Firefast Pty Ltd v Ipswich City Council & Ors [2006] QPEC 76
1
[2006] QPEC 076
PLANNING AND ENVIRONMENT COURT
JUDGE ROBIN QC
P & E Appeal No 1839 of 2006
FIREFAST PTY LTD
(ACN 010 859 793) Applicant
and
IPSWICH CITY COUNCIL Respondent
and
JOHN EDWARDS & JENNY WILLARD First Co-Respondent by
Election
and
GARY SELWYN LUKRITZ & VICKI MAREE
LUKRITZ Second Co-Respondent by
Election
and
RON MURRAY & JENNY MURRAY Third Co-Respondent by
Election
BRISBANE
..DATE 10/07/2006
ORDER
CATCHWORDS: Integrated Planning Act 1997 s 3.5.33 - condition
of approval of a material change of use contained in an order
of the Court resolving an earlier appeal changed so that the 2
year period allowed runs from actual commencement of the use
rather than from the date of the order.
WARNING: The publication of information or details likely to lead to the identification of persons in some proceedings is a criminal
offence. This is so particularly in relation to the identification of children who are involved in criminal proceedings or proceedings for
their protection under the Child Protection Act 1999, and complainants in criminal sexual offences, but is not limited to those
categories. You may wish to seek legal advice before giving others access to the details of any person named in these proceedings.
-- 1 of 5 --
2 ORDER
1
10
20
30
40
50
60
HIS HONOUR: This is an application under s 3.5.33(2) of the
Integrated Planning Act 1997 to change a condition of a
development approval contained in an order made by Judge
Wilson on the 12th of July 2004 in Appeal 129 of 2004. A
sizeable sub-division was involved but the change of condition
sought relates to a development permit for a general store,
which Mr Nicholls confirms is to be located in an existing
house.
The approval in condition 27 stated that "The development
approval for a general store is valid for two years from the
date this approval takes effect", being the date of the order.
The two years are about to run out. As things have turned
out, construction for the general store activity did not occur
as expeditiously as was anticipated and may even now not be
complete. It is said there have been difficulties in
obtaining permits for operational works. What is sought is
that the development permit last mentioned be declared to run
for two years from the commencement of the use. I have had
some concern that it might be important to get that date,
which still lies in the future, identified for purposes of
future reference. As Mr Nicholls says, it is probably going
to be easy enough to identify when a general store opens for
business. The currently binding Court decisions about
commencement of uses indicate, contrary to earlier authority,
that the commencement of a use such as that in question here
occurs only when that particular use is actually implemented,
rather than when some preparatory steps are undertaken. See
McDonald v Douglas Shire Council [2004] 1 QdR 131. I have
-- 2 of 5 --
3 ORDER
1
10
20
30
40
50
60
resiled from my enthusiasm for requiring some means of
identification to be incorporated in the Court's order.
In my opinion, commonsense and ordinary considerations of
fairness dictate the Court's taking a sympathetic approach to
the applicant's having an opportunity to carry out the use in
the absence of special circumstances indicating that the
indulgence of further time should be withheld as in the case
of Reynolds v Redlands Shire Council [2001] QPELR 184.
The co-respondents are limited to three couples, they being
the adverse submitters who participated in the proceeding
concluded before Judge Wilson. Mr Nicholls has placed before
the Court all of the submissions which were made prior to the
original development approval. They include material from
additional concerned people objecting that the general store
activity would lead to rubbish being left in the area and
might attract some undesirable people there "boaties" being
instanced, along with a concern that there were no toilet
facilities and the like. Mr Nicholls relies on Australian
Conservation Foundation Gold Coast Inc. v. Gold Coast City
Council [2001] QPELR 96 as establishing that only those joined
as co-respondents in this application had to be served with
it.
None of those people has appeared when called this morning.
Service has been effected. There has been positive advice
from the Willards that they do not wish to participate. The
local government consents to the application.
-- 3 of 5 --
10072006 T04/DEP29 M/T CMS76/2006 (Robin DCJ)
4 ORDER
1
10
20
30
40
50
60
Having considered in a general way the things the Court's
required to consider under section 3.5.33(7) of the Integrated
Planning Act 1997, in particular in paragraphs (a) and (b), I
can see no reason for the Court's withholding the relief
that's sought. In respect of the proposition that the Court
should not proceed on the basis that further assessable
development would arise from the change - see section
3.5.33(1)(b) - Mr Nicholls has pointed to the practical
approach taken in cases such as Rhema Management Services Pty
Ltd v Noosa Shire Council [2000] QPELR 15 at 16 and Rose Bay
Developments Proprietary Limited v Bowen Shire Council [2001]
QPELR 340 at 342G-I.
He also reminded the Court of the contrary outcome in Hayday
Pty Ltd v the Brisbane City Council [2005] QPEC 050 adopting
the practical approach. The affidavit of Mr S.R. Smith
justifies the determination sought in the circumstances that
there is no further assessable development concerned here.
cf. Martin v Whitsunday Shire Council [2001] QPELR 348 at 350.
Here, there is no change whatever to the applicant's proposal.
It is merely a case of the approved use commencing (and then
running for a period now set at 2 years) at a later time.
There will be an order in terms of the initialled draft.
-----