Cook’s Constructions P/L v Stork Food Systems Aust P/L [2007] QSC 381
SUPREME COURT OF QUEENSLAND
CITATION: Cook’s Constructions P/L v Stork Food Systems Aust P/L
[2007] QSC 381
PARTIES: COOK’S CONSTRUCTIONS PTY LTD
ACN 004 782 558
(plaintiff/applicant)
v
STORK FOOD SYSTEMS AUSTRALIA PTY LTD
ACN 004 448 042
(defendant/respondent)
FILE NO/S: BS 10993 of 2001
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: Orders delivered ex tempore on 7 December 2007
Reasons delivered on 14 December 2007
DELIVERED AT: Brisbane
HEARING DATE: 7 December 2007
JUDGE: Martin J
CATCHWORDS: PROCEDURE – SUPREME COURT PROCEDURE –
QUEENSLAND – PRACTICE UNDER RULES OF COURT
– OTHER MATTER – where plaintiff made application to
adjourn trial date – where parties had made a request for trial
date – where matter set down for four week trial to
commence in under two months – where plaintiff had notice
of defendant’s counterclaim and had sufficient time to seek to
obtain its own expert opinion with respect to the matters
raised – whether adjournment should be granted
Queensland Building Services Authority Act 1991 (Qld), s 42
Di Carlo v Dubois & Ors [2007] QCA 316, cited
State of Queensland v J L Holdings Pty Limited (1997) 189
CLR 146, considered
United Motors Retail Limited v Australian Guarantee
Corporation Limited (1991) 58 SASR 156, cited
COUNSEL: D J Digby QC, with S R Grahame, for the plaintiff/applicant
K E Downes, with S B Hooper, for the defendant/respondent
SOLICITORS: Clarke & Kann, as town agents for McPherson & Kelley, for
the plaintiff/applicant
-- 1 of 6 --
2
McCullough Robertson for the defendant/respondent
[1] MARTIN J: On 7 December I dismissed the plaintiff’s application to adjourn the
commencement of the trial in this matter to a date to be fixed. What follows are my
reasons for dismissal.
[2] The events with which this action is concerned occurred in 1998 when the
defendant contracted with Queensland Nitrates Pty Ltd to construct a plant to
produce ammonium nitrate at Moura in Central Queensland. The defendant
subcontracted aspects of the works to the plaintiff. The plaintiff alleges that it has
been underpaid by the defendant and claims a sum of approximately $1.4 million.
The defendant says that it has overpaid the plaintiff and on that basis, and on the
basis of a failure by the plaintiff to comply with the Queensland Building Services
Authority Act 1991, counterclaims for damages in the sum of approximately
$10 million.
[3] The plaintiff commenced proceedings in the Supreme Court of Victoria in 2001.
Those proceedings were transferred to Queensland in September of that year.
[4] The Statement of Claim in this matter has a sorry history. There have been nine
separate versions of it – not all of which have been filed. The current version was
filed on 5 July 2007. There have been a number of applications to the Court for
summary judgment and for other interlocutory relief.
[5] In December 2004 the defendant delivered the preliminary report of the expert
which it had retained for the trial – a Mr Gordon Leck. The final report from that
expert was delivered to the plaintiff on 22 August this year. The essence of the
report is unchanged and the criticism it makes of the plaintiff’s formulation of its
claim is, likewise, unchanged.
[6] In 2002 the defendant amended its pleadings to include a claim that the plaintiff, in
doing the work for which it made its allegations of underpayment, carried out
building work in contravention of s 42 of the Queensland Building Services
Authority Act 1991 (Qld). If that is correct, then the plaintiff is entitled to recover
compensation for work done but, in effect, no profit on the work done.
[7] On 31 August this year a review of this matter was conducted before Daubney J at
which both parties informed his Honour that the matter was ready for trial. On 15
October 2007 the plaintiff’s solicitors signed the request for trial date. On 20
November 2007, pursuant to a consent order dated 28 September 2007, the parties’
experts (and a representative of each party) met to identify the matters on which the
experts agreed and disagreed, and to attempt to resolve any differences.
[8] In support of its application the plaintiff filed a number of affidavits. The major
affidavit was that of Mr Robert Downing, the solicitor who has the conduct of the
matter on behalf of the plaintiff. He said:
“8. It was not until the meeting of experts that the Defendant’s
position and case on certain important issues, and the view of
its expert Mr Gordon Lecke [sic] as espoused in his Expert
Report of 22 August 2007 became clear to the Plaintiff and its
experts.”
-- 2 of 6 --
3
[9] Mr Downing then goes on to say that it will be necessary for the plaintiff to engage
another expert to respond to certain allegations and that the consequence of that is
that the plaintiff will not be ready for trial on the appointed date and will need an
adjournment of at least four months.
[10] The plaintiff also, through Mr Downing, says that, with respect to the Queensland
Building Services Authority Act point:
“At the time of signing the Certificate of Readiness for Trial, only
some 7 days after the Defendant provided its Further and Better
Particulars, the Plaintiff and its solicitors believed that the Plaintiff
would be able to assess its entitlement under subsection 42(4)
internally. However I am instructed by Jon Trende and believe that,
in fact, because of the accounting system employed by the Plaintiff at
the time of the relevant Subcontract it will need to engage an
independent forensic accountant to undertake the calculation
necessary to defend the Defendant’s Counterclaim …”.
[11] Notwithstanding that the plaintiff has known of the defendant’s allegations with
respect to the Queensland Building Services Authority Act for five years and has
been aware of Mr Leck’s expert opinion for nearly three years, it comes before the
Court seeking an adjournment of the trial set down to commence on 29 January
2008.
[12] The plaintiff’s expert, Mr Robinson, signed a joint report with Mr Leck on
4 December 2007 – only three days before the hearing of this application. The very
short joint report exposes considerable problems for the plaintiff in proving its case.
The joint report records the following:
“Mr Trende [the plaintiff’s Chief Executive Officer] advised the
meeting that – ‘Whether you get an expert report I think will be
entirely determined by what position we end up with at the end of the
three days.’ In the absence of an expert’s report by Mr Robinson, the
meeting proceeded on the basis that that Mr Robinson would be
providing expert evidence with respect to the measurement of
quantities only for some of the plaintiff’s claims (predominantly civil
works) with respect to which he had provided the quantities to the
plaintiff. There was no advice given by Mr Trende as to how expert
evidence on rates of measurement of quantities not dealt with by Mr
Robinson would be addressed by the plaintiff.”
[13] An examination of the principles to be applied on an application such as this must
commence with the decision of the High Court in State of Queensland v J L
Holdings Pty Limited (1997) 189 CLR 146. That concerned a long running
commercial dispute relating to a lease to develop certain land. It was estimated that
the trial would take some four months. There had been a number of interlocutory
hearings and the defence had been amended several times. The defendant applied
again to amend its defence but the judge refused leave to add a defence which,
though arguable, was likely to result in the vacation of the date which had been
fixed for the trial some six months ahead.
[14] In the joint reasons of Dawson, Gaudron and McHugh JJ, their Honours, at 152-
154, in referring to the decision under appeal said:
-- 3 of 6 --
4
“The applicants applied to the Full Court of the Federal Court for
leave to appeal against the refusal of the primary judge to grant the
application for leave to amend. By a majority (Whitlam and
Sundberg JJ, Carr J dissenting) the Full Court granted leave but
dismissed the appeal. In granting leave to appeal, the majority
conceded the potential injustice involved in denying the respondent
the opportunity to ventilate the issue which the proposed amendment
was intended to raise. Their Honours referred to the well-known
passage in the judgment of Bowen LJ in Cropper v Smith … where
his Lordship said:
‘Now, I think it is a well established principle that the object
of Courts is to decide the rights of the parties, and not to
punish them for mistakes they make in the conduct of their
cases by deciding otherwise than in accordance with their
rights. Speaking for myself, and in conformity with what I
have heard laid down by the other division of the Court of
Appeal and by myself as a member of it, I know of no kind
of error or mistake which, if not fraudulent or intended to
overreach, the Court ought not to correct, if it can be done
without injustice to the other party. Courts do not exist for
the sake of discipline, but for the sake of deciding matters in
controversy, and I do not regard such amendment as a
matter of favour or of grace.’
The majority also referred to the decision of this Court in Clough and
Rogers v Frog … where applications for leave to amend the
defences in two actions by adding a new defence had been refused.
The actions had been commenced more than five years previously
and the applications were made two days before the actions were
listed for hearing. The Court in allowing the appeals before it
adopted the words above of Bowen LJ in Cropper v Smith … and
said:
‘As the defence, if established, would be a complete answer
in either action, the amendments sought should have been
allowed unless it appeared that injustice would thereby have
been occasioned to the respondent, there being nothing to
suggest fraud or improper concealment of the defence on the
part of the appellants. With the exception of the suggestion
of prejudice arising in respect of the loss of the possible
claim against the nominal defendant, the matters relied upon
by the respondent in opposition to the amendment sought go
at the most to delay and irregularity only, matters which are
relevant to costs but do not constitute injustice to the
respondent in the sense in which that expression is used.’
The majority in the Full Court dismissed these remarks saying that
‘times have changed since 1884, and even since 1974’. They referred
to a passage from the judgment of Toohey and Gaudron JJ in Sali v
SPC Ltd … where their Honours said:
‘The contemporary approach to court administration has
introduced another element into the equation or, more
accurately, has put another consideration onto the scales….
The view that the conduct of litigation is not merely a matter
-- 4 of 6 --
5
for the parties but is also one for the court and the need to
avoid disruptions in the court’s lists with consequent
inconvenience to the court and prejudice to the interests of
other litigants waiting to be heard are pressing concerns to
which a court may have regard.’
The majority concluded:
‘Unless we are to mouth the repeated cautions about
discretionary judgments, case management, efficiency,
practice and procedure, and the advantages of the managing
judge, only to ignore them when it comes to the crunch, this
appeal must be dismissed.’
It may be said at once that in the passage which we have cited from
Sali v SPC Ltd Toohey and Gaudron JJ are not to be taken as
sanctioning any departure from the principles established in
Cropper v Smith and accepted in Clough and Rogers v Frog. Sali v
SPC Ltd was a case concerning the refusal of an adjournment in
relation to which the proper principles of case management may
have a particular relevance. However, nothing in that case suggests
that those principles might be employed, except perhaps in extreme
circumstances, to shut a party out from litigating an issue which is
fairly arguable. Case management is not an end in itself. It is an
important and useful aid for ensuring the prompt and efficient
disposal of litigation. But it ought always to be borne in mind, even
in changing times, that the ultimate aim of a court is the attainment
of justice and no principle of case management can be allowed to
supplant that aim.”
[15] In order to consider what the justice of the situation requires it is necessary to take
into account a number of factors in this case. I think that the matters of relevance
include:
(a) the knowledge, held by the plaintiff for many years, of the issues in
the case upon which it now seeks an adjournment;
(b) the agreement by the plaintiff that it was ready to proceed to trial.
(c) the fact that a trial of this length would, if adjourned, not be likely to
be heard until 2009;
(d) the length of time which has elapsed since the events upon which this
action is based. This supports a conclusion that further delay will
occasion detriment to the defendant (as well as the plaintiff). See, in
particular, Di Carlo v Dubois & Ors [2007] QCA 316 at [10];
(e) there has not been an adequate explanation for the indulgence now
sought from the Court. The material discloses that the very issue
(concerning expert evidence relating to calculation of the claim)
which the plaintiff now seeks time to investigate, has been raised by
the defendant on a number of occasions. In fact, the defendant
warned the plaintiff of this very problem some years ago;
(f) the absence of any affidavit by Mr Robinson. This is troubling. One
could be forgiven for thinking that his opinion as to the necessity for
further expert evidence and the extent of such evidence would be
valuable. In the circumstances, I think I am justified in drawing the
inference that his evidence could not assist the plaintiff on this
application;
-- 5 of 6 --
6
(g) the material relied upon to support the claim that the plaintiff could
not be ready for trial is hardly compelling. With respect to the
response to Mr Leck’s evidence, the affidavit of Mr Downing only
discloses that one person has been approached to provide assistance.
The area of expertise relied upon is not a narrow or confined area. It
is difficult to accept that there is no one in Queensland, or elsewhere
in Australia, who could provide the necessary assistance within the
time available. Similarly, the material with respect to the Queensland
Building Services Authority Act point provides no indication as to
why the plaintiff cannot, in the time available, do the work necessary
to meet the case.
[16] The issues I have listed above demonstrate that the plaintiff has, by its actions (or
lack of action) ignored the requirements of the Uniform Civil Procedure Rules 1999
(Qld) and the implied undertaking contained in those rules. The “attainment of
justice”, as referred to in J L Holdings does not require that, in situations such as
this, an adjournment will always be granted at the cost of the applicant. The remarks
of Bollen J in United Motors Retail Limited v Australian Guarantee Corporation
Limited (1991) 58 SASR 156 at 163 are apposite in this case:
“The days when a piece of litigation was treated rather as if it were
the property of the parties for them to move at the pace they chose
are well and truly past. The courts must strive to keep the lists
moving at a pace which will do all practicable to reduce delay.
Delay, that is, not only in the progress of any one case but in the
movement of those waiting for trial. It is essential that parties be
ready to start and that they do start on the day fixed for the
commencement of a trial. Of course, sudden unexpected events will
sometimes demand an adjournment or the taking of a case out of the
list. But anything that justifies that action will be exceptional. Parties
who are merely not ready at the right time must take the
consequences. Of course, over all this and over everything said about
case flow management is the umbrella of the interests of justice.
Sometimes that will justify some adjournment or postponement. Nor
must the general moving of the list cause undeserved prejudice to
any party. Everything said by anyone on case flow management is
said subject to the interests of justice. But again I refer to the cases
waiting in the list. The interests of justice demand that they be
delayed for as short a time as possible.
In the case at bar the appellant was merely not ready at the right
time. It had not looked thoroughly into the matter, prepared and
investigated it before the time fixed for the pre-trial conference, still
less prior to trial.”
[17] The plaintiff is, simply, not ready at this time. There is time for it to do the work
necessary to be ready.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2007/381