Biloela Lakelands Developments Group Pty Ltd & Anor v Danbulla Developments Pty Ltd & Ors [2007] QSC 62
1
[2007] QSC 062
SUPREME COURT OF QUEENSLAND
CIVIL JURISDICTION
BYRNE J
No 9697 of 2006
BILOELA LAKELANDS DEVELOPMENT
GROUP PTY LTD
(ABN 85 111 672 827)
First Plaintiff
and
RHT DEVELOPMENTS PTY LTD
(ACN 108 580 801) Second Plaintiff
and
DANBULLA DEVELOPMENTS PTY LTD
(ACN 092 014 358) First Defendant
and
REDDY DEVELOPMENTS PTY LTD
(ACN 091 192 979) Second Defendant
and
TTF DEVELOPMENTS PTY LTD
(ACN 117 666 949) Third Defendant
BRISBANE
..DATE 17/01/2007
JUDGMENT
-- 1 of 8 --
2 JUDGMENT
1
10
20
30
40
50
60
HIS HONOUR: This is an application for security for costs.
The plaintiffs are corporations. One of them, it is
effectively conceded, will be unable to pay any substantial
proportion of the defendants' costs if the plaintiffs' case is
lost. The second plaintiff, whose interests appear to be
identical with those of the first plaintiff, however, resists
the application on the footing that the prescribed tests in
the Uniform Civil Procedure Rules and in the Corporations Law
have not been satisfied.
The plaintiff whose capacity to meet the defendants' costs,
should the defendants succeed is in issue is RHT Developments
Proprietary Limited. This corporation has, as its substantial
assets, land near Biloela which is being developed by
subdivision and construction of houses. The expectation is
that, over time, there will be ten houses and one lot of
common property on the subdivisional development.
The quantum of the security for costs sought to the first day
of trial is $100,000.
The application has been argued on a common assumption, which
seems reasonable in the circumstances, that the costs the
plaintiffs are likely to incur in prosecuting their claim to
trial will be about $150,000. Additionally, if the
plaintiffs' case is lost, it appears to be common ground that
the plaintiffs will be liable to pay the defendants another
approximately $130,000. On this basis, if the case is taken
-- 2 of 8 --
3 JUDGMENT
1
10
20
30
40
50
60
to trial and lost, the plaintiffs can expect to be out of
pocket to the extent of about $400,000.
This is a material consideration in deciding whether, at about
the time of the first day of trial or judgment, and for
present purposes, it does not matter which, the plaintiffs are
likely to have the wherewithal to enable them to meet a
liability to pay the defendants' costs, if that is the outcome
of the litigation.
Several considerations are relied upon to support the
contention that there is reason to believe that RHT
Developments Pty Ltd will be unable to pay the defendants'
costs in the event of their success.
RHT has a nominal paid up capital of $100. It is said, also,
that it did not purchase land about a year or so ago because
of an inability to do so. Its only substantial asset, the
land at Gregory Court, Biloela, was purchased for 144,000, of
which almost $130,000 remains unpaid. This is the $130 to
which I have previously referred, and which, in the event that
the plaintiffs are not successful, RHT will be liable to pay.
Next, it is pointed out that RHT has charged its assets in
favour of the Bank of Western Australia, and is already liable
for substantial borrowings.
It is also suggested that the development at Gregory Court has
stalled for financial reasons, and that work on the site has
been, at best, sporadic. This particular aspect of the case
-- 3 of 8 --
4 JUDGMENT
1
10
20
30
40
50
60
cannot be regarded as having been established, the allegations
relied on to support it in an affidavit of Mr Handley being
denied in an affidavit of Mr Thompson, one of the directors of
RHT.
Also, reliance has been placed upon the state of the accounts
and an earlier communication by a director of RHT concerning
its intentions.
The balance sheet as at 30th June 2006 was brought into
existence recently, seemingly in response to the application
for security of costs. It discloses total current assets of
about $176,000. Total current liabilities are $638,000, or
thereabouts. There is, therefore, a very substantial excess
of current liabilities over current assets. But in the nature
of the asset being developed, this is not a surprising thing.
The balance sheet brings the houses to value as non-current
assets at the construction costs so far been incurred. It is
not shown that this is an inappropriate basis for a balance
sheet entry. But caution must necessarily be entertained
concerning the entry as a reliable guide to the amounts the
assets might fetch.
Two of the houses are completed. Five are only partially
complete. And it would not necessarily follow that the
partially completed houses, if they remained in that state,
will fetch the amount of the construction costs incurred in
building them.
-- 4 of 8 --
5 JUDGMENT
1
10
20
30
40
50
60
The balance sheet shows a total shareholders equity of
$546,000, which exceeds the approximately $400,000 arrived at
by aggregating the $100,000 sought by the defendants, the
150,000 estimate for the plaintiffs' costs, and the $130,000
which will be payable by the plaintiffs in the event that
their case is lost. The balance sheet, as such, does not
establish an adequate basis for supposing that the
jurisdictional foundation for an order for security for costs
has been established.
A director of RHT, Mr Thompson, expresses the view that the
company will be in a position to meet any liability and costs
in the event that the case is lost. Other affidavits of his
have been read. A decision has been made not to cross-examine
him with respect to the contents of his affidavits, or more
generally in relation to the financial circumstances of the
company.
I mention this consideration particularly because reliance was
placed by Mr Clothier, in support of the application, upon an
e-mail sent by one of Mr Thompson's co-directors in July 2005
concerning the proposed method of financing the Gregory Court
development. This e-mail, which was sent to Mr Handley, about
18 months ago spoke of an anticipated expenditure on the
development of about $2.5 million, only $1.84 million of which
was to be acquired from the bank.
-- 5 of 8 --
6 JUDGMENT
1
10
20
30
40
50
60
The e-mail identified as other sources of the funding
necessary to make up the difference by reference to sales or
transactions at other places. These included Lakelands - the
site of a proposed joint venture between the parties, which
has not advanced to fruition.
I do not attribute significance to this e-mail, given that so
much time has passed since it was sent, in view of the fact
that Mr Thompson has not been cross-examined with the
suggestion that it contains material with any significance for
the company's fortunes.
The material does not suggest any reason to suppose that the
properties on sale will fetch less than 3.6 million. That sum
is arrived at by using the price which has been obtained on
one contract for sale of one of the ten houses. Assuming that
that sales price proves to be a fair average of the amounts
which might be received on the others, the development should
fetch gross receipts of $3.6 million.
The material concerning the borrowings and other expenses
associated with the development suggests that the total
expenditure to achieve that 3.6 million will be much less. In
other words, the development, if it proceeds in accordance
with current plans, and, apparently reasonable expectations,
ought to yield a significant sum of money - more than enough
to justify the view that the company will be in a position to
discharge, in addition to its other commitments, any liability
-- 6 of 8 --
7 JUDGMENT
1
10
20
30
40
50
60
to the defendants in the event that the plaintiff's case is
lost.
In these circumstances there is no adequate foundation for any
order for security for costs at the moment; and so it is
unnecessary to consider what might have been ordered had there
been a satisfactory foundation for a conclusion that the case
was a proper one for any security.
The application is dismissed.
...
HIS HONOUR: I am satisfied, having read Ms Heyworth-Smith's
outline concerning the way in which the litigation has so far
proceeded, that there is no proper basis for discharging the
applicant from the undertakings which were given at a time
when orders were made with respect to a caveat removal. It is
true that there have been disputes over particulars and that
the position adopted by the plaintiffs has not been fully
sustained. But, apart from that, there is no reason to
suppose that the plaintiffs have not been proceeding with
reasonable expedition to prosecute the case. So, that
application is also refused.
...
-- 7 of 8 --
17012007 T26/DEP(BNE) M/T 3/2007 (Byrne J)
8
1
10
20
30
40
50
60
HIS HONOUR: There has been a substantial measure of success
but you have not succeeded in every respect, so you can have
two thirds of your costs of the application for particulars.
...
HIS HONOUR: I will vary that. You can have half your costs
of that, Mr Clothier.
...
HIS HONOUR: You may have your costs of the security for costs
application, Ms Heyworth-Smith. Draft order, please,
disposing of that application including the order for costs.
...
-----
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2007/062