CallidePower Management Pty Ltd v Callide Coalfields (Sales) Pty Ltd [2007] QSC 395
SUPREME COURT OF QUEENSLAND
CITATION: CallidePower Management P/L v Callide Coalfields (Sales)
P/L [2007] QSC 395
PARTIES: CALLIDE POWER MANAGEMENT PTY LTD
ACN 082 468 700
(applicant)
v
CALLIDE COALFIELDS (SALES) PTY LTD
ACN 082 543 986
(respondent)
FILE NO/S: BS 8437 of 2007
DIVISION: Trial Division
PROCEEDING: Originating application
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 20 December 2007
DELIVERED AT: Brisbane
HEARING DATE: 4 October 2007
JUDGE: Martin J
ORDER: 1. Declare that upon the true construction of the
agreement of 11 May 1998, and in the events that have
occurred, the notifications given by the applicant to the
respondent dated 9 June 2007 were valid notifications
under the agreement and which bound the respondent to
comply with their terms.
2. The respondent pay the applicant’s costs of and
incidental to the application.
CATCHWORDS: CONTRACTS – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS – OTHER
MATTERS – where applicant and respondent entered
agreement for the supply of coal – where agreement
contained a clause with respect to the supply of additional
quantities of coal – where nominations made under contract
and amended nominations later made – appropriate method
for calculating total coal requirements under the contract –
proper method of calculating costs of coal supplied – proper
construction of the agreement
Charter Reinsurance Co Ltd v Fagan [1997] AC 313, citrf
Codelfa Construction Pty Ltd v State Rail Authority of New
South Wales(1982) 149 CLR 337, applied
Concut Pty Ltd v Worrell (2000) 176 ALR 693
-- 1 of 15 --
2
Investors’ Compensation Scheme Ltd v West Bromwich
Building Society [1998] 1 WLR 896, cited
Décor Blinds Gold Coast Pty Ltd v Décor Blinds Australia
Pty Ltd [2004] QSC 55, applied
Investors’ Compensation Scheme Ltd v West Bromwich
Building Society[1998] 1 WLR 896, cited
Johnson v American Home Assurance Co (1998) 192 CLR
266, cited
McCann v Switzerland Insurance Ltd(2000) 203 CLR 579,
considered
Minchillo v Ford Motor Co of Australia Ltd [1995] 2 VR
594, cited
National Bank of Sharjah v Dellborg (unreported, Court of
Appeal (Civil Division), England and Wales, Saville, Thorpe
and Judge LLJ, No QBCMF 96/0431/B, 9 July 1997, cited
Royal Botanic Gardens and Domain Trust v South Sydney
Council (2002) 76 ALJR 436, cited
Toll (FGCR) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR
165, considered
Upper Hunter County District Council v Australian Chilling
and Freezing Co Ltd (1968) 118 CLR 429, citede
COUNSEL: D B Fraser QC, with P W Telford, for the applicant
R W Gotterson QC for the respondent
SOLICITORS: BCI Duells Lawyers for the applicant
Minter Ellison for the respondent
[1] MARTIN J: Callide Power Management Pty Ltd (“CPM”) operates the Callide
power plant situated near Biloela in Central Queensland. On 11 May 1998 CPM
entered into a contract (“the agreement”) with Callide Coalfields (Sales) Pty Ltd
(“CCS”) for CCS to supply and deliver to CPM commercial quantities of coal for
use in CPM’s generating plant.
Outline of operation of agreement
[2] There is a minimum and a maximum tonnage of coal to be bought and sold in a
calendar year. The minimum is 2.6 million tonnes and a maximum is 3 million
tonnes. See cl. 5.1(b).
[3] In any calendar year a further amount of additional tonnage (“additional tonnage”)
of up to 250,000 tonnes can be required by CPM (subject to a maximum of 600,000
tonnes over four years). Therefore, in any one year the maximum CPM can
purchase, subject to the four year limit, is 3.25 million tonnes. See cl. 5.1A.
[4] CPM must give notice to CCS of its estimated requirements for the quantity of coal
and the potential quantity of additional tonnage not less than five months prior to
the commencement of the calendar year. That notice is not binding on CPM. See cl.
5.3.
[5] CCS must deliver the coal at a monthly rate notified by CPM in a range of not less
than 216,667 tonnes a month to not more than 300,000 tonnes a month. See cl. 5.4.
-- 2 of 15 --
3
[6] CPM can change the monthly rate by giving three months notice of the change
which in any event shall be within the range referred to above. See cl. 5.5.
[7] The obligations under the agreement of a party affected by an event of force
majeure are suspended for the period of the event. See cl. 14.3.
[8] If CCS is prevented by an event of force majeure from producing coal then, when
the event ceases, CCS is not required to supply the quantity of coal it was unable to
supply during that period. See cl. 14.6(a).
Background
[9] The agreement required that the parties provide certain notices to each other with
respect to the amount of coal required and the amount delivered. Pursuant to those
requirements, in July 2006, CPM provided CCS with the annual nominations for the
delivery of coal for the 2007 calendar year. In September 2006 CPM provided CCS
with an amended nomination for the months of January, February and March 2007.
In March 2007 CPM provided CCS with an amended nomination which called for
an increased supply for the months of June, July and August 2007. In June 2007
CPM provided CCS with an amended nomination which called for an increased
supply for the months of September, October and November 2007.
[10] During the months of January and February 2007 CCS notified CPM on four
separate occasions of events which CCS alleged fell within the definition of force
majeure in the agreement. The events in January and February 2007 resulted in CCS
delivering to CPM less than the amount which had been nominated by CPM for that
period. CCS disputes the validity of the notice given by CPM in June 2007. CCS
said that, as the force majeure clause had relieved it of its obligation to deliver the
“shortfall” caused by the force majeure events, it could not be required to deliver
that amount in later months of that year through the mechanism of an increased
nomination.
[11] A table showing the nominations, as made, and the coal delivered is set out below:
Column 1 Column 2 Column 3 Column 4 Column 5
Month
(2007)
Nominations
as at
24/07/06
Nominations
as at
22/09/06
Nominations
as at
09/03/07
Nominations
as at
09/06/07
Coal
Actually
Delivered
Period
of
Alleged
Force
Majeure
January 270,000 300,000 300,000 300,000 296,299
February 250,000 300,000 300,000 300,000 192,499
March 270,000 300,000 300,000 300,000 255,229
April 260,000 260,000 260,000 260,000 261,069
May 270,000 270,000 270,000 270,000 270,515
June 260,000 260,000 291,000 291,000 287,801
July 270,000 270,000 300,000 300,000 299,656
August 270,000 270,000 300,000 300,000 300,000
(nom)
September 270,000 270,000 270,000 291,000 290,000
October 280,000 280,000 280,000 300,000 300,000
(nom)
November 216,667 216,667 216,667 270,000 270,000
-- 3 of 15 --
4
(nom)
December 263,333 263,333 263,333 216,667 216,667
(nom)
Total 3,150,000 3,260,000 3,351,000 3,398,667 3,239,735
The amount in Column 5 assumes delivery in accordance with the nomination for
October-December. The amount of “undelivered” coal during the force majeure
period was approximately 156,000 tonnes.
The issue
[12] CCS asserts that the agreement (particularly cl. 14.6) provides that CPM is limited
in the amount of coal it can receive by: the original nomination, the effect of the
force majeure event, and the monthly limits. In the circumstances, CCS says, CPM
cannot subsequently amend its nominations for later periods in the same calendar
year in a manner which would otherwise comply with the agreement.
[13] CPM argues that for the purposes of calculating its total coal requirements for any
calendar year, it is the volume of coal actually delivered which is important and not
the amounts which it may previously have nominated.
[14] The key to understanding why the parties are contesting this point is the cost of the
coal. If CCS is right in its construction of the agreement then the “extra” coal sought
by CPM can be charged at market rates rather than the lower rate set under the
agreement. Conversely, if CPM is correct then it need only pay the lower rate.
[15] CPM seeks to have the question resolved by its application for a declaration (as
amended during the hearing) that:
“… upon the true construction of the … agreement and in the events
which have occurred [CPM] was entitled to, and has, on 9 June 2007,
validly notified [CCS] as to the ‘Monthly Rate’ at which coal is
required to be delivered to [CCS] pursuant to cl. 5.4 of the …
agreement during September, October, November and December
2007.”
Relevant clauses
[16] The Callide Power Project Coal Supply Agreement is a complex document but for
the purposes of this application the relevant clauses are:
“4, SALE AND PURCHASE
The Seller must sell and deliver to the Buyer and the Buyer must
purchase and take delivery from the Seller the Coal at the rate
determined in accordance with this Agreement for the Contract Price
and on the terms and conditions of this Agreement.
5.1 Minimum and Maximum Tonnage Delivery
The Seller must deliver and the Buyer must accept delivery of not
less than the Minimum Tonnage and not more than the Maximum
Tonnage in any Calendar Year as follows:
(a) from the Effective Date to the Commercial Load Date of Unit
2:
(i) a Minimum Tonnage of l. 3 million Tonnes
Equivalent of Coal; and
-- 4 of 15 --
5
(ii) a Maximum Tonnage of l.5 million Tonnes
Equivalent of Coal,
per annum (and proportionally for any part of a Calendar
Year), and
(b) from the Commercial Load Date of Unit 2:
(i) a Minimum Tonnage of 2.6 million Tonnes
Equivalent of Coal and
(ii) a Maximum Tonnage of 3 million Tonnes Equivalent
of Coal per annum (and proportionally for any part of
a Calendar Year).
5.1A Additional Coal
(a) In any Calendar Year the Buyer may, by giving the Seller
not less than three months' notice, nominate an amount of
Coat of up to and including 250, 000 Tonnes Equivalent
(‘Additional Tonnage’') (provided that the amount of
Additional Tonnage does not exceed 600, 000 Tonnes
Equivalent in any period of four Calendar Years) to be sold
and delivered by the Seller to the Buyer and to be purchased
and taken delivery of by the Buyer from the Seller in
accordance with this Agreement together with the Buyer's
nomination of
(i) a period for the delivery of the Additional Tonnage;
and
(ii) any change in the Monthly Rate in accordance with
Clause 5. 5.
(b) The price of the Additional Tonnage must be the Contract
Price determined, at the time of the commencement of
delivery of the Additional Tonnage, in accordance with
Clause 10.1 and adjusted for variations in as received
quality in accordance with Clause 10.3. The price for the
Additional Tonnage must be adjusted not less than one
month prior to the commencement of delivery of the
Additional Tonnage if:
(i) the Seller can reasonably demonstrate to the
Buyer's satisfaction that the Seller will incur
additional costs in delivering the Additional
Tonnage to the Buyer which will not be recovered
by payment by the Buyer to the Seller of the
Contract Price; or
(ii) the Buyer can reasonably demonstrate that the
Seller will be able to take advantage of economies
of scale of the incremental production represented
by the Additional Tonnage.
(c) For the purposes of calculating the payment of the Contract
Price due by the Buyer to the Seller for the Additional
Tonnage, delivery of the Additional Tonnage in any
Calendar Year is deemed not to commence until delivery of
the Maximum Tonnage in any Calendar Year has been
completed.
-- 5 of 15 --
6
5.2 Commissioning Coal
Despite Clause 5.1, during the period commencing 6 months prior to
(a) the Effective Date; and
(b) the Commercial Load Date of Unit 2,
and, upon the Buyer giving three months notice of its requirements,
the Seller must sell and deliver, in addition to the quantities of Coal set
out in Clause 5.1, a sufficient quantity of Coal for the purposes of
commissioning and testing Unit 1 and Unit 2, ('Commissioning
Coal') as follows:
(c) the price of the Commissioning Coal will be the Contract
Price determined, at the commencement of delivery of' the
Commissioning Coal, in accordance with Clause 10.1 and
adjusted for variations in as received quality in accordance
with Clause 10. 3;
(d) the rate of delivery of Commissioning Coal must be agreed
between the Parties six months prior to the Effective Date or
the Commercial Load Date of Unit 2, as the case may be.
Any variations to that rate of delivery must be agreed by the
Parties by mutual cooperation during the period of delivery
of Commissioning Coal and if the Parties fail to so agree,
then Clauses 5.4 to 5.9 inclusive will apply to the delivery of
Commissioning Coal; and
(e) except as provided in this Clause 5.2, all provisions in this
Agreement will apply to the supply and purchase of
Commissioning Coal.
5.3 Buyer's Notice
The Buyer must give notice (which is not binding on the Buyer) to
the Seller of its estimated requirements for:
(a) the quantity of Coal and the potential quantity of Additional
Tonnage and, where necessary, of the Commissioning Coal;
and
(b) the rate of delivery of Coal (the monthly components of
which are referred to as the 'Monthly Rate '),
as follows:
(c) not less than five months prior to the Effective Date for its
estimated requirements from the Effective Date until the end
of the Calendar Year in which the Effective Date falls; and
(d) not less than five months prior to the commencement of
every Calendar Year after the Calendar Year in which the
Effective Date falls.
5.4 Monthly Rate
The Coal must be delivered by the Seller at a Monthly Rate notified by
the Buyer in the range of not less than that amount of Coal calculated
in accordance with the following formula:
Minimum Tonnage
12
-- 6 of 15 --
7
and not more than that amount of Coal calculated in accordance with
the following formula:
Minimum Tonnage x 1.2
12
unless otherwise provided for in this Agreement or agreed between
the Parties.
5.5 Changes in Monthly Rate
The Buyer must give three months' notice (such notice not to be
issued at intervals of less than three months) of any change in the
Monthly Rate which will in any event be within the range specified in
Clause 5. 4.
5.6 Weekly Rates
Unless otherwise agreed, deliveries of Coal to the Buyer must in any
month as far as is reasonably practicable be at substantially equal
weekly rates.
5.7 Maximum Rate
Deliveries of Coal from the Seller must not exceed the rated capacity
of the Callide B Coal Conveyor System as notified by the Buyer to
the Seller from time to time. The Buyer must ensure that the capacity
of the Callide B Coal Conveyor System is sufficient to allow the
Seller to deliver Coal at the greater of the Monthly Rates referred to
in Clause 5. 4 within the delivery hours set out in Schedule 6.
5. 8 Loadout Bin Availability
The Seller must ensure that the Loadout Bin is available to load out
generally on the days and during such hours in those days as are
mutually agreed between the Seller and the Buyer, but not for a
lesser period than the delivery hours set out in Schedule 6.
5. 9 Maintenance Period Deliveries
The Parties must act so as to eliminate excessive or needless
stockpiling of Coal not required by the Buyer during major
maintenance periods at the Power Station.
14. FORCE MAJEURE
14.1 Definition
'Event of Force Majeure' means an event that:
(a) is beyond the control of either the Coal Mine Owners or the
Station Owners;
(b) causes or results in preventing or delaying the Seller or a
Station Owner from performing any of its obligations
under this Agreement," and
(c) could not or the effects of that event could not have been
prevented, overcome or remedied by the exercise by the
Coal Mine Owners or Station owner prevented or delayed of
a standard (which standard includes (but is not limited to)
the expenditure of reasonable sums of money and the
-- 7 of 15 --
8
application of technology known to reasonable persons) of
care and diligence consistent with that of a reasonable
person under the circumstances,
and includes (but is not limited to):
(d) fire, lightning, explosion, flood earthquake, storm, cyclone,
action of the elements, act of God, natural disaster,
radioactive contamination, toxic or dangerous chemical
contamination or force of nature;
(e) riots, civil commotion, malicious damage, sabotage, act of a
public enemy, war or undeclared) or revolution;
(f) action or inaction by a court, government or authority
(including denial, refusal or failure to grant any permit,
authorisation, licence, approval or despite timely best
endeavours to obtain the grant);
(g) strikes, lockouts, industrial or labour disputes or difficulties,
work bans, blockages or picketing (unless arising from any
act or omission on the part of party claiming an Event of
Force Majeure) ('Industrial Action') including, without
limitation, any Industrial Action affecting directly or
indirectly the Operator,"
(h) any of
(i) breakdown or failure of any facilities, machinery or
equipment;
(ii) unavailability of essential equipment, goods, supplies
or services; or
(iii) mine collapses caused by any one or more of the
events set out in subparagraphs (d) to (g).
(i) abnormal breakdown of facilities, machinery or equipment
which occurs despite the application of Good Operating
Practice towards those facilities, machinery and equipment.
14.2 Notice of Force Majeure Event
If either Party is affected by an Event of Force Majeure, then within
two Business Days after the occurrence of the event it must give
notice to the other of the Event of Force Majeure and provide details
of:
(a) the obligations affected;
(b) the action that the affected Party has taken and proposes to
take to remedy the situation;
(c) the affected Party's estimate of the time during which it will
be unable to carry out the affected obligations due to the
Event of Force Majeure;
(d) the affected Party's estimate of the costs it will incur to
remedy the situation; and
(e) all insurance policies upon which the affected Party will be able
to rely in making good damage caused by the Event of Force
Majeure.
14.3 Suspension of Obligations
-- 8 of 15 --
9
Following an Event of Force Majeure, the affected Party's
obligations (including any obligation to pay money) under this
Agreement will be suspended but:
(a) only to the extent and for so long as the period that such
obligations are genuinely affected by the Event of Force
Majeure;
(b) if the period of suspension continues without interruption
for more than 180 days, the Party not affected by the Event
of Force Majeure may by notice terminate that part of this
Agreement that is affected by the Event of Force Majeure;
and
(c) if the period of suspension continues without interruption
for more than 365 days, either Party may by notice terminate
that part of this Agreement that is affected by the Event of
Force Majeure.
14.4 Affected Party's Obligations
Despite Clause 14. 3, the Party affected by the Event of Force
Majeure will:
(a) use reasonable efforts (including the expenditure of
reasonable sums of money) to mitigate the effect upon its
performance of this Agreement and to fulfil its obligations
under this Agreement (but without prejudice to either
Parties' right to terminate this Agreement) but nothing in this
Clause 14.4 obliges a Party to settle a strike, lockout,
boycott or other industrial dispute;
(b) keep the other Parties informed (not less than fortnightly) of
the steps being taken to mitigate the effect upon their
performance of this Agreement, and an estimate of the
continued duration of the delay,"
(c) when the period for which its obligations are affected by an
Event of Force Majeure ceases, recommence performance of
all its affected obligations under this Agreement the subject
of its original notice under this Clause; and
(d) upon the recommencement of the performance of the
affected obligations, not again invoke the provisions of this
Clause in regard to the same Event of Force Majeure unless
the further effect of that Event of Force Majeure could not
reasonably have been foreseen.
14.5 No Default
Where it has validly issued a notice under Clause 14.2 a Party will
not be deemed to be in default of its obligations under this
Agreement to the extent that a failure or delay in the observance or
performance of those obligations by that Party is caused by the
relevant Event of Force Majeure specified in such a notice.
14.5 No Obligation to Perform
(a) If an Event of Force Majeure causes or results in the Callide
Coalfields losing production or being prevented from
producing, then, when the period for which a Seller's
-- 9 of 15 --
10
obligations are affected by the Event of Force Majeure
ceases, the Seller will not be required to supply the quantity
of coal the Seller was unable to supply during that period
and any reduction or deferment of supply of Coal caused by
or resulting from the Event of Force Majeure may be made
by the Seller on the basis of a pro rata adjustment between
the delivery requirements of the Buyer and the delivery
requirements of any other of the Seller's or Coal Mine
Owners' customers;
(b) If an Event of Force Majeure causes or results in the Power
Station losing production or being prevented from producing
then, when the period for which a Buyer's obligations are
affected by the Event of Force Majeure ceases, the Buyer
will not be required to take delivery of the quantity of coal
the Buyer was unable to take delivery of during that period.
SCHEDULE 1
DEFINITIONS
‘Coal’ means coal supplied by the Seller prepared and processed to
meet the quality requirements contained in Clause 8
‘Monthly Rate’ is the rate of delivery of Coal in each month
determined under Clause 5.”
The June 2007 notice from CPM
[17] In June 2007 CPM provided CCS with two notices. The first was under cl. 5.5. It
provided:
“Callide Power Management Pty Limited (“CPM”) provides Callide
Coalfields (Sales) Pty Ltd (“CCS”) with notice under clause 5.5 of
the Callide Power Project Coal Supply Agreement dated 11 May
1998 (“Agreement) of a change in monthly rate for the months of 10
September 2007 to 9 December 2007, which is more than three
months from the issue of this notice. The delivery rate for these
months is:
1. For 10 September 2007 to 30 September 2007: 300,000 tonnes
per month pro rata.
2. For October 2007: 300,000 tonnes
3. For November 2007: 270,000 tonnes (inclusive of 33,333 tonnes
of additional coal under a 5.1A notice).
Our position refuting the force majeure notice as issued: by Anglo
earlier in 2007 remains. All our rights are reserved with regard to
those notices, including any harm suffered resultant from those
notices.
This issue is issued consistent, and in conjunction with a clause 5.1A
notice.”
[18] The cl. 5.1A notice referred to in the notice set out above was, so far as is relevant,
as follows:
-- 10 of 15 --
11
“CPM notifies CCS that:
1. CPM nominates an amount of additional tonnage in the sum
of the 250,000 tonnes equivalent to be available for sale and
delivery;
2. CPM nominates as the period for delivery of the additional
tonnage to be the period commencing in November 2007
and ending in December 2007 following the delivery of the
maximum tonnage for the 2007 calendar year, and being a
period which commences more than three months after the
date of delivery of this notice to you; and
3. The monthly rate of delivery will be:
. 270,000 in the month of November 2007 in total in
accordance with the applicable clause 5.5 notice
(which is inclusive of 33,333 tonnes of additional
tonnage, and
. 216,667 in the month of December 2007, being the
balance of the additional tonnage.”
Principles relating to the construction of commercial contracts.
[19] Modern authority on the appropriate tests to be applied when considering the
meaning of a commercial document commences with the decision of the High Court
of Australia in Codelfa Construction Pty Ltd v State Rail Authority of New South
Wales1. Since then, there has been further consideration given, both in Australia and
elsewhere, to the extent to which ambiguities in agreements may be resolved by
reference to the “background” of the relevant document. In particular, there has
been much discussion of the 5 point scheme for contractual interpretation advanced
by Lord Hoffman in Investors’ Compensation Scheme Ltd v West Bromwich
Building Society.2 Whatever the merits of the distinctions drawn between the rules
set out in Codelfa and those referred to in the Investors’ Compensation Scheme
case, courts in Australia are to follow the principles in Codelfa.3
[20] In this case perhaps the most useful principles to bear in mind are that the
construction of commercial arrangements is to be based upon the presumption that
parties do not intend their contracts to achieve unreasonable results, and the idea
that a commonsense approach is to be taken to commercial contracts. For example,
as Gleeson CJ said in McCann v Switzerland Insurance Ltd:
“A policy of insurance, even one required by statute, is a commercial
contract and should be given a businesslike interpretation.
Interpreting a commercial document requires attention to the
language used by the parties, the commercial circumstances which
the document addresses, and the objects which it is intended to
secure.”4
[21] Of similar import were the words of the High Court in Toll (FGCR) Pty Ltd v
Alphapharm Pty Ltd where the Court said:
“…The meaning of the terms of a contractual document is to be
determined by what a reasonable person would have understood
1 (1982) 149 CLR 337
2 [1998] 1 WLR 896 at 912-913
3 See Royal Botanic Gardens and Domain Trust v South Sydney Council (2002) 76 ALJR 436 at [39].
4 (2000) 203 CLR 579 at [22]
-- 11 of 15 --
12
them to mean. That, normally, requires consideration not only of the
text, but also of the surrounding circumstances known to the parties,
and the purpose and object of the transaction.”5
[22] The need to arrive at an interpretation which is both practical and commercially
sensible has been frequently emphasised by the courts.6
[23] There is not, of course, any general power to reach a conclusion which is thought to
be reasonable by the court if the words in question are clear and can only have one
meaning. In those cases the court must give effect to that interpretation.7
[24] A convenient collection of the applicable principles appears in Décor Blinds Gold
Coast Pty Ltd v Décor Blinds Australia Pty Ltd:8
“The following principles apply to the construction of a contract in a
commercial context:
(1) the court’s primary task is to construe the words used by the
parties in the contract;9
(2) the common intention of the parties is to be found in the
words used in the contract;10
(3) the court will give effect to the plain meaning of words
which are unambiguous no matter how capricious,
unreasonable, inconvenient or unjust the result; 11
(4) the more unreasonable the result, the more unlikely that the
construction which gives rise to that result is correct unless
an intention to achieve that result is abundantly clear;12
(5) few words have a plain meaning and are unambiguous or not
susceptible of more than one meaning. Until a word, phrase
or sentence is understood in the light of the surrounding
circumstances, it is rarely possible to know what it means;13
(6) if the words have more than one possible meaning, then the
construction will be preferred which is not capricious,
unreasonable, inconvenient or unjust;14
(7) the contract should be looked at as a whole to elucidate the
meaning of each clause: the contract must, if possible, be
5 (2004) 219 CLR 165 at [40]
6 See, for example, Concut Pty Ltd v Worrell (2000) 176 ALR 693 at 708-9, Upper Hunter County
District Council v Australian Chilling and Freezing Co Ltd (1968) 118 CLR 429 at 437, Minchillo v
Ford Motor Co of Australia Ltd [1995] 2 VR 594 at 609.
7 See Johnson v American Home Assurance Co (1998) 192 CLR 266 at 272, Charter Reinsurance Co
Ltd v Fagan [1997] AC 313 at 388.
8 [2004] QSC 55 (24 March 2004) at [26].
9 Australian Broadcasting Commission v Australasian Performing Right Association Ltd (supra) at
109.
10 Australian Broadcasting Commission v Australasian Performing Right Association Ltd (supra);
Taylor v Johnson (1983) 151 CLR 422 at 428-430.
11 Australian Broadcasting Commission v Australasian Performing Right Association Ltd (supra);
Bacchus Marsh Concentrated Milk Co Ltd (In Liquidation) v Joseph Nathan & Co Ltd (supra) at
444.
12 L Schuler AG v Wickman Machine Tool Sales Ltd [1974] AC 235 at 251.
13 Manufacturers Mutual Insurance Ltd v Withers (1988) 5 ANZ Ins Cases 60-853 at 75,343.
14 Australian Broadcasting Commission v Australasian Performing Right Association Ltd (supra) at
109.
-- 12 of 15 --
13
construed so that each clause is consistent in meaning with
the whole of the contract;15
(8) commercial contracts should be construed so as to make
commercial sense of them – a conclusion that reflects
business common sense is to be preferred to one that flouts
it;16
(9) it is necessary to construe a document against the
background in which it was made to determine what the
words in the document mean – the meaning of words cannot
be divorced from their context;17
(10) the meaning given may not necessarily be the most obvious
or grammatically correct;18
(11) the purpose of a provision is part of the context in which the
meaning of words is to be ascertained. A construction is
preferred which gives effect to the commercial purpose of
the contract;19
(12) a commercial contract should be construed fairly and
broadly whether or not the contract was drawn with
assistance of lawyers.20”
Construction of the agreement
[25] Mr Gotterson QC, for CCS, argued that CPM, having nominated figures for a period
which was later affected by a force majeure event, cannot thereafter adjust monthly
rates in a way which would have the effect of forcing CCS to “deliver coal which
under clause 14.6 … it doesn’t have to make up at the end of the force majeure
period.”
[26] In a clarification of the submissions made at the hearing on 4 October, Mr Gotterson
QC later submitted the following: CPM may increase the monthly rates for months
subsequent to a force majeure event (capped at the maximum monthly rate of
300,000 tonnes), but subject to the following limitation (“the limitation”). The
limitation is that CPM may not increase monthly rates so as to require delivery of
coal which it could not deliver as a consequence of force majeure. The limitation
comes about as a result of the effect of cl. 14.6(a). If CPM originally nominated the
minimum tonnage of 2.6 million tonnes, yet in the first three months CCS could not
deliver 300,000 tonnes by reason of an event of force majeure (that is 100,000
tonnes per month), CPM could increase its nominations by 400,000 tonnes because
15 ibid.
16 Geroff & Ors v CAPD Enterprises Pty Ltd & Ors (supra) at [36]; Antaios Compania Naviera SA v
Salen Rederierna AB [1985] AC 191 at 201; Groves v BMW Finance Ltd [2001] QCA 16 at [19],
[54].
17 Arbuthnott v Fagan (unreported) 30 July 1993 Court of Appeal as quoted in Charter Reinsurance Co
Ltd v Fagan [1997] AC 313 at 326; Investors Compensation Scheme Ltd v West Bromwich Building
Society [1998] 1 All ER 98 at 114-115; Royal Botanic Gardens and Domain Trust v South Sydney
City Council (supra) at [10].
18 Australian Broadcasting Commission v Australasian Performing Right Association Ltd (supra) at
109.
19 Arbuthnott v Fagan (supra); Royal Botanic Gardens and Domain Trust v South Sydney City Council
(supra) at [10].
20 Australian Broadcasting Commission v Australasian Performing Right Association Ltd (supra) at
109-110.
-- 13 of 15 --
14
it had that tonnage “to play with” under the original nomination, up to the maximum
tonnage.
[27] Further examples of that nature were considered in Mr Gotterson QC’s submissions
and the basis of his argument returned always to the effect of the “original
nomination” made by CPM.
[28] The problem which I see with the argument advanced for CCS is twofold. First, the
clear practical intention of the agreement is to place an upper and lower limit on the
amount of coal actually delivered by CCS to CPM. There is, as I have noted above,
the possibility of increasing the tonnage in one year by up to 250,000 tonnes but that
increase is, according to CCS, still to be factored in according to the requirements
(as they see them) of cl. 14.6(a). The second point is that the basis of CCS’s
arguments is that the nomination made by CPM in the year preceding the year under
consideration is, in some way, a controlling nomination.
[29] The agreement makes it clear that a nomination may be amended and no complaint
was made when the nominations were amended by CPM on 9 March 2007. CCS
argued that it was only when the June amendment was made that it became obvious
(to it) that cl. 14.6(a) would be offended.
[30] Clause 5.3 of the agreement requires CPM to give notice to CCS of its estimated
requirements not less than five months prior to the commencement of the calendar
year for which the coal is required. It is specifically provided that such notice is not
binding on CPM. It could not be, as cl. 5.5 allows CPM to change the monthly rate
upon the giving of three months notice.
[31] CCS points to cl. 14.6(a) as having the effect that it cannot be required to supply the
coal which was not able to be delivered during a force majeure event if to do so
would take it above the nomination made by CPM in the preceding year. I do not
accept that. Although Mr Gotterson QC abandoned the notion of deeming which
had been advanced by his client in earlier correspondence the thrust of CCS’s case
is either that CPM is bound by a nomination which the agreement specifically
provides does not bind it or CPM is deemed to have received coal which it did not,
in fact, receive.
[32] The effect of cl. 14.6(a) does not deny to CPM the ability granted to it elsewhere in
the agreement to change its nominations so that it can receive coal up to the
maximum amount allowed under the contract per month subject, of course, to the
maximum allowed per year.
[33] Clause 14.6(a) works to protect CCS from the situation which arises when a force
majeure event ceases. Clause 14.3(c) provides that:
“the Party affected by the Event of Force Majeure will:
…
(c) when the period for which its obligations are affected by an
Event of Force Majeure ceases, recommence performance of all its
affected obligations under this Agreement the subject of its original
notice under this Clause.”
[34] Without cl. 14.6(a) it would be open to argument that CPM could use cl. 14.3(c) to
require CCS to perform its affected obligations, that is, to deliver the shortfall in
coal. The damage that that could cause to a producer like CCS is obvious. CCS is
-- 14 of 15 --
15
only required to provide a maximum of 300,000 tonnes a month to CPM. If it is
assumed that, due to a natural disaster of some kind, CCS could not deliver any coal
in a six month period then, without cl. 14.6(a) CPM could demand that CCS “catch
up” by doubling its production in the balance of the calendar year. It could be
argued by CPM that the force majeure provisions which require CCS to
“recommence performance of its affected obligations” meant that the monthly limit
did not apply. A requirement to double production or even to increase it
substantially would be inconsistent with the agreement’s regime of a stream of
production between minimum and maximum levels.
[35] Similarly, cl. 14.6(b) protects CPM from the provisions of cl. 14.3(c) in that CPM is
not required to pay for coal which it could not use during a force majeure event. In
other words, although CPM may have nominated a particular amount for a month it
is not bound to take all or part of it if force majeure events dictate a different
outcome.
[36] The amended nomination of June 2007 was consistent with the terms of the
agreement – it did not seek delivery of coal in excess of 300,000 tonnes a month
and it did not result in delivery of coal for the entire year in excess of 3,250,000
tonnes.
[37] I make the following declaration:
Upon the true construction of the agreement of 11 May 1998, and in the events that
have occurred, the notifications given by the applicant to the respondent dated 9
June 2007 were valid notifications under the agreement and which bound the
respondent to comply with their terms.
[38] The respondent is to pay the applicant’s costs of and incidental to the application.
-- 15 of 15 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2007/395