Crowbay Pty Ltd & Anor v Body Corporate for Southbank Chambers [2007] QDC 62
DISTRICT COURT OF QUEENSLAND
CITATION: Crowbay Pty Ltd & Anor v Body Corporate for Southbank
Chambers [2007] QDC 062
PARTIES: CROWBAY PTY LTD (ACN 010 818 390)
(first appellant)
&
DIANE MARIE WRIGHT
(second appellant)
v
BODY CORPORATE FOR ‘SOUTHBANK
CHAMBERS’ CTS 25675
(respondent)
FILE NO/S: BD3182/06
DIVISION: Civil
PROCEEDING: Appeal
ORIGINATING
COURT: District Court Brisbane
DELIVERED ON: 13 April 2007
DELIVERED AT: Brisbane
HEARING DATE: 27 March 2007
JUDGE: Ryrie DCJ
ORDER: 1. The appeal is dismissed
2. The appellants to pay the respondent’s costs of the appeal
to be assessed on a standard basis.
CATCHWORDS: APPEAL – Body Corporate and Community Management
Act 1997– appeal from adjudicator – common property –
change of use – exclusive use – by-laws – whether
adjudicator failed to correctly apply and interpret section 60
of the Act – whether adjudicator failed to observe the rules of
natural justice – whether adjudicator erred in determining that
a body corporate by ordinary resolution could give consent to
a lot owner’s exclusive use area as a bar and licensed
premises.
Body Corporate and Community Management Act 1997, ss
35, 60, 61, 159, 269, 270 & 289(2)
Body Corporate and Community Management (Standard
Module) Regulation 1997, s159
-- 1 of 8 --
2
Integrated Planning Act 1997, s3.2.1(3), 4.1.2 & Part 3
COUNSEL: Mr A Skoien for the first appellant
Mr B G Cronin for the respondent
SOLICITORS: D M Wrights & Associates for the first appellant
Redchip Lawyers for the respondent
Introduction
[1] This is an appeal from a decision by an adjudicator pursuant to s.289(2) of the Body
Corporate and Community Management Act 1997. The appellants had applied to the
commissioner for orders to the effect that the last recorded community management
statement for the relevant scheme (‘3rd CMS’) was invalid on the basis that it did
not have the relevant local government notation on it and as a consequence, any
motions passed by the Body Corporate for Southbank Chambers (‘respondent’) in
reliance of the 3rd CMS (Resolutions 2 and 4) were invalid. The appellants also
sought a determination that the respondent did not have the power to consent to a
material change of use in respect of Lot 1’s exclusive use area (Resolution 3). On
the 18th September 2006, the adjudicator hearing the application dismissed it.
[2] The appellants’ grounds of appeal before this court have been set out in succinct
form in the Certificate of Readiness which was filed 19th January 2007. Both
counsel used it as a useful reference tool for the purpose of the hearing.
[3] Both parties also provided, for the court’s consideration, detailed and helpful
written submissions.
Background Facts
[4] The appellants are the registered owners of Lot 3 in respect of a four (4) lot
commercial premises (described as CTS 25 675 604-610) in South Brisbane. Each
lot received a right of exclusive use of an area situated at the rear of that respective
lot under the last CMS recorded. The 1st CMS recorded in respect of the premises
(exhibit 1 Tab 10), contained a ‘community management statement notation’ from
the local government (‘the notation’). The 2nd CMS recorded for the scheme did
not contain that notation. (exhibit 1 Tab 11). Nor did the last CMS recorded. By-law
15 in set out in the 1st CMS provided for the exclusive use area (situated at the rear
of the premises) to be used for car parking use only. Each lot was granted two car
spaces each and the right to use two visitor car spaces. In the 2nd CMS (exhibit 1
Tab 11) that exclusive use by-law was re-numbered to by-law 19 but essentially
remained unchanged in substance. By-law 19 in the 3rd CMS (exhibit 1 Tab 12)
however altered that last position in several ways. The restriction on the use of the
exclusive use area for car parking only was removed and in its’ place, an allocation
of the whole of the portion of the common property situated behind each lot was
made for that respective lot’s exclusive use. The question of the 3rd CMS’ validity
however only arose after the owners of Lot 1 indicated an intention of their wish to
operate a licensed bar and restaurant on their lot. That intention also included the
use of the exclusive use area which had been allocated to it under by-law 19. At an
extraordinary general meeting held on the 21st March 2006 by the respondent, three
-- 2 of 8 --
3
resolutions (2, 3 and 4) were passed (Lot 3 being the only dissenter). Resolution 2
consented to improvements being made to the exclusive use car park of Lot 1,
including fencing off the exclusive use area and erecting an awning over that area.
Resolution 3 consented to the use of Lot 1 and its exclusive use area as a bar and
licensed premises and Resolution 4 consented to certain alterations to Lot 1. A
development application had been submitted by the owners of Lot 1 with the
Brisbane City Council for approval. The Council’s decision in respect of that
application is however in abeyance as a result of this dispute.
[5] The appellants’ argument before the adjudicator were, in essence, the same as they
are now, with the exception of the ‘natural justice’ argument now been argued
before this Court.
[6] Essentially what the appellants argue is that even though the 3rd CMS was recorded
with the Land Registry, because it did not have the notation required in accordance
with s.60 and 61 of the Body Corporate and Community Management Act 1997,
reprint no 7D. (‘BCCM Act’), it is invalid and consequently of no effect. It follows
that if that assertion is correct, then the motions passed in reliance of that CMS
(resolutions 2 and 4) would also be invalid. The appellants also argues that the
respondent did not have the power to consent to a material change of use in respect
of Lot 1’s exclusive use area in the manner which it did ( resolution 3), and as such,
that motion is also invalid. The appellants further argue before this court that the
appellants were denied natural justice as a result of adjudicator’s failure to properly
investigate the matters raised in the dispute, by her imposition of the burden of
proof upon the appellants to show why the relevant exclusionary section of the Act
(s.60(6)) did not apply, by the unilateral receipt of correspondence from the
solicitors acting on behalf of Lot 1 and the comments she made in her reasons for
her decision regarding why the appellants may have been taking the stance they
were indicative of bias, and as such, the whole of her decision ought to be set aside.
[7] Accordingly, I shall deal with each of these issues as identified in the Certificate of
Readiness in the following order for convenience.
[8] Exhibit 1 contains the material that was placed before the adjudicator for her
consideration in respect of the dispute.
Issue 1(a) (i), (ii), (iii) and (b) – Did the Adjudicator fail to correctly apply and
interpret s.60 of the BCCM Act 1997?
[9] On any view of the reasons given for the decision, it is clear that the adjudicator
considered that two interpretations were open in respect of s.60 of the BCMM Act.
The adjudicator properly identified that s.60(1) established a prima facie
requirement that a notation is required for any CMS to be recorded. She also
properly identified that ss.(6) of s.60 provided several exemptions to that
requirement, significantly s.60(6)(a) (which in turn refers back to s.60(4)(a),(b) and
(c)).
[10] There is consensus between the parties before this court that the second
interpretation (page 6, 1st paragraph of the decision) primarily relied upon in support
of her decision on this issue was not one that was open if proper regard is had to the
plain and ordinary meaning of that section as a whole. Counsel for the respondent
properly conceded this point and I agree. However, that is not the end of the matter
-- 3 of 8 --
4
as it is clear that the adjudicator also relied upon the 1st interpretation which she had
made, in support of her decision. The appellant argue that the adjudicator fell into
error even on this interpretation when she failed to correctly to apply and interpret
the relevant provisions of s.60 which were under consideration. The appellant
argues that even though the adjudicator properly identified that there was a
difference between the 2nd and 3rd CMS, as it related to by-law 19, the adjudicator
fell into error when she determined that there it wasn’t a ‘difference’ of a kind that
would fall for consideration in respect of the matters set out in s.60(4)(a)(b) or
(c).The appellant submits that the very nature of the changes made to by-law 19 as
set out in the 3rd CMS clearly supports the view that those changes were of a type
which the local authority could have regard to for identifying an inconsistency of a
type specifically envisaged by s.60(4)(a), (b) but more particularly (c). In support of
that argument, the appellant pointed to the fact that under by-law 19 as it currently
stands, the changes which have been made under that by-law allows for any use
whatsoever of the exclusive use area by an allocated lot owner as opposed to that
use being restricted to car parking usage only as it had been previously. The
appellant argues that by ‘opening’ that exclusive use area to any use ‘whatsoever’,
those changes in themselves create an issue of a type contemplated by s.60(4) (a),(b)
or (c) and as such, the 3rd CMS ought to have received the local authority’s notation
prior to its’ registration. The appellant makes that submission even notwithstanding
the effect of clause 3 of by-law 19. While the argument put forward by Counsel for
the appellant, at first blush, certainly holds some attraction, I am unable to accept
that submission. It ignores in my mind, the true meaning of s.60(6) and s.60(4) and
its’ intended effect, particularly when regard is had to s.60 as a whole. In this
instance, clause 3 of by-law 19 specifically states that owners may only use an
exclusive use area for the purposes permitted by the town planning scheme of the
local government and other relevant bodies and shall ensure that all necessary
consents, permits and approvals are obtained before commencing such use. The
adjudicator was of the view that clause by-law 19 therefore covered the situation,
whether it was accepted or not, that the use of that area might include tandem car
parking arrangements, a matter relevant under the local government town planning
scheme, clause (3) of by-law 19 would cover that situation together with any other
situation where the proposed use might be of a kind that a relevant government
body could have regard to for identifying whether there was an inconsistency
between that provision in the 3rd CMS and any of the matters set out in s.60(4)(a),
(b) or (c). While there is no case authority relating to the interpretation of s.60 of the
Act which may have been of assistance, I am of the view that the adjudicator was
correct in her approach to s.60 and as such, did not fall into error as asserted.
[11] Accordingly, these grounds must fail.
Issue 1 (d) and (e) – Did the adjudicator fail to observe the rules of nature justice?
[12] s.269 of the Act requires that an adjudicator act with as little formality and
technicality as is consistent with a fair and proper consideration of an application,
although he or she must observe natural justice.
[13] The appellants argue that the adjudicator failed to observe those rules when she
placed the onus upon the appellants to show why the relevant exclusionary
provision (s.60(6)(a) did not apply (see page 6 last paragraph of the reasons for
decision). In support of that submission, the appellants point to the matters which
were not placed before her by the appellants for consideration and argue that if the
-- 4 of 8 --
5
adjudicator thought she was unable to make a determination without that evidence,
then she ought to have found that prima facie, a notation was required in respect of
the 3rd CMS. I cannot agree with that submission. On any reading of the
adjudicator’s reasons in respect to this issue, the adjudicator was simply setting out
the basis upon which she says was the reasons that she was unable to make the
determination which being sought by the appellants, namely that the use of an
exclusive use area which could include tandem parking was therefore inconsistent
with a lawful requirement of or approval given by the local government under the
Integrated Planning Act 1997(‘IPA’) or its town planning scheme. The adjudicator
quite properly, in my view, noted that it was not a matter within her jurisdiction to
make.
[14] The appellants further argue that the adjudicator ought to have informed the
appellants in any event of any ‘equivocation’ on the part of the Brisbane City
Council (as demonstrated in its’ letter dated 8th September 2006 to the solicitors for
Lot 1), in order that the appellants could have then placed before her, any material
on that issue so that the issue could be decided ‘one way or another’. I cannot accept
that submission. Firstly, the contents of that letter referred to by the adjudicator
(page 7 2nd paragraph of the reasons for decision) simply states the council’s
position which was that it did not consider (quite properly) that it was an issue
which it could make a determination on at that point. Secondly, the issue for
determination before the adjudicator (namely whether or not the 3rd CMS ought to
have contained a local government notation before it was recorded) was, in any
event, only able to be resolved by reference to s.60 of the Act and a determination
of its’ intended meaning, which is exactly what the adjudicator did.
[15] The appellants also argue that they were denied natural justice when the adjudicator
unilaterally received the correspondence referred to above from the solicitor for Lot
1 and an earlier communication from that same solicitor on 12th September 2006.
(page 2 paragraph 5 of the reasons for decision). The appellants say that those
communications ought to have been disclosed to the appellants and relies on case
authorities in support of its submission that the receipt of those communications in
those circumstances, gives rise to a reasonable apprehension of bias.
[16] While it is true that a receipt by a (judge) of a private communication seeking to
influence the outcome of litigation before him places the integrity of the judicial
process at risk, it is also true that an examination of the circumstances of each case
is also important. That examination will include the nature of the communication,
the situation in which it took place, its relationship to the issues for determination
and the nature of the disclosure made by the judge: Re JRL; Ex parte CJL (1986)
161 CLR 342 per Mason J at 351.
[17] In this case, the nature of the communications included a letter sent (8th September
2006) by the solicitor on behalf of the owner of Lot 1 and an earlier oral
communication (12th September 2006) by them again on behalf of the owner of Lot
1 to the Commissioner’s Office indicating that the Brisbane City Council had taken
a neutral position with respect to the development application which it had earlier
received from Lot 1 and that it would not be processing it now until the dispute had
been resolved. Both of those communications were only disclosed by the
adjudicator in her reasons for decision. While the appellants consider that such
failure gives rise to a reasonable apprehension of bias, I am unable to agree. While I
do agree that a more prudent course would have been the disclosure of those
-- 5 of 8 --
6
communications to all parties prior to the decision being given, it is also true that
the relationship of those communications to the issues for determination is also a
relevant factor when determining whether or not a reasonable apprehension of bias
has been raised. Here the only issue for determination as it relates to this point was
whether the 3rd CMS recorded was invalid by reference to s.60 of the Act. Both of
the communications received do no more, in my view, than to confirm the council’s
position, that it was not a matter which it could resolve, but rather, a matter which
ultimately had to be determined by the adjudicator.
[18] Accordingly, this submission cannot succeed.
[19] The appellant further submits (in its written outline) that the comments (page 12
paragraph 2 of the reasons for decision) made by the adjudicator when considering
s.270 of the Act (dismissal of applications) also give rise to a reasonable
apprehension of bias. That submission however ignores the fact that the evidence
before the adjudicator regarding whether the appellants had been acting vexatiously
or not, when read as a whole, does support a view that there are indications that the
appellants had sought to stall the business plans of Lot 1 and as such, a reasonable
inference that was also open, was that the appellants were seeking to pursue their
own business arrangements inconsistent to that of the proposed use of Lot 1’s
exclusive use area.
[20] Accordingly, this submission cannot succeed.
Issue 1 (c) – Did the adjudicator fall into error when she determined that the Body
Corporate could, by ordinary resolution (3:1), give consent to the use of Lot 1’s
exclusive use area as a bar and licensed premises?
[21] The appellants argue that because Lot 1’s proposed development application for the
bar and licensed premises involves the exclusive use area, the Body Corporate can
only give its’ consent to such use through an ordinary resolution without dissent
rather than by ordinary resolution by majority. The appellants argue that the Body
Corporate must obtain the consent of all of the owners of that common property
before any development of a kind proposed by Lot 1 can be approved. The appellant
referred to s.3.2.1(3) of IPA which provides that a development application must
contain, or be supported by, the written consent of the owner of the land to the
making of the application if the application is for, amongst other matters, a material
change of use of premises.
[22] Both parties agree that the proposed development of Lot 1 will also include the Lot
1’s allocated exclusive use area situated behind it. Both parties also agree that the
designation of common property of the Body Corporate as an exclusive use area for
a lot owner’s use does not alter the fact that the area remains part of the common
property and held by the owners of the lots as tenants in common: s.35 BCCM Act.
The appellant has relied on a number of case authorities in support of its’
submission that the Body Corporate must first obtain the consent of all of the
owners of the common property in order that it may approve any use of a kind
proposed by Lot 1.
[23] Most, if not all of those authorities however relate to decisions which have been
given by the Queensland Planning and Environment Court exercising its’
jurisdiction and as such, appear more to lend support to the submissions made by
-- 6 of 8 --
7
the respondent on this issue. The respondent had submitted that all that those cases
demonstrate is, that any question regarding whether valid consent has been given in
respect of a development application in terms of s.3.2.1(3) of IPA is solely within
the province of a local authority and the Planning and Environment Court pursuant
to s.4.1.2.of IPA, and as such, it matters not about the validity of the resolution
which has been passed by the Body Corporate. The respondent submits that even if
resolution 3 on its’ face authorises the granting of consent, whether that consent is
valid or not for the purpose of IPA is another matter entirely and not one which is
within the province of the adjudicator (or even this court) to make.
[24] The appellant, on the other hand, relies on those authorities in support of their
submission that the Body Corporate simply cannot give its’ consent in the manner
which it has unless there was a resolution without dissent as the (purported) consent
obtained by resolution by majority was in respect of common property, the
ownership of which is held by all lot owners as tenants in common.
[25] As the appellant stressed, neither the adjudicator or this court is being asked
whether or not the development application made is a ‘properly made application’
for the purposes of IPA, but rather it is asked to consider whether or not the
resolution (3) passed by majority by the body corporate is a valid resolution or not.
[26] The determination of this issue has not been an easy one, particularly in view of the
fact that both Counsel have been unable to refer me to a case which specifically
deals with this point.
[27] An examination of the BCCM Act certainly provides power to a body corporate to
authorise an owner of a lot to make an improvement to the common property for the
benefit of the owner’s lot: s.159 of the Act and s.114 of the Body Corporate and
Community Management (Standard Module) Regulation 1997.
[28] ‘Improvement’ is defined in the Act as including:
(a) the erection of a building; and
(b) a structural change; and
(c) a non-structural change.
[29] While it would appear that resolutions 2 and 4 relate to improvements proposed in
respect of Lot 1 and its’ exclusive use area, the same cannot be said in respect of
resolution 3. That resolution appears to relate to the proposed use of lot 1 as a bar
and licensed premises rather than simply with respect of any improvements which
are to be made for that purpose. Under the Integrated Planning Act 1997 reprint no.
7, a ‘material change of use’ is relevantly defined in Part 3 Definitions generally as
(i) the start of a new use of the premises; or (iii) a material change in the intensity or
scale of the use of the premises. That definition is therefore different to the
definition relating to an improvement under the BCCM Act.
[30] At first blush, the argument proposed by the appellants has some attraction in
support of the argument that the body corporate simply cannot pass a resolution (by
majority) giving its’ consent to the use of Lot 1 as a bar and premises. To adopt the
position contended for by the appellants however would, in my view, have the
effect of leading to a situation that a lot owner in a scheme will rarely, if ever, be
able to make a development application (with the necessary consent) with respect to
-- 7 of 8 --
8
his own lot and its’ exclusive use area (involving common property) unless he
obtains the consent of the body corporate through a resolution without dissent. That
in my view would have the effect of allowing one lot owner of the scheme to
withhold his or her consent in respect of any other lot owners’ proposed
development application involving common property even notwithstanding the
majority of the other lot owners in the scheme may well have been in favour of the
development going ahead, as indicated by the vote taken at a meeting which had
been held by the body corporate for the purpose.
[31] On balance then, I am of the view that the conclusion by the adjudicator on this
issue (page 11 paragraph 4 of the reasons for decision) is the correct one.
[32] Accordingly, this ground cannot succeed.
Orders
1. The appeal is dismissed.
2. The appellants to pay the respondent’s costs of the appeal to be assessed
on a standard basis.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2007/062