Brisbane Land Pty Ltd v Pine Rivers Shire Council [2007] QPEC 126
[2007] QPEC 126
PLANNING AND ENVIRONMENT COURT
JUDGE ROBIN QC
No 1434 of 2007
BRISBANE LAND PTY LTD Appellant
and
PINE RIVERS SHIRE COUNCIL Respondent
BRISBANE
..DATE 10/09/2007
ORDER
CATCHWORDS: Integrated Planning Act 1997 s 3.5.21, s 3.5.22,
s 4.1.5A - where development approval lapsed at expiration of
the "relevant period" (currency period) - whether timely
written notice "before approval lapses" of an extension being
asked is a "requirement of the Act" held that there was a
discretion to extend time where such notice was given late and
that it should be exercised favourably
1
-- 1 of 13 --
2 ORDER
1
10
20
30
40
50
60
HIS HONOUR: This application within the underlying appeal
against the Council's refusal of its "Request to Extend [a]
Currency Period of [a] Development Permit" seeks relief under
section 4.1.5A of the Integrated Planning Act 1997 by way of
an extension of time for giving written notice by such a
request. The applicant is in the embarrassing situation of
its development permit having lapsed under section 3.5.21 of
the Act:
" 3.5.21 When approval lapses if development not started
(1) To the extent a development approval is for a
material change of use of premises, the approval
lapses if the first change of use under the approval
does not happen within the following period (the
relevant period)-
(a) 4 years starting the day the approval takes
effect; or
(b) if the approval states a different period from
when the approval takes effect - the stated
period.
2. To the extent a development approval is for
reconfiguring a lot, the approval lapses if a plan
for the reconfiguration is not given to the local
government under section 3.7.2(2) within the
following period (also the relevant period)-
(a) for reconfiguration not requiring operational
works - 2 years starting the day the approval
takes effect;
(b) for reconfiguration requiring operational works
- 4 years starting the day the approval takes
effect;
(c) if the approval states a different period from
when the approval takes effect - the stated
period.
3. To the extent a development approval is for
development other than a material change of use of
premises or reconfiguring a lot, the approval lapses
if the development does not substantially start
within the following period (also the relevant
period)-
-- 2 of 13 --
3 ORDER
1
10
20
30
40
50
60
(a) 2 years starting the day the approval takes
effect;
(b) if the approval states a different period from
when the approval takes effect - the stated
period.
(4) Despite subsections (1) and (2), if there is 1 or
more related approvals for a development approval
mentioned in subsection (1) and (2), the relevant
period is taken to have started on the day the
latest related approval takes effect.
(5) If a monetary security has been given in relation to
any development approval, the security must be
released if the approval lapses under this section.
(6) The lapsing of a development approval for a material
change of use of premises or reconfiguring a lot
does not cause an approval mentioned in subsection
(3) to lapse.
(7) In this section -
related approval, for a development approval for a
material change of use of premises (the earlier
approval), means -
(a) the first development approval for a
development application made to a local
government or private certifier within 2 years
of the start of the relevant period, that is-
(i) to the extent the earlier approval is a
preliminary approval-a development permit
for the material change of use of
premises; or
(ii) to the extent the earlier approval is a
development permit or a preliminary
approval for development mentioned in
section 3.1.6(3)(a)(ii) or (iii) - a
development permit for building work or
operational work necessary for the
material change of use of premises to take
place; and
(b) each further development permit, for a
development application made to a local
government or private certifier within 2 years
of the day the last related approval takes
effect, that is for building work or
operational work necessary for the material
change of use of premises to take place.
-- 3 of 13 --
4 ORDER
1
10
20
30
40
50
60
related approval, for a development approval for
reconfiguring a lot (also the earlier approval),
means-
(a) the first development permit for a development
application made to a local government within 2
years of the start of the relevant period, that
is -
(i) to the extent the earlier approval is a
preliminary approval - for the
reconfiguration; or
(ii) to the extent the earlier approval is a
work related to the reconfiguration; and
(b) each further development permit, for a
development application made to a local
government within 2 years of the day the last
related approval takes effect, that is for
operational work related to the
reconfiguration."
Although the applicant was aware of the limited duration of
its development approval, (indeed, concedes it had advice from
a consultant of 23 January 2007 that the currency period would
be "ending in 2007", the issue of compliance in a timely way
with section 3.5.22:
"3.5.22 Request to extend period in s 3.5.21
(1) If, before a development approval lapses under
section 3.5.21, a person wants to extend a period
mentioned in that section, the person must, by
written notice -
(a) advise each entity that was a concurrence
agency that the person is asking for an
extension of the period; and
(b) ask the assessment manager to extend the
period.
(2) The notices must be given at about the same time,
and the notice to the assessment manager must
include a copy of each notice given under subsection
1(a).
-- 4 of 13 --
5 ORDER
1
10
20
30
40
50
60
(3) If the person is not the owner of the land to which
the approval attaches, the request must be
accompanied by the owner's consent.
(4) Subsection (5) applies if an application for the
approval were made at the time the request is made
and evidence under section 3.2.1(5) would be
required to support the application.
(5) The request must also be accompanied by the written
agreement of the chief executive from whom evidence
would need to be obtained under section 3.2.1(5).
(6) If the assessment manager has a form for the
request, the request must be in the form and be
accompanied by the fee -
(a) if the assessment manager is a local government
- set by a resolution of the local government;
or
(b) if the assessment manager is another public
sector entity - prescribed under a regulation
under this or another Act.
(7) A request under this section may not be withdrawn."
was overlooked.
The relevant development permit, which (among other things)
approves a material change of use for some 32 residential lots
in the previously rezoned lot 7 - part of stage B10, Glenwood
Estates; was issued by the Council on 15 March, 2003, received
by the applicant on the 18th. The requisite written notice
was not given to the Council until 30 March 2007, a modest
couple of weeks late.
The explanation for that was that delays occurred in the
obtaining of authority thought to be required for removal of
vegetation.
-- 5 of 13 --
6 ORDER
1
10
20
30
40
50
60
Ultimately the State authority concerned in that aspect (the
Department of Natural Resources) advised that it was not
necessary for the applicant to obtain any such authority in
the circumstances. The explanation apparently lies in
official mapping of vegetation being changed.
If there had been a development permit for vegetation clearing
obtained from the Department of Natural Resources, the issue
of it would have had the effect of extending the period open
to the applicant for getting on with its development. See
s 3.5.21(4).
...
It may or may not be reasonable to attribute some of the
responsibility for delay to the Department of Natural
Resources, in that it took a long time to advise the
conclusion that it had no need to issue any permit. The
application for vegetation clearing was lodged on 14 October
2004, the advice issued on 19 February 2007.
...
The overall development project the applicant is engaged on
is, by common consent, well advanced. Hundreds of lots have
been produced and sold. The Council is supportive of the
development and to the extent that its attitude is known from
a number of communications from its offices, if there had been
a timely request for extension of what used to be called the
-- 6 of 13 --
7 ORDER
1
10
20
30
40
50
60
"currency period" - in section 3.5.22 it is now differently
described - the Council would have been willing to grant the
extension sought. It took the view that it could not grant an
extension upon a request made by written notice after the
development approval lapsed on 15 March 2007.
For what it is worth, the applicant has continued to be
engaged in seeking various authorities in respect of
relatively minor matters in Stage B10, such as provision of
electricity.
Section 4.1.5A is in the following terms:
"4.1.5A How court may deal with matters involving
substantial compliance
(1) Subsection (2) applies if in a proceeding before the
court, the court-
(a) finds a requirement of this Act, or another Act
in its application to this Act, has not been
complied with, or has not been fully complied
with; but
(b) is satisfied the non-compliance, or partial
compliance, has not substantially restricted
the opportunity for a person to exercise the
rights conferred on the person by this or the
other Act.
(2) The court may deal with the matter in the way the
court considers appropriate."
-- 7 of 13 --
8 ORDER
1
10
20
30
40
50
60
The difficulty which the Council points to as confronting the
applicant - although its attitude today is to abide the
Court's order - arises from the Court of Appeal decision in
Lamb v. Brisbane City Council [2007] QCA 149, in particular,
from paragraph [46] on: there must be identified before
section 4.1.5A can be available a "requirement" of the Act.
In the circumstances of Lamb, there was no way in which the
Act could be said to produce a requirement that a person
entitled to make a "development application (superseded
planning scheme)" was required or obliged to make such an
application. Such a person might well have been content if
any planning application were made to make it under the
current planning scheme.
Lamb has occasioned some change in the generous approach to
the application of section 4.1.5A which had come to be adopted
in this Court. The change is exemplified in McNab
Developments Pty Ltd v. Toowoomba City Council [2007] QPEC
069; the Court was concerned with the entitlement of Glenvale
Properties Pty Ltd to be joined as a co-respondent in an
appeal by a developer seeking to achieve a development permit
rather than the preliminary approval which the respondent
council had granted. Entitlement to participate in the appeal
depended upon the applicant there having made a "properly made
submission". Although the provisions in the Act and actual
practice gave rise to possibilities of the council
entertaining a submission other than a "properly made" one,
the entitlement to appeal depended on the submission being
-- 8 of 13 --
9 ORDER
1
10
20
30
40
50
60
"properly made". Although Judge Rackemann accepted that
Glenvale's intention was to make a properly made submission,
in the document completed, its address did not appear, so that
definition of "properly made submission" was not satisfied.
The question before his Honour was discussed in paragraph [7]
and following in light of the decision in Lamb. He concluded
that there could not be identified any requirement of the Act
given that, among other things, it was not incumbent upon a
person wishing to make a submission to make a "properly made"
one.
Shortly before McNab Developments, Judge Wilson in National
Properties Group v. Toowoomba City Council [2007] QPEC 074
published the judgment on which Mr Gore QC, for the applicant
here, relies.
I agree entirely with what his Honour said at paragraphs 12 to
15 and take the liberty of repeating it here:
"[12] The emphasis on the word requirement in s
4.1.5A(1)(a) is to be understood in the context of the
circumstances arising in each of these cases where, in
each instance, it was not a procedural step in the IDAS
path which fell for consideration but, rather, the primal
question whether the process which brought the matter
before the court was deficient in some fundamental
respect.
[13] At first blush, the applicant here might be thought
to face the same difficulty: as it is framed, s 3.2.12
does not immediately present as something expressing a
'requirement'. It is simply a lapsing provision, which
applies automatically where the onus to take the next
step under the IDAS process falls upon an applicant. In
other words, it does not 'require' an applicant under the
IDAS process to commence the notification stage; rather,
it simply states what will happen if the applicant does
not do so within the nominated period.
-- 9 of 13 --
10 ORDER
1
10
20
30
40
50
60
[14] The provision plainly cannot, however, be read in a
vacuum. It is an element of the procedures set up in the
complex IDAS system, which have a consistent theme - to
ensure the development assessment process is undertaken
fairly, logically and progressively, and without undue
delay. It depends, for its operation, upon the
occurrence (or not) of events referrable to ss 3.4.4, and
3.4.3. Read together - as, logically, they must be -
these provisions point inexorably, it seems to me, to a
clear 'requirement' of IPA: that for a development
application to remain alive and effective (for the
purposes of the IDAS process) between the Information and
Referral and Notification stages, the latter must be
commenced within 20 days of completion of the former.
[15] This construction sits comfortably on the broader
canvas of Chapter 3 of IPA, where to speak of the many
other progressive, logical and interlinked steps within
the IDAS process and the various time limits applicable
to them as something other than 'requirements' of the
legislation would be to ignore both the nature of the
processes themselves and, also, the ordinary meaning of
the word including its primary, dictionary meanings - eg,
the Macquarie first defines 'require' as 'need; depend
for success or fulfilment'."
National Properties Group was concerned with section 3.2.12 as
the lapsing provision in the Act, whereas the applicant's
concern here is with section 3.5.21.
In my view the considerations are the same; I have not thought
it necessary to devote time to further deliberations after
today's hearing, in which the Court was greatly assisted by
written submissions filed by the applicant. In view of may
having taken the opportunity to read the relevant filed
material and the submissions and also in view of my having
considered similar matters in the pre-Lamb era on a number of
occasions. The first occasion was Roy Somerville Projects Pty
Ltd v Logan City Council [2006] QPEC 021, when I noted the
decision in Ramsgrove v Beaudesert Shire Council [2005] QPEC
-- 10 of 13 --
10092007 T(1)05-06/ROH(BNE) M/T BRIS11 (Robin DCJ)
11
1
10
20
30
40
50
60
116, which, at that time, was the subject of an application to
the Court of Appeal for leave to appeal. It was understood
that the question for the Court of Appeal was the presently
pertinent one of whether an application (or, presumably, an
approval) which has lapsed by force of the Act can be revived
by the Court taking action under section 4.1.5A.
What I said on that occasion indicates that I was somewhat
sceptical about the possibility of something which has lapsed
in that way reviving. A similar question arose in Coolong Pty
Ltd v Gold Coast City Council [2006] QPEC 027, in which I took
the opportunity to look into the consequences of a statutory
"lapse" in some detail, referring to authorities including the
decision of Fullager J in Esso Research and Engineering
Company v Commissioner of Patents 102 CLR 347, 34 ALJR 83
which contains an interesting discussion of the ability of a
tribunal to extend a period to prevent something lapsing after
it has by definition lapsed. The reasons in Coolong refer to
a number of the decisions in this Court in which section
4.1.5A was used in the way the applicant seeks here. A third
matter was Samford Child Care Centre v Pine Rivers Shire
Council [2006] QPEC 036, in particular paragraph [9], where it
was opined that there was "some question of the Court's
ability to revive a lapsed application by recourse to section
4.1.5A as occurred in Ramsgrove." I noted again that the
views of the Court of Appeal were awaited. My understanding
is that because the would-be appellant elected not to devote
further funding to the exercise, the application to the Court
of Appeal for leave was abandoned.
-- 11 of 13 --
10092007 T(1)05-06/ROH(BNE) M/T BRIS11 (Robin DCJ)
12
1
10
20
30
40
50
60
All of the potential discretionary considerations strongly
tend to support that of s 4.1.5A as sought by the present
applicant, assuming the section is available. The Court of
Appeal's views may now not be sought for some time.
In those circumstances the decisions in this Court which I
collected and Judge Wilson's recent one are a persuasive
collection of authorities favouring the applicant, assuming
that there is statutory "requirements not complied with"
properly identified. There would be introduced a possibly
mischievous conflict of decisions in this Court were I to
yield to my expressed misgiving.
The inclusion in the Act of provisions such as 3.5.21 serves a
very useful purpose. No-one would want to have development
approvals extant forever, reserving to the owner of a site a
never-ending ability to effect a particular development which,
as the years pass, might become highly inappropriate for the
site in its locality. The books contain examples of cases of
that kind in which local governments have declined to extend
currency periods. The present circumstances, for all that
appears, are very different, with the Council supportive of
the development. There is little attraction in an outcome
which determines that an approval in such circumstances has
irretrievably lapsed. The point upon which I agree with Judge
Wilson is that, for section 4.1.5A purposes, a step that must
be taken to prevent the lapsing of an application or approval
may properly be seen as a "requirement" of the Act. It would
-- 12 of 13 --
10092007 T(1)05-06/ROH(BNE) M/T BRIS11 (Robin DCJ)
13
1
10
20
30
40
50
60
be unfortunate to have to reach any other decision, given the
Council's attitude and the determination of the applicant,
which has persisted over the years and still persists, to
pursue its development. It is unnecessary here to give any
attention to the case in which an application or approval
appears to have been abandoned.
Given the role reserved to concurrence agencies by section
3.5.22(1)(a), which is relevant in the present circumstances,
Mr Gore has taken the cautious approach that, rather than seek
an order disposing of the whole appeal in his client's favour
today, matters ought to be put in the state that would pertain
had a timely application been made under section 3.5.22; that,
I think, is entirely appropriate.
The Court's order is, therefore, that in respect of the
development permit reproduced at page 81 of the affidavit of R
M Caswell, filed the 13th of July 2007, the time for giving
written notice as required by section 3.5.22(1) of the
Integrated Planning Act 1997 be extended to the date seven
days after the date of this order. Liberty to apply is
granted as well.
...
-----
-- 13 of 13 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2007/126