Bowers & Anor v Council of the Shire of Pine Rivers [2005] QLC 46 (2005) 26 QLCR 120
LAND COURT OF QUEENSLAND
CITATION: Bowers & Anor v Council of the Shire of Pine Rivers
[2005] QLC 46
PARTIES: Olive Louise Bowers and Lynette Ann Crane (as personal
representatives)
(claimants)
v.
Council of the Shire of Pine Rivers
(respondent)
FILE NO: A2004/0137
DIVISION: Land Court of Queensland
PROCEEDING: Claim for compensation payable consequent upon the
resumption of land for rubbish depot purposes under the
Acquisition of Land Act 1967
DELIVERED ON: 15 September 2005
DELIVERED AT: Brisbane
HEARD AT: Brisbane
MEMBER: Mr RS Jones
ORDERS: 1. Compensation is determined in the amount of
$832,000 (Eight Hundred and Thirty Two
Thousand Dollars).
2. The respondent to pay to the claimants interest
at the rate of 5.50 per cent per annum on the
sum of $812,000 from the date of resumption, 9
May 2003, to 28 November 2003, when the
advance of $400,000 was received and, then on
the balance of $412,000 to the date of payment.
3. The parties will have the opportunity to consider
these reasons and make submissions in respect
of interest on disturbance and/or costs
including reserved costs if any.
(See attached Variation Order made after Judgment
published)
-- 1 of 31 --
2
CATCHWORDS: Resumption – scheme of resumption – Point Gourde
principle – same or different scheme –criteria to be applied
– extension of existing scheme, not part of original scheme
Resumption – scheme of resumption – San Sebastian
principle – relationship of town planning changes to
scheme – need for direct relationship or a step in
resumption process – whole planning scheme not to be
ignored
Town Planning – likelihood of development approval for
subdivision but for resumption scheme – water services
likely impediment – limit on bulk water supply – intensive
subdivision approval not likely
Valuation – sales evidence finally relied on – not fully
analysed by valuers – 'best guess' estimate by Court using
sales evidence
APPEARANCES: Mr G Allan of Counsel for the claimants
Mr C Hughes SC with him Mr A Skoien of Counsel for
the respondent
SOLICITORS: John K Harris for the claimants
Shire Solicitor, Council of the Shire of Pine Rivers, for the
respondent
Details of Resumption
[1] This is a claim for compensation by Olive L Bowers and Lynette A Crane, as personal
representatives ("the claimants"), being the registered proprietors of Lot 1 on Registered
Plan 13591, County of Stanley, Parish of Bunya, consequent upon the resumption of the
whole of that land for rubbish depot purposes by the Council of the Shire of Pine Rivers
("the respondent").
[2] A Notice of Intention to Resume dated 30 August 2001 was served on the claimants
giving notice that the respondent intended to take the whole of the land for "waste
disposal facility purposes". On 9 May 2003 the land was resumed for "rubbish depot
purposes" by a proclamation published in the Government Gazette on that date.
Compensation is therefore to be assessed as at 9 May 2003.
General Description of the Land
[3] The subject land is located approximately 18 km by road from the Brisbane GPO, is
adjacent to the eastern side of Bunya Road and contains an area of 16.187 hectares and is
of irregular shape. The topography of the land consists of various slopes ranging from
approximately one in eight to one in four which could be described as being a mix of
moderate to steep slopes.
-- 2 of 31 --
3
[4] To the north and west the land is effectively bounded by the Bunyaville State Forest Park.
To the immediate east and south are several parcels of land under the ownership of the
respondent which have been acquired over a number of years commencing in 1979. The
combined areas of land owned by the respondent (excluding the subject) consist of park
and recreation (Lot 2 on RP 164889) and operating rubbish depot (Lot 2 on RP 156364)
uses and one uncleared area of land referred to by the parties as the "Chinn" land (Lot 3
on RP 49298). South and west of the land and Bunya Road are established areas of
Special Residential, Rural Residential and Residential A development.
[5] Bunya Road is a sealed bitumen surface road which provides access to the land.
Electricity and telephone services are connected and schools and shops lie within a 4 km
radius. Improvements on the land consist of a highset timber and fibro dwelling,
detached shed and carport. There is a dispute about the level of availability of sewerage
and town water as at 9 May 2003.
The Initial Position of the Parties
[6] A Claim for Compensation pursuant to s.19 of the Acquisition of Land Act 1967, dated 7
November 2003 was served by the claimants on the respondent. The amount claimed was
in the sum of $2,600,000 excluding interest. The claim was made up of two components,
namely "land and improvements" - $2,500,000 and "disturbance", estimated at $100,000.
The claimants commenced proceedings in this Court by filing on 10 November 2004 an
Originating Application seeking compensation in the amount of $2,600,000.
[7] On 28 November 2003 the claimants' solicitors received a cheque in the sum of $400,000
from the respondent by way of an advance against compensation.
The Position of the Parties at the Hearing
The Claimants' Position
[8] The claimants initially relied on a valuation (Exhibit 5) prepared by Mr Walsh, a
registered valuer employed by Taylor Byrne Valuers, assessing compensation in the sum
of $3,185,000 excluding interest and disturbance. Critical to Mr Walsh's assessment of
compensation was that the highest and best use of the land, disregarding what was
referred to as the "… scheme of which the resumption forms a part …", was for
Residential A subdivision. According to Mr Walsh, at the date of resumption, the land
would have been "ripe" for such development. Reliance was placed on a hypothetical
subdivision layout (Plan 12267-5A) prepared by Mr Goodwin, an experienced surveyor.
Mr Goodwin's subdivision envisaged the land being developed into 91 residential
allotments averaging about 830m² in area, the minimum lot area being 600m². About 6
-- 3 of 31 --
4
hectares of land (approximately 37% of the total area) was to be set aside for park / open
space purposes.
[9] The valuation relied on by the claimants was largely dependent upon the advice of experts
in other fields, to the effect that there were no engineering, ecological, traffic or other
town planning impediments which would prevent the hypothetical development relied on
from proceeding and that the development costs would be, on average, about $40,000 per
lot including town water and sewerage.
The Position of the Respondent
[10] The valuation upon which the respondent relied was prepared by Mr Gillespie, a
registered valuer employed by the valuation company Bloxsom Chippindall & Associates
Pty Ltd. Mr Gillespie, like Mr Walsh, relied in part on the opinions and reports of experts
in other fields to conclude that the highest and best use of the land was for a large rural
homesite with potential for up to six Rural Residential allotments having a minimum area
of 2 hectares. At page14 of his report (Exhibit 20) Mr Gillespie put forward an alternate
highest and best use being for one large rural homesite. The first scenario yielded a
valuation of $490,000; the second a value of $400,000. Mr Allan, counsel for the
claimants, accepted that if I were to find that the highest and best use of the land was for a
large rural homesite with potential for up to six Rural Residential allotments, Mr
Gillespie's valuation of $490,000 was a reasonable assessment of compensation exclusive
of any allowances for disturbance and interest.
Final Position of the Parties
[11] On the last day of the hearing of this matter, the claimants, without objection by the
respondent and with the leave of the court, amended their claim to $2,821,000 exclusive
of disturbance and interest. The claims under the heading of "disturbance" were able to
be agreed in the amount of $20,000 on an "all up" basis. The final position of the parties
was therefore:
Claimants: $2,841,000 including disturbance but excluding interest.
Respondent: $420,000 or $510,000 including disturbance but excluding interest.
[12] Before turning to some of the more specific matters that need to be addressed, I should
mention here that the respondent took the position that interest on compensation for land
and improvements should run from the date of the taking of the land (9 May 2003) to the
date of payment, with appropriate allowance for the payment of the advance on 28
November 2003.
-- 4 of 31 --
5
[13] On the second day of the hearing I, together with counsel, inspected the land, its environs
and various land sales relied on by the valuers. The inspection was of assistance in my
understanding of the evidence.
[14] As mentioned above, the valuers for both parties relied heavily on the advice of experts in
other fields. In particular both sides called evidence from qualified and experienced
surveyors, civil engineers and town planners. In determining this matter I do not consider
it necessary to make a final determination in respect of each and every issue raised by the
experts relied on by parties. My role, as I see it, is to decide how the hypothetical
purchaser and vendor, properly advised and acting reasonably and prudently would come
together at a price for the land. By necessary implication, relevant to these proceedings,
this requires me to determine how the prudent vendor and purchaser, acting on
appropriate advice, would assess the development potential of the land.1
The Pointe Gourde and San Sebastian Issues
[15] As is often the case in matters such as this, the value to be attributed to the land largely
depends on the resolution of various factual disputes raised by the witnesses on each side
of the record. However, in this case there is one particular issue which raises matters of
fact and law. In addition to having to rely on advice from other experts in carrying out
their valuations, the valuers were required to disregard certain factual matters in
accordance with what were said to be the principles established in cases such as Pointe
Gourde2 and San Sebastian3.
[16] Mr Walsh, valuer for the claimant, at page 15 of his valuation report under the heading
"Highest and Best Use" stated:
"The highest and best use is defined as the most profitable, achievable legal use for a
property.
To assist in consideration of highest and best use I have had regard to the report of
Buckley Vann Town Planners on the basis that the scheme of the resumption is
disregarded…
The scheme of which the resumption forms part is considered to be the scheme of the
James Drysdale Waste Disposal Facility and is disregarded for the purposes of this
valuation.
When the scheme of the James Drysdale Waste Disposal Facility is disregarded, the
subject land would have been included in the Residential A zone for further subdivision
and residential development.
..."
1 De Ieso v Council of the Highways (1981) 27 SASR 248 at 252-254 per Wells J; Walker Corp Pty Ltd v Sydney
Harbour Foreshore Authority (2004) 134 LGERA 195 at paras [121] - [123] per Talbot J. Spencer v. The
Commonwealth (1907) 5 CLR 418 at 432 per Griffiths CJ and at 441 per Isaacs J.
2 Pointe Gourde Quarrying and Transport Co Ltd v Sub-Intendent of Crown Lands (1947) AC 565 at 572.
3 Housing Commissioner of New South Wales v San Sebastian (1978) 140 CLR 196.
-- 5 of 31 --
6
[17] The Buckley Vann town planning report referred to by Mr Walsh was prepared by Mr
Ovenden, a qualified and experienced town planner. At page 1 of his report4 Mr Ovenden
by way of introduction stated:
" …
The report has regard to the various planning instruments and associated planning scheme
provisions affecting the subject site and surrounding land for the period January 1978 to
May 2003. The report considers the highest and best use in the following context:
assuming the statutory planning provisions of this period did not apply, having
regard to the suitability of the site for development and development trends in
the locality; and
the zoning of the land which, in my opinion would have been applicable to the
land had the scheme of resumption never taken place.
These assumptions take into consideration not only the zonings of the subject site (over
that period) but that of the surrounding land north of Bunya Road (referred to in this
report as the 'Investigation Area') and the wider district which existed prior to the
resumption … "
At page 16 by way of conclusion Mr Ovenden went on to state:
"A detailed review of the Council's planning instruments since 1971 has been undertaken
in the preparation of this report. It has been established that since 1978 in one form or
another there has been reference to the proposed or existing refuse disposal facility. In
my opinion, this has influenced the planning for the Investigation Area to satisfy a
specific objective ie to restrict the ordinary course of development in the Investigation
Area in order to protect the operation and expansion opportunities for the refuse disposal
facility.
It has been established that the highest and best use (assuming that the statutory planning
provisions from January 1978 to May 2003 do not apply) is for the subject site to be
included in the Residential A zone and the majority of the land is suitable for subdivision
into conventional residential lots. … "
[18] At odds with the views of Mr Walsh are those of Mr Gillespie. In his report, under the
heading "Highest and Best Use," Mr Gillespie stated at page 13:
"As the current restrictions to the land associated with 'the scheme' are to be ignored we
have investigated the other uses to which the land can be put.
After considering reports provided to me by the Pine Rivers Shire Council we have
concluded that the highest and best use for the land is as a large rural homesite with
potential for Rural Residential subdivision. That subdivision potential could involve a
subdivision to approximately six Rural Residential lots (2 hectare minimum) … "
[19] The reports considered by Mr Gillespie in reaching his conclusions included those from a
qualified and experienced surveyor, engineer(s) and town planner. Mr Rea, a town
planner employed by and relied on by the respondent at page 1 of his report,5 by way of
introduction stated:
" …
In formulating my response to such a development proposal for Lot 1 on RP 13591, I
have been requested to assume that:
4 Ex 6.
5 Ex 11.
-- 6 of 31 --
7
The tip site and adjacent James Drysdale Reserve do not as a matter of fact exist
and that the land is undeveloped and zoned Rural.
The relevant provisions of the Hills District DCP does not apply.
The strategic plan and all other related planning instruments do apply.
This approach is significantly different from the approach usually taken in the assessment
of proposals of this nature. … "
[20] While the relevant experts say they have applied the principles established by precedent
and, in carrying out their valuations, have ignored the "scheme" underlying the
resumption, there are obvious differences of significance between them. The position of
the claimants is articulated in the written submissions of Mr Allan where he argued the
so-called Pointe Gourde point in the following terms:
"32. It is submitted that the assessment of compensation in respect of the resumed land is
to be made in accordance with the High Court's application of the Pointe Gourde
principle in … San Sebastian. ... Namely, that in respect of the resumed land (and the
'Investigation Area'), the restrictive provisions contained in the existing 1998 scheme and
all historical planning instruments dating back to 1978 (the date of commencement of the
'scheme of resumption') associated with the use or future use of the land for rubbish depot
or waste disposal purposes are to be ignored since there is a direct relationship between
the restrictions imposed by those provisions and the use of the land for rubbish depot
purposes.
…
42. It is submitted on the foregoing authorities … that it is clear the approach of Mr
Ovenden in forming his opinion that but for the 'scheme of resumption' the subject land
would have had a Residential A zoning conforms in all respects with the law. … "
[21] This is to be contrasted with the position of the respondent where, on its behalf, it was
contended that while the existing rubbish depot and James Drysdale Reserve had to be
ignored, the "scheme" did not exclude from consideration in the valuation process the
Rural zoning of the land nor the existing strategic plan and " … all other related planning
instruments". Counsel for the respondent articulated in paragraph 6.7 of their written
submissions, the following argument:
"6.7 The respondent submits that the applicant's assumption is erroneous for the
following reasons:
(a) first, it is at least arguable that the 'Pointe Gourde' principle has no application in the
present case because the respondent has never taken a deliberate step to impose a
restriction upon the use of the subject land - rather it has merely maintained rural
planning controls which have been in place for over 40 years;
(b) second, it is, in this case, impossible to 'ignore' the rural zoning under the 1988
planning scheme (and, for that matter, the rural preferred dominant land use
designation) based upon the so-called 'scheme' because, on the facts of this case, as a
result of the physical characteristics of the subject land; the unavailability of
appropriate services and the balance of provisions of the planning documents
generally; the subject land would probably have been zoned rural and given a rural
preferred dominant land use designation regardless of the existence of the rubbish tip
or the 'scheme'; and
-- 7 of 31 --
8
(c) third, even on the applicant's case, the subject land could not conceivably have been
given a zoning 'greater' than Future Urban, being the zoning which the residential
land south of Bunya Road was given in 1988 … "
Mr Hughes, Senior Counsel for the respondent, in his closing oral submissions argued
that the claimants were not entitled to exclude from consideration in the valuation process
"… planning documents … unless (they) can find within those planning documents that
some deliberate decision was made(to further the purposes of the dump)".
[22] The purpose of the principle stated in Pointe Gourde is to prevent the constructing
authority having to pay more than the market value for land taken where its value at the
date of acquisition has been increased and that increase is entirely due to the scheme
underlying the resumption. The relevant passage of the judgment of Lord MacDermott is
very brief and to the point:
"(it is) well settled that compensation for the compulsory acquisition of land cannot
include an increase in value which is entirely due to the scheme underlying the
acquisition."
This passage was referred to by Scott LJ in Waters & Ors v Welsh Development Agency6
in the following terms:
"The dictum of Lord MacDermott's that I have cited has, in the subsequent case law, been
examined, pored over and construed as though it had been a sentence in an Act of
Parliament. This process, as may be seen from the judgments of the courts below in the
present case, is still continuing. In my respectful opinion the process has been and is
unwarranted. Lord MacDermott, in his two page ex tempore judgment, came to a
conclusion which, if I may respectfully say so, was clearly correct. … "
[23] While Pointe Gourde is concerned about the underlying scheme or project inflating the
value of land, San Sebastian is concerned about circumstances which, if allowed to be
brought into account in the valuation process, would deflate the value of the land. In San
Sebastian it was held that where there was a direct relationship between a restriction on
land use imposed by planning instruments and/or legislation and the scheme or project
underlying the compulsory acquisition, the effect on value of the restriction should be
ignored. This proposition was stated by Jacobs J at pp 206–207 in the following terms:
" … Restrictions on land use, so that, explicitly or practically, use is restricted to a use for
a public purpose for which the land might be resumed, are commonly imposed as a result
of consultation with or direction by the public authority concerned with the carrying out
of the particular public purpose. In such a case where there is a direct relationship
between the restriction on land use and the proposed establishment of the public works
the effect on value of the zoning or restriction ought to be ignored. … "
… "If the zoning was done with the intent or in anticipation that the land should be
resumed for a purpose such as a public reserve or if the zoning was proposed or dictated
by the resuming authority then s.124 requires that the zoning be ignored. It is only a step
in the process of subsequent resumption" …
6 (2004) 2 All ER 915 at para [93].
-- 8 of 31 --
9
[24] Relevantly, in my view, there are two important matters that need to be kept in mind
when applying the so-called "rule" in San Sebastian. First, it is not authority for the
proposition that, where it does apply, it is then necessary to assign and apply a superior
zoning or land use potential to the land. Second, there must be sufficient connection
between the scheme underlying the resumption and the restrictions imposed.
[25] As to the first of these matters, in San Sebastian, while it was held that the proposed
residential zoning in the draft planning instrument was a step in the process which was to
be ignored, Jacobs J at page 211 went on to say:
"… If independently of the proposed resumption for the purpose of public housing the
land was found likely in the varied scheme to have been zoned residential in terms of the
interim development order that would have been a most important finding affecting the
value of the land for purposes of a private hospital."
And to a similar effect at pages 211-212:
"… The fact that the land would probably have been zoned in a manner similar to its
proposed zoning under the draft interim development order would only be of significance
if, contrary to the facts, that zoning would have been regarded as likely to occur
independently of the proposed purpose of public housing and consequent resumption.
Nevertheless it must be made clear that in so far as there was a possibility or likelihood of
such a zoning independently of the purpose of public housing that was a matter properly
to be taken into account in accordance with the principle enunciated in the Stocks &
Parkes Case … "
Hope J.A. in the Court of Appeal, with whose reasons Reynolds J.A. expressed
agreement, stated:
'A special problem arises in the present case because of the mixed history of
planning proposals for the use of land in the Woolloomooloo Basin, and of other
matters bearing on that use. This history included proposals and other matters
indicating that development in the relevant part of Woolloomooloo would
probably or possibly be limited to residential development in a general sense,
but did not suggest any public housing works. In so far as any of these matters
altered the value of the resumed land, s.124 would not require that alteration to
be disregarded. If there were matters not related to any contemplated public
housing scheme which established that the probable zoning of the resumed land
when resubjected to a prescribed planning scheme would be residential, that
probability would be a matter falling within this class.'
With all of this I entirely agree."
[26] The principles established in San Sebastian were later considered by the High Court in
The Crown v Murphy7, where the claimant in that case intended to carry out residential
development at Mon Repos Beach near Bundaberg. Mon Repos Beach is a turtle rookery
of international repute. The application to rezone the land from rural to residential was
refused by the local authority and the land was later resumed by the government for
environmental park purposes. In considering whether or not the local authority could
have (properly) refused the rezoning application, quite apart from the resumption and the
scheme for the protection of turtles, the Court at 595 stated:
7 (1990) 64 ALJR 593.
-- 9 of 31 --
10
"The statement of principle by the majority in the Full Court and the statement of the
necessary consequential enquiry are unexceptionable. One purpose of this principle is to
ensure that a resuming authority does not employ planning restrictions to destroy the
development potential of the land and then assess compensation for its resumption on the
basis that the destroyed potential had never existed: Melwood Units Ltd. v. Main Roads
Cmr [1979] AC 426, at p 434. The principle applies in cases where there is a direct
relationship between the planning restriction and the scheme of which resumption is a
feature and extends to cases where there is merely an indirect relationship, provided that
the planning restriction can properly be regarded as a step in the process of resumption:
Housing Commission of NSW v San Sebastian Pty Ltd, at pp 206-207.
Of course, a characteristic or attribute of the land which affects its value must be taken
into account in the assessment of compensation even if the planning restriction which is a
step in the process of resumption is dependent upon or directed to that characteristic or
attribute. … "
[27] As to the second issue, the requisite degree of connection has been variously described as
being or requiring a "direct relationship"8 or a "direct causal connection".9 In their
submissions, counsel for both parties tended to merge and adopt both tests. Provided that
the latter is understood to mean the same as the former, I have no difficulty with the
approach adopted. However, in Murphy, the High Court at 595 citing San Sebastian
stated that the principle applied in cases not only where there was a "direct" relationship
but also to cases where there was merely an "indirect" relationship, provided that the
planning restriction could properly be regarded as a step in the process of resumption.
That is, the potential scope for the application of the San Sebastian principle is wider than
actually contended for by the parties.
[28] Leaving aside for the moment the question of whether the requisite relationship existed
between the scheme underlying the resumption and the planning restrictions applicable to
the land, there was little dispute about the background history which can be summarised
as follows:
(i) The subject land, together with four other freehold lots formed a precinct
effectively bounded by the Bunyaville State Forest to the north, east and west
and by Bunya Road to the south. This precinct was referred to by the parties
as the "investigation area".
(ii) The subject land had effectively been given a rural designation from the
introduction of the 1965 town planning scheme through to the date of
resumption. The balance of the land making up the investigation area was
zoned Rural Land in 1965 but has been progressively rezoned during the
evolution and development of the rubbish tip and public reserve area known as
the James Drysdale Recreation Reserve.
8 San Sebastian at 206.5; Murphy at 595.
9 Haig v Minister Administering the National Parks and Wildlife Act (1994) 85 LGERA 143 at 149 per Kirby P.
-- 10 of 31 --
11
(iii) In 1978 the amended Arana Hills Development Plan came into operation.
(iv) At or about 24 March 1979 the respondent resumed Lot 2 on RP 164889 for
rubbish depot purposes.
(v) On or about 24 April 1980 the respondent purchased Lot 1 on RP 164889 by
private treaty.
(vi) On or about 1 December 1980 the respondent adopted the Pine Rivers West
Development Control Plan No. 3.
(vii) In May 1983 the Pine Rivers West Development Control Plan No. 3 was
amended.
(viii) In 1985 town water and sewerage headworks areas were established.
(ix) At or about May 1988 the respondent's planning scheme came into effect
including its Strategic Plan and planning scheme schedules and maps.
(x) At or about February 1989 the respondent, by private treaty acquired a two-
third interest in Lot 2 on RP 156364 and, by resumption, acquired the
remaining interest at or about December 1989.
(xi) At or about June 1992 the Hills District Development Control Plan No. 1
(Hills District DCP) came into effect.
(xii) In 1995 the town water and sewerage headworks boundaries of the respondent
were reviewed.
(xiii) At or about June 1997 a Notice of Intention to Resume for local government
purposes was issued to the owners of Lot 3 on RP 49298 (the Chinn land).
However, at or about December 1998 the respondent acquired the land by
private treaty and the resumption process was discontinued.
(xiv) In May 1998 the respondent's consolidated Strategic Plan was gazetted.
(xv) On 9 May 2003 the subject land was resumed for rubbish depot purposes.
The Scheme
[29] As already identified, the proclamation resuming the land stated the purpose of the taking
as being: "…for rubbish depot purposes ...". According to Mr Allan, the scheme
underlying the resumption commenced in 1978, the date at which the first compulsory
acquisition for rubbish depot purposes commenced within the investigation area. Counsel
for the respondent did not contend for any specific date as being the commencement of
the scheme underlying the subject resumption. However, as I understand their written
submissions, the implication was that the relevant scheme did not commence until 1992
with the introduction of the Hills District DCP.
-- 11 of 31 --
12
[30] Notwithstanding lengthy testimony and volumes of documents being tendered by both
sides in the furtherance of their respective cases, very little evidence was specifically
directed at identifying what the relevant scheme was and when it commenced. In fact, the
evidence on these matters was effectively limited to the contents of the various town
planning instruments adopted by the respondent over time. My concern in this regard is
this: Is the resumption in 2003 for rubbish depot purposes a part of the same scheme
which commenced in 1978, or, is it in fact part of a new scheme, namely the expansion of
the then existing waste disposal facility? To my mind, the fact that the resumption of the
subject land was for the same purpose as that underlying the first resumption does not
necessarily mean that both parcels of land were resumed as a part of the same scheme. If
land was resumed in the 1970's for a road and, due to traffic growth in the area, more land
is resumed in 2000 to increase the road from 2 to 4 lanes it could not, in my view, be
necessarily said that both resumptions were part of the same scheme solely on the basis
that the purpose stated in the notice of intention to resume and Proclamation in both cases
was "road purposes". Conversely, the fact that the first resumption occurred in 1979 and
the last in 2003 does not necessarily mean they were not taken as a part of the same
scheme.
[31] The difficultly I have with accepting that the scheme underlying this resumption is the
same as that underlying the first resumption commencing in 1978 is that there is no
convincing evidence to that effect. In the circumstances of this case I find the reasoning
of the Land Appeal Court in Hutchins and Anor v The Council of the Shire of Woongarra
and Steven v The Commissioner of Water Resources10 to be of some assistance. In
Hutchins of pages 290-291 it was said:
" … The question of whether the two resumptions of land are part of the same scheme is
one of fact: Abbey Orchard Property Investments Pty Ltd v Sydney City Council (1978)
37 L.G.R.A. 230, Nuland Developments Pty Ltd v Parramatta City Council (1978) 37
L.G.R.A. 258. In deciding this question, however, the fact that the two resumptions are
some 12 years apart is irrelevant.
We do not think that the present resumption is part of the same scheme as the 1978
resumption. The former taking was for the purpose of constructing sewerage treatment
works for the Thabeban area which could cater for a population of 2,000 persons. A
claim for compensation for the resumed land was settled for the amount of $40,000. The
sewerage treatment works was constructed on the resumed land.
This, in our opinion, constituted the first scheme. There is no evidence to indicate that
the Council considered it to be the first stage of an ongoing scheme. The report by
engineers, G.C. Leddy and Associates, tendered in the Land Court, indicates that the
existing sewerage treatment works was designed as a stand-alone scheme catering for a
population of 2,000 persons, with the treated effluent being discharged into Yellow
Waterholes Creek. Time and population pressure have rendered these works inadequate
and the Council has now considered a scheme will which is quite different from the
existing one. The new scheme will cater for a population of 5,000 persons, with land
10 14 QLCR 286; 13 QLCR 75 respectively.
-- 12 of 31 --
13
disposal of treated effluent instead of the present discharge into Yellow Waterholes
Creek……."
A similar approach or reasoning was adopted by the Land Appeal court in Steven at pages
80–82 to distinguish between an earlier scheme and a later scheme with some common
elements.
[32] Turning then to the various town planning instruments to which my attention was drawn,
Mr Ovenden first referred to the Arana Hills District Development Plan adopted by the
respondent in May 1978. As pointed out by Mr Ovenden only limited reference is made
to a rubbish disposal site in this document. The next instrument referred to was the Pine
Rivers West Development Control Plan No. 311 adopted by the respondent in December
1980. According to Mr Ovenden only Lots 1 and 2 on RP 164889 were identified as
"garbage dump" in that document. Lot 1 was purchased by the respondent in April 1980
and Lot 2 was resumed by the respondent in March 1979. Other land (including the
subject) within the investigation area was identified as "extensive grazing". At pages 57-
58 of this document it is stated:
"Refuse Disposal"
At present there are two rubbish tips within the Study Area. One is at the entrance to the
disused railway tunnel under Mt Samson Road and is approaching the end of its viable
life. The other is a newly opened site at the intersection of Bunya Road and Old North
Road. ... Outside the Study Area, the closest useful refuse tip is located at Francis Road
in Lawnton. … Council is investigating further the problems of refuse disposal within
the Study Area… Once each tip site has reached its maximum capacity the surface
contours will be adjusted to provide for a suitable ultimate use. Such uses are likely to be
recreational or other appropriate land intensive activities in keeping with the uses
proposed for adjacent areas on Policy Plan … "
I was not referred to any specific part of this document as evidencing an ongoing rubbish
disposal or depot scheme or an intention by the respondent to expand the existing facility
at Bunya Road.
[33] Sometime between 1980 and 1988 the respondent was obviously becoming more
concerned about the availability of sufficient land for waste disposal and recreation
purposes to accommodate population growth within the shire. After identifying this
problem, the authors of the 1988 Strategic Plan went on to state:12
"James Drysdale Reserve.
…. The existing area of land is not adequate to fulfil long term needs for playing
fields…. To obtain additional land in the immediate vicinity of the existing facilities has
considerable advantages in that the various sporting bodies will utilise the land more
efficiently. The land immediately to the west of James Drysdale Reserve is suitable for
use as a landfill reclamation site and after filling is completed for district playing field
facilities. The land has been included in the Rural designation as this designation has
been given to land which is constrained or where it is considered that a more appropriate
use is possible in the future."
11 Ex. 59.
12 Ex. 70; Guidelines for Development Pine Rivers West District at page 46.
-- 13 of 31 --
14
[34] The timing of the 1988 Strategic Plan is of some significance. This Plan was adopted by
the respondent in May 1988 and in February 1989 the respondent purchased a two third
interest in Lot 2 on RP 156364. It seems unlikely to me that, at the time the 1988
Strategic Plan was being considered by the respondent, it was not also seriously
contemplating the purchase and/or compulsory acquisition of at least Lot 2 for expansion
of the rubbish depot and reserve areas.
[35] By 1992 even more active steps were being taken to preserve other land within the
investigation area for uses consistent with close proximity to the existing rubbish depot.
In the respondents Hills District Development Control Plan13 the whole of the
investigation area is located within precinct 15. In Part A at pages 38-39 the authors of
this document state:
"Precinct 15 – Special Purpose Area
(a) Intent
This precinct is intended to accommodate a land fill waste disposal site to serve the Hills
District and Albany Creek areas for the foreseeable future. As the land is progressively
filled, it is intended to be used for a wide range of sporting, recreational, community and
local authority purposes. It is intended that privately owned land within this precinct
shall not be used or developed for purposes which would be incompatible with Council's
planning intentions for the land fill waste disposal site(s), such as Residential A, Park
Residential, Rural Residential, or Special Residential sub-division.
(b) Land Uses
…. The preferred use of the privately owned land in this precinct is rural non-residential
uses which, in the opinion of Council, are compatible with the uses to be established on
the Council owned land."
[36] The reference to "this precinct", which includes the subject land, as a "special purpose
area" is, from the evidence that I have been referred to, the strongest language indicating
that the whole of the investigation area was to be preserved only for land uses compatible
with the respondent's rubbish depot use, including expansion. Between 1992 and 1998
the advantages of securing the adjoining land were being more precisely spelt out, though
even then the prospect of further acquisitions was couched in vague terms as it was only
identified that adjacent land "… may be suitable for future expansion"14. However, it
would seem that in fact planning was more advanced as by June 1997 the respondent had
issued a Notice of Intention to Resume in respect of the Chinn land which stated the
intended use as being "local government purposes". This land was later purchased by
13 Ex. 22.
14 1998 Strategic Plan; Ex. 21 at pages 131-132.
-- 14 of 31 --
15
private treaty for what was described in some of the documents as being the future
expansion of the James Drysdale reserve for future refuse purposes.15
[37] Doing the best that I can with the evidence before me I find; first, that the scheme
underlying the resumption of the subject land did not commence in 1978. Second, the
scheme underlying the subject resumption was for the extension or expansion of the then
existing rubbish depot facility. Third, this scheme commenced at or about 1988, some
time prior to the adoption of the 1988 Strategic Plan.
The Hills District - Development Control Plan (No. 1)
[38] As referred to above, counsel for the respondent, while advancing a primary argument for
compensation in the sum of $490,000 excluding disturbance and interest, in their final
address and written submissions left open what was said to be an "arguable" alternate
case based upon the proposition that that section of the Hills District DCP relating to
Precinct 15 was not a part of any scheme of resumption. And, if that section of the Hills
District DCP was a valid consideration in the valuation process, the market value of the
land was only $400,000 on the basis of its highest and best use being limited to only a
large rural homesite. According to the respondent, the Hills District DCP arguably should
not be seen as a deliberate step to impose a restriction on the use of the land as part of the
resumption process but rather as a part of the ongoing policy of the respondent to
maintain the rural zoning which had been in place for some 40 years.
[39] I do not accept this argument for either of two reasons. First, it ignores or unreasonably
reads down the actual wording used in the document concerning Precinct 15. Second,
rural land in Precinct 15 is treated differently than other land designated Rural in the Plan.
In Part A at pages 39-40 of the Plan, under the heading "Land Use" it is said in respect of
Precinct 16:
"… The preferred use of the Rural zoned land in the north-east of the precinct is as a
buffer or transition area between the urban area and the Park Residential area to the north.
Council shall not approve urban forms of residential development on the land. The Rural
zoned land may be suitable for low density forms of Special Residential or Rural
Residential development which, in the opinion of Council, is consistent with the
objectives for Rural Areas described in Part A of the Strategic Plan, which will not
detrimentally affect any area considered as environmentally sensitive by Council, which
does not require the extension of Council's water supply system beyond the 120 metre
contour (at the time of preparation of this DCP Council was reviewing its Water Supply
and Sewerage Headworks Policy and may reconsider this requirement pending the
outcome of that review), and which does not, in the opinion of Council, detrimentally
affect the amenity of the adjoining Park Residential estate to the north.
To my mind, the respondent clearly saw the potential for some form of more intense
development of the rural land in Precinct 16 when compared to land with the same
designation in Precinct 15. The most apparent difference between the two precincts being
15 Eg, Ex. 57; Part of Council minute dated 17 August 1999.
-- 15 of 31 --
16
proximity to the respondent's rubbish depot and reserve. By that I mean to say, but for
the "scheme", there appears to be no other sound town planning or engineering reasons
why the subject land should have been treated differently to that of other land designated
rural in such close proximity.
[40] For the reasons canvassed above I find that the restrictions imposed on the use of the land
by virtue of the operation of that part of the Hills District DCP dealing with Precinct 15 is
to be ignored. In my view, there is a direct relationship between the planning restrictions
imposed by this section of the Plan and the scheme of which the resumption is a part. In
this context I note that senior counsel for the respondent did concede in final submissions
that it was, on the evidence, open for me to conclude that there was a sufficient
relationship between this part of the plan and the scheme to offend the principles
established in San Sebastian.
[41] Accordingly, I reject Mr Gillespie's alternate valuation approach which assessed the value
of the land and improvements in the sum of $400,000.
Zoning and Services
[42] Upon the introduction of the Integrated Planning Act 1997 (IPA), the actual zoning of a
parcel of land arguably became less critical when assessing the development potential of
that land. Under IPA, residential development would not be a prohibited use because of
the historical rural zoning. However, in my view the rural zoning would, in the eyes of
the prudent purchaser, tend to be seen as a negative introducing more risk into any
analysis of the potential of the land for development. In the circumstances of this case,
according to Mr Rea, the respondent's town planner, intensive residential development
depended on the developer being able to demonstrate:16
(i) that essential services could be made available without compromising the entire
water supply network or the rights of other property owners within the existing
headworks area (and that other similarly placed Rural zoned properties could also be
developed) without compromising the provision of essential services.
(ii) the development of the subject property and the other properties within the
"enclave", could occur without creating an unacceptable burden on surrounding land
use or the future residents by way of traffic and general amenity issues; and
(iii) development of the property could occur in an acceptable manner with due regard to
issues related to slope, orientation, vegetation retention, bushfire management etc.
(emphasis added).
In respect of the availability of "essential services" the critical issues were whether or not
at the date of resumption town water and sewerage would have been reasonably available
for connection. Mr Rea, in his response report17 considered the availability of these
16 Ex 11, P 4 "Conclusion".
17 Ex 12, P 5 "Service Availability".
-- 16 of 31 --
17
services to be the most important issue in assessing the development potential of the land.
The theoretical pre-lodgement meeting form18, while clearly identifying a wide range of
matters that would need to be addressed in any development approval process,
specifically noted:
"… NB Water supply and sewerage are not available. Therefore, Residential A
development not supported."
[43] In my view, the other issues identified by Mr Rea, as set out in paragraph [42] above do
not on their own or collectively necessarily rule out Residential A development. That is,
provided that essential services (i.e. town water and sewerage) were available for
connection and the other issues identified by Mr Rea and Mr Vanderent19 could be
satisfactorily addressed in the design and construction stages of development, there was
no reason to suppose that favourable consideration would not have been given for some
form of Residential A type development. That of course does not mean that, even if town
water and sewerage were reasonably available, such development would occur. The
commercial viability of any such development would be critical to the prudent purchaser
and vendor.
Sewerage and Town Water Connection.
[44] The prudent purchaser, particularly since the introduction of IPA, would no doubt find the
zoning of the land to be a matter to consider, however, he or she would be far more
interested to know how likely it was that, as a matter of fact, approval would be given for
his or her development by the relevant local authority. In this context, to an extent, the
rural zoning of the land seemed to me on more than one occasion to be more a matter of
only historical interest to Messrs Rea and Vanderent. Mr Rea, in addition to the opinions
stated in his written reports, emphasised on more than one occasion in the witness-box
that for him the major impediment to Residential A development on the land was the
availability of town water and sewerage, particularly town water.20 The oral evidence of
Mr Vanderent, as far as it went, was of similar effect. For him the "turning point" for the
respondent in considering development applications was the knowledge of the bulk water
supply problems in 1995.21
[45] To my mind, a zoning or designation which would facilitate Residential A development
and the reasonable availability of town water and sewerage are so inter-related that it is
difficult to imagine one without the other, provided sufficient demand for such
development existed. Accordingly, in my view, a critical issue to be resolved is whether,
18 Ex 13, App D at P9.
19 Professional engineer employed by the respondent and author of reports Ex 13 and Ex 14.
20 T 584, L 40-45; T 585; T 593, L 45-50; T 594, L 1-10.
21 T 630, L 40-45; T653, L 20-40.
-- 17 of 31 --
18
but for the scheme underlying the resumption of the land, town water and sewerage would
have been reasonably available for connection on or before the date of resumption.
[46] On behalf of the respondent it was contended that the major obstacles in the path of town
water and sewerage were that the land was and always had been outside of the
respondent's headworks catchment areas. Second, and related to the first obstacle, that on
and from 1995 the limited availability of bulk water effectively meant that the reasonable
opportunity for any meaningful extension of the town water headworks boundary to
include the subject land was gone (if in fact it ever really existed). Third, there was at all
relevant times other land available for residential development within the shire that was
generally superior to the subject because of various attributes including; more appropriate
zoning, topography, area and location, being either within or proximate to the existing
town water and sewerage catchment areas. Of course availability of services, location
and area would be issues likely to occupy the minds of the relevant officers of the
respondent when determining the appropriate land use designation for any parcel of land.
[47] Also, in my view, particular care needs to be taken to ensure that each of the matters
raised by the respondent against the development potential of the land, are considered in a
historical context. One illustration of this is the bulk water issue. Prior to 1995, as I
understand the evidence, the respondent was not aware that the availability of bulk water
was an issue militating against extension of the water headworks areas set in 1985.
However, from 1995 to the present, the availability of bulk water has been seen as a
genuine impediment to the extension of the water headworks areas and a limitation on the
location and approval of more intense residential development generally. If, but for the
scheme underlying the resumption, it would have been a reasonable expectation that the
water headworks area would or could reasonably have been extended to include the
subject land before the 1995 bulk water problems became known of by the respondent,
the later knowledge of that problem by the respondent would be largely irrelevant.
[48] In so far as the availability of town water and sewerage is concerned, the case for the
claimants is concisely stated by Mr Ovenden at page 3 of his response report (Exhibit 30)
in the following terms:
"The Rea report (Section 5.2, Stage 1) considers a theoretical development application
and highlights the importance of first analysing the availability of water supply and
sewerage to the subject site and the Investigation Area. It fails to recognise what is a
reasonable proposition that but for the Scheme of Resumption the sewer and water supply
headworks boundary would have been extended to include the subject site. The reason
why it was not extended as part of the 1985 or 1995 review of headworks boundaries is
that the waste disposal facility was in existence. In undertaking any review of water
supply and sewerage capacity the process would involve a consideration of the planning
scheme (in particular the Strategic Plan and DCP) and liaison with Council officers in
relation to development opportunities and constraints."
-- 18 of 31 --
19
Sewerage Connection
[49] The evidence makes it quite clear in my view that, as between the availability of sewerage
and town water connection, it was the latter which would have caused more concern to
the respondent in the consideration of any Residential A development proposal. This
conclusion is consistent with the evidence of engineers called by both parties. Dr.
Johnson, in his initial report22 relevantly concluded:
"It has been determined that suitable water supply and sewerage infrastructure can
reasonably be supplied to this site, without excessive cost. While it is noted that the site
is outside of Council's headworks area, it is not considered that this would be an
impediment to development, because Council has resolved that it will seek to facilitate
such external developments by the provision of relevant Infrastructure Agreements. …"
Mr Nigel Cartwright (Engineer) was the author of three reports tendered in the case for
the respondent. In one of his reports (Exhibit 16), after identifying that the land was
zoned Rural and located outside of the existing sewerage headworks area, he relevantly
concluded at page 4:
" Impact on Existing Trunk Sewerage
The capacity of the existing sewerage up to PS260 is adequate for ultimate flows that
include flow from the bunya Rd development.
The flow from the development will have only a limited impact on the size and/or staging
of augmentation works proposed downstream of PS260. Pump station capacity would
have to be increased by 3.67 L/s at PS260 and PS203, which have ultimate peak wet
weather flows of 180 L/s and 467 L/s respectively (refer to attached system curves).
However, it is not recommended that the development proceed until the new rising main
from PS260 has been constructed and pump upgrades completed at PS203 where the
existing capacity has been exceeded."
After having had the opportunity to review the reports of Mr Cartwright, Dr Johnson
authored a response report (Exhibit 23) which relevantly concluded at page 5:
"2.3 Technical Memoranda of Nigel Cartwright
Mr Cartwright has provided advice on the provision of water supply and sewerage to the
site. No response is required to the information provided, since the findings are
essentially identical to those outlined in my original report, namely that both water supply
and sewerage can reasonably be provided to the site."
This evidence of Dr Johnson was not challenged in cross-examination and Mr Cartwright
was not called as a witness.
[50] Having regard to the evidence I have reached the conclusion that, leaving questions of
commercial viability aside for the moment, there were no sound engineering or town
planning reasons for refusing Residential A development of the land solely because it lay
outside of the sewerage catchment area. This service would have probably been achieved
by the developer bearing the capital cost of installing the necessary pumping station and
22 Ex 8.
-- 19 of 31 --
20
associated works and then entering into an appropriate infrastructure agreement with the
respondent. The evidence of Mr Vanderent together with that of Dr Johnson left me with
the clear impression that such an arrangement was feasible.
Town Water Connection
[51] It seemed quite clear that, like Mr Rea, Mr Vanderent was of the view that post 1995
there was no reasonable prospect of town water being made available to service
Residential A development on the subject land. At page 653, lines 20-40, when being
questioned by Mr Allan about infrastructure agreements the following exchange took
place:
"Q. And you'd raise such a matter at your pre-lodgement meeting with the relevant expert
who may come to you with the type of concept plan and engineering evidence which
have been produced by the claimant in this case?
A. If someone had come along to a pre- lodgement meeting on this land, 9th May, with
this report we would have said, 'It doesn't matter whether or not you can provide the
service. We're not expanding outside our headworks area because we have a limited
bulk water supply, we have sufficient development of the land in our headworks area
and I wouldn't be recommending council expand into this area.'
Q. So the limit on bulk water supply, as I understand it, is the largest constraint to,
at least in your opinion, making a recommendation to council again - in the
hypothetical situation we're dealing with-----?
A. Exactly. And under the 1985 plan council did approve - that's 1985 headwords plan
- it did accept developments outside the headworks area in a period when it didn't
know there was a bulk water supply issue. 1995 was the turning point when we
discovered a bulk water issue and we were regularly reporting proposals to council
saying, 'They're outside your headworks area. You don't have enough water for your
headworks area. If you approve this you'll be compromising people who have had
development potential inside your area and you shouldn't be doing that'."
[52] Exhibit 74 shows the boundary of the water catchment area at the date of resumption
generally following the location of Bunya Road to the south of the land. There is also no
dispute that the whole of the investigation area, including the subject land, lies in a
different physical catchment area to the Cabbage Tree Creek catchment. As was the case
concerning sewering the land, the evidence of Dr Johnson and Mr Cartwright left me with
the strong impression that there were no insurmountable engineering impediments to
connecting town water to the land. However, neither of these witnesses had regard to the
"bulk water" issue raised by Messrs Rea and Vanderent.
[53] The availability of town water is no doubt complicated by the events of 1995. The
evidence of Messrs Rea and Vanderent, which I accept, points quite clearly to the
respondent having to rethink its water strategies and policies, after learning in 1995 of the
constraints on development within the shire imposed by the bulk water allocation to
which the respondent was subject. As I understand it, the respondent and other local
authorities have a bulk water allocation sourced from various dams including those at
-- 20 of 31 --
21
North Pine and Wivenhoe. According to Mr Vanderent the respondent is required to
ensure that the future planning demands for the shire would not exceed the bulk water
supply allocated to it by the relevant authority.
[54] To return then to the opinions expressed by Mr Ovenden as set out in paragraph [48]
above, what needs to be tested are his clearly inter-related propositions. The evidence
leads me to the conclusion that it would be fair to say that, once the decision had been
made by the respondent to progressively acquire and utilise the land within the
investigation area, it was not going to readily make available the sorts of services likely to
attract intensive residential development. Mr Rea candidly conceded that there was a
deliberate intention by the authors of the Strategic Plan to ensure the privately owned land
within the investigation area was kept in the rural zoning. Notwithstanding this, it need
not necessarily follow that, but for the scheme, the subject land would have been given a
Residential A or Future Urban designation by the respondent and that the water catchment
boundary would have been extended to include the land.
[55] The evidence, particularly that of Messrs Rea and Vanderent, leads me to the conclusion
that from 1995 up to the present the respondent, regardless of the scheme, would have
been opposed to extending the water headworks to include the land which lies in a
different and unserviced catchment. Things might have been different if there was a
shortage of developable land within the shire but that was not the case according to
Messrs Rea and Vanderent, whose evidence on that topic was not seriously challenged.
[56] In support of his opinions to the contrary Mr Ovenden drew attention to instances where
the respondent had approved more intense forms of development reasonably proximate to
the subject land and outside of the water catchment areas set in 1985 and 1995. Some
emphasis was placed on what had occurred on land located to the east and south-west of
the subject land.
[57] As to the development to the east, it is located on land immediately to the north of Collins
Road, a road constructed by the developer of that land. The evidence revealed that the
land referred to and developed for Residential A purposes was part of a large residential
development over some 65 hectares which, prior to the construction of Collins Road, was
a contiguous holding. Further, the respondent's initial approval for residential
development over the entire site dated back to 1984 when the land was rezoned. As I
understand it, the conditions attaching to the 1984 rezoning were not met and it
effectively lapsed. The project was reactivated in February 1993 when the same land was
taken from the Future Urban zone and placed in the Residential A zone as a consequence
of a successful combined rezoning and subdivision application being lodged on behalf of
-- 21 of 31 --
22
the new developers. Mr Rea saw the 1984 rezoning as an important element in the
respondent's consideration of the 1993 application. On balance, I do not consider that a
prudent purchaser or vendor would draw much comfort from what occurred on this land
as representing some form of precedent or giving insight as to how the respondent might
react to a Residential A proposal over the subject land in 2003. There are too many
differences of both a physical and historical character.
[58] The second development to the south-west was described by Mr Ovenden as an example
of where the respondent "… allowed for an extension of the urban footprint into the rural
designated land …". This development was referred to as being part of the Fernlands
Estate. The evidence concerning this development is that it involved an area of land
which made up part of the western section of the Fernlands estate and, notwithstanding
that the land was within the Cabbage Tree Creek catchment it was not included in the
respondent's 1985 water headworks area because, at that time, water supply was not
provided for above 120 m AHD. As Mr Hughes SC put it, the land was suitable for
sewerage but not for reticulated water. As a part of an infrastructure agreement entered
into in the "early" 1990's between the developer of the retirement village to be built on
part of this land, the developer was required to put another water supply reservoir in
place. This in turn allowed for the expansion of the water supply area beyond 120 m
AHD and up to the natural elevation of the Cabbage Tree Creek catchment. Taking these
matters into account I have come to the same conclusion in respect of this example as that
reached concerning the Collins Road development. The third example referred to was the
supply of town water to the rubbish depot and public reserve which now exist on land
acquired by the respondent within the investigation area. I agree with Mr Ovenden that
no sensible comparison can be made between those works and what would be required for
Residential A development on the subject land.
[59] Some reference was also made during the course of the evidence to extensive residential
development occurring in the north-east of the shire involving areas of land lying outside
of the 1995 water headworks boundaries. These areas are said to include the Mango
Hill/North Lakes Estate development areas. These areas have been designated "Special
Development" in the respondent's Town Planning Zone Map. According to Mr Rea, the
Mango Hill/North Lakes development also has its own development control plan and the
developers have entered into significant infrastructure agreements which include certain
guarantees that the shire's ratepayers will not have to contribute to the cost of servicing
the development.
-- 22 of 31 --
23
[60] Finally, reference was also made to residential development of land outside the 1995
water catchment area at Ira Buckby Road, West Cashmere. In this case the headworks
area was not extended to include the land but arrangements were made to provide town
water through infrastructure agreements. This development also involved rather special
circumstances. First, the land was previously designated for extractive industry purposes
but contained significant areas of environmentally sensitive vegetation. Second, the
development on the land was subject to the developer handing over to the respondent
about 50% of the entire holding for environmental purposes and the balance being
developed less intensively. Overall, the development yielded only about 1.2 lots per
hectare compared to the more typical Residential A yield of 8 or 9 lots per hectare.
[61] After consideration of the facts and circumstances surrounding each of these two
developments I have concluded that they offer no support for the proposition or
conclusion that, but for the scheme, town water have been reasonably available to service
the land for Residential A development.
[62] When the headworks catchment areas within the shire were reviewed in 1995 they would
have accommodated sufficient development to provide for a shire population of 180,000.
However, as at 1995 the existing shire population was no more than about 90,00023 and,
as Mr Vanderent pointed out, there was a significant surplus of developable land within
the existing headworks areas and therefore little need to extend them further. The
evidence also revealed that between the setting of the catchment boundaries in 1985 and
1995 these circumstances had not changed dramatically. That is, a surplus of developable
land within the 1985 catchment areas meant that significant expansion in the 1995 review
was not required.24 There was also evidence to the effect that much of the undeveloped
land within the 1985 and 1995 catchment areas would have been easier to develop than
the subject. In this context, the surveyor and engineer called on behalf of the claimants
agreed that the subject land would not have been an easy site to develop for Residential A
purposes.
[63] After reviewing all of the evidence on this topic I am not at all convinced that, ignoring
the scheme underlying the resumption, town water would have been available or
reasonably available to facilitate Residential A development on the subject land any time
prior to 1995, whether by extension of the water catchment boundary or by way of
infrastructure agreement. The land is physically separated from the urban land to the
south and the headworks area, not only by Bunya Road but also by a ridge line which puts
23 T 627 L 40-50; T 628, L 1-5. (Note: The figure of 180,000 was reviewed downward to 160,000 because of bulk
water supply concerns.
24 T 630, L 10-32.
-- 23 of 31 --
24
the land (together with the balance of the investigation area) in its own small catchment.
The latter physical characteristic was an issue which particularly concerned Mr Vanderent
and the 1985 review of the town water and sewerage headworks areas extended the
boundary of those areas only to the northern natural boundary of the Cabbage Tree Creek
catchment area.
[64] As already identified, the evidence left me with the clear impression that from 1995,
when the bulk water issue became known, there was no reasonable prospect of the water
catchment area being extended to include the subject land.
[65] Before leaving this topic I consider it necessary to deal with one further aspect of Mr
Vanderent's evidence. At page 669 of the transcript, Mr Vanderent was asked to make
two assumptions: First, that the investigation area was a "priority infrastructure area" and
second, that the investigation area had a "Future Urban" or "Urban" designation. He was
then asked, making those assumptions, would the respondent then have been prepared to
enter into appropriate infrastructure agreements to service the land. Mr Vanderent's
response was that, if the land " … was zoned Future Urban" there was every likelihood
that such a course of action would have been recommended. Presumably the
recommendations would have come from council officers such as Mr Rea and himself.
[66] Given the assumptions underlying the response, the concession was not a surprising one.
When giving his response, Mr Vanderent clearly saw land with a 'Future Urban' zoning or
designation as being land " ... always intended one day to have water and sewerage". To
that extent, Mr Vanderent tends to confirm what I attempted to articulate in paragraph
[45] above when touching on the almost circular relationship between the urban
designation of land and the availability of services, particularly town water and sewerage.
For reasons already addressed I do not accept that, but for the scheme, it would have been
reasonable to expect or act on the basis that the investigation area, including the subject
land, would have had town water available or reasonably available for connection. In the
circumstances the concession made by Mr Vanderent does little to advance the claimants'
case in my view.
[67] It should be clear from what I have already said that I do not accept that, as at the date of
resumption, the land would have had a Residential A or similar zoning or designation due
to the unavailability of town water. Notwithstanding this conclusion I consider it
appropriate to address some of the other matters raised by the parties concerning the
zoning of the land.
[68] As counsel for both parties acknowledged, I am not required to disregard all of the
respondent's town planning instruments, it is only those about which it could be fairly
-- 24 of 31 --
25
said there was a direct relationship between the town planning restrictions those
instruments imposed and the scheme, or where the restrictions could be properly regarded
as a step in the process of resumption, that are required to be ignored.
[69] The evidence was that the topography of the land did not easily lend itself to Residential
A development. Further, the location of the land is such that it is rather uniquely placed
having regard to other land within the shire designated for more intensive urban
development. First, the investigation area of which the subject land is a part, is a discrete
area separated from Residential A development to the south by Bunya Road and
effectively surrounded on three sides by State forest. Second, as the land lies in a small
and discrete water catchment area it could not be said, in my view with any degree of
confidence that Residential A development would have involved a logical extension of
the existing water supply and sewerage infrastructure. To my mind, the physical
characteristics of the land and its environs are such that a land use designation not
compatible with intensive urban development could not be said to be illogical or
incongruous. In this context, to the near west and south west lie significant areas of land
zoned Future Rural Living, Park Residential and Special Residential requiring less
intensive urban development.
[70] Having regard to all of these matters I am left in the position that I am not satisfied that,
but for the scheme, the land would have had a Residential A or even a future urban
designation or zoning. Nor am I convinced that, regardless of zoning and if the scheme
was ignored, there were reasonable prospects of a Residential A development gaining the
necessary approvals under IPA. Accordingly, I reject the valuation of Mr Walsh based on
a Residential A subdivision of the land.
[71] This conclusion does not necessarily lead to the consequence that, as at the date of
resumption, the highest and best use of the land, with its rural zoning, was for only a large
rural homesite. Mr Gillespie, relying on advice from officers of the respondent,
expressed the opinion that if the restrictions imposed by the Hills District DCP were
ignored, the highest and best use of the land would include potential for Rural Residential
subdivision into 2 hectare lots. Further, as already identified, following the introduction
of IPA, the existing zoning of land does not mean that any particular form of development
is prohibited. Each application for development is to be looked at and have its merits
assessed in accordance with the provisions of that legislation.
Highest and Best Use and Value
[72] In his report (Exhibit 12) at pages 4-5, Mr Rea expressed the view that, as at the date of
resumption, Rural Residential or Park Residential development was more likely to be
-- 25 of 31 --
26
approved than more intensive residential development. Rural Residential development
allows for lot sizes down to 2 hectares in area and requires neither sewerage nor town
water. Park Residential development allows for sub-division down to 6000 square metres
and requires town water but not sewerage. Another form of residential development is
envisaged within the respondent's town planning framework and it is that which Mr Rea
referred to as being "Special Residential". Not surprisingly, this form of development is
permitted in what Mr Rea described as "special circumstances" including topography and
limited availability of services. An example of this form of development is that referred
to in paragraph [60] above at Ira Buckby Road.25
[73] Topography would not be a basis for refusing Park Residential or Special Residential type
development on the evidence before me. The proximity of the land to the forest is also
unlikely to be a bar to such development. Further, the totality of the evidence of Mr Rea
left me with the clear impression that, while after 1995 town water would not have been
made available for Residential A development, it was not ruled out for less intensive
residential development involving significantly fewer lots. At page 5 of Exhibit 12 Mr
Rea states in part:
"The issue of whether one designated the land for either a "Park Residential" or "Rural
Residential" land use, would in my opinion have been decided upon the results of a close
examination, as to the feasibility and economic practicality of providing a town water
supply."
To my mind, when Mr Rea was discussing the possibility of Park Residential or Rural
Residential development the bulk water issue dealt with above was not in itself
determinative. That is, for such development the availability of town water was more to
do with practicability of supply rather than the availability of bulk water. Mr Rea's oral
testimony on this topic was, in my view, consistent with this conclusion.
[74] The engineering evidence, to which I have already referred, makes it quite clear to me
that there were no technical or engineering issues which would prevent town water and,
for that matter, sewerage being made available to service development on the land,
probably by way of infrastructure agreements similar to those put in place to facilitate the
Special Residential development on Ira Buckby Road. It also seems to me to be tolerably
clear that the main reason, if not the only reason, Mr Gillespie rejected Park Residential
as being the highest and best use of the land, was his conclusion that town water would
not have been reasonably available as at the date of resumption. And, further, if Park
Residential was the highest and best use of the land he would have relied on those sales
25 Refer also to Report of Mr Vanderent; Ex 14 at P6.
-- 26 of 31 --
27
set out at page 16 of his report described as being sales of land with "Park Residential
Development Potential".
[75] In the circumstances of this case I have reached the conclusion that the prudent purchaser
and vendor, properly advised, would have been reasonably confident of gaining the
necessary approvals from the respondent at the date of resumption to facilitate at least
Park Residential development of the land.
[76] In light of my findings concerning the highest and best use of the land it is Mr Gillespie's
sales 1 to 4 which are likely to provide the best guide to value. Unfortunately, no doubt
influenced by their assumptions and advices concerning the Point Gourde/San Sebastian
issues raised , neither valuer gave much attention to these sales. Leaving aside sale 1 for
the moment, sales 2, 3 and 4 are generally described as being superior to the subject due
to "land type" and aspect. I understand "Land type" to refer mainly to topography.
However, each of these sales is located some distance further from the Brisbane CBD
than the subject land. Sales 3 and 4 occurred at a date relatively close to the date of
resumption whereas sale 2 occurred some 8 months earlier on what appeared to be a
generally rising market. These sales range in area from 10.02 hectares to 24.53 hectares
and in rates per hectare from $22,418 to $54,890.
[77] Turning to the sales in more detail, I reject Sale 1 as reliable evidence of value. This sale
occurred some seven months prior to the date of resumption in what appears to have been
a generally rising market. Further, the topography, presence of high voltage transmission
lines and low lot yield indicate to me that this sale involves land significantly inferior to
the subject. It seems to me that this must be so given that the sale price reflects a rate of
$8,348 per hectare, almost three times lower than the rate adopted by Mr Gillespie on the
basis of a highest and best use for only Rural Residential development.
[78] I find Mr Gillespie's Sale 4 a very difficult sale to rationalise. While it is described as
being "Superior to the subject due to (its) superior dwelling and aspect", once allowance
has been made for improvements, this sale reflects a rate per hectare less than that
attributed to the subject land which has inferior development potential. No doubt the
"very steep" nature of the timbered western section of the land, its location and size
(about 50% larger than the subject) were all mattes which had an influence on price but to
what extent? In these circumstances, particularly where a higher rate per hectare has been
attributed to the subject notwithstanding a lower order of development potential, I do not
accept this sale as reliable evidence of value.
[79] Sales 2 and 3 are smaller in area to the subject and of superior topography. However,
both of these sales are further removed from the Brisbane CBD, although Mr Gillespie
-- 27 of 31 --
28
did not consider distance to be a major issue for larger lot subdivisions. On the other
hand, the topography of the subject land is such that it would have been likely to cause
design and construction difficulties for any developer, particularly in respect of that land
to the south-east which is effectively isolated by the large gully traversing the block. Sale
2 reflects a rate $33,275 per hectare and Sale 3 $54,890 per hectare. Sale 2 has the
additional difficulty of being some eight months prior to the date of resumption in a
generally rising market. Sale 3 is closest in time to the date of resumption, however,
while it had the advantage of a golf course adjacent to its northern boundary, as identified
by Mr Gillespie, the development of this land was hindered by topography and the
presence of power line easements.
[80] Doing the best I can with the evidence before me and endeavouring to resolve doubts in
the assessment of compensation in a way more generous to the claimants,26 I will adopt a
rate of $45,000 per hectare for the subject land. I will also include Mr Gillespie's value of
improvements in the amount of $83,000. This value was unchallenged for Rural
Residential purposes and I can see no reason why it would not have the same level of
value for Park Residential purposes.
[81] I immediately acknowledge that the adoption of $45,000 per hectare involves an element
of "best guess" when comparing the subject land to the sales I have had regard to.
However, as identified by Hope JA in Leichhardt Municipal Council v Seatainer
Terminals Pty Ltd,27 sometimes that may be the only option open on the available
evidence.
[82] Accordingly, I determine compensation payable by the respondent to the claimants under
all heads at $832,000 made up as follows:
Value of Land (16.2 hectares x $45,000 per hectare) $729,000
Improvements (per Mr Gillespie) $83,000
Disturbance (agreed) $20,000
$832,000
I also order that the respondent to pay to the claimants interest at the rate of 5.50 per cent
per annum on the sum of $812,000 from the date of resumption, 9 May 2003, to 28
November 2003, when the advance of $400,000 was received and, then on the balance of
$412,000 to the date of payment.
26 Commissioner of Succession Duties (SA) v Executor Trustee and Agency Co of South Australia Ltd (1947) 74 CLR
358 at 373–374 per Dixon J; cited with approval by Callinan J in Boland & Anor v Yates Property Corp Ltd
(1999) 167 ALR 575 at para [356]; Merivale Motel Investments Pty Ltd v The Brisbane Exposition and South Bank
Redevelopment Authorities 10 QLCR 268 at 286.
27 (1981) 48 LGRA409 at 434; AMP Henderson v Valuer-General (2004) 134 LGERA 426 at 440.
-- 28 of 31 --
29
[83] As referred to above I was advised during closing argument that disturbance had been
settled in the sum of $20,000 on an "all up" basis. Unfortunately I did not enquire and
was not told whether or not the term "all up" was meant to include interest and no
evidence was led as to whether or not, and if so when, payment of the disturbance items
occurred. In these circumstances, although there is only a relatively small amount of
money involved, I will allow the parties to make submissions, (if they wish to), as to
interest on compensation for disturbance.
Orders
1. Compensation is determined in the amount of $832,000 (Eight Hundred and Thirty
Two Thousand Dollars).
2. The respondent to pay to the claimants interest at the rate of 5.50 per cent per
annum on the sum of $812,000 from the date of resumption, 9 May 2003, to 28
November 2003, when the advance of $400,000 was received and, then on the
balance of $412,000 to the date of payment.
3. The parties will have the opportunity to consider these reasons and make
submissions in respect of interest on disturbance and/or costs including reserved
costs if any.
R S JONES
MEMBER OF THE LAND COURT
-- 29 of 31 --
30
IN THE LAND COURT
OF QUEENSLAND
AV2004/0137
Acquisition of Land Act 1967
BETWEEN:
Olive Louise Bowers and Lynette Ann Crane
(as personal representatives)
Claimants
and
Council of the Shire of Pine Rivers
Respondent
Before Mr RS Jones
BRISBANE
This matter having, on the Fifteenth day of September 2005, come on for judgment, and upon hearing
from Counsel for both parties, the Court ORDERED THAT:
1. Compensation is determined in the amount of $832,000 (Eight Hundred and Thirty Two
Thousand Dollars);
It is FURTHER ORDERED BY CONSENT THAT:
2. Orders 2 and 3 of the published reasons for judgment dated 15 September 2005 be vacated
and in lieu thereof the following orders 3 to 6 be substituted;
3. The respondent to pay interest at the rate of 5.50 per cent per annum:
(a) on the sum of $812,000 from the date of resumption, 9 May 2003 to 1 December
2003, when the advance of $400,000 was received; and
(b) then on the balance of $412,000 from 1 December 2003 to 24 June 2005 when a
further advance of $110,000 was received; and
(c) then on $302,000 from 24 June 2005 to the date of payment;
4. The respondent pay to the claimants interest at the rate of 5.50 per cent per annum on the
agreed disturbance figure of $20,000 from 1 January 2004 to the date of payment 24 June
2005;
-- 30 of 31 --
31
5. Any application for costs by the respondent is to be in writing and filed and served on or
before 4.00 pm Friday 30 September 2005, with written submissions in response by the
claimants to be filed and served on or before 4.00pm Friday 14 October 2005;
6. The further hearing of the matter be adjourned to a date to be fixed.
By the Court
Deputy Registrar
-- 31 of 31 --
Official source: https://www.sclqld.org.au/caselaw/QLC/2005/046