Eastgate Properties P/L v J Hutchinson P/L [2005] QSC 196
SUPREME COURT OF QUEENSLAND
CITATION: Eastgate Properties P/L v J Hutchinson P/L [2005] QSC 196
PARTIES: EASTGATE PROPERTIES PTY LTD
(ACN 099 706 215)
(plaintiff)
v
J HUTCHINSON PTY LTD
(ACN 009 778 330)
(defendant)
FILE NO: S8870 of 2003
DIVISION: Trial Division
PROCEEDING: Trial
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 30 June 2005
DELIVERED AT: Brisbane
HEARING DATE: 14, 15 and 17 June 2005
JUDGE: Muir J
ORDER:
CATCHWORDS: DEED – ESCROW – ALTERATION OF DEED AFTER
EXECUTION – where deed formulated to remedy defendant
builder’s encroachment of neighbouring lots and plaintiff’s
failure to pay defendant – where meeting took place and
defendant demanded payment of full amount arising under
contract, mortgage and deed – where dispute as to
construction of deed – whether deed abandoned – whether
deed delivered as deed or escrow – whether existence of
condition precedent that prevented deed coming into
existence
MORTGAGES – RIGHTS AND LIABILITIES OF
MORTGAGOR AND MORTGAGEE – where defendant
appointed receivers and managers as a result of plaintiff’s
breach of deed – where plaintiff alleges appointment caused
it loss and damage – whether defendant waived plaintiff’s
breaches of the deed and as a consequence defendant’s action
void – whether moneys paid by plaintiff to defendant moneys
paid under duress and returnable to plaintiff
CONTRACTS – CONSIDERATION – WHAT AMOUNTS
TO CONSIDERATION – EXISTING OBLIGATION OR
-- 1 of 28 --
2
DUTY – where meeting took place between plaintiff and
defendant wherein an oral agreement reached as to operation
of deed – where dispute as to content and effect of agreement
after the event – whether there was a variation of contractual
terms – whether what was promised was an existing
obligation or duty – whether valuable consideration by the
defendant to the plaintiff for the alleged variation
Land Sales Act 1984 (Qld)
Administration of the Territory of Papua and New Guinea v
Daera Guba (1973) 130 CLR 353,
André et Compagnie SA v Marine Transocean Ltd (The
Splendind Sun) [1981] QB 694
Avenhouse v Hornsby Shire Council (1998) 44 NSWLR 1
Bellamy v Debenham (1890) 45 Ch D 481,
Berry v British Transport Commission [1962] 1 QB 306
Central Estates (Belgravia) Ltd v Woolgar [1971] 3 All ER
647,
Cockburn v Edwards (1881)18 Ch D 449,
DTR Nominees Pty Ltd v Mona Homes Pty Ltd (1978) 138
CLR 423
Ficom SA v Sociédad Cadex Ltd [1980] 2 Lloyds Rep 118
Fitzgerald v Masters (1956) 95 CLR 420
Gange v Sullivan (1966) 116 CLR 418
GR Securities Pty Ltd v Baulkham Hills Private Hospital Pty
Ltd (1986) 40 NSWLR 631,
Hobartville Stud Pty Ltd v Union Insurance Co Ltd (1991) 25
NSWLR 358,
Integrated Computer Services Pty Ltd v Digital Equipment
Corp (Aust) Pty Ltd (1988) 5 BPR 11,
Lustre Hosiery Ltd v York (1935) 54 CLR 134,
Marminta Pty Ltd v French [2003] QCA 541,
Masters v Cameron (1954) 91 CLR 353,
Maynard v Goode (1926) 37 CLR 529,
Meates v Attorney-General [1983] NZLR 308,
Monarch Petroleum ML v Citco Australia Petroleum Ltd
[1986] WAR 310,
Paal Wilson & Co A/S v Partenreederei Hannah Blumenthal
(The Hannah Blumenthal) [1983] 1 AC 854,
Pearl Mill Co Ltd v Ivy Tannery Co Ltd [1919] 1 KB 78,
Perri v Coolangatta Investments Pty Ltd (1982) 149 CLR
537,
Sportsvision Australia v Tallglen Pty Ltd (1998) 44 NSWLR
103,
Summers v The Commonwealth (1918) 25 CLR 144,
Suttor v Gundowda Pty Ltd (1950) 81 CLR 418,
Tait v Bonnice [1975] VR 102,
Thomas v Hollier (1984) 156 CLR 152,
Thorby v Goldberg (1964) 112 CLR 597,
Vroon BV v Foster’s Brewing Group [1994] 2 VR 32,
Wigan v Edwards (1973) 47 ALJR 586,
-- 2 of 28 --
3
Young v Tibbets (1912) 14 CLR 114,
Zieme v Gregory [1963] VR 214
COUNSEL: P E Hack SC with A Musgrave for the plaintiff
D R Cooper SC with D Quayle for the defendant
SOLICITORS: Lynch & Company for the plaintiff
MacGillivrays for the defendant
Introduction
[1] The plaintiff owner sues to recover damages allegedly suffered by it as a result of
the defendant builder’s tardy rectification of an encroachment of the building works
onto adjoining land and arising from an allegedly wrongful demand and
appointment of receivers under a mortgage given by the plaintiff to the defendant to
secure the contract price.
[2] The plaintiff is a company formed by its directors Garry Reichert, Ian George and
Revon King for the purpose of acquiring, developing and selling six parcels of land
at Lytton Road, Murarrie (“the Land”). They held all the shares in the capital of the
plaintiff through companies which they respectively controlled. Messrs George and
King, who had the day to day management of the plaintiff and of the subject
development, had a falling out with Mr Reichert which gave rise to difficulties in
obtaining finance. That dispute led to litigation which was commenced on 23 July
2004.
[3] The parcels comprising the Land were amalgamated and re-subdivided into three
freehold titles and a strata title complex consisting of eight units. The defendant
builder was engaged to construct buildings on the site and commenced work at
about the end of August 2002. On or about 6 March 2003, the defendant delivered a
progress claim to the plaintiff for $1,678,944. Before and after the delivery of the
claim, the defendant pressed for the execution of a building contract and Messrs
King and George eventually signed a contract in respect of the works on 20 March
2003. By then the bulk of the works had been completed and their value was some
millions of dollars.
[4] No payment was forthcoming in respect of the progress claim and Mr Quinn,
managing director of the defendant, and Mr Norton, the defendant’s finance
director, met with Mr George to discuss the works and, in particular, how and when
the defendant was to be paid. A considerable number of discussions in that regard
took place between Mr George and Mr Quinn between the end of March 2003 and
28 May 2003 when Messrs Norton and Quinn met with Mr George at the offices of
the plaintiff’s solicitors. Mr Quinn handed over engrossments of the proposed
building contract and of a proposed mortgage over the Land and requested that they
be executed. The former (“the Building Contract”), which provided for a contract
price of $3,785,274, was executed by the parties in the defendant’s office on 29
May 2003. The mortgage (“the Mortgage”) was executed at the same time.
[5] On 11 June 2003 the project certifier issued a certificate of classification for the
building. A copy of it was delivered by the defendant to the plaintiff under cover of
a letter dated 13 June. Under the special conditions in Schedule 2 of the Building
-- 3 of 28 --
4
Contract the plaintiff was obliged to pay “the contract price together with any other
entitlements provided for in [the] contract” within 30 days of 11 June.
[6] Surveyors retained by the plaintiff discovered on 11 June 2003 that the building
constructed by the defendant on the development’s proposed lot 10 encroached onto
an adjoining lot and that the building constructed by the defendant on proposed lot
14 encroached on the common property of two different adjoining bodies corporate.
[7] At about this time, in a telephone conversation, Mr George informed Mr Quinn of
the encroachments and said that they had to be dealt with before payment would be
made, but he added that the defendant should not worry too much about the
encroachments as they were just a logistical matter that “happens all the time”. He
also said words to the effect that the encroachment had saved his [Mr George’s]
“bacon” as the plaintiff had not secured finance and the encroachment issue would
give the plaintiff the further time needed by it. In a letter of 19 June 2003 to the
defendant, Mr George, on behalf of the plaintiff, claimed that the certificate of
classification was invalid as a result of the encroachments and requested
confirmation by the defendant that it would not rely on the certificate of
classification “until such time as the defects within the works have been rectified”.
[8] The encroachments affecting the proposed lot 10 were removed by the defendant by
10 July 2003 leaving the encroachment affecting the proposed lot 14.
[9] Between 19 June 2003 and 6 August 2003, Mr Quinn had a number of discussions
with Mr George concerning the encroachment problem and the moneys outstanding
under the Building Contract. Mr Quinn consistently asserted that the defendant
would fix the encroachment but that its existence did not affect the defendant’s
entitlement to payment. He pressed for payment. Mr George, for his part, was
insisting that the encroachment had to be fixed before payment would be made.
[10] On 4 July 2003, at a meeting between Mr Quinn and Mr George, Mr George
requested Mr Quinn to “hang in there”, saying, in effect, that he and King would
triumph over Reichert and “see the defendant paid”. He said, in effect, that the
encroachment was not “the big ticket item” and that Reichert was the cause of the
real difficulties in the way of payment.
[11] On 6 August 2003 the plaintiff and the defendant entered into a deed with a view to
resolving their difficulties. The Deed recited, inter alia:
(a) The plaintiff’s obligation under the Building Contract to pay to the
defendant the contract price within 30 days of the issue of a
Certificate of Classification to the plaintiff concerning the Estate;
(b) The contract price and agreed variations;
(c) That a certificate of classification dated 12 June 2003 was issued to
the plaintiff;
(d) That the defendant claimed to be entitled to be paid by the plaintiff
$3,957,428 excluding GST on 12 July 2003;
(e) The defendant’s failure to construct the works wholly on the Eastgate
land;
(f) That the plaintiff disputed the defendant’s claim for payment “on the
basis of the encroachment referred to in recital H”; and
(g) That the parties had agreed to “resolve the matter in accordance with
the terms of this deed”.
-- 4 of 28 --
5
[12] The Deed then made provision for:
(a) Payment of $3,785,275 (including GST) by the plaintiff to the
defendant within 21 days of the date of the Deed;
(b) Withdrawal of a caveat lodged over the Land by the defendant;
(c) Rectification of the encroachment and payment by the defendant of
compensation costs and expenses in relation thereto;
(d) Payment of the balance contract price;
(e) The plaintiff to make application for finance in a sum sufficient to
enable the plaintiff to pay the defendant $4,353,171.
[13] “Formal written approval” of such application for finance was to be provided by the
plaintiff to the defendant within 10 business days from the date of the Deed.
[14] In breach of the terms of the Deed the “formal written approval” of the finance
application referred to in clause 5 of the Deed was not obtained from the nominated
financier, the National Australia Bank Ltd, and a copy of such approval was not
provided to the defendant within the time required by clause 5 or at all. Nor did the
plaintiff pay the defendant the sum of $3,785,275 required to be paid by 27 August.
[15] On or about 10 September 2003, the defendant became aware that the plaintiff had
obtained or was in the process of obtaining finance approval in the sum of
$4,821,465 of which $3,785,275 had been earmarked for payment to the defendant.
Mr Norton calculated that there would be a shortfall of approximately $300,000 in
the amount payable to the defendant under the Deed. This prompted the defendant
to serve a notice on the plaintiff on 5 September 2003 demanding payment of
$3,785,275 “which was due on the 27 th August 2003”.
[16] Mr Quinn contacted Mr George and arranged for a meeting to be held at the offices
of Lynch & Co. It may also have been the case that Mr Hutchinson, the defendant’s
Chairman of Directors, made a separate approach to Mr King in that regard.
[17] On 16 September 2003, Messrs Quinn, Hutchinson, Norton and Ms Williams, on
behalf of the defendant, and Messrs King and George on behalf of the plaintiff, met
at the offices of Lynch & Co. Ms Williams was the defendant’s finance manager.
What took place at that meeting is central to the resolution of the major issue in
dispute in these proceedings and is considered in detail later.
[18] On 17 September 2003 the defendant’s solicitors wrote to the plaintiff alleging that
at the meeting the previous day there was agreement that:
(a) The defendant would be paid $4,130,000 from the funds expected to
be drawn down by the plaintiff on 19 September;
(b) The balance of moneys owing under the Deed of $223,171 and
interest of $112,976.42 would be payable on the earlier of there
being sufficient proceeds of sale of land in the Estate to satisfy the
debt or the receipt of a GST refund anticipated by the plaintiff;
(c) The provision by the defendant to the plaintiff of specified
documents would extinguish the former’s obligation under the Deed
to rectify the encroachment.
[19] The Mortgage was lodged for registration on 22 August 2003 and registered on 28
August 2003.
[20] The plaintiff paid the defendant $3,785,275 on 22 September 2003.
-- 5 of 28 --
6
[21] The defendant’s solicitors forwarded a number of documents to the plaintiff’s
solicitors on 25 September and claimed that their provision fulfilled their client’s
obligation to rectify the encroachment.
[22] On 6 October 2003 the defendant served on the plaintiff a demand for payment by
9am on 7 October 2003 of $737,201.35 allegedly owing under the Building
Contract, the Mortgage and the Deed. The demand was not complied with by the
plaintiff and the defendant, on 7 October 2003, appointed receivers in respect of the
Land pursuant to the Mortgage. The deed of appointment recited that the
plaintiff/mortgagor was in default under the Mortgage.
[23] The receivers attempted to take possession of the Land on the date of their
appointment and the plaintiff brought an application to this court to restrain them
from entering into possession and from taking any other steps as receivers and
managers. On 10 October 2003 the receivers undertook to refrain from taking any
steps in relation to the Land as receivers and managers.
[24] By a letter from the defendant’s solicitors to the plaintiff’s solicitors dated 9 January
2004, the defendant demanded payment by the plaintiff of $942,494.71 as a
condition of the release of the Mortgage. That sum was paid under protest by the
plaintiff on 14 January 2004 and the Mortgage was released.
The plaintiff’s claims
[25] In breach of clause 7 of the Deed, the defendant failed to undertake all steps
necessary to rectify the encroachment within 30 days of 6 August 2003.
[26] In consequence of such breach or, alternatively, in consequence of the
encroachment, the plaintiff was unable to register the strata plan in respect of lot 14
until 30 January 2004 and was unable to register a survey plan for lot 12 until 13
November 2003.
[27] But for the encroachment and/or breach of clause 7, the plaintiff would have been
able to register the relevant survey plans no later than 20 June 2003 and would have
been able to effect earlier settlements of a number of contracts of sale of land in the
development.
[28] The appointment of receivers and managers on 7 October 2003 was void and in
consequence thereof the plaintiff suffered loss and damage:
(a) In engaging security guards at a cost of $11,511.50; and
(b) In legal costs of $30,624.10 incurred in proceedings to restrain the
receivers and managers from taking possession and to restrain the
defendant from taking steps to enforce the Mortgage.
[29] The demand on 9 January 2004 by the defendant for payment of $942,494.71 as a
condition of release of the Mortgage was unlawful and the moneys were paid under
protest. Consequently, such moneys are moneys had and received by the defendant
to the use of the plaintiff.
[30] The plaintiff claims in respect of the above matters:
(a) Payment of the sum of $942,494.71;
(b) Payment of the sum of $42,135.60 being the total of $11,511.50 and
$30,624.10; and
(c) $275,373.12 damages for breach of contract.
-- 6 of 28 --
7
[31] It was acknowledged in the course of the trial that $567,896, an amount accepted by
the plaintiff as payable under the Deed, had to be deducted from the sum of
$942,494. The claim advanced for moneys had and received was thus $374,598.
The allegations in the defence
[32] The parties did not comply with the terms of the Deed in a number of substantial
respects and, as a consequence, it was abandoned by no later than 27 August 2003.
[33] Alternatively, the Deed was discharged and no longer bound the parties from a time
no later than 27 August 2003. In the further alternative, it was delivered in escrow
and did not take effect.
[34] Because of the conduct of the plaintiff in: failing to notify the solicitors for the
defendant despite three requests of the amount of stamp duty payable on the
contacts for the sale to the plaintiff of the encroachment lands until on or about 11
February 2004; the delivery of applications for exemption under the Land Sales Act1
to the solicitors for the plaintiff on about 3 September 2003; the delivery to the
solicitors for the plaintiff of the notice of development application for SP157341 on
or about 25 September 2003; and the preparation of reconfiguration plans for the
encroached land by the plaintiff’s surveyors on or about 20 September 2003, the
plaintiff elected to accept performance by the defendant of its obligations pursuant
to the Deed after the time stipulated for such performance and waived compliance
with the strict time limits imposed thereunder.
[35] The plaintiff and the defendant orally varied the terms of the Deed on 16 September
2003 with effect that “upon the provision by the solicitors for the defendant to the
solicitors for the plaintiff of executed contracts between the owners of the
encroached land, as vendors, and the plaintiff, as purchaser, and the other
documents discussed between the parties on 16 September 2003 the defendant’s
obligations pursuant to clause 7 of the …Deed would be deemed discharged”.
[36] The required documents were delivered on 25 September 2003 and the defendant’s
obligations in respect of clause 7 of the Deed ceased.
[37] The conduct of the defendant and the encroachment had no material effect on the
date of registration of the subject strata plans as they were incapable of earlier
registration.
[38] Alternatively, if the strata plans were delayed in registration by reason of the
encroachment, the delay was not caused by the conduct of the defendant but was
caused by the failure of the plaintiff and/or its solicitors to act expeditiously.
[39] The plaintiff was entitled to demand payment of $737,201.35 by virtue of clause 6
of the Deed and the acknowledgement of indebtedness in the sum of $567,896 in a
deed of priority entered into between the plaintiff, the defendant and others on 22
September 2003.
[40] The defendant was entitled to appoint receivers and managers pursuant to the
Mortgage by virtue of breaches of the Deed and pursuant to the deed of priority.
1 1984 (Qld).
-- 7 of 28 --
8
Was the Deed held in escrow pending the obtaining of approval for finance in
accordance with clause 5? – the defendant’s contentions
[41] The defendant contends that although the Deed was delivered it was an escrow and
not delivered as a deed. It was intended to take effect only upon the approval for
finance being obtained under clause 5. The following reasons are advanced in
support of this contention:
(a) The words “… it is a condition of this Deed …” in clause 5 and the
fact that everything else in the Deed is predicated upon its fulfilment;
(b) The knowledge of the parties that the plaintiff had a history of
broken promises concerning the provision of finance; the fact that
moneys under the Building Contract were payable to the defendant
irrespective of whether the encroachments were rectified and the
minor nature of the encroachments;
(c) The Deed imposes mutual obligations the subject of express time
stipulations all preconditioned on funding being available to the
plaintiff. If the Deed took effect as such the defendant would have
been able to wind up the plaintiff within 21 days of the date of the
Deed for an admitted debt; and
(d) Such conditional operation is to be inferred from the terms of the
Deed and in particular the interrelated timings of the various matters
to be performed under the Deed.
Construction of the Deed
[42] Clauses 5, 7, 8 and 9 of the Deed provide:
“5. Eastgate Finance Application
Eastgate shall make formal application for finance in a sum sufficient
to pay Hutchinsons its full claim under the Building Contract of
$4,353,171.00 (including GST) upon the execution of this Deed and
shall keep Hutchinsons informed of the progress of such application.
It is a condition of this Deed that formal written approval to this
application is issued by the National Australia Bank Ltd (‘the
financier’) and a copy of same is provided by Eastgate to
Hutchinsons within ten (10) business days (or sooner), from the Date
of this Deed.
7. Rectification of Encroachment
Hutchinsons shall undertake all such steps as are necessary to rectify
the encroachment referred to in recital H so as to permit the
registration of the strata plan for lots 1-8 cancelling Lot 14 on
proposed SP 146462 and Lots 98 and 99 on proposed SP 157341
(‘the strata plan’) within thirty days of the date hereof and
Hutchinsons shall pay for all compensation, costs, charges and
expenses associated with the rectification of the encroachment
including but not limited to legal fees, registration fees, surveyors
fees and stamp duty.
8. Payment of Balance of Contract Price
Eastgate shall authorise the payment to Hutchinsons directly by its
financier of the balance of the contract price immediately upon
Hutchinson discharging its obligations under Clause 7.
9. No action by Hutchinson
Hutchinsons shall refrain from: -
-- 8 of 28 --
9
(a) registering its mortgage
(b) taking any action against Eastgate pursuant to its
mortgage;
(c) commencing any proceedings or making any
demand upon Eastgate seeking the payment of any
monies under the Building Contract;
- until 21 days after the date of this Deed after which time it shall be
at liberty to take such action as it deems necessary against Eastgate
to recover any monies that it alleges are owing to it by Eastgate
pursuant to the Building Contract.”
[43] The contention that “everything else in the Deed is predicated” upon fulfilment of
clause 5 is not borne out by scrutiny of its terms. Clause 4 obliges the defendant to
give access to the works to the plaintiff “from 27 July 2003”. That provision
operates immediately upon execution of the Deed.
[44] Clause 10 has a similar operation and there would appear to be no good reason why
the obligation in clause 1 should be tied to the performance of obligations under
another clause or clauses. Also, the obligation to pay $3,785,275 in clause 2 is
absolute and not conditional upon finance being obtained. The stipulation in the last
sentence of clause 5 does not operate as a condition precedent. Rather, it makes
plain that, in the event of non-performance of the subject obligations, the defendant
has a right of termination. That is the way terms of this nature are normally
construed.
[45] As Mason J pointed out in Perri v Coolangatta Investments Pty Ltd,2 the court tends
to favour a construction which leads to the conclusion that a particular stipulation is
a condition precedent to performance, as against a construction which leads to a
conclusion that the stipulation is a condition precedent to the formation or existence
of a contract. His Honour observed:
“In most cases it is artificial to say, in the face of the details settled
upon by the parties, that there is no binding contract unless the event
in question happens. Instead, it is appropriate in conformity with the
mutual intention of the parties to say that there is a binding contract
which makes the stipulated event a condition precedent to the duty of
one party, or perhaps of both parties, to perform. Furthermore, it
gives the courts greater scope in determining and adjusting the rights
of the parties. For these reasons the condition will not be construed
as a condition precedent to the formation of a contract unless the
contract read as a whole plainly compels this conclusion.”
[46] Also clauses of this nature are normally construed as provisions entitling the
innocent party to terminate by notice in the event of non-fulfilment. 3
[47] A deed, as the plaintiff contends, may be delivered as an escrow or to be held in
escrow4 but the matters discussed above show that the defendant’s argument that the
Deed was delivered as an escrow is fanciful.
2 (1982) 149 CLR 537 at 552-553.
3 See eg Perri v Coolangatta Investments Pty Ltd at 553; Suttor v Gundowda Pty Ltd (1950) 81 CLR
418 at 440-442; Gange v Sullivan (1966) 116 CLR 418; Zieme v Gregory [1963] VR 214 and Tait v
Bonnice [1975] VR 102.
4 See eg, Monarch Petroleum ML v Citco Australia Petroleum Ltd [1986] WAR 310 at 357.
-- 9 of 28 --
10
[48] In oral argument, it was contended that clause 9 supported the defendant’s
contentions in that, upon the expiration of 21 days from the date of the Deed, the
defendant was entitled, not merely to recover the sum of $4,353,171 claimed by the
defendant but “any moneys that [the defendant] alleges are owing … [under] the
Building Contract”. But it does not appear to me that this clause assists the
defendant. It assumes that the Deed continues to operate after the times provided for
in clause 5 have expired.
[49] There is some difficulty in reconciling clause 9 with other provisions of the Deed,
including clause 8. Clause 9, literally construed, permits the defendant to pursue any
claims open to it in respect of the Building Contract after the expiration of 21 days
from the date of the Deed, irrespective of whether the plaintiff has performed its
obligations under the Deed. It may be faintly arguable that clause 8 makes payment
of the balance of the contract price conditional upon performance by the defendant
of its obligations under clause 7.
[50] Properly construed however, clause 8 has no such effect. Clause 9 requires the
defendant to postpone registering and relying on the mortgage to be granted under
clause 6 and from pursuing the plaintiff further in relation to moneys owing under
the Building Contract for a period of 21 days from the date of the Deed. Clause 8
does not prevent the defendant from requiring payment of the balance contract price
until the requirements of clause 7 have been satisfied. It is a provision linked with
clause 5 and cannot operate if finance is not obtained under that clause. It merely
obliges the plaintiff to facilitate payment in the manner stipulated in the clause once
there is compliance with clause 7. By clause 8, the defendant did not abandon its
long asserted position that its right to payment of the whole of the moneys due
under the Building Contract was not affected by the encroachment. That is made
clear by clause 9.
Was the Deed abandoned by the parties?
[51] The defendant contends that the Deed, if not an escrow, was abandoned within 30
days of 6 August 2003 because of non-compliance with its strict time limits or, if an
escrow, was rendered incapable of becoming binding. 5
[52] In order to show that a contract has been abandoned by conduct, it is generally
necessary to show conduct which gives rise to a clear inference that one party does
not wish to proceed with the contract and that the other has consented6 , or that
neither party intends to perform its obligations under it and does not so perform7 , or
that both parties have not performed their obligations and consider them at an end.8
[53] In determining what inference is to be drawn from the relevant facts regard must be
had to what a reasonable person would conclude from the parties’ words and acts.9
[54] The evidence provides direct support for the conclusion that the parties regarded the
Deed as remaining on foot and that a reasonable person in possession of the relevant
5 Monarch Petroleum ML v Citco Australia Petroleum Ltd [1986] WAR 310 at 357.
6 Marminta Pty Ltd v French [2003] QCA 541 at [21] and [22]
7 DTR Nominees Pty Ltd v Mona Homes Pty Ltd (1978) 138 CLR 423 at 434.
8 Summers v The Commonwealth (1918) 25 CLR 144 at 151-152.
9 André et Compagnie S.A. v Marine Transocean Ltd (The Splendid Sun) [1981] QB 694 at 713 and
Paal Wilson & Co A/S v Partenreederei Hannah Blumenthal (The Hannah Blumenthal) [1983] 1 AC
854 at 915-6.
-- 10 of 28 --
11
facts would have reached a like conclusion. For example, the defendant made
demands under it on 5 September 2003 for payment of the sum of $3,785,275. At
the meeting of 16 September, Mr George spoke in terms of the Deed and no one
asserted that the Deed had ceased to operate. Quite the contrary, Mr Hutchinson was
asserting breach of its provisions by the plaintiff and seeking an assurance about the
way in which the defendant’s obligation under clause 7 might be satisfied. The letter
from the defendant’s solicitors to the plaintiff of 17 September 2003 acknowledges
the continued operation of the Deed as does another such letter of 19 September
2003.
[55] Additionally, a demand for payment made by the defendant on 6 October 2003 was
made in reliance, inter alia, on the Deed. There was no abandonment of the Deed at
relevant times.
Were the receivers duly appointed?
[56] The Mortgage secured $3,997,960 and moneys due and payable from time to time
by the plaintiff to the defendant under the Building Contract. The Building Contract
was described in the schedule as being “a Collateral Document” but elsewhere in
the schedule 10 “Collateral Documents” was defined so as to include any “… Deed,
or other agreement under which any Debtor either alone or together with any other
person agrees with the Mortgagee in any way”. The term “Debtor” included
reference to the plaintiff. Accordingly, the Deed is a “Collateral Document” for the
purposes of the Mortgage.
[57] Under clause 6.1 there is an event of default where: the plaintiff defaults in the
performance of any term in the Mortgage or in any collateral document;11 any
indebtedness or obligation of the plaintiff to the defendant is not met when due;12 or
the plaintiff breaches any undertaking given to the defendant or “any condition
imposed by [the defendant] in agreeing to anything”.13
[58] Clause 6.2 empowers the mortgagee, in the event of default, to demand and require
immediate payment of the mortgage debt and to appoint receivers to the mortgaged
land “despite any omission, neglect, delay or waiver of the right to exercise the
option [to exercise rights under clause 6.2] and without liability for loss”.
[59] There had been breaches by the plaintiff of clauses 2 and 5 of the Deed. It is argued
on behalf of the plaintiff that these breaches were waived. I doubt that this was so in
either case. The defendant did not act on them to terminate the Deed and there was a
waiver in that limited sense, but the breaches had been committed and gave rise to
claims by the defendant for damages for breach of contract. The obtaining of
approval for finance did not cease to be of relevance, as without it, clause 8 could
not operate. Even apart from these matters, interest under the Building Contract
accrues daily on moneys owed but unpaid and the interest must be paid on the last
day of each month. Clause N 15.3 provides:
“The interest is calculated daily, from the date the money should
have been paid. The interest must be paid on the last day of each
month. If interest due on the last day of a month is not paid, it is
immediately capitalised and added to the money outstanding.”
10 Clause 1.1.
11 Clause 6.1(a)
12 Clause 6.1(b).
13 Clause 6.1(k).
-- 11 of 28 --
12
[60] By operation of clause 9 of the Deed, the defendant became free to claim interest on
any unpaid portion of the moneys due under the Building Contract as from 12 July
2003, 30 days from the date of issue of the certificate of classification. Even if,
contrary to my view, the defendant could not, by virtue of clauses 7 and 8, charge
interest on the balance contract sum of $567,896, there would appear to be no good
reason why it could not claim and recover interest on the sum of $3,785,275 until its
payment on 22 September 2003. Under clause 9 the defendant also became entitled
to pursue its claims for $3,785,275 and the balance of the contract price.
[61] For the above reasons, I find that the plaintiff’s claims concerning the appointment
of receivers cannot be made out.
[62] The nature of the claims advanced, however, call for additional comment. The
plaintiff claims in respect of the appointment of receivers:
(a) $11,511.50 paid to a security service to secure the premises from the
intrusion of receivers; and
(b) $30,624.10 by way of legal costs incurred in relation to the
appointment of the receivers.
[63] The legal fees appear to relate to costs incurred in interlocutory steps in these
proceedings. Mr Graham, a costs assessor who made an assessment of the subject
fees, swore to his assessment being in respect of “file number 03156 (‘litigation
file’) to determine the solicitor and own client legal fees and costs incurred by the
plaintiff in proceedings to restrain the receivers and managers from taking
possession of the Eastgate land and to restrain the defendant from taking steps to
enforce its mortgage”. No authority was cited by the plaintiff for the proposition
that a party to a proceeding may recover costs in the proceeding as a head of
damage and the proposition is inconsistent with authority. 14
Was any loss suffered through the defendant’s delay in removing the
encroachment? – the contention that no sales of any lots could have been
effected until release of the defendant’s mortgage and resolution of the dispute
with Reichert - the plaintiff’s argument
[64] The defendant contends that, as at 12 June 2003, the plaintiff had not secured
funding to meet its obligations to the defendant and that there was no prospect of it
doing so by early July 2003. The principal reason, it is said, for such inability was
the dispute with Reichert which was not resolved until 6 August 2003. It is further
submitted that the encroachment did not have any material effect on the ability of
the plaintiff to secure funding and that this is borne out by the fact that finance was
secured once that dispute was resolved.
[65] The inability to secure finance meant that the earliest the plaintiff could have sold
lots in the land affected by the encroachment was late September 2003, but the
defendant had its Mortgage over that land supported by a consent caveat. It would
not have permitted any sales to occur until it was paid and Yellowrock Pty Ltd
(“Yellowrock”) would also have insisted on payment out of its mortgage. The
encroachment is a red herring. That is how it was always regarded by Mr
Hutchinson.
14 Cockburn v Edwards (1881)18 Ch D 449; Hobartville Stud Pty Ltd v Union Insurance Ltd (1991) 25
NSWLR 358 at 365; Berry v British Transport Commission [1962] 1 QB 306 and Avenhouse v
Hornsby Shire Council (1998) 44 NSWLR 1 at 33-37.
-- 12 of 28 --
13
Consideration of the plaintiff’s argument
[66] It is reasonably clear that the dispute with Reichert made it difficult for the plaintiff
to secure finance and I find that until the dispute was resolved substantially on about
6 August 2003 the plaintiff was seriously handicapped in its ability to secure
finance. Even if finance could have been obtained, it is probable that there would
have been considerable delays. In one of his affidavits Mr George swore:
“There was little point in resolving the encroachment problem with
the defendant unless the dispute with Yellowrock could also be
settled so that the existing titles could be utilised as security for
finance.”
[67] The deed of compromise entered into on 6 August 2003 between Yellowrock,
Reichert, George, King and their respective companies and Eastgate Properties Pty
Ltd (“Eastgate”) contemplated that Yellowrock be repaid out of sales of lots in the
estate after payment to the defendant of $4,353,171, payment by Eastgate to any of
the parties to the deed of compromise of any sums expended by such parties for the
benefit of Eastgate and payment by Eastgate of its costs, charges and its expenses in
developing the Estate.
[68] Despite the entering into of the deed of compromise, troubles with Mr Reichert
continued. It was a term of the loan agreement for the finance negotiated with
Australian Unity Funds Management Limited that Mr Reichert give a guarantee.
He declined to do so. Yellowrock registered its mortgage after entering into the
deed of compromise and that also stood in the way of finance. Messrs King and
George alleged that this was in breach of the terms of the deed of compromise,
[69] On 19 September 2003 the plaintiff instructed its solicitors to commence
proceedings against Yellowrock for specific performance of the deed of
compromise to enable the refinancing to proceed. An accommodation with
Yellowrock was reached that day and the refinancing proceeded.
[70] The evidence of the surveyor Mr O’Brien shows that the subject plans were not
lodged with the Council until 31 July 2003. The plaintiff in June, July, August and
for much of September 2003 had insufficient funds to discharge its obligations to
the defendant and Yellowrock. The plaintiff’s contention that the defendant was not
entitled to payment under the Deed or under the Building Contract until the
encroachment was removed is erroneous. Because of the dispute with Mr Reichert,
which was not compromised until 6 August 2003, and because of the defendant’s
entitlement to payment secured by the Mortgage, the plaintiff was not in a position
to settle sales of land in the Estate other than on terms dictated by the defendant and
Yellowrock.
[71] The evidence suggests that Mr Reichert would not have abandoned readily a means
of bringing pressure to bear on Messrs George and King, and there is no doubt that
the defendant was most anxious to secure payment. It is likely that the defendant
would have required any proceeds of sale to be applied in satisfaction of the
plaintiff’s obligations to it in consideration of any partial release of the Mortgage.
The consequences of these findings are discussed later.
The 16 September 2003 meeting – introductory observations
-- 13 of 28 --
14
[72] There is considerable controversy as to precisely what was said in some critical
respects in the course of the meeting on 16 September. There is general agreement,
however, between the witnesses as to what happened in the first part of the meeting.
Mr Hutchinson and Mr George were the most active participants. Mr Hutchinson
expressed concern about the plaintiff’s ability to pay all of the moneys payable to
the defendant in respect of the works and asked how the plaintiff intended to
comply with its obligations under the Deed. He said that the defendant would be
presenting an account for about $250,000 on account of interest and legal costs and
asked how the plaintiff was going to pay those moneys. The discussion became
heated. Mr Hutchinson threatened the appointment of receivers to the plaintiff and
said words to the effect that he was having receivership documents delivered, to
which Mr George responded with words to the effect, “If that’s what you want to do
serve your documents. Bring it on”.
[73] Mr Hutchinson left the room for a while to speak to the defendant’s solicitors over
the telephone. In his absence, there was discussion between those remaining about
the defendant’s interest calculations.
[74] After Mr Hutchinson’s return to the meeting the defendant’s obligations to remedy
the encroachment was discussed. Mr Hutchinson pressed Mr George to identify
precisely what matters were required to satisfy the defendant’s obligations under the
Deed in that regard.
[75] The critical difference between the competing versions of the conversations given
by those present at the meeting is whether, as the defendant contends, Mr George
agreed that the provision of certain documents would satisfy the defendant’s
obligations under the Deed or whether, as the plaintiff asserts, Mr George continued
to insist on compliance with the terms of the Deed. Also of relevance is whether
there was agreement varying the components of the contract price payable under the
Deed and agreement on the right of the defendant to be paid interest on the moneys
outstanding under the Building Contract.
Mr George’s account of the meeting
[76] After Mr Hutchinson’s return to the meeting, his conduct was more conciliatory.
There was discussion about costs and interest. Mr George rejected the prospect of
the plaintiff paying any of the defendant’s legal costs, but asked Mr King whether
he would be happy to consider the interest claim. Mr King replied in the affirmative.
Further recalculations were made by Mr Norton. Discussion then returned to “the
impending refinance” of the defendant with Mr Hutchinson saying he wanted to
establish the moneys available to the defendant as a result of it. Mr Hutchinson
pressed for the plaintiff’s agreement to pay the defendant $4,130,000 on settlement
of the “refinance transaction” but Mr George insisted that payments would have to
be made in accordance with the Deed, asserting that the balance of moneys payable
under the Deed were not yet due.
[77] Mr Hutchinson then explained the current state of affairs relating to rectification of
the easement and said that he was waiting for contracts from the bodies corporate
which would not be available until “Thursday at the earliest” but that “he had got
everything else done”. Mr Hutchinson asked for agreement that “if he supplied all
of the rectification documents together with the contracts that this would satisfy [the
defendant’s] obligations under the Deed”. Mr George said:
-- 14 of 28 --
15
“Provided that we have all of the documents required to be lodged in
registrable form I would not require Hutchinsons to wait until all the
plans had registered in order to satisfy their obligations and that it
was not our intention to treat Hutchinsons harshly or unfairly in
relation to the rectification of the encroachment.”
Mr Hutchinson said words to the effect: “OK, that’s fine”.
[78] Towards the end of the meeting, Mr Hutchinson again pressed for confirmation that
the defendant would be entitled to interest and to payment of $4.13 million from the
plaintiff when the encroachment was fixed. Mr George responded that the plaintiff
“would be proceeding in accordance with the Deed”
[79] In cross-examination, Mr George agreed that Mr Hutchinson may have said that he
could get the material required to rectify the encroachment to him by the end of the
following week. He subsequently said that he did not deny that this was said but had
no recollection of it.
Mr King’s version
[80] In his affidavit evidence Mr King said, in substance, that he had read Mr George’s
affidavit and was in agreement with Mr George’s account of events. In oral
evidence he said that he had re-read Mr George’s affidavit prior to the trial. He
agreed that Mr George said at the meeting that “he would pay $4.13 million from
the drawdown”. He accepted that the drawdown was due on about 22 September
and that Mr Hutchinson was insistent “about being told what it was that was
required of him to rectify the encroachment”.
[81] He professed a recollection of Mr George saying “on a couple of occasions… we
would like you to comply with the Deed and we want everything done within the
Deed”. He also professed a recollection of Mr George saying “on a number of
occasions”, “we want you to stick to the Deed”.
[82] He agreed with the proposition put to him in cross-examination that “Mr
Hutchinson said to you that all the documents that we have been discussing would
be available to be given to your company by the end of the following week because
the body corporate meetings were being held on the 24 or 25 of September”. The
documents to which the question referred were minutes of meetings of the bodies
corporate which owned the land the subject of the encroachment, subdivisional
plans capable of registration and possibly, an exemption from the requirements of
the Land Sales Act 1984 (Qld) or from stamp duty. He also answered “yes” to the
question “…he did say, that he’d give you the documents you needed by the end of
the following week”.
Mr Quinn’s account
[83] Mr Hutchinson pressed for “some clear indication of what was going to be made
available to the defendant at settlement”. Mr George responded that the Deed
required the defendant to rectify the encroachment and that had not yet occurred. Mr
Hutchinson queried what was required under the Deed and discussion ensued. Mr
Hutchinson pressed Mr George to be specific as to what was needed to meet the
defendant’s requirements in relation to encroachment, in response to which Mr
George said words to the effect, “the things we need are the signed contracts from
the adjoining owners and the signed subdivisional plans and perhaps the stamp duty
-- 15 of 28 --
16
exemption documents …”. Mr George stated that the subdivisional plans must be in
registrable form. Mr George confirmed that “once those things were available the
defendant’s obligations under the Deed would have been discharged”.
[84] Mr George agreed that the plaintiff pay $4,130,000 by 19 September 2003 and
$223,171 by 25 September 2003. In cross-examination Mr Quinn said that the latter
payment was conditional upon provision of “the encroachment documents”
[85] In his oral evidence, Mr Quinn said that at one stage of the meeting Mr George said
words to the effect that he would be happy to consider a claim for interest but at the
end of the meeting agreed to pay the interest at the conclusion of the project.
[86] He said that Mr Hutchinson on three or four occasions insisted “that we clearly
identify what was required to ensure that Hutchinsons had fulfilled its obligations
under the Deed” and that in response Mr George confirmed that what was required
was signed contracts from the adjoining owners and signed subdivisional plans.
[87] He added that on one occasion or possibly two prior to the end of the meeting he
summarised what was required in that regard and that “we all left the meeting in
agreement”.
[88] Mr Quinn conceded that on the basis of his understanding of how interest should be
calculated the amount payable by the plaintiff would have been $47,315 rather than
the $112,976 now claimed to be the agreed sum.15 Mr Quinn made a note in the
course of the meeting in which, under the heading “Outcome” he wrote:
“$4,130,000 (Friday)
$ 223,171 (25/9/03)
$4,353,171 (Total under Deed)
* out of proceeds of Eastgate sales)
(ie first sale) ) waiting approx 6 weeks
or ) (i.e. end Oct)”
upon receipt of GST )
[89] At the top of the page linked to the writing “(25/9/03)”, by a line, he wrote;
“* signed contracts
* signed subdivisional plans
* application for exemption from “Stamp Duty”.”
Mr Quinn explained in cross-examination that this asterisked list was of “the
documents that were required to satisfy the encroachment issue”.
Mr Norton’s evidence
[90] In his affidavit evidence Mr Norton said that at a time at which Mr Hutchinson was
absent from the meeting, Mr George said that $4,130,000 would be available to the
defendant from the finance to be provided by Perpetual Trustees and that the
balance payable under the Building Contract would be paid either from a GST
refund which the plaintiff expected to receive soon or out of the proceeds of
settlement of the first contract of sale of a lot in the Estate.
15 T 109.
-- 16 of 28 --
17
[91] Mr Hutchinson pressed Mr George to specify what was required in relation to the
encroachment. “Mr George answered to the effect that if the defendant provided the
contracts of sale and the subdivisional plans, the plaintiff would be satisfied”.
[92] Mr Norton made a note at the time of the meeting in which he made various interest
calculations which showed interest on the sum of $3,957,428 from 30/7/03 to
19/9/03 totalling $112,976.41. The note also contained this writing:
“Original amount % $4,358,171
Available $4,130,000
$228,171
payable 19/9/03
out of GST payment and or
first sale proceeds on or
before 31/10/03
Interest by the end of
November.”
[93] In the course of the meeting, Mr Quinn wrote on the top of the page on which
contained the above writing:
“Theoretically, shouldn’t it apply from 27 August to date of
settlement (ie 1 mth)
Shouldn’t interest (%) be
15% ÷ 3785275
÷ 12.”
[94] Mr Quinn accepted in the course of cross-examination that the figure of $3,785,275
was the figure required to be paid by clause 6 of the Deed and that the date was the
date by which such moneys were payable under the Deed.
[95] Mr Norton did not mention in his affidavit any agreement to pay interest being
reached at the meeting of 16 September, but in cross-examination he asserted a
recollection of such an agreement. Mr Norton disagreed with Mr Quinn’s
understanding of how the interest should be calculated. He regarded it as payable
under the Building Contract from a date 30 days from the date of issue of the
certification of classification. He accepted that in the course of the meeting, Mr
George said words to the effect that the plaintiff was placing reliance on the Deed.
[96] Mr Hutchinson asked on numerous occasions about what was required to fulfil the
defendant’s obligations in relation to the encroachment. Mr George replied “if you
give me the contracts of sale together with the subdivisional plans that would be
sufficient”.
[97] The balance moneys of $223,000 were to be paid from sales of property or from the
GST refund to be received no later than 31 October.
[98] The sum of $4,130,000 was to be paid on 19 September.
Ms Williams’ Evidence
[99] Ms Williams, in her affidavit evidence, recalls discussion about “interest payable
under the Building Contract”. Mr Norton made some calculations in that regard
which Mr George rejected. “The question of interest was left on the basis that the
plaintiff would consider any claim for interest payable under the Building
Contract.” She recalls Mr Hutchinson saying that the defendant wanted to be paid
-- 17 of 28 --
18
for $4,130,000 when the loan settlement occurred and his asking Mr George what
was to be done for the balance. Mr George replied that the balance of $223,171
would be paid to the defendant either from a GST refund which Mr George said was
due on or about 31 October 2003 or from proceeds of sale of some of the lots.
[100] She wrote a diary note at the time of a meeting. Under the heading “Outstanding
Items:-” appeared:
“- interest
- legal fees
- holding funds in trust. – how is this?”
[101] Further on in the note she wrote:
“Settlement $4,130,000
Balance $ 223,171
$4,353,171
23-25 Sept repayment due
c return GST – 6 weeks say
31/10/03
dsales proceeds – 7 days after titles
issued”
[102] She explained that the “Outstanding items” part of the document was written whilst
the meeting was in progress. The day after the meeting, Ms Williams wrote a file
note in respect of the meeting which stated, inter alia:
“In summary the following was agreed:
. At settlement we received $4,130,000
. deed of priority to cover the balance which is:
. $223,171 (remaining under the deed)
. $112,946 (interest under the Building Contract to
9/9/2003)
$336,117”
[103] Mr George said that interest calculated by Mr Norton was far too high and that “he
would consider interest as per the Building Contract”. She recalls agreement as to
the payment of $4.13 million on settlement with the balance to be paid out of
settlement proceeds or from a GST payment due on 31 October. She does not recall
Mr George saying that the drawdown would be made in accordance with the Deed.
Mr Hutchinson’s account
[104] Mr Hutchinson recalls that after he returned to the meeting, having made a
telephone call or telephone calls, he said words to the effect, “You guys can’t meet
the conditions of the Deed … You can’t pay us. What are you going to do?” He
demanded to know what moneys the plaintiff was going to receive from the
drawdown of funds from Perpetual Trustees. There was discussion around this point
and he said that the defendant wanted the $4.13 million which Mr George had said
was becoming available. He asked Mr George what was needed to meet the
defendant’s obligations under the Deed and was told that it would be sufficient if
the defendant provided the contracts of sale for the encroached areas and the
subdivisional plans in registrable form. Mr George affirmed that when those things
were provided the defendant’s “obligations will be at an end”. Mr Hutchinson said
that all of the material would be available by the end of the following week.
-- 18 of 28 --
19
[105] He concedes that Mr George said words to the effect that he was happy to consider
the payment of interest.16 He does not recall Mr George saying words to the effect
that the Deed covers what the defendant is to receive on settlement. In response to
the question “He certainly said throughout the meeting that he was placing reliance
on the terms of the Deed”. He responded, “I don’t think that’s correct. He had to not
place reliance on the terms of the Deed because he couldn’t meet it”.
[106] In pressing Mr George on what was required to satisfy the defendant’s obligations
in relation to encroachments under the Deed, he was “trying to make sure that … we
were supplying exactly what [Mr George] wanted to meet that deed… He said the
two things he wanted, not all of the documents, he wanted the contracts for the sale
of the land and he wanted the subdivisional plans in registrable form”.
[107] In relation to the interest question, he said “I saw Steve [Norton] and Greg [Quinn]
doing calculations and sorting it out with Ian and then they … said it was sorted
out”.
The parties’ communications after the meeting
[108] The morning after the meeting, Mr Quinn, together with Mr Norton and Ms
Williams, had a conference call with their solicitor, Mr McLeod of MacGillivrays,
in which they instructed him as to the contents of the consensus reached at the
meeting. Those instructions were contained in a letter dated 17 September from
MacGillivrays to Mr George.
[109] The letter asserted that agreement had been reached at the meeting on five matters,
each of which was addressed in a separate numbered paragraph. Paragraph 1 states
that $4,130,000 was to be paid at the settlement of the drawdown of the plaintiff’s
loan funds “anticipated for Thursday or Friday of this week”. Paragraphs 2 and 4
provided that the balance of the moneys payable under the Deed, plus interest of
$112,976.42 calculated up to 19 September, would be payable on the earlier of
settlement of the “required number of sales to repay the balance moneys … after the
first mortgagee takes 55% of the sale price in each transaction” and the receipt of
GST refund moneys “from the ATO relating to this project”.
[110] Paragraph 3 provides:
“On and from the drawdown of funds, interest will continue to be
payable on any unpaid monies at the rate prescribed under the
Building Contract.”
[111] In respect of the encroachment problem, paragraph 5 provides:
“Your company has agreed, that upon the relevant meetings of the
bodies corporate taking place (set at the 24 th and 25th of this month),
in relation to authorising the execution of the Contracts dealing with
the encroached land (and all ancillary documents) and those
documents being provided to your solicitors, your client will be
deemed to have discharged its obligations under clause 7 of the Deed
between your Company and our client. Your Company will then take
responsibility for finalising both of those transactions. Our client will
pay any disbursements within 48 hours of being requested to do so
…”
16 T 137.
-- 19 of 28 --
20
[112] Contrary to the letter, Mr Quinn confirmed in cross-examination that the payment of
$223,171 was dependent on provision of the encroachment documents by 25
September.17
[113] The plaintiff’s solicitors communicated with the defendant’s solicitors on 18
September 2003 by a facsimile transmission which contained a demand that the
defendant release its mortgage as “the refinance transaction is due to be completed
at 12 noon tomorrow” and threatened legal proceedings. No mention was made of
the 17 September letter or of the assertions in it.
[114] The solicitors for the plaintiff responded to the 17 September letter in a letter of 22
September written on Mr George’s instructions. The letter denied that agreement
had been reached “on items 1, 2 and 3” in the letter. It was asserted that what was
agreed was that “settlement of the draw down would proceed in accordance with the
deeds that are drawn between your client and the company”. There was the further
explanation that:
“It would not be possible for our clients to vary the arrangements of
these deeds without a meeting of the company resulting in a
resolution of the Board of Directors to vary these arrangements.
With regard to payment to your client of $4,130,000 our client was
asked to hazard an estimate of how much would be available from
the advance in surplus funds, assuming settlement of the advance by
19 September 2003.”
The letter did not refer expressly to item 5 in the plaintiff’s solicitor’s letter.
[115] On 25 September 2003 the defendant’s solicitors under cover of two letters of that
date provided the plaintiff’s solicitors with contracts for the sale of the land the
subject of the encroachment, transfer documents, survey plans, notices of
Development Application, moneys on account of anticipated Brisbane City Council
fees and moneys on account of applications for exemption under the Land Sales
Act18.
[116] The letter asserted that the documents provided discharged the defendant’s
obligations under clause 7 of the Deed. The plaintiff’s solicitors wrote back on 29
September stating that the defendant’s obligation “under clause 8 (sic) of the Deed
was to rectify the encroachment”. The defendant’s solicitors responded to that letter
on 1 October 2003 reaffirming the defendant’s position in relation to the agreement
alleged by it.
Consideration on the defendant’s contentions as to the alleged encroachment
agreement
[117] In addresses much was made by counsel for the defendant of the failure of the
plaintiff’s solicitors to specifically refute the assertions of agreement in the
defendant’s solicitor’s letters of 17 September and 1 October. It is submitted that
this failure, unexplained by evidence, “constitutes an admission that the agreement
contended for in the letter of 17 September 2003 was struck”. Lustre Hosiery Pty
Ltd v York,19 Young v Tibbetts20 and Thomas v Hollier21 are cited as authority for the
proposition.
17 T 112.
18 1984 (Qld).
19 (1935) 54 CLR 134 at 143.
-- 20 of 28 --
21
[118] The 1 October letter is of no moment for present purposes. The plaintiff’s solicitor’s
letter of 29 September clearly denied the existence of the agreement alleged by the
defendant and there was no need to repeat the denial in every subsequent item of
correspondence.
[119] The failure of the plaintiff’s solicitor’s letter of 22 September to expressly respond
to the allegation of an agreement concerning clause 7, however, does provide some
support for the defendant’s case. So too does the delay in responding to the
allegations in the 17 September letter despite the plaintiff’s solicitors having written
to the defendant’s solicitors on 18 September, as the matters raised in the 17
September letter were highly pertinent to the distribution of funds expected to
become available on the drawdown expected on 22 September.
[120] A possible explanation for the lack of a specific response to the allegations of an
agreement concerning the encroachment is the assertion in the 22 September letter
that the “arrangements of these deeds could not be varied without a meeting of the
company…”. It is curious though that the letter of 22 September, whilst specifically
addressing payments to be made after drawdown of the loan and the accruing of
interest, did not address the encroachment matter, which also concerned obligations
which continued after the drawdown. A possible further explanation is that Messrs
King and George did not regard the encroachment and the manner of its removal as
being of much importance in the scheme of things. That conclusion also adds some
support to the defendant’s case.
[121] The 17 September letter would have assisted to the plaintiff’s argument more if
paragraph 5 had stated more precisely what Mr Quinn recorded during the meeting
of 16 September as being the contents of the agreement in relation to the
encroachment. The letter makes no reference to signed subdivisional plans or any
application for exemption from stamp duty, unless these documents come within the
expression “ancillary documents”.
[122] An additional argument advanced on behalf of the defendant is that the plaintiff’s
conduct after 1 October 2003 is consistent with the existence of the agreement
alleged by the defendant. On or about that date, the plaintiff’s solicitors took over
the work of obtaining and registering all documents necessary to bring about the
extinguishment of the encroachment. It is submitted that it is inconceivable that, if
the agreement for which the defendant contends was not made at the 16 September
meeting, there would not have been strident complaints and even court proceedings
by the plaintiff to enforce the defendant’s compliance with its obligations.
[123] There is little force in this argument. The defendant, by its solicitor’s letters of 25
September 2003, made it plain that the defendant was asserting that its obligations
under clause 7 of the Deed were at an end. A letter from the plaintiff’s solicitors of
29 September 2003 asserted the plaintiff’s position in relation to clause 7, set out in
some detail the losses which the plaintiff contended would flow from the
defendant’s breach and stated: “We urge your client to resolve the encroachment
problem on an urgent basis”. The defendant’s response in its solicitor’s letter of 1
October 2003 was to reaffirm the defendant’s contention that it had no further
obligations under clause 7 and to suggest that the plaintiff “immediately proceeds
(sic) with the purchase transactions, as agreed” in order to mitigate further losses.
20 (1912) 14 CLR 114 at 121, 122.
21 (1984) 156 CLR 152 at 157.
-- 21 of 28 --
22
The plaintiff thus had no reason to believe that the defendant would take any further
steps to perform obligations in accordance with the unvaried form of clause 7.
The plaintiff’s case in relation to the alleged encroachment agreement.
[124] The following matters are the most significant of those put forward as reasons
militating against a finding in favour of the defendant.
1. The unlikelihood that there would be such an agreement, having regard to
the disagreement with Mr Reichert who was not present at the meeting and
the assertion in the letter of 22 September that a meeting of the Board of
Directors was necessary to vary “the arrangements of these deeds”;
2. The unlikelihood that Messrs King and George would have abandoned an
agreement generous to Eastgate by virtue of the fact that it deferred the
obligation to pay $567,896 until Hutchinson had rectified the encroachment.
That concession would have exposed Eastgate “to the real risk of being in
default and the appointment of receivers without getting any benefit in
return”;
3. Neither Mr George nor Mr King disputes the fact that there was a discussion
about the documents required to remove the encroachment but their
evidence does not support the existence of the alleged agreement. Nor does
the evidence of any of the defendant’s witnesses. The most useful
documentary evidence in support of the defendant’s case is Mr Quinn’s
diary note which makes reference to three categories of documents but it
does not state the fact of agreement;
4. Mr Quinn’s professed recollection is suspect having regard to the “scant
detail in his affidavit of 10 October 2003” in which he addressed the issue of
the agreements allegedly made in the 16 October meeting but did not refer
expressly to the encroachment agreement;
5. The evidence in relation to the alleged agreement as to liability to pay
interest is inconsistent and does not support the existence of such an
agreement. Its relevance is that it highlights the absence of consensus
amongst the defendant’s witnesses on a topic of “perhaps equal importance
and makes it impossible to accept … the much greater unanimity between
the [defendant’s] witnesses on the encroachment aspect of the conversation
at the meeting”;
6. Ms Williams, while asserting the existence of such an agreement, cannot
give the substance of any relevant conversation and does not refer to the
agreement in her detailed diary note of 17 September;
7. Even if there was an agreement such as that alleged, it is not supported by
valuable consideration moving from the defendant to the plaintiff.
Consideration of the plaintiff’s arguments
[125] I do not consider that there is much force in the points made in relation to Mr
Reichert or the want of a board meeting. By the time of the meeting, the deed of
compromise had been entered into or was about to be executed. At the end of the
meeting, Mr Hutchinson asked “what about Reichert’s mortgage” to which Mr
George responded that he would “get it off” by court proceedings if necessary and
that he would “sort that out”. The evidence does not establish that at this stage of
the affairs of Eastgate the directors were holding formal meetings of the Board or,
for that matter, involving Mr Reichert in deliberations such as those under
consideration.
-- 22 of 28 --
23
[126] The unlikelihood of Eastgate’s giving up the advantage of deferring payment of
$567,896 until the defendant’s compliance with clause 7 (if such advantage existed)
may be explicable by the evidence which strongly suggests that Mr George did not
regard the encroachment as presenting any particular problem. It is likely that he
saw it as more of a bargaining chip. There is no evidence that Mr King regarded the
encroachment as being particularly problematic or detrimental to Eastgate’s
interests. I think it likely that discussion at the meeting persuaded Messrs George
and King that the production of the documents necessary to cure the encroachment
problem was imminent and that nothing more than a few formalities were required.
They were put under considerable pressure in the course of the meeting. They had
been stalling in respect of Eastgate’s obligations to make payments to the defendant
for many months. Eventually, they were forced to enter into the Building Contract.
Subsequently, they executed the Deed and by the time of the meeting Eastgate was
in substantial breach of its obligations under it. Mr Hutchinson was threatening to
appoint receivers to Eastgate and that threat was no doubt perceived by Messrs
George and King as both real and imminent. I consider it unlikely that Messrs
George and King did not have real concerns that, despite Mr George’s display of
bravado, the defendant would act on the threat unless it emerged from the meeting
with some concrete assurances concerning payment of the outstanding moneys.
[127] It was not the case that the defendant was unable to obtain payment of the balance
contract price and other moneys owing to it without satisfying its obligations under
clause 7 of the Deed. The defendant had its rights under clause 9. Clause 8
conferred no benefit on the defendant if, as appeared to be the case, there were no
further loan moneys to be drawn down from which the balance contract price could
be paid.
[128] I do not consider that Mr Quinn’s cursory treatment in his affidavit of 10 October
2003 of conversations in the 16 September meeting is of much significance. His
evidence was that the affidavit was completed as a matter of urgency and reference
to it reveals that he took the course of swearing to the contents of the meeting by
affirming the allegations in the defendant’s solicitor’s letter of 17 September.
[129] I accept that there is a degree of inconsistency between the accounts of witnesses
called on behalf of the defendant concerning the alleged agreement to pay interest.
Although I accept that some of the defendant’s representatives believed that there
was an agreement as to the payment of interest, I am not confident that any such
agreement was reached. I think it probable, however, that Mr George made a
number of conciliatory assertions about the payment of interest so as to lead those
present to the view that a claim for interest would not present a difficulty. The fact
that an agreement in that respect was alleged in the letter of 17 September along
with the other matters assists the plaintiff’s argument. On the other hand, the fact
that Mr George denies an agreement to pay the sum of $4,130,000 on draw down of
the finance tells against Mr George’s credibility. Mr King’s evidence supports the
existence of an agreement in this respect as does the evidence of Messrs
Hutchinson, Quinn, Norton and Williams. I find that there was such an agreement.
In my view, the weight of the evidence is against the conclusion that the meeting
produced a result which amounted to little more than “business as usual” under the
Deed.
Conclusions in relation to the encroachment agreement
-- 23 of 28 --
24
[130] Mr George’s primary account of events at the meeting is contained in his affidavit
sworn on 10 October 2003. The meeting was thus reasonably fresh in his mind
when the affidavit was sworn. Much of its contents were accepted as accurate or
broadly accurate by Messrs Quinn and Norton and by Ms Williams. Their
recollections, however, supported to a degree by contemporaneous writings, varied
from Mr George’s account in some critical respects. Mr George said in cross-
examination, in effect, that he could not now remember what was discussed in the
second half of the meeting but that the contents of his affidavit would have been his
best recollection at that time.
[131] What the affidavit represents, however, is a version of events calculated to put a
favourable gloss on matters from the plaintiff’s perspective. It was unlikely to, and I
find it does not, intentionally record conversations and events at the meeting which
Mr George regarded as harmful to the case the plaintiff was mounting at the time. I
consider also that Mr George’s references to the Deed in the course of the meeting
were unlikely to have arisen from any genuinely held belief on his part that the
terms of the Deed were being or ought to be observed. The plaintiff had been in
serious breach of its terms from within days of its having been entered into. Also, as
I have pointed out, the defendant held the Mortgage and was able to exercise its
powers under it. It also had freedom of action under clause 9. Additionally, I
consider it likely that Mr George did not regard an agreement, particularly an oral
one, as imposing an absolute constraint on the plaintiff’s freedom of action should
the plaintiff not be able to meet its terms.
[132] Mr King had very little recollection of the events of the meeting and, in my view,
much of the recollection he professed to have was formed or influenced by
discussion with Mr George and his reading of Mr George’s affidavits. I find that
each of Ms Williams and Messrs Quinn, Norton and Hutchinson gave their evidence
carefully and to the best of their respective recollections.
[133] Mr Hutchinson strongly pressed for two things, payment from the moneys to be
drawn down in the near future of as much as the plaintiff could possibly make
available and certainty in relation to the scope of the acts the defendant had to
perform in order to comply with clause 7 of the Deed. Discussion identified that
there would be $4,130,000 available to satisfy the plaintiff’s obligations to the
defendant. Mr Quinn’s diary note records the payment of that sum on Friday of that
week as one of the “outcomes” of the meeting. I find that his note of the documents
to be provided in respect of the encroachment recorded what was summarised by
him and accepted by Messrs George and King as the documents required to fulfil
the defendant’s obligations in relation to the steps to be taken under clause 9, to
rectify the encroachment except that he failed to record that the plans were to be in
registrable form and that the documents were to be delivered on or before 25
September.
[134] The day after the meeting Ms Williams recorded an agreement that at settlement the
plaintiff would receive $4,130,000. Ms Williams’ diary note and subsequent typed
note of the meeting do not deal expressly with the encroachment agreement but, as
she explained, that was not a matter within her sphere of interest. If, however, she
had regarded clause 7 of the Deed as imposing a constraint on payment of the
balance moneys due under the Building Contract or Deed, the likelihood is that
some mention would have been made of that fact.
-- 24 of 28 --
25
[135] The question of whether a binding contract resulted from negotiations between
parties is to be determined by reference to the intention of the parties “disclosed by
the language the parties have employed”.22
[136] McHugh JA in GR Securities v Baulkham Hills Private Hospital Pty Ltd23 expressed
the question for determination this way:
“However, the decisive issue is always the intention of the parties
which must be objectively ascertained from the terms of the
document when read in the light of the surrounding circumstances”.
Those observations were made in respect of a written agreement but, with
appropriate adaptations, they apply equally to oral agreements.
[137] Also, the question of whether a binding agreement has been concluded is not always
capable of resolution by attempting to draw out of oral or written exchanges a
discrete offer and acceptance.
[138] In Integrated Computer Services Pty Ltd v Digital Equipment Corp (Aust) Pty Ltd 24
McHugh JA, with whose reasons Hope and Mahoney JJA agreed, said:
“It is often difficult to fit a commercial arrangement into the
common lawyers’ analysis of a contractual arrangement. Commercial
discussions are often too unrefined to fit easily into the slots of
‘offer’, ‘acceptance’, ‘consideration’ and ‘intention to create a legal
relationship’ which are the benchmarks of the contract of classical
theory. In classical theory, the typical contract is a bilateral one and
consists of an exchange of promises by means of an offer and its
acceptance together with an intention to create a binding legal
relationship ...”
[139] In Vroon BV v Foster’s Brewing Group,25 Ormiston J referred to the following
passage from the judgment of Cooke J in Meates v Attorney-General26 with
approval:
“I would not treat difficulties in analysing the dealings into a strict
classification of offer and acceptance as necessarily decisive in this
field, although any difficulty on that head is a factor telling against a
contract. The acid test in a case like the present is whether, viewed as
a whole and objectively from the point of view of reasonable persons
on both sides, the dealings show a concluded bargain.”
[140] Having regard to these principles and the facts discussed, I find that there was a
binding agreement as alleged by the defendant.
[141] I find that the plaintiff and the defendant varied clause 7 of the Deed by agreeing
that the defendant’s obligation to “undertake all such steps as are necessary to
rectify the encroachment” so as to permit registration of the relevant plans would be
satisfied by delivery to the defendant’s solicitors on or before 25 September 2003
of:
22 Masters v Cameron (1954) 91 CLR 353 at 362.
23 (1986) 40 NSWLR 631.
24 (1988) 5 BPR 11 at 11,117-11,118.
25 [1994] 2 VR 32 at 82-3.
26 [1983] NZLR 308 at 337.
-- 25 of 28 --
26
(a) Contracts of sale to the plaintiff of the land the subject of the
encroachment and memoranda of transfers;
(b) Signed plans of subdivision in respect of the said land;
(c) Appropriate forms of application from exemption from stamp duty;
all, where appropriate, in registrable form.
Was there consideration for the encroachment agreement?
[142] It is argued on behalf of the plaintiff that the defendant was seeking to substitute a
lesser obligation for a greater one and that that, on the authorities, does not
constitute the provision of valuable consideration.
[143] If the defendant promised to do no more than perform an existing duty under the
Deed, subject to my later observations, there would be no valuable consideration.27
But that was not the case here. The defendant’s obligation under clause 7 was
capable of being satisfied in a variety of ways. For example, the encroachment
could be rectified by obtaining easements over the land on which the building
encroached or it could be satisfied by acquisition of that land. That is the course
which the defendant proposed to follow.
[144] The varied agreement substituted for the defendant’s promise in clause 7 an
obligation different in content which gave or was capable of giving a tangible
benefit to the plaintiff. It acquired title to the land the subject of the encroachment
and thereby avoided the necessity of acquiring and keeping in existence an
easement or easements over that land. It also obtained certainty as to the
documentation to be provided in order to satisfy the obligation. Having regard to the
fact that time had ceased to be of the essence, it obtained certainty or greater
certainty concerning the time within which the defendant’s obligations were to be
performed. The fact that Mr George may have been mistaken as to the general
efficacy of the subject documentation is immaterial for present purposes.28 I find
that there was valuable consideration for the defendant’s promise.
[145] It is relevant also that the subject promise was given as part of a compromise under
which the plaintiff agreed to pay $4,130,000 upon drawdown of the proposed loan
and under which the time within which the balance of the contract price was to be
paid was altered. The plaintiff gained a benefit from this re-arrangement of
obligations.
Conclusion
[146] The two letters from the defendant’s solicitors to the plaintiff’s solicitors dated 25
September 2003 do not list amongst their contents any forms of application for
exemption from stamp duty. But there was no issue during the trial about the
absence of these documents and any failure to provide them. Such failure, if it
occurred, would not affect the outcome of these proceedings. If such documents
were not provided, in breach of the defendant’s obligations under the 16 September
agreement, it is not suggested that there would have been any difficulty in the
plaintiff mitigating its loss by providing them almost immediately. Also, the
defendant would have been relieved of any further obligation to provide them by the
plaintiff’s conduct.
27 Wigan v Edwards (1973) 47 ALJR 586 at 594.
28 Ficom SA v Sociédad Cadex Ltd [1980] 2 Lloyds Rep 118 at 132.
-- 26 of 28 --
27
[147] The plaintiff’s case for additional interest incurred by Eastgate to its financiers, as a
result of delay in registration of titles, is based on the allegation that but for the
encroachment, relevant plans of subdivision would have been able to have been
registered no later than 20 June 2003, sales of lots in the Estate could have been
settled much earlier than in fact happened and moneys would have been available to
reduce borrowings.
[148] No delays were caused by any breach by the defendant of the terms of clause 7 of
the Deed after 25 September 2003. And the evidence does not establish that were it
not for the encroachment the relevant plans would have been registered no later than
20 June 2003 or that settlements of sales could have taken place in accordance with
the timetable put forward in paragraph 16A of the Statement of Claim. The reasons
for these conclusions are set out earlier in these reasons.
[149] In my view it is not possible to determine from the evidence what additional interest
was incurred or paid by Eastgate to its financiers for any period between the date on
which the subdivisional plans for the Land ought to have been registered were it not
for the encroachment and other dates of possible relevance, namely, the date of the
Deed, 25 September 2003 and the date on which registration was finally effected.
Accordingly, I find that the claim for additional interest has not been made out.
[150] The claim for $39,507 on account of additional moneys payable to Yellowrock fails
for the reasons already explained and because it is based on the erroneous premise
that the defendant was not entitled to payment on 14 January 2004 because it had
not rectified the encroachment.
[151] Nothing in the agreement reached on 16 September relieved the defendant from its
obligation to “pay for all compensation, costs, charges and expenses associated with
the rectification of the encroachment”.
[152] The plaintiff’s claims for the cost of rectifying the encroachment were the subject of
evidence by Mr George, who swore that the costs claimed were paid by Eastgate.
Mr Graham, a costs assessor, calculated those costs at $15,869.51. The task
undertaken by him was to assess the plaintiff’s solicitor’s encroachment file “to
determine their solicitor and own client legal fees and costs incurred by the plaintiff
in rectifying the encroachment”.
[153] It is argued on behalf of the plaintiff that its obligations in relation to the
encroachment came to an end on 25 September 2003 and that, in consequence, the
claim must fail. That argument assumes that the agreement reached on 16
September relieved the defendant of any obligation to pay the costs of removal of
the encroachment. The agreement did not have this effect. Neither the words used
by those at the meeting nor the letter of 17 September 2003 suggest that the parties
contemplated releasing the defendant from an obligation to pay the costs of bringing
about the extinguishment of the encroachment. The letter acknowledges a
continuing obligation on the part of the defendant to pay disbursements incurred in
relation to the encroachment. Accordingly, this ground of defence fails. Although
the general rule is that the subsequent conduct of the parties cannot be used for the
purpose of construing their contract;29 the letter is relevant to the determination of
29 Maynard v Goode (1926) 37 CLR 529 at 538 and Administration of the Territory of Papua and New
Guinea v Daera Guba (1973) 130 CLR 353.
-- 27 of 28 --
28
what was said on 16 September. It also constitutes an admission against interest
concerning an agreed term. 30
[154] The only other argument advanced in respect of this claim is that:
“(a) The material does not reveal what work in fact the costs
relate to;
(b) Mr Lynch has not sworn to the work which underlies the
claim, that it in fact relates to rectifying of the encroachment
for the relevant period and that it was in fact reasonable; and
(c) Mr Garrett was not the subject of cross-examination on the
point.”
[155] Mr Graham swears to having been employed as a solicitor in private practice and to
having worked as a costs assessor since 1966. He swears that the work undertaken
by him was to assess costs “incurred by the plaintiff in rectifying the
encroachment”. He further swears that he had regard to material in Lynch & Co’s
litigation file “which comprised of work undertaken by the plaintiff’s solicitors in
rectifying the encroachment”.
[156] Mr Garrett, a costs assessor who gave evidence on behalf of the defendant, swears
that he has perused Mr Graham’s affidavit and that:
“(a) it is impossible to say if the costing of the files of the
solicitors for the plaintiff are accurate because there is
insufficient detail in the assessment performed by Mr
Graham;
(b) secondly, it is also impossible to say if the work to which the
costs assessment relates was reasonable because again, there
is insufficient detail to make the judgment.”
[157] Neither costs assessor was cross-examined. Plainly, substantial costs including
substantial registration fees, stamp duty and other outlays were incurred and were
paid. The evidence of Mr Graham and the lack of evidence from Mr Lynch may
leave a bit to be desired by way of strict proof but, in my view, the evidence is
sufficient to establish the plaintiff’s claim. At the very least, it establishes the
outlays set out in Mr Graham’s material. Accordingly, I find this component of the
plaintiff’s claim has been made good.
[158] I have dealt with the claims based on the alleged unlawful appointment of receivers.
[159] The claim of $374,598 for moneys had and received must fail for the reasons given
earlier.
[160] I will hear the parties in relation to any formal orders to be made and on the
question of costs. My tentative view is that there should be no order as to costs. The
plaintiff’s success was very limited – it lost on most issues including the most
substantial. On the other hand the defendant failed on a number of issues and, in my
view, some of its arguments were singularly lacking in merit.
30 Sportsvision Australia v Tallglen Pty Ltd (1998) 44 NSWLR 103 at 115-116.
-- 28 of 28 --