(d) of an amended statement of claim dated 26th October 2007,
-- 2 of 6 --
3 ORDER
1
10
20
30
40
50
60
which followed receipt of the notice of intention to defend
and a defence which are dated 23rd of December 2005. The
defence has not yet been amended, although the defendant's
solicitors, by facsimile transmission of the 7th of February
2008, advised that meetings were being held with client and
counsel for the purpose of the defence being amended if
necessary.
Four days ago came another facsimile offering to consent to
the present application on terms including the defendant being
ordered to file and serve an amended defence on or before 14
April 2008. It seems that the defendant now does wish to
amend and that is probably necessary. If there is to be an
amendment it may render redundant the plaintiff's present
application. An amended pleading may cause some of the
plaintiff's dissatisfaction with the particularity to go away.
The crucial point of concern for the plaintiff arises from
paragraph 4 of the defence, in particular subparagraph (b),
which admits that the parties' agreement was partly in writing
and partly oral, proceeding as follows:
"(ii) To the extent that the agreement was oral it was
contained in conversations between Mr Bruce Goulden on
behalf of the defendant and Messrs Malcolm Matthews and
Hans Lubbers. (The dates and locations of those
conversations cannot be further particularised until
after disclosure)."
The preceding paragraph had denied the plaintiff's version of
the contract and the following paragraphs of the defence, in
particular 6, 7, 8, deal with paragraph 6 of the statement of
-- 3 of 6 --
4 ORDER
1
10
20
30
40
50
60
claim by way of denial of the oral term pleaded in paragraph
6(a) and non admission of that contended for in paragraph
6(b). As to the balance of the allegations in that paragraph
6, it is pleaded that despite making reasonable inquiries as
to the dates of conversations alleged, the defendant remains
uncertain of the truth or otherwise of the allegations.
The plaintiff in the action asserts that the defendant's work
was ineffective and essentially that the plaintiff wasted its
money. There is also a claim for consequential losses
attributable to the closing of its operation for periods.
I agree with Mr Sheaffe's approach that the plaintiff is
entitled to know what the defendant says were the terms of the
contract. It appears to me that paragraph 4(b)(ii) leaves it
open to the defendant to set up new oral terms. It is not
clear whether the defendant, which may well dispute that the
oral terms contended for by the plaintiff existed, says there
were no oral terms or that there were different oral terms.
The plaintiff is at risk of having its claim jeopardised by
the surprise appearance somewhere down the track of assertions
of further statements or representations having some
contractual effect.
Mr Harding's careful argument for the defendant is essentially
this: it is the plaintiff setting up and suing on an
agreement; it is for the plaintiff to prove what were the
terms of that agreement; it is not incumbent on the defendant,
which has no counterclaim, to make positive allegations as to
-- 4 of 6 --
5 ORDER
1
10
20
30
40
50
60
what were the complete contractual arrangements. I am not
able to accept that argument in our current "no surprises"
litigation system. The plaintiff, in my view, is entitled, by
having particulars provided, to be placed in a position of
certainty that no additional contractual arrangements would be
asserted or that if any are to be asserted tending to weaken
its claim, those will be pleaded.
I have not gone into the detail of proposed arguments as to
how many of the dozen or so requests for particulars the
plaintiff says are still unsatisfied relate to the broad,
important issue I have been canvassing. Mr Harding says it is
only a couple. He is willing, he says, to have an argument
about the sufficiency of the defendant's responses to all
requests for particulars, notwithstanding that the letter of
27th of March 2008 had suggested deferring such aspects for
later consideration if the defence were amended.
I am not critical of Mr Harding or his client or solicitors
for taking that approach; it is sensible enough to use the
court hearing to resolve as much as can be resolved usefully.
However, I think it is a rather sterile exercise for the court
to embark on a detailed consideration of how a pleading which
is likely to be amended ought to be particularised. I think
that the court ought to order as follows:
that the defendant file and serve an amended defence on
or before 14 April 2008 to include a statement of any
-- 5 of 6 --
6 ORDER
1
10
20
30
40
50
60
oral term which it contends formed part of the parties'
agreement;
secondly, the Court should order that the application be
adjourned to a date to be fixed to be brought on by a
party providing two days written notice;
and thirdly, the defendant pay the plaintiff's costs of
the application and today's hearing.
I would repeat the intimation I gave that if it turns out that
there is to be a further hearing about particulars, success in
that for the plaintiff would not necessarily lead to the
plaintiff's obtaining another order for costs. I say that in
deference to Mr Harding's intimation that he is willing to
have everything sorted out today. I am not sure if Mr Sheaffe
was so enthusiastic but that may be an unfair observation to
make. The court was certainly not enthusiastic about
embarking on what might be a hypothetical exercise, but the
question of any such costs, if one arises, is going to be for
the Judge who faces it.
...
-----
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2008/078