Clark & Ors v Cook Shire Council [2006] QPEC 123
PLANNING & ENVIRONMENT COURT
OF QUEENSLAND
CITATION: Clark & Ors v Cook Shire Council [2006] QPEC 123
PARTIES: BARRY JAMES CLARK and MARILYN TERESA
CLARK
First Applicants
And
PATRICK HAGARTY AND MARGARET JOAN
HAGARTY
Second Applicants
And
FOREVER ENDEAVOUR 796 PTY LTD (ABN
075500631)
Third Applicant
And
MINES AND INDUSTRIAL PROTECTIVE COATINGS
PTY LTD (ACN 081804177)
Fourth Applicant
And
KAREN OLSEN AND SELWYN WENDT
Fifth Applicants
V
COOK SHIRE COUNCIL
Respondent
FILE NO/S: Cairns 316/2006
DIVISION: Planning and Environment
PROCEEDING: Originating Application
ORIGINATING
COURT: Planning and Environment Court of Queensland, Cairns
DELIVERED ON: 15 December 2006
DELIVERED AT: Brisbane
HEARING DATE: 12 December 2006
-- 1 of 9 --
2
JUDGE: Alan Wilson SC, DCJ
ORDER: Application dismissed
CATCHWORDS: PLANNING – PLANNING LAW AND LEGISLATION –
introduction of new planning schemes under Integrated
Planning Act 1997 – meaning and effect of Schedule 1 –
whether local authority obliged to give further public notice if
modifications are made to previously publicised scheme of
which submitters and landowners have not had notice
Integrated Planning Act 1997, Schedule 1
Associated Provincial Picture House Ltd v Wednesbury
Corporation (1948) 1 KB 223
Australian Retailers Association v Reserve Bank of Australia
[2005] 19 FCA 1707
Booth v Bosworth [2001] FCA 1453
Coco v The Queen (1993-94) 179 CLR 427
Cox v Maroochy Shire Council [2006] QPEC 051
Foster v Minister for Customs (2000) 200 CLR 442
Hawkesbury City Council v NSW Minister for Infrastructure
& Planning [2004] NSWLEC 188
Leichhardt Municipal Council v Minister for Planning (1995)
87 LGERA 78
Lyons v Misty Morn Developments Pty Ltd [1998] QPELR
268
Minister for Aboriginal Affairs v Peko-Wallsend Ltd (1986)
162 CLR 24
Minister for Education v Eshetu (1999) 197 CLR 611
Project Blue Sky Inc v Australian Broadcasting Authority
(1998) 194 CLR 355
R v Atwell, ex parte Jullie (2002) 2 Qd R 367
Qwiksnax Mobile Industrial & General Caterers Pty Ltd v
Logan City Council [1994] 1 Qd R 291
Resort Management Services v Noosa Shire Council (1995) 1
Qd R 311
Shoreline Park Pty Ltd v Mackay City Council [2006]
QPELR 521
Westfield Management Ltd v Pine Rivers Shire Council
[2004] QPELR 337
COUNSEL: S Keim SC for applicants
S Fynes-Clinton for respondent
SOLICITORS: David Kempton for applicants
King and Company for respondent
[1] The Integrated Planning Act 1997 (IPA) contains, in Chapter 2 Division 3 and
Schedule 1, provisions concerning the manner in which local authorities must
prepare and introduce new planning schemes. In this case the question is whether
or not Cook Shire Council has correctly followed those procedures. The applicants’
-- 2 of 9 --
3
complaint is that they were, in effect, ambushed at a late stage in the process and
improperly denied the opportunity to make submissions about modifications to an
earlier form of the new scheme which affect their land, but to which they were not
previously alerted. Council concedes that the changes were made without any
warning or the opportunity for further submissions from the applicants but contends
that is permissible under IPA, in the circumstances arising here.
[2] IPA compelled local authorities to introduce new planning schemes: s 6.1.11. Ch 2,
Div 3 sets out the process for preparing these new schemes. It involves three stages
(preliminary consultation and preparation, consideration of State interests and
consultation, and adoption) and requires the local authority to follow the steps set
out in Schedule 1: s 2.1.5. The particular question arising here springs from the
latter part of the second stage and concerns Council’s power to modify a previously
notified draft planning scheme without undertaking additional public consultation:
Sch 1, s 16.
[3] Each of the applicants owns a property in Cook Shire which was designated as
falling within a particular zone in an earlier draft of the planning scheme, about
which some of them made submissions. Subsequent to that notification, however,
Council modified that previous scheme in a way which changed the zone for all or
part of the properties in question. The applicants’ contention is that this new,
modified planning scheme is, in the words of s 16, significantly different from the
previous version and Council is therefore required under s 16(2) to recommence the
public notification process.
[4] Although a great deal of evidence was placed before the court there are no real
factual disputes (save in one respect which, for reasons which follow, is not of
moment). The first applicants, the Clarks, own several large lots near the mouth of
the Endeavour River which contain an old wartime runway, a quarry, and industrial
areas. The original notified proposed scheme designated about 80 per cent of
Lot 39 on RP 71022 (about 79 hectares) in the Conservation Zone, with the balance
(about 20 hectares) in the Rural Zone, and the adjoining Lot 40 (containing the
disused airstrip) was placed wholly in the Rural Zone. Under the new, modified
scheme about 90 per cent or 89 hectares of Lot 39 is included in the Conservation
Zone, with the balance in the Industrial Zone, and the whole of Lot 40 is placed in
the Conservation Zone.
[5] Each of the second to fifth applicants owns a waterfront urban lot of around
1,000 - 1,600 m2 save for the fifth applicant, whose parcel contains just under
6,000m2. Under the original proposed scheme each of these lots was included in the
Medium Density Residential Zone but under the new, modified scheme each is
placed in the Low Density Residential Zone.
[6] The Clarks made representations about the original proposed scheme. The factual
dispute concerns the question whether Council misunderstood that submission and
introduced the modifications under the misapprehension that they were in accord
with it – when, as seems evident, they were in fact directly contrary to it. Evidence
from a Council officer shows, however, that the submission was fully considered
and comprehensively addressed. Even if the contrary view is open the matter is not
one which avails the Clarks, as the reasons which follow show.
-- 3 of 9 --
4
[7] The other applicants were content with the Medium Density Residential Zoning
shown in the scheme in its earlier form and did not perceive any need to make a
submission. Their complaint was that, had they known the respondent was
considering a change to Low Density Residential, they would have done so.
[8] Argument focussed, then, on the nature and effect of the IPA requirements for
public consultation. Mr Keim SC went so far as to suggest that the legislation
enshrines a fundamental right of landowners to be heard before any changes are
made to a planning scheme which might affect the value of their interest1. That
may put the matter a little high, but it has been acknowledged that landowners are
not lightly denied a voice when local authorities act in ways which affect those
interests. In Qwiksnax Mobile Industrial & General Caterers Pty Ltd v Logan City
Council [1994] 1 Qd R 291 Thomas J said, at 305:
Denial to citizens of an adequate right to object to a bylaw which affects commerce
generally, and which imposes penalties for non-compliance, is a serious matter. If
it is breached, it cannot be said that the local authority has substantially complied
with the statutory requirements.
[9] Chapter 2 and Sch 1 place a strong emphasis on public consultation. Section 2.1.5,
which has already been mentioned, refers to a consultation stage. Section 2.1.6
protects a planning scheme which has been made in substantial compliance with the
steps set out in Sch 1 from any allegation of invalidity, so long as the non-
compliance has not:
(a) adversely affected the awareness of the public of the existence and nature of the
proposed scheme; or
(b) restricted the opportunity of the public under Schedule 1 to make properly made
submissions; or
(c) restricted the opportunity of the Minister to exercise the Minister’s powers under
Schedule 1, sections 10, 11 and 18 (emphasis added).
[10] Under Sch 1 the first, necessary step requires the local government to prepare a
statement of its proposals for its new scheme and, under s 5, publish a notice with
information about that statement and invite written submissions, from any person,
during a consultation period of at least 40 days. Under s 7 the Council must
consider every properly made submission it receives. Once those and other steps
are completed it may prepare a proposed planning scheme and offer it for inspection
and, again, invite written submissions: s 12. Council is then required, under s 14, to
“… consider every properly made submission about the proposed planning
scheme”. That is the stage which had been reached when the Clarks made their
submissions, and the other applicants determined not to lodge any.
[11] The next stage, critical here, is addressed in s 16:
16 Decision on proceeding with proposed planning scheme
(1) After considering every properly made submission, the local
government must decide whether to –
(a) proceed with the proposed planning scheme as notified; or
(b) proceed with the proposed planning scheme with modifications; or
(c) not proceed with the proposed planning scheme.
1 vide Coco v The Queen (1993-94) 179 CLR 427, at 437 per Mason CJ and Brennan, Gaudron and McHugh
JJ.
-- 4 of 9 --
5
(2) If the local government decides to proceed with the proposed
planning scheme with modifications and is satisfied the modifications
make the proposed planning scheme significantly different from the
proposed planning scheme as notified, it must recommence the
process outlined in this schedule from section 12. (emphasis added)
Section 17 then requires that the local government prepare a report
“… explaining in general terms how it has dealt with the submissions received”,
and provide it to submitters.
[12] The applicants contend that the modified planning scheme is significantly different
from the earlier one and it should be declared that Council is, therefore, required to
recommence the public notification process under s 12. The proceedings are
brought in reliance upon this Court’s declaratory powers under IPA s 4.1.21 which,
the Council accepts, are sufficient to embrace questions about the lawfulness of a
local government’s compliance or purported compliance with a prescribed and
mandatory procedural step in the process leading up to the making of a planning
scheme2.
[13] Section 16 is to be construed so as to give it the meaning the legislature apparently
intended and, ordinarily, that legal meaning will correspond with the grammatical
meaning of the words used: Project Blue Sky Inc v Australian Broadcasting
Authority3. It was submitted for the applicants that some other provisions of IPA,
over and above those already mentioned, should be included in the statutory context
in which s 16 is considered. They include s 4.1.5A which contains a general
excusatory provision, and other parts which give objectors to development
applications statutory rights of appeal. All are, however, quite different and remote
from the mechanisms contained in Sch 1, which relate to a distinctly separate part of
the legislation and an entirely unrelated process and do not, materially, provide
submitters with any right of appeal.
[14] The proper starting point is, rather, an analysis of s 16 based upon its language, and
its context within the provisions of which it forms part: i.e., Ch 2 and Sch 1. While
it is true that a number of those provisions including, in particular, s 2.1.6 preserve
and indeed emphasise the importance of the public consultation process, s 16(1)
simply specifies what the local government must do after it has considered all
submissions and does not require, or even imply, a necessary causal link between
the content of any particular submission and the decision which is taken.
[15] In other words, the power to proceed with the proposed planning scheme as notified
is not conditioned upon there being nothing raised in submissions which the Council
considers gives rise to a need for modifications; nor is the power to decide to not
proceed with the proposed scheme conditioned upon there being something in the
submissions which persuades Council to take that decision; and, in particular, the
power to proceed with the proposed scheme in its modified form is not conditioned
upon those modifications being made in a way which responds to submissions
2 Resort Management Services v Noosa Shire Council (1995) 1 Qd R 311, while dealing with a different
process for planning schemes under previous legislation supports the proposition that even if the ultimate
procedure which gives a planning scheme the force of law is legislative, the distinct preliminary steps to be
followed before that power may be exercised are properly characterised as administrative, and therefore
subject to review.
3 (1998) 194 CLR 355 at 384 per McHugh, Gummow, Kirby and Hayne JJ
-- 5 of 9 --
6
received. Even more clearly, it is not conditioned upon those modifications being
consistent with modification requests contained in a submission, or submissions.
[16] As Mr Fynes-Clinton (for the Council) submitted, if Parliament had intended that
the alternative courses of action under s 16(1) were constrained so that they could
be taken only as a direct response to (and consistently with) a course of action urged
in a submission, it could and would have said so. A provision of that kind would be
a very significant restriction on local government law making power, and have to be
plainly expressed4.
[17] On its face s 16(1) gives a local government the power to make changes to a
proposed, notified planning scheme without apparent constraint. Those changes
may include modifications which respond to submissions which have been received
but, importantly, are not limited to them. The only express restraint is contained in
s 16(2) and concerns Council’s satisfaction, or otherwise, about the question
whether the modified proposed planning scheme is “significantly different” from the
notified scheme. The requirement for satisfaction means the local government must
turn its mind to, among other things, the question whether additional or materially
different submissions would be likely to be received in respect of the modified
scheme as compared to those already received in the face of the notified scheme.
[18] The test implicit in s 16(2) is to be considered against a statutory background which
requires that before a proposed planning scheme is prepared the local government
undertakes a preliminary consultation process which identifies proposals for it, and
invites submissions; that process contributes to the preparation of the proposed
planning scheme itself, which is then notified to the public; that notified scheme
reflects, then, the local authority’s detailed identification of the issues relevant to
future development within its entire area, and how they should be addressed.
[19] At its core the test involves a comparison between the notified and modified
schemes and the formation of an opinion as to whether the latter is significantly
different from the former, as a whole.
[20] Not without some hesitation – because the construction for which Council contends
has the effect, ultimately, of denying landowners the right to make further
submissions even if, unbeknownst to them, modifications are being considered at
this late stage which will adversely affect their interests – I have come to the view
that, in context, the phrase “significantly different” does not necessarily prohibit that
course. S 16 itself, and other aspects of the legislation relevant to its meaning,
contain elements indicating that it is a result within the contemplation of the
Legislature.
[21] First, as Mr Keim SC had to concede during oral submissions, the phrase must
involve questions of degree and very minor changes affecting but a few parcels
within a local government area could not, realistically, be said to fall within the
obvious meaning of the words. (Here, the modifications affect a total area of less
than 34 hectares, in a Shire with a planning scheme covering 11.5 million hectares.)
It is most unlikely the Legislature intended that a change in the proposed zoning of
one parcel or a small proportion of those included in a scheme area to something
different from that previously notified is, in itself, a significant difference. IPA
4 See, generally R v Atwell, ex parte Jullie (2002) 2 Qd R 367
-- 6 of 9 --
7
planning schemes are voluminous and serve a number of purposes but, essentially,
they prescribe preferred forms of development. While particular designations and
zonings of areas and districts are an integral part of them, to construe the word
‘modifications’ to include changes to zonings on a scale which is, in the context of
the scheme as a whole, minor would make the exercise under Sch 1 unworkable.
[22] Secondly, it is material that the consultation process under Sch 1, ss 1-8 and s 12
does not involve notice to individual landowners but, rather, to the public generally
by advertisement in a newspaper; and, that the submissions which are invited are,
again, not site specific but may address “any aspect” and be made by “any person”.
These terms indicate the process is consultative, in the broad sense of that word. It
has no particular focus on the individual personal interests of landowners (while not
excluding them) but, rather, on the wider planning issues which confront the shire,
town or city.
[23] Then, the public is again invited to comment upon Council’s provisional decisions
about those issues. That mandatory step – for Council to consider submissions –
requires and enables it to address differences between the manner in which it has
approached planning issues, and the way submitters suggest they should be
addressed, so as to make a more fully informed and considered decision about the
final form of the planning scheme.
[24] In this broader context, the more compelling meaning of the phrase is that a
modified planning scheme would be “significantly different” from the previous
notified scheme if the modifications raised new issues on a significant scale: i.e.
about permitted or desirable forms or patterns of development within the local
government area as a whole, or an identifiable and significant locality within it; and,
if those new issues were not ones upon which the Council previously formed a view
which had been notified to the public, and exposed to submissions.
[25] In short, the phrase is one which is more apt, in the context of the legislation, to
apply to the macrocosm of the planning scheme as a whole, rather than the
microcosm of possible submissions or objections from particular landowners on
grounds involving an assertion that personal interests have been adversely affected.
On this analysis, the matter for consideration under s 16(2) is whether the proposed
changes raise a significant new question about planning alternatives to deal with a
material planning issue for the Shire or a particular locality, such that further public
consultation could be reasonably expected to bring forward material considerations
for Council’s decision which had not previously been advanced.
[26] The matter has not, according to counsels’ research, been previously considered in
Queensland but Mr Keim SC relied upon an earlier decision of this Court, and two
New South Wales cases, for support for the proposition that the proper test includes
an inquiry whether the public has been misled about the nature of the scheme or
compromised in its ability to make fully informed decisions. The decision in this
Court, Shoreline Park Pty Ltd v Mackay City Council5 involved an application for
an interim injunction in circumstances where the local authority had publicly
advertised an intention to include the applicant’s land, in its proposed new planning
scheme, in a zone permitting uses for tourism purposes. The applicant, having no
objection, made no submission but the modified scheme changed the designation of
5 [2006] QPELR 521
-- 7 of 9 --
8
the land to “open space”. The applicant contended the modification was
significantly different and, without giving reasons, Judge Wall QC found the change
in zoning raised a serious question to be tried in relation to whether the Council had
complied with s 16. The arguments advanced here were not, it appears, considered.
[27] Leichhardt Municipal Council v Minister for Planning6 concerned a different
statutory regime and involved the scope of the power to make changes to a notified
instrument under relevant NSW legislation. The other NSW decision, Hawkesbury
City Council v NSW Minister for Infrastructure & Planning7 involved the
application of test postulated in Leichhardt, which requires the court to consider
whether a plan, as amended by the Minister after public notification, remained “the
outcome of the process which included the public exhibition of the draft plan”.
[28] In fact, that test is not dissimilar to the one which should apply here: it involves an
examination of what has been notified, the submissions received and the manner in
which Council has responded to them and, then, a determination whether the
modified form is justifiable as an outcome of that process or the result of some
entirely new consideration, by the local authority, of matters unrelated to the
previous steps.
[29] The ordinary meaning of the word “significant” also supports the conclusion that
something more than modifications which touch only zonings for a few parcels, and
some individual landowners, is contemplated. In the Oxford Australian Dictionary
it is relevantly defined to mean “noteworthy; important; consequential”; and, in
Booth v Bosworth [2001] FCA 1453 Branson J accepted that the phrase “significant
impact” means “impact that is important, notable or of consequence having regard
to its context of intensity”.
[30] The applicants’ originating application, and submissions from Mr Keim SC, argued
two distinct errors of law had been made by Council: first, that no reasonable
Council could have failed to form the opinion, or have been satisfied, that the
modified planning scheme was significantly different from the original proposed
scheme; and, secondly, that Council failed to take relevant considerations into
account when it decided to adopt the latter scheme without recommencing the
public notification process.
[31] The first raises what is conventionally referred to as “Wednesbury
unreasonableness”8, and involves principles previously considered by this Court. In
particular, Skoien SJDC summarised the law in Lyons v Misty Morn Developments
Pty Ltd9:
There have been many cases in which a court has been asked to review something
done by a person or body under an Act of Parliament where the authority to do that
thing is expressed by the Act to be dependent on that person reaching a specified
state of satisfaction.
…
The law on this topic is clear. The opinion of the Council must be accepted unless
it can be shown to have been one that no reasonable Council could have formed or
that it was based on any relevant consideration or that in some other way it was
6 (1995) 87 LGERA 78
7 [2004] NSWLEC 188
8 Associated Provincial Picture House Ltd v Wednesbury Corporation (1948) 1 KB 223
9 [1998] QPELR 268, at 272
-- 8 of 9 --
9
unjustifiable. If it is unjustifiable, it stands whether or not others may disagree
with it. …
[32] A similar statement fell from his Honour in Cox v Maroochy Shire Council10 in
which he also referred to a passage from Australian Retailers Association v Reserve
Bank of Australia11, to the effect that the invocation of the principle to invalidate a
decision should be:
Confined to extreme cases; its application should not involve the Courts in
trawling through the fine details of the administration’s work, looking for errors.
Rather, it amounts to the sort of low level quality control which most management
systems should maintain in any event … There would be serious credibility cost to
the system if demonstrably absurd decisions were allowed to go unchecked.
[33] The applicants were obliged to show, then, that the only reasonable conclusion open
to the local authority was that for which they contend – or, in other words, that the
decision was one for which no logical basis could be discerned12. The test involves,
plainly, a high hurdle. For the reasons already set out, however, even if the bar is
lowered there is no ground for concluding, here, that it was unreasonable for the
Council to determine that the changes were not significantly different from the
scheme which was publicly advertised.
[34] The second particular complaint is the alleged failure of Council to properly take
into account relevant considerations raised in the Clarks’ submissions, or to
properly apprehend what was shown in them. Again, the argument involves an
assertion of unlawfulness expressed in terms relevant to familiar principles of
administrative law, under which the ground is only made out if the decision maker
has failed to take into account something it is bound to consider13. The factors
which are mandatory must, however, be discernible in the section and appear from
its apparent scope and purpose. They are not, under Sch 1 s 16, express and must
therefore be found by the process of statutory construction and analysis already
undertaken. Again, as these reasons show, those factors do not include those of
small scale or degree – the microcosm – of the sort raised by the applicants.
[35] Lastly, it is not immaterial that the statutory context includes IPA provisions which
have the effect that, notwithstanding the modifications, existing use rights are fully
protected14; and the applicants may ultimately have the opportunity of recourse to
compensation provisions15.
[36] The application is dismissed.
10 [2006] QPEC 051
11 [2005] 19 FCA 1707
12 Minister for Education v Eshetu (1999) 197 CLR 611 per Gaudron and Kirby JJ at 640
13 Minister for Aboriginal Affairs v Peko-Wallsend Ltd (1986) 162 CLR 24, at 39 and 55-56; and, Foster v
Minister for Customs (2000) 200 CLR 442 at 452
14 IPA, s 1.4.2
15 IPA, s 5.4.2
-- 9 of 9 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2006/123