Begley v Fisigi Pty Ltd [2006] QDC 416
DISTRICT COURT OF QUEENSLAND
CITATION: Begley v Fisigi Pty Ltd [2006] QDC 416
PARTIES: TRACEY ELIZABETH BEGLEY
Plaintiff
V
FISIGI PTY LTD
Defendant
FILE NO/S: D1508/06
DIVISION:
PROCEEDING: Application
ORIGINATING
COURT: District Court, Brisbane
DELIVERED ON: 21 December 2006
DELIVERED AT: Brisbane
HEARING DATE: 11 December 2006
JUDGE: McGill DCJ
ORDER: Declarations as per paragraphs 1 and 2 of the application;
judgment that the defendant pay the plaintiff $27,000,
including $500 by way of interest; defendant’s application
and counterclaim dismissed with costs; order that the
defendant pay the plaintiff’s costs of the action including
the applications to be assessed.
CATCHWORDS: VENDOR AND PURCHASER – Termination of contract –
sale of proposed allotment – statutory right to avoid –
whether time for exercise expired before notice given.
Land Sales Act 1984 s 9(5).
COUNSEL: D. J. Thomae of the plaintiff
D. A. Quayle for the defendant
SOLICITORS: Bain Gasteen Lawyers for the plaintiff
Redchip Lawyers for the defendant
[1] The plaintiff entered into a contract for the sale of land on 12 December 2004.1 It is
not disputed that the contract is one to which the Land Sales Act 1984 (“the Act”)
applied. Section 9 of that Act required the defendant, the vendor, to give the
1 Affidavit of Ford filed 17 November 2006 Exhibit MRF1; this affidavit contains all the relevant
factual material.
-- 1 of 11 --
2
plaintiff before she entered into the contract (relevantly) a disclosure plan and a
disclosure statement for what was then a proposed allotment. A disclosure plan and
a disclosure statement were given, but it was common ground they did not comply
with all the relevant requirements identified in s 9, so that the plaintiff had, pursuant
to s 9(5) of the Act, a right to avoid the contract “by written notice given to the
vendor or vendor’s agent before the vendor gives the purchaser the registrable
instrument of transfer for the allotment.” Written notice was given on 12 October
2005. The plaintiff alleges that that notice was effective to terminate the contract;
the defendant disputes that proposition. The plaintiff filed an application for
summary judgment, and on the last business day before that application came on to
be heard, the defendant filed a cross-application for summary judgment.
[2] On the pleadings and as the matter was argued before me, there were only two
issues. It was common ground that the date fixed for settlement under the contract
was 13 October 2005. Under cover of a letter dated 5 October 2005, the then
solicitors for the defendant forwarded a transfer in form 1 executed by the
defendant. The letter said inter alia:
“We return the enclosed documents to you on your undertaking to hold
the stamped transfer on our behalf pending settlement and to use the
transfer for stamping purposes only.”
[3] That transfer was signed by the vendor but was not dated, as required by the form
under the Land Title Act. The issue was whether, as a result of that form having
been then sent to the plaintiff’s solicitors, the defendant had “given” the plaintiff the
registrable instrument of transfer for the allotment for the purposes of s 9(5). It was
submitted on behalf of the plaintiff that that had not occurred, for two reasons:
(a) because the document was forwarded only for the limited purpose specified
in the letter enclosing it, until settlement it was not a registrable instrument
of transfer which had been given to the plaintiff;
(b) because the document was undated, it was not in any event a registrable
instrument of transfer.
[4] The term “registrable instrument of transfer” is defined in s 6 of the Act.2
Relevantly, the term means:
“In respect of land that was a proposed allotment of freehold land at the
time when a person entered upon the purchase thereof – a memorandum
of transfer of the land in favour of that purchaser capable of immediate
registration (subject to its being properly stamped under the Duties Act
2001) in the land registry.”
[5] The plaintiff’s argument in relation to the first point was essentially that when the
letter was sent enclosing the transfer, the transfer was not capable of immediate
registration in the land registry because it was expressly to be held subject to
settlement. It was a transfer and may well have been capable of registration in the
Titles Office (subject to being first stamped), but it was then forwarded expressly on
the basis that it would not be registered unless and until settlement occurred, and
therefore it was not capable of immediate registration. In effect, the plaintiff’s
2 The relevant version of the Act appears to be Reprint 4G.
-- 2 of 11 --
3
argument is that what is contemplated by s 9(5) is that the right to avoid the contract
will continue until completion.
[6] The defendant, however, submitted that that was not in terms required by the
statute, and so long as the document had been given, on any basis and for any
purpose, to the purchaser, then the cut off point for avoidance under s 9(5) had been
reached. Both counsel said that they were unable to identify any earlier decisions
under this legislation in which this particular point had been considered, and I have
not myself been able to find any such decision. Nevertheless, it seems to me that a
consideration of the history of the legislation indicates that the submissions for the
plaintiff are to be preferred.
History of the legislation – the original Act
[7] The Land Sales Act 1994 is a much-amended Act. Indeed, even before it
commenced (on 1 July 1985), it had been amended by the first of two amendment
Acts passed during 1985. It replaced restrictions formerly appearing in the
Auctioneers and Agents Act 1971 on the sale of land which, in the case of freehold
land, was subject to an unregistered plan of subdivision, or a proposed plan of
subdivision. The Act prohibited selling such land in the case of freehold land unless
the subdivision plan had been approved by the appropriate local authority before the
purchaser entered upon the purchase3: s 8. It also required that, before the
purchaser entered upon the purchase of the relevant land, the purchaser be provided
with a copy of the relevant subdivisional plan approved by the local authority
clearly identifying the land being purchased: s 9.
[8] Section 10 then dealt with the situation where the copy plan subsequently became
inaccurate; the vendor was required to give to the purchaser a notice in writing “that
rectifies the inaccuracy”, which duty continued until a certificate of title in respect
of freehold land that related to the land in question only had been issued by the
Registrar of Titles: s 10. There was also a provision governing the holding of
money paid under the contract. Section 13 provided that where there had not been
compliance with s 9(1), or where the copy plan was found to have been or to have
become inaccurate, a purchaser might (subject to certain restrictions which have
since disappeared and need not be considered further) avoid the contract by notice
in writing given to the vendor or the vendor’s agent.
[9] Subsection(2) then provided that notice of avoidance, if it was to be effectual, had to
be given “in the case of a sale or purchase of relevant freehold land, before a
certificate of title that relates to that land only has been issued by the Registrar of
Titles… .” There was an alternative provision in circumstances where the purchaser
was relying on some inaccuracy in the copy plan, or responding to a notice of
rectification under s 10, where potentially a different period could operate. In
addition, by s 15, the purchaser had a right to avoid the contract if no certificate of
title to the land had issued and a period of six months had elapsed from the day on
which it was made, unless the purchaser had already disposed of his interest in the
land. In the circumstances, it is not surprising that there was nothing in the debates
when the 1984 Act was being discussed which throws any light on the present issue.
3 This term effectively means signs the contract: s 6(2). It was later extended to becomes bound to
purchase: s 6A, and definition of “purchase” and “sell” in s 6; Wan v NPD Property Development
Pty Ltd [2005] 1 Qd R 340.
-- 3 of 11 --
4
[10] Accordingly, as the statute then stood, if there was a failure to do what was required
by s 9(1) of the Act, the purchaser had a right to avoid the contract by notice in
writing (subject to certain conditions) but only before a certificate of title which
related to that land only had issued. The weakness of this as an exercise in
consumer protection was readily apparent, and evidently it received a certain
amount of criticism. For example, Professor Duncan was critical of the 1984 Act in
its original form in an article published in the Queensland Law Society Journal in
August 1984.4 At p 151, he said that the right to avoid should not come to an end
when the certificate of title issued, pointing out that there was nothing to prevent a
vendor from holding off giving a notice under s 10 until the certificate of title
issued. He continued: “Clearly a purchaser should have the right to avoid up until
the date for completion.” He also said at p 152 that a right to avoid under ss 14 and
15 should be extended to the date of completion.
– The first amendment
[11] In March 1985, legislation to amend the Act was introduced. The then
Attorney-General in the second reading speech5 said inter alia:
“It was considered that, by limiting the time for the avoidance of the
contract of [sic] the issue of the plan … the ability of the purchaser to
avoid the contract may be limited unfairly as he may not become aware
of an alteration to the plan until that date. To correct this position, the
bill extends the date whereby [sic] a purchaser may avoid the contract to
which a notice of rectification relating to either before the expiration of
30 days after the receipt by him of the notice or before the delivery of a
registrable instrument. My concern has been to ensure fair dealing
between the parties to the contract and a viable option to the purchaser.”
[12] In the course of the debate on p 4811, a representative of the opposition indicated
support for the bill and added “under the original Act, it could fairly be said that
unscrupulous operators could have taken people to the cleaners.”
[13] The Amendment Act did not alter s 9. Section 10 was amended so that the duty
imposed by it continued until “a registrable instrument of transfer that relates to the
land in question has been delivered by the vendor or the vendor’s agent … to the
purchaser or his agent.” Section 13 was amended so that the notice of avoidance, if
it was to be given, was to be given by that same time. The term “registrable
instrument of transfer” was defined in s 6 as inter alia:
“In respect of land that was relevant freehold land at the time when a
person entered upon the purchase thereof, a memorandum of transfer of
the land in favour of that purchase capable of being registered in the
office of the Registrar of Titles.”
[14] Reading that definition into the form of words inserted in ss 10 and 13, the cut-off
date became the time when “a memorandum of transfer of the land in favour of the
purchaser capable of being registered in the office of the Registrar of Titles was
delivered by the vendor or the vendor’s agent to the purchaser or his agent.” That
is, it seems to me, essentially a description of part of what happens on completion or
4 Vol 14 p 149.
5 Queensland Hansard March 1985 Vol 298 p 4471.
-- 4 of 11 --
5
settlement of a contract. Under the then current REIQ contract in Queensland for
the sale of land, on completion “the balance of the purchase price shall be paid … in
exchange for possession … together with a duly executed transfer in favour of the
purchaser capable of immediate registration (after stamping) in the appropriate
office … .”6 It would appear that in this respect the legislation was taking up the
suggestion of Professor Duncan in the Law Society journal article.
Professor Duncan certainly thought so.7
– Analysis of the Act after this amendment
[15] Apart from the similarities in the wording used in the amending Act and part of
what occurs on completion, there is also the consideration that the legislature
obviously intended to change the balance between the vendor and purchaser in the
operation of these provisions, in a way which was more favourable to the purchaser,
and in a way which was intended to make it more difficult for a vendor artificially
to manipulate the process so as to deprive the purchaser of the protection of the
legislation, or so as to reduce the value of the protection to the purchaser.
[16] In such circumstances, the date for completion is a natural date for the legislature to
choose when seeking to fix a point at which the right to avoid the contract comes to
an end. A right in equity to have a contract set aside on the ground of innocent
misrepresentation will be lost once the contract has been completed.8 Until the
contract is completed, there is nothing to be undone if the contract is avoided except
to provide for the recovery of any deposit paid, and the statute had other provisions
designed to ensure that the deposit would be available to be recovered by the
purchaser if necessary. One would, however, not expect that a right of this nature
would be available after completion. The real question is whether the legislative
intent was consistent with the right coming to an end if the transfer were delivered
to the purchaser or the purchaser’s agent prior to completion.
[17] Ordinarily, a transfer is prepared by the purchaser’s solicitor and forwarded to the
vendor’s solicitor for execution,9 and then lent back to the purchaser’s solicitor
prior to completion for stamping. This is essentially a matter of convenience; the
vendor can prepare the transfer and is entitled to tender an unstamped transfer,
because of the terms of the contract as to what is to be handed over on completion.10
Allowing the purchaser to stamp the transfer prior to completion makes it possible
6 REIQ Contract 1982 Clause 2; a copy appears in Duncan and Weld (The Standard Land Contract in
Queensland) (3rd edition 1990) p LXXIII.
7 See his article “Queensland consumer protection legislation and land dealings – reality or mere
illusion?” in 9 Queensland Lawyer 116, at pp 121-2, where he stated that the right to give a notice of
avoidance continues up until settlement. Also, W D Duncan “Real Estate Agency Law in
Queensland” (3rd edition 2001) p 95, speaking about the time limit in s 10A, which is now expressed
in the same terms.
8 Svanosio v McNamara (1956) 96 CLR 186. Strictly speaking, it is lost on conveyance, that is the
transfer of the legal title. Under the old system, conveyance occurred at settlement by the delivery of
the deed of conveyance, but under the current system the legal title is not transferred until the
transfer is registered in the Titles office. Nevertheless, there is a tendency to treat completion of the
contract as being equivalent to a conveyance even under the Torrens system, and it is unlikely that
the legislature would have intended that the right to avoid under the Act could have been exercised
between completion and registration of the transfer.
9 This was required in this case by clause 5.2(1) of the standard terms of contract: Exhibit MRF1 p 6.
10 TLI Management Pty Ltd v Nufate Pty Ltd [1988] 1 Qd R 717 at 724. By clause 5.2(2) the defendant
could have been required to produce the transfer to the Office of State Revenue for stamping before
settlement.
-- 5 of 11 --
6
for the purchaser to lodge the transfer of the registration more quickly after
completion.
[18] If the interpretation contended for on behalf of the defendant is correct, after the
1985 amendment it would still have been possible as soon as a separate certificate
of title for the land had issued for the vendor’s solicitor to send the purchaser’s
solicitor a transfer, subject to the condition that it would not be registered prior to
completion, and in that way render the amendment made in 1985 virtually of no
effect. The sort of vendor against whom a consumer would most particularly need
legislative protection is perhaps the sort of vendor who would be most likely to take
such a step. I think therefore that it is unlikely that the legislature in 1985 when
extending the time available within which the purchaser could avoid a contract
under s 13, intended to extend the time to an event, the occurrence of which would
be entirely in the hands of the vendor, so that a vendor if he chose could by
unilateral action cut short the purchaser’s statutory right to rescind.
[19] The legislation is to be given a purposive construction.11 It seems to me that the
legislative purpose in 1985 was to extend the period within which there was a right
to avoid the contract up to completion of the contract, and in my opinion that is the
effect that should be given to the words then used.
– Further amendments
[20] The words used at the time have since been amended to some extent; indeed, there
have been various changes to the legislation. Later in 1985 came the second
amending Act of that year12, by which the definition of “registrable instrument of
transfer” was amended by substituting for the words “being registered” the words
“immediate registration (subject to its being duly stamped as required by any
applicable law relating to stamp duty)”, thus bringing it closer to the wording of the
REIQ contract.13 Section 13 was amended by redrafting subsection (1) to make its
operation more clear, and by redrafting part of subsection (2) in the same way,
though not subsection (2)(a).
[21] In addition, s 10 was redrafted to provide that if the plan referred to in s 9 were
varied at any time, there was a requirement after registration of the relevant plan to
give to the purchaser or his agent a copy of the plan in the form in which it was
registered. The obligation arose whether s 9 had been complied with or not.
Subsection (4) then provided:
“Where a vendor or a vendor’s agent is required under subsection (1) to
give to the purchaser or his agent a copy plan of survey, then—
(a) the vendor or his agent shall not deliver to the purchaser or his
agent a registrable instrument of transfer in respect of relevant
land the subject of the purchase in question; and
11 Acts Interpretation Act 1954 s 14A.
12 Land Sales Act Amendment Act (No 2) 1985, No 105.
13 This amendment, made in committee, was made expressly “to ensure that the wording of the clause
strictly mirrors the relevant obligations imposed by the REIQ standard form contract. It ensures that
transfer documents need not be stamped prior to settlement … .” Hansard, vol 301 p 3308. This
shows a legislature understanding that the registrable instrument of transfer was what was delivered
at settlement.
-- 6 of 11 --
7
(b) the purchaser shall not be required to pay the outstanding
purchase moneys,
until the expiration of a period of 30 days after the receipt by the
purchaser or his agent of a copy plan of survey in accordance with
subdivision (1) or until the time stipulated by the instrument in respect of
the sale and purchase for the payment of those purchase moneys
(whichever period is the later to expire) unless it is otherwise agreed in
writing between the vendor or his agent and the purchaser or his agent
after the receipt by the purchaser or his agent of a copy plan in
accordance with subsection (1).”
[22] In other words, if the plan of survey were varied after the plan provided under s 9
had been provided, a copy of the registered plan of survey had to be provided, and
completion was not to occur for at least 30 days, unless the purchaser agreed in
writing after receiving the registered plan of subdivision. It seems to me that what
was described in paragraphs (a) and (b) in subsection (4) was essentially
completion.14 It seems to me that the wording in subsection (4) really only makes
sense on the basis that the legislature was assuming that the delivery referred to in
paragraph (a) was delivery on completion.
[23] This is consistent with the second reading speech for the bill for this amending act
of the Attorney who said, apparently of this amendment, “It is proposed that the
purchaser will now have at least 30 days after receipt of the registered plan to
consider his position. This will enable a purchaser to seek legal advice, if
necessary, and to complete the contract with full knowledge of his position.”15 He
had earlier said that one of the purposes of the bill was “to ensure that the legislation
remains consistent with long-established and accepted commercial and
conveyancing practice.”16 As well, s 11 was amended in a way which indicated that
the legislature assumed that the registrable instrument of transfer would be handed
over, ie delivered, on completion.17
– the 1997 amendments
[24] There were amendments to the definition of “registrable instrument of transfer” in
1992, but they were formal only. The next significant amendments were those of
1997 by the Land of Sales and Land of Title Amendment Act No 40 of 1997. This
Act introduced the statement of the objects of the Act in s 2. There was no
statement of the objects of the legislation in the Acts prior to this time, and therefore
it could not have governed the interpretation of any part of the Act at that time.
[25] There was an explanatory note to the Bill which became the 1997 Amendment Act.18
That indicated that these amendments were a response to a lobbying campaign by
the real estate and development industries who were keen to remove or lessen the
restrictions on the selling of allotments prior to the approval of the plan of
subdivision provided that certainty of identification of the land purchased was
14 The other two usual elements of completion are the transfer of possession and the delivery of the
certificate of title, but the latter did not necessarily occur (Clause 8) and the former was not
necessarily vacant possession, and see clause 3 – possession before completion.
15 Hansard vol 301 p 2921.
16 Ibid p 2920.
17 See ibid p 2920. This particular wording has survived intact into the current form of the Act.
18 1999 Explanatory Notes Vol 2 p 1337.
-- 7 of 11 --
8
assured. The proposed amendments were not intended to infringe the original
policy objectives of minimising as far as possible the deliberate or inadvertent
misdescription of land, and providing readily available remedies to consumers who
were nevertheless adversely affected. Now they were to be achieved inter alia by
“provisions, including the supply of a disclosure statement and disclosure plan to a
purchaser, to ensure that a proposed allotment, in relation to which a registrable
instrument of title is ultimately delivered to the purchaser, is substantially identical
to that which was originally purchased by him or her; … if the allotment is not
substantially identical but there is a significant variation between the disclosure plan
and either the plan showing the constructed works or the plan proposed to be
registered, the purchaser have an automatic right to avoid the contract of sale.” In
addition, the period of nine months19 between the date of contract and the date of
“delivery of a registrable instrument of transfer for the proposed allotment” was to
be extended to 18 months, but the ministerial discretion to extend that period was to
be removed.
[26] Accordingly, s 9(1) was replaced with a provision which permitted, as an alternative
to providing a copy of a sealed plan, a disclosure statement and disclosure plan; in
other respects the section was essentially put into its current form,20 setting out the
detailed requirements of the disclosure statement and the disclosure plan. The
explanatory note went on to say (p 1343) that the amendment to the section “also
provides that a purchaser may avoid the contract prior to being given the registrable
instrument of transfer if the vendor contravenes this section … .” This meant that
the provision in the former s 13 could be repealed because the relevant part had
been placed in s 9. Section 10A was to be inserted to give effect to the 18-month
time limit.
[27] Section 10A as originally formulated was not well drafted, a fact recognised by
amendments made in 1999, that put the section into essentially its current form;
there was an 18 month limit for the vendor to give the purchaser the registrable
instrument of transfer, and in addition, in those cases where the approved plan of
subdivision was not provided prior to the purchaser entering into the contract, the
vendor was required to give the purchaser certain other documents, again not later
than 18 months after the purchaser entered upon the purchase.
[28] There is nothing to suggest that the change in 1997 from “delivered” to “gives” in
relation to what must be done with the registrable instrument of transfer was
intended to produce any change in the substantive meaning of the section, or in the
operation of the Act. I suspect that the change was simply one of drafting style.21
Although the former word more readily identifies the formality associated with the
completion of a contract, I do not think that the mere change in the wording was
intended to change the essential meaning of the term, so that the provision can now
refer to something other than the handing over on completion.
[29] The current wording of s 10 provides in subsection (3) that:
19 The original six months for a certificate of title was increased to nine months by the first 1985
amendment Act, by which the cut off date was changed to apply to the delivery of the registrable
instrument of transfer, and the second 1985 amendment Act introduced a power in the Minister to
extend the period. The only sensible interpretation of this provision is that it put a time limit on
completion.
20 Subsequent amendments to s 9 have been inconsequential at least for present purposes.
21 Note the effect of Acts Interpretation Act 1954 s 14C.
-- 8 of 11 --
9
“If the vendor gives the purchaser a significant variation notice … (b) the
vendor must not, until the end of the prescribed period –
(i) ask the purchaser to pay the balance of the purchase price; or
(ii) give the purchaser a registrable instrument of transfer for the
allotment.”
[30] The “prescribed period” is defined in subsection (5) in a way which picks up the
concepts originally included in the latter part of subsection (4). Again, the change
of wording does not suggest any particular intention to change the meaning, and
none is found in the explanatory notes; it may be put down to a change in drafting
style. The most significant change perhaps is that the conjunction “and” has been
replaced by the conjunction “or”, although the overall expression does not as clearly
identify the process of completion as did the original expression. In the light of the
history of the legislation, however, I think it likely that what is being spoken of in
s 10(3)(b) is still completion. The obligation to pay the purchase price and to
transfer title on completion are concurrent, so that prior to completion the vendor is
not entitled to ask the purchaser to pay the balance of the purchase price anyway.22
Accordingly, the provision prohibits the vendor from doing either of the things
which a vendor would necessarily do on completion. This provision in my opinion
supports an interpretation that the expression “give the purchaser a registrable
instrument of transfer” is a reference to the “giving” that occurs on completion.
Analysis
[31] Counsel for the defendant relied on the interpretation of the expression “capable of
immediate registration … in the land registry” in Cawood v Infraworth Pty Ltd
[1990] 2 Qd R 114, where it was held that the word “immediate” had no temporal
connotation, but required a transfer directly from the registered proprietor to the
purchaser. It was submitted that the absence of temporal connotation meant that a
transfer could be capable of immediate registration, and hence a registrable
instrument of transfer for the purposes of the Act, even though in terms of the
contract it was not yet open for the purchaser to lodge the transfer for registration.
In my opinion, the significance of the expression in the definition in s 6 is that it
corresponds with the expression used in the then standard contract in relation to
completion, and provides an indication that what was being spoken about was the
handing over on completion.
[32] I accept that in the definition in s 6 the word “immediate” has the interpretation
given to it by the Full Court in Cawood. But for present purposes the point is that
prior to completion the transfer was not capable of registration, because the
purchaser was not entitled to lodge it for registration in terms of the contractual
arrangements between the parties. If the purchaser had, immediately after the
transfer was forwarded, stamped the transfer and then lodged it for registration prior
to completion, that would have been not only in breach of the contract between the
parties and in breach of the undertaking on the basis of which it was provided by the
vendor’s solicitors, but probably also a fraud on the vendor. I do not think that the
concept included in the definition of “registrable instrument of transfer” was
intended to refer merely to a document which was in the correct form. I expect the
legislature would have intended that the reference to “capable of immediate
registration” was intended to be a reference to something which could be done
22 Ireland v Leigh [1982] Qd R 145 at 151.
-- 9 of 11 --
10
lawfully. That was not the case for registration of this transfer prior to the date on
which the notice of avoidance was given.
[33] The original legislation was not solely an exercise in consumer protection, because
to some extent it involved a relaxation of a prohibition which previously existed,
and in that sense it was to facilitate property development in Queensland. The 1997
legislation was to the same effect, in the sense that it involved a further relaxation,
on terms, and in that way facilitated property development, while at the same time
retaining the consumer protection element. The first amendment in 1985, however,
was clearly legislation intending to change the Act in a way which made it more
beneficial for consumers. The consumer protection element of the Act has been
recognised by the courts.23 The Act does this by making various requirements on
sales of land which fall within its scope, and by providing “readily available
remedies” if, relevantly, those requirements were not satisfied. This may well mean
that a contract could fall over for what on its face is a relatively minor technicality.
But consumer protection legislation should be strictly applied, and it is important
that those who are selling land subject to this Act do whatever is necessary in order
properly to comply with it.24
[34] In my opinion, on the true construction of the statute, and on the uncontested facts,
the time in which it was open to the plaintiff to avoid the contract because of the
defendant’s admitted breach of s 9 of the Act had not expired at a time when that
right was exercised. Accordingly, the contract is at an end, and the plaintiff is
entitled to recover the deposit.
An alternative reason
[35] It occurs to me that there is a further reason why this must be correct in the present
case. The letter of 5 October 2005 provided the transfer to the purchaser’s solicitor
on the basis of the solicitor’s undertaking to hold the stamped transfer “on our
behalf” pending settlement, that is to say, on behalf of the vendor’s solicitor.
Relevantly, therefore, the purchaser’s solicitor, when holding the transfer, was not
doing so as agent for the purchaser, but was doing so as agent for the vendor, or the
vendor’s solicitor. Accordingly, the defendant had not given the plaintiff the
registrable instrument of transfer for the allotment; all that had happened is that one
agent of the defendant had passed the document over to someone else to hold as
another agent for the defendant (or for the first agent, as agent for the defendant).
That in my opinion did not amount to giving to the purchaser for the purposes of
s 9(5). For that reason also the time limit in that subsection had not expired at the
time when the notice to avoid the contract was given.
Conclusion
[36] In these circumstances, it is unnecessary to consider whether the document was not
a registrable instrument of transfer because, although executed on behalf of the
defendant, it was not dated. In relation to this, the defendant sought to rely on an
affidavit giving some evidence as to practice in the titles office, which was served
only on the last business day before the date of hearing of the application. The
23 Francis v NPD Property Development Pty Ltd [2005] 1 Qd R 240 at 252; Wan v NPD Property
Development Pty Ltd [2005] 1 Qd R 340 at 346.
24 Note the comments, in the context of other consumer protection legislation, of the Chief Justice in
MNM Developments Pty Ltd v Gerrard [2005] 2 Qd R 515 at 519, 520.
-- 10 of 11 --
11
timing of the defendant’s material was not in accordance with the rules; although
the plaintiff’s solicitors sent the application for summary judgment and the
affidavits in support under cover of a letter sent by facsimile to the defendant’s
solicitors on 17 November 2006, well outside the eight business days required for
service of such an application under UCPR r 296(1), the defendant did not file this
material in response within the time limited by r 296(2). In addition, on the last
business day before the date of hearing, the defendant filed a cross-application for
summary judgment.
[37] On the date of the hearing, counsel for the plaintiff objected to having to respond to
the affidavit filed on behalf of the defendant in relation to conveyancing practice, or
perhaps titles office practice, in the time available. In the event it has been possible
to determine the matter without regard to that consideration. If, however, I had not
been able to do so, I would not have decided the application without giving the
plaintiff a further opportunity to consider her position, and to decide whether to put
on further material. I would also not have decided the defendant’s application
without giving the plaintiff a proper opportunity to respond. It is not necessarily the
case that, if the plaintiff’s application failed, the defendant’s application would have
to succeed.
[38] Although only one point was argued in the matter before me, because it was
conceded that if the defendant lost on that point the plaintiff was entitled to succeed
in the action, it does not necessarily follow, and it was not expressly conceded, that
if the plaintiff lost on that point the defendant was entitled to succeed in the action.
In the event, however, the defendant’s application should be dismissed, as it has
become superfluous. There is a counterclaim, but it was conceded that if the
plaintiff’s claim succeeded, the counterclaim would fail, and there should be
judgment for the plaintiff on the counterclaim as well.
[39] In the present case, the matter before me turns essentially on a question of statutory
interpretation. On the view that I take of the interpretation of the statute, there is no
factual issue remaining in dispute, and the plaintiff would be bound to succeed at
trial. In these circumstances, it is appropriate to give summary judgment for the
plaintiff. I will therefore make the declarations sought in paragraphs 1 and 2 of the
application, and give judgment that the defendant pay the plaintiff $26,500 being
the amount of the deposit paid together with interest from the date on which
payment ought to have been made, 13 October 2006, to the date of judgment.
[40] The plaintiff sought in the application interest at 10 per cent per annum under the
Supreme Court Act. That is a higher rate than I would ordinarily allow under that
Act, although I note that under the contract there is provision for a default interest
rate of 10 per cent per annum; in terms of the contract, however, that is to apply
only to money payable by the plaintiff to the defendant under the contract which is
not paid at the appropriate time. Nevertheless, as the defendant regards that as a fair
figure for a default interest rate, I intend to adopt that as the interest rate payable
under the Supreme Court Act. I will therefore allow interest at the rate of
10 per cent per annum, which I calculate at $500. There will therefore be judgment
that the defendant pay the plaintiff $27,000, including $500 by way of interest. I
will also order the defendant to pay the plaintiff’s costs of and incidental to the
action, including both applications, to be assessed. Because of the declarations
made, costs should be assessed on the District Court scale.
-- 11 of 11 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2006/416