Australian Mining and Industrial Communications Pty Ltd v Parklands Blue Metal Pty Ltd [2005] QDC 54
1
[2005] QDC 054
DISTRICT COURT
CIVIL JURISDICTION
JUDGE ROBIN QC
No D11 of 2004
AUSTRALIAN MINING AND INDUSTRIAL
COMMUNICATIONS PTY LTD (ACN 082 253
450)
Plaintiff
and
PARKLANDS BLUE METAL PTY LTD (ACN 010
471 548) Defendant
MT ISA
..DATE 28/02/2005
DAY 1
EXTRACT OF PROCEEDINGS – RULING
CATCHWORDS: Uniform Civil Procedure Rules r150, r155, r161 – pleading of damages – plaintiff
made a claim for its usual charge out rate of $400 per day for a forklift for the whole time
while repairs were effected following its return after a hiring by the defendant – pleaded
defence disputed the correctness of the number of days claimed, but not the daily rate –
request for particulars capable of being regarded as enquiring about the appropriateness of
the daily rate was answered by the plaintiff’s repetition of its original calculation, then
never pursued – at trial the defendant unsuccessfully sought striking out of the damages claim
(and another claim) as not properly pleaded – plaintiff ordered to give the particulars sought
basis of a notional amendment of the defence. on
ORDER
WARNING: The publication of information or details likely to lead to the identification of persons in some proceedings is a criminal
offence. s is so particularly in relation to the identification of children who are involved in criminal proceedings or proceedings for
their protection under the Child Protection Act 1999, and complainants in criminal sexual offences, but is not limited to those
categories. You may wish to seek legal advice before giving others access to the details of any person named in these proceedings.
Thi
-- 1 of 5 --
28022005 D.2 T1/CK (Robin DCJ)
2
1
10
20
30
40
50
60
1
10
20
30
40
50
60
This is an unusual example of a civil trial proceeding in the
Court at Mt Isa. It has been slow to get underway, and the
reason for that is the defendant is raising criticisms of the
state of the plaintiff's pleading including the plaintiff's
particulars.
There was a dry hire of a forklift at an agreed rate of $400
per day. The equipment went back to the plaintiff late but
the agreed rate was paid so long as the defendant retained the
forklift. It came back to the plaintiff, according to it, in
a damaged condition. Repairs were effected for charges set
out in the plaintiff's pleading, which the defendant did not
accept, with a belief being pleaded that those charges were
excessive.
The bulk of the plaintiff's claim is for $400 per day lost
hire for a period of 25 weeks throughout which, allegedly, the
forklift could not be hired out, although there were customers
available in such numbers that for every single day a customer
would have been available to pay $400 per day.
The plaintiff brings alternative claims in contract,
negligence and bailment. The second, possibly the first, are
or may be want of reasonable care claims, but the bailment
claim is something much closer to an absolute liability
situation, although it may nowadays be more accurate to say
that what constitutes reasonable care of a chattel may be
different in a bailment context.
In respect of the negligence aspect is the plaintiff's case
that the forklift was damaged in an accident in the mine at
Mount Isa and that that is the main cause of the
unavailability of the forklift in good condition for hiring
out.
Mr Radcliff submitted that the plaintiff in giving
particulars of the defendant's failings as a bailee as
follows:
"The defendant has failed to take proper care of the
machine while it was in the defendant's control and,
instead, has allowed the machine to be damaged.",
related its whole claim to the accident in the mine and
physical damage occasioned there. Mr Radcliff sought to limit
the plaintiff to making a case based on that damage.
I am not persuaded of his point and rather think that in the
bailment claim, which is the one being particularised, what
counts is whether the machine was damaged when returned to the
plaintiff rather than exactly when and how it got damaged in
bailment. If I recall correctly, the onus is on the bailee to
show that proper care is taken. For the other heads of claim,
the plaintiff has, or may have to, prove want of proper care
by the defendant.
In dollar terms, the more significant question is what
Mr Radcliff has called a demurrage claim at $400 a day. He
-- 2 of 5 --
28022005 D.2 T1/CK (Robin DCJ)
3
1
10
20
30
40
50
60
1
10
20
30
40
50
60
retracted a criticism that the defendant had not made it clear
what days were included and it is clear from the particulars
that the 25 weeks are those running from the 15th of June
2002. One must wonder how consistent that is with the
information the Court has that hire was paid by the defendant
for a month or so after that date, which was the one when the
hire was to terminate; is that right?
MR RADCLIFF: That's right.
HIS HONOUR: That's a special problem. While the defence
raised an issue as to whether the repair costs the plaintiff
claims were paid were unreasonable and too high, no issue is
raised in the defence regarding the validity or reasonableness
of the $400 per day allegedly lost.
What the defence said in that regard is:
"The defendant denies the allegations in paragraph 18 of
the statement of claim because the plaintiff is unable to
verify that they would have been able to hire out the
fork lift for the 25 week period at $400 a day.
Therefore, the amount claimed of $50,000 is excessive and
should be reduced accordingly."
The only opposition made to that aspect of the plaintiff's
claim is that the $400, regarding which nothing is said, might
not have been available to the plaintiff for as many days as
the plaintiff asserted. However, the defendant revealed an
interest in going behind the $400 per day figure in a request
for particulars of the 21st of January 2004 which inquired
about:
"(a) the manner and calculation of the alleged hire
charge of $400 a day; (b) full and precise particulars of
the hire cost of like hire machines to establish that the
hire charge is fair and reasonable; (c) the duration of
the alleged period for which the machine could not be
hired; and (d) full and precise particulars for the
reason for the extended period for which the machine
could not be hired."
It seems to me that (a) is the one of most importance among
those.
The plaintiff's response dated 27th of January 2004 in respect
of (a) was that, "The plaintiff could not hire the machine out
at its ordinary charge-out rate of $400 per day." That request
for particulars was not followed up as, in my opinion, it
could have been and in retrospect probably should have been.
The defendant may have been able to resort to rules 162 or
163, whichever is the one authorising the Court to impose
severe sanctions on a party not providing particulars as
ordered.
Mr Radcliff relies on a group of authorities, copies of which
he has handed to the Court, which emphasise that the new
pleading rules in the UCPR ought to be taken seriously and, in
-- 3 of 5 --
28022005 D.2 T1/CK (Robin DCJ)
4
1
10
20
30
40
50
60
1
10
20
30
40
50
60
particular, rules requiring pleading of details of damages
claims.
The cases are Meredith v. Palmcam Pty Ltd [2001] 1 Qd.R. 645,
a decision of the Court of Appeal, Moynihan J's decision in
Cook's Construction Pty Ltd v. Stork ICM Australia Pty Ltd
BC200401348, SC 10993 of 2001, 16 March 2004, also reported,
it seems, at 2004 QSC 66, and the final case is a decision of
Judge McGill in Millhouse IAG Pty Ltd v. Environautics Pty Ltd
[2000] QDC 196. They all are matters that involve
interlocutory arguments about particulars and they do
emphasise the importance of compliance with the new rules.
Mr Radcliff's argument is that there is even more reason to
hold litigants strictly to the rules of pleading once the
trial is reached. From one point of view, obviously, the
luxury of interlocutory applications is no longer available.
To an extent perhaps, I am influenced by my view of what
attempting to do justice according to law in a centre such as
Mount Isa might require. In the not too distant past it has
been identified, unflatteringly, and perhaps inappropriately,
as palm tree justice. But even putting such considerations
aside, I think that the defendant's complaints about being
brought to Court to face a substantial damages claim which has
not been properly particularised are balanced by the
defendant's own failure by its pleadings to suggest that any
issue was being raised about the appropriateness of $400 as a
daily charge in respect of such dates as the plaintiff could
show were relevant. It must be conceded that by its request
for particulars, the defendant clearly evinced an interest in
that issue, without attracting any useful response from the
plaintiff. As I said, the matter was not pursued further.
I am not prepared to accept that by its request for
particulars the defendant changed the issues in a way that
required looking behind the hire of $400 per day. I think,
assuming the defence was in order, the request for particulars
was a proper one and the defendant ought to have been supplied
with those particulars in order to know the claim it faced.
Not the least of reasons for providing the other side with
details of that kind is that it may facilitate a resolution
of, if not the whole matter, at least certain quantum issues.
I think the plaintiff ought to be ordered to give the
particulars requested.
Technically, maybe, the defendant ought to be ordered to amend
its defence. I do not know if it is necessary to go through
that formality now, but it has been made clear today that the
defendant seriously wishes to pursue whether $400 is indeed
the correct daily amount or whether it is something more
modest if an exercise is embarked on of trying to identify
what the plaintiff's actual losses were, as opposed to the
gross income it might have got from hiring the forklift.
I am going to order you to give the particulars. You will
have to get instructions about it, presumably, won't you?
-- 4 of 5 --
28022005 D.2 T1/CK (Robin DCJ)
5
1
10
20
30
40
50
60
1
10
20
30
40
50
60
MR BASSETT: Yes, your Honour.
HIS HONOUR: I refuse Mr Radcliff's application to strike out
the $400 per day claim, likewise, any claim based on damage to
the fork lift that did not arise in the accident in the mine.
-- 5 of 5 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2005/054