D'Aguilar Gold Ltd v Gympie Eldorado Mining Pty Ltd [2006] QLRT 10
LAND AND RESOURCES TRIBUNAL
QUEENSLAND
CITATION: D’Aguilar Gold Ltd v Gympie Eldorado Mining Pty Ltd
[2006] QLRT 10
PARTIES: D’Aguilar Gold Ltd (Applicant)
v
Gympie Eldorado Mining Pty Ltd (Respondent)
FILE NO: CAV23/06
PROCEEDING: Application to continue caveat
DELIVERED ON: 1 March 2006
DELIVERED AT: Brisbane
HEARING DATE: 28 February 2006
MEMBER: Koppenol P
ORDER: 1. Caveat continued until 13 June 2006 or earlier
order by the tribunal. (at [16])
2. No order as to costs. (at [16])
CATCHWORDS: CAVEAT – EXPLORATION PERMIT FOR MINING
– Whether caveat should be continued – Factors
relevant
Mineral Resources Act 1989, ss 126, 152, 154
Land Title Act 1994, s. 126
Land and Resources Tribunal Act 1999, s. 50(2)
Moneywood Pty Ltd v Salamon Nominees Pty Ltd
(2001) 202 CLR 351, applied
COUNSEL: Mr. P. Dunning SC for Applicant
SOLICITORS: Hopgood Ganim for Applicant
Ms. Z. Farmer for Respondent
Application
[1] This is an application under section 154(2)(c) of the Mineral Resources Act 1989
(MRA) to continue the term of a caveat.
-- 1 of 4 --
Background
[2] On or about 29 May 2003, the applicant entered into a written agreement
(agreement) with Gympie Eldorado Goldmines Pty Ltd (seller), under which the
applicant was granted various rights of use and enjoyment with respect to 6 sub-
blocks1 on Exploration Permit for Minerals No 6031 (EPM 6031) which was held by
the seller. Subsequently, receivers and managers were appointed to the seller and
they assigned (assignment) EPM 6031 to the respondent.
[3] A dispute later emerged when the applicant proposed to exercise the rights conferred
and the respondent maintained that it was still the sole legal and beneficial owner of
the 6 sub-blocks and was not bound by the agreement. The respondent then filed an
application in the Tribunal seeking orders to that effect. On 28 November 2005, I
struck out that application on the basis that the Tribunal did not have jurisdiction to
hear it.2
[4] The applicant lodged a caveat over EPM 6031 on 14 December 2005; unless
extended it will lapse on 13 March 2006.
Submissions
[5] The applicant submitted that it holds a caveatable interest because (a) the agreement
was recorded in the register under section 158 (Recording of agreements,
arrangements, dealings or interests) prior to the assignment and its subsequent
recording under that section, thus creating an interest by force of statute, and/or (b)
the nature of the agreement itself was sufficient to create a claim of an interest for
section 152 (Lodgment of caveat) purposes. It was desirable that the caveat
continues as it constitutes notice to the world and prevents further assignments of the
EPM. That would also give the respondent the opportunity to apply to the Supreme
Court to have determined the question of the ownership of the 6 sub-blocks.
However unlike section 126 of the Land Title Act 1994, section 154 of the MRA
does not require the caveator, if it does not want the caveat to lapse, to start a
proceeding in a court of competent jurisdiction to establish the interest claimed under
the caveat.
[6] The respondent argued that no caveatable interest existed because neither section 158
nor the agreement had the effect of creating a caveatable interest. Reference was
made to my earlier decision to establish that the applicant did not have an interest in
the EPM. The applicant had not applied to the Supreme Court to establish its interest
and it should not be for the respondent to apply to court for appropriate relief.
Analysis
[7] Caveatable interest: In my opinion, the argument about section 158 can be put to
one side for present purposes. The caveat here expressed the “nature of right or
interest claimed by the caveator” in the following terms:
1 As defined in MRA section 126.
2 [2005] QLRT 156.
-- 2 of 4 --
“The nature of the interest claimed by the Caveator is the right under the Agreement entered
into between the Caveator and Gympie Eldorado Gold Mines Pty Ltd for the rights of use and
enjoyment with respect to sub-lots N, O, S, T, W, X of EPM 6031.”
[8] Section 152(1) of the MRA provides that “[a] person who claims a right or interest in
or in respect of an exploration permit” may lodge a caveat forbidding the approval of
any assignments of the EPM. Thus it is not necessary for the caveator to claim a
right or interest in an EPM; a claim to a right or interest in respect of an EPM is
sufficient.
[9] In Moneywood Pty Ltd v Salamon Nominees Pty Ltd,3 Gummow J said that the
phrase “in respect of” has:
“… the widest possible meaning of any expression intended to convey some connection or
relation between the two subject matters to which the words refer.”
[10] The right or interest claimed in the caveat is expressed to be under the agreement for
rights of use and enjoyment with respect to the 6 sub-lots of the EPM. So expressed,
the claimed right or interest clearly conveys a connection or relation between the
agreement and the EPM—and on that basis, constitutes a caveatable interest under
section 152(1). It is not necessary for present purposes to consider whether the
applicant has an interest in the EPM.
[11] Ms Farmer drew attention to my comments in the earlier strike out application that
the applicant had only rights of use and enjoyment in the 6 sub-blocks on the EPM—
“albeit rights which might later mature into an interest.”4 However, those comments
do not relate to whether the applicant had a section 152(1) right or interest in respect
of an EPM.
[12] Balance of convenience: If the caveat is not continued, the respondent would be free
to assign the EPM. Any such assignment could result in detriment to the applicant
and, if the applicant’s claimed right or interest is ultimately upheld by the Supreme
Court, to an assignee from the respondent. On the other hand, there was no evidence
before me that the respondent could suffer prejudice if the caveat were continued.
[13] Unlike the Land Title Act, the MRA does not require the caveator, if it does not want
the caveat to lapse, to start a proceeding in a court of competent jurisdiction to
establish the interest claimed. If the applicant had started such a proceeding, that
would undoubtedly have been a factor in favour of continuing the caveat. However I
am not satisfied that the non-commencement of a proceeding should be regarded as a
factor militating against a continuation. No authorities on the point were cited and in
the circumstances, I can see no reason at present for conditioning the continuation of
the caveat upon the applicant instituting such a proceeding. Naturally, the
respondent is at liberty (if so advised) to start its own Supreme Court proceedings
seeking appropriate declaratory and other relief about the agreement and the
assignment. That would determine the issue one way or the other.
3 (2001) 202 CLR 351, 380 [96], applying State Government Insurance Office (Q) v Crittenden (1966) 117 CLR 412,
416.
4 [2005] QLRT 156 at [13].
-- 3 of 4 --
Disposition
[14] I have concluded that the caveat should be continued in force, without conditions.
The applicant sought a continuation until further order by the Tribunal. A period of
3 months was initially claimed in the caveat and that is the default period provided in
section 154(2)(d). That period seems appropriate in the present case. There will
therefore be an order that the subject caveat be continued until 13 June 2006 or
earlier order by the Tribunal.
[15] The applicant sought costs but I am not satisfied that special circumstances exist
under section 50(2) of the Land and Resources Tribunal Act 1999. There will be no
order as to costs.
Orders
[16] The orders that I make are as follows:
1. Caveat continued until 13 June 2006 or earlier order by the Tribunal.
2. No order as to costs.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QLRT/2006/010