Devpro (a firm) v Seamark & Anor [2007] QCA 241
SUPREME COURT OF QUEENSLAND
CITATION: Devpro (a firm) v Seamark & Anor [2007] QCA 241
PARTIES: DEVPRO (A FIRM)
(plaintiff/ first respondent)
v
SEAMARK PTY LTD ACN 058 624 516
(first defendant/ appellant)
MACPRO PTY LTD ACN 068 964 447
(second defendant/ second respondent)
FILE NO/S: Appeal No 474 of 2007
SC No 3221 of 2004
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 27 July 2007
DELIVERED AT: Brisbane
HEARING DATE: 15 June 2007
JUDGES: Jerrard JA, White and Atkinson JJ
Separate reasons for judgment of each member of the Court,
each concurring as to the orders made
ORDER: 1. Dismiss the appeal
2. Appellant pay the first respondent’s costs
CATCHWORDS: CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS – OTHER
MATTERS – where a contract to purchase a site for
development was entered into – where the contract was
executed – where the appellant later purported to terminate
the agreement – whether the termination was valid in
accordance with clause 16.6 of the contract
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS – OTHER
MATTERS – where the learned trial judge was required to
calculate a “development fee” in accordance with clause 13 in
the contract – where the calculation of the development fee
was contingent on the interpretation of the terms “Building”
and “fully leased” – whether in the circumstances the
buildings were fully leased
-- 1 of 26 --
2
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS – OTHER
MATTERS – where the contract provided a dispute
resolution mechanism in clause 22 – where the contract also
contained a requirement of “full faith” in clause 28 – whether
clauses 22 and 28 can be used to determine what the
percentage profit would be for the purposes of clause 13.2 –
whether a term relating to the payment of a fair and
reasonable percentage should be implied in the contract
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS – OTHER
MATTERS – where the learned trial judge calculated a
reasonable construction cost – whether the calculation was
correct
TRADE AND COMMERCE – TRADE PRACTICES ACT
1974 (CTH) AND RELATED LEGISLATION –
CONSUMER PROTECTION – UNCONSCIONABLE
CONDUCT – WHAT CONSTITUTES – whether the
conduct was unconscionable
Trade Practices Act 1974 (Cth), s 52AC
Booker Industries Pty Ltd v Wilson Parking (Qld) Pty Ltd
(1982) 149 CLR 600, applied
Foley v Classique Coaches Ltd (1934) 2 KB 1, distinguished
Sargent v ASL Developments Ltd (1974-75) 131 CLR 634,
distinguished
Sudbrook Trading Estates Ltd v Eggleton [1983] 1 AC 444,
distinguished
COUNSEL: M Stewart SC, with D O’Sullivan, for the appellant
S Couper QC for the first respondent
SOLICITORS: Schweikert Lawyers for the appellant
Forbes Dowling Lawyers for the first respondent
McCullough Robertson for the second respondent (the second
respondent withdrew from the appeal)
[1] JERRARD JA: This appeal concerns the construction of an agreement executed
on 10 December 1998 between the appellant Seamark Pty Ltd and Devpro, the latter
being a partnership formed between Woodcroft Trading Co Pty Ltd (“WTC”) and
Macpro Pty Ltd (“Macpro”), formed to undertake land development. The
agreement between Devpro and Seamark concerned the development of a parcel of
land at the corner of Progress Road and Garden Road at Richlands, known as
“Progress Corner”. The learned trial judge gave reasons for judgment on 18
December 2006, upholding claims by Devpro for payment to it of a Development
Fee under the agreement, and a further, much smaller, claim for a quantum meruit
payment. On 20 December 2006 the judge settled the final order that the appellant
pay the respondent the sum of $1,106,154.11, including interest in the sum of
-- 2 of 26 --
3
$257,508.61 from 26 August 2003 to 20 December 2006. Seamark’s grounds of
appeal, amended by leave granted on 15 June 2007, attack the order and reasons for
it on a variety of grounds.
The actors
[2] WTC was led or managed by a Mr Woodcroft-Brown and Macpro by a Mr Grant
McLennan. Mr Woodcroft-Brown was a Civil Engineer whose involvement in
developments in Brisbane was on the basis of identifying sites and then finding
financiers to allow development to proceed under his supervision. In or about
March 1998 he learnt of Progress Corner as a potential site for a drive-through KFC
outlet, on land which included a service station patronised by heavy vehicles
coming off the Ipswich Motorway and out of existing industrial areas which the
motorway served. The land was adjacent to Progress Road, a busy thoroughfare
giving access to a large residential development. Devpro acquired an option to
purchase the site, and Mr Woodcroft-Brown was later introduced to Mr Harold
Shand of Seamark Pty Ltd. Mr Shand, formerly a practicing solicitor, was then
looking for an investment project with a short turnover, and he and Mr Woodcroft-
Brown ultimately agreed to a plan whereby the appellant Seamark would acquire
the land, it would be subdivided (with Seamark retaining ownership of the service
station site), and the respondent Devpro would develop and then sell the balance.
Subdivisional approval was given by the Council on 2 December 1998, and
Seamark entered into a contract on 18 June 1998 to purchase the site for
approximately $2.6million. On 10 December 1998 the agreement the subject of this
litigation, a Development Agreement, was executed between Seamark and Devpro.
The principal matter litigated in this action was Devpro’s claim under that
agreement to what was styled a Development Fee.
Some Agreement terms
[3] The agreement defined1 the “Project” as:
“the subdivision of the Parcel and the construction of the Buildings
on the Development Land and its surrounds in accordance with the
Plans and Specifications, the leasing of the Buildings and the sale of
the Development Land and Buildings. The project does not include
the ownership of the Ampol Land.”
The “Buildings” were defined as:
“the building or buildings comprising a fast foods store, a restaurant
and a shop as defined in the Town Plan to be erected on the
Development Land in accordance with the Plans and Specifications
and where the context so admits any part of the Buildings.”
“Plans and Specifications” were defined to mean:
“the plans and specifications to develop the Development Land
which have been approved by the Council and the Owner and any
variations or amendments agreed upon pursuant to the provisions of
this Agreement.”
When the agreement was executed, there were no plans and specifications which
had been approved by the Council, but a number of different sketches had been
1 The definitions in the agreement applied “unless the subject or context is inconsistent.”
-- 3 of 26 --
4
considered by Mr Woodcroft-Brown and Mr Shand during the negotiation phase.
They had settled on one described as “Sketch A”2 as that which they would pursue.
It showed a drive-through fast food premises on the north west corner, diagonally
opposite an L-shaped building containing a fast food outlet of 130m2 , a retail area of
300m2 , and a separate fast food outlet area of 340m2 . That L-shaped building
adjoined the service station land, which was to the east.
[4] As it happened the L-shaped building, which came to be described as Stage 1, was
all that was constructed under the agreement. That was because by November 1990
all hope of obtaining a tenant for a drive-through fast food outlet had dissipated. On
or about 9 December 1999 a material change of use application was lodged,
approved on 17 May 2000, for permission to have retail as well as fast food use of
the site. But the parties did not make any alteration or amendment to the agreement
and the definition of “Buildings”. “Stage 2” came to be envisaged as a
complimentary L-shaped building along the north east of the site, but was not
constructed, because of difficulty in securing future tenants. Stage 1 as constructed
did include a fast food store (a Dominos Pizza store), a restaurant (a Subway outlet,
which was within the definition of “restaurant” in the Town Plan), and a video shop,
as well as other tenancies. The approved plan for what was termed Stage 1 showed
12 tenancies, and it appears that what was built allowed for that many.
[5] The learned trial judge concluded that since both parties to the agreement knew that
no plans and specifications had been approved at the time it was entered into, they
must be taken to have intended to use the future perfect tense – that is:
“The plans and specifications... which shall have been approved”
in the definition of “Plans and Specifications” in the agreement. I agree, and there
was no serious challenge to that construction on the appeal. But so construing
“Plans and Specifications” does not necessarily assist in the construction of
“Buildings”, which is a critical part of the appellant’s alternative case. It argued
that the learned judge was wrong to understand that term when used in Clause 13 of
the agreement as restricted to the buildings specifically described in the definition of
“Buildings”, namely a fast food store, a restaurant, and a shop. The pleadings show
agreement between the parties that the project pursuant to the Development
Agreement was originally the construction, leasing and sale of a fast food
restaurant, a shop and a drive-through food store,3 and the pleadings describe the
context in which the Development Agreement was made. That context is relevant
to its proper construction; the parties left the definitions in their agreement
unamended if and when its execution varied from what was originally
contemplated.
[6] The Development Agreement essentially required that the appellant make the land
available for development and provide finance, and that the respondent was to be:
“... responsible for the construction and administration of the Project
on a day to day basis to ensure development of the Development
Land in accordance with the Plans and Specifications, the leasing of
the Buildings (subject to the Owner’s consent) and the sale of the
Development Land and Buildings (subject to the Owner’s consent)
and shall use its best endeavours to complete the Project in
2 Reproduced at AR 769.
3 Paragraph 2(a) of the Further Amended Statement of Claim, admitted by paragraph 3 of the second
Further Amended Defence (at AR 2427 and 2511 respectively).
-- 4 of 26 --
5
accordance with the Plans and Specifications by the Sunset Date
and..”
There followed a list of obligations placed on the respondent. The Sunset Date was
extended by agreement to 15 April 2001.
Did the appellant validly terminate?
[7] Clause 16.6 read:
“If completion of the Project is delayed beyond the Sunset Date (as
extended pursuant to Clause 16.2) the Owner may at any time
terminate this Agreement by notice in writing to the Developer, in
which event the Developer shall have no further Claim of any kind
whatsoever against the Owner arising under this Agreement or by
reason of any act or thing done or to be done by the Developer on the
Owner’s behalf except the right to terminate this Agreement,
provided however that such termination shall be without prejudice to
any existing liability of the Owner to pay the expenses payable by it
under this Agreement then already incurred.”
The first and principal ground of appeal contends that the appellant did validly
terminate the agreement by notice in writing on 28 May 2002. It was common
ground that the date of completion of the project was the date of sale of the
development land (excluding the Service Station, which Seamark retained) on
27 June 2003, for $4million. That date of completion was well after the date on
which the appellant claimed to have exercised the right to terminate under Clause
16.6. If that termination was valid, then the respondent was not entitled to the
Development Fee which the learned judge ordered the appellant pay it, in an amount
of $840,017.50, together with interest thereon. The learned judge had found the
respondent was entitled to that Development Fee, in accordance with Clause 13 of
the Agreement.
[8] Clause 13 read:
“13. Development Fee
13.1 If the Buildings are fully leased at the Date of Completion of
the Project, the Owner shall pay to the Developer within 60
days from the Date of Completion of the Project a
Development Fee calculated as follows:-
Development Fee = A + B + C
Where: -
A = 5% of the Development costs less the
Developer’s Fee paid to the Developer by the Owner
in accordance with Clause 12.
B = 20% of the Growth Rental.
C = 45% of the Profit.
13.2 If the Buildings are not fully leased at the Date of
Completion of the Project, the Owner shall pay to the
Developer within 60 days from the Date of Completion of
the Project a Development Fee calculated as follows:
Development Fee = A + B + C
Where:-
-- 5 of 26 --
6
A = 5% of the Development Costs less the Developer’s Fee
paid to the Developer by the Owner in accordance with
Clause 12.
B = 20% of the Gross Rental (if any).
C = % of the Profit: a proportion of the profit as agreed.”
[9] It was also common ground that the parties had been unable to agree on the
proportion of the profit to be paid under Clause 13.2 as the component C of the
Development Fee, if the Buildings were not fully leased at the Date of Completion.
Since the appellant contended that on the proper construction of “the Buildings”,
they were not fully leased at the date of completion (27 June 2003), it contended
that Clause 13.2 applied, with the result that the respondent was not entitled to any
fee. That result followed from the failure to agree to item C of that fee, and from
the fact that the respondent had abandoned an argument that there could be a
severance of the un-agreed component from the two other items.
[10] The learned trial judge described the project as fraught with delays and other
problems variously attributable to Council requirements, lack of mutual respect
between Mr Woodcroft-Brown and Mr Shand, Mr Shand’s overriding the tender
process initiated by Mr Woodcroft-Brown and insisting upon the appointment of a
builder of Mr Shand’s choosing, an extremely poor relationship between Mr
Woodcroft-Brown and Mr Bennett, the builder’s principal, the need to negotiate
with Caltex, and difficulties attracting tenants. The judgment records Mr Shand
being intent upon the appointment of a builder trading as Boss Constructions, with
Mr Bennett as the principal, although the judge found that Mr Shand’s reason for
enthusiasm for Mr Bennett’s company was not revealed, even at the trial. The judge
also found that Mr Woodcroft-Brown had remonstrated about the appointment of
Boss Constructions, to no avail, and that Mr Shand had not supplied Mr Woodcroft-
Brown with a copy of the building contract between Seamark and Boss
Constructions, despite repeated requests. The judge found that Mr Shand assumed
the role of superintendent under the contract, effectively excluding Mr Woodcroft-
Brown from the supervisory and co-ordinating role assigned to the latter under the
Development Agreement, and that Mr Shand had deliberately given Mr Woodcroft-
Brown mixed messages about his wish to proceed with the project, in order to keep
pressure on Devpro.
[11] The judge found that Mr Shand’s strategy was to pretend to Mr Woodcroft-Brown
and Devpro that Mr Shand wanted to build Stage 2; in fact Mr Shand wanted to
flush out a potential buyer of the land, who might be interested in a larger scheme
that would include the land on which Stage 2 would be built. But he had no
intention of building Stage 2 in the absence of solid tenant interest. Devpro
continued to seek tenants for Stage 2, and Mr Woodcroft-Brown eventually
introduced the Director and Chief Executive Officer of the Queensland Lions
Soccer Club, and Pivotal Holdings Pty Ltd, to Mr Shand. Ultimately the
Queensland Lions Soccer Club acquired the development land for $4million, (not
including the service station) and settlement was on 23 June 2003. Devpro claimed
a right to the Development Fee under Clause 13.1, contending that the “Buildings”
as defined in the agreement were fully leased at the date of completion of the
project, and that it was entitled to the fee calculated in accord with Clause 13.1.
That claim was upheld by the learned judge.
-- 6 of 26 --
7
First ground of argument
[12] The appellant’s first argument was that the learned trial judge had erred in
concluding that a letter by it, dated 28 May 2002, in which it purported to terminate
the Development Agreement in accordance with Clause 16.6, was not effective to
do so. The learned judge so held because the judge concluded that Seamark had
earlier irrevocably elected not to exercise that right. The learned judge’s
conclusions were expressed in paragraph [60] of the reasons for judgment as
follows:
“By 16.6 the first defendant could terminate the Development
Agreement ‘at any time’ after 15 April 2001 because the Project was
not complete. It was confronted with the choice of terminating the
agreement or keeping it on foot. The right of termination was a
continuing one, not required to be exercised properly. Whether the
first defendant exercised its right to election must be inferred from its
conduct after 15 April 2001. As the High Court observed in Immer
(No 145) Pty Ltd v The Uniting Church in Australia Property Trust
(NSW) 4 –
‘The point is that where the right to rescind is a continuing
one, it is not so readily concluded that the party entitled to
rescind has abandoned that right completely as opposed to
taking no action to exercise the right at the time in question.’
Nevertheless, once an election is made, it cannot be exercised again.
Here the first defendant by Mr Shand made a deliberate decision not
to terminate in reliance on Clause 16.6 because the project was then
commercially unsaleable and by memoranda dated 24 May 2001 and
5 July 2001 it called on the plaintiff to perform its obligations under
the agreement. As its senior counsel conceded, Mr Shand’s conduct
effected an election not to terminate.”
[13] The Sunset Date originally fixed in the agreement was December 31, 1999 but that
was amended to 30 April 2000, and by further agreement pursuant to Clause 16.2,
to 15 April 2001. Devpro wrote a memorandum dated 23 March 2001 to the
appellant, for the attention of Mr Shand, which suggested that they agree on the
timing and Sunset Date for Stage 2.5 Mr Shand replied to that particular suggestion,
in a memorandum dated 3 April 2001, that:
“Stage 2 – First and foremost, the timing and sunset date will be
driven by the tenants. Get the tenants in place and I can then make
some considered decisions rather than agreeing to dates that cannot
be achieved.”
[14] Mr Shand did not exercise on the appellant’s behalf the right to terminate on or
about 15 April 2001, and his evidence in cross-examination was that he had made a
deliberate decision at that time not to do that, because the project was then
commercially unsaleable.6 What he did do was write to the first respondent on
24 May 2001, in a short note that read:
“Re Richlands
4 (1992-1993) 182 CLR 26, 42.
5 At AR 1401.
6 At AR 318.
-- 7 of 26 --
8
I think you and Grant promised a tenancy update yesterday. Can you
let me know what is going on? I am keen to have building work
under way as soon as possible so it can be completed in time for
November opening.”7
He had earlier sent Mr Woodcroft-Brown an action list on 2 May 2001,8 listing
“outstanding matters”, and what each of Mr Shand, Mr Woodcroft-Brown, and Mr
McLennan were required to do. That list self-evidently assumed the Development
Agreement continued, and the document concluded with the statement that “I am
now in a position to move forward without the constraints that the failure to sell
Toowoomba caused.” The last remark referred to problems with another project of
his in Toowoomba.
[15] He sent another memorandum dated 5 July 2001, which relevantly read:
“2. The other issues all relate to tenancies where a lot seems to
be happening but nothing is getting reported e.g.
• A potential tenant for the hot bread shop in stage
I.
• A tenant for the other vacancy in stage I.
• The position with the Supermarket &
newsagency in stage 2.
• Fauldings in stage 2.
Can you please get me some feedback and give me a list of
the potential tenants with their contact details so I can find
out exactly where they are up to.”
[16] Mr Shand agreed in cross-examination that he had (thereby) required Mr
Woodcroft-Brown and Mr McLennan on behalf of the first respondent to continue
to find tenants for Stage 1, and agreed that the only obligation they had to do that
was pursuant to the Development Agreement. He also agreed that at a later time he
had instructed them to begin finding tenants for Stage 2, and that again the only
obligation they could have had to do that was pursuant to the agreement. He
acknowledged that he then wanted them to perform their obligations to achieve the
objects of the Development Agreement.
[17] In a further memorandum dated 17 September 2001, Mr Shand asked Mr
Woodcroft-Brown:
“2. Richlands
What is the state of play with the tenants and the
convenience store. Is anything going to happen or should
we just shut Stage 2 down and wait till things improve and
tenants or developers start to approach us? Otherwise we
just seem to be wasting time and money and effort.”
On 1 October 2001 Mr Shand wrote again to Mr Woodcroft-Brown, and that
communication included the following:
7 At AR 1418.
8 At AR 1417.
-- 8 of 26 --
9
“4. Tenants at Richlands continue to be a concern. The Sunset
Clause on our joint venture agreement, which had been
extended twice, has long since expired. I think it is
important that we move to re-introduce a Sunset Clause so
we can bring about some closure on the development would
appreciate your suggestions of a date by which you expect
to bring about some real progress in the leasing of Stage 2.
As you observe, this impacts on the performance of tenants
in Stage I. We need to finalise our involvement in the
project so we can get on with other developments and I am
sure you are in the same position.”
[18] Devpro relied on those communications to support the finding of an election to
forgo the right of termination given by Clause 16.6. But the appellant argued there
were other, later, communications from both parties, in which Mr Shand impliedly
asserted in his correspondence a right to terminate, and Mr Woodcroft-Brown
impliedly accepted (or did not challenge) that the right may exist. That acceptance
was first suggested by a memorandum from Mr Woodcroft-Brown dated
1 November 2001, which included the request:
“...that any decision to sell the property or terminate the joint venture
is held over until February 2002. There has never been a Sunset
Date agreed on for Stage 2, and a reasonable period will be needed to
tenant and build this stage. February is therefore not the Sunset Date
but a decision date.”
[19] The right of termination implicitly acknowledged was one contended for by senior
counsel for Seamark at the trial, namely that it was open to Seamark (not
withstanding any earlier election to forego or abandon its rights of termination
under Clause 16.6) to call for the project to be completed within a reasonable time,
and in the event that it was not, to terminate the Development Agreement. The
learned trial judge understood that argument to be based on the general principle
that where an agreement is not of a finite duration, it may be brought to an end by
one party on reasonable notice to the other.9 The judge recorded that senior counsel
for Seamark had submitted that the evidence supported the conclusion that in the
period from about October 2001 to 28 May 2002, Mr Shand had made it clear to Mr
Woodcroft-Brown, that unless the project was completed promptly, or the plaintiff
either alone or with others took it over on terms satisfactory to Seamark, Seamark
would terminate the agreement.
[20] The learned judge held that termination on that basis had not been pleaded, and that
in any event the factual foundation for the submission was not made out, because
Mr Shand had not made his position unequivocally clear to Mr Woodcroft-Brown,
and on the contrary had deliberately continued to send mixed messages. On the
appeal senior counsel for Seamark relied only on the argument that the
Development Agreement had been terminated by the notice given on 28 May 2002,
exercising the right given under Clause 16.6, and did not contend that termination
had occurred after the giving of reasonable notice by Seamark; none of the learned
judge’s findings of fact about Mr Shand and his dealings with Mr Woodcroft-Brown
were challenged on the appeal. That absence of challenge is relevant because Mr
Woodcroft-Brown’s letter of 1 November 2001, remarking there had been no Sunset
9 The learned judge discussed these matters at [61] of the reasons for judgment.
-- 9 of 26 --
10
Date agreed for Stage 2, and describing his opinion of a difference between a Sunset
Date and a decision date, is fairly explicable on an understanding and acceptance of
a right to terminate after reasonable notice, rather than on the basis of Clause 16.6.
[21] Mr Shand replied on 5 November 2001 to Mr Woodcroft-Brown’s communication
of 1 November 2001, contending there was no Sunset Date for Stage 2 because
there was never any distinction in the documents between Stage 1 and Stage 2:
“i.e. the Sunset Date was to finish the entire project. I don’t agree
with your idea of February being a decision date. We need to bring
things to a head for a decision by 30 November 2001.” 10
[22] He then wrote on 10 December 2001 to Mr Woodcroft-Brown. That
communication included that:
“As you said earlier, we need to set a decision date to get on or get
out. I have finalised all the outstanding issues with Caltex to extend
the lease term. To be on the safe side, I need to notify formally of
our intentions. I understand there a (sic) no current unconditional
lease commitments in place. I therefore propose to terminate any
Joint Venture arrangements, which may exist between us with effect
from 31 January 2002. I will terminate any leasing appointments and
you are instructed not to appoint any leasing agents from today.”
That memorandum did not assert that Mr Shand was relying on the appellant’s
behalf on Clause 16.6 of the Development Agreement. Despite that declaration,
Mr Shand later wrote to Mr Woodcroft-Brown on 22 April 2002, that he wanted to
“fast track”, in the hope:
“This will encourage the existing tenants in Stage 1 and fire up some
of the wavering prospective tenants in Stage 2... Seamark wants to
wrap it up by completing the development and moving on with other
projects it has...”
That communication was inconsistent with any termination on 31 January 2002.
But then Mr Shand wrote a letter dated 28 May 2002 to Mr Woodcroft-Brown. It
relevantly read:
“I therefore give notice under the Development Agreement of the
termination of the Development Agreement as contemplated by
Clause 16.6 of the agreement. Consistent with the owner’s
obligations under that Clause, I am enclosing a cheque for
$23,367.30 for outstanding fees claimed by you.”
Devpro did not accept that any such right to terminate any longer existed.
[23] The appellant argues that the learned judge mistook the concession in its written
argument, which was only that if a power to terminate pursuant to Clause 16.6 was
one which it was required to exercise promptly, then the evidence justified the
conclusion that Mr Shand’s conduct had effected an election not to exercise the
power. The appellant pointed to the conclusion by the learned judge that the right
of termination given by that clause was a continuing one, not required to be
exercised promptly, and submitted that its concession was misapplied. That may be
accurate, but the issue is not the concession but whether the learned trial judge was
correct in concluding that the appellant had, by its conduct, effected an election not
10 At AR 1458.
-- 10 of 26 --
11
to terminate. As to that, the appellant submitted that while Mr Shand conceded
having made a deliberate decision on or about 15 April 2001 not to terminate in
reliance on Clause 16.6, because of the difficulty in selling the project, it did not
follow that that involved an election which was communicated to Devpro. The
appellant argued that the memoranda dated 24 May 2001 and 5 July 2001 did not
evidence a deliberate decision not to terminate, nor communication of an election.
[24] It referred to the judgment of Mason J in Sargent v ASL Developments Ltd (1975)
131 CLR 634 at 655 as follows:
“A person is said to have a right of election when events occur which
enable him to exercise alternative and inconsistent rights, i.e. when
he has the right to determine an estate or terminate a contract for
breach of covenant or contract and the alternative right to insist on
the continuation of the estate or the performance of the contract. It
matters not whether the right to terminate the contract is conferred by
the contract or arises at common law for fundamental breach – in
each instance the alternative right to insist on performance creates a
right of election.
Essential to the making of an election is communication to the party
affected by words or conduct of the choice thereby made and it is
accepted that once an election is made it cannot be retracted.
(Citations omitted). No doubt this rule was adopted in the interest of
certainty and because it has been thought to be fair as between the
parties that the person affected is entitled to know where he stands
and that the person electing should not have the opportunity of
changing his election and subjecting his adversary to different
obligations.
A person confronted with a choice between the exercise of
alternative and inconsistent rights is not bound to elect at once. He
may keep the question open, so long as he does affirm the contract or
continuance of the estate and so long as the delay does not cause
prejudice to the other side. An election takes place when the conduct
of the party is such that it would be justifiable only if an election had
been made one way or the other... So, words or conduct which do
not constitute the exercise of a right conferred by or under a contract
and merely involve a recognition of the contract may not amount to
an election to affirm the contract.”11
[25] The appellant also referred the Court to the statements in Immer (No 145) Pty Ltd v
The Uniting Church in Australia Property Trust (NSW) (at 182 CLR 38 and 39)
where the following remarks of Stephen J in Sargent v ASL Developments12 were
quoted:
“The words or conduct ordinarily required to constitute an election
must be unequivocal in the sense that it is consistent only with the
exercise of one of the two sets of rights and inconsistent with the
exercise of the other.”
11 At CLR 655, 656.
12 At (1974) 131 CLR at 646.
-- 11 of 26 --
12
The joint judgment by Deane J, Toohey J, Gaudron J, and McHugh in Immer went
on (at CLR 39):
“The consequences of election may well be serious for the party
electing; in particular, election involves the abandoning of a right
that is available. A party can only be held to have elected ‘if he has
so communicated his election to the other party in clear and
unequivocal terms” (citing from “The Kanchenjunga” [1990] 1
Loyd’s Rep 391, at p 398 per Lord Goff of Chieveley).
[26] Their Honours added, a little later, (at CLR 42, in the passage cited by the learned
trial judge) that:
“The point is that where the right to rescind is a continuing one, it is
not so readily concluded that the party entitled to rescind has
abandoned that right completely as opposed to taking no action to
exercise the right at the time in question.”
The appellant relies on those statements of the applicable law in support of its
contention that Mr Shand had simply not exercised the right to terminate before
May 2002, and that its communications before that had merely involved a
recognition of the contract, while taking no action to exercise the still existing right
given by the contract to terminate. The appellant argued that an unequivocal
abandonment had to be demonstrated, to show an election, and none had been
shown.
[27] The appellant did not suggest that the learned judge had erred in any way in the
judge’s description of the applicable law or relevant authorities. The
communications coming from Mr Shand and quoted herein show that he did assert
inconsistent positions to Mr Woodcroft-Brown, as the learned judge found. He both
required that Devpro continue to perform its obligations under the agreement, and
represented that Seamark would too; but occasionally asserted a right and an
intention to terminate their agreement, while also requesting an agreement that yet
another Sunset Date be fixed. Finally, he asserted a right to terminate based on the
Sunset Date which had been reached a little over a year earlier. But the point made
by Mason J in Sargent v ASL Developments Ltd was that Mr Shand and Seamark
could not exercise inconsistent rights and were required to elect between them, and
Mr Shand by his conduct communicated both the requirement that Devpro continue
to fulfil the contractual role it had, and that Mr Shand accepted the agreement
continued. It was open to the learned judge to conclude, as the judge did, that Mr
Shand’s conduct effected an election to terminate.
[28] I therefore agree with the learned trial judge that the appellant’s conduct after April
2001 asserted a position inconsistent with the continued option available to it, to
terminate the agreement in reliance on Clause 16.6. It had communicated an
affirmation of the continuance of the contract in clear and unequivocal terms, and
that was an election not to terminate in reliance on Clause 16.6. It was no longer
open to it to rely on that clause in May 2002.
Were the Buildings fully leased?
[29] Mr M Stewart SC, senior counsel for Seamark, submitted in his next argument that
the learned judge had erred in construing the term “Buildings” in Clause 13.1 of the
agreement, and had accordingly erred in concluding that those buildings were fully
-- 12 of 26 --
13
leased as at the date of completion of the project. That had the result that the
learned judge erroneously assessed the Development Fee owing to the plaintiff in
reliance on Clause 13.1 of the agreement. Mr Stewart SC submitted that on the
proper construction of “Buildings”, the evidence showed that there was one which
had not been leased as at the date of completion, and accordingly Clause 13.2
applied. Since it applied, and since there had been no agreement between Devpro
and Seamark as to the profit percentage in item C of that calculation, Mr Stewart SC
submitted that Clause 13.2 was unenforceable for uncertainty. He referred to
Relwood Pty Ltd v Manning Holmes Pty Ltd [1990] 1 Qd R 481 (where a guarantee
provided for a credit limit “to be agreed” and - there being no such agreement - the
guarantee did not come into operation) and to Randazzo v Goulding [1968] Qd R
433. The latter case concerned an option to renew a lease, provided the rental to be
paid should be “mutually agreed upon between the parties”, which had not
happened. The Full Court held that, there being no agreement, the clause imposed
no binding obligation; both Hoare J and WB Campbell J referred to the absence of
any machinery to meet the situation of a failure to agree, as part of the reasoning
that the clause had no legal effect, in the absence of agreement.
Mr Stewart SC also submitted that Mr Couper QC for the respondent was in error in
submitting that the agreement did provide a mechanism or machinery for fixing the
percentage, should the parties fail to agree.
[30] The first matter to consider is the proper construction of “the Buildings” in Clause
13.1. Mr Stewart SC submitted, correctly in my opinion, that the object of that
clause was to provide an incentive to Devpro to act in a way which maximised the
profit which would be received by Seamark. He submitted that the learned trial
judge had correctly accepted that the best way to do that was to build and lease as
many premises as possible. While the judge accepted that submission, the judge
also accepted the submission by Devpro’s senior counsel, that to that end the parties
had agreed that the whole of Stage 1 would be built, but that agreement had not
enlarged the obligation of Devpro, described in the Development Agreement, before
it became entitled to the Development Fee under Clause 13.1. The judge concluded
that because the three tenancies designated in the definition of “Buildings” in the
Development Agreement were leased as at 27 June 2003, that was sufficient for
Devpro to be entitled to the Development Fee.
[31] Mr Stewart SC submitted that that construction undermined the object of providing
Devpro with an incentive to maximise Seamark’s profit, and that the expression
“the Buildings” in Clause 13.1 should be construed as the buildings depicted in the
plans and specifications that came to be approved by the local authority, and which
were constructed in accordance with that approval. He argued that the word
“comprising” in the definition of “Buildings” in the agreement should be read as
“including”; and that in any event since Clause 1.2 of the agreement included an
agreement that words denoting the singular should include the plural and vice versa,
the reference to “a fast foods store, a restaurant and a shop” in the definition of
“Buildings” included fast food stores, restaurants, and shops. He also submitted
that all of the tenancies depicted in the plans that were approved for Stage 1, and all
the buildings that were constructed, fell within one or other of those three
categories; so that considered together, they did comprise a fast food store, a
restaurant or a shop. He argued that only that construction made commercial sense.
-- 13 of 26 --
14
[32] Mr Couper QC submitted that the use of the singular in Clause 13.1 must have been
deliberate, because the sketch (“sketch A”)13 quite clearly showed that the parties at
that early stage were considering more than three shops or tenancies. Nevertheless,
when it came to the question of what had to be built and sold for Devpro to earn its
Development Fee, the parties defined those matters by reference to only three
particular shops, each of a different variety. He submitted that decision was
deliberate, and that while Devpro wanted to know what it had to do to be paid, both
parties were aware that the more tenancies let on the site, the larger the profit was
likely to be on the sale of the site. The definition of “the Profit” in the agreement
shows that, as one might expect, Devpro’s 45 per cent would be more if there was in
fact a bigger profit; so Devpro had the same financial incentive as Seamark, to build
and let as many premises as would increase the value of the site. The definition of
“Buildings” accordingly described the minimum necessary for Devpro to earn its
fee under 13.1. “Comprising” in the definition meant what it said; those premises
had to be built and let, to get the fee.
[33] That was the submission accepted by the learned judge. It puts the bar rather low
for Devpro, but it is clear that when the Development Agreement was signed the
parties then did envisage many more than three tenancies. Had the use of the
singular not been deliberate, as Mr Couper QC contended, it would have been very
easy either to express Clause 13.1 differently, or to define “Buildings” differently.
The construction reached by the learned judge accorded with the pleaded context in
which the agreement was reached, with the fact that the parties even then
contemplated the construction of buildings containing considerably more than three
tenancies, with a profit motive to enliven Devpro, and with the express restrictions
or limitations in the definition of “Buildings”. I agreed with the learned judge that
the construction, as intended, of “Buildings” with a considerably larger number of
tenancies did not enlarge the agreed obligation on Devpro before it qualified for the
Development Fee.
Were the “Buildings” “fully leased”?
[34] If that conclusion be wrong, then I accept the submission by Mr Stewart SC that the
learned judge was in error in the conclusion that the buildings were fully leased as
at the date of completion. The evidence was quite clear that one tenancy, which had
been negotiated before the completion date, had not been executed by either the
intended tenant or the landlord by that date. The learned judge accepted the
submission that the negotiations between Seamark and the tenant were concluded
when the last term was agreed shortly before the completion date, and all that
remained to be done was the execution of the lease. The judge accepted that it was
“practically too late for the lease to be executed, and it was thought better for the
purchaser to grant the lease as lessor”14 , and the judge accordingly accepted that if
the judge was in error as to the construction of “Buildings”, then they were
nevertheless fully leased.
[35] On the appeal Mr Stewart SC put an uncontested chronology before this Court,
which established that the evidence was that there were negotiations on the terms of
the lease after the date of completion, held between the intending tenant and the
ultimate purchaser of the site, and the terms of the proposed lease were amended
13 Reproduced at AR 769.
14 At reasons [77].
-- 14 of 26 --
15
after that date. The learned judge was therefore in error in fact in accepting the
submission that the terms had been agreed upon before the completion date; they
had not been. As at the date of completion the proposed tenant had not signed a
lease, nor paid the deposit, and the final terms were only agreed upon, the deposit
paid, and the lease executed by the new lessor and the lessee, after the date of
completion. In those circumstances, if the appellant’s construction of “Buildings”
in Clause 13.1 is correct, the buildings were not fully leased at the date of
completion of the project. Accordingly, Clause 13.2 would apply, and I accept the
appellant’s submission that that clause was unenforceable for uncertainty.
[36] Mr Couper QC challenged that last conclusion, and repeated on the appeal the
submissions made to the learned trial judge, that Clause 22 of the Development
Agreement provided a dispute resolution provision to which the Court could have
regard if Clause 13.2 applied, and that Clause 28 provided the criteria by which the
dispute should be resolved. Clause 22 read:
22. “DISPUTE RESOLUTION
22.1 In the event of any dispute between the Parties concerning
this Agreement or any matter arising under it which is not
resolved by agreement between them within 15 Business
Days after notice from one to the other, the dispute may be
referred by any Party for the final decision of a person (“the
Expert”) appointed in accordance with Clause 22.2 who
must give a decision in writing on the matter. The Party
who wishes to refer a matter to the Expert must serve on the
other Party a written reference giving full particulars of the
matter and must serve on the other Party a written reference
giving full particulars of the matter and thereupon the
Parties must attempt to reach agreement on the appointment
of the Expert.
22.2 If after 5 Business Days from service of the written
reference the Parties are unable to agree upon the
appointment of the Expert, any Party may request the
President for the time being of the Queensland Law Society
Inc. to nominate a person having the qualifications set out in
Clause 22.3.
22.3 The Expert referred to in Clause 22.1 must be a professional
person in the discipline most appropriate to the character of
the dispute and must be an individual member, or a director
of a corporate member, of the Expert’s professional body
with not less than 10 years continuous professional
experience in his discipline.
22.4 In determining a matter referred to him, the Expert shall act
as an expert and not as an arbitrator.
22.5 In the event that any Party:-
-- 15 of 26 --
16
(a) does not agree with the wish of the other that a matter be
referred to the Expert for determination;
(b) is not satisfied with a decision of the Expert,
it shall be at liberty to apply to the court for its determination upon
the matter. Unless the Parties agree to waive time limits, an
application to the court must be made:-
under Clause 22.5(a), not later than 10 Business Days after
the service of a written reference on that Party under Clause
22.1;
under Clause 22.5(b), not later than 15 Business Days after
that Party receives the written decision of the Expert.
22.6 Where a determination of the court amends or alters a decision of
the Expert the determination of the court supersedes the decision of
the Expert.
22.7 Nothing in this Clause shall be construed to prevent the Parties
from agreeing that the Expert’s decision is final and binding in
respect of a particular matter and, except in a case of error of law,
any such agreement has effect according to its terms.”
[37] Clause 28 read as follows:
28. “FULL FAITH AND FURTHER ASSURANCE
28.1 Each Party will:-
perform its Obligations and be just and faithful to the other
in all its activities and dealings concerning the Project, and
any other matter provided for in this Agreement; and
at all times, whether or not expressly required to do so, give
a full and true account to the other Party of all mattes within
its knowledge relating to the Project.
28.2 Each Party will execute all further documents and do all other
things as are necessary or desirable to give full effect to this
Agreement.”
[38] Mr Couper QC submitted in the respondent’s written argument that Clause 28.1
involved the notion that the percentage profit would be determined by reference to
what was a fair and reasonable percentage between the parties. His written
submission continued that even in the absence of a clause such as 28.1, there would
be implied into the agreement a term that the amount to be paid to the developer as a
percentage would be a fair and reasonable percentage. In his oral submissions, he
submitted that Clause 28.1 provided an inherent obligation that when coming to an
agreement on a percentage payable under Clause 13.2, the agreement would be as to
a reasonable percentage or a reasonable sum. Those submissions referred to Foley v
Classique Coaches Ltd (1934) 2 KB 1, Xstrata Queensland Limited v Santos Ltd &
-- 16 of 26 --
17
Ors [2005] QSC 323 at [34]-[37], Sudbrook Trading Estates Ltd v Eggleton [1983]
1 AC 444, Booker Industries Pty Ltd v Wilson Parking (Qld) Pty Ltd (1982) 149
CLR 600 (particularly from Brennan J at 614-616) and to Helmos Enterprises Pty
Ltd v Jaylor (2005) 12 BPR 23, 021 at 23031-23, 034.
[39] An immediate problem with that submission is that it assumes what is not obvious,
that the parties’ inability to agree on the proportion of the profit to be paid under
Clause 13.2 was a:
“...dispute between the Parties concerning this Agreement or any
matter arising under it which is not resolved by agreement between
them” (Clause 22.1).
[40] But assuming that it was, the respondent had not at any time sought to avail itself of
the provisions of that clause to agree to a proportion of the profits, and none of the
steps required under that clause were taken. The respondent did not refer the
“dispute” to a person appointed in accordance with Clause 22.2, as it might have
done. As to that failure, the respondent relied on, inter alia, Secured Income Real
Estate (Australia) Ltd v St Martins Investments Pty Ltd (1979) 144 CLR 596 at 607
and Mackay v Dick (1881) 6 App Case 251, for the argument that the appellant, by a
wrongful assertion that the agreement had been terminated, prevented there being
any attempt by Devpro to agree to a percentage for element C of Clause 13.2. Mr
Couper QC submitted that if there was a requirement that there be such an attempt
to reach agreement, before the dispute resolution Clause 22 was triggered, then that
requirement was to be taken to have been fulfilled by reason of Seamark’s wrongful
claim of termination. Accordingly, the provisions of Clause 22 fell to be applied as
if Devpro had given the requisite notice under Clause 22.1, and as if a person had
been appointed in accordance with Clause 22.2 to give a decision in writing on the
matter. Assuming, without deciding against the argument, that such beneficial
constructions of both the agreement and the events are available to Devpro, the
court or other decision maker would then be obliged to give a decision on what
proportion of the profit should be agreed between the parties, as a reasonable or fair
and reasonable one.
[41] Mr Couper QC submitted that Clause 28 provided the standard or basis upon which
the court (or the Expert) would determine any dispute between the parties, including
as to the agreed amount of the profit. That applicable standard derived from the
requirement that each party be “just and faithful” to the other in all dealings
concerning “… any … matter provided for in this Agreement.” But the agreement
in Clause 28 was not an agreement by either party that it would put aside its self-
interest, and consider the interests of the other, when bargaining for a share of the
profit. The cases on which the respondent relied do not lead to that construction
either. In Foley v Classique Coaches Ltd, the respondent plaintiff was a retail
dealer in petrol, and the appellant defendants were the owners of motor coaches,
who carried on business on premises adjoining those of the plaintiff. The plaintiff
agreed to sell that property to the defendants, and the sale was subject to conditions
which included that the defendants would enter into an agreement with the plaintiffs
to buy from them the fuel the appellant used in his business. That part of the
agreement was expressed:
“1. The vendor shall sell to the company and the company shall
purchase from the vendor all petrol which shall be required by
the company for the running of their said business at a price to
be agreed by the parties in writing and from time to time”.
-- 17 of 26 --
18
[42] For three years the appellants bought petrol from the respondent in pursuance of
that agreement, at prices charged by the respondent in accounts delivered to the
appellants each week. Then disputes arose as to the price and quality of the petrol.
Eventually the appellants contended that no agreement in writing as to price had
ever been made, and that they were not bound to get petrol from the respondent. A
Court of Appeal headed by Scrutton LJ upheld the decision of Lord Hewart C.J.,
essentially because there was no doubt that the parties intended to make a binding
contract and had acted for three years as if they had, including executing the
agreement to sell the land, which was sold only because of the promise to buy petrol
in the future. The Court implied a term that, in the absence of agreement as to the
price, a reasonable price must be paid, holding that if the parties could not agree on
what was a reasonable price, then (there being an arbitration clause) arbitration must
take place. That result was reached in part by the finding that there was a concluded
contract for the sale of the land, which had included the agreement that the
purchaser would buy fuel from the vendor, and in part because there was the
arbitration provision.
[43] The respondent’s position here is much weaker. What was in dispute in Foley v
Classique Coaches was the price to be paid for a commodity, petrol, generally
commercially available and for which a reasonable price could be calculated. The
matter now under appeal involves agreement on a proportion of overall profits.
Nothing in the development agreement or the evidence would give any assistance in
deciding what is either a fair, or a reasonable, percentage of the overall profit for
each of the parties. It is a very different exercise from finding, on the basis of
evidence, a reasonable price for a commercially available commodity.
[44] The respondent also relied on Sudbrook Trading Ltd v Eggleton, but that case too
involved determining the price of something (land), which could be established by
evidence. In Sudbrook, four separate leases had been made in 1949, 1955, 1966 and
1968 of four adjacent industrial premises, let for various terms of years all expiring
on December 24, 1997. Clause 9 of the lease dated November 18, 1959, provided
an option to the lessees to “purchase the reversion in fee simple in the premises
hereby demised … at such price not being less than £12,000 as may be agreed upon
by two valuers, one to be nominated by the lessor and the other by the lessee and in
default of such agreement by an umpire appointed by the … valuers.” The other
leases contained option clauses in identical terms, save as to the minimum price.
The lessees exercised their options to purchase the reversions, but the lessors
refused to appoint a valuer. The lessees sought declarations that upon the true
construction of the leases the option clauses conferred upon them valid options to
purchase the reversions in fee simple at a valuation, and that those options had been
validly exercised, and they asked for specific performance. The House of Lords
held by majority that the contract in each case upon its true construction was a
contract for sale to the lessees at a fair and reasonable price, to be assessed by
applying objective standards, namely those used by valuers.15
[45] The majority judgments treated the machinery provisions in Clause 9, for the
appointment of two valuers (or an umpire appointed by them), as a “convenient and
sensible machinery for ascertaining what is a fair and reasonable price”16 , or as
15 At [1983] A.C. at p. 479 per Lord Diplock, p. 483 per Lord Fraser of Tullybelton and p. 487-488 per
Lord Scarman and Lord Bridge of Harwich.
16 Per Lord Diplock at 479.
-- 18 of 26 --
19
subsidiary and non-essential17 (or a convenient) way of ascertaining a fair and
reasonable price at the date when the option was exercised.18 Those majority
judgments declined to hold the provisions for the mode of ascertaining the value
were an essential part of the agreement. Their Lordships went on to hold that since
the only thing that prevented the agreed machinery operating was the lessors’ own
breach of contract in refusing to appoint their valuer, the lessors should be ordered
to perform their contractual obligations to convey the fee simple for payment of a
fair and reasonable price, the latter to be assessed by applying the objective
standards of valuers. Simply because the machinery provided by the parties had
broken down, there was no reason for the court not to substitute other machinery to
carry out what had been concluded to be the main purpose, namely fixing a fair or
reasonable value for the purchase price of the property. It is an important part of the
majority reasoning that in that matter the court was satisfied that value could be
established by the expert evidence of valuers. Although the decision is a significant
one for legal principle, it applies when an agreed or contracted mode of ascertaining
a value, which value can be established by evidence, is subsidiary and non-essential.
In this matter, the mode of fixing the percentage of profit was by agreement
between the parties, a matter not susceptible to proof by evidence from others, and
one which made the mode essential.
[46] The respondent relied on the remarks by Brennan J, as his Honour then was, in
Booker Industries Pty Ltd v Wilson Parking (Qld) Pty Ltd (1982) 149 CLR 600 at
614-61. There His Honour understood the judgment in Sudbrook Trading v
Eggleton to be that a contract for sale which required the price to be fixed by a
valuer to be a contract for sale at a fair value to be ascertained by the valuer or, in
default, by the court. But that approach does not help this respondent, because there
was no agreement that it would be paid a percentage fixed by another person or
party, and (by implication) that it would (only) be a fair percentage. The joint
judgment in Booker Industries v Wilson Parking, of Gibbs CJ, Murphy J and
Wilson J, is really against the respondent; it reads:
“It is established by authority, both ancient and modern, that the
courts will not lend their aid to the enforcement of an incomplete
agreement, being no more than an agreement of the parties to agree
at some time in the future. Consequently, if the lease provided for a
renewal ‘at a rental to be agreed’ there would clearly be no
enforceable agreement. On the other hand, it is also well established
that the parties to a contract may leave terms – even essential terms –
to be determined by a third person: see the cases cited in Godecke v
Kirwan19 . In the present case, the lease itself provides the entire
mechanism for determining the rental for the renewed term. There is
no further agreement required of the parties.”20
[47] The joint judgment in Booker Industries applied the decision of the House of Lords
in Sudbrook Trading Estates Ltd v Eggleton to the extent that the joint judgment
held that decision was consistent with earlier Australian authorities, such as Butts v
O’Dwyer21 and Kennedy v Bercoe.22 In Booker Industries the High Court
17 Per Lord Fraser at 483.
18 Per Lord Scarman at 488.
19 (1973) 129 CLR 629 at 645.
20 At 149 CLR 604 and 605.
21 (1952) 87 CLR 267.
22 (1960) 105 CLR 521
-- 19 of 26 --
20
considered a lease containing a provision entitling the lessee to an option for an
extension for a further three years at:
“Such rental as may be mutually agreed between Lessor and the
Lessee and failing agreement then such rental as may be fixed by an
arbitrator nominated in accordance with the provisions of Clause
3.05(b).”
Clause 3.05(b) provided for the appointment of a single arbitrator to be nominated
by the President for the time being of the Queensland Law Society Inc. The joint
judgment held that Butts v O’Dwyer, Kennedy v Bercoe, and Sudbrook Trading
Estates v Eggleton were authority for the proposition that if the other conditions
specified in the lease were performed, both parties were obliged to do all that was
reasonably necessary to procure the nomination by the President of the Law Society
of an arbitrator, and under an obligation to request the President to nominate one.
But that was as far as the joint judgment went in applying the decision in Sudbrook
Trading Estates Ltd v Eggleton. The joint judgment is not authority overturning the
views in the majority judgments in Hall v Busst (1961) 104 CLR 206 that for a
promise to pay a reasonable price to be sufficiently certain to give an agreement for
sale legal efficacy, there must be an established market for the commodity the
subject of the bargain.23
[48] The respondent submitted that Brennan J in Booker, and Young CJ in Helmos
Enterprises Pty Ltd v Jaylor, referred to a well established principle that where a
contract has come into existence and been performed, courts will do all that is
possible to imply terms to enable it to be carried out. Mr Couper QC submitted that
the only implication required was the natural one that the price to be determined
would be a reasonable price in the circumstances. But, with respect, the parties did
not agree that a profit would be determined; they stipulated that Devpro would be
paid an agreed portion of it. I therefore disagree with Mr Couper’s submission that
Clauses 13.2, 22, and 28 entitles Devpro to ask the court to fix a fair and reasonable,
or reasonable, profit percentage for Devpro as the proportion “agreed upon”
between the parties.
[49] Nor do I accept the submission of Mr Couper QC that in any event the authorities
cited support the implication of a term that the amount to be paid to Devpro under
13.2 as part of C would be either a fair and reasonable percentage of the profit, or a
reasonable one. If the submission is correct, and if the parties had agreed a
percentage under 13.2 – as they did under 13.1 – then on Mr Couper’s submission,
either party could still object to the payment or receipt of the agreed percentage, and
contend before an expert appointed under Clause 22, or a court under Clause 22.5,
that the agreed amount, while agreed, was not a fair and reasonable percentage (or
reasonable percentage) as required by law. That would be a very curious result.
Calculation of the Development Fee
[50] The appellant’s third major ground of challenge to the judgment attacked the
judge’s quantification of the Development Fee payable to Devpro under, as the
learned judge found, Clause 13.1. Devpro pleaded it was entitled to $931,860.60,
23 Per Dixon CJ at 104 CLR 216. “(But that could only be when a recognised value or
standard of value measuring the price existed).” And per Menzies J at CLR 234.
-- 20 of 26 --
21
and the learned judge ultimately ordered payment of a Development Fee calculated
at $840,017.50. An important part of the learned judge’s method of calculation
was the conclusion that the Development Costs should be assessed at $2,292,801.
The Development Costs were a significant component in the calculations of the
Development Fee under Clause 13.1, and as Mr Stewart SC submitted in the
appellant’s written outline, any reduction in the Development Costs increased the
Profit and the overall Development Fee payable. The learned judge had accepted
that the Development Costs actually incurred were $2,940,464, as the appellant
contended, but the judge reduced those by a figure of $647,663, for the following
reasons.
[51] Devpro contended in its pleading that when Seamark appointed Boss Construction
as builder, Mr Shand had agreed on behalf of Seamark that it would take
responsibility for all risk (including excess of building costs over the tender prices
obtained by Devpro) arising from the appointment of Boss Construction as builder.
The Boss contract price was $1,565,473, and the actual amount paid to it was
$2,363,274. (There were other components of the Development Costs). Other
tenders obtained by Devpro were less than the Boss contract price, with the lowest
being one by J Kelly of $1,305,782, and Devpro’s own estimate of the costs being
$1,387,255.
[52] The learned judge did not accept Devpro’s pleaded case that Seamark had agreed to
be responsible for all building costs over the tender prices obtained by Devpro.
Instead, the learned judge accepted that Mr Woodcroft-Brown’s own evidence24
established an agreement as pleaded by Seamark, namely that when Seamark
appointed Boss Construction:
“Mr Shand, on behalf of it, and Mr Woodcroft-Brown, on behalf of
the plaintiff, orally agreed in approximately November or December,
1999 that a quantity surveyor would be appointed and that, to the
extent that the building costs actually incurred as a result of the
appointment of Boss Constructions exceeded the sum assessed by the
quantity surveyor as representing a reasonable construction price for
the works actually constructed by Boss Constructions, the first
defendant would bear the difference;”
[53] The judge was satisfied that there was an agreement in those terms, but was also
satisfied that Mr Shand never intended to appoint a quantity surveyor, and that
representations that he made to Mr Woodcroft-Brown that he had the appointment
in hand, and that an appointment had been made, were deliberately false. Those
findings were not challenged and nor were the following ones:
“[88] … Mr Shand was a hard-headed business man who was
increasingly frustrated by delays associated with a
development he had hoped would take only about 18
months. I was unimpressed by his explanations of having
perceived the necessity to pursue strategies to bring the
development to a commercially acceptable conclusion. He
was high-handed and at times blatantly misleading in his
dealings with Mr Woodcroft-Brown. He paid scant regard to
his obligations under Clause 28 of the Development
Agreement to be just and faithful in all matters provided for
24 At AR 185, quoted by the learned judge at [87] of the reasons.
-- 21 of 26 --
22
in that agreement and at all times to give the plaintiff a full
and true account of all matters within his knowledge relating
to the Project.
[89] Having appointed Boss as a builder, Mr Shand was cavalier
in the extreme in his administration of contract claims.
Progress claims submitted by Boss should have been
accompanied by supporting documentation and certified by
an architect pursuant to Clause 11.1 of the Development
Agreement. Mr Shand arranged for Lloyd Bennett &
Associates, a firm of which Mr Bennett was the principal to
be appointed as the architect, and then paid the claims
without sighting supporting documentation.”
[54] The learned judge went on:
“[90] By the time the dispute came to trial, it was no longer
practicable to engage a quantity surveyor: the Development
Land and Buildings had been sold and the builder had
destroyed its records. This eventuality will not prevent the
Court from assessing the amount payable to the plaintiff. If
there is evidence from which it can otherwise determine
what would have been a reasonable construction cost, the
Court must do the best it can to quantify the plaintiff’s loss.”
[55] The learned judge cited, for that last proposition, The Commonwealth v Amann
Aviation Pty Ltd (1991) 174 CLR 64, at 83; Ted Brown Quarries Pty Ltd v General
Quarries (Gilston) Pty Ltd (1977) 16 ALR 23, at 26 and 37; and Ray Teese Pty Ltd
v Syntex Australia Ltd [1998] 1 Qd R 104 at 109-110. I respectfully observe that
the passages cited supported the learned judge’s contention, and the appellant did
not submit otherwise. Instead, the appellant complained that the learned judge, in
calculating a reasonable construction cost, had effectively awarded the plaintiff
damages for an agreement it did not plead and which the parties did not make.
[56] Part of the appellant’s argument on that was that there was no evidence to support
the conclusion by the judge that it was no longer practicable at the date of trial
(August and September 2006) to engage a quantity surveyor. The reality is that the
learned judge was correct. There were no records, the buildings had been sold, and
the first time that Mr Woodcroft-Brown saw an executed copy of the building
contract between Boss Constructions and Seamark was in February 2006.
Seamark’s counsel repeatedly made the point on this appeal that the term pleaded by
it, and found by the learned judge, namely that the parties had agreed “a quantity
surveyor would be appointed”, was not an agreement that Seamark would appoint a
quantity surveyor, and was something Devpro could do itself, and by itself. As an
academic proposition that is accurate, but without a copy of the building contract –
for which, on the evidence accepted by the learned judge, Mr Woodcroft-Brown had
repeatedly and unsuccessfully made requests – Devpro would have had considerable
difficulty in giving sensible instructions to any quantity surveyor. Further, the judge
found that Mr Shand deliberately and falsely represented to Mr Woodcroft-Brown
that Mr Shand had appointed a quantity surveyor.
[57] What follows from all that is that it was both no longer practicable to engage a
quantity surveyor when the matter came to trial, and that there was a very good
-- 22 of 26 --
23
reason why Devpro had not taken that step before. The appellant’s argument was
that Devpro failed to take that step because it pleaded and asserted at the trial a
different agreement, namely that Mr Shand would be responsible for all excesses of
actual costs over tender prices; but that submission does not face the finding that Mr
Woodcroft-Brown was falsely told that Mr Shand had appointed a quantity
surveyor. Mr Woodcroft-Brown was not given any reason to consider that two
quantity surveyors were necessary.
[58] The learned judge set about the task of calculating from the evidence a reasonable
construction price for the works actually constructed by Boss Constructions, and
began by settling upon $1,400,000 as the starting point for a tender figure. The
judge reached that by reference to the actual contract price submitted by Boss
Constructions, and the other tenders offered; the appellant does not challenge that
figure settled upon by the judge, or the reasoning leading to it, but complains about
the judge undertaking the task at all. The learned judge then considered the
variations, for which reasonable allowance had to be made, and then made a
comprehensive and detailed survey of those, allowed some and disallowed others.
[59] Once again, none of those careful and thorough calculations by the judge are subject
to any challenge as to accuracy, validity, or any complaint that the outcome is not a
fair and reasonable one. Nor is there any challenge on the facts to the conclusion
reached by the learned judge, as to the amount that was a reasonable construction
cost, fixed by the judge, and then used by the judge to assess the applicable
Development Fee. The calculations made by the learned judge relied on evidence
called from a Mr Greenhalgh, a Civil Engineer, whom the judge described as having
meticulously reviewed the variation claims; and the judge largely rejected evidence
given by Mr Bennett, the principal of Boss Constructions, whom the judge
described as an unimpressive witness. That conclusion was not challenged, and nor
was the learned judge’s reliance on and acceptance of the evidence of Mr
Greenhalgh. There was no challenge on the appeal to the accuracy of Mr
Greenhalgh’s calculations, upon which the judge relied.
[60] The complaint on appeal was simply that the learned judge, in calculating a
reasonable construction cost, had imposed on the appellant a liability for damages in
a case not pleaded by Devpro. That was that Clause 13.1 had been varied by the
term it pleaded, and which the judge found to have been made, namely that a
quantity surveyor would be appointed and that the appellant would bear the
difference between reasonable construction costs assessed by that quantity surveyor
and the price paid to Boss Constructions. The appellant contended the learned
judge then set about finding what a quantity surveyor would have determined to be
a reasonable price for the work Boss Constructions did, and then found that
Seamark was in breach of that agreement by not appointing a quantity surveyor, and
that the Development Costs in Clause 13.1 were to be calculated by reference to
those reasonable construction costs, to be proved by evidence.
[61] It is quite true that Devpro did not plead a case in those terms, but nor did the
learned trial judge so hold. The reasons for judgment do not reveal that the judge
did as Mr Stewart SC contended. Instead, the learned judge did as the judge
described, namely found that the Development Agreement had not been terminated;
found that Clause 13.1 applied; found that the parties had agreed as Seamark
pleaded and the judge found regarding the difference between what Boss
Constructions would be paid and what a quantity surveyor would assess as
-- 23 of 26 --
24
representing a reasonable construction price for the works actually constructed;
found it was impracticable to engage a quantity surveyor by the time of the trial; but
nevertheless performed the task necessitated by the judge’s role of calculating the
Development Fee and Costs described in the agreement made by the parties. That
required the court to calculate a reasonable construction cost, and it was not argued
that the judge had not done that. The fact that the same or similar enquiries or
conclusions would have resulted, had the case been pleaded and presented
differently, is neither here nor there. The learned judge was required to calculate
the Development Fee, to which the plaintiff was entitled, doing the best the judge
could.
[62] The respondent also advanced an argument in reliance on the statements by Brennan
J in Booker Industries, which argument depended upon the premise that the
machinery provisions agreed between the parties for the determination of reasonable
construction costs had been frustrated by the appellant’s failure to appoint a quantity
surveyor. That failure, the respondent contended, should not “stymie” a court from
ascertaining those reasonable construction costs, because the court would not allow
the conduct of one party to defeat, the mechanism to stop it carrying out the
assessment.25 The submission assumed that Seamark breached the agreement by
not appointing a quantity surveyor, but that conclusion was not established either by
the pleading or the evidence accepted by the learned judge. The judge did not
purport to rely at all on the principle the respondent derived from Booker Industries
or like cases, when the judge was assessing the Development Fee, and reliance on
that argument was an unnecessary exertion by the respondent’s counsel.
[63] The appellant also complained that there was no pleaded issue as to the reasonable
construction cost, and alternatively that quantifying those costs required evidence as
to the opinion of a quantity surveyor. As to the latter point, what mattered was
whatever evidence there was, and the appellant did not argue that the evidence
relied on by the judge did not establish the reasonable construction costs. As to the
first point, while the pleadings did not put in issue the amount of “reasonable
construction costs”, senior counsel for the respondent is correct in the submission
that those issues, if not pleaded, were certainly raised at the trial. As his written
outline of argument contends in paragraph 37 thereof, Seamark’s quantum
document, exhibit 10, was tendered by consent (at AR 267-268) at the trial by the
plaintiff’s counsel, who informed the learned judge that the tender was designed to
define the remaining issues with respect to quantum. There was no demurr from the
statement that “the issue as to costs concerns Items 1 and 2, the sum was paid to the
builder and the prolongation claim, it also relates to the builder, so that’s the
remaining issue”26 . The plaintiff led evidence regarding the reasonableness of those
costs and variation claims, without objection, and the appellant led evidence from
Mr Bennett going to those same issues. It follows that the learned judge calculated
the fee claimed by the plaintiff in accordance with the evidence led without
objection, and the issues identified as in dispute, by the senior counsel appearing for
the two parties. The learned judge was not in error in any way in doing that, and
that attack on the judgment should be dismissed.
[64] It is worth adding that the appellant’s Exhibit 10 calculated the Development Costs
of the Project – as did the learned judge – with respect to all of the buildings on the
25 Transcript at page 73.
26 At AR 267.
-- 24 of 26 --
25
site, and that is the only commercially sensible way of calculating those costs or the
defined Profit. The appellant did not suggest on this appeal that there was any
inconsistency between the judge (and the parties, when they calculated the
Development Fee for the judge, based on the judge’s reasons) doing that, and the
judge’s narrowed construction of “the Buildings” in 13.1.
Section 51AC claim under the Trade Practices Act 1974
[65] The learned trial judge recorded that Devpro did not pursue its claim for damages
pursuant to s 51AC and 82 of the Trade Practices Act 1974 (Cth), and this Court
was told it made no submissions on that at trial. Its written submission on the
appeal contended that it was necessary to consider that claim, if the court rejected its
other submissions, which I do not; but I make these brief observations. The
plaintiff’s pleaded case in its paragraph 10 was that by reason of the matters pleaded
in its paragraphs 2 to 2L, Seamark’s refusal to pay the Development Fee claimed by
the plaintiff was unconscionable conduct. The matters pleaded in paragraphs 2 to
2L alleged the performance of the Development Agreement by Seamark in a
particular way, including the failure to agree on a new Sunset Date, and conduct
preventing the project proceeding to Stage 2, and an allegation that Devpro
continued to perform its obligations under the agreement up until the completion
date. There is no allegation of an agreement to appoint a quantity surveyor to
determine the reasonableness of the prices charged by Boss Constructions, or of a
failure to appoint one. But the respondent’s written submissions on that pleading
rely on the submission that the appellant was seeking to avoid paying the full
Development Fee by reason of the absence of the appointment of a quantity
surveyor and the calculation of a reasonable cost by a quantity surveyor, and that in
the circumstances the court should find that reliance on that absence was
unconscionable. As the appellant submitted, that was not the unconscionable
conduct which was pleaded, and the matter was not argued before the learned trial
judge. Finally, it is difficult to see how it would be unconscionable for the appellant
to refuse to pay a Development Fee it was not obliged to pay.
[66] Finally, the appellant contended that a small portion of the damages, ordered to be
paid by way of quantum meruit, should be set aside in full, because the claim should
have been brought by Woodcroft or its principal, Mr Woodcroft-Brown, and not by
Devpro. That was because the learned judge found that it was Mr Woodcroft-
Brown who was asked to do the work, for the which the quantum meruit was
ordered. At best that is a complaint that the proceeding was brought in the name of
the wrong plaintiff, a matter not pleaded or raised in any way at the trial; and Mr
Woodcroft-Brown was entitled, if he wished, to sue on the basis that other work he
was doing was for the benefit of the partnership.
[67] I would dismiss the appeal, and order that the appellant pay the respondent’s costs
of the appeal, assessed on the standard basis.
[68] WHITE J: I have read the reasons for judgment of Jerrard JA and agree with his
Honour that the appeal ought be dismissed.
[69] His Honour has carefully and fully set out the relevant facts and competing
submissions about them on behalf of the parties. As his Honour notes, there was no
dissent from the findings of fact made by the learned trial judge, nor, indeed, was
there disagreement about the applicable legal principles. Rather, the parties sought
-- 25 of 26 --
26
to draw different consequences from the application of the principles to the facts as
found.
[70] This is particularly the case with the important question whether the appellant
validly terminated the agreement with the respondent by notice in writing on
28 May 2002 pursuant to clause 16.6 of their agreement. To my mind, the facts
plainly establish that Mr Shand was not simply acknowledging the continuation of
the contract after he was entitled to terminate, Sargent v ASLD Developments
Limited27 . As Mr Shand’s evidence demonstrated he deliberately blew “hot and
cold” on the agreement but the clear preponderance of evidence established that Mr
Shand elected to continue with the agreement when confronted with a choice and
communicated that choice not to terminate to the respondent by his conduct.
[71] I agree with the manner in which his Honour has disposed of the other arguments.
[72] ATKINSON J: I have read the reasons for judgment of Jerrard JA and White J. I
agree that the appeal should be dismissed and with their Honours’ reasons for doing
so
27 (1975) 131 CLR 634 per Mason J at 658
-- 26 of 26 --