Chang & Anor v Laidley Shire Council [2005] QPEC 75
PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND
CITATION: Chang & Another v Laidley Shire Council [2005] QPEC 075
PARTIES: SHU-LING CHANG
Appellant
TAI-HSING CHEN
Second Appellant
LAIDLEY SHIRE COUNCIL
Respondent
FILE NO/S: BD464 of 2005
DIVISION: Appellate
PROCEEDING: Application in Pending Proceeding (Appeal)
ORIGINATING
COURT: Planning and Environment Court, Brisbane
DELIVERED ON: 18 August 2005
DELIVERED AT: Brisbane
HEARING DATE: 4 August 2005
JUDGE: Robin DCJ
ORDER: Application dismissed
CATCHWORDS: Integrated Planning Act 1997 (IPA) ss 2.5A.24, 3.2.1(7)(f),
4.1.5A
“Draft Regulatory Provisions” (DRP) included in the Draft
South East Queensland Regional Plan expressed to “have
effect” from gazettal (on 27 October 2004) – whether
prohibition contained therein of development by way of
subdivision into lots smaller than 100ha applied to –
subsequent development application (superseded planning
scheme) for reconfiguration of 16.67ha into 25 lots – DRP
exception for “land designated or zoned for rural residential
purposes” held to cover land so designated or zoned as at
commencement of DRP – although site was so zoned in 1996
Planning Scheme, its designation changed to rural landscape
in the new planning scheme as from 28 March 2003 –
Council could refuse to accept the development application
(superseded planning scheme) notwithstanding IPA
provisions permitting it for 2 years from that date –
consequence that applicants shut out of potential
compensation under IPA s5.4.2 – s 4.1.5A of IPA not
-- 1 of 20 --
2
available to save an application for development that is
prohibited
COUNSEL: Mr T Trotter and Mr Keliher for the Applicants/Appellants
Mr Hinson SC for the Respondent
SOLICITORS: Robert Milne Legal for the Applicants/Appellants
Connor O’Meara for the Respondent
[1] Before the court for determination (pursuant to an order of Judge Wilson SC of 1
July 2005) is the Appellant-developers’ “application in pending proceeding” for
determinations by the court:
“That the Application that is the subject of this appeal:
a) is not contrary to the draft regulatory provisions of the
Draft South East Queensland Regional Plan (“the Draft
SEQ Regional Plan”) as it is a reconfiguration for rural
residential purposes in accordance with section 4(3)(c)(i) of
the draft regulatory provisions, being the zoning under the
superseded planning scheme.
b) In addition or in the alternative to (a) above, is not contrary
to the draft regulatory provisions of the Draft SEQ
Regional Plan as it is associated with a material change of
use for which a development approval is in effect, in
accordance with section 4(3)(b) of the draft regulatory
provisions as in effect on 28 October 2004, being a
rezoning approval.
c) In addition or in the alternative to (a) and (b) above, the
Application remained a current application despite the
Respondent returning the application fees to the Appellants.
d) The Application is a properly made application pursuant to
section 3.2.1 of the Integrated Planning Act 1997.
e) The Respondent must give to the Appellants an
acknowledgement notice. …”
[2] The Appellants did not pursue (b). Their underlying appeal is “against the refusal by
Laidley Shire Council (the Respondent) to grant a development approval … for the
Reconfiguring of a lot under a Superseded Planning Scheme”, seeking that the
appeal be allowed, the development application “be accepted as a properly made
-- 2 of 20 --
3
application” and be approved subject only to the imposition of reasonable and
relevant conditions.
[3] The Council received the application (to reconfigure a 16.67 hectare site as 25 rural
residential lots) on or about 3 December 2004. It advised its approach in a letter of
21 January 2005:
“Council advises that the Acknowledgement Notice for this
development application is due to be given on Monday, 24 th January
2005, and this letter is designed to explain why the Council will not
be issuing an Acknowledgement Notice.
We note:
1. The application was lodged after 28 October 2004, the day when
the Draft Regulatory Provisions of the Draft South East
Queensland Regional Plan took effect and seeks to create
allotments having an area less than 100 hectares;
2. The application relates to land in Regional Landscape and Rural
Production Area;
3. The land is currently zoned “Rural Landscape” in the Laidley
Shire Planning Scheme;
4. The land was zoned “Rural Residential A” under the transitional
planning scheme;
5. The application is a development application (superseded
planning scheme).
Section 4 of the Draft Regulatory Provisions provides:
1. Subsection (2) applies for land in the following areas:
(a) the Regional Landscape and Rural Production Area;
(b) …
2. Reconfiguration of a lot may not occur if any resulting lot
would have an area less than:
(a) If the planning scheme states a minimum lot size
greater than 100 hectares – the area stated
(b) To the extent the land is located in a designated
agricultural area the minimum lot size stated in the
planning scheme; or
(c) In any other case – 100 hectares.
3. However subsection (2) does not apply if:
-- 3 of 20 --
4
(a) …
(b) …
(c) The reconfiguration is:
(i) For rural residential purposes on land
designated or zoned for rural residential
purposes; and
(ii) The application for the reconfiguration is
made within two years of the day these Draft
Regulatory Provisions came into effect”.
Legal advice the Council has obtained has concluded that the
exception created by section 4(3)(c) of the Draft Regulatory
Provisions does not apply to this development application as the land
is currently not designated or zoned for rural residential purposes.
Consequently the development application is contrary to the Draft
Regulatory Provisions and, pursuant to section 3.2.1(7)(f) of the
Integrated Planning Act 1997, is not a properly made application.”
(The erroneous reference to 28 October 2004 (a day late) is replicated elsewhere.)
[4] At some point fees of $4,200 which had accompanied the development application
were returned. There was no attempt by the Council to exercise any discretion it
might have had under s3.2.1(9) of the Integrated Planning Act 1997 (IPA) to
“accept” the development application. In the circumstances there is no “refusal” of
it to be the subject of the appeal. The parties were not interested in pursuing arid
procedural points; rather, they were content to have the court determine the issues –
which are important ones regarding the effect of the first instalment of changes in
the planning regime for south-east Queensland in the form of the Draft South-East
Queensland Regional Plan. That instrument or document was gazetted on 27
October 2004 (see Exhibit 1) when the responsible Minister notified under s2.5A.14
of the IPA that it was available for inspection and comment. The IPA had already
been amended to provide for the making of “The SEQ Regional Plan”. See Chapter
2, Part 5A. Section 2.5A.10 is:
“(1) The SEQ regional plan is the instrument made by the
regional planning Minister under section 2.5A.15(2).
(2) The SEQ regional plan is a statutory instrument under the
Statutory Instruments Act 1992 and has the force of law.”
-- 4 of 20 --
5
[5] Public consultation about the contents of the Plan was envisaged, for which purpose
s2.5A.13(1) required the Minister to “prepare a Draft SEQ Regional Plan”. Section
2.5A.24(1) provides:
“(1) When a notice is published under section 2.5A.14(1)(a), any
proposed regulatory provisions of the draft SEQ regional
plan (the draft regulatory provisions) have effect until the
SEQ regional plan comes into effect.”
[6] It might be noted (the parties did not refer to it) that it is declared in subsection
(5)(b) that “draft regulatory provisions may state transitional arrangements for
development applications affected by the draft regulatory provisions.”
[7] Part G of the Draft SEQ Regional Plan contains the “Draft Regulatory Provisions”
referred to. Section 1 allocates all land in the region to one of the following:
“(a) Regional Landscape and Rural Production Area;
(b) Rural Living Area;
(c) Urban Footprint;
(d) Investigation Area;
(e) Mt Lindesay/North Beaudesert Investigation Area.”
[8] The mapping referred to allocates the Appellants’ land to (a). Quite specific
provision is made in the DRP about certain development:
“Division 3 – Provisions regulating development (Act
s2.5A.12(2)(d))
4. Certain reconfiguration prohibited
(1) Subsection (2) applies for land in the following areas:
(a) the Regional Landscape and Rural Production Area;
(b) the Investigation Area;
(2) Reconfiguration of a lot may not occur if any resulting lot
would have an area less than:
(a) if the planning scheme states a minimum lot size
greater than 100 hectares - the area stated in the
planning scheme; or
(b) to the extent the land is located in a designated
agricultural area the minimum lot size stated in the
planning scheme; or
(c) in any other case - 100 hectares.
(3) However subsection (2) does not apply if:
-- 5 of 20 --
6
(a) the number of lots that would be created by the
reconfiguration is the same or less than the number
of lots to be reconfigured; or
(b) the reconfiguration is associated with a material
change of use for which a development approval is
in effect; or
(c) the reconfiguration is:
(i) for rural residential purposes on land
designated or zoned for rural residential
purposes; and
(ii) the application for the reconfiguration is
made within two years of the day these Draft
Regulatory Provisions came into effect.”
[9] Section 2.5A.12(2)(d) provides that “regulatory provisions” which may be included
in “the SEQ Regional Plan” may “otherwise regulate a development by, for
example, stating aspects of development that may not occur in stated localities; [and
(e) state transitional arrangements for development applications affected by the
regulatory provisions]”.
[10] The era of the DRP came to an end on 30 June 2005, the day when there was
gazetted the Minister’s notification under s2.5A.16 “that the South East Queensland
Regional Plan 2005-2026 (the SEQ Regional Plan) was made on 29 June 2005 and
has effect on and from 30 June 2005”. See Exhibit 2. The South East Queensland
Regional Plan 2005-2026 includes Part H Regulatory Provisions, which are not in
exactly the same terms as the superseded Part G draft regulatory provisions. It is
now s5 that controls subdivision for land in the (a) area. It was common ground
between the parties that the now superseded s4 is the provision requiring
consideration by the court; subsection 3(c) makes transitional arrangements which
the Appellants contend are applicable; no other potentially relevant transitional
provisions were pointed to.
[11] What is at stake for the Appellants is their ability to carry out the reconfiguration
they applied for. Also at stake, if they are denied that ability, is their possible claim
-- 6 of 20 --
7
to compensation. The IPA deals with the topic of compensation for what used to be
called injurious affection by changes in planning arrangements in Chapter 5, Part 4,
most importantly s5.4.2:
“5.4.2 Compensation for reduced value of interest in land
An owner of an interest in land is entitled to be paid reasonable
compensation by a local government if--
(a) a change reduces the value of the interest; and
(b) a development application (superseded planning scheme) for
a development permit relating to the land has been made;
and
(c) the application is assessed having regard to the planning
scheme and planning scheme policies in effect when the
application was made; and
(d) the assessment manager, or, on appeal, the court--
(i) refuses the application; or
(ii) approves the application in part or subject to
conditions or both in part and subject to conditions.”
[12] Only by the steps described in (b), (c) and (d) may the Appellants avail themselves
of possible compensation. Mr Trotter, for the Appellants, collected authorities
demonstrating the law’s approach to construction whereby in cases of injurious
affection, exclusion of compensation is not lightly found. See Kettering Pty Ltd v
Noosa Shire Council [2004] HCA 33 at [31] and [32], Resort Management Services
Ltd v Noosa Shire Council (1996) 92 LGERA 387, at 389-391 and 392 (a case about
s20(2)(c) of the Acts Interpretation Act 1954), Mabo v Queensland (No. 2) (1992)
175 CLR 1 at [62] and Bromley v The Forestry Commission of NSW [2001]
NSWCA 34 at [44]. However, there can be injurious affection or dispossession
without compensation, as in Bone v Mothershaw [2003] 2 Qd R 600; 121 LGERA
75. See in particular para. [37], per Williams JA.
[13] Mr Hinson SC (for the Council, which may be presumed to be unenthusiastic at the
prospect of having to pay compensation to the Appellants) pointed to s5.4.4(1) of
the IPA whereby:
“(1) Despite sections 5.4.2 and 5.4.3, compensation is not
payable if the change–—
-- 7 of 20 --
8
(a) has the same effect as another statutory instrument, in
respect of which compensation is not payable …”
It is not clear that the DRP, which are silent as the compensation, are a statutory
instrument, although appearing to satisfy s7(2) and (3) (notification of a public
nature) of the Statutory Instrument Act 1992; one would think that the “effect”
given to them by s2.5A.24(1) corresponds with the effect enjoyed by the SEQ
Regional Plan; it is given statutory instrument/force of law status by s2.5A.10(2). It
appears to follow that the IPA provisions about compensation admit of significant
exceptions.
[14] Mr Trotter and Mr Keliher, appearing for the Appellants, supplied a written outline
of argument containing the following summary:
“1. In this matter it is appropriate to take a purposive approach
when reading the various provisions. The purpose of the
Draft Regulatory Provisions having immediate effect is to
maintain the status quo until the final SEQ Regional Plan
takes effect. There is no apparent purpose to remove the
rights of persons in the situation of the Applicants to lodge a
superseded planning scheme application, nor is there any
apparent purpose to remove their potential rights to
compensation.
2. There is no necessary inconsistency between the provisions
of the Draft Regulatory Provisions and the sections of the
IPA permitting the making of a superseded planning scheme
application; they can be read together, and should be so read.
3. The provisions of the Draft Regulatory Provisions should not
be read in such a way as to impliedly repeal sections of the
IPA in the circumstances of this matter.
4. It is not correct to read the provisions in such a way as to not
only find inconsistency but to find an implied repeal in these
circumstances, as such a reading would take away vested
rights, including a potential right to compensation.
5. The Draft Regulatory Provisions are regulations made under
delegated authority made under one Part of the IPA and can
therefore not be inconsistent with other Parts of the IPA.
6. Despite the introduction of the Draft Regulatory Provisions,
the Applicants’ right to lodge a development application
-- 8 of 20 --
9
(superseded planning scheme) remained extant until 28
March 2005.
7. The wording of s.3.2.1(7)(f) of the IPA involves a conclusion
of law that would ordinarily fall within the jurisdiction of this
Court in determining an appeal on its merits. Such
determination would include reliance on many provisions of
the IPA, including s.4.1.5A.
8. Unlike the matters referred to in s.3.2.1(10) of the IPA, the
assessment manager, in this case, is entitled to accept the
application, even if it is, in his opinion, not properly made.
9. Given the consequences for the Applicants in the current
circumstances, it is appropriate that the Court exercise its
discretion if that be necessary under s.4.1.5A. Such discretion
extends to circumstances where the application is not
properly made.1 ”
[15] The proposition in the second sentence in para. 1 is one borne out by the
explanatory notes accompanying the Integrated Planning and other Legislation
Amendment Bill 2004 in respect of the provision which became section 2.5A.24:
“The key reason for the regulatory provisions to have effect is to
ensure that the provisions can implement a “holding pattern” with
respect to key regional development outcomes pending the
finalisation of the regional plan, amendment or replacement”.
I have difficulty in reconciling the Appellants’ proposition which follows that
sentence. By definition, a “holding pattern” is compromised by letting through any
new applications for rural residential-type development in areas where such
development is clearly intended to be prohibited. As has been seen, the DRP leave a
door open to a limited extent. It is a question whether section 4(3)(c) avails the
Appellants.
[16] They had every expectation, prior to 27 October 2004, of being able to establish a
rural residential subdivision on their land. On 4 December 1992 in respect of that
land there was gazetted an Order in the Council excluding it from the Rural “A”
zone as provided for in the Planning Scheme in the Shire of Laidley (its approval
had been notified in the gazette on 12 November 1977) and including it in the Rural
Residential Zone. That zoning continued by its adoption in the Shire’s new planning
-- 9 of 20 --
10
scheme adopted in 1996. It did not survive in the current Planning Scheme for
Laidley Shire gazetted 28 March 2003 in which the land is placed in the “Rural
Landscape” designation; the minimum lot size contemplated for reconfiguration is
60 hectares. Given what Mr Trotter described as the IPA’s “prohibition of
prohibitions”, the current local planning arrangements would not necessarily be
fatal to the development application (superseded planning scheme) lodged on 3
December 2004. Section 2.1.23(2) of the IPA provides that “a local planning
instrument may not prohibit development on, or the use of, premises. Mr Hinson is
correct that the Appellants gain no assistance from the 1992 re-zoning, which came
into effect as an amendment of the 1977 Planning Scheme. The reason is that that
planning scheme was in time superseded by the 1996 one, which, rather than the
1992 re-zoning approval, gives rise to the development rights which the Appellants
seek to exercise. A comparable situation existed in Mimehaven Pty Ltd v Cairns
City Council [2002] 121 LGERA 216. (Section 2.5A.12(3) of the IPA provides that
“regulatory provisions-(a) are taken to be a temporary local planning instrument”;
this is so only to the extent of their doing any of the matters mentioned in subsection
(2)(a)(c); it is not the case in respect of regulatory provisions described by (d) or
(e).)
[17] The “the prohibition of prohibitions” does not apply to the DRP: they do not satisfy
the schedule 10 definition of “local planning instrument” as “a planning scheme,
temporary local planning instrument or planning scheme policy.”
[18] The Appellants’ application to the Council satisfies the requirements of the schedule
10 definition of “development application (superseded planning scheme)” in
particular in having been made:
“(iii) within two years after the day of the planning scheme or
planning scheme policy creating the superseded planning scheme
was adopted or the amendment creating the superseded planning
scheme was adopted.”
[19] Section 3.2.5 regulates acknowledgement notices for such applications. It provides
for things the acknowledgment notice “must state”, including by subsection (3):
“(a) that the application will be assessed under the superseded
planing scheme; or
1 Oakden Investments Pty Ltd v Pine Rivers Shire Council & Anor [2002] QCA 470;(2002) LGERA 256 at 260 Per
Mullins J.
-- 10 of 20 --
11
(b) that the application will be assessed under the existing planning
scheme.”
The former situation is picked up by section 3.5.4(4) of the IPA:
“(4) If the application is a development application (superseded
planning scheme) and the applicant has been given a notice
under section 3.2.5(3)(a), the assessment manager must
assess and decide the application as if—
(a) the application were an application to which the
superseded planning scheme applied; and
(b) the existing planning scheme was not in force; and
(c) for chapter 5, part 1, the infrastructure provisions of
the existing planning scheme applied.”
In such circumstances, as one finds in section 4.1.52(3)(b), the court also must:
“(i) consider the appeal as if the application were made under the
superseded planning scheme; and
(ii) disregard the planning scheme applying when the application was
made.”
On the other hand, where the acknowledgement notice states in terms of section
3.2.5(3)(b), the applicant may be able to establish a claim to compensation if section
5.4.2 is satisfied. The Appellants have been shut out of that possibility (likewise the
possibility of their development application succeeding) by the Council’s refusal to
“receive or to accept” the application.
[20] Section 3.2.1 of the IPA deals with receipt and acceptance of development
applications which must be made to the assessment manager in the approved form
and contain the specified “mandatory requirements”. The concept of a “properly
made application” is created by subsection (7):
“An application is a properly made application if–
(a) the application is made to the assessment manager; and
(b) the application is made in the approved form; and
(c) the mandatory requirements part of the approved form is
correctly completed; and
(d) the application is accompanied by the fee for administering
the application; and
(e) if subsection (6) applies – the application is supported by the
evidence required under subsection (5); and
(f) the development would not be contrary to the regulatory
provisions or the draft regulatory provisions.”
-- 11 of 20 --
12
As its content suggests, (f) was added to the IPA along with chapter 2 part 5A (by
the Integrated Planning and Other Legislation Amendment Act 2004). The new
subsection (10)(b), replicating (7)(f), removes the assessment manager’s discretion
under (9) to receive, and after consideration accept “an application that is not a
properly made application”, whereupon it “is taken to be a properly made
application.”
The remaining subsection to be noticed is:
“(8) The assessment manager may refuse to receive an application
that is not a properly made application”
It would appear that even if the assessment manager purported to act under (9)
“after consideration”, the provision would not have the effect of requiring an
application such as the one presently in issue to be taken to be properly made. In my
opinion, where a development applied for would be contrary to the DRP, the
application for it is not a properly made application.
[21] The lack of a “properly made application” is not necessarily fatal to an applicant’s
cause. A saving indulgence may be made available by the court under section
4.1.5A of the IPA:
“4.1.5A How court may deal with matters involving substantial
compliance
(1) Subsection (2) applies if in a proceeding before the
court, the court -
(a) finds a requirement of this Act, or another Act in
its application to this Act, has not been complied
with, or has not been fully complied with; but
(b) is satisfied the non-compliance, or partial
compliance, has not substantially restricted the
opportunity for a person to exercise the rights
conferred on the person by this or the other Act.
(2) The court may deal with the matter in the way the court
considers appropriate
In respect of the predecessor provision in section 4.1.53, which was more narrowly
expressed, the Court of Appeal in Oakden Investments Pty Ltd v Pine Rivers Shire
Council [2002] QCA 470 took the view:
-- 12 of 20 --
13
“that the expression ‘properly made application’ is used in the
Integrated Planning Act when it intended by the legislature to be
used. The power given to the Court under section 4.1.53 is not
circumscribed by reference to an application that is a properly made
application for the purposes of section 3.2.1 of the Integrated
Planning Act. The operation of section 4.1.53 is not by its terms
limited to IDAS requirements of a procedural kind, and there is no
reason for implying such a limitation”.
I am unable to identify any scope for application of section 4.1.5A here. It was
calculated to provide relief to a person who should and could have complied fully
with some requirement of IPA or another Act. There is nothing the Appellants could
have done to comply with the implied requirement that their proposed development
not be contrary to the DRP, consistently with continued pursuit of that proposal.
[22] Assuming contrariety, Council by subsection (8) was entitled (if not obliged) to
refuse to accept the application. No case is made for this court’s overriding the
Council’s approach.
[23] In a context such as the present it is necessary to be alert to the implications of
section 20(2)(c) of the Acts Interpretation Act 1954, to the effect that the
“amendment” of an Act (which may occur by implication: see (b) in the definition
of “amend” in section 36) does not “affect a right, privilege or liability acquired,
accrued or occurred under the Act” - and of like provisions. The Appellants have
had the right to make development applications in respect of their land all along
which they could expect to have assessed under the law as of the date of the
application. That law included the right to make a development application
(superseded planning scheme) within two years after the coming into effect of a new
planning scheme. Before the Appellants applied, the law was changed by the
coming into effect of the DRP. Barring their disallowance in some way, the IPA
gives them “effect” from 27 October 2004. The Council says they preclude the
development applied for. They certainly do not preclude all development
applications in respect of the land. Whatever may have been the Appellants’
situation had their development application preceded 27 October 2004, I am unable
to perceive any scope for operation of the Acts Interpretation Act. I do not think Mr
Trotter argued otherwise. However, he pointed to it as part of our legal
environment, and a factor which may persuade the court to embark on its task of
construction with a bias against finding inconsistency between the DRP and the
-- 13 of 20 --
14
supporting provisions of the IPA on the one hand and the established provisions of
the IPA (nowhere specifically referred to in recent amendments) which are the
source of the Appellants’ reasonable expectations, on the other. He cited Alexander
Jonathan Brown v Environment Protection Authority [1992] NSWLEC 103 and B
and D Kelly v Shoalhaven City Council [1991] NSWLEC 119.
[24] I do not think it can be contended that the general prohibition in s4 of the DRP does
not apply. While it was not argued that the exemption in (3)(b) applies, it was
contended that the following exemption in (c)(i) for a reconfiguration “for rural
purposes on land designated or zoned for rural residential purposes” did. “Rural-
residential” is defined in the accompanying glossary as “a form of low-density
residential developments characterised by large lots of between 2,000m2 to 5
hectares in a rural or semi-rural setting and with a net residential density of less than
four dwellings or residential lots per hectare,” which is descriptive of the proposed
development.
[25] The crucial issue is whether the land is “designated or zoned for rural-residential
purposes.” It was so zoned in consequence of the 1992 approval, and the 1996
Planning Scheme, but has not been so zoned or designated since 28 March 2003.
Mr Hinson submitted that (c)(i) focuses on a current designation or zoning; the
Appellants’ contention is that some historical examination may be undertaken and
reliance placed on the zoning which prevailed from 1992 until March 2003. Such
an approach may be considered supported by the potential for the Appellants to
make a development application (superseded planning scheme) until 28 March
2005. Mr Hinson pointed to passages at pages 13 and 15 of the Draft South-East
Queensland Regional Plan which in terms indicate that the reference in the DRP is
to the way in which lands are “currently” allocated or zoned:
“The Draft Regional Plan allocates all land in SEQ into one of five
broad categories. These areas provide the spatial context for the
-- 14 of 20 --
15
Draft Regulatory Provisions set out in Part G of the Draft Regional
Plan …
The intent of the Regional Landscape and Rural Production Area is
to ensure its long term protection from inappropriate forms of
development, particularly the encroachment of urban land uses and
the further fragmentation of land holdings for rural residential and
other similar activities. This is achieved through the Draft
Regulatory Provisions of the Draft Regional Plan in Part G.”
“The Regional Landscape and Rural Production Area preserves
existing development rights to ensure the continuation of significant
activities including agricultural production, availability of natural
resources, water storage, tourism, nature-based recreational
activities and nature conservation in currently designated areas.
However, the Regional Plan does envisage that some lands currently
allocated for rural residential in local government planning
schemes, but not developed or included in the Rural Living Area, will
have a limited opportunity for development. …(Page 13)
Rural Living areas comprise certain areas that are currently zoned
for rural residential development in local government planning
schemes and are substantially developed for that purpose. Future
rural residential development through infill and consolidation of
these areas is permitted under the Regional Plan.” (Page 15)
There is room for doubt about the status of such material. Whereas the whole of the
SEQ Regional Plan (which may or may not contain similar statements) is made a
statutory instrument with the force of law by s2.5A.10(2) of the IPA, so far as the
Draft SEQ Regional Plan is concerned, nothing is said about its efficacy other than
that “any proposed regulatory provisions…have effect”: s2.5A.24(1). It is not
necessary to have any regard to such problematic material to reach the conclusion
(which I do reach) that references in s4(3)(c)(i) are relevantly to the 2003 Planning
Scheme.
[26] A similar exercise in construction was undertaken in Devine Ltd v State of
Queensland [2005] QPELR 326, where the statute referred to circumstances
“existing” and it was determined that there was no requirement that those
circumstances continued to exist after the relevant commencement date. If I am
correct about s 4(3)(c)(i), the DRP cannot be construed so as to avoid inconsistency
with what the Appellants contend are their vested rights to pursue their development
-- 15 of 20 --
16
application (superseded planning scheme). The Appellants’ submissions expanded
slightly on their summary in this respect:
“7. The Applicants’ position is that the IPA specifically permits
the lodging of a superseded planning scheme application,
and the Draft Regulatory Provisions cannot and do not
prevent the lodging of such an application. Further, such an
application is to be treated as if the new planning scheme
was not in force (i.e. the subject land is to be treated as if it
is zoned “Rural Residential A”), and would therefore fall
within the exception provided for by s.4(3)(c) of the Draft
Regulatory Provisions.
8. The essential question for the Court to determine today is:
Did these Draft Regulatory Provisions remove the right of
the Applicants to make a superseded planning scheme
application?
9. In others words, are these regulations made under delegated
authority to be read as operating in such a way as to
impliedly repeal certain sections of the IPA in circumstances
such as the present, thereby depriving the Applicants of
vested rights, including the potential right to compensation?”
[27] Authorities relied on as telling against a conclusion that there was any implied
repeal of sections of the IPA or defeating of the Appellants’ vested rights included
Goodwin v Phillips (1908) 7 CLR 1, 10, Hack v The Minister for Lands (NSW)
(1905) 3 CLR 10, 23, Butler v The Attorney-General (Vic) (1961) 106 CLR 268,
275-76, Alexander Cowan & Sons Ltd v Lockyer (1904) 1 CLR 460, 466, Sargood
Brothers v The Commonwealth (1910) 11 CLR 258, 279, The Commonwealth v
Hazeldell Ltd (1918) 25 CLR 552, 563, Mabo (supra), Bromley (supra), Resort
Management Services (supra), Kettering (supra), R v Industrial Registrar ex parte
Sulphide Corporation Ltd (1918) 25 CLR 9, 20-21, The Great Fingall Consolidated
Ltd v Sheehan (1905) 3 CLR 176, 184, Northbuild Constructions Pty Ltd v Lockton
[1999] QCA 91 at [5] (in the reasons of Thomas JA), Verdouw v City of Unley
[2000] SASC 410 at [19] and Kingston v Stickens [2002] QDC 255 at [12]. Various
passages from D J Gifford & K H Gifford, How to Understand an Act of Parliament
(8 th ) were relied on and Dixon J’s statement in Federal Capital Commission v
-- 16 of 20 --
17
Laristan Building & Investment Co Pty Ltd (1929) 42 CLR 582 at 588 to the effect
that the words “subject to this Act and to any other ordinance”:
“… indicate no intention that the legislative power of the Governor-
General in Council may be exercised otherwise than consistently
with the will of Parliament as disclosed by this or any other Statute.”
[28] Everything comes down to what Parliament wills. There is a pithy statement in
MacAdam and Smith, Statutes, (3 rd ) at 286 to the effect that “if the provision
conferring power to make regulations contains a provision, in effect authorising the
amendment of the Act by regulations, then the regulations are treated in the same
way as an amending Act.” No authority is cited, but the proposition is convincingly
reflected with copious citation of authority in Bennion, Statutory Interpretation (4th )
in passages that may be found at 199-202:
“Must not conflict with law Unless the enabling Act so provides, delegated
legislation cannot override any Act – and certainly not the enabling Act
itself.1 Indeed it is taken not to be impliedly authorised to override any rule
of the general law.2
…
However this restrictive principle cannot apply where the implication
necessarily arises from the words used in the enabling provision. This arises
from the very nature of delegated legislation, and does not need to be stated
in the enabling Act.3
…
Has effect as if made by Act Subject to the rule just mentioned that without
authority it must not conflict with existing law, a provision of delegated
legislation has statutory force. Its effect is the same as if it were contained in
an Act.4 Formerly this would usually be spelt out in the enabling Act. 5
1 Re Davis, ex p Davis (1872) 7 Ch Application 526 at 529.
2 5 Co Rep 63a; Hall v Nixon (1875) LR 10 QB 152 at 159; Rossi v Edinburgh Corpn [1905] AC 21. See further Code
s58.
3 In earlier times less afraid of tautology, such statements were included: see everything the Recovery of Small Debts
(Scotland) Act 1825 s 23 (repealed).
4 Dale’s Case (1881) 6 QBD 376 at 398; Re Langlois and Biden [1891] 1 QB 349 at 355; Kruse v Johnson [1898] 2 QB
91 at 96; Re Macartney, Brookhouse v Barman (1920) 36 TLR 394; Swain v Law Society [1983] 1 AC 598; Ex p
Austintel Ltd (1996) Times, 11 November; Hughes v Kingston upon Hull City Council [1999] 2 All ER 49.
5 The practice has been traced back to the Statute of the Staple 1385: W Graham Harrison, Notes on the Delegation by
Parliament of Legislative Powers (1931), p 66.
-- 17 of 20 --
18
The effect is the same, whether or not the enabling Act spells it out.1 This
applies even where the person entrusted with the delegated legislative power
is not an emanation of the state.2
…
May amend Act The enabling Act may confer power on the delegate to
amend the enabling Act itself, or any other Act. A provision conferring such
power was formerly known as a Henry VII clause, since it was supposed to
reflect that monarch’s autocratic tendencies.3 Such provisions began to
appear in the second half of the nineteenth century.4 They are often used in
relation to local Acts.
Example 50.5 The Public Health Act 1875 s 303 (repealed) conferred power to
`repeal, alter or amend’ by provisional order any local Act `which relates to the
same subject-matter as this Act’.
It is not unknown even for modern Acts to give power to amend, or even
repeal, public general enactments by delegated legislation.
Example 50.6 The Local Government Act 1972 s252(1) gives power to make
modifications in any public general Act, or any instrument `of a legislative
character’.5
Delegated power is often given to amend monetary limits in Acts.6
Sweeping general powers to increase, using delegated legislation, the
amounts of fines imposed by Act are widely conferred.7 The Deregulation
and Contracting Out Act 1994 s 1 gave Ministers a broad power to amend or
repeal any Act passed up to the end of the 1993-94 session, in order to
remove or reduce a statutory burden where the effect of the provision in
question is to impose, or authorise or require the imposition of, a burden
affecting any person in the carrying out of any trade, business or profession.
The Act provides a special procedure for such orders, which are popularly
known as deregulation orders.
Apart from a power to amend the enabling Act, delegated power may be
given to modify its effect from time to time.
Example 50.7 The Supreme Court of Judicature (Consolidation) Act 1925
s50(1) (repealed) said that subject to rules of court costs should be in the
1 Institute of Patent Agents v Lockwood [1894] AC 347 at 361.
2 Swain v Law Society [1983] 1 AC 598; Mohamed v Alaga & Co (a firm) [1998] 2 All ER 720 (rules made by Law
Society under Solicitors Act 1974).
3 C K Allen, Law and orders (3 rd edn, 1965) Stevens & Sons, pp 100-102. See also R v Minister of Health, ex p Wortley
RDC [1927] 2 KB 229.
4 See everything the Factory Acts Extension Act 1867 s 14 (repealed); Anatomy Act (1832) Amendment Act 1871 s 2
(repealed).
5 Another example is the House of Commons Disqualification Act 1975 s5 (power to amend list of offices set out in Sch
1 to the Act). See also the Banking Act 1987 s7; Town and Country Planning Act 1971 s287(6) (repealed). As
to the construction of an Act by reference to amendments made in it by delegated legislation see Deposit
Protection Board v Dalia [1993] Ch 243 at 254.
6 See eg the Companies Act 1967 s48(2) (repealed); Gas Act 1972 s19(1) (repealed); Consumer Credit Act 1974 s181.
7 See eg. the Magistrates’ Courts Act 1980 s 143; Criminal Justice Act 1982 s 38.
-- 18 of 20 --
19
discretion of the court or judge.1 This meant that, while the Act itself gave full
discretion on costs to the court or judge, delegated legislation could curtail or
even remove this. 2
Lord Scarman described as ‘startling’ the power conferred by the Social
Security Act 1975 s37A (repealed) to limit the scope of the Act by delegated
legislation.3
…
Judicial control The courts have long maintained a right to superintend
delegated legislation, though their powers are necessarily limited by the
terms of the relevant enabling Act.4 ‘All that the court can do is to see that
the power which it is claimed to exercise is one which falls within the four
corners of the powers given by the legislature and to see that the powers are
exercised in good faith. Apart from that the courts have no power at all to
enquire into the reasonableness, the policy, the sense or any other aspect of
the transaction.’5
…
Parliamentary Control As to parliamentary control over delegated
legislation see Code s51. …”
[29] There is little point in casting around for examples of potent delegated legislation.
The application and the effect of the Environmental Protection Act 1994 depends
crucially on the contents of the regulations made under it. One example familiar to
all Judges in the State is the Criminal Offence Victims Regulation (1995), both
generally and particularly in respect of reg 1A and associated regulations effective
by SL number 488 of 1997 as from 19 December 1997. This adds enormously to
the effect of the Criminal Offence Victims Act 1995 (as the provisions of the Act
permitted), and to the amount of compensation some offenders are ordered to pay.
It is more concerning to find the effect of an Act cut down; however, in principle,
that can be done, and appears to have been done quite deliberately here.
1 Emphasis added. See now the Supreme Court Act 1981 s51(1) as amended by the Courts and Legal
Services Act 1990.
2 As to the precise juridical nature of such provisions see EMI Records Ltd v Ian Cameron Wallace Ltd
[1982] 3 WLR 245, per Megarry V-C at 254.
3 Lees v Secretary of State for Social Services [1985] AC 930 at 933.
4 In relation to byelaws, the courts have exercised a more stringent supervision than in the case of other
forms of delegated legislation: see Code s 65.
5 Carltona Ltd v Comrs of Works [1943] 2 All ER 560, per Lord Greene MR at 564. See also Lewisham
Borough Council v Roberts [1949] 2 KB 608; Minister of Agriculture and Fisheries v Matthews
[1950] 1 KB 148. Various aspects of judicial control are dealt with in the following sections of the
Code: s 15 (the Padfield approach), s24 (judicial review); s57 (duty to exercise delegated powers);
s58 (doctrine of ultra vires); s59 (rule of primary intention); s65 (byelaws); s67 (sub-delegation) s329
(natural justice etc).
-- 19 of 20 --
20
[30] The IPA was amended in September 2004 to provide for the formulation and
coming into effect of the SEQ Regional Plan according to legislated parameters.
“Stating aspects of development that may not occur in stated localities” by
regulatory provisions was in terms envisaged by s2.5A.12(2)(d) – this might occur
without attracting the status of “temporary local planning instrument”, which
subsection (3) described as the fate of provisions described in (2)(a), (b) or (c). It is
inescapable that Parliament wished the regional planning Minister to be in a
position to change the planning regime in South-East Queensland in the short term
from the provisions of s2.5A.13 requiring a draft SEQ Regional Plan to be prepared.
The draft is to be publicised under s2.5A.14 with a view to attracting submissions.
It is no more than logic and commonsense that the draft might contain anything that
the SEQ Regional Plan is permitted to contain. A possibility under s2.5A.15(2)(a)
is that the SEQ Regional Plan may be in the same terms as the draft SEQ Regional
Plan as published.
[31] By s2.5A.24(1) the DRP are given “effect” on publication of the notice referred to.
As to the meaning of the “have effect”, it is difficult to see how the DRP would be
any less potent than the SEQ Regional Plan under s2.5A.10. Be that as it may,
s3.2.1(7)(f) requires, among other things, of a “properly made application” for
development approval that “the development would not be contrary to … the draft
regulatory provisions”. The IPA in this regard defers to the DRP. The development
proposed here is contrary to the DRP, unless I am wrong about s 4(3)(c)(i). The
assessment manager was therefore under subsection (8) entitled to refuse to receive
an application for approval of that development. As noted already, subsection
(10)(b) precluded granting of the indulgence referred to in subsection (9). Here, the
court’s conclusion is that the IPA provisions regarding a development application
(superseded planning scheme), and/or the effect such an application may have, have
been considerably modified, pursuant to a process established by the IPA. There
was no “properly made application”. The Council came under no obligation to give
an acknowledgement notice.
[32] The relief sought in the Appellants’ application filed 27 June 2005 must be refused.
Mr Hinson is probably correct in his submission that, in such circumstances, the
appeal ought to be dismissed. The parties will have the opportunity to make further
submissions in light of these reasons before final orders are pronounced.
-- 20 of 20 --
Official source: https://www.sclqld.org.au/caselaw/QPEC/2005/075