Fazzari, Re [2005] QLRT 163
LAND AND RESOURCES TRIBUNAL
QUEENSLAND
CITATION: Re Fazzari [2005] QLRT 163
PARTIES: Frank Fazzari (Applicant)
FILE NO/S: AML180/05
PROCEEDING: Application for grant of Mining Lease No. 60393
DELIVERED ON: 7 December 2005
DELIVERED AT: Brisbane
HEARING DATE: Heard on the papers
MEMBER: Koppenol P
ORDER/S: Application recommended for grant. (at [5])
CATCHWORDS: MINING – APPLICATION FOR MINING LEASE
– RECOMMENDATION
Mineral Resources Act 1989, ss 245, 269
COUNSEL: N/A
SOLICITORS: N/A
[1] This is an unopposed application under section 245 of the Mineral Resources Act
1989 (the Act) for the grant of a mining lease over a 2.5391ha area of land situated
90km north-west of Eromanga for the mining of opal.
[2] In such a case, the Tribunal’s statutory function is under section 269 of the Act—
namely to take into account and consider a number of factors and then to make a
recommendation to the Minister for Natural Resources and Mines as to whether the
application should be granted or rejected in whole or in part. Various material was
provided to the Tribunal by the applicant and the mining registrar to assist in that
regard.
[3] Section 269(4) provides as follows:
“269 Tribunal’s recommendation on hearing
…
(4) The tribunal, when making a recommendation to the Minister that an application for a
mining lease be granted in whole or in part, shall take into account and consider whether—
(a) the provisions of this Act have been complied with; and
-- 1 of 2 --
(b) the area of land applied for is mineralised or the other purposes for which the
lease is sought are appropriate; and
(c) if the land applied for is mineralised there will be an acceptable level of
development and utilisation of the mineral resources within the area applied for;
and
(d) the land and the surface area of the land in respect of which the mining lease is
sought is of an appropriate size and shape in relation to—
(i) the matters mentioned in paragraphs (b) and (c); and
(ii) the type and location of the activities proposed to be carried out under the
lease and their likely impact on the surface of the land; and
(e) the term sought is appropriate; and
(f) the applicant has the necessary financial and technical capabilities to carry on
mining operations under the proposed mining lease; and
(g) the past performance of the applicant has been satisfactory; and
(h) any disadvantage may result to the rights of—
(i) holders of existing exploration permits or mineral development licences; or
(ii) existing applicants for exploration permits or mineral development licences;
and
(i) the operations to be carried on under the authority of the proposed mining lease
will conform with sound land use management; and
(j) there will be any adverse environmental impact caused by those operations and, if
so, the extent thereof; and
(k) the public right and interest will be prejudiced; and
(l) any good reason has been shown for a refusal to grant the mining lease; and
(m) taking into consideration the current and prospective uses of that land, the
proposed mining operation is an appropriate land use.
… .”
[4] The mining registrar has certified that the applicant has complied with the
requirements of the Act and the applicant has lodged the relevant declarations of
compliance. An indigenous land use agreement has been entered into and it
authorises the grant of this application. The area concerned is an old opal mine
which was first worked in the 1930s. The mining program envisages progressive
small scale open cut mining by mobile earthmoving machinery. All supporting
infrastructure will be provided on site. The size and shape of the area applied for
encompasses the area which is potentially opal bearing and surrounding area for
camp site and stockpiles. A 10-year term is sought to give sufficient time to mine the
area. The applicant has confirmed his financial capacity to carry on the mining
operations. He has many years experience in opal mining. The land is currently
used for low intensity grazing—its only possible use apart from mining, which I
regard as an appropriate land use. The mining activities will be carried out in
accordance with the draft environmental authority (mining activities) issued by the
Environmental Protection Agency. That should minimise any adverse environmental
impact. There is no evidence that the public right and interest will be prejudiced or
of any good reason why this application should be refused.
[5] Having taken into account and considered all of the section 269(4) factors, I
recommend to the Honourable the Minister for Natural Resources and Mines that this
application be granted in whole.
-- 2 of 2 --
Official source: https://www.sclqld.org.au/caselaw/QLRT/2005/163