Austrak Pty Ltd v John Holland Pty Ltd [2006] QSC 103
SUPREME COURT OF QUEENSLAND
CITATION: Austrak Pty Ltd v John Holland Pty Ltd [2006] QSC 103
PARTIES: AUSTRAK PTY LTD (ABN 72 008 925 031)
(applicant)
v
JOHN HOLLAND PTY LTD (TRADING AS
REGIONAL RAIL LINK) (ABN 11 004 282 268)
(respondent)
FILE NO: S3403 of 2006
DIVISION: Trial
PROCEEDING: Originating application
ORIGINATING
COURT: Supreme Court of Queensland
DELIVERED ON: 12 May 2006
DELIVERED AT: Brisbane
HEARING DATE: 8 May 2006
JUDGE: Chesterman J
ORDER: Upon the applicant giving the usual undertaking as to
damages:
1. the respondent be restrained by itself, its officers,
servants, agents or assigns until trial or earlier order
from making any demand that HSBC Bank Australia
Ltd convert unconditional undertaking no. 11084204
dated 30 March 2005 into money;
2. the respondent pay to the applicant the sum of
$1,804,353.10 by way of bank cheque in exchange for
the applicant delivering to the respondent an
unconditional undertaking by HSBC Bank Australia
Ltd promising to pay the respondent on demand the
sum of $1,804,353.10;
3. the respondent by itself, its officers, servants, agents
or assigns until trial or earlier order be restrained
from making any demand on HSBC Bank Australia
Ltd to convert the said undertaking into money;
4. the respondent’s cross-application to have the
originating application transferred to the Supreme
Court of Victoria is adjourned; and
5. the costs of both applications be reserved.
-- 1 of 14 --
2
CATCHWORDS: EQUITY – EQUITABLE REMEDIES – INJUNCTIONS –
INTERLOCUTORY INJUNCTIONS – Injunctions to
preserve status quo and property pending determination of
rights – Other matters – where applicant provided first
unconditional undertaking to guarantee performance of
contract – where respondent alleges applicant's performance
was defective – where respondent's right to convert
undertaking subject to implied negative stipulation in contract
– where respondent intimated intention to convert
undertaking – where there is a serious question to be tried as
to respondent's right to convert undertaking – whether
applicant is entitled to interlocutory relief restraining
respondent from converting unconditional undertaking
EQUITY – EQUITABLE REMEDIES – INJUNCTIONS –
INTERLOCUTORY INJUNCTIONS – Balance of
convenience – where applicant provided second
unconditional undertaking – where terms of contract
governing right to convert undertaking are in dispute – where
respondent converted undertaking – where there is a serious
question to be tried as to respondent's right to convert
undertaking – where applicant alleges respondent's calling on
undertaking will cause irreparable damage to reputation if
respondent not required to reimburse applicant for amount of
undertaking – where applicant seeks mandatory interlocutory
injunction requiring respondent to reimburse applicant for
amount of undertaking – whether the balance of convenience
favours granting interlocutory relief
Jurisdiction of Courts (Cross Vesting) Act 1987 (Qld), s 5(2)
Abigroup Contractors Pty Ltd v Peninsula Balmain Pty Ltd
(unreported, Supreme Court of New South Wales, Hunter J, 2
December 1999, No. 55034/99), followed
Bachmann Pty Ltd v BHP Power New Zealand Ltd [1999] 1
VR 420, cited
Barclay Mowlem Construction Ltd v Simon Engineering
(Australia) Pty Ltd (1991) 23 NSWLR 451, followed
CS Phillips Pty Ltd v Baulderstone Hornibrook Pty Ltd
(unreported, Supreme Court of New South Wales, Giles J,
26 October 1994, 55040/94), followed
Films Rover International Ltd v Cannon Film Sales Ltd
[1987] 1 WLR 670, followed
Pearson Bridge (NSW) Pty Ltd v State Rail Authority of NSW
(1982) 1 AusConstrLR 81, cited
Reed Construction Services Pty Ltd v Khen Seng (Australia)
Pty Ltd (1999) 15 BCL 158, followed
Rejan Constructions Pty Ltd v Manningham Medical Centre
Pty Ltd (2003) 19 BCL 451, cited
Walter Construction Group Ltd v Secretary, Department of
Infrastructure (unreported, Supreme Court of Victoria,
Byrne J, 6 June 2000, No. 4637/00), followed
-- 2 of 14 --
3
COUNSEL: J Bond SC with P Franco for the applicant
D J S Jackson QC with P Roney for the respondent
SOLICITORS: Clayton Utz for the applicant
Deacons for the respondent
[1] On 5 August 2003 the applicant and the respondent made a written contract by
which the applicant was to supply 175,000 concrete railway sleepers for the
‘Regional Fast Rail Project’, the improvement of four regional railway lines in
Victoria to enable them to carry trains travelling at speeds of 160 kilometres per
hour. The respondent (together with another contractor) was awarded contracts by
the Victorian Government to design and construct two of the regional railway lines.
The contract between the applicant and the respondent has been performed but in
2004 the respondent complained that on some segments of the lines the tracks were
too close together.
[2] The respondent has been put to considerable expense to rectify the problem created
by the gauge of the railway lines being too narrow. It asserts that the problem with
the gauge was caused by the sleepers, or numbers of them, not having been
constructed to the contractual dimensions. It asserts that the applicant had
tentatively admitted liability. The applicant denies that its performance of the
contract was defective. It also denies having made any admissions to the effect that
it had not properly performed the contract.
[3] The applicant procured its bank, HSBC Australia Ltd (‘HSBC’), to provide two
unconditional undertakings each addressed to the respondent promising to pay, on
demand, sums of money specified respectively in the undertakings.
[4] By an originating application the applicant seeks:
(a) an injunction restraining the respondent until trial or earlier order from making
any demand upon HSBC to convert its unconditional undertaking no.
11084204, dated 30 March 2005, into money;
(b) an injunction requiring the respondent to pay to the applicant the sum of
$1,804,353.10 by way of bank cheque in exchange for the applicant delivering
to the respondent a new guarantee in the same terms as the unconditional
undertaking 11084203 dated 1 April 2005 given by HSBC; and
(c) an injunction restraining the respondent until trial or earlier order from making
any demand that HSBC convert the undertaking referred to in (b) into money.
[5] The respondent has intimated that it intends to make demand upon HSBC for the
amount of the undertaking referred to in para 4(a). It has made demand, and been
paid, the amount which HSBC promised to pay pursuant to the undertaking referred
to in para 4(b). The applicant insists that the respondent had no right to demand
payment from HSBC and seeks repayment of the money, which it has had to
reimburse HSBC, on terms that will protect the respondent’s rights until trial.
[6] The two undertakings give rise to different legal considerations and should be dealt
with separately. The respondent does not seriously dispute the applicant’s
-- 3 of 14 --
4
entitlement to interlocutory relief restraining it from making demand on HSBC for
payment of the amount the subject of the undertaking dated 30 March 2005.
[7] That undertaking, no. 11084204, provided that:
‘At the request of [the applicant] … and in consideration of [the
respondent] accepting this undertaking in respect of the contract for
supply of prestressed concrete railway sleepers … HSBC …
unconditionally undertakes to pay on demand any sum from time to
time demanded by [the respondent] to a maximum aggregate sum of
… AUD[$]394,525.52 … .
The undertaking is to continue until either:
(a) [the respondent] notifies [HSBC] that the undertaking is no
longer required …, or
(b) [the respondent] returns the undertaking to [HSBC], or
(c) [HSBC] pays the … sum to [the respondent] … .
If [HSBC] receives a notice from [the respondent] demanding
payment … then [HSBC] unconditionally agrees to pay the full
amount demanded … subject to the following terms:-
(a) [The respondent’s] notice … must be in writing and signed …;
and
(b) [HSBC] shall make payment without reference to [the
applicant] and notwithstanding any contrary notice or
representations by [the applicant] …’
[8] Clauses 23 and 24 of the contract for the supply of sleepers provided that:
‘23.1 Any debt due from [the applicant] to [the respondent] under
this Contract may be deducted by [the respondent] from:
(a) any monies which may become payable to [the
applicant] by [the respondent] under this Contract; and
(b) any retention monies or security held by [the
respondent].
…
24.1 As security for the due and proper performance of this
Contract by [the applicant], [the applicant], within … 28 …
days shall … provide [the respondent] with unconditional
banker’s undertakings … for the amount and for the period in
Schedule 1.
…
-- 4 of 14 --
5
24.3 [The respondent] may have recourse to security and may
convert into money security that does not consist of money
only after giving [the applicant] 5 Business Days notice in
writing of its intention to do so.’
[9] The applicant’s submission is that clauses 23 and 24 together specify the
respondent’s rights to have recourse to the security provided by the applicant and,
by implication, limit its right to recourse to those specified contractual
circumstances. In particular it is submitted that the respondent’s right to convert the
unconditional undertaking given by HSBC into cash is limited to cases where there
is a debt due from the applicant to the respondent. The applicant’s written
submissions identify a number of circumstances in which the operation of the
contract would give rise to a debt owed by the applicant to the respondent. In the
present case, however, the respondent does not assert that the applicant is indebted
to it, whether pursuant to particular provisions of the contract or otherwise. The
respondent wishes to make a demand upon HSBC for payment of the $394,525.52
as compensation for the loss it has incurred in rectifying the consequences of what it
claims are defective sleepers. It seeks to recover the money as a payment on
account of unliquidated damages for breach of contract.
[10] As I mentioned the applicant’s claim for an interlocutory injunction restraining the
respondent from calling up this unconditional undertaking is not seriously
contested. Counsel for the respondent accepts that there are cases which have
treated clauses such as 23 and 24 as containing implied negative stipulations, the
effect of which is that a contracting party in the respondent’s position may only
demand payment pursuant to a bank guarantee or undertaking where the
pre-conditions identified by the contract for the demand have been met. The courts
have restrained contracting parties from demanding payment pursuant to
unconditional bank undertakings where it appears that a demand would contravene
the implied negative stipulation in the contract. Examples are: Bachmann Pty Ltd v
BHP Power New Zealand Ltd [1999] 1 VR 420; Reed Construction Services Pty Ltd
v Kheng Seng (Australia) Pty Ltd (1999) 15 BCL 158; Rejan Constructions Pty Ltd
v Manningham Medical Centre Pty Ltd (2003) 19 BCL 451; Pearson Bridge (NSW)
Pty Ltd v State Rail Authority of NSW (1982) 1 AusConstrLR 81.
[11] There is a serious question to be tried as to whether the respondent has the right to
demand payment from HSBC when it does not assert the existence of a debt owed
to it by the applicant. The balance of convenience favours the grant of the
injunction. It will preserve the status quo. HSBC’s undertaking will remain in
force for the duration of the injunction. A delay in receiving payment until it
demonstrates its right to receive payment will not prejudice the respondent. Any
cost to which the delayed payment gives rise can be met by an award of interest. It
is accepted that the applicant is a company of substance. There is evidence that the
applicant’s business reputation would suffer should a call be made on a banker’s
undertaking it provided by way of security. This has been regarded as a significant
factor in favour of the injunction. Examples are Barclay Mowlem Construction Ltd
v Simon Engineering (Australia) Pty Ltd (1991) 23 NSWLR 451 at 461-462 and
Reed Construction Services at 167. I will therefore make the order sought by the
applicant with respect to the unconditional undertaking given by HSBC dated
30 March 2005.
-- 5 of 14 --
6
[12] The second undertaking raises different considerations.
[13] It was identical in format and terms to the earlier undertaking, but differed in its
recital of the consideration for HSBC’s promise to pay on demand. It was in these
terms:
‘At the request of [the applicant] … and in consideration of [the
respondent] … accepting this undertaking in respect of a claim by
[the respondent] that there are defects in works carried out by [the
applicant] under contract for supply of prestressed concrete railway
sleepers dated 4th August 2003 … HSBC … unconditionally
undertakes to pay on demand any sum from time to time demanded
by [the respondent] to a maximum aggregate sum of …
AUD[$]1,804,353.10 … .’
As I mentioned earlier this undertaking was dated 1 April 2005.
[14] On 19 April 2006 the respondent made demand upon HSBC pursuant to the
undertaking and received from it payment in full of the amount of $1,804,353.10.
The applicant commenced its proceedings on 24 April and on 26 April orders and
undertakings were given, the effect of which was, inter alia, to preserve the
proceeds paid pursuant to the second guarantee in a separate account until 4.00 pm
on 8 May 2006. The undertaking has been extended until judgment is given on this
application.
[15] In July 2004 the applicant made its last claim for a progress payment under the
contract, the amount being $1,804,353.10. The official designated by the contract
to certify the amount due in the claim did not do so and the respondent refused to
pay any part of it. The refusal was predicated upon the respondent’s belief that the
applicant was responsible for the problems with the railway gauge, the rectification
of which had involved it in cost. The applicant contemplated commencing
proceedings to enforce payment of its claim for a progress payment but instead
engaged in discussions with the respondent in an endeavour to resolve the dispute.
Conversations were between Mr Douglas, the applicant’s then general manager and
Mr Chudacek, the respondent’s then project director. Both men have filed affidavits
setting out their recollection of the conversations. There was little common ground.
They disagree fundamentally about the terms of their conversations which resulted
in the respondent paying the applicant’s disputed progress claim but the applicant
providing HSBC’s unconditional undertaking for the same amount.
[16] Mr Douglas’ account of the agreement is that he said to Mr Chudacek on
7 February 2005, ‘If we put up a bond, will you release the amount owing to us on
[our last] claim?’ Mr Chudacek said he would ‘think about that’. In a later
conversation on 4 March 2005 Mr Douglas said to Mr Chudacek, ‘Have you
accepted that we can put up a bond in lieu of the final payment?’ He received an
affirmative response. Mr Douglas told Mr Chudacek that he could not think of any
‘other approach to fix the problem associated with the tight gauge than the one [the
respondent] was adopting’. That apparently involved grinding the rails where they
were attached to the sleepers to increase the width of the gauge. Mr Douglas is
adamant that he did not say anything that might give rise to an inference that the
applicant was responsible for the cost of the rectification.
-- 6 of 14 --
7
[17] Mr Douglas asserts that the effect of their conversation was that the respondent
would not call upon any guarantee the applicant would provide unless the applicant
accepted that it was responsible for the problem with the gauge and its rectification,
or there was some determination, whether arbitral or curial, that the applicant had
performed the contract defectively and was liable for the cost of making the defects
good. He recalls saying words, in effect, ‘If it is determined that [the applicant] is at
fault you can have recourse to the bond’. The bond is, of course, a reference to the
undertaking to be given by HSBC.
[18] Mr Chudacek’s account of the conversations is quite different. His recollection is
that he told Mr Douglas that ‘it was open’ to the respondent to value the applicant’s
progress claim by deducting ‘an appropriate amount to take into account … that [the
applicant’s] sleepers were not supplied in accordance with the contract
requirements.’ Mr Douglas said that he had no criticism of the manner in which the
respondent was trying to resolve the problem and he ‘ultimately agreed’ that the
applicant would provide a bank guarantee in the amount of the final payment claim.
Mr Chudacek assured Mr Douglas that it was the respondent’s ‘obligation to find
the cheapest solution’. He said this ‘on the basis that costs of resolving the problem
were to [the applicant’s] account.’
[19] Mr Chudacek denies that Mr Douglas said anything to suggest that the guarantee
could be called upon only after a determination that the applicant was liable for the
cost of rectifying the too narrow gauge.
[20] There followed some correspondence concerning the terms in which the
undertaking would be furnished. An early draft provided by the applicant was
rejected and an undertaking in the terms I have quoted was eventually given and
accepted and signed by HSBC on 1 April 2005. During the course of these
discussions Messrs Douglas and Chudacek again spoke. Mr Chudacek claims he
said that the respondent ‘was only prepared to release the final payment on the basis
of having an unconditional bank undertaking that the costs of any … rectification
would be to [the applicant’s] account.’ Mr Douglas said that the applicant ‘would
comply with [its] contractual responsibility’, to which Mr Chudacek replied that the
undertaking ‘was to ensure that this happened.’ Mr Chudacek understood
Mr Douglas to say, or to mean, that the applicant would reimburse the respondent
the costs associated with grinding the rails. Mr Douglas said that he accepted the
applicant ‘had problems with the sleepers’ but ‘could not admit liability’.
[21] Mr Douglas adamantly denies making any such admission and he controverts
Mr Chudacek’s suggestion that the conversation proceeded on the basis of a mutual,
if implicit, acceptance that the applicant was liable for the cost of rectification.
[22] Following their conversations Mr Chudacek wrote to Mr Douglas on
31 March 2005:
‘We confirm that discussions and correspondence have recently
taken place regarding the provision of a bank guarantee to [the
respondent] … to release [the applicant’s] final payment. [The
respondent] wish[es] to advise that the release of this final payment
in no way alleviates [the applicant’s] obligations under the contract
to correct the non-conforming sleepers. The value of the bank
guarantee … $1,804,353.10 is in no way a limit … on [the
-- 7 of 14 --
8
applicant’s] obligations and liabilities … The agreement to release
the final payment is taking place as a sign of goodwill by [the
respondent], and on the understanding that [the applicant] will
reimburse [the respondent] all cost incurred as a result of the sleepers
being non-conforming.’
[23] Mr Douglas replied, about a month later, on 26 April 2005:
‘We strongly disagree that the terms of your letter … correctly set
out the position …
1. We agree that the payment of $1,804,353-10 does not
“alleviate” … [the applicant] from any obligation under the
Contract to correct any non-conforming sleepers.
2. Any limit of liability … will be determined in accordance with
the … Contract.
3. [The applicant] disagrees with the proposition that payment was
a sign of good faith on the part of [the respondent]. … [U]nder
the Contract … the sum of $1,804,353-10 was due and payable
to [the applicant] on 4 September 2004. Accordingly, the
provision of the bank guarantee … avoided the escalation of
[the respondent’s] failure to make payment …’
[24] Other details are in dispute but it is pointless to recount them. There is a clear
conflict of testimony and of fact as to the terms of the contract between the parties
which led to the provision of the second bank undertaking. The applicant’s case is
that it was a security provided in accordance with the terms of the written contract
which I have set out, although that contract does not seem to have been mentioned.
If this basis be made out the respondent could not make demand under the
undertaking unless the applicant was indebted to it, and on giving five days’ notice.
No notice at all was given and the respondent has not established that there is any
debt due to it from the applicant in respect of making good the railway gauge. The
respondent’s case is that the contract concerning the second guarantee was entirely
oral and arose from the disputed conversations. The respondent asserts that the
relevant term of the contract was that it could call upon the undertaking at any time
when it was satisfied that the applicant was responsible for the cost of rectification
by reason of supplying defective sleepers and that the costs had been ascertained.
The applicant contends that if the agreement was entirely oral the relevant term was
that the respondent could not call upon the undertaking unless the applicant’s
liability for the costs of grinding the rails had been established either by its
acceptance of the fact or by some objective determination.
[25] There is clearly a serious question to be tried. The respondent’s right to make
demand upon HSBC depends upon the terms of the agreement which are the subject
of hot dispute. If the applicant’s position should be vindicated after a trial the
respondent acted in breach of contract in demanding payment.
[26] Where does the balance of convenience lie?
-- 8 of 14 --
9
[27] The applicant relies upon a lack of prejudice to the respondent if the injunction is
granted, and damage to its reputation by reason of the bank undertaking being called
upon if the status quo ante is not restored by an injunction, as showing that the
balance of convenience favours the injunction.
[28] As to the first point the respondent’s financial statements for the year ended
31 December 2005 show it has a surplus of assets over liabilities of about
$196,000,000 including cash in excess of $113,000,000. Its net profit for the six
months ending 31 December 2005 was more than $33,000,000. The respondent’s
overall profitability and financial stability will not be affected by having to pay back
the $1,804,353.10. As well the respondent’s position is protected by the provision
of a replacement undertaking in identical terms to be provided by HSBC which will
enable the respondent to recover the money immediately once it has established its
right to payment. The applicant offers the usual undertakings as to damages and it
is accepted that the undertaking is valuable.
[29] By contrast the applicant claims it will suffer ‘irreparable damage’ to its reputation
if the respondent does not have to repay the money obtained from the undertaking.
[30] Mr Brogan, the applicant’s general manager, deposed:
‘Virtually all the construction contracts to which [the applicant] is a
party require [it] to lodge security in favour of the other contracting
party to secure [the applicant’s] performance … under the …
contract. This security is normally provided in the form of bank
guarantees …
…
A contractor’s “security” history (in the sense of whether any of its
bank guarantees … have ever been cashed) is an important part of
that contractor’s reputation, and … is taken into account by
prospective clients of the contractor when considering “Expressions
of Interest” or tenders …
…
[The applicant] built its business on meeting its contractual
obligations. This means completing its obligations without the need
for security ever being called upon.
… [The applicant] has never had any of its bank guarantees …
cashed.
I believe that if [the applicant’s] bank guarantee … dated 1 April
2005 … is not promptly restored … irreparable damage will be done
to [the applicant’s] reputation … as [its] clients may question [its]
ability to meet its contractual obligations. If … [the] bank guarantee
… is restored promptly, then this will minimise any damage to [the
applicant’s] reputation.’
-- 9 of 14 --
10
[31] Such evidence was regarded as important by Hunter J in Abigroup Contractors Pty
Ltd v Peninsula Balmain Pty Ltd (unreported, Supreme Court of New South Wales,
2 December 1999, No. 55034/99). His Honour said:
‘… the question of commercial reputation and the effect of a demand
on a large contractor, with a record to date which has been evidenced
in that context, should not be underestimated and there is a strong
legitimate entitlement on the part of such a contractor to protect that
reputation to the hilt.’
[32] Rolfe J took the same view, which was expressed at greater length, in Barclay
Mowlem. His Honour said (at 461-2):
‘… once the evidence [of damage to reputation] is admitted … it
demonstrates how inadequate a remedy in damages would be. The
matter, so far as the plaintiff is concerned, which is detrimentally
affected upon a performance bond being called-up, is the perceived
ability of the plaintiff to properly perform its obligations under a
contract. If the plaintiff’s ability in this regard is called in question,
even improperly, it is not difficult to infer that there will be damage
to its reputation in the industry in which it operates. Nor is it
difficult to infer that its competitors would be quick to utilise such
information in competing with the plaintiff. Finally, particularly as
matters presently stand in the commercial world, questions may be
raised as to the financial viability of the plaintiff … This would be
underlined if … there has not previously been any call upon a
performance bond. In other words people may be tempted to ask
whether the plaintiff’s business was “going downhill”.’
[33] In Reed Construction Services Austin J said (at 167):
‘As to the balance of convenience, I am content to adopt almost
everything that Rolfe J said in … Barclay Mowlem … the calling-up
of a performance … bond is a very serious matter for the builder,
having an effect on the builder’s reputation in the industry which
competitors could quickly take advantage of.’
[34] But for these expressions of opinion I would not myself have accorded particular
significance to the effect on business reputation of a contractor suffering a demand
on a bank undertaking. I would have thought there was much to be said for the
submission made by counsel for the respondent that news of the dispute between the
parties in this case, and of the respondent’s assertions that the applicant’s
performance of its contract has been defective, would be at least as damaging to the
applicant’s reputation as knowledge that one of its banker’s undertakings had been
called on. The dispute has been in existence for about two years and the
participants in the applicant’s line of business are few in number and, presumably,
well aware of each other’s affairs, to the extent that these things are talked about. I
might have thought it unlikely that serious businessmen would jump to the
speculations described by Rolfe J because a bank guarantee, provided to answer for
a number of contractual contingencies, had been called on. Nevertheless I do not
feel free to disregard the strong expressions of opinion from judges experienced in
this field. Accordingly I accept that the applicant may suffer damage to its
-- 10 of 14 --
11
reputation which could not be adequately recompensed by an award of damages
should it turn out that the respondent wrongly demanded payment.
[35] The respondent points to the unusual nature of the relief sought by the applicant and
further submits that, questions of reputation apart, damages will be an adequate
remedy should the applicant prove in due course that the respondent’s call upon the
undertaking was a breach of the contract between it and the applicant.
[36] The first point is that the order sought is of a mandatory interlocutory injunction
which courts are notoriously reluctant to pronounce. The respondent has called
upon the undertaking and been paid. The applicant seeks an order that the
respondent reimburse it the money it had to pay HSBC consequent upon HSBC’s
payment to the respondent to honour the undertaking. Because all that is involved
is a payment of money, damages are said to be adequate as a remedy.
[37] It is true that mandatory interlocutory injunctions are rare but I take the relevant
principles to be those which appear in the judgment of Hoffmann J in Films Rover
International Ltd v Cannon Film Sales Ltd [1987] 1 WLR 670 at 80. Having
referred to a decision of the Court of Appeal in which it had been said that the court
is far more reluctant to grant a mandatory interlocutory injunction than a prohibitory
one and that ‘in a normal case’ the court must feel a high degree of assurance that at
a trial it would appear that the injunction was rightly granted, his Lordship said:
‘But I think it is important … to distinguish between fundamental
principles and … “guidelines”, ie useful generalisations about the
way to deal with the normal run of cases falling within a particular
category. The principal dilemma about the grant of interlocutory
injunctions, whether prohibitory or mandatory, is that there is by
definition a risk that the court may make the “wrong” decision, in the
sense of granting an injunction to a party who fails to establish his
right at the trial … or … in failing to grant an injunction to a party
who succeeds … at trial. A fundamental principle is therefore that
the court should take whichever course appears to carry the lower
risk of injustice if it should turn out to have been “wrong” in the
sense I have described. The guidelines for the grant of both kinds of
interlocutory injunctions are derived from this principle.
…
… [T]he features which justify describing an injunction as
“mandatory” will usually also have the consequence of creating a
greater risk of injustice if it is granted rather than withheld … The
question of substance is whether the granting of the injunction would
carry that higher risk of injustice which is normally associated with
the grant of a mandatory injunction. … If it appears to the court
that, exceptionally, the case is one in which withholding a mandatory
interlocutory injunction would in fact carry a greater risk of injustice
than granting it even though the court does not feel a “high degree of
assurance” about the plaintiff’s chances of establishing his right,
there cannot be any rational basis for withholding the injunction.’
-- 11 of 14 --
12
[38] The authors of Equity Doctrines and Remedies, 3rd ed, Meagher, Gummow and
Lehane, thought that (at para 2178):
‘… a judge hearing an application for an interlocutory mandatory
injunction must apply exactly the same tests as he would in a case of
an application for an interlocutory prohibitory injunction, not some
different or more exacting test; … but in the application of the
normal test, often, but not always, the fact that the relief sought is
mandatory will tilt the balance of convenience in the defendant’s
favour.’
[39] Similar orders to those sought by the applicant have been made in the past. In
CS Phillips Pty Ltd v Baulderstone Hornibrook Pty Ltd (unreported, Supreme Court
of New South Wales, 26 October 1994, No. 55040/1994) Giles J ordered the
defendant to repay to the plaintiff an amount equal to the sum it had obtained by
calling upon a bank guarantee provided by the plaintiff in return for the plaintiff
providing a replacement guarantee. The order was made pending trial. Giles J said
(BC9403175 at 29):
‘If the orders sought … be made Baulderstone will not suffer the loss
of its security, but will still hold bank guarantees … and the orders
will effectively restore the status quo … The balance of convenience
in these respects favours the making of the orders, and in the
circumstances the fact that the interlocutory orders sought are
mandatory orders is not of great consequence. Although
Baulderstone would be required to act to its detriment, it would still
have its security and if its position was ultimately upheld would only
be delayed in calling for payment.’
[40] A similar order was made by Byrne J in Walter Construction Group Ltd v
Secretary, Department of Infrastructure (unreported Supreme Court of Victoria,
6 June 2000, No. 4637/00). His Honour said (at [14] to [15]):
‘The balance of convenience is indisputably in favour of [the
plaintiff]. Its construction manager … deposed as to the adverse
commercial consequences of the calling up of the bank undertakings.
Counsel for [the defendant] accepted that, if the undertakings were
reinstated, his client’s position would not be jeopardised. It will
have substitute undertakings … In the event that it should hereafter
appear that [the defendant] is entitled to call upon these
undertakings, any other losses can be adequately protected by an
undertaking as to damages.
Any concerns which I might have had as to the appropriateness of
mandatory injunctions of the kind here sought were dispelled upon
my reading of the judgments in New South Wales where this course
had been adopted.’
[41] In my opinion the balance of convenience favours the injunction. The risk of
injustice is greater if the injunction is withheld than if it were granted. If the order
is made the parties will be restored to their former position in which they disputed
whether the respondent could demand payment on the undertaking without first
-- 12 of 14 --
13
establishing that the applicant’s performance of its contract had been defective.
Damage to the applicant’s reputation will be minimised. The respondent will be
protected by the issue of a replacement undertaking which it can call upon as soon
as it establishes that the applicant’s performance of the contract was defective or
that, regardless of that determination, the oral contract made between
Messrs Douglas and Chudacek accords with the latter’s evidence. The act required
to comply with the injunction can be quickly and readily performed and will not
prejudice the respondent for the reasons earlier identified. The effect of the order
will be to preserve the status quo ante.
[42] Another factor of significance is that the determination of the question whether the
respondent was entitled to demand payment from HSBC can be resolved very
quickly so that the duration of the injunction should be short. The answer depends
upon the terms of the contract made in March 2005 between Messrs Douglas and
Chudacek. That involves the testimony of two witnesses and the perusal of a small
number of documents. The trial would last half a day and could be got ready in a
week or two. It should be possible to obtain a trial very quickly. The issue for
adjudication at trial would be whether the parties agreed that the respondent could
call upon the guarantee at any time, or only after the applicant conceded it was
liable for the supply of defective sleepers or that fact had been objectively
determined. A third possibility is that the right to call upon the undertaking was
governed by clauses 23 and 24 of the written contract. In that case the respondent
could not have made demand until the provisions of the contract it operated so to
create a debt from the applicant to the respondent. That would, practically
speaking, be equivalent to a determination that the applicant had performed its
contract defectively and supplied sleepers that did not comply with the contract.
[43] Should the trial result in a finding that the terms of the contract accords with
Mr Chudacek’s testimony the respondent can make an immediate call upon the
replacement guarantee and recover the money. Any damages it has suffered by
being deprived of the money for a month or two can be paid pursuant to the
undertaking as to damages. Should the trial go the other way the respondent will
have to commence proceedings to vindicate its claim that the applicant’s sleepers
were defective and that the respondent has suffered loss as a consequence. Until it
can prove those facts it was not and will not have been entitled to make a demand
on HSBC’s undertaking. The undertaking will stand pending the vindication of the
respondent’s claim.
[44] The respondent itself applied for an order pursuant to s 5(2)(b)(iii) of the
Jurisdiction of Courts (Cross Vesting) Act 1987 (Qld) for an order that the
originating application be transferred to the Supreme Court of Victoria. This
application should be adjourned until it is known what further proceedings will be
instituted between the parties. It is clear that the contract for the supply of sleepers
has a close connection with Victoria and any action brought in respect of the
contract should be heard in the courts of Victoria. It is equally clear that any action
which hangs off such an action should be heard in Victoria. It is not so clear that an
action of the kind I have just described, to determine what were the terms of the
contract with respect to the provision of the unconditional undertaking, should itself
be heard in Victoria. It may be that it could be heard with equal convenience and
greater speed in Queensland. These are matters for another day.
-- 13 of 14 --
14
[45] I order that, upon the applicant giving the usual undertaking as to damages:
1. the respondent be restrained by itself, its officers, servants, agents or assigns
until trial or earlier order from making any demand that HSBC convert
unconditional undertaking no. 11084204 dated 30 March 2005 into money;
2. the respondent pay to the applicant the sum of $1,804,353.10 by way of bank
cheque in exchange for the applicant delivering to the respondent an
unconditional undertaking by HSBC Bank Australia Ltd promising to pay the
respondent on demand the sum of $1,804,353.10;
3. the respondent by itself, its officers, servants, agents or assigns until trial or
earlier order be restrained from making any demand on HSBC to convert the
said undertaking into money;
4. the respondent’s cross-application to have the originating application
transferred to the Supreme Court of Victoria is adjourned; and
5. the costs of both applications be reserved.
-- 14 of 14 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2006/103