Canungra Commercial Pty Ltd v Beaudesert Shire Council [2007] QPEC 51 (2007) QPELR 552
PLANNING & ENVIRONMENT COURT
OF QUEENSLAND
CITATION: Canungra Commercial Pty Ltd v Beaudesert Shire Council
[2007] QPEC 51
PARTIES: CANUNGRA COMMERCIAL PTY LTD
Applicant
and
BEAUDESERT SHIRE COUNCIL
Respondent
FILE NO: BD 1216 of 2007
PROCEEDING: Application for a declaration or order under s 4.1.5A of The
Integrated Planning Act 1997
DELIVERED ON: 19 June 2007
DELIVERED AT: Brisbane
HEARING DATE: 14 June 2007
JUDGE: Judge Brabazon QC
ORDER: Order that assessment of the plan of development proceed.
CATCHWORDS: ENVIRONMENT AND PLANNING – DEVELOPMENT
CONTROL – APPLICATIONS – where s 3.2.9 IPA required
the IDAS process to start again from the start of the
acknowledgment period – whether the court should exercise
its discretion under s 4.1.5A IPA to excuse compliance with s
3.2.9 IPA
COUNSEL: Mr S M Ure for the Applicant
Mr R Litster for the Respondent
SOLICITORS: Flower & Hart Lawyers for the applicant
Corrs Chambers Westgarth for the respondent
The Issue
[1] There is an issue about the effect of s 3.2.9 of the Integrated Planning Act 1997
(“IPA”). Should the application for approval be considered by Council, or must it
go back to the acknowledgment period?
-- 1 of 9 --
2
The Facts
[2] On 16 March 2006 the applicant, Canungra Commercial, lodged an application with
the Beaudesert Shire Council, for approval of a staged development, including a
supermarket, at Christie Street, Canungra.
[3] Informal discussions with Council officers followed. They resulted in an amended
application, lodged on 22 May 2006. The amendments included provision for the
sale of petroleum products, and sewerage treatment.
[4] The Council’s Acknowledgment Notice of the amended application was not given
until 20 June 2006. The Council’s letter observed that it had 10 business days from
the date of the Acknowledgment Notice to determine whether further information
needs to be submitted. See s 3.3.6 of IPA. The letter went on:
“However, in this particular instance, this Acknowledgment Notice
has been provided to the applicant after the time specified in section
3.2.15(a) of IPA. As this is the case, the Council will not be making
a formal Information Request as provided for under section 3.3.6.
However, in this instance, the Council may make an informal
Information Request, in order to assist with the further assessment of
the application.
A response to such a Request should be forthcoming in writing and
may entail the following:
(a) the full provision of requested information;
(b) the part provision of information, with a notice asking the
requesting authority to proceed in assessing the application; and
(c) by giving the requesting authority a notice stating that you do
not intend to supply any of the information requested, and
asking the requesting authority to proceed in assessing the
application.
You will be advised as to whether Council officers require any
additional information to properly assess the development application
in separate correspondence.”
[5] It is common ground here that a formal Information Request was never made by
Council. Such a request has to be in writing. See s 3.3.6(2) of IPA. There were
-- 2 of 9 --
3
further informal discussions between Council officers and Mr Kelly, who
represented Canungra Commercial.
[6] The Acknowledgment Notice said that referral was required to two concurrence
agencies – the Department of Main Roads and the Environmental Protection
Agency.
[7] On 4 July 2006 Mr Kelly wrote to Main Roads. On 17 July the EPA received the
application, and on 20 July it issued an Information Request, with respect to the
petroleum storage and sewerage.
[8] On 21 July 2006 Main Roads wrote, saying that it was extending the time for an
Information Request, according to s 3.3.6(6) and (7) of IPA. There is a suggestion
here that the decision was late, but no point about it was taken at the time, and a
response was made to the request. Then, on 4 August 2006, Main Roads delivered
its Information Request. In particular, it required a revised Traffic Impact
Assessment, with various requirements set out.
[9] The ongoing discussions with Council officers resulted in several changes to the
plans that had been lodged. There were meetings on 11 October and 9 November
2006. The changes were not made because of the Information Requests. The
service station component was omitted from the application. The specialty shops in
the proposed Stage 2 were extended, both towards the Christie Street frontage, and
in area – an extra 250m2 was added. The service driveway was separated from the
customer driveway onto Christie Street, internal pedestrian pathways were
improved between Christie Street and Finch Street and central to the site, and some
temporary playground structures were removed and replaced with lawns and picnic
benches. The position of the maintenance shed at the bowls club was moved
-- 3 of 9 --
4
slightly. The car parks were extended, from 21 to 30. All those things were done at
the request of Council’s officers.
[10] The result was a change to the proposed plan of development. An amended
drawing, SD04, dated May 2006, was sent to Council. Mr Kelly’s letter of 23
November 2006 mentioned those changes. His letter concluded:
“An Information Request was received from the EPA by facsimile on
21st July 2006. An Information Request was received from
Queensland Main Roads in correspondence dated 4th August 2006.
The information responses are attached for Council’s records. The
public notification process will now be undertaken.
Enclosed are triplicate copies of …”
[11] The copies included the amended plan, SD04.
[12] In saying that the notification stage could start, Mr Kelly was relying on s 3.4.3(3)
of IPA:
“When can notification stage start
3. If an information request has been made during the information
request period, the applicant may start the notification period as
soon as the applicant gives –
(a) all information request responses to all Information
Requests made, and
(b) copies of the responses to the assessment manager.”
[13] According to Mr Kelly, it was never Council’s practice to advise when notification
could start.
[14] On the same day, Mr Kelly sent the required information to Main Roads. Also on
that day, he sent the response to the EPA. He pointed out to that agency that the
service station had been deleted, and that only the sewerage proposal would
continue. His letters show that he sent the amended plan to each agency.
[15] On 22 December 2006 Mr Kelly wrote again to Council. He observed that “the
advertised date for the close of submissions related to the above described
-- 4 of 9 --
5
application has passed.” He enclosed evidence of the notification to the public. His
letter concluded:-
“Could you please arrange to have a copy of any submissions
received regarding the application forwarded to our office. If you
have any questions please contact me.”
[16] There were 10 submissions, some of which were in a common form. Those
submissions were given to Mr Kelly by Council.
[17] On 25 January 2007 the Main Roads’ response was given. It required a change to
the proposed access, and the upgrading to the intersection on Christie Street. Lights
were required.
[18] On 30 January 2007 Council responded. The letter noted the changes sought in the
amended application of 23 November 2006, and went on:
“Whilst these changes may have arisen from discussions with
Council officers, a development application can only be amended in
response to an Information Request issued by Council or under the
provisions of section 3.2.9 of IPA. Given that Council did not issue
an Information Request in this instance, it is considered that these
changes to the current proposal can only be facilitated under section
3.2.9 of IPA.
Council officers also request the submission of an amended plan of
development that only shows those land uses for which a
development permit is being sought. Whilst the plans submitted to
Council on 23rd November 2006 show how the current proposal can
potentially integrate with the surrounding Canungra township, an
amended plan is required to eliminate any confusion regarding what
aspects of development that approval is being sought. In particular,
reference to the relocation of the ambulance station and future
development and car park sites are requested to be omitted.”
[19] On 18 April 2007 Council sent a further Acknowledgment Notice. The letter noted
the amendments of 23 November 2006 and went on, “Please provide an amended
plan of development that reflects these changes so that we can start the assessment
of your application”.
-- 5 of 9 --
6
[20] The EPA response was not made until 6 June 2007. Its decision was to grant the
application in full, with conditions. The standard sewerage treatment works were
approved.
The Submissions
[21] It was common ground here, that s 3.2.9 of IPA did apply to the amended
application. That is, changes that were made were not in response to a statutory
Information Request from Council. See s 3.2.9(5). Therefore, s 3.2.9(3)(ii) applied.
As there were referral agencies, the IDAS process had to start again from the start of
the acknowledgment period. That remains Council’s position.
[22] For Canungra Commercial, it was submitted that the court’s discretion should be
exercised under 4.1.5A of IPA:
“How court may deal with matters involving substantial
compliance
(1) Subsection (2) applies if in a proceeding before the court the
court –
(a) finds a requirement of this Act, or another Act in its
application to this Act, has not been complied with, or has
not been fully complied with; but
(b) is satisfied that the non-compliance, or partial compliance,
has not substantially restricted the opportunity for a person
to exercise the rights conferred on the person by this or any
other Act.
(2) The court may deal with the matter in the way the court considers
appropriate.”
[23] The requirement, in s 3.2.9(3)(a)(ii), is the need to start the application process
again, following Council’s second Acknowledgment Notice. For Canungra
Commercial, it was submitted there was no utility in that course, as there would
simply be a repetition of the existing steps, and that would be a waste of time,
-- 6 of 9 --
7
money, and resources. It was submitted that no one had lost an opportunity to
object to the proposal.
[24] For the Council, it was submitted that it, and the concurrence agencies, would lose
the right to again issue Information Requests. The application should be dealt with
according to law.
The Decision
[25] The submissions on behalf of Canungra Commercial should be accepted, for several
reasons. First, it is true that the amended plan, which was advertised to the public,
did show an “existing ambulance centre to be relocated” and “a future car park and
development site”. In another part of the plan, there was an area described as
“future ambulance centre, 1,600m2 ”. Those notations were suggested by the
Council officers. They were meant to show such changes, to follow as a result of
the present proposal. In my opinion, there is no reasonable prospect of any person
interested in the proposal being misled. The proposal in the public notices did not
refer to those things. The information was likely to assist the members of the public,
by giving them advance notice of some of the likely consequences of the
development. Canungra Commercial had no intention of getting approval for any
such uses. Those uses were included at the suggestion of Council officers, or a
councillor.
[26] Secondly, the question of the changed access can be dealt with by Council when
considering the application. The service driveway shown on the western side of
SD04 has to be omitted. The entrance and exit shown on the plans has to be a “left
in/left out” arrangement. A pedestrian crossing to the primary school is to the west
of this proposed development, along Christie Street. The letters from the submitters
-- 7 of 9 --
8
show concerns about the safety of children on that crossing. Those concerns were
also held by Main Roads. The access has to be at least 20 metres from the school
crossing. The effect is that the impact of the advertised plans will be less, if they
are approved along the lines required by Main Roads.
[27] Thirdly, it appears from Mr Kelly’s affidavit that the amended plans were sent to
Council and to the concurrence agencies.
[28] Fourthly, Council officers have been involved from the time of the original
application. The Council chose to deal with the matter by informal discussions,
rather than by way of an Information Request. That was an advantage to Council.
An Information Request could only deal with an existing proposal, while the
informal discussions ranged much further, and resulted in changes to the proposal.
[29] Fifthly, after Mr Kelly’s letter of 23 November, making clear what had been done,
Council made no response until 30 January 2007.
[30] Council had no power to excuse non-compliance with the requirements of the
Integrated Planning Act. Its insistence upon the need for a new Acknowledgment
Notice is understandable. It is this court which has the power to excuse compliance,
in appropriate circumstances. It is appropriate to do so in this case, for the above
reasons. The non-compliance with s 3.2.9 of IPA has not substantially restricted the
opportunity of any person to exercise the rights to make a submission about the
proposed development. The approach of Judge Quirk in Lali Investments Pty Ltd v
Burnett Shire Council (2004) QPELR 25 at 27, should be followed – that is, if the
opportunity to make submissions is not substantially restricted, the object of
s 4.1.5A is to avoid waste of time and assets (both public and private) as a result of
-- 8 of 9 --
9
what is nothing more than a technical deficiency with no consequences of any
substance.
[31] Here, the public has been fully informed about the proposal, in its final form.
[32] In my opinion, the decision of the Court of Appeal in Metrostar v Gold Coast City
Council (2006) QCA 410 does not assist the Council. There, the Court of Appeal
held that the court has power under s4.1.5A to make orders putting a person who
was noncompliant in the same position as would prevail if there had been
compliance, so long as the non-compliant party is not placed in a better position
than the party would be in had they adhered to the requirements of the IPA. In this
case, there is no non-compliance on behalf of Canungra Commerical. In Metrostar,
that company failed to ask for approval for changes to the development. Therefore,
it contravened the development approval, and carried out assessable development
without a development permit. Here the court should exercise its discretion to allow
non-compliance with s3.2.9 IPA. Canungra Commercial is not seeking any
significant advantage, by not observing the requirements of s 3.2.9.
[33] There should be an order that the assessment of the plan of development proceed as
if s 3.2.9 of IPA did not apply.
-- 9 of 9 --