CBQ v Welsh & Ian Hammett Electrical Pty Ltd [2006] QSC 235
SUPREME COURT OF QUEENSLAND
CITATION: CBQ v Welsh & Ian Hammett Electrical Pty Limited [2006]
QSC 235
PARTIES: CBQ PTY LTD ACN 066 599 559
(Applicant)
AND
RUSSELL WELSH
(First Respondent)
AND
IAN HAMMETT ELECTRICAL PTY LTD
ACN 010 797 323
(Second Respondent)
FILE NO/S: S736 of 2005
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court
DELIVERED ON: 19 June 2006
DELIVERED AT: TOWNSVILLE
HEARING DATE: 14 June 2006
JUDGE: Cullinane J
ORDER: Application dismissed with costs to be assessed.
CATCHWORDS: ADMINISTRATIVE LAW – STATUTORY REVIEW –
Where applicant sourt a review of adjudication of the
Building and Construction Industry Payments Act 2004 (Qld)
– where contract concluded before 1st October 2004 – where
written contract after 1st October 2004.
Building and Construction Industry Payments Act 2004 (Qld)
The King v Blakeley: Ex Parte Association of Architects etc
of Australia (1950) 82 CLR 54 cited
Trollope & Colls Ltd & Anor v Nuclear Civil Constructors &
Anor (1973) 1 WLR 601 cited
COUNSEL: Mr D. Morzone for the Applicant
-- 1 of 6 --
2
Mr A.T. Moon for the Respondent
SOLICITORS: Boulton Cleary Kern Lawyers for the Applicant
Wilson Ryan Grose Lawyers for the Respondent
[1] This is an application for a statutory review of an order of the First
Respondent an adjudicator under the Building and Construction Industry
Payments Act 2004.
[2] The order made by the First Respondent was made on the 25th October 2005.
it required the Applicant to pay to the Second Respondent the sum of
$34,907.35 together with interest.
[3] The nature of the scheme provided for by the legislation and its evident aims
do not fall for consideration here.
[4] The primary challenge made to the adjudicator’s decision is that the contract
between the Applicant and the Second Respondent was concluded prior to 1 st
October 2004 and that being so the First Respondent had no jurisdiction to
make any order under the Act. The application preceded upon the basis that
this was correct.
[5] The Applicant did not place any material before the First Respondent nor did
it place any submissions before him.
[6] The issue which was raised here was not raised before the First Respondent
who made the following finding on the subject of jurisdiction: “5.1. The
construction contract was entered into after the commencement of the Act
pursuant to s.3(1) of the Act.”
[7] It was not however contended by the Second Respondent that it was not
open to the Applicant to agitate a jurisdictional fact of this nature on an
application for judicial review. See also The King v Blakeley: Ex Parte
Association of Architects etc of Australia (1950) 82 CLR 54
[8] The parties entered into a sub-contract in a standard form (MW.SC-12002)
commencing at page 24.
[9] This contract contains the following clause:
“R.10 Entire Contract
This subcontract contains everything the contractor has agreed with
the sub-contractor in relation to the matters it deals with. Neither
party may rely on an earlier contract, or on anything else said or
done by the other party (or by an officer, agent or employee of the
other party) before this subcontract was entered into.
[10] The date that the contract was executed was the 9th November 2004.
-- 2 of 6 --
3
[11] The Applicant here contends that a contract had been earlier concluded in
dealings (both written and oral) between the parties and that it had been
concluded prior to 1st October 2004.
[12] There are a number of affidavits filed on either other side and the deponents
were called to give evidence. One of these was John Barei who is a director
of the Applicant. A significant part of the first of two affidavits sworn by
him was based upon hearsay or is assertive in character and objection was
taken to this and upheld.
[13] Similarly some parts of the Affidavit of Colin John Schmitzer who was the
construction site supervisor of the Applicant at the relevant time were
successfully objected to on similar grounds.
[14] The Applicant relies upon what is said to be an oral acceptance of a written
offer by the Second Respondent. It is said to have been accepted by one
Gary Nilsson who at the time was the Applicant’s general manager. Mr
Nilsson was not called to give evidence and his whereabouts are said to be
unknown
[15] The result was that the Applicant was ultimately driven to rely upon what is
contained in some correspondence and documentation in order to contend for
the existence of a contract prior to 1st October 2004.
[16] The principal of the Second Respondent one Ian John Hammett was a
deponent. He gave evidence. All relevant dealings on behalf of the Second
Respondent involved him.
[17] On 25th May 2004 the Second Respondent wrote a letter to the Applicant
submitting a tender for the works. The works were electrical work to be
performed in the course of the construction of a block of apartments
described as The Docks at Magnetic Island. The amount tendered related to
the works described in that letter and there were also some provisional cost
items referred to. There had been an earlier tender by the Second
Respondent. At some time after this a further tender was made. The
documentation relating to this does not appear to be before the court.
[18] By a letter of 17th September 2004 (which appears to have followed some
discussions between the parties) the Applicant wrote to the First Respondent
in the following terms:
“THE DOCKS APARTMENTS – MAGNETIC ISLAND
SUBCONTRACT – ELECTRICAL
In accordance with our discussions we hereby confirm our intention to
negotiate a Subcontract Agreement with Hammett Technologies Pty Ltd
(quotation date 25/05/04) for the Electrical Trade applicable to the above
project.
The Contract will be forwarded to you by Friday 24 th September 2004.
Contract Particulars are:
-- 3 of 6 --
4
Contract Conditions- ABIC MW-1 2003 Major Works
Contract
Project Commencement Date - Monday 20th September 2004
Project Completion Date - Thursday 31st March 2005
CBQ Pty Ltd Project Manager - Gary Cox, Tel 4775 5822
CBQ Pty Ltd Site Supervisor - Colin Schmitzer, Tel 0418 1823 318
Site Address - 13-15 Terrace Place
Magnetic Harbour
Nelly Bay
Magnetic Island”
[19] In a further letter of 21st September 2004 the Applicant wrote to the Second
Respondent stating that it had previously issued a letter of intent for the
project which “as previously discussed is to incorporate the removal of
reference to L.P.C. sums.” It went on to ask for the Second Respondent’s
response to this.
[20] The Second Respondent provided this in a letter dated 21st September 2004.
By a letter dated 22nd September 2004 the Second Respondent referred to the
Applicant’s letter of 17th September and pointed out that the Second
Respondent had re-tendered for the project since the tender of 25th May 2004
referred to in the Applicant’s letter and the re-tendered amount was
considerably higher.
[21] By a letter of 22nd October 2004 the Applicant forwarded to the Second
Respondent a number of documents essentially being the subcontract
agreement in standard for subsequently executed and associated documents.
[22] In response the Second Respondent wrote on 25th October 2004:
“With reference to the above document I would like to advise that we are not
in a position to sign this document in its current form. The sub contract
document received make reference to our initial tender submission dated
May2004.
You may not be aware we forwarded to Gary Nilsson our revised bid for this
project on the 21st September 2004 which was verbally accepted a few days
later.
Please amend your current sub contract agreement to reflect this latest offer
and reforward to our office at your earliest convenience.
Should you wish to discuss this matter further please do not hesitate to
contact me at your earliest convenience.”
-- 4 of 6 --
5
[23] The Applicant relies upon what is contained in this letter is evidence that
there has been a concluded contract constituted by Mr Nilsson’s acceptance
of “our revised bid for this project.” Reliance was also placed upon a
document which is exhibited to the Affidavit of Mr Schmitzer called a daily
project report of 28th September 2004. It related that an electrician had
attended on the side to check on a layout. At the same time a document
described as “general information and site rules” was signed by Mr
Hammett. A copy of this is exhibited to the second Affidavit of Mr Barei.
[24] The effect of evidence for the Applicant was that the Second Respondent
would not have been allowed to enter upon the premises except for the
purposes of carrying out work for which he had already been engaged.
There was evidence that it was the practice of the Applicant to have sub-
contractors sign the “general information and site rules” document.
[25] Mr Hammett acknowledges that he was on the site on 28 th September but
says that it was for the purposes of looking at provisional sum of some items
so as to “firm the price”. He says that Mr Nilsson had wanted fixed sums for
these items and that he was still in negotiations with Mr Nilsson about these
matters as at 1 st October.
[26] It is common ground that shortly after 1st October the Second Respondent
was on site performing certain works and that these works were the subject
of the contract. Mr Hammett said that he had been asked to commence these
works by the Applicant and that they were done in anticipation of a written
contract being concluded.
[27] There are it seems to me three difficulties about the Applicant’s claim that
the court should be satisfied that the parties had concluded the contract prior
to the 1st October 2004 and that, as the argument must go, the subsequent
formal contract did no more than record an agreement already in place.
[28] The first difficulty is the evidence of Mr Hammett, that he and Mr Nilsson
were still negotiating in relation to what had been provisional cost items as at
1st October and that it was in relation to these that he went on the site on 28th
September. I thought he was an honest and reliable witness and his account
was not at odds with the documentary evidence. In fact it seems to me to be
consistent with the letter from the Applicant to the Second Respondent on
21 st September 2004 and some following correspondence.
[29] On this basis there was no concluded contract prior to 1 st October
notwithstanding that (I infer) Mr Nilsson may have been content with the
altered tender price.
[30] Secondly as will be seen by reference to the correspondence (a letter from
the Applicant to the Second Respondent dated 17th September 2004 and the
letters passing between the parties on 22 nd October 2004 and 25th October
2004) the parties clearly contemplated the execution of a formal written
contract. In my view the proper conclusion to draw is that they intended to
be contractually bound by the execution of such a document, a conclusion
which is not affected by the fact that work was performed in anticipation of
-- 5 of 6 --
6
this occurring. See Trollope & Colls Ltd & Anor v Nuclear Civil
Constructors & Anor (1973) 1 WLR 601.
[31] Finally there is clause R.10 of the contract. On the fact of it it amounts to an
acceptance by both parties that it is the written contract with provides for the
parties’ rights and obligations and not any prior dealings. In many if not
most cases a written contract would be preceded by an agreement of some
kind. Clause R10 expressly precludes reliance upon any agreement but the
written one.
[32] The primary challenge to the order made therefore must fail. The only
remaining ground relates to an alleged failure on the part of the adjudicator
to allow the Second Respondent to make further submissions.
[33] In his adjudication the First Respondent relates at clause 4.2:
“Pursuant to section 25(4)(a) of the Act, I requested further written
submission from the claimant in respect of confirmation that the adjudication
application had been served on the respondent. Pursuant to section
(25(4)(b) of the Act a deadline of 17 th October 2005 was set for the further
submission, with a deadline of 18th October 2005 set for the respondent’s
comments. The claimant made the requested further submission on 17 th
October 2005, comprising the following:-
Facsimile from Wilson Ryan Grose Lawyers dated 17 th October 2005
-Statutory Declaration of Helen Louise Harbourne.”
[34] The first sentence I am told relates to confirmation sought by the First
Respondent that the adjudication application had been served on the
Applicant. It goes on to relate that a deadline for further submissions by
both parties was then set.
[35] The Applicant did not place any material before the First Respondent nor
make any submissions.
[36] Mr Barei swears that he cannot find any record of having received any
notification of a further deadline for submissions. He referred in his evidence
to “a missing document which we weren’t able to find”.
[37] Simply to state that no document can now be found cannot constitute a basis
for a positive conclusion that the Applicant was not given an opportunity to
make further submission. I repeat the Applicant had previously chosen not
to place any material or submissions before the First Respondent.
[38] The application must fail.
[39] I order that the application be dismissed with costs to be assessed.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2006/235