ABC Developmental Learning Centres Pty Ltd v Pine Rivers Shire Council & Ors [2007] QPEC 38 (2007) QPELR 508
PLANNING & ENVIRONMENT COURT
OF QUEENSLAND
CITATION: ABC Developmental Learning Centres Pty Ltd v Pine Rivers
Shire Council & Ors [2007] QPEC 038
PARTIES: ABC DEVELOPMENTAL LEARNING CENTRES PTY
LTD ACN 010 788 502
Appellant
V
PINE RIVERS SHIRE COUNCIL
Respondent
And
MARK PERRY ARCHITECTS
First Co-Respondent
And
STATE OF QUEENSLAND
Second Co-Respondent
FILE NO/S: BD1725/2005
DIVISION: Planning and Environment
PROCEEDING: Application for costs
ORIGINATING
COURT: Planning and Environment Court of Queensland, Brisbane
DELIVERED ON: 2 May 2007
DELIVERED AT: Brisbane
HEARING DATE: 23, 27 April 2007
JUDGE: Alan Wilson SC, DCJ
ORDER: Application for costs dismissed
CATCHWORDS: PLANNING – PLANNING LAW – COSTS – COSTS OF
PROCEEDING – Integrated Planning Act 1997, s 4.1.23 –
discretion to award costs – whether proceedings instituted
merely to delay or obstruct – whether proceeding or part of
proceeding frivolous or vexatious – whether default in
observation of court’s procedural requirements
-- 1 of 7 --
2
Integrated Planning Act 1997, s 4.1.23
Cases considered:
Dawson v Maroochy Shire Council [2004] QPELR 254
Hall v Nanango Shire Council [2006] QPELR 278
Mudie v Gainriver Pty Ltd (No. 2) [2003] 2 Qd R 271
O’Connor v Herberton Shire Council [1998] QPELR 485
Oakden Investments Pty Ltd v Pine Rivers Shire Council
[2003] QPELR 333
R D Williams Tractors Pty Ltd v Queensland [1998] QPELR
26
Reelaw Pty Ltd v Queensland Heritage Council [2005]
QPELR 335
Walsgott v Maroochy Shire Council [2005] QPELR 521
COUNSEL: R Litster for respondent/appellant
M Howard for first applicant/first co-respondent
SOLICITORS: Dibbs Abbott Stillman for appellant
First applicant/first co-respondent self represented
[1] This matter, involving an application for costs by the first co-respondent, was
originally heard on 23 April 2007. The parties were advised that judgment, with
Reasons, would be delivered at 9.15am on 27 April 2007. On 26 April 2007, Mr
Howard, representing the first applicant/first co-respondent, sent an email to my
Associate raising, and seeking to introduce, what was said to be new material which
could affect the decision in the application. When the judgment was called on at
9.15 on 27 April 2007 it was stood over until later in the morning.
[2] During submissions at that later time, Mr Litster, Counsel for the appellant, fairly
categorised what was sought as an application by the first co-respondent for an
adjournment of his earlier application (the original application for costs) so that new
material might be obtained. For reasons which follow, I am not persuaded an
adjournment is necessary, or appropriate.
[3] In April 2005 Pine Rivers Shire Council (“the Council”) allowed an application by
the first co-respondent to develop a childcare centre on land at 47 Old Dayboro
Road. Petrie. The appellant, ABC Developmental Learning Centres Pty Ltd
(“ABC”), had lodged a submission opposing the development application and,
following Council’s approval notwithstanding that submission, brought this appeal
in May 2005.
[4] The appeal was listed for hearing in this court commencing on 30 March 2007. The
appellant signified on that day that it would consent to an order dismissing the
appeal. The co-respondent, represented by Mr Howard, indicated a wish to seek
costs against the appellant. Directions about an exchange of affidavit material
between those parties, concerning the claim for costs, were given by his Honour
Judge Rackemann and the matter was listed for hearing on 23 April 2007. Council
and the second co-respondent were excused from attending at that hearing.
[5] Mr Howard is not, I understand, a member of the firm of architects shown as the
first co-respondent. Two firms of solicitors have previously acted for that party but
-- 2 of 7 --
3
the second withdrew in early November 2006. No notice appointing Mr Howard or
Ms Wilhemina Howard, who has also played an active part in the proceedings, has
ever been filed but Mr Litster of counsel, for the appellant, sensibly indicated no
point would be taken about that aspect of the matter.
[6] Mr Howard filed an affidavit and sent written submissions signifying the claim for
costs was advanced in reliance upon s 4.1.23(2)(a), and (b) of the Integrated
Planning Act 1997 (IPA), which relevantly provide:
4.1.23
(1) Each party to a proceeding in the court must bear the party’s own costs
for the proceeding.
(2) However, the court may order costs for the proceeding (including
allowances to witnesses attending for giving evidence at that
proceeding) as it considers appropriate in the following circumstances –
(a) The court considers the proceeding was instituted merely to
delay or obstruct;
(b) the court considers the proceeding (or part of the proceeding) to
have been frivolous or vexatious;
…
[7] Mr Howard’s submissions about s 4.1.23(2)(a), and his affidavit, were directed
towards two matters: first, a general complaint that ABC, said to be the largest
childcare centre operator in Australia and a potential rival of the co-respondent’s
proposed development, submitted its appeal merely to delay the development for as
long as possible with the goal, ultimately, of forcing the respondent to discontinue
it. The second complaint related particularly to alleged delay in the proceedings
between the making of an amended Directions Order by Rackemann DCJ on 10
November 2006, continuing through to the day the appeal was due to commence on
30 March 2007.
[8] Mr Madden, the solicitor for ABC who has carriage of the matter, has also filed a
lengthy affidavit disputing some of Mr Howard’s claims about the causes, and
circumstances, of some of the delays in procedural steps involving the exchange of
expert’s reports, expert’s meetings and the like. Neither party required the other for
cross-examination, and I am unable to resolve where the blame for these delays, if
any, might lie.
[9] The delays complained of also have to be considered, however, in the context of
general delay in the course of the proceedings including, in particular, the first co-
respondent’s failure to take any steps until late in 2006 to advance the appeal. The
parties first appeared in court in August 2005 seeking directions, but no order was
made. It was not until the second part of 2006, when the appellant’s solicitors
complained, that the first co-respondent took steps to meet its obligation to file an
affidavit establishing compliance with public notification requirements under Ch 3
Pt 4 of IPA. On 6 September 2006 further directions were made about the conduct
of the matter, including an order that it be listed for hearing for three days in the
court’s sittings in December 2006. The parties exchanged lists of documents but
-- 3 of 7 --
4
there arose, then, a further dispute about the adequacy of the first respondent’s
disclosure; and, the notification, by the appellant, of further issues in the appeal.
[10] On 10 November 2006 Rackemann DCJ gave further directions. It was ordered that
the appellant answer a request from the first co-respondent for further and better
particulars by 22 November 2006; that on or before 1 December 2006 the parties
exchange lists specifying the names and fields of expertise of each expert they
would retain; that those experts meet on or before 15 December 2006; that the
parties hold “without prejudice” meetings in December 2007 and January 2007;
and, that the matter be placed in the February 2007 sittings. Subsequently on 19
January 2007 this order of events was again changed, and the matter was moved to
the March 2007 sittings.
[11] The first co-respondent’s principal complaint is that these various steps were
delayed, without satisfactory explanation and, it may be inferred, mischievously, by
the appellant. Mr Madden, for the appellant, denies these things and offers
plausible explanations, in his lengthy affidavit, for the delays which actually
occurred. As noted earlier I am unable to resolve these questions, which descend to
matters of credit but are presently mere untested assertions. It is to be noted,
however, that the delays since November last year have not been lengthy and cannot
be described, in the ordinary hurly-burly of proceedings in this court, as either
surprising or inordinate.
[12] The meaning and effect of s 4.1.23 generally, and some of its sub-sections in
particular, were considered in Walsgott v Maroochy Shire Council [2005] QPELR
521. The cases traversed in that decision included the judgment of Quirk DCJ in
Oakden Investments Pty Ltd v Pine Rivers Shire Council [2003] QPELR 333 in
which his Honour said, at 334:
The operative word is “merely”. A sensible interpretation of the sub-section would
indicate that it contemplates an absence of any real merit in the appellant’s case (or
a basis for belief on the appellant’s part in the presence of some such merit). A
desire to delay or obstruct a project would not, in itself, be enough.
[13] In Dawson v Maroochy Shire Council [2004] QPELR 254 Dodds DCJ observed, at
256:
The discretion to make a costs order exists only in limited circumstances. The
circumstances in s 4.1.23(2)(a) IPA requires not just that the person instituting the
proceedings have a desire to delay or obstruct but that was their only purpose.
[14] In Walsgott it was said, at 524:
[11] Raising serious questions in a proceeding may not raise a shield against the
operation of the sub-section. Nor can it be allowed to mask an applicant’s true
motive; but when, as here, the applicant can show that real issues surround its
application, the conclusion that its sole motive was delay or obstruction is not
readily reached. When genuine issues are manifest it may be relatively easy for an
applicant, in a matter of this kind, to show “public interest character” of the kind
mentioned in Mudie.1
1 Mudie v Gainriver Pty Ltd (No. 2) [2003] 2 Qd R 271.
-- 4 of 7 --
5
[15] Affidavits filed on the appellants behalf show that it retained experts in a number of
disciplines, and those experts attended meetings with experts in the same
disciplines, retained on behalf of the co-respondents; and, joint experts’ reports
were prepared in late January 2007. That evidence also establishes that the experts
were largely able to reach agreement about matters raised in the appeal, save for the
terms of any conditions relating to the hours of operation. Eventually, although the
evidence is not entirely clear, it seems the appellant resolved to abandon all
arguments about proper conditions, and the appeal itself.
[16] The sub-section looks to the institution of the proceedings but there is no good
reason to construe the phrase “… was instituted merely to delay or obstruct” as
involving a sole, or primary focus upon the appellant’s motives in beginning the
proceedings. Rather, as the cases already mentioned appear to accept, the
appellant’s conduct ought fairly to be looked at on the wider canvass of the appeal
proceeding itself. That construction is supported by the introductory words in sub-
section (2) which extend the ambit of a potential costs order to include costs of
witnesses who attend to give evidence.
[17] Sub-section (2)(a) is often likely, it might be thought, to present some hurdles to a
party seeking to rely upon it because of the implied requirement to establish motive
– in effect, to lift the veil of the proceedings themselves and show that what lies
beneath is wholly, or in the main, an intention to delay or obstruct. Certainly, when
the legislation permits any person to make a submission (s 3.4.9)2 and then gives
submitters a right to appeal (s 4.1.28), it will be a rare case in which the mere fact of
an appeal itself will be sufficient evidence, without anything else, of conduct which
offends the sub-section.
[18] The evidence here falls short of establishing the proceeding should attract the
operation of the sub-section. Despite ABC’s position as a competitor, it was
lawfully entitled to appeal, and the history of the action itself is not redolent of the
kind of improper motive against which the provision turns its face. The proceeding
was, from time to time, advanced by ABC in the face of dilatory conduct on the part
of the first co-respondent; the original submission raises legitimate grounds for
objection; the notice of appeal has the same qualities; and, the progress of the appeal
itself (while a little disorganised from time to time) does not suggest conduct based
upon some improper motive – in particular, a motive founded in nothing more than
a desire to delay, or obstruct. The fact the appeal eventually collapsed can be
ascribed to the evaporation of issues but, again, that is not an uncommon event in
this jurisdiction after experts undertake the processes prescribed by Practice
Direction 1 of 2006.
[19] For these reasons the first co-respondent has failed to persuade me that it is proper
to find the proceeding was instituted merely to delay, or obstruct.
[20] As to s 4.1.23(2)(b), in Mudie (supra) McMurdo P and Atkinson J said at 204:
Unquestionably, something much more than lack of success needs to be shown
before a party’s proceedings are frivolous or vexatious … where the proceedings
are vexatious or oppressive will turn on the circumstances of the case and will
include public policy considerations and the interests of justice.
2 See ‘Planning and Development Queensland’, Fogg, Meurling and Hodgetts, para [3705]
-- 5 of 7 --
6
[21] Other decisions of this court show that before proceedings will be categorised in
this way they must be clearly seen to be manifestly groundless; and, they will not
usually be so classified if they are not groundless, superficial, or devoid of merit3 .
[22] In Hall v Nanango Shire Council [2006] QPELR 278, McLauchlan QC, DCJ said at
279:
Various cases have referred to the definition of these words (frivolous or
vexatious) in the Macquarie Dictionary, and the shorter Oxford Dictionary. There
is, in my view, no necessary connotation of deliberate conduct in these
expressions. Rather it is a question of whether the proceeding or part of it,
including the conduct therefore by the relevant party, should be seen upon an
objective examination to have been frivolous or vexatious, that is, characterised by
a lack of seriousness or sense, or vexing or annoying. That would normally
involve conclusions about the proceeding itself, and about the conduct of the party
concerned in relation to the proceeding.
[23] Mr Howard’s complaint under this head focuses upon ABC’s ultimate failure to
adduce evidence from noise or traffic experts which showed any meaningful error
on Council’s part in approving the development application. He says “… none of
the appellant’s concerns have been substantiated as being of real concern”.
Against that, however, the history of the matter and the issues it involved (which
have already been traversed) do not suggest the appellant’s submission or grounds
of appeal were unarguable, superficial, or devoid of merit.
[24] It is possible they were not strong (and could never have been described as strong)
but they were tested in the fire of experts’ meetings and reports and while it seems
they were, figuratively, consumed by that flame, that does not automatically mean
they can have the adjectives used in sub-section (2)(b) attached to them. The relief
is discretionary, and the various circumstances set out in sub section (2) must be
considered in the light of the fundamental premise about costs in this jurisdiction
contained in sub-section (1)4 . This is not a case where it would be fair to categorise
ABC’s conduct as frivolous or vexatious.
[25] Although the matter was not argued by Mr Howard, the fact he was self represented
means it is also appropriate to consider whether or not a remedy might have been
available to him under s 4.1.23(2)(e), which attracts the discretion to award costs
where “… a party has incurred costs because another party has defaulted in the
court’s procedural requirements”. The history of the appeal, discussed earlier,
shows some failures on the part of the appellant to meet the requirements of
Directions Orders, but that occurred in circumstances where the first co-respondent
was also, it appears, responsible from time to time for delays and failures and non-
compliance. As previously remarked, the dispute about responsibility for these
delays involves untested claims and counter-claims about fault; and, again, the
appeal ultimately came to a hearing within a reasonable period and with delays
which are not uncommon, or surprising.
3 R D Williams Tractors Pty Ltd v Queensland [1998] QPELR 26; O’Connor v Herberton Shire
Council [1998] QPELR 485; Dawson v Maroochy Shire Council (supra); Reelaw Pty Ltd v
Queensland Heritage Council [2005] QPELR 335
4 Wallsgott v Maroochy Shire Council (supra) at 523, para [4] and [5].
-- 6 of 7 --
7
[26] The new material Mr Howard sought to introduce on 27 April 2007 relied upon a
document which had apparently been in the possession of the first co-respondent
since August 2005. The order of his Honour Judge Rackemann on 30 March 2007
provided a timetable, up to 20 April 2007, for the filing and serving of any affidavit
material upon which any party intended to rely at the hearing of the costs
application. Mr Howard filed an affidavit on 10 April 2007 which does not mention
the matter he now wishes to raise.
[27] The document he now presents merely suggests that another company which had
expressed an interest in the site some time ago may be connected with the appellant.
The first co-respondent seeks more time to investigate that possibility. An affidavit
filed by leave on behalf of the appellant on 27 April 2007 shows, however, that
while this other company has been engaged to build centres for ABC, they are not
otherwise affiliated.
[28] The further enquiries Mr Howard seeks time to make are intended to support, it is
said, a possible submission that if the first co-respondent had awarded a lease of the
site to this other company, the appellant would have discontinued the appeal. That
submission would support, it is further said, the first co-respondent’s contentions
under s 4.1.23(2)(b). It plainly rests, however, on a chain of nebulous things.
Firstly, it is unclear whether the allegations said to support it can, in fact, be made
out. Secondly, the limited evidence said to warrant further investigation has been
produced very late, and in contravention of clear directions from the court.
Ultimately, even if these two hurdles are overcome, it remains doubtful that the
submission would avail the first co-respondent in its attempts to establish grounds
under sub-section (2).
[29] Even if a close commercial connection between ABC and this other company was
shown to exist the first co-respondent would yet have to establish, on the balance of
probabilities, that the connection could only reasonably be viewed as pointing to
one outcome, or course of events: ABC abandoning its appeal. Then the Court must
be persuaded this is a sound, and just, basis for a finding the proceedings offend s
4.1.23(2). The various components of the submission and the links between them
are all too uncertain, and tenuous. When, as here, it is unclear if they can ever be
made out, and they have also been raised at a very late hour, they do not warrant a
further adjournment of the application.
[30] For these reasons the first co-respondent’s application is dismissed.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2007/038