Doolan & Anor v Rubikcon (Qld) Pty Ltd & Ors [2007] QSC 168 [2008] 2 Qd R 117
1
SUPREME COURT OF QUEENSLAND
CITATION: Doolan and Anor v Rubikcon (Qld) Pty Ltd and Ors
[2007] QSC 168
PARTIES: SANDRA DOOLAN AND STEPHEN DOOLAN
(applicants)
v
RUBIKCON (QLD) PTY LTD
ACN 099 635 275
(first respondent)
IAN HILLMAN
(second respondent)
AUSTRALIAN SOLUTIONS CENTRE PTY LTD
ACN 085 917 219
(third respondent)
FILE NO: SC No 3832 of 2007
DIVISION: Trial
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court
DELIVERED ON: 10 July 2007
DELIVERED AT: Brisbane
HEARING DATE: 10 July 2007
JUDGE: Fryberg J
ORDER: 1) Pursuant to section 30(1) of the Judicial Review Act
1991, the decision of the Second Respondent dated 2 April
2007 (a copy of which is exhibit “SPD-19” to the affidavit
of Stephen Patrick Doolan filed in these proceedings on 12
June 2007) is set aside, with the effect from the date
thereof.
2) The judgment entered by the First Respondent against
the Applicants on 16 May 2007 in proceedings 4145/07 of
this court is set aside
3) The amount of $43,533.82 (Forty-three thousand, five
hundred and thirty-three dollars and eighty-two cents) is
to be paid into court by the Applicants within 45 days to
abide the outcome of the proceedings referred to in the
First Respondent’s undertaking recorded above, to be
paid out (together with any accretions thereon) upon
further order of this court, whether made by consent of
the Applicants and the First Respondent pursuant to Rule
-- 1 of 15 --
10072007 T(1)13&14/JRR(BNE) M/T BRIS05 (Fryberg J)
2 ORDER
1
10
20
30
40
50
60
666, or otherwise
4) The First Respondent pay the Applicant’s costs of and
incidental to this application on the standard basis
5) No order as to the costs of proceedings 4145/07
6) Each party have liberty to apply on three (3) clear
days notice in writing
CATCHWORDS: Contracts – Building, engineering and related contracts –
Remuneration – Statutory regulation of entitlement to and
recovery of progress payments – Adjudicator ordered
payment of money claimed in two identical claims – Identical
claims not allowed under act – No jurisdiction to decide
claims – Order invalid
Building and Construction Industry Payments Act 2004 (Qld)
s12, s17, s25, s31, s33
Building and Construction Industry Security of Payment Act
1999 (NSW) s13
Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421, cited
Falgatt Constructions Pty Ltd v Equity Australia Corporation
Pty Ltd (2006) NSWCA 259, cited
Shellbridge Pty Ltd v Rider Hunt Sydney Pty Ltd [2005]
NSWCA 259, distinguished
COUNSEL: Applicant: G I Thompson
First Respondent: P Bickford
Second Respondent: no appearance
Third Respondent: no appearance
SOLICITORS: Applicant: Answorth Lawyers
First Respondent: Warlow Scott Solicitors
Second Respondent: no appearance
Third Respondent: no appearance
-- 2 of 15 --
10072007 T(1)13&14/JRR(BNE) M/T BRIS05 (Fryberg J)
3 ORDER
1
10
20
30
40
50
60
SUPREME COURT OF QUEENSLAND
CIVIL JURISDICTION [2007] QSC 168
FRYBERG J
No 3832 of 2007
SANDRA DOOLAN AND STEPHEN DOOLAN Applicants
and
RUBIKCON (QLD) PTY LTD
(ACN 099 635 275)
and
IAN HILLMAN
and
AUSTRALIAN SOLUTIONS CENTRE PTY LTD
(ACN 085 917 219)
First Respondent
Second Respondent
Third Respondent
BRISBANE
..DATE 10/07/2007
ORDER
-- 3 of 15 --
10072007 T(1)13&14/JRR(BNE) M/T BRIS05 (Fryberg J)
4 ORDER
1
10
20
30
40
50
60
HIS HONOUR: This is an application to review the decision of
an adjudicator appointed under the Building and Construction
Industry Payments Act 2004.
The decision was that the applicants pay a progress payment to
the first respondent in the sum of $43,533.82, and the total
adjudication fees and expenses.
The second respondent is the adjudicator and the third
respondent the appointing authority, and they have not
appeared because they are abiding the decision of the Court.
The applicant, as owner, entered into a building contract with
the first respondent on a Queensland Master Builders
Association Standard Form on the 8th of February 2005. The
contract provided for the first respondent, Rubikcon, to
construct for the applicants, the Doolans, eleven new
townhouses at Scarborough.
The work apparently proceeded and trouble arose only toward
the end of the job. The detail of how the trouble arose does
not matter for present purposes. It suffices to say that it
related to the making of a final inspection and issue of a
certificate and whether or not all works had been done which
needed to be done.
There were also some questions, I gather, about defects but
that does not matter for present purposes.
-- 4 of 15 --
10072007 T(1)13&14/JRR(BNE) M/T BRIS05 (Fryberg J)
5 ORDER
1
10
20
30
40
50
60
Rubikcon sought payment of a claim which it styled "Final
Claim" for the amount to which I have already referred. The
Doolans did not pay that claim.
The contract provided for progress payments. They were to be
paid in accordance with a schedule which in the standard form
provided two alternatives. The alternative selected by the
parties was under the heading "Method B". It stated in
handwriting under the sub-heading "Name of Stage or
Description of Stage of Works":
"Proforma and tax invoice issued on or near to 20th of
each month. Proforma to be a trade breakdown and
percentages of work completed shown."
That is a rather opaque way of expressing what is supposed to
be set out in the form (that is, the percentages of the
contract price and amounts payable at the completion of each
stage) and it does not sit happily with Cl 11.6 of the
contract under which it is made, however nothing turns upon
that in the present proceedings and no argument has been based
upon it.
The money not having been paid, Rubikcon sought the
appointment of Mr Hillman as adjudicator under the Act. That
was done.
Mr Hillman dealt with the case and determined that the money
should be paid. He decided on the 2nd of April this year that
the Doolans should be liable to Rubikcon for that amount and
-- 5 of 15 --
10072007 T(1)13&14/JRR(BNE) M/T BRIS05 (Fryberg J)
6 ORDER
1
10
20
30
40
50
60
that under the Act that amount became payable on the 27th of
February 2007.
Since then Rubikcon has, in accordance with s 31 of the Act,
filed an Adjudication Certificate in this Court as a judgment
for debt and accompanied it with the necessary affidavit.
The Doolans now seek judicial review of Mr Hillman's decision.
They submit that it is wrong in a number of respects. They
submit that there has been an error of law and that there have
been breaches of the rules of natural justice, but as the
matter was developed before me, at least, the former category
essentially included the latter. Three distinct arguments
were developed but in view of my assessment of the first of
them it is unnecessary that I deal with the others.
...
HIS HONOUR: The amount of the final claim has been claimed
twice and that is the fact which is at the heart of the first
point raised by the Doolans. It was first claimed in a
document called a tax invoice, sub-headed "Final Claim", and
dated 15 November 2006.
That claim became the subject of an attempted adjudication
under the Act, but the adjudication failed and was treated as
a nullity by an adjudicator who wrote to the parties on the
15th of February 2007 advising that, because the timing of
Rubikcon's notice was outside the period contemplated by the
-- 6 of 15 --
10072007 T(1)13&14/JRR(BNE) M/T BRIS05 (Fryberg J)
7 ORDER
1
10
20
30
40
50
60
Act, he would not provide a decision pursuant to s 25 of the
Act.
The parties accepted that outcome in respect of that referral,
but on the 16th of February 2007 Rubikcon issued another tax
invoice. Apart from the date it was identical to the first
invoice. The date was stated as 15 November 2006, but then
underneath it appeared the words "Reissued 16 February 2006".
It was, as I have said, otherwise identical to the earlier
invoice.
I turn to the legislation. The Act is based on the provisions
of a New South Wales Act, the Building and Construction
Industry Security of Payments Act 1999.
It is apparent from a reading of the Act that its purpose is
to secure to builders prompt payment of progress claims. No
doubt the mischief at which it was aimed was owners who place
financial pressure on builders by withholding payment
improperly.
It provides for a quick and cheap way of having disputes about
progress claims adjudicated without finally determining the
rights and wrongs of the dispute. If the adjudicator makes a
finding that the amount is payable, then the Act requires it
to be paid. Cross-claims, defences in the nature of other
contractual claims and so forth cannot be raised as matters of
set-off or counterclaim.
-- 7 of 15 --
10072007 T(1)13&14/JRR(BNE) M/T BRIS05 (Fryberg J)
8 ORDER
1
10
20
30
40
50
60
Nonetheless, although the adjudicator does not finally
determine rights, and in the event that he makes a mistake and
a payment is made pursuant to his ruling, the money can be
recovered if it is subsequently determined that the owner was
not obliged to make the payment, the adjudicator's decision is
subject to judicial review.
That much, at least, was common ground between the parties
today. It was accepted by the parties that subject to the
discretion provided by the Judicial Review Act, the Court is
entitled, indeed obliged, to consider whether the adjudicator
has, among other things, erred in law in reaching his
decision.
One of the matters before the adjudicator was the question of
whether Rubikcon was entitled to issue a second claim
identical to the first and to found proceedings before the
adjudicator upon that claim. As to that argument, the
adjudicator's response was, "As the contract reference date as
described above is on or near to 20th of each month, I am
satisfied that the claimant has not served two payment claims
in relation to the one reference date". Presumably the
adjudicator meant that the reference date for the second claim
was a different reference date from that for the first claim.
That is the way the argument has developed before me and it is
a question of construction of the Act as to whether that is an
acceptable approach.
-- 8 of 15 --
10072007 D.1 T(2)15/MEB(BNE) M/T BRIS05 (Fryberg J)
9
1
10
20
30
40
50
60
The starting point in considering the provisions of the Act is
section 12. That section provides: "For each reference date
under a construction contract, a person is entitled to a
progress payment if the person has undertaken to carry out
construction work or supply related goods and services under
the contract." There is no doubt that the contract in issue
in the present case was a construction contract within the
meaning of that section, or that Rubikcon had undertaken to
carry out construction work under the contract.
"Reference date" is defined in the Act to mean,
"(a) a date stated in, or worked out under, the
contract as the date on which a claim for a
progress payment may be made for construction work
carried out or undertaken to be carried out or
related goods and services supplied or undertaken
to be supplied under a contract, or
(b) ...".
Both parties accept that paragraph (a) of the definition is
the part which applies in the present case.
I quoted the contract provision relating to the date of
payment earlier. The argument developed on behalf of the
Doolans had two limbs. The first made no distinction between
whether the payment in question was a final payment or not.
The second had reference to the fact that it was a final
payment. I will revert to that second argument a little later.
-- 9 of 15 --
10072007 D.1 T(2)15/MEB(BNE) M/T BRIS05 (Fryberg J)
10
1
10
20
30
40
50
60
Section 17 of the Act provides that a person mentioned in s 12
who claims to be entitled to a progress payment, may serve a
payment claim on the person who, under the construction
contract concerned, is or may be liable to make the payment.
Payment claim in defined simply as a claim referred to in
s 17. The section nominates what the claim must include and
specifies that it may include not only work or related goods
and services to which it relates, but also liabilities of the
respondent under s 33(3) of the Act. That relates to losses
and expenses incurred as a result of the removal by the
respondent of any part of the work or supply.
Subsections 5 and 6 are the critical provisions for present
purposes:
"(5) A claimant cannot serve more than one payment
claim in relation to each reference date under the
construction contract.
(6) However, (5) does not prevent the claimant from
including in a payment claim an amount that has
been the subject of a previous claim."
For Rubikcon, Mr Bickford submits that (5) provides that a
claimant cannot serve more than one payment claim in relation
to each reference date. It does not say that a claimant
cannot, on multiple reference dates, make the same payment
claim. Consequently in his submission, Rubikcon was entitled
to do what it did and was entitled to base a subsequent
reference to adjudication on the second claim. Consequently
in his submission, Rubikcon was entitled to do what it did and
-- 10 of 15 --
10072007 T16/NLT(BNE) M/T BRIS05 (Fryberg J)
11 ORDER
1
10
20
30
40
50
60
was entitled to base a subsequent reference to adjudication on
the second claim.
In support of that submission reliance was placed on the
decision of the New South Wales Court of Appeal in Brodyn Pty
Limited v. Davenport (2004) 61 NSWLR 421 and in particular to
a passage in the judgment of Justice Hodgson at pp 443 to 444.
There the Court pointed out that the equivalent provision in
the New South Wales legislation did not provide that reference
dates cease on termination of a contract or cessation of work.
Mr Bickford submitted that that was the position in the
present case. He submitted that at the date when the second
tax invoice was submitted there was simply a new reference
date and the invoice with the claim embodied in it was a
legitimate payment claim under the Act.
What Justice Hodgson said bears quotation:
"63 However, s.8(2) of the Act does not provide that
reference dates cease on termination of a contract
or cessation of work. This may be the case under
s.8(2)(a) if the contract so provides but not
otherwise; while s.8(2)(b) provides a starting
reference date but not a concluding one. In my
opinion, the only non-contractual limit to the
occurrence of reference dates is that which in
effect flows from the limits in s.13(4): reference
dates cannot support the serving of any payment
claims outside these limits.
64 In my opinion, as submitted by Mr Fisher for Dasein,
this view is supported by s.13(6), which indicates
that successive payment claims do not necessarily
have to be in respect of additional work; and
especially by s.13(3)(a), which provides for
inclusion in payment claims of amounts for which the
respondent is liable under s.27(2A). Losses and
expenses arising from suspension of work could arise
-- 11 of 15 --
10072007 T16/NLT(BNE) M/T BRIS05 (Fryberg J)
12 ORDER
1
10
20
30
40
50
60
progressively for a substantial time after work has
ceased on a project, and s.13(3)(a) expressly
contemplates that further payment claims for these
losses and expenses may be made progressively."
I would respectfully agree with that passage. Subject to the
alternative argument to which I have yet to refer the present
was a contract where reference dates continued to occur. It
was therefore a case where the only non contractual limit to
occurrence of reference dates was that which flowed from
s 17(4) of the Act, the equivalent of the New South Wales
s 13(4).
However, it is in my judgment reasonably clear that his Honour
in saying that successive payment claims do not necessarily
have to be in respect of additional work was not saying that
successive payment claims may be identical. That is because
payment claims may include not only work but claims for goods
and services and also claims for liability under section
33(3).
His Honours point was that the mere fact that work had ceased
did not mean that new claims in respect of new reference dates
could not arise. That, in fact, seems to have been what
happened in that case.
The various claims were not identical. There is, therefore,
in a situation such as that scope to apply both sub-s (5) and
sub-s (6) of s 17. Such a construction is, in my judgment,
-- 12 of 15 --
10072007 T16/NLT(BNE) M/T BRIS05 (Fryberg J)
13 ORDER
1
10
20
30
40
50
60
also consonant with s 12 of the Act. That section relates each
reference date to an entitlement to a progress payment.
This construction accords with the text of s 17(6) which
permits a previous claim to be included in a later one. It
seems to me that there is a one to one relationship between
the claim made and the reference date on which it is made.
That is not to say that the claim must include all work done
up to that date. If something is omitted from a claim, not
withstanding that it could have been claimed on a particular
reference date, there is no reason why it cannot be claimed on
the next reference date. Likewise anything further which
gives rise to a claim after the first of such reference dates,
may also be included in the next claim. Subsection 17(6)
permits also the inclusion of an amount which has been the
subject of a previous claim but that does not mean that a
previous claim can be the sole item included in the later
claim.
No case has been cited to me where such a claim was permitted.
To allow it seems to me to fly in the face of the words of
ss 12 and 17.
I do not read the judgment of the Court of Appeal in Falgatt
Constructions Pty Ltd v Equity Australia Corporation Pty Ltd
[2006] NSWCA 259 as departing from Brodin in any way.
-- 13 of 15 --
10072007 T(2)17/JB(BNE) M/T BRIS05 (Fryberg J)
14 ORDER
1
10
20
30
40
50
60
In Shellbridge Pty Ltd v Rider Hunt Sydney Pty Ltd [2005]
NSWSC 1152 Justice Barrett said of the equivalent sections:
"It is thus clear that section 13(5) precludes the
service of more than one payment claim in respect of any
one reference date but does not seek to preclude
cumulation of amounts in successive 'payment' claims. As
a result, if, in a case within section 8(2)(b), the claim
in respect of the first reference date is for $10,000,
which is not promptly paid, and there is then a claim for
$25,000 (inclusive of the first $10,000) in respect of
the second reference date, there is no overstepping of
the limit allowed by section 13(5)."
That is the situation to which I have referred as permissible
and I respectfully agree with what his Honour has said. What
distinguishes the present case in my judgment is the fact that
the second claim was identical to the first.
In my judgment therefore, the claim was not capable of
founding the jurisdiction of the adjudicator and consequently
the order made by him was invalid.
The alternative argument advanced on behalf of the Doolans was
that in any event clause 17.1 of the contract dealt expressly
with the question of a final claim. It was a section in the
contract which did terminate the running of reference dates.
Consequently, once a claim had been made in respect of that
clause, no further claim under the Act was possible, there
being no further reference dates occurring.
That argument is attractive on its face. Mr Bickford, for
Rubikcon, submitted that it failed because clause 17.1 was
inconsistent with the schedule setting out method B to which I
-- 14 of 15 --
10072007 T(2)17/JB(BNE) M/T BRIS05 (Fryberg J)
15 ORDER
1
10
20
30
40
50
60
have referred or, if not inconsistent when read with that
schedule, meant that the time for the final claim had to be
calculated in accordance with method B with the result that
there could be repeated reference dates.
It is unnecessary, finally, to determine the correctness of
that argument. I do not see the provisions of the contract as
being inconsistent with the Act in that regard.
I will hear the parties on the question of the form of the
order and also in relation to what should happen with regard
to the filing of the adjudication certificate in this Court.
-----
-- 15 of 15 --