De Tournouer v Chief Executive, Department of Natural Resources and Water [2008] QLC 151
LAND COURT OF QUEENSLAND
CITATION: De Tournouer v Chief Executive, Department of Natural
Resources and Water [2008] QLC 151
PARTIES: Margaret Frances De Tournouer
(appellant)
v.
Chief Executive, Department of Natural Resources and
Water
(respondent)
FILE NO: A2007/0023
DIVISION: Land Court of Queensland
PROCEEDING: Appeal under the Water Act 2000.
DELIVERED ON: 22 July 2008
DELIVERED AT: Brisbane
HEARD AT: Brisbane
MEMBER: Mr RP Scott
ORDER: The appeal is dismissed and the review decision is
affirmed.
CATCHWORDS: Water Act s.210 – Water Resources (Barron Plan) 2002 s.
53 – evidence fails to satisfy the Barron Plan – Court
unable to identify volume needed for intended use.
Expert evidence – witness displayed behaviour warranting
exclusion of his opinion evidence.
APPEARANCES: Mr DR Gore QC with him Mr D Pyle instructed by John
Hill and Staff for the appellant.
Mr W Isdale of Crown Law instructed by Ms L Marshall,
Senior Legal Officer for the respondent.
Background
[1] This is an appeal pursuant to s.877 of the Water Act 2000 against a review decision of the
Chief Executive refusing the application by the appellant for a water licence.
[2] The appellant had applied to take 715 Megalitres per annum (ML/a) from her land
located within the Atherton Basalt Sub-Artesian area (Management Area B) as described
-- 1 of 8 --
2
in the Water Resources (Barron) Plan 2002. That application was received in the
respondent’s Mareeba office on 20 February 2003.
[3] On 9 November 2006 the Chief Executive granted a licence to take 80 ML/a. In an
"Information Notice" given pursuant to s.211(3) of the Act the respondent justified the
grant of that volume on the following basis:
“In view of the considerable investment made by applicants to locate and test possible
groundwater supplies it was decided to grant some entitlement in the Peterson Creek sub-
area based on the mean entitlement of other licensees. This results in a possible
entitlement of 80 ML/a for each applicant in this sub-area.”
[4] The appellant sought a review of that decision1 by way of an application lodged on 7
December 2006. By “Notice of Review Decision” dated 13 February 2006 the appellant
was advised that the decision of the reviewer under s.864(2) was to “confirm (in whole)
the original decision”. That review decision was the subject of a notice of appeal filed in
this Court on 26 March 2007.
[5] An appeal under s.877 is “by way of rehearing, unaffected by the reviewer’s decision.”2
The power of this Court in an appeal of this nature is provided for in s.882(1):
“882 Powers of court on appeal
(1) In deciding an appeal, the court may—
(a) confirm the review decision; or
(b) set aside the review decision; or
(c) amend the review decision in the way the court considers appropriate;
or
(d) send the matter back to the reviewer and give the directions the court
considers appropriate; or
(e) set aside the review decision and substitute it with a decision the court
considers appropriate.”
[6] Whilst s.882(1) does not not make express reference to s.210 of the Act, it was common
ground that it is this provision which is the primary guide to the Court in the exercise of
its jurisdiction. Section 210 provides:
“210 Criteria for deciding application for water licence
(1) In deciding whether to grant or refuse the application or the conditions for the
water licence, the chief executive must consider the following—
(a) the application and additional information given in relation to the
application;
(b) if notice of the application has been published—all properly made
submissions made about the application;
1 s.862 of the Act.
2 s.880(2) of the Act.
-- 2 of 8 --
3
(c) any water resource plan, resource operations plan and wild river
declaration that may apply to the licence;
(d) existing water entitlements and authorities to take or interfere with
water;
(e) any information about the effects of taking, or interfering with, water
on natural ecosystems;
(f) any information about the effects of taking, or interfering with, water
on the physical integrity of watercourses, lakes, springs or aquifers;
(g) strategies and policies for the sustainable management of water in the
area to which the application relates;
(h) the sustainable resource management strategies and policies for the
catchment, including any relevant coastal zone and regional aquifer
systems;
(i) public interest.
(2) The chief executive may also consider whether the applicant has been
convicted of an offence against this Act, the repealed Act or an interstate
law.”
[7] The added emphases are mine. I highlight clause (g) simply because it appears to be a
criterion which the Chief Executive placed particular reliance on in the original decision
on the application. The emphasis placed on (c) is, however, of greater significance.
[8] The Barron Plan applies to the appellant's land. That plan provides in s.11(2):
“(2) Both surface water and subartesian water are to be allocated and managed in a way
that seeks to achieve a balance in the following outcomes —
(a) to allow water to be used for the following—
(i) agriculture;
(ii) aquaculture;
(iii) industrial needs;
(iv) small scale uses;
(v) stock and domestic purposes;
(vi) tourism and recreational uses;
(vii) urban needs;
(b) to provide for the continued use of all water entitlements and other
authorisations to take or interfere with water;
(c) to encourage the efficient use of water;
(d) to maintain areas of significant tourism and recreational value, including the
Barron Falls, Barron Gorge and Tinaroo Falls Dam;
(e) to allow cultural use by Aboriginal or Torres Strait Islander communities;
(f) to provide water to support natural ecosystems.” (my added emphasis)
-- 3 of 8 --
4
Pursuant to s.210(1)(c) of the Act the Chief Executive, and in turn this Court, must
consider the above highlighted parts of the Barron Plan, amongst other matters.
[9] At their broadest, cases of this nature are concerned with three elements: the availability
of water for allocation; the potential environmental impacts of making the allocation
sought; and the use to which allocated water is to be put. Sections 11(2)(b) and (c) of the
Barron Plan are concerned with the third element.
[10] Evidence led before me from various experts focused mainly on the first element: the
question of the availability of water to meet the application. As the water sought by the
appellant is sub-artesian, the evidence was necessarily complex, requiring conclusions to
be drawn on such evidence as is available to indicate the nature of what lies beneath the
ground and is therefore hidden from view. There was also evidence as to the potential
impacts of making the water allocation sought. This evidence concentrated more on the
impact of water availability including surface flows than on other aspects of the natural
environment.
[11] Given the conclusion that I have drawn below on the third of the elements I mention
above; that is the use to which the allocated water is to be put, I need not dwell on the
expert evidence referred to in the preceding paragraph except to say two things. First,
given the manner in which each of the parties treated the case advanced by the appellant
through her expert Mr Iain Hair (Hydrogeologist) and deficiencies in the expert evidence
advanced for the Minister; the evidence as to the availability of the sub-artesian water is
not as complex as might first thought to be the case.
[12] Second, and this relates in some part to the first point, I have concluded that the opinion
evidence provided by Dr John Bernard Prendergast (Hydrologist and Principal Policy
Officer, Department of Natural Resources and Water) could not be safely relied upon.
He attempted to distance himself from important aspects of his own earlier co-authored
reports; was selective in his treatment of such material; was evasive in cross-
examination; and was intellectually arrogant in his treatment of Mr Hair’s expert
evidence.
[13] An expert witness, unlike a lay witness, is permitted to offer opinions to a Court as to the
meaning and implications of proven factual evidence. There is, co-existent with that
privilege, a requirement that the expert exhibit such objectivity in his evidence that
opinions given can be relied on by the Court as being opinions which resulted from the
application of expert knowledge to the factual evidence. Any tendency of an expert to be
less than objective or to become an advocate in the cause of the party who called him,
-- 4 of 8 --
5
will undermine the confidence that a Court can place in his opinion evidence.3 This is
not to say that an expert witness may not be passionate in advocating the correctness of
the opinion he advances, but he ought not display the behaviour I observed in Dr
Prendergast.
[14] The rationale behind Dr Prendergast’s inclusion in the case is somewhat perplexing.
Orders were made requiring the parties to file and serve statements of experts' evidence
by 29 October 2007 and statements in reply by 9 November 2007. Experts in each field
of expertise were required to confer and to produce by 20 November 2007 a joint
statement setting out points of agreement and disagreement. Pursuant to those orders Mr
Hair and Mr Robert Lait (a Hydrogeologist retained by the Minister) met on 13
November 2007 and on 19 November 2007 produced a joint report dealing with matters
of disagreement and agreement between them. The joint report both narrowed the issues
and provided a useful focus on the matters which remained as issues for debate between
the parties. Then on 24 December 2007 a facsimile was sent by the Department of
Natural Resources and Water to Mr Lait asking him a number of questions which can
best be characterised as challenging opinions expressed by him in his expert report
(Exhibit 8) and his reply report (Exhibit 9) to Mr Hair’s expert report and in the joint
report produced by Mr Lait and Mr Hair. Mr Lait answered the questions by a
memorandum dated 15 February 2008 (Exhibit 11).
[15] Dr Prendergast had, according to his recollection, become involved in the case either in
early 2008 or in December 2007. By arrangement between the parties he was permitted
to produce a report and such report dated 2 April 2008 which purported to respond to a
response report by Mr Hair and dated 19 March 2008 (Exhibit 10) was tendered for the
Minister. That document was not, I concluded, a response to the report by Mr Hair so I
did not accept its tender. A further report of Dr Prendergast dated 23 May 2008 (Exhibit
29) was received into evidence. It responded in large part to Exhibit 10 and to a further
report of Mr Hair (Exhibit 24). For reasons not clear to me, Dr Prendergast’s report
introduced a new case for the Minister – one inconsistent in important respects with the
case based on Mr Lait’s evidence and inconsistent with the pre-trial process of meeting
of experts and the production of the joint report by Mr Lait and Mr Hair.
[16] I set out this brief history relating to the introduction of Dr Prendergast as a witness, not
because it is relevant to my conclusion as to the acceptability of his opinion evidence, but
because it indicates a lack of cohesion in the presentation of the case from the Chief
3 See for example Cominos & Co Pty Ltd v Chief Executive, Department of Lands (1996) 16 QLCR 311 at 336 to
339; Foody v Horewood (No. 2) [2004] VSC 222 at [16] to [22] and Barns v Transport [1996 - 1997] 16 QLCR
22 at 28 – 29.
-- 5 of 8 --
6
Executive, an entity expected to demonstrate the attributes of the model litigant. In
saying this I must make it perfectly clear that no criticism is intended or implied against
Mr W Isdale, counsel for the Minister. He conducted himself impeccably before me and
made the submission which ultimately led to my conclusion in this appeal. I now turn to
the issue raised by that submission.
[17] Evidence as to the use to which the allocation of 715 ML/a of water would be put was
provided by Mr James Maurice De Tournouer, the appellant's son and active manager of
the enterprise on the land. In an affidavit sworn 22 August 2007 Mr De Tournouer
deposed:
“The motive behind our making the Application in the first place was to drought proof
the property as in 2002 we were severely effected by drought and suffered badly from
having to buy feed and supplements. We are again in a drought situation and there is
little or no standing grass…”
[18] The appellant's land is a grazing property and has been managed as such since 1971.
When asked in cross-examination about his intended use of the water he said "I want to
irrigate pasture". Mr De Tournouer did not at any time provide evidence as to how much
water would be needed to drought-proof the property even though he was cross-
examined on the point. Nor did he refer to any plans whether detailed or rudimentary, as
to how the drought-proofing would be given effect to including, in particular, how much
water would be needed. He simply said that he would grow winter “crops” that is winter
rye grass and clover and thereby, in his estimate, almost double the carrying capacity of
the land for cattle. I observe at this point that this idea of doubling of carrying capacity
appears to me to be inconsistent with such evidence as was led as to the volume of water
required and which I discuss below. There was no evidence as to the area to be sown to
winter crops and the water needs for such plantings. He said that he would harvest grass
seed, produced hay and graze the area.
[19] It appears to me that the requirement for an allocation of 715 ML/a was based on
s.53(1)(b) of the Barron Plan:
“53 Restriction on annual volumetric limit
(1) In deciding the annual volumetric limit for a licence granted after the
commencement of this plan, the chief executive —
(a) …
(b) must not decide a volume that is more than—
(i) for a licence to take water for irrigation purposes—
(A) in the Atherton Subartesian Area—5ML for each
hectare to be irrigated; and
(B) in the Cairns Northern Beaches Subartesian Area—
1.75ML for each hectare to be irrigated; and
-- 6 of 8 --
7
(ii) for a licence to take water for another purpose—the volume
estimated by the chief executive to be required for the
purpose.
(2) …”
[20] That is, the volume sought was not estimated by reference to a plan of productive and
effective usage, but represented the maximum volume that might be allowed. If such
volume was to be permitted it would place the applicant's within the top 1% of water
allocations in the Barron River catchment. Clearly, cogent justification for such an
outcome or for a slightly lower allocation of, say, 633 ML/a is required.
[21] Whilst Mr De Tournouer said that he intended drought-proofing the property, and that
the growth of such crops as vegetables (potatoes were mentioned) was not a specific
proposal but an option that he had in mind if beef prices declined, such evidence as there
was as to the volume of water requirements of the property were based essentially on
non-forage cropping. Mr De Tournouer and his wife had met with Mr David McQuillam
of Malanda Rural Supplies on or before 17 July 2007. And it was in that meeting that Mr
McQuillam advised the De Tournouer’s as to the appropriate crops that could be planted
and the amount of water considered necessary to sustain those crops. Immediately
following that meeting, the advice from Mr McQuillam was transmitted (apparently by
facsimile) to the appellant's solicitor by letter dated 17 July 2007; that is, after the filing
of the notice of appeal.
[22] Whilst the letter was produced on the letterhead of Malanda Rural Supplies it was
explained by Mr De Tournouer that it represented a typed version prepared by Mrs De
Tournouer of handwritten notes prepared by Mr McQuillam. Mr De Tournouer added
some brief annotations to the typed version and the salutation “Dear John”, a reference to
the appellant's solicitor.
[23] The letter commences with, “This is a suggested usage of water from the four bores on
our property” – words added by Mr De Tournouer. That is, it does not purport to be a
cropping and water usage plan based on the appellant's intentions but represents
suggested water usage if cropping of the type outlined in the letter ever eventuates. The
letter assumes that a total area of 140.93 ha would be irrigated. On the basis of s.53 of
the Barron Plan the maximum volume of water that could be allocated is therefore
524.65 ML/a whereas the letter suggests a maximum of 539 ML/a. In evidence Mr De
Tournouer suggested 633 ML/a as being the maximum required based on Mr
McQuillam’s assumptions; however, the derivation of that higher figure was not fully
explained.
[24] The volume of 539 ML/a was based on there being no rainfall on the appellant's land,
whilst a volume of 458.5 ML/a was calculated on the basis of rainfall figures “considered
-- 7 of 8 --
8
low” for the area. There was no attempt by the appellant to explain what irrigation
requirements there would be in an average rainfall season. Mr McQuillam was not called
to give evidence.
[25] The water usage presented in the letter assumes the planting of potatoes, corn (silage) and
“hay – grass seed" on 84.7 ha. Crop rotation is needed when potatoes are grown. The
letter also assumes the establishment of orchard trees in one paddock of 20.23 ha. Four
thousand orchard trees comprising avocadoes, citrus and macadamia are mentioned.
[26] The water volumes attributed to Mr McQuillam assume an intensive use of the
appellant's land for cropping and the devotion of part of it to permanent tree crops.
Those uses are not consistent with Mr De Tournouer’s stated intention in his affidavit to
drought-proof the property as a grazing enterprise and his expectation of doubling the
grazing capacity nor with his evidence that he viewed cropping as an option without any
present commitment to pursue that option. Not only does the evidence as presented by
the appellant provide me with no sound basis for an identification of the volume of water
needed for the drought-proofing of the property but I cannot conclude that such a
cropping usage of the type set out in the letter under discussion is intended by the
appellant. It is apparent that the information from Mr McQuillam was not produced to
serve a plan of land usage intended by the appellant, but was probably produced for the
purpose of providing evidence in the hearing and to give Mr De Tournouer some idea of
what cropping might be carried out on the land should he discontinue or modify the
current cattle grazing use.
[27] In short, I am not convinced that the volume of water sought by the appellant will be
used for the purposes apparently assumed by Mr McQuillam. The appellant has not
therefore demonstrated that there would be a “continued use of (the) water entitlement”
sought, nor of any identifiable lesser entitlement. I have been presented with no means
of ascertaining what would constitute “the efficient use of” any water entitlement that
could be ordered by me.
[28] The demand for water continues to grow whilst its supply remains at best constant or at
worst in decline. It is therefore a resource whose efficient and productive continuing use
is to be encouraged consistent with maintaining the integrity of the aquatic environment.
It is not a resource that is to be sequestered to an individual for purposes not patently
involved in economic production. As much as made clear in s.53 of the Barron Plan.
[29] The appeal is dismissed and, consequently, the review decision is affirmed.
RP SCOTT
MEMBER OF THE LAND COURT
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QLC/2008/151