Cant Contracting P/L v Casella & Anor [2006] QSC 242
SUPREME COURT OF QUEENSLAND
CITATION: Cant Contracting P/L v Casella & Anor [2006] QSC 242
PARTIES: CANT CONTRACTING PTY LTD (ACN 079 036 025)
(plaintiff)
v
CON CASELLA
(defendant)
MICHELLE LYNDSAY CASELLA
(defendant)
FILE NO/S: SC No 5925 of 2005
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 1 September 2006
DELIVERED AT: Brisbane
HEARING DATE: 24 August 2006
JUDGE: de Jersey CJ
ORDER: 1. That the plaintiff have leave to amend its claim in
accordance with the amended claim in Ex 1 to the
affidavit of Troy Jonathan Lewis filed 3 August 2006
2. That there be judgment for the plaintiff against the
defendants in the amount of $493,339.45 together with
interest under s 47 of the Supreme Court Act 1995
(Qld) from 15 April 2006 to judgment
3. That the defendants pay the plaintiff’s costs of and
incidental to the application filed 3 August 2006, to be
assessed on the standard basis
CATCHWORDS: BUILDING, ENGINEERING AND RELATED
CONTRACTS – REMUNERATION – RECOVERY ON
QUANTUM MERUIT – IN GENERAL – statutory right of
debt recovery under s 19 Building and Construction Industry
Payments Act 2004 (Qld) – where no payment schedule
delivered – unlicensed builder – whether statutory right of
recovery is qualified by s 42 Queensland Building Services
Authority Act 1991 (Qld)
Building and Construction Industry Payments Act 2004
(Qld), s 10, s 17, s 18, s 19
Queensland Building Services Authority Act 1991 (Qld), s 42,
s 43
-- 1 of 4 --
2
Brodyn Pty Ltd t/as Time Cost and Quality [2004] NSWCA
394, cited
Lucas Stuart Pty Ltd v Council of the City of Sydney [2005]
NSWSC 840, cited
COUNSEL: M J F Burnett for the plaintiff
P J McHugh for the defendants
SOLICITORS: Holding Redlich for the plaintiff
Graham & Associates for the defendants
[2] de JERSEY CJ: By its original claim, the plaintiff claimed $493,339.45 as monies
owing under an agreement between the parties of 1 November 2004, or on the basis
of a quantum meruit under s 43 of the Queensland Building Services Authority Act
1991 (Qld).
[3] It is common ground between the parties that on or about 1 November 2004, the
plaintiff and the defendants agreed that the plaintiff manufacture, supply and erect
poultry houses for the defendants. It was likewise not disputed that the agreement
was a “construction contract” within the meaning of the Building and Construction
Industry Payment Act 2004 (Qld) (see Sch 2 and s 10). The terms of the contract
relating to payment entitled the plaintiff to what that Act terms “progress payments”
(Sch 2). See the document headed “quotation”. It is also not disputed that the
plaintiff carried out the work under the contract, for which the plaintiff has not been
paid notwithstanding demand, in the amount of $493,339.45, the amount presently
claimed.
[4] On 31 March 2006, the plaintiff served on the defendants a “payment claim” under
s 17 of that Act. There is no dispute about the procedural regularity of that claim.
Section 18 entitled the defendants to serve, in response, a “payment schedule”,
within a prescribed timeframe. That was not done.
[5] Section 18(5) provides that in such circumstances, the defendants “become liable to
pay the claimed amounts…on the due date for the progress payment to which the
payment claim relates”. Section 19 then operates to entitle the plaintiff to “recover
the unpaid portion of the claimed amount…as a debt owing to the (plaintiff)”. The
plaintiff seeks to amend the claim to add an alternative claim for the sum as a debt
due under s 19 of that Act.
[6] Mr McHugh, who appeared for the defendants, did not oppose the grant of leave to
amend the claim. There is no limitations issue, and on 5 July 2006, the plaintiff
delivered an amended statement of claim adding this basis for relief. Leave to
amend the claim to bring it into conformity with the amended statement of claim
should therefore be granted.
[7] In their original form, the claim and the statement of claim needed to confront the
circumstance that on the evidence before me, the plaintiff did not, when it carried
out the relevant work, hold the requisite contractor’s licence. That may eventually
become a matter of dispute, if the proceeding continues, but for present purposes
that is where the factual position sits. Consequently, the plaintiff would be limited,
in its recovery, by s 42(4) of the Queensland Building Services Authority Act 1991.
But Mr Burnett, who appeared for the plaintiff, submitted that would be irrelevant
-- 2 of 4 --
3
to the claim added by amendment, founded on s 19 of the Building and
Construction Industry Payments Act 2004.
[8] Mr McHugh essentially submitted that the otherwise apparently plain right of
recovery arising in the plaintiff’s favour under s 19(2) of the Building and
Construction Industry Payments Act should be read as subject to the qualified right
of recovery limited by s 42 of the Queensland Building Services Authority Act. The
amendment to the claim having been made, Mr Burnett sought summary judgment
for the amount claimed, on the basis of his construction of the Building and
Construction Industry Payments Act. Mr McHugh accepted that if Mr Burnett’s
construction were upheld, summary judgment should be given, and in the amount
claimed. The question is purely one of statutory construction, and it is one which
can and should be answered summarily.
[9] Mr Burnett rightly conceded that had the defendants wished to rely on the absence
of the requisite licence in response to the plaintiff’s claim, as made in its “payment
claim” under s 17 of the Building and Construction Industry Payments Act, the
defendants could have done so in a “payment schedule” under s 18. The issue is
whether, the defendants’ having failed to deliver a payment schedule, the defendants
can resist the plaintiff’s apparent right to judgment under s 19(2)(a) by subsequently
raising the licensing issue; in other words, whether the ultimate operation of the
mechanism established by the Building and Construction Industry Payments Act is
to be read as subject to a supervening qualification arising from s 42 of the
Queensland Building Services Authority Act.
[10] Apart from the absence of any expression of such a qualification in s 19 of the
Building and Construction Industry Payments Act, Mr Burnett pointed to the
circumstance that that Act does in other situations import certain provisions of the
Queensland Building Services Authority Act. See, especially, s 26(2)(a), which
obliges an adjudicator to have regard to Part 4A of the Queensland Building
Services Authority Act. Section 19 of that Act does not fall within its Part 4A.
[11] A broadly comparable situation confronted the Supreme Court of New South Wales
in Lucas Stuart Pty Ltd v Council of the City of Sydney [2005] NSWSC 840, a
decision given on 23 August 2005. No payment schedule had been delivered, yet
the respondents sought to rely on various defences in the context of a claim for
summary judgment. On the basis of legislation in materially the same terms as
these, Einstein J said (para 21):
“…the Court may comfortably be satisfied that…the Council has
become ‘liable to pay the claimed amount to the claimant under s
14(4) as a consequence of having failed to provide a payment
schedule to the claimant within the time allowed by that section’,
within the meaning of these words as found in s 15(1)(a). The
critical words are ‘has become liable to pay the claimed amount to
the claimant under s 14(4)’. These words create what may be
described as a strictly mechanical scheme. Whilst ever the
environment concerns the engagement of the fast track interim
provisions of the Act [as opposed to the parties retained curial rights
to have a final determination of their dispute on a later occasion]
there is simply no room for moving outside of this scheme…the
Council can be seen by its stance in the instant proceedings to seek to
-- 3 of 4 --
4
move outside this strictly mechanical scheme. The Act permits no
such thing.”
[12] The New South Wales Court of Appeal in Brodyn Pty Ltd t/as Time Cost and
Quality v Davenport [2004] NSWCA 394, dealt with the relevance, to the statutory
right to recover the amount claimed as a debt, of the absence of the requisite
builder’s licence. The legislation was again comparable. In this case the respondent
delivered a payment schedule in response to a payment claim, but omitted to raise
as a ground for non-payment the fact that the builder was not licensed. The point
was first raised on appeal. Hodgson JA said (para 82):
“…the civil consequences for an unlicensed contractor for its breach
of s 4 are those set out in s 10, and not any wider deprivation of
remedies … this is confirmed by the different provisions of s 94 …
the remedy given by the Act is not of the nature of damages or any
other remedy in respect of breach of contract nor is it enforcement of
the contract: it is a statutory remedy, albeit one that in part makes
reference to the terms of a contract, and thus it is not affected by s 10
of the HBA (Home Building Act).”
[13] I accept Mr Burnett’s submissions.
[14] I make the following orders:
1. That the plaintiff have leave to amend its claim in accordance with the
amended claim in Ex 1 to the affidavit of Troy Jonathan Lewis filed 3
August 2006;
2. That there be judgment for the plaintiff against the defendants in the amount
of $493,339.45 together with interest under s 47 of the Supreme Court Act
1995 (Qld) from 15 April 2006 to judgment;
3. That the defendants pay the plaintiff’s costs of and incidental to the
application filed 3 August 2006, to be assessed on the standard basis.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2006/242