Bezzina Developers Pty Ltd v Deemah Stone (Qld) Pty Ltd [2007] QSC 286
SUPREME COURT OF QUEENSLAND
CITATION: Bezzina Developers P/L v Deemah Stone (Qld) P/L [2007]
QSC 286
PARTIES: BEZZINA DEVELOPERS PTY LTD ACN 079 373 470
(applicant)
v
DEEMAH STONE (QLD) PTY LTD ACN 115 129 014
(first respondent)
MAX TONKIN
(second respondent)
HELEN DURHAM
(third respondent)
ADJUDICATE TODAY PTY LTD ABN 32 109 605 021
(fourth respondent)
FILE NO: BS 3546 of 2007
DIVISION: Trial Division
PROCEEDING: Originating Application
ORIGINATING
COURT: Supreme Court, Brisbane
DELIVERED ON: 8 October 2007
DELIVERED AT: Supreme Court, Brisbane
HEARING DATE: 21 September 2007
JUDGE: Douglas J
ORDER: Further submissions sought as to the terms of the order
and costs.
CATCHWORDS: ADMINISTRATIVE LAW – JUDICIAL REVIEW –
GROUNDS OF REVIEW – ERROR OF LAW – application
for judicial review of decision of adjudicator made under
Building and Construction Industry Payments Act 2004 (Qld)
- whether parties were parties to a construction contract –
whether adjudicator had valued work done under the
construction contract – where second adjudicator failed to
take into account s. 27 of the Act and its effect on his
obligation to value the work which was the subject of the
payment claim before him by giving it the same value as that
previously decided in an earlier adjudication application -
because of failure to apply s. 27, refusal of relief under s. 100
not appropriate- necessary extension of time under s. 26 of
-- 1 of 11 --
2
the JR Act granted for the making of a statutory order of
review.
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
CONSTRUCTION OF PARTICULAR CONTRACTS AND
IMPLIED CONDITIONS – OTHER MATTERS – –
application for judicial review of decision of adjudicator
made under Building and Construction Industry Payments
Act 2004 (Qld) - whether parties were parties to a
construction contract – whether adjudicator had valued work
done under the construction contract – where second
adjudicator failed to take into account s. 27 of the Act and its
effect on his obligation to value the work which was the
subject of the payment claim before him by giving it the same
value as that previously decided in an earlier adjudication
application - because of failure to apply s. 27, refusal of relief
under s. 100 not appropriate- necessary extension of time
under s. 26 of the JR Act granted for the making of a
statutory order of review.
Building and Construction Industry Payments Act 2004, s14,
s24(4), s25(4)(a), s26(2), S26(3)(a), s25(4), s27, s27(2), s100
Judicial Review Act 1991, s 13, 20(2)(c), s26
Justice and Other Legislation Amendment Bill 2007
ACN 060 559 971 Pty Ltd v O’Brien [2007] QSC 91, cited
Anvil Hill Project Watch Association Inc v Minister for the
Environment and Water Resources [2007] FCA 1480, cited
Bermingham v Corrective Services Commission (NSW)
(1988) 15 NSWLR 292, cited
Brodyn Pty Ltd v Devonport (2004) 61 NSWLR 421, cited
Coordinated Construction Co Pty Ltd v JM Hargreaves
(NSW) Pty Ltd (2005) 21 BCL 312; [2005] NSWSC 77,
considered and distinguished
Craig v South Australia (1995) 184 CLR 163, applied
Fifty Property Investments Pty Ltd v O'Mara [2006] NSWSC
428, cited
Intero Hospitality Projects Pty Ltd v Empire Interior
(Australia) Pty Ltd [2007] QSC 220, cited
John Goss Projects Pty Ltd v Leighton Contractors Pty Ltd
[2006] NSWSC 798, cited
Minister for Commerce v Contrax Plumbing (NSW) Pty Ltd
[2005] NSWCA 142, cited
Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC
1140, cited
Newcastle City Council v GIO General Ltd (1997) 191 CLR
85, cited
Okaroo Pty Ltd v Vos Construction and Joinery Pty Ltd
[2005] NSWSC 45, followed
-- 2 of 11 --
3
Pacific General Securities Ltd v Soliman & Sons Pty Ltd
[2006] NSWSC 13, cited
Rothnere Pty Ltd v Quasar Constructions NSW Pty Ltd
[2004] NSWSC 1151, cited
State of Queensland v Epoca Constructions Pty Ltd [2006]
QSC 324, cited
Timbarra Protection Coalition Inc v Ross Mining NL (1999)
46 NSWLR 55,cited
COUNSEL: Mr G D Beacham for the applicant
Mr P Bickford with Mr A Wallace for the respondents
SOLICITORS: Holding Redlich for the applicant
Moray Agnew Solicitors for the respondents
[1] Douglas J: This is an application to review two adjudication decisions made under
the Building and Construction Industry Payments Act 2004 (“the Payments Act”).
The decisions deal with a contract for the supply of stone work for a construction
project, “Jade Apartments”, in Surfers Paradise. The applicant is the builder and
developer of the project, Bezzina Developers Pty Ltd (“Bezzina”). The first
respondent is Deemah Stone (Qld) Pty Ltd (“Deemah”). It appears likely that the
original contracting parties were Bezzina and a company associated with Deemah.
Deemah’s associated company was called Deemah Stone Pty Limited which was
said to have originally provided the quotation to Bezzina. By a letter of 8
September 2006, however, it was asserted that the contract had been assigned to
Deemah. The first adjudication decision valued the work done at an amount
significantly less than the second decision by a different adjudicator who had not
been told the result of the first decision.
Background
[2] During the course of the works Deemah provided Bezzina with 13 progress claims,
the first 11 of which were paid. These disputes relate to progress claims numbers
12 and 13.
[3] When the twelfth claim for $712,149.58 (excluding GST) was not paid Deemah
made an adjudication application. That occurred on 27 February 2007 but it was
not served on Bezzina until 5 March 2007. On 28 February 2007 Deemah served its
thirteenth claim on Bezzina incorporating a claim for an additional sum of
$971,995.68 excluding GST.
[4] On 28 March 2007 the third respondent made an adjudication decision in favour of
Deemah in the amount of $218,382.14 (excluding GST). That decision was not
released to the parties by the fourth respondent, the authorised nominating authority
under the Act, until 13 April 2007 because it was not until then that Deemah paid
the fourth respondent the adjudicator’s costs for that first decision.
[5] In the interim, Deemah had made an adjudication application on 28 March 2007 in
respect of the thirteenth progress claim. Bezzina had served a payment schedule in
respect of that claim but did not serve an adjudication response.
-- 3 of 11 --
4
[6] That dispute was not referred to the adjudicator who had dealt with the twelfth
progress claim but to a different adjudicator, the second respondent. On 24 April
2007, the second respondent made his decision in respect of the second adjudication
application. It was in favour of Deemah in an amount of $655,978.91 excluding
GST. That decision was not released to the parties until 26 April 2007 when
Deemah paid the fourth respondent the second respondent’s adjudication costs.
[7] The second adjudication decision was made in ignorance of the result of the first
decision although the second adjudicator (the second respondent to these
proceedings) had been told that an adjudication application in relation to the twelfth
progress claim had been lodged; see para 13 of the second adjudication decision.
The applicant’s complaints
[8] The first adjudication decision was criticised by Bezzina as having been made in the
absence of proper evidence that Bezzina and Deemah were parties to a construction
contract. The second adjudication decision is attacked by Bezzina on two bases.
[9] The first is that the second adjudicator did not value the construction work carried
out pursuant to s. 14 of the Payments Act but, in Bezzina’s submission, approached
the exercise by accepting the claimed price as a given and then by examining
whether any of the work performed by Deemah was defective as alleged by
Bezzina. It submitted that the valuation of the work should have been done in the
first place before any consideration of the cost of rectifying any defect had been
entered into. It was notable, however, that no submission was made by Bezzina to
the second adjudicator challenging the value of the amount claimed, particularly
because of its failure to lodge an adjudication response in respect of that claim.
[10] The question of the valuation of the construction work by the second adjudicator
was, however, important. According to s. 27 of the Payments Act, if an earlier
adjudicator has decided the value of any construction work carried out under a
construction contract, then the later adjudicator must, in any later adjudication
application that involves the working out of the value of that work or of those goods
and services, give the work or the goods and services the same value as that
previously decided, unless the claimant or respondent satisfies the adjudicator
concerned that the value of the work or the goods and services has changed since
the previous decision. The section reads as follows:
“27 Valuation of work etc. in later adjudication application
(1) Subsection (2) applies if, in deciding an adjudication
application, an adjudicator has, under section 14,17 decided—
(a) the value of any construction work carried out under a
construction contract; or
(b) the value of any related goods and services supplied
under a construction contract.
(2) The adjudicator or another adjudicator must, in any later
adjudication application that involves the working out of the
value of that work or of those goods and services, give the
work, or the goods and services, the same value as that
previously decided unless the claimant or respondent satisfies
the adjudicator concerned that the value of the work, or the
goods and services, has changed since the previous decision.”
-- 4 of 11 --
5
[11] The practical problem that arises here is that the second adjudicator was not
informed of the result of the first adjudicator’s decision and his decision was at
variance with hers because she had assessed the sum owing to Deemah as
$218,382.14 where the claim was $712,149.58, thus valuing the work at almost
$500,000 less than the claim. The second adjudicator, however, in awarding the
first respondent $655,978.91, had effectively decided, if not in those precise terms,
that the value of the work assessed by the first adjudicator had increased, in the
absence of any submissions by either Bezzina or Deemah to satisfy him that the
value of that work had changed since the first decision. The increase is of the order
of $500,000.
The scheme of the Payments Act
[12] The object of the Payments Act is to enable contractors doing work for a developer
or builder pursuant to a construction contract to receive and recover progress
payments by serving a payment claim upon the other party. The parties served may
respond with a payment schedule which sets out the amount that is admitted to be
owed to the contractor and the reasons why that amount is less than the payment
claim.
[13] If a payment schedule is served the contractor may refer the payment claim for
adjudication and make submissions in support of its payment claim and against the
matters set out in the payments schedule. The other party is entitled to deliver an
adjudication response containing its submissions on the payment claim and payment
schedules.
[14] The matter is then determined by an adjudicator whose task is to value the work
performed by the contractor and, as I have already indicated, if there is a subsequent
adjudication the second adjudicator must give the work the same value as the
previous adjudicator unless the party satisfies the adjudicator that its value has
changed.
[15] An adjudicator’s decision may be registered in the court in which case it takes effect
as a judgment debt. The procedure is summary and very expeditious requiring, for
example, an adjudicator to make his or her decision as quickly as possible and, in
any case, within 10 business days after the earlier of the date on which the
adjudicator receives the adjudication response or should have received that
response; s. 25(3)(a). Section 25(4), however, permits an adjudicator to ask for
further written submissions from either party.
[16] Section 100 of the Payments Act, in effect, allows these decisions to be
reconsidered in normal civil proceedings and permits the court in those proceedings
to make orders for the restitution of any amount paid pursuant to the procedures for
recovering progress payments created by part 3 of the Payments Act. Palmer J, in
the New South Wales Supreme Court, appropriately dubbed the approach in their
equivalent legislation as a “pay now, argue later” solution to the problem of
recovery by contractors of progress payments from builders and developers;
Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140 at [96].
[17] It has been recognised, however, that adjudications under the Payments Act are
susceptible to judicial review under the Judicial Review Act 1991 (“the JR Act”);
see, e.g. State of Queensland v Epoca Constructions Pty Ltd [2006] QSC 324 at
[16]-[35]. That may be about to change as a result of part 17 of the Justice and
-- 5 of 11 --
6
Other Legislation Amendment Bill 2007. There may also be differing views as to
whether s. 100 of the Payments Act is a provision under which an applicant is
entitled to seek a review of the matter by another court or tribunal for the purposes
of enlivening the power to dismiss an application for a statutory order of review
under s. 13 of the JR Act; cf. State of Queensland v Epoca Constructions at [36]
with Intero Hospitality Projects Pty Ltd v Empire Interior (Australia) Pty Ltd
[2007] QSC 220 at [7]-[8].
[18] For reasons that will appear, however, it seems unnecessary to me to resolve that
issue in this decision.
The first adjudication decision – was there a construction contract?
[19] The submissions for Bezzina in respect of the first adjudication decision were that it
had not been established that Deemah was a party to the construction contract
because the quotation was submitted by its associated company. Mr Beacham, for
Bezzina, submitted that the evidence that the contract had been assigned to Deemah
was deficient and not enough to support a finding that it was a party to the
construction contract. He submitted that the mere assignment of the benefit of such
a contract was not enough to constitute the assignee as a person who had undertaken
to carry out construction work under the contract within the meaning of s. 12 of the
Payments Act. In other words he submitted the evidence simply established an
alleged assignment and did not prove that Deemah was entitled not only to the
benefits of the construction contract but also subject to its burdens, namely the
performance of the work. From there he argued that the adjudicators did not have
jurisdiction to make the adjudication decisions within s. 20(2)(c) of the JR Act or
that they erred in law or failed to take into account a relevant consideration in
making those decisions.
[20] He submitted that those were essential conditions to the exercise of jurisdiction
under the Act failure to comply with which meant that any adjudicator’s
determination would be void and not merely voidable; see Brodyn Pty Ltd v
Devonport (2004) 61 NSWLR 421, 441-442 at [52], [55].
[21] When one examines the progress claims made by Deemah one sees that they appear
on its letterhead and detail the work said to have been done. The fair inference from
the making of those claims in circumstances where the contract was said to have
been assigned to it is that it was the company that also did the work. The meaning
attributed to “construction contract” in Schedule 2 of the Payments Act is “a
contract, agreement or other arrangement under which one party undertakes to carry
out construction work for, or to supply related goods and services to another party”
(my emphasis). In this context Mr Bickford for Deemah, drew my attention to the
discussion by Nicholas J in Okaroo Pty Ltd v Vos Construction and Joinery Pty Ltd
[2005] NSWSC 45 at [41] where his Honour said:
“With regard to the authorities, and to its context in the Act, in my
opinion the term “arrangement” in the definition is a wide one, and
encompasses transactions or relationships which are not legally
enforceable agreements. The distinction in the definition between “a
contract” and “other arrangement” is intended by the legislature to be
one of substance so that under the Act construction contracts include
agreements which are legally enforceable and transactions which are
not. Thus in distinguishing between these relationships I understand
-- 6 of 11 --
7
the legislature intends that “contract” is to be given its common law
meaning and that “arrangement” means a transaction or relationship
which is not enforceable at law as a contract would be. Accordingly I
reject the submission for Okaroo that the term “arrangement” should
be understood to mean an agreement which is tantamount to a
contract enforceable at law.”
[22] In my view that is a correct approach to the construction of that word in this context
and there was evidence before both adjudicators to satisfy them that the
arrangement between Bezzina and Deemah was sufficient to meet the definition of
“construction contract” under the Act.
[23] Deemah also sought, against objection, to prove the written assignment which had
been asserted by it in its letter of 8 September 2006 as relevant to these issues. It
seemed to me to be admissible if, for no other reason, than to address the issue
whether I should exercise any discretion to grant judicial review in the
circumstances. It was also admissible to establish the truth of the jurisdictional fact
the respondent relied on, namely that it had performed work under a construction
contract. I do not see why I should be limited in examining that question to the
evidence that happened to be before the adjudicator; cf., e.g., Fifty Property
Investments Pty Ltd v O'Mara [2006] NSWSC 428 at [18]-[20]. As Spigelman CJ
pointed out in Timbarra Protection Coalition Inc v Ross Mining NL (1999) 46
NSWLR 55 at 64:
“[40] Where the process of construction leads to the conclusion that
parliament intended that the factual reference can only be satisfied by
the actual existence (or non-existence) of the fact or facts, then the
rule of law requires a court with a judicial review jurisdiction to give
effect to that intention by inquiry into the existence of the fact or
facts.”
[24] He went on to say at 71:
“[85] … facts, even where they are described as ‘objective’, do not
have an existence independent of their identification by some process
of human agency. An administrative decision-maker often has to
determine jurisdictional facts, but does not do so conclusively. This
has been recognised as long ago as Bunbury v Fuller (1853) 9 Ex
111 at 140; 156 ER 47 at 60.”
[25] See also Anvil Hill Project Watch Association Inc v Minister for the Environment
and Water Resources [2007] FCA 1480 at [59]-[61].
[26] The tender of the progress claims was also objected to but all but one of them were
already in evidence before the adjudicators so there was little point in the objection
and, in any event, they were admissible to help me examine the jurisdictional facts
said not to exist, namely a construction contract between the applicant and the first
respondent. In my view both objections, to paragraphs 2 and 8 of the affidavit of
Ms Melham filed by leave on 21 September 2007 should be rejected.
The second adjudication decision – valuation of the construction work
[27] Had the only argument available to Bezzina been that the second adjudicator did not
approach his task properly by valuing the work before considering the defects
alleged by Bezzina, I would not have been disposed to interfere with his decision.
-- 7 of 11 --
8
Bezzina, apart from drawing my attention to the obligation to value construction
work in s. 14 of the Payments Act, also relied upon the reasons of Brereton J in
Pacific General Securities Ltd v Soliman & Sons Pty Ltd [2006] NSWSC 13 where
his Honour, at [82]-[86], found that the adjudicator’s duty was to come to a view as
to what was properly payable on what the adjudicator considered to be the true
construction of the contract and the Act and the true merits of the claim. He treated
the obligation to determine whether the construction work identified in the payment
claim had been carried out and its value as part of the basic and essential
requirements of validity. In reaching that conclusion he said that if an adjudicator
allowed a claim in full just because a respondent’s submissions were rejected,
without determining whether the construction work had been performed and without
valuing it, that would bespeak a misconception of what was required by an
adjudicator, leading to jurisdictional error resulting in invalidity.
[28] In these circumstances, however, there was no issue raised by Bezzina about
whether the work had been performed or about the value claimed by Deemah.
Bezzina’s submissions focussed more upon the alleged defects. Had that been the
only problem associated with the second adjudication decision I would not have
been inclined to exercise my discretion to review it. Nor would I have been inclined
to grant the extension of time necessary to review the decision under s. 26 of the JR
Act in respect of the relief claimed for a statutory order of review under that Act.
[29] It seems to me, however, to be a significant issue that the exercise apparently
required by s. 27(2) of the Payments Act has not occurred, namely the second
adjudicator did not give the same value to the work, goods or services as that
previously assessed by the first adjudicator. The first adjudicator approached her
task as one requiring her to value the work in arriving at her views as to the
appropriate progress payments to order; see, e.g., paras 37, 46, 64, 87 and 119 of the
first adjudication decision.
[30] It was argued that the second adjudication did not decide the value of the
construction work but examined whether there should be a deduction from the price
claimed for alleged defects and some other matters dealt with in detail by the
adjudicator. The consequence argued was that his adjudication did not involve “the
working out of the value of that work” to use the language of s. 27(2). Reference
was also made to the decision of Mullins J in ACN 060 559 971 Pty Ltd v O’Brien
[2007] QSC 91 at [32]-[34] where her Honour considered two decisions of the New
South Wales Supreme Court dealing with the interpretation of their statute’s
equivalent section; Rothnere Pty Ltd v Quasar Constructions NSW Pty Ltd [2004]
NSWSC 1151 and John Goss Projects Pty Ltd v Leighton Contractors Pty Ltd
[2006] NSWSC 798 (“Goss Projects”). McDougall J in Goss Projects drew a
distinction at [40] “between the calculation of the amount of a progress payment
(which is, ultimately, what the adjudicator is required to do) and the valuation of
construction work.” Her Honour applied that approach, correctly in my respectful
view, to conclude that a deduction for liquidated damages, was “distinct from the
value of work carried out by the contractor in the performance of the contract”; see
at [34].
[31] It seems to me, however, that the exercise engaged in by the second adjudicator here
of examining the possible deduction of claimed defects from the price claimed for
work done does involve the “working out of the value of that work” to use the
words of s. 27(2). Here the only evidence of value was the price claimed which was
-- 8 of 11 --
9
not itself put in issue and alleged defects in that work, if established, must be
matters that are involved in working out its value.
[32] It is difficult to criticise the second adjudicator for his omission to give the work
examined by him the same value as that given to it by the first adjudicator because
the parties did not bring the result of the first adjudication to his attention. Bezzina
argued that it was circumscribed in doing so because of the limitations placed on it
in respect of the provision of reasons for withholding payment unless the reasons
have already been included in the payment schedule served on Deemah; see s.
24(4).
[33] The limitations on the adjudicator in deciding an adjudication application under s.
26(2) were also drawn to my attention. An adjudicator is entitled to consider certain
matters only, namely:
“26(2) In deciding an adjudication application, the adjudicator is to
consider the following matters only—
(a) the provisions of this Act and, to the extent they are
relevant, the provisions of the Queensland Building
Services Authority Act 1991, part 4A;
(b) the provisions of the construction contract from which
the application arose;
(c) the payment claim to which the application relates,
together with all submissions, including relevant
documentation, that have been properly made by the
claimant in support of the claim;
(d) the payment schedule, if any, to which the application
relates, together with all submissions, including relevant
documentation, that have been properly made by the
respondent in support of the schedule;
(e) the results of any inspection carried out by the
adjudicator of any matter to which the claim relates.”
[34] Nonetheless, however, the second adjudicator had been informed of the making of
the first adjudication application and, in taking into account the provisions of the
Act pursuant to s. 26(2)(a), had the power to ask for further written submissions
from either party under s. 25(4)(a) to deal with his potential duty to apply s. 27. I
appreciate that he was acting under severe constraints of time imposed by the Act,
but the practical result of the failure to inform him, or of his failure to inquire about
the result, of the first adjudication application was that he failed to give the same
value as that previously decided to the value of the work being “worked out” in the
application before him. That seems to me to be a failure to comply with an
important provision of the Act in circumstances where, as here, a very different
result would have occurred if the obligations imposed by the Payments Act had
been met.
[35] One issue canvassed in argument on this issue was whether s. 27(2) of the Payments
Act should be construed to apply only to the results of previous adjudication
decisions of which a later adjudicator had been informed. The adjudicator’s power
under s. 25(4)(a) to call for further written submissions, his knowledge of the earlier
reference to adjudication and the apparent purpose of the provision in s. 27(2) as
one designed to discourage “forum shopping” among adjudicators suggest to me
that this is not necessarily a case where parliament has failed to deal with this
-- 9 of 11 --
10
eventuality in such a way as to permit me to read such words into the Act; see, e.g.,
Bermingham v Corrective Services Commission (NSW) (1988) 15 NSWLR 292, 302
and Newcastle City Council v GIO General Ltd (1997) 191 CLR 85, 113.
Parliament may just as well have expected that the later adjudicator, in carrying out
the task of valuing the work under s. 14 or of giving the work the same value as that
previously decided under s. 27, would have taken steps to inform himself or herself
of whether there had been such a decision and of the value attributed to the work by
the earlier adjudicator.
[36] As Hodgson JA said in Minister for Commerce v Contrax Plumbing (NSW) Pty Ltd
[2005] NSWCA 142 at [35] the sections requiring the adjudicator to consider the
provisions of the Payments Act and the provisions of the construction contract
entitled and indeed required the adjudicator to take into account any considerations
(other than considerations arising from facts and circumstances of the particular
case not otherwise before him or her) that he or she thought relevant to the
construction of that Act, the construction of the contract, and the validity of terms of
the contract having regard to the provisions of the Act.
[37] As a result it seems to me that there are good reasons for concluding that the second
respondent failed to take into account s. 27 of the Payments Act and its effects on
his obligation to value the work the subject of the payment claimed before him by
giving it the same value as that previously decided in the first adjudication
application. That failure to comply with the statutory procedure involved an error
of law sufficient to allow me to exercise jurisdiction under s. 20(2)(f) of the JR Act.
[38] There is an argument that it does not constitute a jurisdictional error invalidating the
decision apart from that Act canvassed in Coordinated Construction Co Pty Ltd v
JM Hargreaves (NSW) Pty Ltd (2005) 21 BCL 312; [2005] NSWSC 77 at [57]-[58].
It seems to me, however, to constitute a jurisdictional error, pursuant to the decision
in Craig v South Australia (1995) 184 CLR 163, 179, as a failure by the adjudicator
to take into account a relevant consideration, namely his statutory obligation to give
the same value to the work as that previously decided. That would also enliven my
jurisdiction to grant declaratory and/or injunctive relief and to set aside the
judgment already obtained.
[39] Because of the failure to apply s. 27 of the Act it seems to me that it is not
appropriate to refuse relief because of the existence of s. 100 of the Payments Act.
Any re-examination of the entitlements of the parties at that later stage will not deal
with this defect in the application of the Payments Act at this stage which has
resulted in a significant departure from the result intended to be achieved by the
statutory process.
Extension of time under JR Act
[40] The seriousness of the consequences of this error to Bezzina, its explanation for its
delay in bringing the application for a statutory order of review because of its
ignorance of the time limits under the JR Act for such relief, its payment into Court
of the money in dispute and the absence of significant evidence of prejudice to
Deemah unassociated with the merits of the dispute, encourage me to grant any
necessary extension of time under s. 26 of the JR Act for the making of a statutory
order of review.
-- 10 of 11 --
11
Orders
[41] I shall hear further submissions as to the form of any order and as to costs.
-- 11 of 11 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2007/286