Chang & Anor v Laidley Shire Council [2006] QCA 172 (2006)146 LGERA 283
SUPREME COURT OF QUEENSLAND
CITATION: Chang & Anor v Laidley SC [2006] QCA 172
PARTIES: SHU-LING CHANG and TAI-HSING CHEN
(applicants/applicants)
v
LAIDLEY SHIRE COUNCIL
(respondent/respondent)
FILE NO/S: Appeal No 8164 of 2005
P & E Appeal No 464 of 2005
DIVISION: Court of Appeal
PROCEEDING: Planning and Environment Appeal
ORIGINATING
COURT: Planning and Environment Court at Brisbane
DELIVERED ON: 26 May 2006
DELIVERED AT: Brisbane
HEARING DATE: 27 April 2006
JUDGES: Jerrard and Keane JJA and Philippides J
Separate reasons for judgment of each member of the Court,
each concurring as to the orders made
ORDER: 1. Application for leave to appeal refused
2. Applicants to pay the respondent's costs of and incidental
to the application to be assessed on the standard basis
CATCHWORDS: ENVIRONMENT AND PLANNING - ENVIRONMENTAL
PLANNING - PLANNING SCHEMES AND INSTRUMENTS
- QUEENSLAND - GENERALLY - where applicants made
application to the respondent in December 2004 for the
reconfiguration of the applicants' land from one lot into 25 lots -
where respondent refused to accept applicants' application for
assessment and decision - where applicants seek compensation
for reduction in value of their land which they assert resulted
from changes made in March 2003 to the planning arrangements
applicable to their land - where applicants sought a declaration
from the Planning and Environment Court that their application
was a "development application (superseded planning scheme)
for a development permit relating to the land" - where learned
primary judge refused this application because it was not a
"properly made application" - where applicants argued before
this Court that they had lost an accrued right to compensation or
an accrued right to apply to reconfigure their land and to have
the processes appropriate to a development application
(superseded planning scheme) applied to their application -
-- 1 of 21 --
2
whether leave to appeal should be granted
Acts Interpretation Act 1954 (Qld), s 20
Integrated Planning Act 1997 (Qld), s 1.3.1, s 1.3.2, s 2.5A.12,
s 2.5A.24, s 3.2.1, s 3.2.5, s 4.1.5A, s 4.1.56, s 5.4.2
Integrated Planning and Other Legislation Amendment Act 2004
(Qld)
Local Government (Planning and Environment) Act 1990 (Qld),
s 3.5
Draft Regulatory Provisions 2004, s 4, s 6
Attorney-General for the State of Queensland v Australian
Industrial Relations Commission and Ors (2002) 213 CLR 485;
[2002] HCA 42, applied
Cameron v Noosa SC [2006] QCA 109; Appeal No 7232 of
2005, 13 April 2006, cited
Dossett v TKJ Nominees Pty Ltd (2003) 218 CLR 1; [2003]
HCA 69, cited
Kettering Pty Ltd v Noosa Shire Council (2004) 78 ALJR 1022;
[2004] HCA 33, cited
Marshall v Department of Transport (2001) 205 CLR 603;
[2001] HCA 37, cited
Pauls Ltd v Elkington (2001) 189 ALR 551; [2001] QCA 414,
cited
Resort Management Services Pty Ltd v Noosa Shire Council
[1997] 2 Qd R 291; [1996] QCA 441, considered
COUNSEL: D R Gore QC, with T N Trotter, for the applicants
M D Hinson SC for the respondent
SOLICITORS: Robert Milne Legal for the applicants
Connor O'Meara for the respondent
[1] JERRARD JA: In this application I have had the benefit of reading the reasons for
judgment and order proposed by Keane JA, and respectfully agree with those
reasons and orders. I add the following reasons of my own, in which I adopt
Keane JA’s description of the relevant facts, and his terminology.
Some terms and provisions of the IPA
[2] Under the IPA the term “reconfiguring a lot” describes, inter alia, what would
commonly be understood as subdividing a lot.1 An “assessment manager” in
respect of an application for development approval is the entity which administers
and decides an application, usually the local government authority.2 Section 3.2.5(3)
of the IPA provides that where an application is a DA(SPS) in which the applicant
asks the assessment manager to assess the application under the superseded
planning scheme, the acknowledgement notice must state:
“(a) that the application will be assessed under the superseded
planning scheme; or
(b) that the application will be assessed under the existing
planning scheme.”
1 See s 1.3.5 of the IPA.
2 See s 3.1.7 and Schedule 8A of the IPA.
-- 2 of 21 --
3
Chronology
[3] Mr Gore QC included a helpful chronology in the written outline of argument
presented by Mr Gore and Mr Trotter of Counsel on the applicants’ behalf. It
informs that the relevant dates and events were:
12.11.77 The land was included in the Rural A Zone under the
1977 planning scheme.
22.07.92 An application was made to rezone the land to the Rural
Residential Zone.
3.12.92 The rezoning of the land to the Rural Residential Zone
was gazetted.
6.12.96 The land was included in the Rural Residential A Zone
under the 1996 Laidley Shire Council Town Plan.
17.09.04 The IPOLA 2004 commenced.
27.10.04 The DRP in the draft SEQ Regional Plan took effect.
3.12.04 The applicants lodged a DA(SPS) with the Council.
21.01.05 The Council advised the applicants that the DA(SPS) was
not properly made.
11.02.05 The applicants instituted their appeal to the (P & E)
Court.
28.03.05 The 2 year period for lodging a DA(SPS), provided for in
the definition of a “Development Application (Superseded Planning
Scheme)” in schedule 10 of the IPA, expired in respect of the change
of zoning affected for the subject land by the 2003 Laidley Shire
Council Planning Scheme.
30.06.05 The SEQRP was gazetted.
The IPA position absent the IPOLA
[4] Studying that chronology reveals that, had the IPOLA not amended the IPA, the
applicants would have had two years after 28 March 2003 within which to make a
DA(SPS) to the Council, which may have resulted in their being compensated if the
change to the applicable planning scheme reduced the value of their interest in the
subject land.3 They had not made a DA(SPS) application in the 17 months which
elapsed before the DRP took effect.
Did the IPOLA apply?
[5] In this Court Mr Gore QC submitted that s 3.2.1(7)(f) of the IPA, inserted by s 10(1)
of the IPOLA, did not apply to the applicants. That was because the provisions in
the IPOLA which referred to “development applications” should be construed as
excluding those development applications which were DA(SPS) ones. It followed
in his submission, that the reference to an “application” in s 6 of the IPA was to a
3 Section 5.4.1 of the IPA.
-- 3 of 21 --
4
non-DA(SPS) one; and s 4 of the IPA would likewise validly deal only with
non-DA(SPS) matters.
[6] The IPOLA introduced a Part 5A into Chapter 2 of the IPA, and made other
amendments to it. Mr Gore’s submission means that the provision in
s 2.5A.12(2)(e) (providing that the regulatory provisions in SEQ Regional Plan
might state transitional arrangements for development applications affected by the
regulatory provisions), and the provision in s 2.5A.24(5)(b) (relevantly providing
that to remove doubt, it was declared that draft regulatory provisions might state
transitional arrangements for development applications affected by the draft
regulatory provisions) should each be construed as referring only to development
applications under current, non superseded planning schemes.
[7] Section 3.2.1 of the IPA, dealing with applications for development approval,
describes various requirements for those applications; in s 3.2.1(7) the requirements
for a properly made application are listed in subsections (a) to (f) inclusive. Since
s 3.2.3, dealing with acknowledgement notices and the obligations placed on
assessment managers, specifically describes in s 3.2.3(b) the obligation on an
assessment manager who receives a properly made application for a DA(SPS), it is
very difficult to construe s 3.2.1(7)(f) as not applying to DA(SPS) applications.
Section 3.2.1(7) is expressed to apply to all applications for development approval,
and s 3.2.1(7)(a) to (e) obviously enough all apply to DA(SPS). That makes the
conclusion that s 3.2.1(7)(f) does not seem very odd.
[8] The other provisions of the IPOLA mitigate against Mr Gore’s construction of it.
Section 2.5A.22 in Part 5A requires a local government to amend its planning
scheme (in accordance with the process described in Schedule 1 of the IPA), to
reflect the SEQ Regional Plan as made, amended or replaced; and s 2.5A.23(2)
provides that to the extent that there is an inconsistency between the SEQ Regional
Plan and any other plan, policy or code, including any other planning instrument,
the SEQ Regional Plan prevails. Those provisions mean that any inconsistent
planning scheme of a local authority was automatically overridden and required
amendment when the SEQ Regional Plan came into effect, or was amended.
Section 2.5A.22 provided for the regional planning Minister to unilaterally amend
any inconsistent planning scheme of a local government, if that local government
did not do so within 90 business days of the gazettal of SEQ Regional Plan.
[9] Those provisions have the result that unless all of the planning schemes of the
18 city and Shire Councils constituting the SEQ region4 already had planning
schemes entirely consistent with the SEQ Regional Plan when it was gazetted, then
there would be at least some superseded planning schemes on that gazettal. Section
2.5A.24(1), referred to by Keane JA, provided that a proposed regulatory provision
of the draft SEQ Regional Plan would have effect until the SEQ Regional Plan came
into effect. That provision meant that the draft regulatory provisions (DRP) would
have the force of law5 , and it was predictable enough that those DRP would be
inconsistent with at least some of the planning instruments of those 18 local
governments. If not, the SEQ Regional Plan would be otiose. Consistently with
that, s 2.5A.24(5)(b), authorising the DRP to state transitional arrangements for
development applications effected by the DRP, should be construed as including
4 Listed in s 2.5A.2 of the IPA.
5 By reason of s 2.5A.10(2) of the IPA.
-- 4 of 21 --
5
DA(SPS) ones. It would follow that the IPOLA did make provision for DA(SPS)
applications, contrary to Mr Gore’s argument.
[10] At the same time the IPOLA amended s 3.2.1(7) and (10) of the IPA, to prevent
applications being acknowledged that were contrary to the DRP, by declaring those
not properly made applications. The IPOLA also amended s 3.5.11 of the IPA, by
introducing a subsection 4A, which provided that an assessment manager’s decision
must not be contrary to the regulatory provisions or the DRP; and inserted a
s 4.3.5A into the IPA, providing that a person must not carry out development
contrary to the regulatory provisions or the DRP. Thus the IPOLA provided that
development contrary to the DRP could not be applied for, approved, or carried out
once the DRP came into force; but the IPOLA did provide that transitional
provisions could be made (in the DRP) for development applications. These were
made in the sections in the DRP quoted by Keane JA, sections 4 and 6.
[11] Section 6 simply read:
“6. Development applications may continue
These Draft Regulatory Provisions do not apply for a
development application made before the day these Draft
Regulatory Provisions came into effect.”
Mr Gore submitted that s 6 did not apply to a DA(SPS), and applied only to
development applications under then current planning schemes. His submission
would have this effect, if accurate. If his clients had made a DA(SPS) to the
Council in, say, March 2004, that application would not be protected by s 6. On his
construction, s 4(1) and (2) of the DRP would therefore apply to his clients if they
had made a pre-DRP DA(SPS) application; but in that case they could not claim the
benefit of s 4(3)(c)(i), since the reconfiguration for which they had sought
development approval was not on land (then) designated or zoned for rural
residential purposes. Nor, on the most obvious construction of “within two years”,
as meaning “within two years after”, would such an applicant meet the time
qualifications in s 4(3)(c)(ii).
[12] On his construction, such a pre-DRP DA(SPS) applicant would be disadvantaged,
because the application could not be approved (3.5.11(4A) of the IPA); and that
applicant would have to overcome the hurdle in s 5.4.4(1)(a) of the IPA, briefly
referred to by Keane JA, before qualifying for compensation. The possibility of
compensation would be their only hope; the application could not be approved.
Mr Gore’s argument would mean that pre-DRP DA(SPS) applicants were in the
same position as post-DRP DA(SPS) applicants, such as his clients, who could not
benefit from s 4(3)(c)(i), because of their land designation or zoning. Yet the more
obvious construction of s 6 of the IPA was that it was intended by s 6 to protect the
rights of all those who had always made as yet undetermined applications.
Mr Gore’s arguments significantly reduce the rights of those pre-DRP DA(SPS)
applicants, in equating them with what he contends is his clients’ position.
[13] It is considerably more consistent with the object of the IPOLA and the apparent
purpose of s 4 and s 6 of the DRP to construe s 4(3)(c) as applicable to applications
(both DA(SPS) ones and ordinary applications) for reconfiguration made after the
DRP came into effect, and within two years of the date that it did, and s 6 to the like
applications made before it came into effect. In my opinion the DRP made
transitional provision, firstly for applications made after it came into force (in s 4)
and for applications made before it did (s 6), and that for each the transitional
-- 5 of 21 --
6
provisions included both ordinary development applications and DA(SPS) ones.
Regarding s 4, it made transitional provision for applications (of either variety) if
the land was zoned rural residential at the time DRP came into force, and if the
application for reconfiguration was made within two years of that date.
[14] No provision was made for land holders who had an unexercised right to make a
DA(SPS) for reconfiguration into rural residential lots on the date the DRP came
into effect, and whose land was not designated or zoned for rural residential
purposes as at that date of coming into effect. Those owners lost that right because
no transitional provision was made for them. The provisions which were made did
not apply to them.
[15] Section 4(3)(c) is such a transitional provision, and Part 4 of Division 9 of Chapter 5
of the IPA – dealing with compensation – would apply to an application made
pursuant to it. So too would s 3.2.5, dealing with acknowledgment notices. The
choice given to a local government by s 3.2.5(3) of the IPA, to assess an application
under a superseded or existing planning scheme, would be available on a
reconfiguration application described by s 4(3)(c) of the DRP. That is because
s 4(2) of the DRP would not apply. Accordingly s 3.2.1(7)(f), applicable to the
application for reconfiguration, would not be engaged by such an application for
reconfigure, because the application would not be contrary to the DRP.
[16] Likewise the s 3.2.5(3) choice, of assessing the application under the 1996 or the
2003 planning scheme, would be available on applications which were DA(SPS)
applications that had been made before the date the DRP came into effect. The
assessment manager could make a decision to assess the application under the 1996
scheme because that would not be contrary to the DRP; s 6 provides that it did not
apply. Therefore s 3.2.1(7)(f) would also apply to that application, but would not
render it one not properly made.
[17] The result of that analysis, if correct, is that s 3.2.1(7) applies in its entirety to both
ordinary development applications and DA(SPS) varieties of those, including
subparagraph 7(f), in a manner consistent with the IPOLA scheme’s exclusion of
the possibility of development approval or development contrary to the DRP
provisions, but subject (by the IPOLA provisions) to the described transitional
provisions. The applicants’ argument that 3.2.1(7)(f) should be construed to
exclude DA(SPS) applications accordingly describes a step unnecessary for the
DA(SPS) applications provided for by the DRP, and is inconsistent with the scheme
of the IPOLA and with s 2.5A.24(5)(b) allowing provision to be made for
development applications affected by the DRP.
[18] The applicants’ construction of s 3.2.1(7)(f) not only puts “late” applicants, whose
land was not zoned rural residential at the time the DRP came into force, in the
same position as applicants who had made a DA(SPS) application regarding such
land before the DRP came into effect, but it gives both a potential advantage over
applicants who made a non-DA(SPS) application before the DRP came into effect,
and to whom Mr Gore agrees s 6 of the DRP applies. On the applicants’
construction of the IPOLA and the DRP, namely that they were inapplicable to
DA(SPS) matters and that s 3.2.1.7(f) did not apply to those, the local authority
assessing those applications would be unable to make the s 3.2.5(3) choice, because
the assessment manager could not make a decision contrary to the DRP, which
would otherwise apply to the land. Accordingly those applications would of
-- 6 of 21 --
7
necessity be considered under the 2003 planning scheme, and subject to s 4.4(1)(a),
that class of applicant would automatically have a right to compensation. This
would be so because the compensation “hurdles” erected in s 5.4.2(c) and (d) would
necessarily apply in those applicants’ favour once those owners took the s 5.4.2(b)
step of applying for a development permit. Yet on Mr Gore’s construction that
advantage would not accrue to land owners who had made non-DA(SPS)
applications before or after the DRP came into effect, if their applications were
refused. Mr Gore’s argument has the result for his clients of returning the
compensation provisions in the IPA to the pre-existing regime.
[19] Mr Gore contends that his construction follows from s 20 Acts Interpretation Act,
and from the common law principle of construction referred to by Keane JA, that
property rights are only removed without compensation when that is done in the
clearest terms. Mr Gore argues that there is no injustice, or any principle or result
offensive to planning law, which would flow from accepting his arguments. But a
State legislature can take away rights of private property without compensation,6
and that is what has happened. It has been done with very little notice, and
unobtrusively, but done in quite clear terms.
[20] I agree with what Keane JA has written about the submissions made on s 20 of the
AIA, and the common law, and consider that while s 3.2.1(7)(f), foreshadowing a
possible loss of rights, could have been made clearer, the loss of rights were made
explicit when the DRP came into force. There is no room for the construction
Mr Gore seeks, because the IPOLA provisions did refer in s 2.5A.24(5)(b) to
development applications, and in my opinion to both varieties; Mr Gore’s
construction would require reading into s 3.2.1(7)(f) the words “other than for
development applications (superseded planning schemes),” an astonishingly
unwieldy result; his construction would give late applicants a potential for a
windfall; his construction is unnecessary on my interpretation of the DRP, s 3.2.1(f),
and the IPOLA, and necessary only to achieve the windfall result; and would
specifically disadvantage pre-DRP DA(SPS) people, as explained.
[21] For these further reasons I agree with Keane JA.
[22] KEANE JA: The applicants made an application on 3 December 2004 to the
respondent ("the Council") whereby they sought approval for the reconfiguration of
their land at Mt Berryman Road, Blenheim from one lot into 25 lots. The Council
declined to accept this application for assessment and decision by it.
[23] The applicants wish to claim compensation for the reduction in the value of their
land which they assert resulted from changes in the planning arrangements
applicable to their land in March 2003. The entitlement to be paid compensation
arises under s 5.4.2 of the Integrated Planning Act 1997 (Qld) ("the IPA").
[24] Under the IPA, in certain circumstances, an applicant can request that an application
for development approval be assessed under the terms of a planning scheme that has
been superseded by the current scheme. If the assessing authority accedes to that
request, the question of an entitlement to compensation will not arise. If, on the
other hand, the assessing authority assesses the application under the terms of the
new planning scheme, the applicant may be entitled to compensation in certain
6 Pauls Ltd v Elkington [2005] QCA 414 at [15] per McPherson JA, citing Durham Holdings Pty Ltd v
New South Wales (2001) 75 ALJR 501.
-- 7 of 21 --
8
circumstances. An applicant will not be entitled to compensation, however, where
the application is not a "development application (superseded planning scheme)
("DA (SPS)") for a development permit". It is common ground that an application
is not a DA (SPS) unless it is what the IPA refers to as "a properly made
application".
[25] The applicants sought a declaration from the Planning and Environment Court ("the
court") that their application for reconfiguration of their land was a "development
application (superseded planning scheme) for a development permit relating to the
land" within the meaning of s 5.4.2 of the IPA. The learned primary judge refused
to make that declaration because the applicants' application was not a "properly
made application".
[26] The applicants now seek leave, pursuant to s 4.1.56 of the IPA, to appeal to this
Court against the decision of the primary judge. In order to understand the
arguments which the applicants wish to agitate on appeal, it is necessary to have an
appreciation of the factual and legal context in which those arguments arise. I will
therefore summarise briefly the circumstances of the applicants' claim, the relevant
statutory framework and the reasons for the decision of the primary judge. I will
then proceed to a discussion of the arguments which the applicants seek to agitate
on appeal.
The circumstances of the application to the Council
[27] The applicants' land has an area of 16.67 hectares. Under the planning scheme
which applied prior to 28 March 2003, the land was zoned Rural Residential A. On
28 March 2003, a new planning scheme came into force under which the land was
zoned Rural Landscape.
[28] The application to the Council of 3 December 2004 was made as a DA (SPS) for a
development permit to reconfigure the land to create 25 new rural residential lots.
The 25 lots in the applicants' proposed reconfiguration of the land ranged in area
from 5,970 m2 to 9,287 m2 , with an average lot size of about 6,224 m2 . Under the
planning scheme which applied before 28 March 2003, the minimum allotment area
was 4,000 m2 . Under the 2003 planning scheme, the minimum lot area for land
zoned Rural Landscape is 60 hectares.
[29] On 27 October 2004, pursuant to amendments made by the Integrated Planning and
Other Legislation Amendment Act 2004 (Qld) ("the IPOLA") in connection with the
promulgation and implementation of the South East Queensland Regional Plan,
"draft regulatory provisions" ("DRP") came into effect. It will be necessary to refer
in greater detail to the IPOLA and the DRP, but for present purposes, it is sufficient
to note that s 4(2) of the DRP prohibited the development which the applicants
proposed.
[30] Section 4(3)(c) of the DRP provided an exception to the prohibition contained in
s 4(2), as will be explained below. The position taken by the Council in relation to
the application made by the applicants was that s 4(3)(c) of the DRP was not
available to the applicants to obviate the prohibition on reconfiguration contained in
s 4(2) of the DRP. By letter dated 21 January 2005, the Council advised the
applicants that their application of 3 December 2004 was not a properly made
application because:
-- 8 of 21 --
9
"the exception created by section 4(3)(c) of the Draft Regulatory
Provisions does not apply to this development application as the land
is currently not designated or zoned for rural residential purposes.
Consequently, the development application is contrary to the Draft
Regulatory Provisions and, pursuant to section 3.2.1(7)(f) of the
Integrated Planning Act 1997, is not a properly made application."
[31] It is apparent that the Council was not purporting to assess the application for the
purposes of s 5.4.2 of the IPA: rather the Council was taking the position that the
application was not one which engaged the Council's functions of assessment at all
because it was not a "properly made application". On that basis, the Council
refused to receive the application.
[32] A clear understanding of why it was said that the application was not "a properly
made application" requires some detailed reference to the relevant provisions of the
IPA and the DRP.
The statutory framework
[33] As I have said, s 5.4.2 of the IPA provides for compensation for a land owner
adversely affected by a change in the planning scheme or any planning scheme
policy affecting the land. It provides:
"Compensation for reduced value of interest in land
An owner of an interest in land is entitled to be paid reasonable
compensation by a local government if -
(a) a change reduces the value of the interest; and
(b) a development application (superseded planning
scheme) for a development permit relating to the land has
been made; and
(c) the application is assessed having regard to the
planning scheme and planning scheme policies in effect
when the application was made; and
(d) the assessment manager, or, on appeal, the court -
(i) refuses the application; or
(ii) approves the application in part or subject to
conditions or both in part and subject to conditions."
[34] At this point, one may note that the provisions of s 5.4.2 of the IPA stand in stark
contrast to the provisions of s 3.5(1) of the now repealed7 Local Government
(Planning and Environment) Act 1990 (Qld) ("the 1990 Act"). The more
"expansive" provisions of the 1990 Act were discussed by the High Court in
Kettering Pty Ltd v Noosa Shire Council,8 and by this Court in Cameron v Noosa
SC. 9 Section 3.5(1) of the 1990 Act was relevantly in the following terms:
"Where a person -
(a) has an interest in premises within a planning scheme
area and the interest is injuriously affected -
(i) by the coming into force of any provision
contained in a planning scheme; or
(ii) by any prohibition or restriction imposed by
the planning scheme; or
7 See s 6.2.1 of the IPA which became operational on 30 March 1998.
8 (2004) 78 ALJR 1022; [2004] HCA 33 esp at [30] - [34].
9 [2006] QCA 109; Appeal No 7232 of 2005 at [25] - [33] and [41] - [46].
-- 9 of 21 --
10
…
the person is, subject to compliance with this section, entitled to
obtain from the local government compensation in respect of the
injurious affection or expenditure and may claim that compensation
in accordance with this section."
[35] Under s 3.5(1) of the 1990 Act, an entitlement to compensation was conferred on
the owner of an interest in premises within a planning scheme area whose interest
was injuriously affected "by the coming into force of any provision contained in a
planning scheme; or … by any prohibition or restriction imposed by the planning
scheme". In contrast, under s 5.4.2 of the IPA, no entitlement to compensation
arises merely because a change to the planning scheme or any planning scheme
policy operates adversely to affect, or to reduce the value of, the owner's interest in
the land. Under s 5.4.2 of the IPA, an entitlement to compensation only arises if a
DA (SPS) for a development permit relating to the land has been made, and
assessed, and either refused or allowed only in part or subject to conditions.
[36] Because the assessment contemplated by s 5.4.2(c) proceeds by reference to the
planning scheme and planning scheme policies in effect when the DA (SPS) is
made, it is evident that compensation obtainable under s 5.4.2 of the IPA is intended
to reflect the extent to which the value of the owner's interest in the land has been
adversely affected by the decision of the local authority to assess the development
application on the basis of the planning scheme policies in effect at the time the
application is made, rather than on the basis of the planning scheme and policies
previously in force. Accordingly, no entitlement to compensation arises at all in the
absence of the assessment by the assessment manager of a DA (SPS) for a
development permit contemplated by s 5.4.2(c) and (d) of the IPA.
[37] Under the provisions of the IPA, apart from the IPOLA, it is a matter for decision
by the assessment manager, in this case the Council, whether the assessment of an
application should proceed by reference to the current planning scheme or the
superseded planning scheme. It is only where the Council has decided to assess an
application pursuant to the current planning scheme that the possibility of a liability
in the Council to pay compensation arises. That situation will only arise where the
Council has decided not to exercise its power effectively to override the current
planning scheme in its assessment of the application. In the present case, the
Council made no such decision.
[38] The view that the application was not a "properly made application" is the
consequence of amendments to the IPA introduced by the IPOLA for the special
purpose of giving effect to the South East Queensland Regional Plan ("the SEQ
Regional Plan"). These provisions preclude the possibility of a Council allowing
development which is contrary to the terms of the SEQ Regional Plan.
[39] By s 1.3.2 of the IPA "development" is defined so as to include "reconfiguring a
lot". By virtue of s 1.3.1 and Sch 10 of the IPA:
• "development application" means an application for a development approval;
• "development application (superseded planning scheme)" means relevantly
"… a development application -
(i) in which the applicant asks the assessment manager to
assess the application under a superseded planning scheme; and
…
-- 10 of 21 --
11
(iii) made within 2 years after the day the planning scheme or
planning scheme policy creating the superseded planning scheme
was adopted or the amendment creating the superseded planning
scheme was adopted."
• "development approval" means relevantly "a decision notice … that …
approves, wholly or partially, development applied for in a development
application and … is in the form of a … development permit …".
• a "superseded planning scheme" for a planning scheme area means the planning
scheme, or any related planning scheme policies, in force immediately before -
"(a) the planning scheme or policies, under which a development
application is made, were adopted; or
(b) the amendment, creating the superseded planning scheme,
was adopted."
[40] By virtue of s 3.1.5(3) of the IPA, a "development permit" authorises assessable
development to occur to the extent stated in the permit. It is common ground that
the reconfiguration proposed by the applicants is assessable development. 10
[41] As I have noted, it is common ground between the parties that s 5.4.2(b) of the IPA,
in speaking of a "development application (superseded planning scheme) for a
development permit" ("DA (SPS)") is to be taken to refer to a "properly made
application". The concept of a "properly made application" is the creature of
s 3.2.1(7) of the IPA, which is in the following terms:
"An application is a properly made application if -
(a) the application is made to the assessment manager;
and
(b) the application is made in the approved form; and
(c) the mandatory requirements part of the approved
form is correctly completed; and
(d) the application is accompanied by the fee for
administering the application; and
(e) if subsection (6) applies - the application is
supported by the evidence required under subsection (5);
and
(f) the development would not be contrary to the
regulatory provisions or the draft regulatory provisions."
It should be noted at this point that s 3.2.1(7)(f) was added to the IPA by the
IPOLA.
[42] It is readily apparent from the terms of s 3.2.1(7)(f) of the IPA that an application
proposing a development which, if it were to proceed, "would be" contrary to the
DRP is not a "properly made application".
[43] Section 3.2.1(8) of the IPA provides: "The assessment manager may refuse to
receive an application that is not a properly made application." Section 3.2.1(9) of
the IPA provides that the assessment manager might "after consideration" accept
"an application that is not a properly made application", whereupon it "is taken to be
a properly made application". That discretion was removed in relation to
s 3.2.1(7)(f) by the new s 3.2.1(10)(b) which was also introduced by the IPOLA.
Section s 3.2.1(10)(b) of the IPA relevantly provides:
10 See Sch 8, table 3, item 1 of the IPA.
-- 11 of 21 --
12
"Subsection (9) does not apply to an application -
…
(b) if the development would be contrary to the … draft regulatory
provisions".
[44] If the application is not a "properly made application", or deemed to be a "properly
made application", the assessment process cannot proceed. In this regard, s 3.2.3 of
the IPA provides relevantly that:
"(1) The assessment manager for an application must give the
applicant a notice (the acknowledgment notice) within -
…
(b) if the application is a development application
(superseded planning scheme) - 30 business days after
receiving the properly made application (also the
acknowledgment period)."
[45] By virtue of s 3.2.5(3)(b), the acknowledgment notice for a DA (SPS) must state the
Council's decision as to whether the application will be assessed under the
superseded planning scheme, ie in the present case the scheme in force before
March 2003, or under the existing planning scheme.
[46] If the Council as assessment manager were to elect to assess the application under
the existing planning scheme, the elements of a claim for compensation referred to
in s 5.4.2(a) and (d) of the IPA could be established.11 Because of the terms of the
2003 planning scheme, such an assessment would inevitably lead to the refusal of
the application as is contemplated by s 5.4.2(d)(i) of the IPA. In this way, so the
applicants argue, their entitlement to compensation might be established.
[47] The IPA contemplates that the Planning and Environment Court may excuse
non-compliance with the requirements of s 3.2.1 in certain circumstances. In that
regard, s 4.1.5A provides:
"How court may deal with matters involving substantial
compliance
(1) Subsection (2) applies if in a proceeding before the court,
the court -
(a) finds a requirement of this Act, or another Act in its
application to this Act, has not been complied with, or has
not been fully complied with; but
(b) is satisfied the non-compliance, or partial
compliance, has not substantially restricted the opportunity
for a person to exercise the rights conferred on the person by
this or the other Act.
(2) The court may deal with the matter in the way the court
considers appropriate."
[48] The DRP referred to above were the draft regulatory provisions of the Draft South
East Queensland Regional Plan ("the Draft SEQ Regional Plan"). Section 2.5A.13
and 14 were added to the IPA by the IPOLA. These provisions of the Act required
the Draft SEQ Regional Plan to be prepared by the Minister and published in the
Government Gazette. Section 2.5A.24(1) of the IPA provides:
11 See also s 5.4.9 of the IPA.
-- 12 of 21 --
13
"When a notice is published under section 2.5A.14(1)(a), any
proposed regulatory provisions of the draft SEQ regional plan (the
draft regulatory provisions) have effect until the SEQ regional plan
comes into effect."
[49] The notice contemplated by s 2.5A.14(1)(a) of the IPA was published in the
Government Gazette on 27 October 2004.
[50] As to the "effect" of the DRP referred to in s 2.5A.24(1), it may be noted that
s 2.5A.10(2) provides: "The SEQ regional plan is a statutory instrument under the
Statutory Instruments Act 1992 and has the force of law." The combined effect of
these provisions then is that, until the SEQ Regional Plan comes into effect, the
DRP have the force of law. They have that force by virtue of the IPA as amended
by the IPOLA.
[51] Section 2.5A.12(2)(d) of the IPA provides that "regulatory provisions" in the "SEQ
Regional Plan" may "… regulate development by, for example, stating aspects of
development that may not occur in stated localities". The regulatory provisions may
also "state transitional arrangements for development applications affected by the
regulatory provisions".
[52] The DRP are to be found in Pt 6 of the Draft SEQ Regional Plan. By s 1 of Pt 6, all
land in the region is allocated to one of five designated areas. One of those
designated areas is the "Regional Landscape and Rural Production Area". The
applicants' land is in this designated area.
[53] In relation to land within the Regional Landscape and Rural Production Area, the
DRP provide, by s 4:
"Certain reconfiguration prohibited
(1) Subsection (2) applies for land in the following areas:
(a) the Regional Landscape and Rural Production Area;
…
(2) Reconfiguration of a lot may not occur if any resulting lot
would have an area less than:
(a) if the planning scheme states a minimum lot size
greater than 100 hectares - the area stated in the planning
scheme; or
(b) to the extent the land is located in a designated
agricultural area the minimum lot size stated in the planning
scheme; or
(c) in any other case - 100 hectares.
(3) However subsection (2) does not apply if:
(a) the number of lots that would be created by the
reconfiguration is the same or less than the number of lots to
be reconfigured; or
(b) the reconfiguration is associated with a material
change of use for which a development approval is in effect;
or
(c) the reconfiguration is:
(i) for rural residential purposes on land
designated or zoned for rural residential purposes;
and
-- 13 of 21 --
14
(ii) the application for the reconfiguration is
made within two years of the day these Draft
Regulatory Provisions came into effect."
[54] In relation to s 4(3)(c)(i) of the DRP, the term "rural residential" was defined by the
DRP, as a "form of low-density residential developments characterised by large lots
of between 2,000 m2 to five hectares in a rural or semi-rural setting and with a net
residential density of less than four dwellings or residential lots per hectare".
[55] Section 6 of the DRP provided that the DRP does not apply to development
applications made before it came into effect.
[56] On 30 June 2005, there was published in the Government Gazette the notification of
the Minister under s 2.5A.16 of the IPA "that the South East Queensland Regional
Plan 2005 - 2026 (the SEQ Regional Plan) was made on 29 June 2005 and has
effect on and from 30 June 2005". It is common ground between the parties that
s 5(3)(c) of the regulatory provisions of the SEQ Regional Plan serves to continue
the application of the now superseded s 4 of the DRP in relation to the applicants'
application to the Council of 3 December 2004.
The decision of the primary judge
[57] Before the primary judge, the applicants argued that s 4(3)(c)(i) of the DRP did
apply to their application to the Council so that the application was a "properly
made application". This was contrary to the position taken by the Council. The
judge rejected the applicants' contention, holding that the applicants' land was not,
at the date of the application, currently "designated or zoned for rural-residential
purposes".12 It had been so zoned prior to the commencement of the 2003 planning
scheme; but was not so designated or zoned since 28 March 2003. The applicants
do not now seek to contest the correctness of this conclusion.
[58] The applicants also sought, at first instance, to rely upon s 20(2)(c) of the Acts
Interpretation Act 1954 (Qld) ("the AIA"). Section 20(2)(c) of the AIA serves to
preserve rights accrued under an Act from unintended abrogation or restriction.
That provision is to the effect that, in the absence of a clear indication of a contrary
intention, an amendment of an Act does not "affect a right, privilege or liability
acquired, accrued or incurred under the Act".
[59] The learned judge could not "perceive any scope for the operation of" the AIA.13
His Honour held that the IPA contemplates that a DA (SPS) for a development
permit may be denied the character of a properly made application by reason of the
operation of the DRP.14 If a development application is not a properly made
application, it cannot give rise to a right to compensation under the IPA. His
Honour proceeded on the footing that s 3.2.1(7)(f) of the IPA applies to a DA (SPS)
for a development permit. By reason of s 2.5A.12(2)(d) and s 2.5A.24(1) of the
IPA, the terms of the DRP may validly proscribe the development proposed by the
applicants. As a result, his Honour concluded, the Council had correctly refused to
accept the applicants' DA (SPS) for the reconfiguration of their land. It is this
conclusion which is the principal focus of the applicants' challenge in this Court.
12 Chang & Anor v Laidley Shire Council [2005] QPEC 075 at [25] - [26].
13 Chang & Anor v Laidley Shire Council [2005] QPEC 075 at [23].
14 Chang & Anor v Laidley Shire Council [2005] QPEC 075 at [26] - [31].
-- 14 of 21 --
15
[60] The applicants also sought to argue that s 4.1.5A of the IPA could be relied upon to
excuse the conflict between their application and s 4(2) of the DRP. His Honour
held that s 4.1.5A of the IPA was not of assistance to the applicants in this regard
for two reasons. First, his Honour was of the view that s 4.1.5A of the IPA afforded
the possibility of relief only to a:
"... person who should and could have complied fully with some
requirement of IPA or another Act. There is nothing the [applicants]
could have done to comply with the implied requirement that their
proposed development not be contrary to the DRP, consistently with
continued pursuit of that proposal."15
Secondly, his Honour considered that the Council was, by s 3.2.1(8) of the IPA,
"entitled (if not obliged) to refuse to accept the application".16
The applicants' arguments
[61] The first argument which the applicants would seek to agitate on appeal is that
"[t]he real issue is whether the applicants' potential compensation rights were lost".
The applicants rely on principles of statutory interpretation which require a
legislative intention to destroy rights to be clearly expressed.17
[62] The applicants, recognising that there are difficulties in putting their case on the
basis of an accrued right to compensation in terms of s 5.4.2 of the IPA, also seek to
put their case on the alternative basis that they had an accrued right to apply to
reconfigure their land and to have the processes appropriate to a DA (SPS) applied
to their application. Of course, to speak of a right to apply to reconfigure land is
not to identify a right which can sensibly be described as an entitlement to
compensation; but the applicants contend that the Council was obliged to accept,
assess and decide their application. If that contention were to be accepted, it might,
as I have earlier explained, then be possible for the applicants to satisfy the
requirements of s 5.4.2 so as to establish a right to compensation.
[63] The respondent submits that the right to make a DA (SPS) for a development permit
is not taken away by the DRP. Rather, s 3.2.1(7)(f) of the IPA operates to deny to
the particular application made by the applicants the character of a "properly made
application" for a development permit. Since "a properly made application" for a
development permit is essential to the operation of s 5.4.2, no right to compensation
could ever arise under that provision in respect of the application of 3 December
2004.
Discussion
[64] The applicants seek to invoke well established principles of statutory interpretation
against the unintended destruction of rights by general statutory provisions.18 The
applicants also seek to invoke the terms of s 20(2)(c) of the AIA against the
retrospective abrogation of accrued rights. The respondent contends that
s 3.2.1(7)(f) and s 5.4.2 of the IPA and s 4(2) of the DRP are quite specific in their
15 Chang & Anor v Laidley Shire Council [2005] QPEC 075 at [21].
16 Chang & Anor v Laidley Shire Council [2005] QPEC 075 at [21] - [22].
17 Cf Marshall v Department of Transport (2001) 205 CLR 603; [2001] HCA 37; Dossett v TKJ
Nominees Pty Ltd (2003) 218 CLR 1; [2003] HCA 69.
18 The Commonwealth v Hazeldell Ltd (1918) 25 CLR 552 at 563; Mabo v Queensland (No 2) (1991 -
1992) 175 CLR 1 at 111; Wik Peoples v State of Queensland (1996) 187 CLR 1 at 155; Marshall v
Department of Transport (2001) 205 CLR 603 at 623; Dossett v TKJ Nominees Pty Ltd (2003) 218
CLR 1 at 8 [21], 24 [80].
-- 15 of 21 --
16
terms; and, furthermore, emphasises that these provisions were in force when the
applicants' application for approval to reconfigure their land was made.
[65] The applicants place heavy reliance on the decision of this Court in Resort
Management Services Pty Ltd v Noosa Shire Council.19 That case was concerned
with the operation of s 33(10)(a) of the Local Government Act 1936 (Qld) ("the
1936 Act"). It was similar in its terms and effect to s 3.5(1) of the 1990 Act to
which reference has already been made. Section 33(10)(a) of the 1936 Act provided
relevantly:
"Claims for compensation.
(a) Subject to this section any person -
(i) who has an estate or interest in land included
within a town planning scheme ... and such estate or
interest is injuriously affected -
(a) by the coming into operation of any
provision contained in the scheme; or
(b) by any prohibition or restriction imposed
by or under the scheme …
shall, if he makes a claim therefore within the time
prescribed, be entitled to obtain from the Local
Authority compensation in respect of such injurious
affection …"
[66] The material facts in Resort Management Services Pty Ltd v Noosa Shire Council
were as follows. On 15 December 1990, an amendment to a town planning scheme
injuriously affected the respondent's interest in its land. On 15 April 1991, s 33 of
the 1936 Act was repealed. On 14 December 1993, and within the time allowed by
s 33 of the 1936 Act, the respondent lodged a claim with the applicants for
compensation for the injurious affection. The applicants argued that the respondent
had no right to compensation because no claim for compensation had been made
when s 33 of the 1936 Act was repealed. This Court held that the injurious
affection of the respondent's property was an event which led to the acquisition or
accrual of a right to compensation within the meaning of what is now s 20(2)(c) of
the AIA, even though the procedures for giving effect to that right had not
commenced at the time the 1936 Act was repealed.
[67] In that case, McPherson JA said:20
"In the end, the submission on behalf of the appellant Council now
comes down to this; that s. 33(10)(a) was the only basis for Resort
Management’s entitlement to compensation; and that, when that
provision was repealed on 15 April 1991, s. 20(1)(c) was not
effective to prevent its being extinguished. The statutory entitlement
to obtain compensation under s. 33(10) was, so it was said, not
within the meaning of s. 20(1)(c) a 'right' or a 'right acquired' so as to
be capable of surviving repeal of that provision; or at most it was,
until the claim was in fact made in 1993, only an inchoate or
contingent right on which s. 20(1)(c) did not or could not operate.
The submission on behalf of the Council possibly gains a little
(although very little) force from the presence in s. 33(10) of the
19 [1997] 2 Qd R 291.
20 [1997] 2 Qd R 291 at 297 - 298.
-- 16 of 21 --
17
words 'to obtain'; but that consideration is itself more than offset by
the use of the term 'entitlement' in the same context. I find it
impossible to view a statutory entitlement to compensation like
that conferred by s. 33(10)(a) on an identifiable person as
affording no more than a mere prospect or hope of recompense
for rights lost or taken away. No doubt it is true that, unless a
claim for compensation is made, no compensation will be paid;
but it does not follow that, until such a claim is made, the
entitlement has no existence, or that it is of such an inchoate or
contingent character as to be beyond the scope or protection of
s. 20(1)(c). By way of analogy, a common law right to recover
damages is viewed as a chose in action before any judgment for
damages is given, and even before any writ or claim to recover it has
been issued or made. As such, it is a form of personal property
capable of attracting the protection of the law: cf. Georgiadis v.
Australian and Overseas Telecommunications Corporation (1994)
179 C.L.R. 297.
The 'entitlement' to compensation conferred by s. 33(10) of the
Local Government Act is admittedly a creature not of the common
law but of statute; but it is not, for that reason, less capable of being
considered a 'right' within the meaning of s. 20(1)(c) of the Acts
Interpretation Act. It may be taken away, as it was created, by
statutory enactment; but so too may a right at common law. The
primary purpose of s. 20(1)(c) is to prevent rights which have
been created or conferred by statutes from being casually, or it
may be unintentionally, destroyed by repeal of the statute and
without any further or other specific indication of a legislative
intention to do so going beyond the fact of the repeal itself. Apart
from that, s. 20(1)(c) has no recognisable function." (emphasis
added)
[68] Fryberg J said:21
"How then should s. 33(10)(a) of the 1936 Act be construed? Is the
making of a claim within the prescribed time part of the definition of
the right conferred by the section? If it is not there seems little doubt
that the right is one falling under s. 20(1)(c) of the Acts
Interpretation Act 1954. Obviously, the clause expresses a condition.
It refers to matters of procedure which are spelled out in greater
detail in s. 33(12). In Esber v. The [Commonwealth] the majority
said, 'Section 8 of the Acts Interpretation Act protects anything that
may truly be described as a right, ‘although that right might fairly be
called inchoate or contingent’.' ((1992) 174 CLR at 440) In my
judgment that describes the situation in the present case. Resort
Management had a right to compensation subject to the adoption
of the procedures prescribed by the statute for working out that
right. As the Privy Council said in Director of Public Works v. Ho
Po Sang:
'It may be, therefore, that under some repealed enactment
a right has been given but that in respect of it some
investigation or legal proceeding is necessary. The right
21 [1997] 2 Qd R 291 at 307 - 308 (citations footnoted in original).
-- 17 of 21 --
18
is then unaffected and preserved. It will be preserved
even if a process of quantification is necessary. But there
is a manifest distinction between an investigation in
respect of a right and an investigation which is to decide
whether some right should or should not be given. Upon
a repeal the former is preserved by the Interpretation
Act.' ([1961] AC at 922).
The present case is in the former class referred to by the Privy
Council. Making a timely claim is not one of the elements
defining the right but is merely a condition of its exercise. The
function of the condition is not to limit the class of people who
would otherwise acquire the right - that was achieved by the
other elements of s. 33(10)(a). It is to provide a cross-reference to
the procedure prescribed for the exercise of the right. That is why
this case differs from cases like Continental Liqueurs Pty Ltd v. G.F.
Heublein and Bro. Inc., where commencement of proceedings is the
factor that marks out those who have rights (to pursue litigation or
some other process) from the public in general (or a large class of it)
who merely have a right to take advantage of an enactment."
(emphasis added)
[69] These passages highlight the contrast between the effect of provisions such as
s 33(10) of the 1936 Act and s 3.5(1) of the 1990 Act on the one hand, and the
statutory provisions of present concern on the other. Section 5.4.2 of the IPA
creates a right to compensation, not upon the occurrence of injurious affection, but
upon, and by reference to, the outcome of the process of assessment by the Council
of an application to carry out a form of development. There can be no entitlement
to compensation unless there is a decision by the Council as assessment manager
which establishes the basis for compensation. The decision of the local authority in
respect of the proposed development is essential to the existence of an entitlement
to compensation. It is not merely a step in the process of enforcing an entitlement
to compensation.
[70] The steps contemplated by the provisions of s 5.4.2(b) to (d) of the IPA are not,
either as a matter of form or substance, merely "a cross-reference to the procedure
prescribed for the exercise of the right" to compensation: they are "elements
defining the right". Under IPA, the Council, as assessment manager, may, apart
from the IPOLA amendments, choose to assess a development application on the
basis that an applicant's development rights are those conferred by the superseded
planning scheme. If the assessment proceeds on that basis, the Council will have
exercised a choice to override its current planning scheme and policies. As a result,
there will be no entitlement to compensation. In the present case, by reason of the
IPOLA amendments and s 3.2.1(7)(f) and s 3.2.1(10)(b), the Council's power to
choose to assess an application on the basis of the superseded planning scheme has
been forestalled by the legislature where the proposed development would be
contrary to the DRP. This modification of the Council's role and powers is a matter
of substance. It goes to the Council's power to override the planning arrangements
otherwise applicable to the land and to the consequential possibility of a right to
compensation as opposed to the procedure whereby that right is to be enforced.
This state of affairs has come about because of an evident legislative intention that
councils should not be able to override the terms of the SEQ Regional Plan.
-- 18 of 21 --
19
[71] The second point to be made here is that there can be no suggestion that the
legislature may be taken to have "casually or … unintentionally" destroyed any
right to compensation of a landowner by the enactment of s 5.4.2 of the Act. To the
extent that, in the present case, it is true to say, as the applicants do, that their
application for reconfiguration was bound to be refused by the Council, that is a
consequence which flows from the legislative decision to forestall the assessment
process by the assessment manager in cases where the development proposed is not
in accordance with the DRP. Under s 3.5.1 of the 1990 Act, an entitlement to
compensation arose upon the occurrence of "adverse affection" as had been the case
under s 33 of the 1936 Act. In the IPA, the legislature took a radically different
approach to defining the right to compensation for what was previously called
"injurious affection" in the formulation of s 5.4.2 of the Act. It cannot be accepted
that, by the IPOLA amendments to the IPA, the legislature failed to advert to the
likely effect on claims for compensation under s 5.4.2 as a result of the introduction
of s 3.2.1(7)(f) and s 3.2.1(10)(b). These provisions were plainly apt to have the
effect that the assessment necessary to the accrual of a right to compensation could
not occur in respect of an application in respect of which the DRP prohibited
development which might otherwise have been allowed under a superseded
planning scheme. It is, in my respectful opinion, impossible to conclude that
s 3.2.1(7)(f) and s 3.2.1(10)(b) were not deliberately intended to have that effect,
bearing in mind that they were enacted as part of the package of measures
introduced by IPOLA and that they were clearly intended to operate in respect of
applications made after the IPOLA commenced to operate.
[72] In truth, the question is not, as the applicants seek to frame it, whether the
legislature has abrogated a right by "clear words or a necessary implication to that
effect".22 The true question is whether any right to compensation has accrued at all
to the applicants under the statute which creates that right. It is, in my respectful
opinion, clear that no such right could accrue to the applicants until the assessment
process contemplated by s 5.4.2 of the IPA has been completed. As a result of the
amendments to the IPA effected by the IPOLA, persons in the position of the
applicants could not establish a right to compensation where the development rights
which were said to be adversely affected were so affected by limitations on
development imposed by the DRP in force by virtue of the IPOLA at the time a
development application is made.
[73] The difficulty which confronts the applicants is not avoided by the contention that
the right which had accrued to the applicants and which was not abrogated by the
IPOLA was a right to make their application and to have it assessed in accordance
with s 5.4.2 of the IPA as if the IPOLA and the DRP had not come into force.
[74] The provisions of s 3.2.1(7)(f) and s 3.2.1(10)(b) apply to all applications made
after they came into force as part of the IPOLA. They operate to prevent the
Council, as an assessment manager, accepting the application for assessment
because the DRP, not a new planning scheme, had prohibited the use in question.23
The provisions of the IPOLA mean that the Council's role in the assessment of
development applications is forestalled in the case of applications for development
which is contrary to the DRP. The Council may not make either a decision to
22 Dossett v TKJ Nominees Pty Ltd (2003) 218 CLR 1 at 8.
23 Cf Attorney-General (Qld) v AIRC (2002) 213 CLR 485.
-- 19 of 21 --
20
override the planning regime established by the SEQ Regional Plan, or a decision
not to do so, and thereby establish an entitlement to compensation.
[75] In my respectful opinion, it is clear that s 3.2.1(7)(f) and s 3.2.1(10)(b) of the IPA,
as amended by the IPOLA, apply to any development application made after the
commencement of the IPOLA to prevent the assessment by the local authority of
such an application. To paraphrase the language of Gleeson CJ in Attorney-General
for the State of Queensland v Australian Industrial Relations Commission and
Ors, 24 these sections do not provide that the Council may assess some applications,
which are not "properly made applications" because they are contrary to the DRP,
but not others. They simply provide that the Council may not assess any such
applications.
[76] The applicants were driven to argue that a DA (SPS) within s 5.4.2 of the IPA is not
an "application" within the meaning of s 3.2.1(7)(f) and its associated provisions.
This argument is untenable. There is no dichotomy between a development
application and a DA (SPS) for a development permit. The provisions of the IPA
treat a DA (SPS) as a particular kind of development application. In this regard, the
first element of the definition of the term DA (SPS) is "a development application".
Similarly, s 3.2.3(1) of the IPA imposes the obligation of giving an
acknowledgment notice upon "the assessment manager for an application", and
s 3.2.3(1)(b) expressly refers to a DA (SPS) as a species of application. Moreover,
there are no provisions of the IPA, other than the provisions which deal with the
making and assessment of development applications generally, which provide for
the making and assessment of a DA (SPS) for a development permit.
[77] The provisions of s 4.1.5A of the IPA do not assist the applicants. The general
provisions of s 4.1.5A cannot prevail against the specific provisions of s 3.2.1(7)(f)
and s 3.2.1(10)(b) which are directly concerned to ensure that an application for a
development permit for development which is contrary to the DRP should not even
be received by the assessment manager.
[78] For the sake of completeness, I should also mention that during the hearing of the
application there was extensive argument in relation to the operation of s 5.4.4 of
the IPA on the basis that this provision might have the effect of confirming that no
compensation was payable to the applicants because any diminution in the value of
their land was due to the DRP as well as to the 2003 planning scheme. In the end, it
is unnecessary to determine the proper construction of s 5.4.4, and any implications
which that might have for the resolution of the issues in this case.
[79] The rejection of the applicants' submissions does not reflect a narrow interpretation
of the provisions of the IPA, much less a failure to give effect to well-known
presumptions against the casual or unintended or retrospective destruction of rights.
Whatever view one may have of the desirability of the means whereby the SEQ
Regional Plan has been facilitated by the IPOLA as a matter of policy, this Court
cannot ignore the limitations which the legislature has placed on the recovery of
compensation from local authorities for the adverse effects upon property owners of
changes in planning arrangements effected pursuant to the IPOLA.
24 (2002) 213 CLR 485 at 493.
-- 20 of 21 --
21
Conclusion and orders
[80] In my respectful opinion, the decision of the learned primary judge was clearly
correct. Accordingly, I would refuse the application for leave to appeal.
[81] The applicants should pay the respondent's costs of and incidental to the application
to be assessed on the standard basis.
[82] PHILIPPIDES J: I have had the advantage of reading the reasons for judgment of
Keane JA for which I am grateful. I respectfully agree for the reasons stated by
Keane JA that the application for leave to appeal should be refused with costs.
-- 21 of 21 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2006/172