Discovery Beach Project P/L v Northbuild Construction P/L [2005] QSC 322
SUPREME COURT OF QUEENSLAND
CITATION: Discovery Beach Project P/L v Northbuild Construction P/L
[2005] QSC 322
PARTIES: DISCOVERY BEACH PROJECT PTY LTD
ACN 100 500 981
(applicant)
v
NORTHBUILD CONSTRUCTION PTY LTD
ACN 011 063 764
(respondent)
FILE NO/S: BS 7831 of 2005
BS 7832 of 2005
BS 7834 of 2005
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court, Brisbane
DELIVERED ON: 4 November 2005
DELIVERED AT: Brisbane
HEARING DATE: 28 October 2005
JUDGE: de Jersey CJ
ORDERS: 1. The arbitrator’s award of 19 August 2005,
determining that he had jurisdiction to hear and
determine variation requests 71 as amended, and 75,
is set aside
2. The arbitrator’s award dated 28 August 2005,
determining that he had jurisdiction to hear and
determine variation order 97, is set aside
3. Costs reserved, with liberty to apply
CATCHWORDS: ARBITRATION – THE AWARD – APPEAL OR
JUDICIAL REVIEW – GROUNDS FOR REMITTING OR
SETTING ASIDE – WANT OF JURISDICTION AND
EXCESS OF AUTHORITY – where a provision of the
building contract between the parties provided for referral of
disputes to arbitration – where the parties entered separate
agreements, referring certain matters to experts for
determination – where agreements were each conditional
upon the consent of a financier, which was not expressly
forthcoming – where nevertheless, the parties had proceeded
consistently with the subsistence of the agreements – where,
while the experts were seized of those matters, the
-- 1 of 12 --
2
respondent, purportedly acting under the building contract,
referred them to arbitration – where the arbitrator made an
award, determining that he had jurisdiction – whether the
agreements referring issues for expert determination were
subject to a condition precedent which was not fulfilled –
whether the arbitrator made the award without jurisdiction –
whether the award amounted to misconduct on the part of an
arbitrator – whether to justify setting aside an award, the error
of law relied on must appear ex facie
ARBITRATION – THE AWARD – APPEAL OR
JUDICIAL REVIEW – PROCEDURE – APPEALS AND
LEAVE TO APPEAL – LEAVE TO APPEAL FROM
DECISION OF ARBITRATOR – QUESTION OR ERROR
OF LAW – whether, alternatively, the court should grant the
applicant leave to appeal against the arbitrator’s
determinations
Commercial Arbitration Act 1990 (Qld), s 8, s 38, s 43
Brambles Holdings Ltd v Bathurst City Council (2001) 53
NSWLR 153
Consolidated Constructions Pty Ltd v Saipem Australia Pty
Ltd (1999) 15 BCL 64
Hodgkinson v Fernie (1857) 3 CBNS 189
Kennedy-Taylor (Qld) Pty Ltd v Civil and Civic Pty Ltd,
unreported, Court of Appeal, Qld, No 17 of 1994, 2
November 1994
Kent v Elstob (1802) 3 East 18
Re Scibilia & Lejo Holdings Pty Ltd Arbitration (1985) 1 Qd
R 94
COUNSEL: P H Morrison QC, with P Hastie, for the applicant
P Dunning for the respondent
SOLICITORS: Minter Ellison for the applicant
Ebsworth & Ebsworth for the respondent
Introduction
[1] On 23 May 2003, the applicant (“Discovery Beach”) and the respondent
(“Northbuild”) entered into a building contract in relation to the Surfair Resort
redevelopment at Marcoola. In the course of the project, disputes arose. The
contract contained a mechanism for the resolution of disputes. That mechanism
provided for arbitration, or determination by an expert.
[2] This proceeding concerns two variation requests, numbered VR71 (amended) and
VR75, which related to a prolongation claim; and one variation order, VO97, which
concerned the provisional sum with respect to the work on the beach houses.
[3] The applicant contends that the variation requests were, by agreement separate from
the building contract, committed to experts. While the experts were seized of those
matters, the respondent – purportedly acting under the building contract – referred
-- 2 of 12 --
3
them to arbitration, and an arbitrator was appointed. The applicant challenged the
arbitrator’s jurisdiction. On 19 August 2005, the arbitrator ruled that he had
jurisdiction in respect of them.
[4] The respondent also referred the variation order to arbitration. The applicant in fact
withdrew the variation order on 28 July 2005. The applicant contends that the
subject matter of that variation order had also been committed, by separate
agreement, to expert determination. On 28 August 2005, the arbitrator ruled that he
had jurisdiction in respect of that matter as well.
[5] The applicant applies under s 43 of the Commercial Arbitration Act 1990 (Qld)
(“the Act”) for orders setting aside those rulings, which amount to awards. Section
42(1)(a) empowers the court to set aside an award “where there has been
misconduct on the part of an arbitrator”. The concept of “misconduct” embraces
error of law on the face of the award: Kennedy-Taylor (Qld) Pty Ltd v Civil and
Civic Pty Ltd, (unreported, Court of Appeal, Qld, No 17 of 1994, 2 November 1994,
p 7); Kent v Elstob (1802) 3 East 18; Hodgkinson v Fernie (1857) 3 CBNS 189; Re
Scibilia and Lejo Holdings Pty Ltd Arbitration (1985) 1 Qd R 94, 98. It also
embraces mistaking the scope of the arbitrator’s authority, or dealing with matters
not properly referred – in effect, making a decision without jurisdiction (cf.
Consolidated Constructions Pty Ltd v Saipem Australia Pty Ltd (1999) 15 BCL 64).
(The definition of “misconduct” in s 4 of the Act is inclusory.)
[6] Alternatively, the applicant seeks leave to appeal against the awards, pursuant to s 8
of the Act.
The contract provisions
[7] The provisions in the building contract for the resolution of disputes are as follows:
“13.1 NOTICE OF DISPUTE
13.1.1 If a dispute arises then either party may give
the other written notice of Dispute which
adequately identifies and provides details of
it.
13.1.2 Notwithstanding the existence of a Dispute,
the parties must continue to perform this
Agreement.
13.2 CONFERENCE
13.2.1 Within 14 days after receiving a notice of
Dispute, the parties must confer at least once
to resolve the Dispute or to agree on methods
of doing so. At each such conference each
party must be represented by a person having
authority to agree to such resolution or
methods. All aspects of such conferences
except the fact of occurrence will be
privileged.
-- 3 of 12 --
4
13.2.2 If a Dispute has not been resolved within
twenty-eight (28) days of service of a notice
of Dispute then it will be referred to
arbitration unless the party giving the notice
of Dispute:
.1 informs the other party in writing within that
twenty-eight (28) days that it elects to have
the dispute determined by expert
determination; and
.2 delivers notification to the organisation
pursuant to section 13.4.1, with a copy of that
notice to be delivered to the other party at the
same time as providing the other party with
the notice under section 13.2.1.
13.3 ARBITRATION
Arbitration will be effected by an arbitrator nominated by the
President or Chief Executive Officer of the organisation
specified in Item 1 of Schedule 26.
13.4 EXPERT DETERMINATION
13.4.1 Expert determination will be -
.1 effected by an expert nominated by the
President or Chief Executive Officer of the
organisation in Item 1 of Schedule 26; and
.2 in accordance with the rules in Item 2 of
Schedule 26 in accordance with the process
in Schedule 26.”
Item 1 of Schedule 26 states:
“Expert to be nominated by Queensland Law Society
(If no organisation stated, the President or Chief Executive
Officer of the State of Territory Chapter of the Institute of
Arbitrators or Mediators Australia in which the Works are to be
carried out.)”
Agreement to refer to experts
[8] But as I have said, the applicant’s contention is that by agreement between the
parties, independently of the building contract, the issues involved in VR71 and
VR75, as well as those involved in VO97, were referred to experts for
determination.
[9] By letter to Northbuild dated 19 August 2004, Discovery Beach recorded the terms
of an agreement which had been reached on 13 August 2004, covering many aspects
of the future progress of the project, including payment. Paragraph 6.1 referred to
payments by Discovery Beach as “subject to adjustment when the proper amount
for each category of works is resolved either by agreement, expert determination or
-- 4 of 12 --
5
litigation”. (In relation to a particular submission made, I would not consider
“litigation”, as there used, to include arbitration.) Under para 6.3, the provisional
sum for the South East Beach House fit out – subject matter of VO90, to which I
will come – was to be agreed “or determined by expert determination”. See also
paras 8 and 10.
[10] On 18 August 2004, after the agreement of 13 August, Northbuild’s solicitors wrote
to the solicitors for Discovery Beach. As that letter shows, Messrs Orange and
Callaghan had by then been appointed as experts to determine “the range of issues
presently in dispute”. The proposal was they deal with the issues in the schedule to
the letter, which included “Prolongation claim VR71” and “VR65 South Tower
Beach Houses Provisional Sum Adjustment” (part of what became VO90). Then
the letter proposed that “issues relating solely to the calculation of time be dealt
with separately by Mr Lee” (another expert).
[11] In their response of 25 August 2004, Discovery Beach’s solicitors generally
accepted that proposal, subject to some matters of detail not of present significance.
Specifically, they agreed to the appointment of Mr Lee in relation to extension of
time claims.
[12] Northbuild’s solicitors, on 24 August 2004, wrote to Messrs Orange and Callaghan
informing them the parties had agreed to the referral of “any disputes relating to
time and prolongation” to Mr Lee, saying: “you ought exclude these matters from
your consideration”. Those solicitors wrote, again making that point, on 3
September 2004 (Exhibit 1).
[13] Then on 30 September 2004, Northbuild wrote to Discovery Beach recording
further matters agreed the day before. Among other things, that agreement related
to completion of the North East Beach House work (VO90) and payment for that.
The amount payable, the letter said, “will be referred to the experts forthwith for
determination” (para 4(a)(ii)). Messrs Orange and Callaghan were those experts.
See also para 4(c) and (d).
[14] The end position is that both prolongation issues, and adjustment of the provisional
sum issue, were by agreement referred for expert determination; and in a “self-
executing” way, in that no further step had to be taken to ensure the determination
was committed in that way.
[15] As confirmed by the solicitors for Northbuild in their letter of 18 August 2004, it
was agreed that the “existing experts” deal with the matters listed in a schedule,
which included “South Tower Beach Houses Provisional Sum Adjustment” (part of
what became VO90), and “Prolongation claim VR71”. The parties agreed,
however, that issues relating solely to the calculation of time be dealt with by
another expert, Mr Lee.
[16] The parties could choose not to utilize the procedure set up by cl 13 of the building
contract, and agree to a different process for the determination of matters in issue
between them. That is what they did, in relation to the issues covered by the
agreements reached in August and September 2004. Of their own force, those
agreements resulted in the referral of the subject matter to experts. It was not
-- 5 of 12 --
6
necessary that the parties follow the (inapplicable) notification requirements of cl
13.
Non-fulfilment of “condition precedent”
[17] There was a contention, however, that the agreement which extended to referring
issues for expert determination in that way was subject to a condition precedent
which was not fulfilled. The agreements confirmed by the letters of 19 August
2004 and 30 September 2004 were each conditional upon the consent of the
financier Capital Finance Australia Ltd (“CFAL”). That consent was not expressly
forthcoming in respect of the latter agreement, which related particularly to what
became the subject matter of VO90. But that is without consequence, because the
parties proceeded consistently with the subsistence of the agreement. For example,
Northbuild’s amended VR71 lodged on 14 February 2005 refers to the agreements
of 19 August 2004 and 30 September 2004 as subsisting (p 12). Further, Mr Lee
proceeded substantially with the exercise committed to him pursuant to those
agreements, to the point in January 2005 of making an interim determination.
[18] Mr Morrison QC, who appeared for the applicant, submitted that the condition is
properly characterized, in any event, as a condition subsequent, waived by
Northbuild in proceeding under its terms with the construction, and in seeking
subsequently to enforce the August and September agreements (cf. Northbuild’s
letters to Discovery Beach of 3 December 2004 and 5 January 2005). (Northbuild
had regarded the need for CFAL consent as “a mere formality” – see its solicitors’
letter of 25 October 2004.)
[19] It is not necessary to resolve the question whether the requirement for CFAL
consent should be characterized as a condition subsequent, as a condition precedent,
or in any particular way. That is because the parties plainly proceeded on the basis
the agreements of both August and September 2004 were on foot. Either fulfilment
of the condition was waived, or the parties by their conduct affirmed their persisting
contractual relationship, as defined by those agreements, notwithstanding the
absence of the financier’s formal consent to the latter. See, generally, Brambles
Holdings Ltd v Bathurst City Council (2001) 53 NSWLR 153, 176-9.
Characterization of amended VR71 and VR75
[20] On 14 February 2005 Northbuild lodged an amended VR71. That followed and was
consequent upon the interim expert determination by Mr Lee published on 14
January 2005. Northbuild said it “reserve[d] … rights to amend the claim when Mr
Lee makes his [final] determination”.
[21] Mr Dunning, who appeared for the respondent, submitted that the amended claim
was really a fresh, distinct claim. It was separately identifiable, it is true, but I
accept it was simply an update of the original, albeit in a substantially increased
amount. It remained the prolongation claim, such as the parties had referred for
expert determination.
[22] Two days later, Northbuild lodged VR75, a claim for the payment of additional
costs and expenses incurred by subcontractors and suppliers. Mr Dunning again
styled this “a separate variation requirement in relation to particular claims that had
-- 6 of 12 --
7
never previously been the subject of a variation requirement”. But this also was
part of the prolongation claim which had been referred for expert determination.
Northbuild reserved the right to amend that claim also, following publication of Mr
Lee’s final determination.
[23] Inconsistently, on 23 February 2005, Discovery Beach gave notice of dispute under
cl 13.1 of the contract in relation to each of those claims, VR71 and VR75,
foreshadowing, absent agreement, referral for expert determination. In the letter
referring to VR71, however, Discovery Beach did speak of referring it “to the extent
that the subject matter of this dispute has not previously been referred to expert
determination”. Discovery Beach’s present contention is that determination of the
dispute had already been committed to experts, a course possible notwithstanding
the provision in cl 6 of the contract relating to the processing of variations: the
treatment of this issue had been specially provided for by the agreements of August
and September 2004.
Reference to arbitration
[24] On 23 February 2005, Northbuild gave notice of dispute under cl 13.1,
foreshadowing arbitration. On 15 April 2005, Northbuild’s solicitors sought the
appointment of an arbitrator. The solicitors for Discovery Beach objected, on the
basis the subject matter of VR71 and VR75 was, by agreement, to be determined by
experts: that awaited Mr Lee’s final determination on the matter of delay. The
arbitrator Mr Fisher was nevertheless appointed.
[25] In a letter dated 28 July 2005 to Mr Ryan (who had in the meantime replaced Mr
Orange) and Mr Callaghan, the solicitors for Northbuild stated their client’s wish to
have all matters of dispute determined in the one forum, by an arbitrator.
[26] The parties then ventilated the question whether Mr Fisher had jurisdiction to
determine VR71 and VR75. The solicitors made submissions to the arbitrator by
letter. On 19 August 2005, the arbitrator made his award, determining that he had
jurisdiction.
Error of law
[27] The arbitrator found that “subject to any binding contract agreed between the
parties”, Northbuild had validly referred the matters to arbitration. He thereby
properly acknowledged the parties’ entitlement to agree on an alternate regime. The
arbitrator concluded however there was no “agreement for the automatic or
unilateral referral” of these disputes for expert determination.
[28] That ruling ignored the circumstances previously set out in this judgment under the
heading “Agreement to refer to experts” (paras [8] to [16]).
[29] The letter of 18 August 2004 from the solicitors for Northbuild recorded the parties’
agreement to commit “the prolongation claim” for expert determination. See para 2,
and the schedule, which refers to “Prolongation claim VR71”. That claim was fed
in, as it were, to the then current facility for expert determination, endorsed under
the agreements reached on 13 August 2004 and 29 September 2004. On 24 August
-- 7 of 12 --
8
2004, those solicitors advised Messrs Orange and Callaghan the parties had agreed
to refer “any disputes relating to time and prolongation” to Mr Lee.
[30] I have already said that the amended VR71 should be regarded as falling within the
scope of the parties’ agreement for expert determination. Likewise, VR75, itself
part of the prolongation claim, falls within the scope of the reference effected on 18
August 2004.
[31] It is true that the schedule to the letter of 18 August 2004 referred only to the then
designation of the prolongation claim, VR71. That reflected the “prolongation
claim” as then understood. If asked, however, the parties would have embraced
within that reference any amended version of VR71, and also the follow on claim,
VR75 relating to sub-contractors and suppliers. That was another foreseeable
expression of the prolongation claim. The parties should, in other words, be
regarded as having committed for expert determination the prolongation claim
comprehensively. Consistently there is the reference in Northbuild’s solicitor’s
letter of 24 August 2004 to Messrs Orange and Callaghan, to the parties’ agreement
to commit “any disputes relating to time and prolongation” to Mr Lee. There is also
para 2 of the letter of 18 August 2004, from the solicitors for Northbuild, referring
to Mr Lee dealing with “the issues relating solely to the calculation of time”. It
would be surprising had the parties intended to commit part of the prolongation
claim for determination under one regime, while contemplating that the balance
might be determined under a different regime.
[32] The arbitrator erred in concluding the parties had not effected the referral of these
issues for expert determination, by means of the agreements reached in August and
September 2004, leading to his determination, erroneous in law, that he had
jurisdiction to determine these disputes. That error amounted to technical
misconduct. The court should set aside the arbitrator’s award of 19 August 2005
determining that he had jurisdiction to hear and determine variation requests 71 (as
amended) and 75.
[33] Mr Dunning pointed out that courts traditionally show deference to arbitration
agreements. That is so, but in this case there was an operative concurrent, or
competing agreement. Where parties separately bind themselves to and have
engaged another regime to govern the determination of particular disputes, that must
be respected.
[34] Acknowledging the parties’ agreement that dispute resolution proceed in a
particular way, then if, as I say, they have engaged that different mechanism, it
would be wrong to adopt a pedantic interpretation with the result of limiting the
matters subject to that particular regime. Accordingly, in the present situation,
where they have agreed that the, in the sense of any, prolongation claim be subject
comprehensively to expert determination, it would not be right to limit that to only
the prolongation claim as formulated and presented by a particular stage.
[35] Mr Dunning submitted that the reference of these issues to expert determination was
not attended by a degree of formality one would expect, comparably for example
with a reference to arbitration (cf. Kudeweh v T & J Kelleher Builders Pty Ltd
[1990] VR 701, 711, 714). The answer to that submission is that the parties, by
their agreement, chose to proceed as they did in relation to the determination of
-- 8 of 12 --
9
these issues, and that was their entitlement. Mr Dunning also raised whether the
expert was clearly seized of the matters committed to him. There seems no doubt
he was. See, for example, Mr Lee’s letter to the solicitors for Northbuild, dated
17 November 2004.
VO90 and VO97
[36] I have referred already to the means by which the issues over the beach houses
provisional sum were referred for expert determination. Northbuild’s solicitors, by
letter of 8 October 2004, acknowledged that those issues were subject to expert
determination, querying only its timing.
[37] On 3 November 2004, Discovery Beach advised Northbuild of what it considered to
be the amount of the relevant reduction, but confirming that the issue was to be
determined by the experts. On 22 November 2004, Discovery Beach’s agent Global
Management Corporation (Qld) Pty Ltd issued VO90, providing for an adjustment
by the amount of $933,664. On 3 December 2004, Northbuild wrote to Discovery
Beach submitting that the issue of VO90 amounted to a breach of the August and
September agreements and the building contract. On 13 December 2004,
Northbuild invited Discovery Beach to withdraw VO90. Discovery Beach did so.
On the advice of its quantity surveyor, Discovery Beach brought that about by
issuing VO97, which “deleted VO90”.
[38] On 21 March 2005, Northbuild gave notice of dispute over the issue of VO97, in the
course of which it inaccurately suggested VO97 operated to “delete works from the
contract”. (All VO97 did was restore the position obtaining before the issue of
VO90.) On 29 April 2005, Northbuild referred that dispute to arbitration, and Mr
Fisher was again appointed as arbitrator.
[39] The solicitors for Discovery Beach submitted that the arbitrator lacked jurisdiction
because the issue had already been committed for expert determination. Discovery
Beach offered in any event to withdraw VO97. The arbitrator ruled that in that case,
he would exclude VO97 from the arbitration otherwise on foot in relation to VR71
and VR75. On 28 July 2005, Discovery Beach confirmed to Northbuild that it
withdrew both VO90 and VO97. The solicitors for Northbuild asserted to the
arbitrator that that “does not necessarily resolve the dispute”. The arbitrator ruled
he had jurisdiction, by his award published on 28 August 2005. The basis was that
it was not established that the issue had been committed to expert determination.
[40] In their submissions of 11 August 2005, the solicitors for Discovery Beach had
taken the arbitrator through the process by which the issues relating to the
provisional sum and the value of the fit out works for the North and South East
Beach Houses had been effectively referred for expert determination. They had
referred in particular to the agreement of 30 September 2004. In their responding
submissions, the solicitors for Northbuild contended that the absence of CFAL
consent to that agreement meant it had not become operative.
[41] In his ruling of 28 August 2005, the arbitrator appears to have held that the
agreement did not become operative because of non-fulfilment of a condition
precedent.
-- 9 of 12 --
10
[42] For reasons already expressed, that result favoured by the arbitrator was contrary to
the subsequent conduct of the parties, which were clearly proceeding on the basis
the agreement was on foot. As examples in addition to those already advanced
(para [17] above), in a letter of 8 October 2004, Northbuild said: “we acknowledge
that the matter is to be referred to expert determination”; and in a letter of 3
December 2004, Northbuild said: “Northbuild is keen to complete the North East
Beach Houses under the terms of the September Agreement.”
[43] The arbitrator had invited a submission from Discovery Beach in response to the
Northbuild submission, and Discovery Beach had chosen simply to rely on
submissions already presented. It seems the arbitrator likely drew from that an
implied concession that the Northbuild submission should be upheld, although that
is not entirely clear. In any case, it is not necessary to explore that aspect further,
because of what I consider to be the arbitrator’s error as to the significance of the
absence of CFAL consent.
[44] The arbitrator erred in law in concluding that he had jurisdiction to deal with the
issues raised in VO97. All of those issues had, for reasons already expressed, been
committed for expert determination by quite separate operative agreement of the
parties. Additionally, with the withdrawal of VO97 (and VO90), there was simply
no live issue which could concern the arbitrator.
[45] Mr Morrison demonstrated by reference to Exhibit 2 that the end result of the
withdrawal of those variation orders was in no way prejudicial to the financial
interests of Northbuild. The question of the adjustment of the provisional sum
simply remained outstanding, to be determined by the experts.
[46] The arbitrator’s award dated 28 August 2005, determining that he had jurisdiction to
hear and determine VO97, should be set aside.
Error on the face of the awards
[47] By wrongly assuming jurisdiction, the arbitrator erred in law. These precedent steps
also involved error in law: misconstruction of the agreement between the parties, as
to what claims were covered; and concluding that the agreement had not come into
effect because of non-fulfilment of what the arbitrator styled a condition precedent.
[48] I have not had to address, in a conclusive way, the question whether, to justify
setting aside an award, the error of law relied on must appear ex facie. Mr Morrison
mounted an argument that to constitute “misconduct” justifying setting aside an
award, as opposed to removing an arbitrator, it need not. The submission focused
on the express reference to “error of law on the face of the award” in s 38 of the
Act. His submission was that the error which I have found occurred, is apparent,
emerging from a consideration of the issues and materials before the arbitrator,
apparent from his published awards, with the materials they incorporate.
[49] He submitted, as to VO97, that the arbitrator wrongly, on the face of his award of
28 August 2005, relied on non-fulfilment of a condition precedent in respect of the
30 September agreement; and as to VR71 and 75, that in his determination of 19
August 2005, the arbitrator erred in law in his expressed conclusion there was no
binding agreement for the referral to expert determination other than within the
-- 10 of 12 --
11
building contract, and in not regarding the amended VR71 and VR75 as part of the
overall prolongation claim committed for that expert determination.
[50] It is not necessary to express final conclusions about the precise extent to which an
arbitrator’s reasons need themselves expose how he fell into error, though on the
traditional approach, to warrant setting aside, my view is they should at least in
broad terms expose that error. I note that Mr Dunning did not submit that were I
satisfied error of law occurred, as contended for by Mr Morrison, that error was not
apparent on the face of the award in any particular respect – that is, that this or that
particular error was not susceptible of demonstration. There were no detailed
submissions of that character.
[51] That aside, this judgment need not depend on establishing ex facie error. That is
because the result of the arbitrator’s approach is that he has taken on jurisdiction
over issues not properly committed to him, in that the parties had effectually, and
patently, reserved them for determination in another arena. That amounted to
“misconduct”, in the technical sense, sufficient to warrant setting aside the awards,
and justifying the exercise of any residual discretion in the court to do so.
Arbitrator’s right to determine jurisdiction
[52] There was no submission made to me that it fell within the arbitrator’s
“jurisdiction” to determine, wrongly, that he had jurisdiction, and that the
applications therefore should fail. For the respondent, the matter was presented, at
least substantially, on the basis that the arbitrator’s conclusions that he had
jurisdiction were justified by the evidence before him and me. I consider they
plainly were not, and it sufficies, to dispose of the applications, to characterize the
arbitrator’s assumption of jurisdiction nevertheless, as an instance of “misconduct”,
in the technical sense, warranting setting aside the awards.
The significance of the parties’ agreement
[53] It is understandable why submissions of that technical character were not actively
pursued in this unusual case. I am referring to submissions as to the need to
establish ex facie error, and as to an arbitrator’s “entitlement” in law to make a
wrong determination on jurisdiction. This is not the case sometimes encountered
where the question is simply whether a dispute has been effectually referred for
arbitration.
[54] This case is distinctive in two important respects: first, it turns on the unavailability
of the (arbitration) referring mechanism itself, where the parties have, as it was put
during argument, “contracted out” of the building contract mechanism; and second,
the determination of the disputes was, by the time of the purported reference to
arbitration, already well under way: all relevant issues had been referred to the
experts, and Mr Lee was substantially advanced in his treatment of the delay aspects
of the prolongation claim. These unusual features combine to bespeak serious error
on the part of an arbitrator then claiming to have jurisdiction to deal with those very
issues.
[55] The ultimate determinant in a matter like this is the parties’ contractual intention.
Here that intention is plain: that these matters be determined by experts, not an
-- 11 of 12 --
12
arbitrator. The case is distinctive and unusual, and not one where the technical
principles sometimes applied to protect and respect arbitrations have application.
Leave to appeal
[56] There is consequently no need to deal with the issue of leave to appeal, which I
acknowledge was, while raised, not the subject of detailed submissions. I should
say that my preliminary inclination, subject to any detailed submissions, would have
been to grant leave to appeal against the arbitrator’s determinations, under s
38(4)(b). That is because there is what seems, to my mind, to be compelling
evidence the arbitrator erred in law (s 38(5)(b)(ii)); the determination of the
question whether the arbitrator has jurisdiction in these matters could substantially
affect the rights of the parties – in a practical sense, especially, because the expert
determination was substantially advanced by the time of the purported referrals to
arbitration (s 38(5)(a)); and a determination upon the right of an arbitrator to assume
jurisdiction in this sort of case, notwithstanding the clarity of the parties’ separately
agreed reference of the issues for expert determination, may add substantially to the
certainty of commercial law in the field of construction contracts (s 38(5)(b)(ii)). In
short, when parties clearly bind themselves to an alternate regime as here, it would
be helpful and constructive for the court to affirm they have placed the jurisdiction
beyond an arbitrator’s reach, notwithstanding the subsequent change of mind of one
of them.
Orders
[57] There will be orders:
1. that the arbitrator’s award of 19 August 2005, determining that he had
jurisdiction to hear and determine variation requests 71 as amended, and 75,
is set aside;
2. that the arbitrator’s award dated 28 August 2005, determining that he had
jurisdiction to hear and determine variation order 97, is set aside;
3. at this stage, costs reserved, with liberty to apply.
-- 12 of 12 --