Abel Point Marina (Whitsundays) Pty Ltd v O'Brien & Anor [2007] QSC 91 [2008] 2 Qd R 396
SUPREME COURT OF QUEENSLAND
CITATION: ACN 060 559 971 Pty Ltd v O’Brien & Anor [2007] QSC 91
PARTIES: ACN 060 559 971 PTY LTD (ACN 060 559 971) (formerly
ABEL POINT MARINA (WHITSUNDAYS) PTY LTD)
(applicant)
v
JOHN O’BRIEN
(first respondent)
and
SEA-SLIP MARINAS (AUST) PTY LTD (ACN 103 644
640)
(second respondent)
FILE NO/S: BS51 of 2007
DIVISION: Trial
PROCEEDING: Application for statutory order of review and application for
review
DELIVERED ON: 19 April 2007
DELIVERED AT: Brisbane
HEARING DATE: 1-2 March 2007
JUDGE: Mullins J
ORDER: Orders to be determined after further submissions from
the parties.
CATCHWORDS: ADMINISTRATIVE LAW – JUDICIAL REVIEW –
GROUNDS OF REVIEW – ERROR OF LAW – application
for judicial review of decision of adjudicator made under
Building and Construction Industry Payments Act 2004 (Qld)
– where contractor’s claim for costs of delay or disruption
allowed by adjudicator – where claim made under clause of
the building contract – where liability of principal for delay
or disruption costs necessarily incurred by contractor by
reason of the delay was expressed in the relevant clause as
dependent on the grant of an extension of time for delay or
disruption caused by the principal, the superintendent, or
those under the control of the principal or the superintendent
– where adjudicator construed the relevant clause in such a
way that did not require a determination of what extensions
of time for the principal’s delay should have been granted
under the building contract – where adjudicator erred in
construction of relevant clause of the building contract
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – THE CONTRACT –
-- 1 of 17 --
2
CONSTRUCTION OF PARTICULAR CONTRACTS AND
IMPLIED CONDITIONS – OTHER MATTERS –
construction of clause in building contract making principal
liable for delay or disruption costs incurred by contractor –
where the principal’s liability for delay or disruption costs
was expressed in the relevant clause as dependent on the
grant of an extension of time for delay or disruption caused
by the principal, the superintendent, or those under the
control of the principal or the superintendent – where liability
of principal for delay or disruption costs required
determination of what extensions of time for the principal’s
delay should have been granted under the building contract
Building and Construction Industry Payments Act 2004, s 13,
s 17, s 21, s 25, s 26, s 27, s 99
Judicial Review Act 1991, s 4, s 30
Abacus Funds Management Ltd v Davenport [2003] NSWSC
1027, considered
Abel Point Marina (Whitsundays) Pty Ltd v Uher [2006] QSC
295, considered
Australian Broadcasting Tribunal v Bond (1990) 170 CLR
321, considered
Coordinated Construction Co Pty Ltd v JM Hargreaves
(NSW) Pty Ltd (2005) 63 NSWLR 385, followed
John Goss Projects Pty Ltd v Leighton Contractors Pty Ltd
[2006] NSWSC 798, followed
Rothnere Pty Ltd v Quasar Constructions NSW Pty Ltd
[2004] NSWSC 1151, followed
State of Queensland v Epoca Constructions Pty Ltd [2006]
QSC 324, followed
Thiess Watkins White Construction Ltd v Commonwealth of
Australia (1992) 14 BCL 61, considered
COUNSEL: RA Holt SC and SA McLeod for the applicant
G Inatey SC and DT Miller for the second respondent
SOLICITORS: Allens Arthur Robinson for the applicant
McMahons National Lawyers for the second respondent
[1] MULLINS J: The applicant applies for a statutory order of review and review of
the adjudication of the first respondent dated 20 December 2006 under the Building
and Construction Industry Payments Act 2004 (“the Act”). The first respondent
determined that the applicant pay as the progress payment an amount of
$2,628,364.74 (including GST) to the second respondent (“SSM”).
The contract and the claim
[2] The applicant and SSM entered into a contract in December 2004 for the design and
construction by SSM for the applicant of stages 2 and 3 berths and ancillary works
at the Abel Point Marina, Airlie Beach. The contract incorporated General
-- 2 of 17 --
3
Conditions of Contract AS4300-1995. The date for practical completion was shown
as 1 December 2005. By late 2005 the parties were in dispute and, after
negotiations, entered into a document described as “Agreement for Completion of
Works” dated 14 December 2005 which has been referred to by the parties as the
December Variation Agreement (“DVA”). Clause 8.0 of the DVA stated:
“[The applicant] shall accept completion by the 31st March 2006,
however earlier completion is encouraged.”
[3] SSM served a voluminous payment claim progress claim number 15 in the amount
of $3,425,854.53 (including GST) on the applicant on 31 October 2006. The
applicant served a detailed payment schedule in response on 14 November 2006
together with the superintendent’s payment certificate number 14 that was
responsive to SSM’s progress claim number 15. The amount that the applicant
proposed to pay to SSM in respect of the payment claim was nil. SSM lodged an
application for adjudication on 28 November 2006 with an authorised nominating
authority and the first respondent accepted an appointment as adjudicator on 30
November 2006. The payment claim together with supporting material and
submissions and the payment schedule were contained in six large folders that SSM
provided to the first respondent. The applicant’s adjudication response was lodged
on 6 December 2006. As required by s 25(3) of the Act, the first respondent
decided the adjudication application by making his decision and giving the reasons
for the decision by 20 December 2006. The first respondent’s decision and reasons
comprises 20 pages. I will refer to this decision and reasons by using the page
numbers of the document as prepared by the first respondent.
The first respondent’s decision
[4] The payment claim contained 24 items. Items 1 to 13 and 15 to 18 were claims
dealt with by another adjudicator, Mr Uher, in a previous adjudication dated 17
August 2006. He had decided that SSM was entitled to payment of $435,431.84 of
the amount claimed in payment claim number 11 served on 30 June 2006. Mr
Uher’s adjudication was the subject of an application for statutory order for review
that was dismissed by Wilson J: Abel Point Marina (Whitsundays) Pty Ltd v Uher
[2006] QSC 295 (“Abel Point No 1”). SSM submitted to the first respondent that
Mr Uher’s decision could not be reviewed, as the value of the items decided by him
had not changed since he made his decision. The first respondent accepted this
submission (at p 9) and decided not to review or revalue Mr Uher’s valuation of the
claims before him, but stated (at p 9) that if he were wrong and the amount
adjudicated by Mr Uher was able to be reviewed, he was “satisfied that Mr Uher’s
Decision in respect of the deductions made by the [applicant], including his findings
as to practical completion and liquidated damages, was correct in the light of the
matters he was then dealing with.”
[5] The primary focus of the first respondent’s decision was item 23 of the payment
claim which was the claim for delay and disruption costs in the amount of
$1,993,575.36 (plus GST). SSM claimed that dredging carried out on behalf of the
applicant caused SSM to be delayed from the original date for practical completion
of 1 December 2005 through to 6 September 2006. Both parties made submissions
to the first respondent based on the decision of the New South Wales Court of
Appeal in Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd
(2005) 63 NSWLR 385 (“Hargreaves”). The applicant submitted to the first
respondent that SSM was not entitled to claim under the Act any amount for “delay
-- 3 of 17 --
4
and disruption” where such claim was in reality damages for alleged breach of
contract and not an amount due for construction work. The first respondent applied
(at p 12) the statement made by Hodgson JA in Hargreaves at 397 [41]:
“… any amount that a construction contract requires to be paid as
part of the total price of construction work is generally, in my
opinion, an amount due for that construction work, even if the
contract labels it as ‘damages’ or ‘interest’ … .”
and concluded (at p 12) that SSM’s claim for delay and disruption did fall within
the description of an amount that was due for construction work.
[6] Although the first respondent observed (at p 12) that “delay costs are only payable if
there is an entitlement to an extension of time (EOT) as a result of some general act
or omission of the [applicant] or its agents”, he also stated (at p 12):
“I do not think that a claim by a contractor under clause 36 is
sustainable only where the Superintendent has granted an EOT under
clause 35.5 and that granted EOT qualifies in some way the ‘costs as
are necessarily incurred by the Contractor by reason of the delay’.
Certainly, there is no such constraint under the Act and, if the
Contract restricts the operation of the Act in so far as restricting the
[SSM’s] rights to make claims for construction work, then section 99
operates to render such provisions void.”
[7] The first respondent dealt with the issue of whether the applicant caused any delay
or disruption to SSM and concluded (at p 13) that SSM “did suffer delay and
disruption as a result of, in particular, dredging activities in its work area which
continued throughout construction as a result of dredging processes and procedures
proving ineffective” for which SSM was not responsible. The first respondent did
not expressly identify the period of delay or disruption that was suffered by SSM
and was caused by the applicant or those under the control of the applicant.
[8] The next issue considered by the first respondent was whether SSM incurred the
costs it claimed as a result of the delay and disruption. The first respondent was
satisfied (at p 14) “that the delay and disruption caused to [SSM] would have led to
it incurring significant costs” and that “the cost items listed by [SSM] in the
Payment Claim are consistent with the type of expenses and costs one would expect
to find there”. The first respondent noted (at p 14) that, while the applicant
attempted to discredit SSM’s listed costs and their valuations, it did not provide an
alternative valuation, but maintained that SSM had no entitlement whatsoever.
[9] The first respondent accepted (at p 15) that the superintendent under the contract
failed to exercise his obligations to value claims as required by the contract and that
he did not exercise his obligations impartially so as to meet the requirements
imposed on him by clause 23 of the contract. The first respondent then referred (at
p 15) to the applicant’s assertion that the DVA was intended to preclude any
entitlement to delay costs prior to 14 December 2005 and that no extensions of time
have been granted since then for any delay or disruption caused by any of the events
referred to in clause 35.5(b)(i) of the contract. The first respondent stated at (at p
15):
“…I am satisfied that the [applicant] did grant an EOT at some point
for delay and disruption caused by the [applicant], whatever it says
about this now. As is clear from the submissions, what is in dispute
-- 4 of 17 --
5
is not what EOTs were granted or whether they were reasonable but
whether they were granted at all.”
[10] The first respondent referred (at p 16) to the fact that the DVA did not use the
expression “Practical Completion” and that it stated that “[the applicant] shall
accept completion by 31st March 2006”. The first respondent noted again (at p 16)
that Mr Uher decided that there was insufficient evidence that the date in the DVA
referred to the date for practical completion and that Mr Uher “was entitled to come
to that decision”. The first respondent then expressly accepted (at p 16) the
submissions made by SSM in the adjudication application that stated:
“There is nothing in the DVA about Practical Completion. The term
is not used. There is no mention of a Date for Practical
Completion…It does not say that [SSM] must bring the Works or
any portion to the stage of Practical Completion by 31 March 2006.”
The first respondent concluded (at p 18) that there was nothing in the DVA which
barred a claim for delay or disruption based on events which occurred prior to 15
December 2005 or required clause 36 of the contract to be read subject to the DVA.
[11] The first respondent then repeated (at p 18) that he was “satisfied that delay and
disruption and extra costs resulting from these have been incurred by [SSM] and
that the responsibility for such delay and disruption lies with the [applicant].”
[12] The first respondent dealt with the parties’ submissions on the operation of clause
36 of the contract as follows (at p 18):
“[SSM] further submits that it is not a matter for me as Adjudicator
to consider ‘what extensions of time the Superintendent granted or
even should have granted. The important issue is to determine what
delay and disruption was caused by the [applicant]. The measure of
delay or disruption is not the same as the measure of extensions of
time’. I have read the [applicant’s] submissions in respect of this and
do not accept that [SSM’s] submission is tantamount to asking me to
disregard both the Act and the Contract. The submission merely
points out that whatever extensions of time were or were not granted
by the Superintendent, that is not material to and does not directly
govern actual delay and disruption caused or the actual costs of that
delay and disruption.”
[13] The first respondent then dealt with the cost of the delay and disruption caused by
the applicant (in respect of which he was satisfied that SSM was entitled to claim)
on the evidence that was put before him by the parties. The first respondent noted
(at p 19) that he was obliged under the Act to assess the value of the claim and that
he was “placed in a position of accepting the assessment of [SSM] or that of the
[applicant]; all or nothing so to speak”. The first respondent accepted (at p19)
SSM’s assessment of costs arising from the delay and disruption to the works.
[14] The adjudicated amount decided by the first respondent pursuant to s 26(1)(a) of the
Act of $2,628,364.74 was calculated as follows:
Amount of progress payment decided by Mr Uher $435,431.84
Item 23 delay and disruption costs $1,993,575.36
GST on the item 23 amount $199,357.54
Total $2,628,364.74
-- 5 of 17 --
6
[15] The applicant has paid the amount that was the subject of the adjudication by Mr
Uher. Instead of paying the balance of the adjudicated amount decided by the first
respondent, the applicant commenced this application and paid the sum of
$2,275,974.39 into court on 19 January 2007 to abide the order of the court. On 19
January 2007 the court made an order with the consent of the parties restraining
SSM until the final determination of this application or further order of the court
from taking any step to recover the moneys the subject of the first respondent’s
adjudication. That order was subsequently substituted with an undertaking by SSM
to the same effect.
Whether decision reviewable
[16] The applicant submits that the decision of the first respondent is reviewable under
the Judicial Review Act 1991 (“JRA”) as it satisfies the tests set out in paragraph (a)
of the definition of “decision to which this Act applies” in s 4 of the JRA. The
applicant submits that is consistent with the conclusion reached in other judgments
in the Trial Division of this Court including State of Queensland v Epoca
Constructions Pty Ltd [2006] QSC 324 (“Epoca”) at paragraphs [16] to [35] and JJ
McDonald & Sons Engineering Pty Ltd v Gall [2005] QSC 305 (cf Vis
Constructions Pty Ltd v Cockburn [2006] QSC 416 at [42]). Although SSM argued
the application on the assumption that the first respondent’s decision was
reviewable under the JRA as a decision of an administrative character made under
an enactment, it expressly preserved its position to argue otherwise on an appeal.
For the reasons given in Epoca, I consider that the first respondent’s decision is one
to which Part 3 of the JRA applies.
Nature of the first respondent’s decision
[17] The application must be considered in the context of the nature and purpose of the
decision making undertaken by the first respondent. The adjudication of disputes
under Division 2 of Part 3 of the Act occurs after a claimant under a construction
contract claims to be entitled to a progress payment and has served a payment claim
under s 17 of the Act. The conditions that must be satisfied before the claimant
makes an adjudication application as set out in s 21 of the Act. The adjudication
application must contain the submissions of the applicant. The relevant respondent
to the payment claim must give any response to the claimant’s adjudication
application at any time within the later of five business days after that respondent
has received a copy of the application or two business days after that respondent has
received notice of the adjudicator’s acceptance of the application. Under s 25(3) of
the Act an adjudicator is required to decide an adjudication application “as quickly
as possible” and within 10 business days after the earlier of the date on which the
adjudicator received the adjudication response or the date on which the adjudicator
should have received the adjudication response or within the further time the
claimant and the respondent may agree, whether before or after the end of the 10
business days. Under s 26(2) of the Act the adjudicator is restricted to considering
the matters that are specified in that provision in deciding an adjudication
application.
[18] The object of the Act and how the object is to be achieved are set out in ss 7 and 8
of the Act. The object of the Act was summarised in the Explanatory Notes for the
-- 6 of 17 --
7
relevant Bill as “to entitle certain persons who carry out construction work (or who
supply related goods or services) to a timely payment for the work they carry out
and the goods and services they supply” by “establishing a procedure for securing
progress payments to which a person becomes entitled … “. Under s 99 of the Act,
the provisions of the Act are given effect despite any attempt to contract out of the
provisions. Section 100 of the Act makes it clear that nothing in Part 3 of the Act
affects any right that a party to a construction contract may have under or in relation
to that contract and that nothing done under or for Part 3 of the Act affects any civil
proceedings arising under a construction contract (except to take into account any
payment made under Part 3).
[19] The Act was modelled on the New South Wales Building and Construction Industry
Security of Payment Act 1999 (“the NSW Act”). There have been numerous
decisions on the NSW Act in which observations have been made about the scheme
of the NSW Act and the role of the adjudicator which are equally applicable to the
Act. Bergin J referred to the “somewhat pressure cooker environment in which
adjudicators provide their determinations” in Shell Refining (Australia) Pty Ltd v A
J Mayr Engineering Pty Ltd [2006] NSWSC 94 at paragraph [27] and note
paragraph [26]. Einstein J observed in Lucas Stuart Pty Ltd v Council of the City of
Sydney [2005] NSWSC 840 at paragraph [13]:
“… the Act provides those who carry out construction work [or the
supply of related goods and services] under a construction contract to
access to a ‘fast track’ adjudication procedure whereby the amount of
such payments can be determined on an interim basis and enforced
immediately without prejudice to the right of the parties to have
disputes ultimately determined in accordance with ordinary litigious
procedures … .”
Similar observations on the Act were made by Wilson J in Abel Point No 1 at
paragraph [11]:
“The Act provides for progress payments to contractors whether or
not the relevant contract makes provision for progress payments and
establishes a procedure for the making and recovery of such claims
and their speedy adjudication where they are disputed. However, an
adjudication does not finally determine the rights of the parties in the
sense that a party may “claw back” progress payments which it is
forced to make through the adjudication process in subsequent civil
proceedings.” (footnotes omitted)
Grounds of review
[20] The applicant asserts that the first respondent erred in failing to review Mr Uher’s
decision and thereby erred:
(a) in determining that the applicant was not entitled to deduct the amount of
$250,000 (plus GST) for liquidated damages from any progress payment
due to SSM; and
(b) in failing to determine that the date for practical completion under the
contract was not 31 March 2006 as provided for in the DVA.
[21] The applicant also asserts that the first respondent erred in determining that the
amount of $1,993,575.36 (exclusive of GST) was all claimable as delay and
disruption costs under the contract.
-- 7 of 17 --
8
[22] In respect of each aspect of the first respondent’s decision that is the subject of this
application, the applicant relies upon the grounds of review of error of law, contrary
to law, improper exercise of power by failing to take into account relevant
considerations and unreasonableness.
The applicant’s claim for liquidated damages and the date for practical
completion
[23] Clause 35 of the contract covers practical completion. Clause 35.6 provides:
“If the Contractor fails to reach Practical Completion by the Date for
Practical Completion, the Contractor shall be indebted to the
Principal for liquidated damages at the rate stated in Annexure Part
A for every day after the Date for Practical Completion to and
including the Date of Practical Completion or the date that the
Contract is terminated pursuant to Clause 44, whichever first
occurs.”
Clause 35.7 of the contract specifies that the contractor’s liability under clause 35.6
is limited to the amount stated in Annexure Part A. The relevant amount is
$250,000.
[24] Clause 36 of the contract provides:
“Where the Contractor has been granted an extension of time under
Clause 35.5 for any delay or disruption caused by any of the events
referred to in Clause 35.5(b)(i), the Principal shall pay to the
Contractor such extra costs as are necessarily incurred by the
Contractor by reason of the delay.
Where the Contract has been granted an extension of time under
Clause 35.5 for any delay caused by any other event for which
payment of extra costs for delay or disruption is provided for in
Annexure Part A or elsewhere in the Contract, the Principal shall pay
to the Contractor such extra costs as are necessarily incurred by the
Contractor by reason of the delay.
Nothing in this Clause 36 shall—
(a) oblige the Principal to pay extra costs for delay or disruption
which have already been included in the value of a variation
or any other payment under the Contract;
or
(b) limit the Principal’s liability for damages for breach of
contract.
Clause 35.5(b)(i) of the contract covers delay or disruption caused by the principal,
the superintendent or an employee, consultant, other contractor or agent of the
principal or the superintendent.
[25] On this issue the applicant submits that the first respondent erred in relying on s 27
of the Act. The applicant submits that the set off that it sought to make for
liquidated damages could not be characterised as valuing construction work (within
-- 8 of 17 --
9
the meaning of s 27(1)(a) of the Act) and that therefore s 27(2) of the Act did not
apply to Mr Uher’s findings as to the date of practical completion and liquidated
damages. The first respondent did not limit his refusal to depart from Mr Uher’s
decision on the applicant’s claim to liquidated damages to the application of s 27 of
the Act. To the extent that the first respondent relied on the alternative reason that
Mr Uher’s decision was correct, the applicant submitted that the first respondent
misconstrued Mr Uher’s reasons. The applicant argues that it was plain that Mr
Uher formed the opinion on the material before him that he was unable to determine
the date for practical completion and, consequently, the applicant’s claim for
liquidated damages and therefore he did not determine those issues. The applicant
argues that because the first respondent characterised Mr Uher’s reasons on these
issues as findings, he failed properly to consider the applicant’s claim for liquidated
damages and erred in failing to take into account the applicant’s submissions in its
adjudication response as to why its claim for liquidated damages should be allowed.
[26] The applicant argues that the restriction found in s 27(2) of the Act which prevents
another adjudicator from departing from the value of any construction work carried
out under a construction contract as decided for the purpose of an earlier
adjudication applies only to that part of the earlier adjudicator’s decision that is
concerned with valuing the relevant construction work and does not extend to that
part of the earlier adjudicator’s decision that might involve determining whether
there should be any deductions from the valuation made by the earlier adjudicator of
the relevant construction work.
[27] SSM seeks to support the first respondent’s application of s 27 of the Act to Mr
Uher’s decision not to allow the applicant’s deduction for liquidated damages. SSM
argues that Mr Uher did undertake a valuation exercise that dealt with, but rejected,
the applicant’s liquidated damages claim of $250,000. It is put that Mr Uher carried
out this valuation in accordance with the applicant’s submission to him that the
contract required the amount payable to SSM to be a net amount after the deduction
of any amount due for liquidated damages. Because the deduction claims were
rejected by Mr Uher, SSM submits that Mr Uher valued that claim at $Nil and that
s 27(2) of the Act operated in respect of that valuation for the purpose of the
adjudication application before the first respondent, unless the applicant could
satisfy the first respondent that the value of the work had changed since Mr Uher’s
decision.
[28] SSM also claims that the first respondent did reconsider the claim for liquidated
damages himself, but came to the same conclusion as Mr Uher. SSM argues that
the first respondent’s reasons disclose that he found as a matter of fact that there had
been delays and that those delays to the works required of SSM were a consequence
of acts or omissions of the applicant which had the necessary consequence that the
applicant could not make out its claim for liquidated damages.
[29] On this aspect of the first respondent’s decision, the submissions of the parties made
on this application require the following matters to be considered:
(a) did the first respondent err in relying on s 27 of the Act? and
(b) if so, did the first respondent consider the applicant’s claim for
liquidated damages and the related claim as to the date for practical
completion on the material that was before the first respondent?
[30] Section 27 of the Act provides:
-- 9 of 17 --
10
“27 Valuation of work etc. in later adjudication application
(1) Subsection (2) applies if, in deciding an adjudication
application, an adjudicator has, under section 14,
decided—
(a) the value of any construction work carried out
under a construction contract; or
(b) the value of any related goods and services supplied
under a construction contract.
(2) The adjudicator or another adjudicator must, in any later
adjudication application that involves the working out of
the value of that work or of those goods and services,
give the work, or the goods and services, the same value
as that previously decided unless the claimant or
respondent satisfies the adjudicator concerned that the
value of the work, or the goods and services, has
changed since the previous decision.”
[31] Rothnere Pty Ltd v Quasar Constructions NSW Pty Ltd [2004] NSWSC 1151
(“Rothnere”) and John Goss Projects Pty Ltd v Leighton Contractors Pty Ltd [2006]
NSWSC 798 (“Goss Projects”) considered s 22(4) of the NSW Act which is the
provision equivalent to s 27 of the Act.
[32] In Rothnere McDougall J noted at paragraph [43] that a determination under the
NSW Act may involve both questions of quantification and questions of entitlement
or it may involve one or the other. McDougall J then stated at paragraph [44]:
“In my judgment, s 22(4) itself makes it clear that an adjudication
determination need not necessarily include the valuation of
construction work: the use of the introductory word "If" makes this
clear. Subsection (4) therefore only applies where a component of a
determination - that is to say, in terms of s 22(1)(a), of the
determination of the amount of the progress payment (if any) to be
paid - includes a determination of the value of construction work.
Where it does, then subs (4) applies. Where it does not (either
because the work has not at all been valued before or because the
value of the work has changed) then s 10(1) applies. But there is
nothing in these considerations that indicates that the phase
"construction work" when used in s 22(4) should be construed in any
way other than the way that it is used throughout the Act.”
[33] The issue of whether McDougall J’s construction of s 22(4) of the NSW Act was
correct arose in Goss Projects. As a matter of construction of the NSW Act,
McDougall J determined at paragraph [40] in Goss Projects that it was clear “that
there is a distinction between the calculation of the amount of a progress payment
(which is, ultimately, what the adjudicator is required to do) and the valuation of
construction work”.
[34] I respectfully agree with the approach to construction of s 22(4) of the NSW Act of
McDougall J in Rothnere and Goss Projects. The right under clause 35.6 of the
contract for the applicant to claim liquidated damages at the rate stated in Annexure
Part A of the contract is not referable to any particular item of construction work
-- 10 of 17 --
11
under the contract, but affects the calculation of the amount due by the principal to
the contractor (or the amount due by the contractor to the principal). Under clauses
35.6 and 42.1 of the contract liquidated damages can be deducted from any payment
otherwise due by the principal to the contractor. Relevantly, clause 42.1 of the
contract treats an amount due by the contractor to the principal, such as a deduction
for liquidated damages, as distinct from the value of work carried out by the
contractor in the performance of the contract. The claim by the applicant to
liquidated damages on the adjudication application before Mr Uher was relevant to
the entitlement of SSM to the quantum of the progress payment that was determined
by Mr Uher, but not the value of any construction work carried out under the
contract that was determined by Mr Uher. The first respondent erred in law in
relying on s 27 of the Act as a reason for not departing from Mr Uher’s decision on
the applicant’s claim to liquidated damages.
[35] It is therefore necessary to decide whether the first respondent did, in fact, consider
the applicant’s submissions on its claim to deduct liquidated damages in reaching
his conclusion that he would not depart from Mr Uher’s decision. The
superintendent’s deduction for liquidated damages in payment certificate number 14
was based on identical reasons to those which the superintendent had advanced in
making the deduction in respect of the claim made by SSM in its payment
certificate that was before Mr Uher.
[36] Mr Uher rejected the deduction for liquidated damages on the basis that there was
insufficient evidence before him to allow him to reach that conclusion. The
materials and submissions before the first respondent were not limited to those that
were before Mr Uher. It was for the first respondent to decide that issue on the
basis of the materials and submissions before him. He has not done so to the extent
that his reasons merely endorsed Mr Uher’s conclusion that there was insufficient
material before Mr Uher to allow the deduction for liquidated damages.
[37] This does not dispose of the argument of SSM that the first respondent could not
reach the conclusion that he did on the entitlement of SSM to costs for delay or
disruption, unless he impliedly rejected the applicant’s deduction for liquidated
damages, as according to counsel of SSM they were “inextricably related” and
“mutually exclusive”. As it was expressed during oral submissions (at Transcript p
48), counsel for SSM stated that the first respondent “determined the entitlement to
extensions of time from the 1st of December 2005 until 6 September 2006, and as a
necessary consequence of that would not deduct any liquidated damages in respect
of any claim for liquidated damages within that period.” It is necessary to analyse
the first respondent’s decision on SSM’s claim for costs for delay or disruption,
before considering whether that part of the first respondent’s decision addressed the
applicant’s submissions on the date for practical completion and the deduction for
liquidated damages.
SSM’s claim for delay and disruption
[38] The applicant submits that the first respondent erred in deciding the question of
delay and disruption without regard to clauses 35.5 and 36 of the contract. The
parties differed markedly in their submissions on the significance of clause 36 and
their respective constructions of clause 36 that were advanced to the first respondent
on the extent and nature of the satisfaction of the pre-condition expressed in clause
36 that gives rise to a claim for delay or disruption costs under clause 36. The
-- 11 of 17 --
12
applicant submits that the first respondent adopted the construction of clause 36 of
the contract put forward by SSM and that was an error of law. The applicant
contends that the reference by the first respondent (at pp 12 and 18 of his reasons) to
an entitlement of SSM under the Act to claim the costs of delay and disruption,
without making reference to the contract, was also an error of law.
[39] The applicant argues that the first respondent failed to make any assessment of an
entitlement of SSM to extensions of time for the period in respect of which costs for
delay or disruption were claimed by SSM. The applicant argues that as the first
respondent was satisfied that the superintendent had abrogated his role under the
contract, the first respondent should have undertaken the task of the superintendent
of determining what extensions of time should have been granted under clause
35.5(b)(i): Abacus Funds Management Ltd v Davenport [2003] NSWSC 1027 at
paragraphs [35]-[39]. The applicant also argues that in the acceptance by the first
respondent of SSM’s assessment of its costs arising from the delay and disruption to
the works, the first respondent failed to address the amount claimed on its merits,
notwithstanding that the applicant had not put forward an alternative valuation.
[40] SSM argues that the only question that was before the first respondent, because of
the way that the applicant had framed its adjudication response, was whether the
DVA had resulted in the waiver of any right by SSM to bring claims based on
events which occurred prior to 14 December 2005. SSM argues that the applicant
did not frame the issue before the first respondent on costs for delay or disruption in
the manner that it now contends which is based on the construction of clause 36.
[41] Although in its adjudication application SSM relied on clause 42.1 of the contract as
entitling SSM to pursue by way of progress payment its claim against the applicant
for costs of delay and disruption, SSM did not avoid clause 36 and made
submissions to the first respondent on the application and construction of clause 36.
On the hearing of this application, SSM’s submissions (both written and oral)
accepted that clause 36 of the contract was relevant to the determination of SSM’s
claim for costs of delay or disruption. Consistent with that approach, SSM argues
that, in any case, what the first respondent did, in effect, was decide that the
superintendent had not exercised his powers fairly and that the first respondent
would determine the entitlement of SSM to extensions of time for delays caused by
events within clause 35.5(b)(i). SSM therefore submits (at Transcript p 67) that the
adjudicator did find an entitlement of SSM to an extension of time from 1
December 2005 to 6 September 2006. The interpretation given by counsel for SSM
to the first respondent’s reasons reflects this submission. Counsel for SSM refers to
the first respondent’s statement (at p 15 of his reasons) that “what is in dispute is not
what EOTs were granted or whether they were reasonable but whether they were
granted at all” and submits (at Transcript p 68) that what the first respondent was
saying was that whether the superintendent granted 10 days or 15 days did not
matter, because the first respondent was now dealing with that issue.
[42] SSM provided particulars in its payment claim of the calculation of the claim of
$1,993,575.36 for delay or disruption costs. This amount was broken down into
four components in the payment claim: extended contract preliminaries of
$1,090,300, disruption costs of $97,537.50, barge and crane downtime of
$174,352.21 and loss of recovery of overheads and profit during prolongation
period of $631,385.65. The loss of overheads and profit claim was calculated by
applying the Hudson formula (see Hudson’s Building and Engineering Contracts,
-- 12 of 17 --
13
11th ed, paragraph 8.182), based on the contract period being prolonged by a further
40 weeks from the original date for practical completion claimed by SSM as 1
December 2005 until the estimated revised date for practical completion claimed by
SSM as 6 September 2006. The rationale for this claim was that SSM had to
maintain its supervision, labour and site establishment resources on the project and
was unable to reallocate those same resources to more profitable work elsewhere.
SSM therefore claimed that it had been denied the head office overhead and profit
recovery of 7.4% that would have accrued over such period, but for the delay.
Construction of clause 36 of the contract
[43] It was a fundamental step in the process of determining SSM’s claim for delay or
disruption costs that the first respondent had to consider the terms of clause 36 of
the contract. This was mandatory under s 26(2)(b) of the Act. It was also in
accordance with Hargreaves that SSM had to rely on the relevant provision of the
contract that allowed it to pursue in its payment claim the costs of delay or
disruption attributable to the applicant as part of the calculation of the value of
construction work carried out under the contract.
[44] The construction for which the applicant contended before the first respondent (and
also on this application) was unequivocally articulated in a number of places in the
adjudication response (such as p 573 of the affidavit of AJ Ritchie filed 3 January
2007) as follows:
“Before [SSM] is entitled to be paid delay and disruption costs under
the first paragraph of cl 36, [SSM] must have an entitlement under
the contract to an extension of time under cl 35.5. There would be
little point in having this pre-condition unless it was to circumscribe
the amount of the delay and disruption costs payable. This is made
clear by the fact that [SSM] is to be paid the ‘costs as are necessarily
incurred by the Contractor by reason of the delay’, the delay referred
to is the delay for which the extension of time was granted.”
The arguments that the applicant put forward to the first respondent as to why SSM
was not entitled to any costs for delay or disruption under clause 36 of the contract
(ie the claim was in reality damages for alleged breach of contract and all delays had
been resolved as a result of the DVA) were predicated on the application of the
construction of clause 36 of the contract put forward by the applicant to the first
respondent.
[45] SSM’s construction was that provided any extension of time for delay or disruption
caused by an event referred to in clause 35.5(b)(i) of the contract had been granted,
then SSM was entitled to costs that it incurred by reason of delay that could be
attributed to events referred to in clause 35.5(b)(i), even if the extension of time had
not been granted for all that delay. This was articulated in SSM’s submissions in
support of the adjudication application as follows (at p 10):
“If [SSM] was granted an extension of time to the end of March
2006 then [SSM] was granted an extension of time for any delay or
disruption caused by the events referred to in Clause 35.5(b)(i). The
number of days extension on account of the delay or disruption is
irrelevant for purposes of clause 36. The entitlement under clause 36
is not proportional to the number of days extension granted.”
-- 13 of 17 --
14
and also as follows (at p 12):
“[SSM] respectfully submits that there is no purpose to be served by
considering what extensions of time the Superintendent granted or
even should have granted. The important issue is to determine what
delay and disruption was caused by the respondent. The measure of
the delay or disruption is not the same as the measure of extensions
of time.”
[46] The first respondent’s determination of the claim for costs for delay or disruption
was based on the first respondent’s acceptance of SSM’s construction of clause 36
of the contract. That was reflected by the paraphrasing by the first respondent (at p
18 of his reasons) of the submissions made by SSM (including that last quoted in
the preceding paragraph) when rejecting the applicant’s criticism of these
submissions and the express rejection by the first respondent (at p 12 of his reasons)
of the construction advanced by the applicant that required as a pre-condition to the
claim for delay or disruption costs under clause 36 that SSM was granted an
extension of time under clause 35.5.
[47] The construction contended for by the applicant of clause 36 of the contract before
the first respondent and on this application must be correct. The condition within
the first paragraph of clause 36 that makes the principal liable to pay to the
contractor “such extra costs as are necessarily incurred…by reason of the delay” is
that delay or disruption has been caused by the principal or the superintendent or
any of their employees, agents or other contractors for which an extension of time
has been granted under the contract. The delay for which the principal becomes
liable to the contractor to pay costs is the same delay that is the subject of the
extension of time that must be granted as a pre-condition for the principal’s liability
for the costs of the delay. It is a literal construction, which lacks logic, to suggest
that any extension of time for delay caused by an event referred to in clause
35.5(b)(i) gives rise to a liability on the part of the principal for costs incurred by
the contractor as a result of all delays caused by the principal (whether an extension
of time has been granted or not).
[48] It cannot be concluded that the first respondent impliedly identified the period of
delay caused by the applicant, the superintendent or those under their control for
which the superintendent should have granted extensions of time under clause
35.5(b)(i). Although the first respondent did accept (at p 15 of his reasons) that the
superintendent had not exercised his powers fairly under clause 23.1 of the contract,
the first respondent did not undertake the exercise of deciding what extensions of
time the superintendent should have granted for delay caused by events under clause
35.5(b)(i). It is not surprising that the first respondent did not do that in the light of
his acceptance of the submission made by SSM that it did not matter what period of
extension of time had been granted for delay in respect of the costs sought under
clause 36 as long as there had been the grant of an extension of time for delay
caused by the applicant.
[49] SSM’s submissions to the first respondent caused him to err in the construction and
application of clause 36 of the contract in a most significant way. It had the result
that the first respondent did not engage in the essential step in the process of
determining what extensions of time the superintendent should have granted under
clause 35.5 for delay or disruption caused by any of the events referred to in clause
35.5(b)(i). It also had the consequence that the first respondent did not assess the
-- 14 of 17 --
15
costs for delay or disruption in accordance with clause 36 of the contract, as the
assessment depended on the determination of the period of the delay or disruption
which was caused by the principal, the superintendent or those under the control of
the principal or the superintendent for which SSM was entitled to be granted an
extension of time under clause 35.5(b)(i).
[50] In view of the conclusion that I have reached about the first respondent’s error in the
construction and application of clause 36 of the contract, it is not necessary to deal
with the applicant’s claim that the first respondent erred in law in treating SSM as
having an entitlement under the Act to claim the costs of delay or disruption,
without reference to the mechanism contained in the contract for the assessment of
delay and disruption costs. I will, however, make brief observations on this
argument which is connected with the first respondent’s error in respect of clause
36. The applicant pointed to the first respondent’s statement (at p 12 of his reasons)
which was to the effect that the pre-condition in the first paragraph of clause 36
relied on by the applicant amounted to a constraint on SSM’s right under the Act to
make claims for construction work and that s 99 of the Act rendered such pre-
condition void. The decision in Hargreaves does not give a contractor the right to
include in its payment claim under the Act a claim for costs of delay or disruption
caused by the principal as part of the value of construction work carried out under
the contract, in the absence of a contractual right for the contractor to pursue such
claim for costs of delay or disruption caused by the principal. The first respondent
erred in stating that s 99 of the Act rendered the pre-condition in clause 36 of the
contract void.
[51] SSM seeks a favourable exercise of the discretion that the court has under s 30 of
the JRA whether to grant relief on an application for a statutory order of review,
when a ground of review is established. Although an adjudicator’s decision is made
as part of a process that is intended to determine the quantum of progress payments
paid under a contract for construction work in a timely and cost effective way,
pending any ultimate determination between the parties of their legal rights, the
error of law on the construction of clause 36 was of such significance in the first
respondent’s decision making that it is appropriate to exercise the discretion to set
aside at least that part of the first respondent’s decision that resulted in the inclusion
of item 23 delay and disruption costs and GST on the item 23 amount (in total the
sum of $2,192,932.90) in the adjudicated amount: Australian Broadcasting
Tribunal v Bond (1990) 170 CLR 321, 353.
Other matters
[52] It follows from the error of law made by the first respondent in the construction and
application of clause 36 of the contract and that the first respondent’s decision on
that aspect must be set aside, that it is unnecessary to dispose of the arguments
addressed to the assessment of the costs of delay or disruption. I will make some
observations, however, on the applicant’s submission on the component of SSM’s
delay or disruption costs attributed to loss of recovery of overheads and profit
during the period between 1 December 2005 and 6 September 2006 of $631,385.65
that was calculated by applying the Hudson formula. The submission made by the
applicant was that damages calculated according to the Hudson formula are not
“costs” within the meaning of that word in clause 36 of the contract and can
therefore not be included in a progress payment adjudicated under the Act, applying
Hargreaves.
-- 15 of 17 --
16
[53] Hargreaves concerned clause 34.9 of the subcontract that was an amended version
of AS4903-2000 which stated:
“For every day the subject of an EOT for a Compensable Cause and
for which the Subcontractor gives the Subcontract Superintendent a
claim for delay damages pursuant to sub clause 41.1, damages
certified by the Subcontract Superintendent under sub clause 41.4
shall be due and payable to the Subcontractor.”
Hodgson JA at paragraph [42] in Hargreaves found that under that provision delay
damages were payable only if an EOT is for a compensable cause and they were not
of their nature damages for breach, but rather additional amounts which may
become due and payable under the contract. Hodgson JA then stated at paragraph
[44]:
“If they represent off-site costs (such as office overheads) or other
on-site costs, it may be a question of fact and degree whether they
are for construction work carried out or for related goods and
services supplied. They would in my opinion properly be regarded at
least as part of the price for the totality of the construction work
when completed. And it would seem artificial to say that they are
excluded from the Act if they are not referable to work that has
already been carried out, particularly when s 9(b) refers to the value
of construction work undertaken to be carried out and related goods
and services undertaken to be supplied.”
[54] There is a distinct difference between clause 36 of the contract and the provision
that was considered in Hargreaves in that clause 36 makes the principal liable to
pay to the contractor “such extra costs as are necessarily incurred” by the contractor
by reason of the delay for which the contractor has been granted an extension of
time for any event referred to in clause 35.5(b)(i).
[55] Clause 36 of the contract is concerned with payment by the principal during the
course of the contract to compensate the contractor for costs incurred as a result of
the delay, where the conditions specified in clause 36 have been satisfied. Clause
36 does not close off rights that the contractor may have to sue the principal for
damages for breach of contract. The quantum of the progress payment that can be
determined by an adjudicator under the Act is limited by s 13 of the Act. The use of
the expression “such other costs as are necessarily incurred…by reason of the
delay” suggests that the payment for which the principal may be liable under clause
36 of the contract does not extend to recovery of a contribution to off site overheads
(which would have been incurred by the contractor in any case) and loss of profits
from other opportunities that are unable to be utilised because of the delay. This is
consistent with the observation made by Giles J in Thiess Watkins White
Construction Ltd v Commonwealth of Australia (1992) 14 BCL 61, 77 that “loss
suffered by reason of delay is not the same as extra costs incurred by reason of
delay”. The provision that was considered in that case was “extra costs
incurred…by reason of or as a result of or arising from the exercise by the
superintendent of the power to grant or allow any extension of time”.
[56] If it had been necessary to consider the reliance on the Hudson formula in
calculating one of the components of the delay and disruption costs, I would have
accepted the applicant’s submissions on that component because of the terms of
clause 36.
-- 16 of 17 --
17
Conclusion on claim for liquidated damages and date for practical completion
[57] Subject to SSM’s arguments that the applicant’s claim for liquidated damages was
taken care of by the first respondent’s determination on the costs of delay and
disruption, I was satisfied that the first respondent failed to consider the applicant’s
claim for liquidated damages (and the related claim as to the date for practical
completion) on the material that was before the first respondent and had therefore
made an error of law. My conclusion on the error of law made by the first
respondent in the construction and application of clause 36 of the contract has the
result that SSM cannot rely on the first respondent’s determination of the costs for
delay or disruption as resolving the issue of liquidated damages in favour of SSM.
[58] The applicant’s claim for liquidated damages in the payment schedule was sought in
general terms, in the sense that the applicant claimed that in the event that any
moneys were found by the first respondent to be owing by the applicant to SSM
under the contract, the applicant claimed an entitlement to deduct from such moneys
the amount of $250,000 which the applicant claimed as liquidated damages under
clause 35.6 of the contract, as a result of the claimant’s delay in achieving practical
completion. The claim of liquidated damages cannot be resolved without the
determination of the date for practical completion. As the applicant has paid the
adjudicated amount decided by Mr Uher, the claim for liquidated damages (and the
date for practical completion) will remain relevant in relation to the finalisation of
SSM’s claim that was before the first respondent.
Orders
[59] The applicant seeks an order setting aside the first respondent’s adjudication
decision. The only two components of the adjudicated amount determined by the
first respondent were the adjudicated amount decided by Mr Uher and the costs for
delay and disruption. There is no utility in setting aside that part of the decision that
relates to Mr Uher’s adjudicated amount, because it has been paid.
[60] Subject to any further submissions that the parties make on the terms of the orders, I
consider that the first respondent’s decision dated 20 December 2006 on item 23
delay and disruption costs (including GST) should be set aside. I will hear the
parties as to the terms of the orders that should be made to reflect the conclusions
that I have reached and what consequential orders are appropriate, including
whether SSM’s claim for costs of delay and disruption and the applicant’s claim in
respect of the date for practical completion and the deduction for liquidated
damages should be referred to the first respondent for further consideration,
according to law. I will also hear submissions of the parties on the question of
costs.
-- 17 of 17 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2007/091