Clift and Anor v Gold Coast City Council [2005] QPEC 106
PLANNING & ENVIRONMENT COURT
OF QUEENSLAND
CITATION: Clift and Anor v Gold Coast City Council [2005] QPEC 106
PARTIES: JOHN LAWRENCE CLIFT and
LINDA RAIMONDA CLIFT
Appellants
v
GOLD COAST CITY COUNCIL
Respondent
FILE NO/S: BD 3937 of 2004
DIVISION: Appellate
PROCEEDING: Applicant’s conditions appeal
ORIGINATING
COURT: Planning and Environment Court, Brisbane
DELIVERED ON: 31 October 2005
DELIVERED AT: Southport
HEARING DATE: 02/10/05, 03/10/05, 05/10/05
JUDGE: Robin DCJ
ORDER: Appeal allowed, conditions to be varied
CATCHWORDS: Integrated Planning Act 1997 s 3.5.30 – developer’s
“conditions” appeal – whether infrastructure contributions
required of developers under Council’s Planning Scheme
Policies about water supply, sewerage network and recreation
facilities were irrelevant to or an unreasonable imposition on
the actual development proposed – contributions calculated
on basis of maximum potential development, alleged by
Council to be 57 bedrooms – developer proposed 12
bedrooms (over 9 storeys) – the only element in the
calculations susceptible of variation was “yield factor” –
whether yield factor should be reduced below 1 (representing
maximum development) – appellants’ contention that it
should be reduced to the “planned yield factor” rejected –
Council’s contention that maximum potential development
was achievable in practice rejected – maximum practicable
found to be 9 x 3 bedroom units on the evidence before the
court.
COUNSEL: Mr S Ure – Appellants
Mr M Hinson SC – Respondents
-- 1 of 30 --
2
with him Mr S Fynes-Clinton
SOLICITORS: Phillips Fox – Appellants
Corrs Chambers Westgarth – Respondents
[1] This is a developer’s “conditions” appeal under s 4.1.27 (1)(b) of the Integrated
Planning Act 1997 (IPA), the Council having approved: -
“subject to conditions, a development application for a development
permit for a material change of use and preliminary approval for
building work for a nine storey apartment building over land
described as Lot 1 on RP 21845, Country of Ward, Parish of Gilston
and located at 79 Garfield Terrace, Surfers Paradise (the land)”
What is sought from the court, should the appeal succeed, is approval of the
application “subject to conditions that are relevant to, but not an unreasonable
imposition on the development or are reasonably required in respect of the
development.” The notice of appeal identifies the conditions complained of: -
“ 9 Conditions 2,3,4,5 and 6 of the decision notice state:
2 Contributions toward Recreation Facilities Network
Infrastructure shall be paid to the Council in accordance
with Planning Scheme Policy 16 prior to the endorsement of
the plan of survey, the issue of a Certificate for Building
Works or the carrying out of final Plumbing inspection
whichever occurs first. The amount of the contribution shall
be as follows:
Recreation Facilities – Surfers
Account: 74648
RDPU03 29.0000 Equivalent Tenements @ $6,085.00 =
176,465.00
TOTAL $176,465.00
Contributions shall be calculated at rates current at due
date for payment.
3 Contributions toward Sewerage Network Infrastructure
shall be paid to the Council in accordance with Planning
Scheme Policy 3B prior to the endorsement of the plan of
survey, the issue of a Certificate for Building Works or the
-- 2 of 30 --
3
carrying out of final Plumbing inspection whichever occurs
first. The amount of the contribution shall be as follows:
Sewer 2 Infrastructure – Coombabah
Account: 74648
S2COOMB 20.0000 Equivalent Tenements @ $1679.00 =
33,580.00
Sewer 1 Infrastructure – Coombabah
Account: 74648
S1COOMB 20.0000 Equivalent Tenements @ $2,382.00 =
47,640.00
TOTAL $81,220.00
Contributions shall be calculated at rates current at due
date for payment.
4 Contributions toward Transport Network Infrastructure
shall be paid to the Council in accordance with Planning
Scheme Policy 19 prior to the endorsement of the plan of
survey, the issue of a Certificate for Building Works or the
carrying out of final Plumbing inspection whichever occurs
first. The amount of the contribution shall be as follows.
Transport Infrastructure – Surfers
Account: 74648
TRANSPORT 17.500 Vehicle Trips @ $295.00 = 5,162.50
TOTAL $5,162.50
Contributions shall be calculated at rates current at due
date for payment.
5 Contributions toward Water Supply Network Infrastructure
shall be paid to the Council in accordance with Planning
Scheme Policy 3A prior to the endorsement of the plan of
survey, the issue of a Certificate for Building Works or the
carrying out of final plumbing inspection whichever occurs
first. The amount of the contribution shall be as follows:
Water 2 Infrastructure – Molendinar
Account: 74648
W2MOLEND 20.0000 Equivalent Tenements @ $1,741.00 =
34,820.00
TOTAL $55,940.00
Contributions shall be calculated at rates current at due
date of payment.
-- 3 of 30 --
4
6 A contribution of fourteen thousand three hundred dollars
($14,300) is to be made to the proposed beachfront
footpath/cycleway (Account Bikediv(7) 74648). The
Contribution is to be made to Council prior to the
commencement of the use the subject of this approval.”
The Council has abandoned condition 6; the appellants are not any longer
contesting condition 4, which is calculated on the basis of the increased demand
their proposed development will place on the Council’s transport infrastructure. The
contributions required under the Planning Scheme Policies mentioned in the other
three conditions are based on a notional development on the site much more
intensive than what is proposed. Section 6.1.31 of the IPA is relied on to support the
still contentious conditions.
[2] Section 3.5.30 of the IPA is: -
“3.5.30 Conditions must be relevant or reasonable
(1) A condition must—
(a) be relevant to, but not an unreasonable imposition on,
the development or use of premises as a consequence of the
development;
(b) be reasonably required in respect of the development or use of
premises as a consequence of the development.
(2) Subsection (1) applies despite the laws that are administered by,
and the policies that are reasonably identifiable as policies applied
by, an assessment manager or concurrence agency.”
The appellants say that none of the contentious conditions can be supported under
section 3.5.30(1) (a) or (b). I thought this section applicable to conditions imposed
under s 6.1.31(2)(c) in Hickey Lawyers (a firm) v Gold Coast City Council [2005]
QPEC 22. Leave to appeal was applied for, but I am given to understand the matter
has been resolved. The appellants contend that, contrary to another view I took, the
three Policies identified are “policies” within s 3.5.30(2).
[3] Unusually, the Council regards the proposal as underdevelopment. It contains only
four three-bedroom apartments; each will occupy two whole floors, the uppermost
-- 4 of 30 --
5
including a roof area to be partly roofed itself. There is presently an old three-
bedroom dwelling of two storeys on the 792m2 site, whose northern frontage is to
Enderley Avenue; technically, there is an eastern frontage to a gazetted Esplanade
which has never been constructed on the dunes. There is thus direct pedestrian
access to the beach.
[4] The site is in Precinct 2 High Rise Accommodation in the Surfers Paradise Local
Area Plan for purposes of the Gold Coast Planning Scheme 2003. The Intent is
unusual in “encouraging” high rise development, as opposed to permitting it: -
“5.2 Precinct 2: Intent for High Rise Accommodation
This precinct incorporates land south and north of the Entertainment
Precinct, shown on LAP Map 25.2. This area is already extensively
developed, providing, a range of residential and resort
accommodation. Retailing is confined largely to the Gold Coast
Highway and Ferny Avenue. The intent for this precinct is to
encourage further high rise accommodation, both for permanent
residents and tourists in appropriate locations. Buildings should be
of high quality, both in terms of design and finishes, and sited amidst
lush sub-tropical grounds with minimal hard stand areas. In
encouraging further high rise development, the precinct seeks to
minimise those uses which adversely impact upon the residential
amenity of these areas. As a result, high impact non-residential uses
should be confined to arterial roads.
The amenity of the beach must be preserved. In this regard, it is
essential that development along the beachfront complements the
existing built form of this area, to enhance the iconic value of towers
along the beach. The proximity of this precinct to the beach front
and associated pedestrian and open space areas also provides an
opportunity to develop a small scale cosmopolitan dining strip along
The Esplanade, with an emphasis on al fresco dining be incorporated
in the future development of this precinct.”
In Precincts 3, 4 and 6 the Intent is to “retain the low key residential nature”; in
Precinct 5 it is “to encourage” further low to medium rise accommodation. The
Precinct 2 height limit is 30 storeys, which will doubtless be achieved on
sufficiently large sites, if it is not being achieved already. Plot ratio has recently
been increased to 4:1. Site coverage is 40 per cent. The Surfers Paradise maximum
-- 5 of 30 --
6
residential density map prescribes “one bedroom per 13m2 of net site area (up to
769 bedrooms per net hectare)”, allocating the site to RD 8.
[5] The approved plans, as noted, provide for four apartments only. There is no
suggestion that the appellants intend (or that the plans allow any scope for)
converting them to or using them as a greater number of separate dwelling-units.
They are apparently intended for occupation by permanent residents. The proposal
has been given the unusual name Eau on Enderley, explicable not only by the ocean
frontage but by a 20 metre “waterfall” proposed for the Garfield Terrace frontage,
and four balustrades along Enderley Avenue which will be see-through lap pools.
Mr and Mrs Clift have been the owners for a long time. It is a commentary on our
times that they have felt compelled to defend their chosen development as the
highest and best use – unsuccessfully as it turns out, in the view of Mr Murphy, an
experienced valuer who became a last-minute expert witness for them, called to
rebut the Council’s contention that the site could feasibly be developed with 57
bedrooms. The 57 represents a concession necessary to recognise that it is the “net”
site area of 747m2 (what will remain after a dedication for the widening of Garfield
Terrace) that is taken into account, rather than the area of the time of the
application.
[6] Oddly, the proposal has had to confront an issue of being too bulky. At the time of
the application, the maximum allowable plot ratio was 1.692:1, producing a total
GFA of 926m2 – grossly exceeded by the 1770.8m2 proposed, which represents a
plot ratio of 2.23:1. Relaxation was sought, indeed, a two-stage relaxation:
(a) Initially, 21.7:1, based on additional landscaping; and
(b) then to the ratio required, based on “outstanding urban design
quality” outstripping the merit “normally demonstrated by a
complying development”
-- 6 of 30 --
7
and was recommended by the Council’s planning officers in their assessment
report. The allowable plot ratio has now been increased to 4:1. An inference is
easily drawn that this change is part of a number adopted to boost, in a practical
way, the “encouragement” mentioned in the Intent. The Surfers Paradise local area
plan in 8.3 Development Requirements set out performance criteria and acceptable
solutions, PC28 being: -
“LOT SIZE
PC28
All allotments are to be sufficient
area and dimensions to
accommodate buildings designed to
the criteria in this LAP
AS28.1
The minimum lot size for each precinct is as
follows
PRECINCT MINIMUM
ALLOTMENT SIZE
NOT LESS THAN
1,2,5 and 7 1,000m 2
3,4 and 6 400m 2
AS28.2
In all precincts, the minimum frontage of
land proposed to be used for non-residential
or commercial purposes in this LAP is
fifteen metres.”
this going on top of provisions in 6.0, Table of Development, in G: reconfiguring a
lot whereby impact assessment (as opposed to code assessment) was required if the
reconfiguration resulted in one or more lot(s) with an area less than 1000m2 . One
can speculate that the market has not worked as expected to produce lots of
1000m2 , by amalgamation if necessary, resulting in developments being proposed
for lots (like the site) that are smaller. Rather than hold out to force amalgamations,
the Council has changed the Gold Coast Planning Scheme so that PC28 as quoted
from version 1.0 is now, in version 1.1, PC26, under the new heading “LOT SIZE
(FOR SUBDIVISION ONLY)”. The Council’s approach of facilitating more
intensive development makes sense when related to the Planning Policies involved
in this appeal.
-- 7 of 30 --
8
GOLD COAST PLANNING SCHEME POLICIES
The reasons in the Hickey Lawyers appeal contain some description of the
Council’s changing approach to charging for infrastructure necessitated by a
development. It has been attempted to avoid case by case calculations of
appropriate charges in respect of particular developments by mapping the local
government area with a view to treating all properties within geographical areas
delineated alike, in the sense that contributions will be worked out by calculations
based on inputs about which there should be no argument. I think it is notorious
that, understandably, there are political pressures to ensure, if possible, that
developers (or those who purchase or use what they create) pay for provision of
infrastructure required by new development, in relief of the general body of rate
payers and/or those who bear the burden of rates indirectly. Representative of the
Policies is Planning Policy 3B which commences:
“1.0 PURPOSE
The purpose of this Policy is to present the developer contributions
for the Gold Coast City Council sewerage network. The
contributions will only be used to held fund the provision of the
infrastructure needed to serve new development and redevelopment.
This is Planning Scheme Policy No. 3B, Policy for Infrastructure
(Sewerage Network Developer Contributions), which has been
prepared in accordance with the Integrated Planning Act 1997(IPA).
The provisions of this Policy shall apply to every development
application for development, which is situated in a part of the City
and which, in the opinion of Council, may be connected to the
sewerage network immediately or in the future.
The Policy is supported by the infrastructure planning reports
detailed in Section 14.
2.0 PHILOSOPHY
An applicant shall pay relevant and reasonable contributions towards
the capital cost of the provision of the sewerage network to meet the
demand placed on the network by the development.
-- 8 of 30 --
9
Contributions are based on the methodology outlined in the
subsequent sections of this Policy. The application of this policy and
determination of contributions for all developments will be carried
out by the Chief Executive Officer or authorised delegate.
Contributions shall include financing costs required for funding the
construction of infrastructure and administrative costs.
Such contributions are held by Council and used for the
administration, planning and construction of works or the payment of
loans to provide a reliable sewerage network as outlines in the
Policy.”
The other Policies presently relevant deal with the water supply network and the
recreation facilities network. The following sections in the Policies include much
material by way of explanation, justification and history. Setting aside for the
moment the question whether the “philosophy” is operative as a control, rather than
an assertion of what is being (or sought to be) achieved, the crux of each Policy is
set out in a flowchart which offers step by step instructions for calculation of
contributions, in a “pick a path” format.
[7] The instructions (taken from Policy 16) begin: -
“FLOWCHART TO DETERMINE DEVELOPER CONTRIBUTION FOR THE
RECREATION FACILITIES NETWORK
Start Determine both the Assessable
impact (ET) and the Developer
Contribution Rate ($/ET) to
determine the developer
contribution
Identify proposed
development
location
-- 9 of 30 --
10
One is then directed to the paths headed “Developer Contribution Rate” and
“Assessable ET”; they lead to identification of components to go into the final
calculations. A glossary of terms helps explain the latter: -
“equivalent tenement (ET)” is a property based unit of
measurement used to indicate infrastructure demand for the property.
The demand from each property is related to the type of development
allowed on the property with a detached dwelling on a standard
residential lot being 1 ET. Other residential developments such as
flats/units/villas are usually rated lower ET per dwelling.”
There is a direction:-
“Calculate Assessable “ET” for
the development = gross area x
yield factor x maximum
ET/Ha”
Another provision of the glossary should be noted: -
“yield factor” represents the percentage of developable land within a
specific lot. It accounts for future roads, transport corridors,
floodplain areas, open space and other constraints to development.”
Yield Factor is taken from the mapping in Appendix B; here it is one (1) - which is
typical of all areas east of the Gold Coast Highway, indeed, east of Bermuda Street.
[8] Attention is then directed away from a theoretical maximum development to the
specifics of the development application:-
“Calculate proposed ET =
proposed number of dwellings or
bedrooms or lots x density
conversion, Appendix A”
Then comes the question whether the proposed ET falls short of, equals or exceeds
Assessable ET. In the first case (encountered in this appeal), the flow chart
provides:
-- 10 of 30 --
11
“If developer believes the yield
factor to be unreasonable, then the
developer may apply to Council
for a relaxation of the yield factor
at the developer’s cost. CEO or
delegated officer is to determine if
policy yield factor is to be used or
revised”
[9] The appellant’s case is that this stage introduces the necessary flexibility to ensure
that contributions exacted are relevant and reasonable “to meet the demand created
by the development” – which means the development actually proposed. The
Council says that the definition of “yield factor” indicates that only loss of part of
the land by dedication for some public purpose can lead to a reduction in yield
factor. Further, the Council argues, it is relevant and reasonable to charge
contributions on the basis of the most intensive development possible, even if that is
not applied for. The reason is that infrastructure must be in place before private
development occurs, if development is to be orderly and efficient. Water and
sewerage infrastructure in particular must be provided to serve the maximum
demand anticipated (equivalent to the maximum development permitted to be
achieved). Not only works near development sites are to be considered, but remote
head works: reservoirs, sewerage treatment works, etc. The undoubted vice of
charging more modest developments by reference to actual demand created by them
is that, should more intensive development occur later, within the limits of what is
allowed, servicing that may require works to replace mains, etc, which will not only
be extremely costly, but also extremely disruptive to the citizenry, who may be
subjected to months or more of inconvenience while roads are dug up and so on.
On this basis, it can be seen as antisocial for a developer to resist paying
contributions as if the maximum development were proposed and constructed. From
the standpoint that, for present purposes, development for further high-rise
-- 11 of 30 --
12
accommodation is encouraged, it might be seen as antisocial to refrain from
developing to the maximum. Either approach represents something of a revolution
and sits oddly with the right owners of potential development sites presumably
continue to enjoy, of not developing at all. What is happening is the attempted
charging of the equivalent of “key money” if any (at least, most kinds of)
development should be undertaken.
[10] In Hickey Lawyers v Gold Coast City Council [2005] QPEC 022, the general
approach of the Policies met a sympathetic response from the court, indeed from the
appellants there; they did not challenge the relevant policies which were Policy 16
(recreation facilities) and Policy 19 (transport network), but, rather, contended that
the contributions required by calculations made in accordance with Policies led to
conditions offending s 3.5.30. Those appellants proposed to develop their site
intensively, by a mixed development incorporating more than 100 new apartments
in a 34-storey tower. The following appears at [49]: -
“Whether or not there is an effective presumption of relevance and
reasonableness having regard to the way in which planning scheme
policies come about, compliance with IPA authorised guidelines,
albeit strictly for a different purpose (a closely related one) is in my
view an indicator that a planning scheme policy very likely satisfies
s3.5.30(1)(a); there arises a new factor which a dissatisfied developer
must overcome in order to succeed in the task it faces of showing
that a resulting condition is irrelevant to or an unreasonable
imposition on the proposed development. It may not be an easy task
to persuade the court that conditions complying with s 6.1.31(2)(c)
flowing from planning scheme policies duly adopted are
unreasonable or irrelevant. The possibility is nevertheless open, in
my opinion.”
followed in [50] by:
“In 6.1.31 sub-s (1) formerly did not refer to planning scheme
policies (merely to the local government not having an infrastructure
charges plan); sub-s (2) formerly did not authorize imposition of a
condition under a planning scheme policy. Where the circumstances
now contemplated by it are encountered, satisfying IPA in that
regard, it would ordinarily be a curious outcome to discover s 3.5.30
-- 12 of 30 --
13
rendered the condition unlawful. One would think that what IPA
mandates or permits is by definition both relevant and reasonable for
IPA purposes. The possibility cannot be excluded that something
may be incorporated in a planning scheme policy that results in a
condition being proposed that is clearly offensive to s 3.5.30(1) when
examined. That examination must be conducted, not on the basis of
the statute and case law as they formerly existed, but on the new
basis created by IPOLA.” (Integrated Planning and Other
Legislation Amendment Act 2003.)
[11] The present circumstances are different in that Mr and Mrs Clift are not proposing
the most intensive development permitted under the planning scheme, but (if they
determine to implement the approval they have) will be charged with contributions
towards some infrastructure as if they were. There is no way that their proposal will
generate demands on infrastructure to the extent envisaged in the contribution
calculations.
[12] In planning law, there appears to have developed something like a common law
about conditions, against which the provisions of legislation and planning
documents are interpreted. Thus in Western Australian Planning Commission v
Temwood Holdings Pty Ltd (2004) 211 ALR 472, where the Town Planning Act of
Western Australia gave “a broad discretion to impose conditions” (483) both
McHugh J, who formed part of the majority (at 487) and Callinan J, who dissented
(at 513), were referring to House of Lords and other English authority in relation to
what are “planning purposes”. Their Honours formulated a test that a condition
“must reasonably and fairly relate to the permitted development to be valid” (491),
“must fairly and reasonably relate to the proposed development” (513). There has, I
think, always been a notion that there ought to be some proportionality between any
condition and what the developer proposes. In special circumstances, a condition
apparently disproportionately onerous might be permissible. I took that view in
Hammercall Pty Ltd v Gold Coast City Council [2004] QPELR 122 in respect of a
condition requiring a very large dedication of land for road purposes (which I found
-- 13 of 30 --
14
had earlier been agreed to) in relation to minor development proposals (which
related to land forming part of a larger tract being developed in stages). For reasons
explained by Jerrard JA, that view was pronounced erroneous. See [2005] QPELR
498 (see also [2005] QCA 029; his Honour said at [89] – [91]:
“…the problem for the respondent is that the conditions do not
achieve the goal … imposition of those conditions does not go far
enough to achieve the provision of the preferred and planned for
access to the Pacific Highway. … [The evidence did not show it] …
would result in the foreseeable future in any identifiable
improvement or change in the standard of the road system in the area
… Further, … Hammercall could simply elect not to proceed …
Imposing dedication requirements alone, without conditions
requiring construction of the relevant works, does not sufficiently
achieve the goal … the Council need not reproach itself for having
asked now for too little; requiring the dedication and construction of
the Bermuda Street extension, the future service road, the
interchange, and widening Old Coast Road, would now be too
onerous and accordingly an unreasonable imposition …”
[13] (The possibility exists that infrastructure planned and to be funded under the
Policies will never be built. The Council would be condemned if it failed to keep
the list of projected works under review, and make changes to accommodate
emerging needs not planned for, or the unexpected redundancy of works already
scheduled. I do not think there is cause for the concern analogous to that in
Hammercall that an onerous dedication might not lead to any new road.
Hammercall had nothing to do with contributions required under the Policies, or
anything equivalent. IPA authorises the Policies (speaking generally); it is inherent
that there is no link required between a particular development proposal and the
actual construction of some specific infrastructure item. It is clear that contributions
charged are impressed with a trust to ensure they are used for the provision of
infrastructure of the relevant kind: Bathurst City Council v PWC Properties Pty Ltd
(1998) 195 CLR 566.)
-- 14 of 30 --
15
[14] The appellants contend that the contributions required of them are too onerous. As
the written submissions of their counsel, Mr Ure summarise it, the proposed
development produces “an actual impact of 3 ET with respect to Policy 16 (i.e. –
four proposed ET minus one existing ET) and 3.2 ETs with respect to Policies 3A
and 3B (i.e. – 4.2 proposed ET minus one existing ET).” They relied on the report
(Exhibit 5) and evidence of Mr Sutherland, an environmental scientist. The report
reproduces parts of the Council’s “Guidelines” for its infrastructure policies of
March 2005. Point 2 notes the development of “a yield factor layer that is aimed at
providing a benchmark for infrastructure planning. The yield factor map converts
the gross developable area to the net developable area… Planning Scheme
residential densities are then applied to give the yield expected for the lot.”
Scenarios are then identified in which proposed densities match those of the yield
factor, exceed it or fall short of it. As to the last, the Guidelines say:
“(c) The proposed densities to be developed are lower than
those of the yield factor;
Where this scenario occurs, there are conflicts between infrastructure
planning and development density proposals. The applicant is
encouraged to review the densities proposed from the
development and increase the densities to those of the yield
factor.
The standard contribution will be calculated by Council’s Headworks
Section, and should be applied without further negotiation in the
majority of cases.
The applicant can submit written grounds to support their argument
that a lower yield factor should be applied to their site if the
development cannot yield the densities planned. If the applicant
chooses not to develop the planned density, and Council’s Strategic
Planning Branch determines the planned yields are reasonable,
then the applicant is to pay developer contributions for the planned
yield. Any resulting developer contribution reductions may only
occur on a case-by-case basis if the infrastructure planning review
supports reduction of developer contributions.
-- 15 of 30 --
16
Note: Only the yield factor is subject to challenge in this way.
The other aspects of calculating the contribution will not be reviewed
as part of the assessment of the application.”
[15] Mr Sutherland went on to set out the history after the Council’s initial calculations
based on 29 ETs with respect to Condition 2 (Policy 16) and 20 ETs with respect to
Conditions 3 and 5 (Policies 3P and 3A respectively):
“These calculations were later revised to consider net site area after
road widening, resulting in ET values in relation to Conditions 2, 3
and 5 of 27.5, 18.95 and 18.95 respectively.
In determining these final ET figures, Council found that the
theoretical maximum density of the site was 57 bedrooms. In then
calculating contributions under Conditions 3 and 5, their theoretical
maximum density was conceived exclusively on the 57 bedrooms
figure, regardless of how many dwellings that might constitute.”
[16] This last observation is pertinent, because, in respect of Policy 16, at p 41 of 43, in
respect of Density Conversion ET/Dwelling, the allocation for high-rise
accommodation in the Surfers Paradise Local Area Plan is 0.5 ET/bedroom to a
maximum of one. A one-bedroom apartment equates to 0.5 ET, a two-bedroom
apartment, or larger, to the maximum ET of one. It is difficult to see any
justification for disadvantaging a developer (like the Clifts) for making the choice of
three-bedroom apartments.
[17] The submission made on their behalf is that it must have been contemplated (and
that the proper interpretation is) that to arrive at “relevant and reasonable
contributions” to satisfy the Philosophy or contribution that “fairly and reasonable
relate to the proposed development” (to quote Callinan J) the yield factor may be
adjusted downwards from one. The “glossary” definition acknowledges
“constraints”, which might be seen as of general application. The natural reading of
the definition of yield factor is that what matters is actual loss of land from the
-- 16 of 30 --
17
development, and that it does not invite adjustment where particular areas remain
with the developer, although they cannot be made use of because of setback or site
cover requirements, and the like. A particular consideration here concerns the rules
about shadow, which operate as a de facto setback requirement on the southern side.
One suspects that the definition was formulated very much with greenfield
developments and broad acres in mind. The centrality of the flowchart in the
Policies is such that I entertain considerable misgivings about regarding the
philosophy provision as a source of rights or obligations. The extent to which the
“philosophy” of the Uniform Civil Procedure Rules in r 5 may have such an effect
is still being worked out. It has been used to support decisions about costs.
[18] Accepting that it may be seen as straining things to an extent, I have concluded that
the appropriate element of flexibility or discretion is conferred by reference to yield
factor, that in circumstances such as the present where (relevantly) no land is lost,
because reference is to net area after the road dedication, that constraints may
nevertheless be considered, and that expression interpreted widely. I am concerned
that such an approach may sabotage the effort culminating in the Policies to avoid
the need for case-specific determination about contributions in development
applications generally. However, the Guidelines contemplate it and, further, it may
well be that instances of arguable underdevelopment as stark as the present are not
common.
[19] Callinan J said in Temwood at 512 it was “highly unlikely that the legislature of
Western Australia would have intended to confer upon any planning authority in
that State a power to impose conditions that were not reasonably required by the
subdivision.” In similar vein, I would not impute to the Council an intention to
impose conditions not reasonably required by a particular development. The clear
-- 17 of 30 --
18
statement of philosophy confirms that approach. Adopting a practical,
commonsense and broad interpretation, as the court is expected to do in respect of
local governments’ planning schemes, the yield factor has to be construed as
supplying the mechanism whereby requirements of relevance and reasonableness,
whatever their genesis, may be satisfied. There are two features inviting a flexible
approach to yield factor over and above the Guidelines’ contemplation that “planned
yields are reasonable”: terms may not be explained in a “glossary” with the same
rigidity as in a “definition” or a dictionary of the kind found in modern legislation;
further, some looseness may be imported by the use of “represents”, rather than
“means” or “is”. In similar vein, I would not read the Guidelines as limiting what
the Council may deem “reasonable” to either “policy yield factor” or “planned yield
factor”. A suitable outcome may come somewhere in between.
[20] The appellants, who bear the onus, under s 4.1.50(1) of the IPA, have not satisfied
me that it is irrelevant to or an unreasonable imposition on the development actually
proposed to require a contribution whose calculation is based on a number of ETs
greater than that actually proposed. It is not necessary to repeat what was said in
Hickey Lawyers regarding the imprimatur given to the Policies by the IPA in its
current form, which I think is a factor in assessing reasonableness issues, as is the
methodology followed in devising the Policies. It is made clear elsewhere that this
does not mean the outcome in respect of a particular proposed development will
pass muster 1 . The Full Court in Sabdoran Pty Limited v Hervey Bay Town Council
[1983] 2 Qd R 172 accepted that financial contributions for infrastructure
disproportionate to the demand created by a particular proposal may be reasonable.
Connolly J said at 180-81:
1 Instances of conditions that might reasonably be seen as disproportionate to actual development
proposed can be found in the cases mentioned in Hickey Lawyers in par [10]
-- 18 of 30 --
19
“A more difficult question arises in relation to the quantum of the charge.
It is obviously questionable whether a condition which requires the
subdividers of the first 400 blocks to pay four times the cost, assuming that
cost to be distributed over 2,600 allotments, can be described as so
unreasonable that no reasonable planning authority could have imposed it.
As I have already said, it is not for this Court to determine what would be a
reasonable charge. The answer to that question obviously goes beyond
matters of law. We cannot interfere unless persuaded that the charge is
wholly unreasonable. Now the way in which I have posed the question
may seem to lead to an affirmative answer but it must be remembered that
there is in truth no prospect of 2,600 allotments being opened and provided
with water at much the same time. On the contrary, the implementation of
Stage I is expected to take 15 to 18 years. Over that period the respondent
must put the Stage I works into operation and maintain them, bearing
holding costs and getting a return in terms of rates which in the early years
will be small. Of the nature of things, local authorities operate on
borrowed funds for capital works. Commercial subdivision must always
face local authorities with demands for various services the funding of
which, if they are to be provided at all, must be within feasible limits.
Moreover there is no real certainly that 2,600 allotments will ultimately be
served by the Stage I works. Bearing all these considerations in mind, I am
not prepared to conclude that no reasonable planning authority could
require of the first developers that they pay very much more than their
theoretical share of the cost of the development.”
[21] The bulk of Mr Ure’s submissions, reflecting the evidence and arguments in the
appeal generally, went to the “appellants’ alternative submission” which the court
endorses, that the yield factor is capable of and should be subjected to reduction to
produce an appropriate outcome in a special case. This poses the question, what is
the realistic maximum development potential of the site? A contrast is made with
the theoretical maximum development on which the calculation methodology set
out in the flowcharts is based.
[22] Annexure B to Mr Venn’s report, Exhibit 8, is a record of a conclave which he, as
the Council’s consultant planner attended with the appellants’ planner and which, as
he said, produced no agreement on any particular points in dispute:
“31 May 2005
RECORD OF CONCLAVE
POINTS OF AGREEMENT
-- 19 of 30 --
20
• Site address 79 Garfield Terrace, Surfers Paradise;
• Site within Precinct 2 of Surfers Paradise Local Area Plan
• Site designation ‘highrise accommodation’;
• Desirable maximum height (LAP Map 2.3) 30 storeys;
• Applicable Planning Scheme Code – ‘High Rise Residential
and Tourist Accommodation Code’;
• Gross site area of 792 sq.m. affected by road dedication of
45 sq.m. resulting in net site area of 749 sq.m.;
• Provision of Yield Factor not exploited;
• Setback from seawall suggested by the Acceptable Solutions
does not affect the land as the offset of it to the Esplanade
boundary exceeds the 8.1m setback;
POINTS MADE BY MR. RANSOM WERE
• All recent developments on beachfront sites of a similar
nature have been in a ‘one unit per level’ format due to the
fact that the economies of the exercise dictate that large
units be provided to meet market expectations;
• The proposal to amend the Planning Scheme to allow plot
ratio of 4:1 was known at the time of the Pre-Lodgement
Meetings but it was not possible to achieve, due to the
interaction with other planning parameters that act to
provide a building envelope that is acceptable to Council,
i.e. beach shadow requirements, southern shadow
requirements, car parking requirements, landscaped area
requirements, etc.;
• 13/14 storeys had been achieved across Enderley Street
owing to the luxury of being able to allow shadow to cross
the street – which was not possible on the subject site;
• While it was the case that the beach shadow criterion had
not been reached, height was controlled instead by the
shadow to the southern boundary which Council had not
shown a history of relaxing, but if Council were to agree in
this instance then advantage would be taken of it;
• The Yield Factor incorporated into the Policies had not been
raised at the pre-lodgement meetings. The Yield Factor
concept is acceptable if Council were to change
infrastructure contributions at a rate relative to the
theoretical maximum potential of the site;
• It is absolutely impossible to achieve the maximum
permitted residential density on the site in a manner that
would result in the development being approved by Gold
Coast City Council. It may be possible to increase the
-- 20 of 30 --
21
number of dwellings within the development scheme as it is,
but again, it would be impossible to achieve the maximum;
• Irrespective of the fact that smaller units could be
configured, the market demand has been met and the Policy
should be based on that. It would be impossible to develop
single and double bedroom units on the site in a manner that
would be economically viable. There is no point charging
infrastructure against the development in relation to a design
that would never actually be developed. The market will
always provide larger residential units on beachfront sites
such that the potential yield will not be achieved in the vast
majority of instances. If Council plan their infrastructure on
the basis that beachfront sites will be maximized in terms of
residential density, there will be significant over capacity in
the infrastructure system;
• In regard to Mr Venn’s proposition that the site could be
maximised through the use of 20 or so 3 bedroom units, not
2 bedroom units, 45m2 of landscaped area would be required
for each 3 bedroom unit in accordance with Council code
requirements, meaning that the total landscape area
requirement would be approximately 900m2 or significantly
larger than the area of the site. Mr Ransom then made the
point that the Council would rigidly adhere to this
requirement, and that this will regulate the number of units
on the site;
• The car parking configuration required to service 20 units
was impractical. He indicated that he was not aware of any
similar situation anywhere where such a basement
arrangement has been constructed and that the high
construction costs would prevent this from occurring, (20 x
3 bedroom units would require approximately 46 spaces to
be provided within the proposed basement);
• The Infrastructure Charges Scheme consists of 4
components, three of which are charged on a theoretical
maximum development scenario, while the fourth
(Transport) is based on the actual demands created by the
development. The Transport method is a more equitable
method of measuring the Impacts associated with the
development; and
• Not every site in Surfers Paradise will be developed to an
RD8 density, as a very large site area and usable site shape
and location will be required to overcome the other
applicable development parameters. Half of the sites in the
locality (including the majority of site located on the
beachfront) would fall into this category. If Council
-- 21 of 30 --
22
construct their infrastructure on this basis, there will be a
significant oversupply in the system.
POINTS MADE BY MR. VENN WERE
• The Planning Scheme need not take cognisance of the
particular market preference of the day; The Planning
Scheme need only consider practically feasible, and not
market driven, unit sizes and configurations;
• Irrespective of number of units desired and practicality of
car parking, a consideration of development attainable
required one to take into account that which was physically
possible;
• The development parameters offered by the Council-desired
Solutions were generally achievable given the view that
Council has exhibited in the past to relaxation of parameters;
• It is a valid planning outcome to consider that shadow may
climb up an 1800 boundary fence but not exceed it – thus
permitting 10 instead of 8 storeys;
• The currently proposed building envelope could be
configured for 24 small units comprising 48 bedrooms;
• The Planning Scheme maximization of a development
containing 60 bedrooms was achievable within a building of
10 storeys occupying 40% site cover at less than 4:1 plot
ratio;
• The car parking configuration is practical and engineeringly
feasible;
• Infrastructure provision cannot respond to individual site
constraints or market preferences, it must be funded and
instituted prior to the construction of the majority of
development that it is to serve, or even be applied for;
• The answer to ‘attainable yield’ is not to be derived from
what is normal practice by Council’s assessment managers
in interpreting discretions to relax various Acceptable
Solutions of the Codes but what features of a proposal offer
realistic and sustainable planning options in pursuit of a
Performance Criterion based solution that will satisfy the
particular Purpose of the relevant Code.”
-- 22 of 30 --
23
[23] Mr Ransom’s report is Exhibit 1. Both planners gave evidence. Mr Venn’s point
was to show that the maximum theoretical yield was actually achievable, making in
passing a criticism of the appellants at 4.12.1:
“It is also noted from the application documentation for the subject
matter, that the applicant (Clift) discarded the notion of
amalgamation although no valid reasoning was offered. The fact that
applicants on both sides seek similar development must signal a
willingness to curtail the existing use and a desire to realise an
advantage from redevelopment. This, of course, does not, of itself,
signify any probability of amalgamating the properties but it does
signify a potential.”
The information Mr Venn thought he had about an application from the site’s
southern neighbour proved to be inaccurate. His report went on to note:
“4.12.2 Both the Planning Scheme and the SEQRP (South-East
Queensland Regional Plan) encourage amalgamation in the
interests of a more efficient land use pattern, consolidation
of the urban footprint, efficiency of infrastructure provision
and, in the case of the Planning Scheme, through the plot
ratio bonus policy.
4.12.3 That being the case, it is legitimate for a planning policy to
maintain a level of charging commensurate with that
potential, but as yet unfulfilled, development intensity
facilitated by the Planning Scheme. However, there appears
little point on theorising on site amalgamation as the
development yield possible, as calculated in the above
sections, fulfils the intent of the Planning Scheme
instruments in any event.”
Mr Venn reached that conclusion on the basis of a hypothetical exercise, which
attracted a response in terms of the difficulties the Planning Scheme placed in the
way of this theoretical development. Mr Ransom had the advantage of intimate
association with the appellants’ proposal, which has been fully designed, to the
stage of approved plans. Notwithstanding Mr Venn’s apparent confidence that
answers could be found to the criticisms raised, I did not find this persuasive. His
proposal of a 10-storey building would necessitate a second lift, reducing the space
available per floor to accommodate units, which is limited by the 40 per cent site
-- 23 of 30 --
24
cover requirements. Compliance with the requirements for on-site parking would
dictate that there be four or more basement levels, something unprecedented for
such a small site, likely to encounter problems with the water table, even if it were
economical to construct. The provision of ramps to allow movement between
levels would lead to an inefficient design, with much “waste” space. Mr Venn
knew of parking basements of such depth elsewhere on the Gold Coast, in
commercial developments. There was mention of possible use of a lift to transport
vehicles to and from basement levels, but that was not gone in to in any detail.
[24] Perhaps most significant is the difficulty the southern shadow of Mr Venn’s
theoretical 10-storey building would cast. The ordinary standards (acceptable
solutions) require that the shadow to true south of a building be confined to its own
site. Relaxation is possible, but comes at the cost of the amenity of the southern
neighbour. The only instances of relaxation actually being obtained which the court
heard of arose in exceptional circumstances, such as the southern neighbour’s being
a commercial development where there already existed a large blank wall. I am not
persuaded by Mr Venn’s assertion (vital to the maintainability of a project of
10 storeys) of the acceptability of a southern shadow touching the top of a standard
1.8 metre fence along the boundary – on a theory that such a fence, if solid, would
cast its own shadow. The High Rise Residential and Tourist Accommodation Code
provides:
PERFORMANCE CRITERIA ACCEPTABLE SOLUTIONS
PC19
The building must be located on the
site so as to minimise the period of
shadow intrusion onto surrounding
sites or other buildings on the same
site.
AS19
The shadow cast by the building in a
true south direction has a length of
0.25 times the height of the building,
as measured from ground level
adjacent to the southern side of the
subject building to the top of the
topmost storey, and does not intrude
onto any other site, or does not cast
shadow onto any other building on the
-- 24 of 30 --
25
same site.
[25] On analysis, the gesture made towards limiting shadow is fairly paltry. It is only the
true south shadow which is considered, a phenomenon which would be encountered
only momentarily each day. Common experience is that, in winter, shadow cast by
structures to the north at the other moments of the day may be very substantial.
Mr Ransom’s assertion is credible (and one would hope) that the Council would not
contemplate any significant relaxation in the absence of consent from the southern
neighbour or equivalent circumstances.
[26] Mr Venn’s proposed building appeared to require 42 per cent site cover, again
something unprecedented (according to Mr Ransom and the Council’s supervising
planner for material change of use “city wide”, Mr Sharpe) for any building above 5
storeys in height. See PC3.
[27] It is worth setting out Mr Ure’s submission regarding PC22, which:
“requires that the development must provide sufficient communal
open space which provides adequate and useable recreational areas
required to service the needs of residents or guests of the
development and aesthetically complements the buildings and
enhances the attractiveness of the development.
The acceptable solution suggests, and Mr Venn agrees, that it would
be appropriate to provide for a three-bedroomed scenario 900 sq.m
of communal open space for recreation and landscaping purposes.
The acceptable solutions also provide that at least 10% of the site
area compromise deep planting.
It is unlikely that this could be achieved as Mr Venn’s basement car
park occupies almost the entirety of the site.
Mr Venn suggests that 316 sq.m could be provided on a roof terrace.
This exceeds the 40 per cent site coverage (298.8 sq.m) and does not
take into account roof services such as lift plant, stairwells, etc.
-- 25 of 30 --
26
Further, it is difficult to see how landscaping on a roof terrace could
be said to ‘aesthetically complement the buildings and enhance the
attractiveness of the development’.
Mr Venn was driven to suggest that there could be a basement
gymnasium in the order of some 200 sq.m. Such a facility could not
be considered communal open space. In Ritek Building Systems
(NQ) Pty Ltd v Cairns City Council [2005] QCA 347 McPherson JA
said:
‘It is not easy to see that an area enclosed by a floor, four
walls and a ceiling is an open space according to any
ordinary meaning of those words.’”
[28] It is unnecessary in the circumstances to descend to any detail regarding the points
raised against Mr Venn’s hypothetical in relation to PC1 (site setbacks), PC11
(landscaped areas adjoining frontages which enhance the streetscape), PC7
(articulation of walls) and PC16 (which would require 66 car parking spaces, and
maybe five or six levels of parking on top of the gymnasium, “for the Council’s 57
one-bedroom scenario”). In those instances, Mr Venn’s hypothetical building may
well be susceptible of redesign. Otherwise, I think the difficulties raised by the
appellants are pretty well insurmountable, that the proposal is one which,
realistically, could never be built, unless the Council abandons any regard for the
amenity of neighbours. It seems to me fundamentally unsound to rely on
“relaxations” in a context like the present, to postulate a maximum potential
development having nothing to do with the development actually proposed, for the
purpose of exacting contributions. In my opinion, the exercise of calculating
contributions should ordinarily be conducted on the basis of a development which
complies with the ordinary development standards set out in acceptable solutions. I
think it is reasonable to regard the acceptable solutions as “constraints”, and to
avoid contemplating that a developer has to beg for some indulgence.
-- 26 of 30 --
27
[29] Mr Murphy was called to establish that the market was such that in this location, no
more than one unit per floor on a site of this size would be expected. Mr Venn was
postulating combinations of units, ranging in size from one bedroom to three.
Applying the formula of one bedroom per 13m2 of net site area, to indicate
57 bedrooms, many combinations would be possible. The Council’s approach was
that there could be two three-bedroom units on a floor, three two-bedroom units.
Mr Venn identified other developments (not on the beach) where apartments of the
modest proportions involved were being provided. The evidence about it persuades
me that, for prime sites on the beach, where land is extremely expensive, there is no
shortage of willing buyers for large “one per floor” apartments. There would be no
shortage of buyers for the multi-floor apartments proposed by the Clifts,
presumably. The buildings identified by Mr Venn and Mr Sharpe as containing
one-bedroom units and two-bedroom units are not comparable, as their sites are not
comparable with the Clifts’. I am in no doubt that, if they chose to develop one or
two-bedroom units, there would be buyers available for them, too. I do not consider
that there is anything requiring the court to say that the Planning Scheme or the
Policies require a developer to opt for a greater number of units, as opposed to a
lesser number, on pain of being subjected to penal contributions. (It has to be
remembered that we are dealing with a planning area where heights of 30 storeys
are encouraged, something totally unachievable on this site.)
[30] Assuming that the court has become charged with working out, on the basis of the
evidence, what is the “yield factor”, there may be a range, all the way from
Mr Ransom’s First Class Development of 12 bedrooms to something within striking
distance of Mr Venn’s Economy 57. The obstacles faced by the latter, outlined
above, are such that it is difficult to know how far to scale back. I am not persuaded
-- 27 of 30 --
28
that a building over nine storeys is feasible. There remains the issue of “how many
units per floor?” The principal constraints here relate to on-site parking and the
feasibility of multi-level basements, also communal open space. It is not clear that,
in practice, the requirements under acceptable solutions for even two units per floor
could be provided. Those were the difficulties identified by Mr Ransom in his
evidence at p 61 where he expressed the opinion that “the greatest density you could
realistically achieve on this site would be one unit per floor. It would be a three-
bedroom unit…” He went on to note that no investigation or detailed design had
been done “and that it may well be that there are still planning parameters that might
even prevent that occurring”. I am not persuaded that the reservations mentioned
make it inappropriate to find that nine three-bedroom units could realistically be
constructed, one per floor. It might be that, unusually, the highest would be the
smallest, depending on what facilities were to be provided on top of the building
and shadow considerations. It would be regrettable if it were necessary to embark
on detailed theoretical design exercises just for the purpose of calculating
contributions under the Policies.
[31] The cross-examination of Mr Ransom was directed towards getting him to accept
that Mr Venn’s approach was reasonable, that the relaxations needed could be
expected. Mr Ransom gave nothing away. He was not really challenged about his
own opinion about maximum realistic development. In the circumstances, I
propose to act on it, and eschew the exercise of selecting some number of three-
bedroom units between nine and 17 or so. I will leave to the parties what is
presumably a simple mechanical exercise of working out where the flowcharts lead
on that basis.
-- 28 of 30 --
29
[32] Some time was spent dealing with the assertion made in the appellants’ case that
they or their successors in title would be overcharged for infrastructure upon future
redevelopment of the site. Exhibit 5A was a table prepared by Mr Sutherland to
demonstrate this phenomenon, which Mr Ransom said concerned him: he “wouldn't
put it past them (the Council)” (142). The concern is based on the theory that,
although a developer has made relevant infrastructure contributions for a site in
reference to some theoretical ET or number of bedrooms, when contributions come
to be assessed for a future redevelopment, credit will not be given against future
contributions towards the same type of infrastructure for what was actually paid in
the past, but only for the (lower) level of contributions which would have been
attracted by the constructed development on the site. It is said that a literal reading
of flowchart provisions indicates the approach of reference to existing use of the
site, rather than contributions paid. The new infrastructure charging regime
embodied in the Policies necessarily focuses on existing use and development,
because there will have been no contributions in the past. It seems to me the
appellants’ fears are groundless and that the court should not be troubled by
suggestions that, if credits are allowed for actual contributions, they may be lost
because records go astray. Assuming the Policies endure, I do not think they can be
construed to permit overcharging of the kind allegedly feared. The point was made
with a view to persuading the court to limit contributions now strictly to the
development actually proposed, the dimensions of which can readily be discovered
on an inspection.
[33] On the Council’s side, the inconvenience flowing from some future redevelopment
of greater intensity (leading to more contributions being collected) was alluded to.
It was suggested the Council would be happy if the appellants and their successors
-- 29 of 30 --
30
in title could, in some binding way, be precluded from developing more intensively
– which would give the Council some certainty about the long-term demands of the
site on the services it has to provide. There is probably no opportunity remaining in
this appeal to explore it, but a possibility might be for the Council (which takes
many other easements) to take a volumetric easement over the space above the
building, so as to preclude any taller future development without the Council’s
consent. That would presumably have some impact on the site’s market value.
[34] There is no perfect solution in a situation like this. From the planner’s perspective,
(like others) the site is too small: the Council suffers the disadvantage of many
governmental institutions in a free society that if the people are left to make their
own decisions, the result will not necessarily match what the instrumentality expects
or desires. Long-term infrastructure planning is going to be a difficult exercise –
under-provision will be costly to remedy; over-provision will waste resources. Only
by “fluke” will the Policies work perfectly, (especially in “brownfields” where
unpredictable redevelopment is under way on a site by site basis). In my opinion it
has to be acknowledged that they cannot reasonably be made to work perfectly. It is
not acceptable, if s 3.5.30 (or the philosophy) applies, to adopt what I dubbed the
“key money” concept. The position seems to be that the Council must make its best
judgment about what infrastructure should physically be constructed when the time
for actual construction arrives and, if contributions collected under the Policies are
insufficient, fund the shortfall from other resources. It may turn out that future
redevelopment brings in some reimbursement. Either way, we are dealing with one
of the burdens of governmental responsibility.
[35] The appeal succeeds.
-- 30 of 30 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2005/106