Begun Property P/L v Business in Focus (Aust) P/L & Anor [2007] QSC 342
SUPREME COURT OF QUEENSLAND
CITATION: Begun Property P/L v Business in Focus (Aust) P/L & Anor
[2007] QSC 342
PARTIES: BEGUN PROPERTY PTY LTD
ACN 104 730 976
(plaintiff)
v
BUSINESS IN FOCUS (AUST) PTY LTD
ACN 062 413 665
(first defendant)
WELBON BUILDING & PLUMBING PTY LTD
ACN 003 640 373
(second defendant)
FILE NO/S: BS 3383 of 2007
DIVISION: Trial Division
PROCEEDING: Trial
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 19 November 2007
DELIVERED AT: Brisbane
HEARING DATE: 8 & 9 November 2007
JUDGE: Martin J
ORDER: Order in terms of the draft provided by the plaintiff
CATCHWORDS: DAMAGES – GENERAL PRINCIPLES – MEASURE OF
DAMAGES FOR BREACH OF FIDUCIARY DUTY –
where parties had entered a venture agreement for the running
of a tourist resort – where disputes arose and Begun took
steps to terminate the agreement – where defendant failed to
perform obligations under venture agreement – where
plaintiff's successfully applied to court for removal of consent
caveat – where bank guarantee given to protect the
defendants' interests – where plaintiff claims damages for loss
occasioned by defendants' failure to comply with their
obligations under the venture agreement and loss of
opportunity arising from that failure – where plaintiff also
claims damages for loss occasioned by having to secure a
bank guarantee for removal of caveat – whether damages
should be awarded under these heads – appropriate measure
of damages for breach of fiduciary duty – whether set-off of
arbitration costs and four costs orders should be allowed
-- 1 of 7 --
2
Hull v Thompson [2001] NSWCA 359, cited
COUNSEL: J W Peden for the plaintiff
T A Hall (sol) for the defendants
SOLICITORS: Nicholsons Solicitors for the plaintiff
Hall Partners for the defendants
[1] MARTIN J: On 12 October this year judgment was given for the plaintiff in this
matter in the following terms:
“1. That there be judgment for the Plaintiff in terms of
paragraphs 2 to 9 below;
2. The defence be struck out;
3. Damages, alternatively equitable compensation, for breaches
of fiduciary duty to be assessed in accordance with
paragraphs 5 to 8 below;
4. Damages for breach of the venture agreement to be assessed
in accordance with paragraph 5 – 8 below;
5. A declaration that the Begun Value is $1,393,750.00 being
fifty percent of the value of the developed land as determined
by Mr J D Dodds;
6. A declaration that Begun is entitled to have the option
specifically performed and carried into execution by the First
and Second Defendant;
7. The assessment for damages at paragraph 3 and 4 be heard on
8 th & 9 th November 2007;
8. That the First and Second Defendants specifically perform
and carry into execution the option with the settlement date
fixed as seven days after the damages have been assessed and
fixed in accordance with paragraph 7 above.”
[2] This is the assessment of the damages referred to in the order above.
Background
[3] In September 2003 the plaintiff, Michael Steven Begun (MB), the defendants and
Gloucester Point (Aust) Pty Ltd (GPA) entered into a venture agreement to develop
and operate a tourist resort situated at Gloucester Point some 47 kilometres by road
north of Proserpine. The basis of the proposal was that the defendants would build
the resort and that MB would provide the necessary land. Construction started at
about the time that the parties entered into the venture agreement but by August
2004 the parties were in dispute about various matters.
[4] The land upon which the resort was being built was one part of a larger parcel of
land owned by MB. The larger parcel had an area of about 57 hectares (the gross
land). The land upon which the tourist resort was to be constructed had an area of
about 16 hectares (the development land). It was provided in the venture agreement
that GPA would apply for approval to subdivide the gross land and that the relevant
parties would take the necessary steps to ensure that the subdivision went ahead.
[5] Clause 12 of the venture agreement provided:
“12.1 If the subdivision approval is not granted or granted on terms
that are not acceptable to the Venturers and the business of the
-- 2 of 7 --
3
resort has been operating for a period of not less than 12
months and if either of the Venturers wish to wind up the
Venture then the following shall occur in the priority as set
out below:
12.1.1 Begun or its nominee shall have the option to
purchase the interest of BWG in the venture for the
Begun Value which shall be exercised within 14 days
of the Venturers being notified by GPA that the
subdivision approval has not been granted or having
been granted is not acceptable.
…
12.1.3 Each of the payments referred to in clauses 12.1.1 and
12.1.2 shall be made within 90 days after the exercise
of the first right of refusal by either Venturer in
exchange for any legal transfers for the relevant
interest(s) including repayment of any loan moneys,
and in respect of Begun’s first right of refusal being
exercised, the Loan.”
[6] Clause 12.2 defined some of the terms used in the above clauses as follows:
“‘Valuer’ means the price determined by an independent valuer of
not less than five years experience appointed by agreement between
the Venturers or failing agreement the President of the Queensland
Law Society Incorporated.”
“‘Begun value’ means 50% of the Value of the Developed Land
including the business and all improvements.”
[7] In February 2005 the Begun interests took steps to terminate the joint venture
agreement. Those steps were resisted by the respondents. That led to an arbitration
in which the arbitrator (Mr Bain of Queens Counsel) found in favour of the Begun
interests and directed that steps occur which would lead to the determination of the
agreement and the buyout by the Begun interests of the defendants’ interests.
[8] The defendants did not comply with the award and the plaintiff had the award
registered as a judgment of this Court. The arbitrator had made certain orders which
required that steps be taken which would result in the defendants paying the
plaintiff 50 per cent of the Begun value.
[9] After some delays a valuer was engaged in May 2006. Both parties briefed the
valuer and it was agreed that he should produce a valuation at the date of inspection
– 12 June 2006 – and at 15 February 2005. The latter date was the date at which, on
the plaintiff’s case, the plaintiff could have purchased the defendants’ interests in
accordance with the Notice it had given at the time and which had been resisted by
the defendants. The former date was the date agreed upon by the parties as the
appropriate date for assessment of the Begun value following the decision of the
arbitrator. The valuation was completed in November 2006 and the valuations at the
particular dates were:
1. 15 February 2005 – $2,100,000;
2. 12 June 2006 – $2,787,500.
-- 3 of 7 --
4
[10] In accordance with the definition in the venture agreement the Begun value at 15
February 2005 was $1,050,000 and at 12 June 2006 was $1,393,750. The latter
value is the subject of the declaration in paragraph 2 of these reasons.
[11] After receiving the valuation the plaintiff, consistent with the decision of the
arbitrator and the provisions of the venture agreement, gave the requisite notices to
complete and sought settlement on 7 December 2006. The plaintiff’s
representatives attended the settlement with all necessary documents and a bank
cheque payable to the defendants in the correct amount.
[12] The defendants did not attend the settlement.
[13] It is recorded in the venture agreement that the defendants and GPA were to
advance to MB the sum of $500,000 (described as “the Loan”) on the execution of
the venture agreement and that in exchange for the Loan MB was to execute and
deliver to the defendants and GPA a consent caveat over the gross land to “better
secure the repayment of the Loan and the obligations of Mr Begun and [the
plaintiff] in the venture agreement”.
[14] That amount was advanced and a consent caveat was lodged.
[15] Following the failed settlement attempt the plaintiff and MB brought an application
before this Court for the removal of the caveat. The matter came on before
P D McMurdo J (in Begun & Anor v Business in Focus (Aust) Pty Ltd & Ors (BS
2213 of 2005, unreported)) and on 15 December 2006 his Honour ordered that the
caveat be removed conditional upon the provision by the applicants in that
application of a bank guarantee in the amount of $1.5 million.
[16] His Honour was satisfied that the defendants would be sufficiently protected by the
provision of the bank guarantee referred to above.
[17] The defendants, notwithstanding the arbitrator’s award, its registration as a
judgment of this Court and the decision of P D McMurdo J still refused to settle in
accordance with the requirements of the venture agreement.
[18] In May this year Begun Property Pty Ltd commenced these proceedings against the
defendants seeking, among other things, specific performance of the option for
purchase contained within the venture agreement. A defence to the claim was filed
in July but, following a series of failures to comply with both the rules of this Court
and orders made for disclosure, the defence was struck out and the order set out in
paragraph 2 above was made.
[19] The plaintiff seeks damages in two parts:
the Loss of Opportunity Claim: the difference between the Begun value
at February 2005 ($1,050,000) and at June 2006 ($1,393,750), i.e,
$343,750, and
the Bank Guarantee Claim: the costs associated with procuring the bank
guarantee so that the caveat might be released – $46,833.93.
Loss of Opportunity Claim
[20] The defendant has failed at every step to resist the plaintiff’s claims with respect to
the performance of the defendant’s obligations under the venture agreement. Had
the defendants complied with the conditions of the venture agreement, then the
-- 4 of 7 --
5
plaintiff would have paid to them the amount of $1,050,000 (with any adjustments)
in February 2005 and the defendants’ interests would have been conveyed to the
Begun interests. Because of the defendants’ breach the plaintiff was not able to
comply with various requirements in the venture agreement and so, on its own case,
it has to pay the higher Begun value in accordance with the arbitrator’s award –
$1,393,750.
[21] MB gave evidence that the plaintiff had the capacity to raise the funds necessary to
pay the Begun value at either February 2005 or June 2006. He also outlined the
steps he had taken to give the appropriate notices under the venture agreement and
to determine the amount for which the plaintiff would be liable. This latter point
was supported by the plaintiff having obtained a separate valuation of the property
prior to giving the relevant notice in January 2005. It was conceded by the
defendants that the plaintiff was willing to engage in the transfer of property.
[22] There was nothing put to MB on behalf of the defendants to suggest that the
plaintiff was not ready, willing and able to complete at either February 2005 or June
2006. Although MB’s evidence on the plaintiff’s ability to pay the appropriate
amount was not detailed I regard it as credible and, in the absence of any challenge,
I accept it. (Hull v Thompson [2001] NSWCA 359)
[23] In answer to the plaintiff’s analysis of its loss the defendants put the following
argument:
any assessment of damages must take into account the benefits that have
accrued to the plaintiff by virtue of the defendants’ failure to complete;
the plaintiff benefited from not paying the Begun value in 2005 by
reason of not having to pay interest on money borrowed to finance the
purchase;
the plaintiff benefited by remaining in possession of the resort from the
time of the defendants’ initial breach in early 2005;
it follows, say the defendants, that an amount equivalent to the interest
which did not need to be paid and an amount representing the value of
remaining in possession of the resort should be deducted from any
damages arising out of the difference between the 2005 Begun value and
the 2006 Begun value.
[24] I will deal with the latter point first. The plaintiff was not in possession of the resort
after March 2005. From that month another company, Begun Resorts Pty Ltd, was
in possession of the resort until another entity, not associated with any of the parties,
started to conduct the resort.
[25] The argument put forward on the major point – that the defendants should benefit
from the financial arrangements of the plaintiff – must be dismissed. Should it be
otherwise then it would mean that, while the plaintiff’s damages would be reduced
by the notional interest payments, the defendants would still receive the higher of
the Begun valuations. The calculations put forward in support of this argument were
entirely speculative and completely lacking in any evidentiary basis.
[26] Had the venture agreement not contained the process which requires that the 2006
Begun value be the amount to be the paid by the plaintiff, then, in the ordinary way,
the 2005 Begun value would have been the amount required to be paid and, thus,
upon an order for specific performance, the plaintiff would have been liable only for
-- 5 of 7 --
6
that amount. The defendants’ breach has caused that amount to increase and the
plaintiff lost the opportunity to purchase at the lower figure. The damage suffered,
then, is the difference between those two amounts.
Bank Guarantee Claim
[27] The plaintiff claims it is entitled to damages equal to the costs incurred in obtaining
a bank guarantee to replace the security constituted by the consent caveat. Had the
defendants honoured their obligations under the venture agreement they would have
attended at the settlement on 7 December 2006 and they would have received the
requisite amount. The reason for the caveat would have dissolved and the caveat
would have been removed.
[28] As was observed by P D McMurdo J in his reasons for ordering the removal of the
caveat:
“The applicants [the plaintiff and MB] wish to proceed with the
development of the land and the existence of the caveat [i]s a
substantial impediment to their obtaining finance to do so. They are
also interested in the trading of the resort by Begun Resorts Pty Ltd
which is trading at a loss and is likely to have to close the resort
unless the Begun interests can obtain refinance, again, dependent
upon the removal of the caveat. The caveat is there only to secure
the payment of money.”
[29] The action taken by the plaintiff in replacing the caveat with a bank guarantee was
generated by the failure of the defendants to complete their bargain in the terms of
the venture agreement. The costs incurred include the legal costs expended in the
application to this Court and the fees charged by the bank for the guarantee. I find
that the total of those costs is $46,833.93 and that they are damages recoverable by
the plaintiff.
Other matters
[30] It is agreed between the parties that the costs of the arbitration ($205,000) are to be
set-off against the amount otherwise owed by the plaintiff to the defendants for the
2006 Begun valuation.
[31] The plaintiff also seeks to set-off the amount of $97,829.96 which is the sum of four
costs orders in favour of the plaintiff against the defendants. Three of those orders
were made in this Court and one was made in the Federal Court. There is agreement
as to the quantum of the costs payable under those orders but no agreement that they
be set-off in the same way as the arbitration costs. In paragraph 37(a) of the
Statement of Claim an amount of “Approximately $75,000” is claimed as the costs
of the proceedings to remove the caveat but no claim is made to set-off that sum or
any other amount. In any event an amount has already been awarded in respect of
the caveat proceedings. The other costs orders are not the subject of any claim in
the pleadings and no application was made to amend. I reject the claim to set-off
the amount owing under the costs orders against the amount to be paid under the
venture agreement.
-- 6 of 7 --
7
Assessment
[32] I assess damages in the sum of $390,583.93. I direct the plaintiff to bring in
minutes of order reflecting this assessment and I direct that such orders allow for
execution of necessary documents by a person other than the defendants should the
defendants fail to carry into effect the order for specific performance made on 12
October 2007.
Addendum
[33] When this matter came on for the delivery of these reasons, I was informed by Mr
Peden of Counsel (for the plaintiff) that there was an agreement between the parties
concerning the amount for costs referred to in [31] above. Mr Hall (for the
defendants) concurred. That agreement is in the same terms as those set out in [30].
Therefore, the sum otherwise payable by the plaintiff to the defendants pursuant to
the order for specific performance will reflect that agreement by being reduced by
the amount of $97,829.96.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2007/342