Cant Contracting Pty Ltd v Casella & Anor [2006] QCA 538 [2007] 2 Qd R 13
SUPREME COURT OF QUEENSLAND
CITATION: Cant Contracting P/L v Casella & Anor [2006] QCA 538
PARTIES: CANT CONTRACTING PTY LTD
ACN 079 036 025
(plaintiff/respondent)
v
CON CASELLA
(defendant/appellant)
MICHELLE LYNDSAY CASELLA
(defendant/appellant)
FILE NO/S: Appeal No 8063 of 2006
SC No 5925 of 2005
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 15 December 2006
DELIVERED AT: Brisbane
HEARING DATE: 23 October 2006
JUDGES: Williams and Jerrard JJA and Philip McMurdo J
Separate reasons for judgment of each member of the Court,
each concurring as to the order made
ORDER: 1. Appeal allowed
2. The judgment of 1 September 2006 is set aside
3. The application for summary judgment is dismissed with
costs
4. The respondent is to pay the appellants’ costs of the
appeal
CATCHWORDS: BUILDING, ENGINEERING AND RELATED CONTRACTS
– REMUNERATION – RECOVERY ON QUANTUM
MERUIT – IN GENERAL – where the respondent agreed to
construct poultry sheds for the appellants – substantial work had
been carried out before the Laidley Shire Council issued a stop
work order – pursuant to the Building and Construction Industry
Payment Act 2004 (Qld) the respondent sought progress
payments by way of a payment claim – the appellants did not
serve a corresponding payment schedule on the respondent –
summary judgment was awarded against the appellants – where
the appellants had filed a defence and counter-claim against
summary judgment arguing that the respondent did not hold an
appropriate licence at the time construction was carried out –
-- 1 of 18 --
2
whether the respondent was entitled to summary judgment,
regardless of the fact that he may not have held an appropriate
construction licence in contravention of s 42(1) Queensland
Building Services Authority Act 1991 (Qld)
Building & Construction Industry Payment Act 2004 (Qld), s 3, s
7, s 8, s 13, s 17, s 18, s 19, s 26
Home Building Act 1989 (NSW), s 10, s 94
Queensland Building Services Authority Act 1991 (Qld), s 42
Brodyn Pty Ltd v Davenport [2004] NSWCA 394; (2004) 61
NSWLR 421, distinguished
Lucas Stuart Pty Ltd v Council of the City of Sydney [2005]
NSWSC 840; File No 50077 of 2005, 23 August 2005,
distinguished
COUNSEL: J A Griffin QC, with T F Mylne, for the appellants
P L O’Shea SC, with M J F Burnett, for the respondent
SOLICITORS: Graham & Associates for the appellants
Holding Redlich for the respondent
[1] WILLIAMS JA: On 1 September 2006 the respondent (the plaintiff in the action)
obtained summary judgment against the appellants (the defendants in the action) in
the sum of $493,339.45 with interest and costs. The appellants have appealed
against that decision. To appreciate the submissions on the hearing of the appeal it
is necessary to set out the history of dealings between the parties.
[2] By contract made 1 November 2004 the respondent agreed to construct five poultry
sheds for the appellants at a cost of $211,143 per shed. Substantial work was
carried out by the respondent until the Laidley Shire Council issued a stop work
order on 14 February 2005. By then the appellants had made payments totalling
$522,578.95 pursuant to the agreement.
[3] The respondent then commenced proceedings in the Supreme Court on 21 July 2005
seeking to recover what it asserted was the balance due and owing. By the original
statement of claim filed 21 July 2005 the respondent claimed the sum of
$348,385.95 as being due and payable pursuant to the agreement. In the alternative,
a claim was made on the basis of the reasonable cost of labour and material
supplied; it was asserted that a total of $841,825.76 was payable on that basis and in
consequence a claim was made for $318,556.47 as being due and owing.
[4] The appellants filed a defence and counter-claim on 29 August 2005. In paragraph
[8] of that pleading it was alleged that the respondent was in breach of s 42(1) of the
Queensland Building Services Authority Act 1991 (Qld) ("the Building Act") which
provided that a person must not carry out building work unless the appropriate
licence was held. The assertion was made that the respondent did not hold the
appropriate licence and therefore contravened s 42(1). It was then asserted that the
respondent's only remedy was pursuant to s 42(3) and s 42(4) of the Building Act.
Again in the counter-claim (paragraph [11]) it was asserted that the respondent did
not hold the requisite building licence to perform the work the subject of the
agreement.
-- 2 of 18 --
3
[5] In a reply filed 13 October 2005 the respondent effectively put in issue whether it
held the appropriate licence at the material time.
[6] Pursuant to r 378 of the UCPR the respondent amended its statement of claim on
5 July 2006. Those amendments introduced a claim pursuant to the Building and
Construction Industry Payments Act 2004 (Qld) ("the Payment Act"). It was
alleged that the Payment Act applied to the contract and that in terms of that Act the
appellants were responsible for payment. It was then alleged that between 1
November 2004 and 4 April 2005 the respondent carried out work pursuant to the
contract. It was then asserted that work to the value of $493,339.45 had been
carried out and payment had not been received. It was asserted that pursuant to s 13
of the Payment Act the respondent was entitled to progress payments in that sum.
Then it was alleged that on 31 March 2006 the respondent served a payment claim
pursuant to s 17 of the Payment Act for the sum in question and that no payment
schedule was served on the respondent by the appellants within the time limit
prescribed by s 18(4) of that Act. Reference in the pleading was then made to other
provisions found in s 18 and s 19 of the Payment Act, and the respondent claimed
the sum of $493,339.45 as a debt due and owing pursuant to s 19(2)(a)(i) of the
Payment Act.
[7] In paragraphs [8A], [8B] and [8C] of the amended defence and counterclaim of
19 July 2006, the appellants pleaded defences to the claim under the Payment Act.
In essence it was asserted that nothing in the Payment Act derogated from the
obligation of the respondent as a builder to comply with s 42 of the Building Act. It
was then alleged that the respondent was not entitled to any benefits under the
Payment Act, but was limited to a remedy pursuant to s 42(3) and s 42(4) of the
Building Act.
[8] With the pleadings in that state the respondent applied for summary judgment by
application filed 3 August 2006; the matter was heard on 24 August 2006 and
judgment given for the respondent on 1 September 2006.
[9] Before considering the reasons for judgment of the Chief Justice it is necessary to
refer to the relevant provisions of the statutes in question. The Building Act defines
"building work" as including the "erection or construction of a building"; it was
disputed that the construction of the poultry sheds in question constituted building
work. Section 42(1) of that Act then provides:
"A person must not carry out, or undertake to carry out, building
work unless that person holds a contractor's licence of the
appropriate class under this Act."
Contravention of the section constitutes an offence; subsection (9). Relevantly then
for present purposes subsection (3) thereof provides:
"Subject to subsection (4), a person who carries out building work
in contravention of this section is not entitled to any monetary or
other consideration for doing so."
[10] Subsection (4) then provides some amelioration for the builder who carries out work
in contravention of the section. Such a person may claim "reasonable remuneration
for carrying out building work" but only as calculated in accordance with the
provisions of that subsection. The builder is not entitled to recover anything for his
-- 3 of 18 --
4
own labour or any profit; the claim is limited to the actual cost of supplying other
labour and materials.
[11] Leaving aside for the moment the provisions of the Payment Act, if it was held that
the respondent did not hold the requisite licence for carrying out the building work
in question, then it would not be entitled to recover the amounts claimed in the
statement of claim as originally drawn. It would not be entitled to recover monies
due under the contract or on the common law quantum meruit basis alleged in that
statement of claim. It would be restricted to a claim quantified in accordance with
s 42(4) of the Building Act.
[12] The long title of the Payment Act states that it is an "Act to imply terms in
construction contracts, to provide for adjudication of payment disputes under
construction contracts, and for other purposes." Section 3 relevantly provides that
the Act applies to "construction contracts"; that expression is then defined in s 10(2)
to include "building work" as defined in the Building Act.
[13] Sections 7 and 8 then deal with the objects of the Act. Section 7 provides that the
"object of this Act is to ensure that a person is entitled to receive, and is able to
recover, progress payments if the person - (a) undertakes to carry out construction
work under a construction contract". That is provided for pursuant to s 8 by
"granting an entitlement to progress payments whether or not the relevant contract
makes provision for progress payments". The expression "reference date" is defined
to mean either the date stated in a contract as the date on which a progress payment
may be made or in the absence of such a provision the last day of the month in
which the construction work was first carried out and the last day of each
succeeding month. Relevantly s 12 then provides:
"From each reference date under a construction contract, a person is
entitled to a progress payment if the person has undertaken to carry
out construction work . . . under the contract".
It would appear from the definition of "progress payment" in Schedule 2 and section
13, that the claim under the Act could be for the whole of the contact price.
[14] That then leads to sections 17, 18 and 19 which are central to the resolution of the
issues raised in this case; relevantly they provide:
"17(1) A person mentioned in section 12 who is or who claims to
be entitled to a progress payment (the claimant) may serve a
payment claim on the person who, under the construction
contract concerned, is or may be liable to make the payment
(the respondent).
(2) A payment claim -
(a) must identify the construction work . . . to which the
progress payment relates; and
(b) must state the amount of the progress payment that the
claimant claims to be payable (the claimed amount);
and
(c) must state that it is made under this Act.
-- 4 of 18 --
5
. . .
18(1) A respondent served with a payment claim may reply to the
claim by serving a payment schedule on the claimant.
(2) A payment schedule -
(a) must identify the payment claim to which it relates;
and
(b) must state the amount of the payment, if any, that the
respondent proposes to make (the scheduled amount).
(3) If the scheduled amount is less than the amount claimed, the
schedule must state why the scheduled amount is less and, if
it is less because the respondent is withholding payment for
any reason, the respondent's reasons for withholding
payment.
(4) Subsection (5) applies if -
(a) a claimant serves a payment claim on a respondent;
and
(b) the respondent does not serve a payment schedule on
the claimant within . . . 10 business days after the
payment claim is served.
(5) The respondent becomes liable to pay the claimed amount to
the claimant on the due date for the progress payment to
which the payment claim relates.
19(1) This section applies if the respondent -
(a) becomes liable to pay the claimed amount to the
claimant under section 18 because the respondent
failed to serve a payment schedule on the claimant
within the time allowed by the section; and
(b) fails to pay the whole or any part of the claimed
amount on or before the due date for the progress
payment to which the payment claim relates.
(2) The claimant -
(a) may -
(i) recover the unpaid portion of the claimed
amount from the respondent, as a debt owing to
the claimant, in any court of competent
jurisdiction;
-- 5 of 18 --
6
. . .
(4) If the claimant starts proceedings under subsection 2(a)(i) to
recover the unpaid portion of the claimed amount from the
respondent as a debt -
(a) judgment in favour of the claimant is not to be given
by a court unless the court is satisfied of the existence
of the circumstances referred to in subsection (1); and
(b) the respondent is not, in those proceedings, entitled -
(i) to bring any counterclaim against the claimant;
or
(ii) to raise any defence in relation to matters
arising under the construction contract."
[15] It was not disputed in the present case that the appellants did not serve a payment
schedule on the respondent in accordance with the provisions of the Payment Act.
In support of the application for summary judgment the respondent relied on
s 19(4)(b) of that Act.
[16] On the hearing of the application for summary judgment there was no dispute about
the procedural regularity of what the respondent did relying on the Payment Act.
The Chief Justice noted in his reasons that the contract between the parties entitled
the respondent to "progress payments"; prima facie that brought the Payment Act
into play.
[17] The Chief Justice then said that on the basis of the pleadings as originally drafted
the respondent had to "confront the circumstance that . . . [it] did not, when it
carried out the relevant work, hold a requisite contractor's licence". He noted that if
that was eventually established the respondent "would be limited, in its recovery by
s 42(4)" of the Building Act. But he then recorded the submission of counsel for the
respondent that "that would be irrelevant to the claim added by amendment,
founded on s 19" of the Payment Act.
[18] The issue raised by the appellants at first instance was that the Payment Act "should
be read as subject to the qualified right of recovery limited by s 42" of the Building
Act. Counsel for the respondent met that by saying that in order to rely on the
absence of the requisite licence the issue had to be raised in a "payment schedule".
Thus the Chief Justice was able to identify the issue before him as follows:
"The issue is whether, the defendants having failed to deliver a
payment schedule the defendants can resist the plaintiff's apparent
right to judgment under s 19(2)(a) by subsequently raising the
licensing issue; in other words, whether the ultimate operation of the
mechanism established by the [Payment Act] is to be read as subject
to a supervening qualification arising from s 42 of the [Building
Act]."
[19] The Chief Justice referred to the absence of any express qualification giving effect
to the condition of the appellants in s 19 and to the decisions of Einstein J in Lucas
Stuart Pty Ltd v Council of the City of Sydney [2005] NSWSC 840 and the New
-- 6 of 18 --
7
South Wales Court of Appeal in Brodyn Pty Ltd v Davenport (2004) 61 NSWLR
421. The Payment Act appears to be based on the Building and Construction
Industry Security of Payment Act 1999 (NSW) ("the NSW Act"). After referring to
those matters the Chief Justice said he accepted the submissions of counsel for the
respondent and granted summary judgment.
[20] The principal submission on behalf of the appellants in this Court is that the
Payment Act does not overrule s 42 of the Building Act, and that when the Payment
Act refers to a "construction contract" it must be referring to a lawful contract.
Further, the use of the word "entitled" in sections 7, 12 and 17 must mean lawfully
entitled.
[21] Counsel for the respondent in a very careful argument contended that the Payment
Act was designed to ensure that a contractor received progress payments on an
interim basis, with the parties having the right at a later point of time to litigate all
issues arising under the construction contract (cf s 100 of the Payment Act and
Roadtek, Department of Main Roads v Davenport and Anor [2006] QSC 47). On
that approach the failure to raise the illegality in a "payment schedule" precluded the
appellants from relying on that illegality on the summary judgment application
(s 19(4)(b)(ii) of the Payment Act).
[22] Because the judgment at first instance and the submissions on appeal on behalf of
the respondent relied heavily on the reasoning in the New South Wales decisions
referred to, it is necessary to consider the relevant New South Wales legislation and
the reasoning in those cases.
[23] Section 15 of the NSW Act is in the same terms as s 19 of the Payment Act.
Einstein J in Lucas Stuart was concerned with a claim for summary judgment in
circumstances where the principal failed to serve a payment schedule. On the
hearing of the summary judgment application the principal sought to rely on a
defence of equitable estoppel and defences under the Trade Practices Act.
Summary judgment was granted. The reasoning emphasised that the legislation
provided for a determination on "an interim basis" which was "subject [to] a final
hearing in the fullness of time". There was no basis for "moving outside of this
scheme" and in consequence it was held that the principal was not entitled, given
the terms of the section, to rely on the matters sought to be raised by way of
defence. Significantly for present purposes, there was no question in that case of
the contract founding the claim for progress payments being illegal or
unenforceable.
[24] The Court of Appeal in Brodyn had to consider a somewhat similar question to that
which arises in the instant case, but it arose in different circumstances. The
contractor delivered a payment claim and the principal responded with a payment
schedule. The matter then went to adjudication, and there was a finding in favour of
the contractor. The contractor then filed that decision in the court and it became
enforceable as a judgment debt (the NSW equivalent of s 31 of the Payment Act).
The principal then applied to the Supreme Court for relief in the nature of certiorari.
That relief was refused at first instance and an appeal was lodged. Between the
lodging of the notice of appeal and it coming on for hearing the principal became
aware for the first time that the contractor did not have at relevant times a licence
under the Home Building Act 1989 (NSW). So far as is relevant s 10 of that Act
provided:
-- 7 of 18 --
8
"(1) A person who contracts to do any residential building work,
or any specialist work, and who so contracts:
(a) in contravention of section 4 (Unlicensed
contracting), or
. . .
is not entitled to damages or to enforce any other remedy in
respect of a breach of the contract committed by any other
party to the contract, and the contract is unenforceable by the
person who contracted to do the work. However, the person
is liable for damages and subject to any other remedy in
respect of a breach of the contract committed by the person."
[25] It is also necessary to have regard to s 94 of that Act; relevantly it provided:
"If a contract of insurance required by section 92 is not in force, in
the name of the person who contracted to do the work, in relation to
any residential building work done under a contract (the uninsured
work), the contractor who did the work:
(a) is not entitled to damages, or to enforce any other remedy in
respect of a breach of the contract committed by any other
party to the contract, in relation to that work, and
(b) is not entitled to recover money in respect of that work under
any other right of action (including a quantum meruit)."
[26] Against that background Hodgson JA, with the concurrence of Mason P and Giles
JA, concluded at 449:
"It was submitted for Brodyn that, because Dasein did not have a
licence under the Home Building Act, the subcontract was illegal
(s 4) and unenforceable (s 10). Accordingly, Dasein was not entitled
to any progress payment.
In my opinion, the civil consequences for an unlicensed contractor
for its breach of s 4 are those set out in s 10, and not any wider
deprivation of remedies. In my opinion this is confirmed by the
different provisions of s 94, which explicitly precludes, in the event
of breach of the insurance provisions, the obtaining of a quantum
meruit unless a court considers it just and equitable. In my opinion,
the remedy given by the Act is not of the nature of damages or any
other remedy in respect of breach of contract nor is it enforcement of
the contract: it is a statutory remedy, albeit one that in part makes
reference to the terms of a contract, and thus it is not affected by s 10
of the Home Building Act.
Accordingly, in my opinion Dasein's failure to have a licence could
not be a ground on which the adjudicator's determination could be
considered void, or for otherwise giving relief in respect of the
determination."
-- 8 of 18 --
9
[27] It will be immediately obvious that s 94 of the Home Building Act is substantially
similar to s 42(3) and (4) of the Building Act; that distinguishes the present case
from Brodyn. Clearly the New South Wales Court of Appeal would have reached a
different conclusion in Brodyn if s 94 and not s 10 applied.
[28] Further, s 10 of the Home Building Act only disentitles the unlicensed contractor to
damages or other remedy in respect of a breach of contract committed by the
principal, where s 42(3) of the Building Act disentitles an unlicensed contractor to
any monetary consideration for work done pursuant to the contract. Hodgson JA
may well have been right in concluding that, under the legislation in question in
Brodyn, a claim for a progress payment was not "enforcement of the contract"; but it
is not necessary to consider that aspect further because of the different statutory
provision in question here. The words "any monetary or other consideration" are of
very wide import and must be given full effect.
[29] It follows that the conclusion in Brodyn is of no assistance when considering the
present appeal. Insofar as the Chief Justice relied on Brodyn in support of his
conclusion he was, in my respectful opinion, wrong. On careful consideration the
reasoning of Hodgson JA, if anything, supports the submission of the appellant in
this case.
[30] Because s 42(3) of the Building Act provides that an unlicensed contractor "is not
entitled to any monetary or other consideration" for doing work pursuant to the
contract, such a contractor cannot be said to have an entitlement to progress
payments pursuant to ss 7, 12 and 17 of the Payment Act.
[31] Counsel for the respondent relied heavily on the reference in s 17 of the Payment
Act to a person "who is or claims to be entitled to a progress payment"; he submitted
that in consequence a person could come within the section even though at the end
of the day it was shown that his claim was unjustified. The inclusion of the
expression "claims to be entitled" is intended, in my view, to meet the situation
where a claim is made under the Payment Act in the face of an ongoing dispute
between the parties as to such entitlement. But that does not meet the present
situation where, given the provisions of the Building Act, the respondent has no
legal entitlement to any monetary consideration for work done pursuant to the
contract.
[32] Counsel for the respondent sought to obtain comfort from the reference in s 26(2) of
the Payment Act to the Building Act. Section 26(2) is concerned with the matters an
adjudicator must consider in arriving at his decision. Subparagraph (a) not
surprisingly obliges the adjudicator to have regard to "the provisions of this Act"
and then it goes on to say regard must also be had to the provisions of the Building
Act Pt 4A to the extent they are relevant. Relevantly Pt 4A of the Building Act deals
with issues such as set-off under building contracts, retention amounts, and late
progress payments. The reference in s 26 of the Payment Act to Pt 4A of the
Building Act is not surprising because the latter is concerned with the calculation of
the amount owing under a building contract.
[33] Counsel for the respondent contended that because there was such a specific
reference to Pt 4A, and no specific reference to s 42, the legislature must have
intended that s 42 of the Building Act was not a relevant consideration when
considering a claim under the Payment Act. Such a submission must be rejected.
-- 9 of 18 --
10
Parliament could not have intended that pursuant to the Payment Act an unlicensed
contractor could immediately recover the whole of the contract price for doing the
work, in the face of the statutory prohibition in the Building Act on such a contractor
recovering any monetary consideration, other than as specified in s 42(4) for doing
work under the contract. It is not a sufficient answer to say that the principal might
subsequently obtain a judgment entitling it to "claw back" that whole of the contract
price.
[34] As already noted the respondent commenced proceedings in the Supreme Court not
relying on the provisions of the Payment Act. In those proceedings the question
whether or not the money claimed was recoverable in the face of s 42 of the
Building Act was squarely raised. The Supreme Court was initially seized of the
issue as to the legality of the contract and, if the respondent's contentions on the
appeal are successful, it would effectively mean that the Court's jurisdiction to
determine that issue was ousted. There are sound reasons, it seems to me, for
concluding that if the parties have joined issue in Supreme Court proceedings on a
particular question, the jurisdiction of the Court to adjudicate upon that issue cannot
be ousted by subsequent reliance on provisions of the Payment Act. But it is not
necessary for the determination of this appeal to express a concluded opinion on
that point.
[35] It is sufficient for present purposes to say that at the time the application for
summary judgment was made there was clearly a triable issue as to the respondent's
entitlement to recover anything under the contract and s 19(4)(b)(ii) did not in the
circumstances then existing preclude the appellant from relying on s 42 of the
Building Act. It follows that summary judgment ought not to have been granted.
The appeal should be allowed, the judgment of 1 September 2006 should be set
aside, the application for summary judgment should be dismissed with costs, and
the respondent should pay the appellant's costs of the appeal. That would enable the
matter to proceed to trial where factual issues relating to the licensing of the
respondent would be determined.
[36] JERRARD JA: In this appeal I have read the judgments of Williams JA and
McMurdo J, and agree with their Honours’ reasons and the orders proposed by
Williams JA. I add the following reasons of my own, which adopt the relevant
facts described by Williams JA.
[37] The Queensland Building Services Authority Act 1991 (Qld) (“the 1991 Act”)
provides in s 42 that a person must not carry out or undertake to carry out building
work unless that person holds a contractor’s licence of the appropriate class under
the 1991 Act. In s 42(3) it provides that “subject to subsection (4), a person who
carries out building work in contravention of this section is not entitled to any
monetary or other consideration for doing so.” Section 42(4) allows such a person
to claim as reasonable remuneration the amount paid by that person in supplying
materials and labour, but not any amount for the person’s own labour, for profit, or
for costs incurred in supplying materials and labour if not reasonably incurred.
Section 42(9) provides that a person who contravenes s 42 commits an offence.
[38] The Building and Construction Industry Payments Act 2004 (Qld) (“the 2004 Act”)
provides a regime for prompt payment of sums claimed as owing under construction
contracts. Those are defined in schedule 2 of the 2004 Act to mean a contract,
agreement or other arrangement under which one party undertakes to carry out
-- 10 of 18 --
11
construction work for, or to supply related goods and services to, another party.
Section 10(2) declares that construction work includes building work within the
meaning of the 1991 Act.
[39] Section 12 of the 2004 Act provides that:
“From each reference date under a construction contract, a person is
entitled to a progress payment if the person has undertaken to carry out
construction work, or supply related goods and services, under the
contract.”
A progress payment is defined in schedule 2 to mean a payment to which a person is
entitled under s 12, and includes, without affecting any entitlement under the
section:
“(a) the final payment for construction work carried out, or for
related goods and services supplied, under a construction
contract; or
(b) a single or one-off payment for carrying out construction
work, or for supplying related goods and services, under a
construction contract; or
(c) a payment that is based on an event or date, known in the
building and construction industry as a ‘milestone
payment’.”
[40] Schedule 2 defines a reference date under a construction contract to mean:
(a) a date stated in, or worked out under, the contract as the date on
which a claim for a progress payment may be made for construction
work carried out or undertaken to be carried out, or related goods
and services supplied or undertaken to be supplied, under the
contract; or
(b) if the contract does not provide for the matter –
(i) the last day of the named month in which the construction
work was first carried out, or the related goods and services
were first supplied, under the contract; and
(ii) the last day of each later named month.
[41] Section 13 provides for the amount of the progress payment. It reads:
“The amount of a progress payment to which a person is entitled in relation
to a construction contract is –
(a) the amount calculated under the contract; or
(b) if the contract does not provide for the matter, the amount
calculated on the basis of the value of construction work
carried out or undertaken to be carried out, or related goods
and services supplied or undertaken to be supplied, by the
person, under the contract.”
-- 11 of 18 --
12
[42] It seems obvious that the 2004 Act has attempted to catch all varieties of
construction contracts, in the expansive definitions of progress payment, reference
date, and in the provisions as to the amount of progress payment. Progress
payments include final payments, single or one off payments, milestone payments;
reference dates, if not provided for, are the last day of each month; the amount of
the progress payment, if not provided for, is the value of the work carried out. The
2004 Act applies to situations where a contract makes no provision for progress
payments at all. But there is no sign of an intent to outflank or override the
requirements in the 1991 Act, that builders be appropriately licensed.
[43] In this matter the appellant defendants pleaded in their original defence that the
respondent plaintiff did not hold the classes of licence required to perform the
building work the subject of the building agreement between the plaintiff and the
defendants, and that accordingly the plaintiff’s only remedy was pursuant to s 42(3)
and (4) of the 1991 Act. Subsequent to that pleading the plaintiff responded by
amending to add a claim under the 2004 Act. The plaintiff’s amended claim under
the 2004 Act was for construction work it had carried out, to a claimed value of
$493,339.45. In paragraph 21 of its amended claim, it pleaded an entitlement,
pursuant to s 13 (of the 2004 Act), to progress payments in that sum under the
contract.
[44] Its counsel on this appeal submitted that, although it was pleaded and not denied
that the respondent plaintiff was an unlicensed builder prohibited from carrying out
or undertaking to carry out that building work, and although it committed an offence
under the 1991 Act by undertaking to carry out that construction work, and although
it was not entitled to any monetary or other consideration for any building work that
it carried out in contravention of s 42, and although by reason of that Act it could
recover only the cost of labour and material supplied, it was nevertheless “entitled”
to a progress payment in terms of s 12 of the 2004 Act for the work it had carried
out or undertaken to carry out. Respectfully, I disagree. The respondent was not
entitled under ss 12 or 13 of the 2004 Act to a progress payment for any building
work it had carried out, because s 42(3) of the 1991 Act says so. The progress
payment it claimed was a monetary consideration for the building work carried out.
The amended defence pleaded in paragraph 8A(b) that the plaintiff was not entitled
to any benefits under the 2004 Act.
[45] The respondent accepted on the appeal that it was not a person “entitled” to a
progress payment within the meaning of s 17(1) of the 2004 Act, although arguing it
was “entitled” under s 12. Section 17(1) reads:
“A person mentioned in section 12 who is or who claims to be
entitled to a progress payment (the claimant) may serve a payment
claim on the person who, under the construction contract concerned,
is or may be liable to make the payment (the respondent).”
However, the respondent contended it was a person who “claims to be entitled” to a
progress payment, albeit not a person who was entitled. Mr O’Shea submitted for
the respondent that “entitled” in s 17 meant entitled both in a “section 12” sense,
and in all senses; thus excluding contractors who did not hold the appropriate
contractor’s licence. Mr O’Shea argued however that contractors without licence
could “claim to be entitled”, and that respondents to s 17 payment claims from
unlicensed contractors could raise the lack of the appropriate licence in the payment
schedule served in response under s 18 of the 2004 Act. He argued that any
-- 12 of 18 --
13
adjudicator to whom the matter was then referred would be obliged to consider the
absence of a licence, by reason of s 26(2)(d) of the 2004 Act, because the point
would be raised in the payment schedule.
[46] Mr O’Shea submitted that the decision in Brodyn Pty Ltd v Davenport (2004) 61
NSWLR 4211 established, for relevantly similar New South Wales legislation,2 the
essential requirements for a valid adjudicator’s determination. Those included the
existence of a construction contract, but did not include that the contract be with a
builder holding the appropriate contractor’s licence. He submitted that the reason
an unlicensed builder could claim to be entitled to a progress payment under s 17
was simply because the 2004 Act clearly provided for claims to be made, and for
payment ordered in respect of them, even if those claims were later shown to be
unjustified. The purpose of the legislation was to provide for a system of quick
payments, with s 100 of the 2004 Act providing for later correction in subsequent
civil proceedings, including orders for restitution of any amount paid.
[47] Assuming the New South Wales Court of Appeal is correct in Brodyn Pty Ltd v
Davenport as to the essential requirements for a valid adjudicator’s determination,
and accepting that the 2004 Act has as its object ensuring that a person entitled to
receive progress payments is able to recover them if the person undertakes to carry
out construction work, the respondent plaintiff was not entitled in relation to the
construction contract, under s 13, to an amount calculated on the basis of the value
of the construction work the plaintiff had carried out. Section 42(3) of the 1991 Act
prevented his being entitled. Mr O’Shea conceded the 1991 Act had the effect that
the plaintiff was not entitled under s 17 to a progress payment. In my opinion the
plaintiff could not claim to be entitled to those payments. It pleaded an entitlement
pursuant to s 13 which it did not have, and pleaded that only after pleadings in this
Court had raised the issue of its being unlicensed. If it was unlicensed, no
investigation (prompt or slow) could advance its s 13 claim to entitlement to a
progress payment.
[48] The appellants’ pleading, if accurate, revealed that the respondent had no proper
claim to be entitled to a progress payment, and accordingly the respondent was not
entitled to serve a payment claim for progress payments on the appellants. It was
appropriate for the appellants to plead, as they did, that the plaintiff was not entitled
to any benefits under the 2004 Act, and although perhaps unnecessary, they could
have sought a declaration to that effect, or an order setting aside service of that s 17
payment claim. Their current pleading, that the plaintiff was not entitled to any
benefits under the 2004 Act by reason of it not holding the appropriate class of
licence, if upheld, has the result that neither ss 17, 18, or 19 of the 2004 Act could
be availed of by the plaintiff. It follows that summary judgment for the plaintiff in
the amount of $493,339.45 should be set aside.
[49] PHILIP McMURDO J: Section 42 of the Queensland Building Services Authority
Act 1991 (Qld) (“the Building Act”) prohibits a person from carrying out, or
undertaking to carry out, building work unless that person holds a licence which is
appropriate for that work. A person who contravenes s 42 commits an offence: s
42(9).
1 [2004] NSWCA 394; Appeal No 40296 of 2004, 3 November 2004.
2 (2004) 61 NSWLR 421 at 441.
-- 13 of 18 --
14
[50] Section 42(3) provides that a person who carries out building work whilst
unlicensed “is not entitled to any monetary or other consideration for doing so”,
except on the limited bases allowed by s 42(4). Yet in the present case, the
respondent builder, which for present purposes had to be treated as unlicensed, was
held entitled to a monetary consideration for doing the work, and without purporting
to limit its claim according to s 42(4). The respondent’s argument, which the Chief
Justice as the primary judge accepted, was that a builder’s entitlement to a progress
payment by the operation of the Building and Construction Industry Payments Act
2004 (Qld) (“the Payments Act”) was not affected by s 42. The Payments Act does
not expressly provide that a builder’s entitlement to a progress payment is outside
the disentitling provisions of s 42 of the Building Act. And s 42(3) is in the widest
terms: it refers to “any monetary or other consideration”, which on any view would
include a payment for (part of) the work.
[51] The Payments Act closely corresponds with the terms of the Building and
Construction Industry Security of Payment Act 1999 (NSW). The operation of that
Act, in the context of a claim by a builder which was not licensed as required by the
Home Building Act 1989 (NSW), was examined by the New South Wales Court of
Appeal in Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421. There is no
relevant distinction between the terms of the Payments Act and that corresponding
statute in New South Wales. But, there is a difference between s 42 of the Building
Act and s 10 of the Home Building Act of New South Wales, which is, in
these.terms:
“10 Enforceability of contracts and other rights
(1) A person who contracts to do any residential building work,
or any specialist work, and who so contracts:
(a) in contravention of section 4 (Unlicensed contracting), or
(b) under a contract to which the requirements of section 7 apply that is
not in writing or that does not have sufficient description of the work
to which it relates (not being a contract entered into in the
circumstances described in section 6 (2)), or
(c) in contravention of any other provision of this Act or the regulations
that is prescribed for the purposes of this paragraph.
is not entitled to damages or to enforce any other remedy in respect of a breach
of the contract committed by any other party to the contract, and the contract is
unenforceable by the person who contracted to do the work. However, the
person is liable for damages and subject to any other remedy in respect of a
breach of the contract committed by the person.
(2), (3) (Repealed)
(4) This section does not affect the liability of the person for an offence
against a provision of or made under this or any other Act.”
In Brodyn, the conclusion of Hodgson JA, with whom Mason P and Giles JA
agreed, was that the builder’s entitlement to a progress payment was a statutory
entitlement which was outside the operation of s 10 because it was neither a remedy
-- 14 of 18 --
15
by way of “damages” nor a “remedy in respect of breach of contract”.3 Hodgson JA
compared s 10 with s 94 of the same Act, which provides for the effect of a builder’s
doing work without the insurance as required by that Act. In that circumstance, the
uninsured contractor:
“(a) is not entitled to damages, or to enforce any other remedy in
respect of a breach of the contract committed by any other party to
the contract in relation to that work, and
(b) is not entitled to recover money in respect of that work under
any other right of action (including a quantum meruit)”4
Hodgson JA said that his opinion as to the limited scope of s 10 was confirmed by
the different terms of s 94. 5 The difference is that s 94 also contains the wide
expression: “money in respect of that work”. As Williams JA has said, that
expression in s 94 seems much the same as that in s 42 of the Building Act, so that
Hodgson JA’s judgment in Brodyn indicates the difference between the provision
which was relied upon there, s 10 of the Home Building Act and the wider terms of s
42 of the Building Act. In Brodyn, the alleged entitlement to a progress payment
was simply outside the terms of the statutory limitation upon recovery by unlicensed
builders. In Queensland, that alleged entitlement is apparently within the terms of s
42. The present question, for which Brodyn does not indicate an answer, is whether
the Payments Act was intended to override the disentitlement to any payment
resulting from s 42.
[52] The expressed object of the Payments Act is to ensure that a person is entitled to
receive, and is able to recover, progress payments if the person undertakes to carry
out construction work or to supply related goods and services under a construction
contract.6 That object is achieved by granting an entitlement to progress payments,
whether or not the relevant contract provides for them, and establishing a procedure
for their recovery.7 That procedure involves the making of a payment claim, the
possible provision of a response to that claim (“a payment schedule”), the referral of
a disputed or unpaid claim to an adjudicator for decision and the payment of the
amount decided by the adjudicator.8
[53] Section 12 creates an entitlement to a progress payment where a person has
undertaken, under a construction contract, to carry out construction work or supply
related goods and services. As Hodgson JA held in Brodyn, one essential
prerequisite for the operation of this statute is the existence of a construction
contract to which the Act applies. So in the present case, the respondent’s
entitlement, if any, to a progress payment and to the benefit of this scheme for its
recovery, must derive from its having undertaken to carry out construction work.
Yet, assuming that the respondent was then an unlicensed builder, it committed an
offence in undertaking to carry out that work. The respondent’s case therefore
proceeds from the unattractive proposition that its committing an offence was an
essential step to its becoming entitled to the beneficial operation of this scheme.
3 (2004) 61 NSWLR 421, 449.
4 Subject to an allowance on a quantum meruit basis if a Court or Tribunal considers it just and equitable: s
94(1A).
5 (2004) 61 NSWLR 421, 449.
6 s 7.
7 s 8.
8 s 8.
-- 15 of 18 --
16
[54] The respondent’s argument meets a further obstacle in the provisions by which a
progress payment is to be quantified. Section 13 provides that the amount of a
progress payment to which a person is entitled is either the amount calculated under
the contract, or, if the contract does not provide for the matter, then an amount
calculated on the basis of the value of the construction work carried out or
undertaken to be carried out. Section 14 provides for how that value is to be
assessed, as follows:
“(1) Construction work carried out or undertaken to be carried out
under a construction contract is to be valued -
(a) under the contract; or
(b) if the contract does not provide for the matter, having regard
to –
(a) the contract price for the work; and
(b) any other rates or prices stated in the contract; and
(c) any variation agreed to by the parties to the contract by
which the contract price, or any other rate or price stated
in the contract, is to be adjusted by a specific amount; and
(d) if any of the work is defective, the estimated cost of
rectifying the defect.”
Leaving aside the case of defective work, it can be seen that construction work is to
be valued according only to what the parties had agreed, because the valuation of
the work, which quantifies the progress payment, must derive from the contract
price, from rates or prices stated in the contract or from any agreed variation to
those things.
[55] This is a difficulty in the operation of the Payments Act in the case of an unlicensed
builder, because that builder is not entitled to enforce its contract and, in particular,
to recover its contract price. The builder is limited effectively to recovering its
costs, according to s 42(4) of the Building Act, except that if its costs are greater
than the agreed price, the builder is limited to the price: s 42(4)(c). The respondent
does not suggest that an unlicensed builder’s ultimate entitlement (or disentitlement)
is not according to s 42. It argues only that an unlicensed builder is entitled to
progress payments as if s 42 had no operation, although in the final accounting, s 42
applies, and a builder could be ordered to make restitution pursuant to s 100(3) of
the Payments Act.
[56] Accordingly, the respondent’s argument is that the Payments Act is intended to
facilitate the recovery of a progress payment or payments, which in at least many
cases, would be more than the cost of performing the work to that point, although
ultimately the builder would be entitled to no more than its costs. Had the Payments
Act provided for some progressive recovery by progress claims quantified by
reference to an unlicensed builder’s limited entitlement under s 42(4), it would have
an evident policy. But there is no evident reason in policy why an unlicensed
-- 16 of 18 --
17
builder should be given a right to part payments, which must be quantified not
according to its ultimate entitlement for the whole works, but in higher sums
according to terms of a contract which the builder cannot enforce.
[57] Section 21 provides that a claimant may apply for adjudication of a payment claim
if the respondent to its claim has duly disputed the claim or failed to pay such of the
claim which is not disputed. By s 26, an adjudicator is to decide the amount of the
progress payment, if any, to be paid.9 Section 26(2) provides that the adjudicator is
to consider only these matters:
“(a) the provisions of this Act and, to the extent they are relevant,
the provisions of the Queensland Building Services Authority
Act 1991, part 4A;
(b) the provisions of the construction contract from which the
application arose;
(c) the payment claim to which the application relates, together
with all submissions, including relevant documentation, that
have been properly made by the claimant in support of the
claim;
(d) the payment schedule, if any, to which the application relates,
together with all submissions, including relevant
documentation, that have been properly made by the
respondent in support of the schedule;
(e) the results of any inspection carried out by the adjudicator of
any matter to which the claim relates.
Section 42 of the Building Act is not within Part 4A of that Act. Therefore, in the
case of an unlicensed builder’s claim, the adjudicator could not consider s 42. The
adjudicator would be obliged to value the work according to s 14. And, by s 27, in a
subsequent adjudication, the adjudicator would have to adopt “the same value as that
previously decided unless (satisfied) that the value of the work … has changed since
the previous decision”.
[58] Accordingly, another unattractive aspect of the respondent’s argument is that the
regime of adjudication would often result in something higher than the
commensurate share of the builder’s ultimate entitlement, and, therefore, in an
overpayment.
[59] In some cases, which the arguments agree is the case here, there could be a genuine
question as to whether the builder is relevantly unlicensed. In particular, there
could be questions of fact going to the classification of the work for the purposes of
the licensing requirements, which cast doubt on whether the builder held the licence
appropriate for the agreed work. But, that is not a matter which could be
investigated by the adjudicator, who would be confined to a consideration of the
matters listed in s 26(2). Nor could the respondent to a payment claim, dispute the
claim on that basis, within its “payment schedule” given under s 18, because if this
9 As well as the date for payment and the rate of interest payable on any amount: s 26(1)(b) and s 26(1)(c).
-- 17 of 18 --
18
regime applies to unlicensed builders then the absence of a licence would have no
relevance in the valuation of the progress claim.
[60] In these ways, the operation of the Payments Act in the case of an unlicensed
builder would lead to a result in at least many cases which is unjust, judged by the
policy of the licensing provisions of the Building Act. The operation of this scheme
by the overpayment of unlicensed builders pending a final reconciliation, is likely to
have effects which cannot be cured by an order under s 100. There is no sensible
explanation for the Payments Act to have an operation of that kind.
[61] The purpose of a scheme of progress payments is to permit a builder to be paid the
agreed consideration for the works progressively, by a part payment which is
commensurate with that part of the works performed to that point. This scheme for
progress claims and their recovery is evidently unsuitable for the case of
unregistered builders, because it operates from a premise of the builder’s
entitlement being according to its contract. The long title of the Payments Act
describes it as an “Act to imply terms in construction contracts …” It is unlikely the
Act was intended to benefit builders who cannot enforce the payment provisions of
their contracts, especially when the making of such a contract involved an offence
by the builder. Ultimately, it far from appears that the Payments Act was intended
to override the disentitlement according to s 42; the contrary appears. In my view,
the Payments Act operates only when there is a construction contract of which the
terms as to payment are enforceable by the builder.
[62] The respondent’s claim in these proceedings, even when given its new appearance
as a purported progress claim, is precluded by s 42 if the respondent did not hold the
relevant licence. As there is at least an issue to be tried on that matter, the
respondent should not have been given summary judgment. I agree with the orders
proposed by Williams JA.
-- 18 of 18 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2006/538