Barooga Projects (Investments) Pty Ltd v Redcliffe City Council [2007] QPEC 84
[2007] QPEC 084
PLANNING AND ENVIRONMENT COURT
JUDGE BRABAZON QC
P and E Appeal No 681 of 2007
P and E Appeal No 682 of 2007
P and E Appeal No 683 of 2007
BAROOGA PROJECTS (INVESTMENTS)
PTY LTD Appellant
and
REDCLIFFE CITY COUNCIL Respondent
BRISBANE
..DATE 13/09/2007
JUDGMENT
1
-- 1 of 8 --
2 JUDGMENT
1
10
20
30
40
50
60
HIS HONOUR: This hearing deals with three appeals against
decisions made by the Redcliffe City Council. The Council
decided to refuse three development applications which involve
the development of multiple dwellings, I think only because
there were three titles, lots 93, 94 and 95. There were three
applications and three decisions but, effectively, it is the
one project.
After the refusal, negotiations between Barooga Projects and
Council have resulted in changes which the Council is now
content to accept subject, necessarily, to the Court's
decision that the changes are "minor changes". That is the
issue here, whether or not they are minor.
I should say that I am grateful for Mr Cochrane's submissions
which comprehensively point out the contemporary ways in which
this Court has approached questions of this kind. It will be
remembered that section 4.1.52(2)(b) of IPA says that in a
situation like this where the Council has received an
application and refused it:
"The Court must not consider a change to the application
on which the decision being appealed was made unless the
change is only a minor change."
Not surprisingly, perhaps, there are now many decisions of
this Court dealing with the issue of "minor change". One
thing that has influenced the cases from time to time is a
definition of "minor change" in a different context, that is,
in Schedule 10 of IPA. There, minor change is defined by
-- 2 of 8 --
3 JUDGMENT
1
10
20
30
40
50
60
reference to three things that would not require any
activities such as referral to additional concurrence
agencies, or to cause development previously requiring only
code assessment to require impact assessment, or where impact
assessment is required be likely, in assessment manager's
opinion, to cause a person to make a properly made submission
objecting to the proposal, if the circumstances allowed.
It is now really apparent that, fundamentally, one must pay
attention to the words themselves in this section as this is
not literally an occasion on which the application of Schedule
10 is called for.
It must be said that the Judges of this Court have tried to
take a functional view of the idea of "minor change", that is
to look behind what may superficially seem to be a substantial
change to see whether that is, in truth, the case. For
example, it needs to be recognised that the power to modify an
application is a beneficial one, and that the town planning
process itself would be greatly narrowed and made more
difficult if appropriate changes could not be made. For
example see Judge Rackemann's remarks in Heilbron and Partners
-v- Gold Coast City Council [2005] QPELR 386 at 392.
Judge Wilson of this Court in several decisions has recently
collected together some of the more important themes in these
cases. For example, see the decisions in Studio Tekton Pty
Ltd -v- Redland Shire Council [2006] QPEC 107, Grant -v- Pine
-- 3 of 8 --
4 JUDGMENT
1
10
20
30
40
50
60
Rivers Shire Council [2006] QPELR 112 at 116, and Parcel One
Pty Ltd -v- Ipswich City Council [2007] QPEC 033.
One thing he did point out in Studio Tekton, was that the
Court in being careful in its consideration of what
constitutes a minor change would take into account changes
which both attempt to ameliorate impacts and those which are
intended to improve a design. In that context, he points out
an occasional irony, as he called it - that is, a significant
alteration to a proposal to make it more acceptable to
submitters but simply because of its scale exposed itself to
categorisation as a major rather than minor change.
In the Parcel One decision he emphasised that which is now
accepted, that the phrase "only a minor change" is meant to
be:
"...a simple and straightforward one which should be
construed principally by reference to matters of scale
and degree, broadly and fairly."
He went on to say, and I agree, that:
"It is attractive to adopt a generous approach to the
interpretation of the limits within which an application
like this may be changed."
He did go on to say that:
"The statutory requirement had to be served and that some
assistance can be gained from looking at Schedule 10 of
IPA."
-- 4 of 8 --
5 JUDGMENT
1
10
20
30
40
50
60
He also pointed out that:
"If changes are beneficial or ameliorative, it may be of
assistance and that it would also be helpful to see
exactly what it was that was changed, that is to say
whether it be a salient or incidental feature of the
original proposal."
It is also probably necessary in cases of this sort to take
into account whether or not there are, or are likely to be,
submitters and whether or not those who, as happens in many
cases, were opposed to a project become supportive of it once
changes are made to their satisfaction. It might be noted in
this case there were no submitters.
Having said all that, it is necessary to turn to the changes
that have been made here. The three lots, as I say, have been
treated separately and one might note the changes which are
relatively similar in each case. For example, in lot 93 the
number of units, 38, has been reduced to 26. The gross floor
area has gone down from around 4000 square metres to around
3000 square metres. The site coverage has been reduced from
35 per cent to some 26 per cent. All that has been achieved
largely by removing the third story leaving it a 2-story
building. The setbacks are larger. The appearance, at least
according to Mr Cochrane's summary, is different. The
original proposal, which the Council considered, was rendered
masonry with Colorbond roofing whereas now it will be
blockwork with Colorbond roofing.
-- 5 of 8 --
6 JUDGMENT
1
10
20
30
40
50
60
I might say that his note attached to his submissions
indicated face brick but as I understand the plans, they say
it will be blockwork.
The number of carparks has been reduced from 38 to 26 and with
respect to visitors from 15 to 9. The traffic arrangements
have been altered somewhat from a one-way entry and one-way
exit to a single entry and exit for the lot 93 units.
The changes to lot 94 and 95 are substantially along the same
pattern. Overall, it can be seen that each of the structures
will be of two storys rather than three. The original
proposal for 86 units has become 59. I have mentioned the
changes to the outside appearance with regard to the masonry
or blockwork.
The traffic changes apply to each of the three lots. Before
there was one entrance to the whole project and one exit from
the whole project. Now there are four separate entrances or
exits over the footpath, that is to say one in/one out and two
which combine an in/out arrangement.
A look at the floor plan will show that the layout of the
units is quite different. For example, the garages, some of
which were located against the rear boundary, have all been
moved from that position.
It is necessary to look at the elevations. For example, to
take one of the three, elevations to lot 93 can be compared to
-- 6 of 8 --
7 JUDGMENT
1
10
20
30
40
50
60
the old elevations. It can be seen that the style of the
building and the treatment of windows and shape of the roof is
different in each case. The north elevations, lot 93,
presents as a substantial building which has become about half
that width in the new elevation. With regard to the east
elevation, before one looked at three substantial buildings
fairly close together with relatively flat roofs. They have
now become four buildings with steeper roofs.
The west elevation is also different. There are four
buildings whereas before one saw three. In fact, the truth of
the matter is that anyone looking at these plans would be hard
pressed to think that it was the same project.
The fact of the matter is the project has been entirely
reworked to what would be, I imagine, a much more satisfactory
result to the Council's officers. However, if I may say so,
it is outside the range where the Court can agree that it is a
minor change.
I also wish to say that in my experience in recent times there
have been a number of applications of this kind where it is
apparent that the envelope is being pushed to its absolute
limit. In this case if the application were acceded to that
limit would be exceeded. In my view, it is simply impossible
to regard this as a minor change, bearing in mind the sort of
differences that I have mentioned - in particular, the
appearance of the buildings to anyone who might be interested
and think of making an objection to it.
-- 7 of 8 --
8 JUDGMENT
1
10
20
30
40
50
60
It does seem apparent, and I should say I have heard this
suggested in other quarters, that an amendment to the
legislation is necessary. There is nothing more I can say
about that today.
The application is refused.
...
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2007/084